HANDBOOK OF ENVIRONMENTAL IMPACT...
Transcript of HANDBOOK OF ENVIRONMENTAL IMPACT...
1
HANDBOOK OF
ENVIRONMENTAL
IMPACT ASSESSMENT
GUIDELINES
BAHAGIAN PENILAIAN
JAS IBU PEJABAT
27 Oktober 2015
HANDBOOK OF
ENVIRONMENTAL IMPACT
ASSESSMENT GUIDELINES
Requirements under provision of Section 34A (2c) of the Environmental
Quality Act 1974.
2
SECTION 34A, EQA 1974 (AMENDMENT) 2012
• Subsection 34A (2C)
The report shall be in accordance with theguidelines as the Director General may prescribeand shall contain:
a. an assessment of the impact such activity willhave or is likely to have on the environment;and
b. the proposed measures that shall beundertaken to prevent, reduce or control theadverse impact on the environment
3
HANDBOOK OF ENVIRONMENTAL IMPACT
ASSESSMENT GUIDELINES
4
1• Concept and procedure of EIA in Malaysia
2
• Policy and legislations relating to EIA Procedures in Malaysia
3
• Requirement for pre-submission of EIA Report (screening and scoping)
4
• Requirements during submission of EIA Report (review process)
HANDBOOK OF ENVIRONMENTAL IMPACT
ASSESSMENT GUIDELINES
5
5
• Requirements on procedural steps for First Schedule prescribe activities
6• Requirements on procedural steps for Second Schedule
prescribe activities
7• Specifications and format of EIA Report
8
• Specifications and format of report on EMP and Performance Monitoring
9• Self regulatory practice
• EIA Guiding Principles
6
1• Concept and procedure of EIA in Malaysia
Development Befitting to Nature
Proactive
Transparent
Credible
Cost-effective
Practical
• EIA Guiding Principles (cont’d)
7
1• Concept and procedure of EIA in Malaysia
Social Accountability
Quality Control
Self-Regulatory
Ethics of EIA Practitioners
Participatory
Sustainability
1.EIA Guiding Principles
a. Development Befitting to Nature
Project proponent
• - have insight understanding of the existingenvironmental conditions
• - rationalise his project to ensure that theproposed development is fitting to nature andnot “nature befitting development”.
8
1. EIA Guiding Principles
b. Proactive
• process should start as early as possible withinthe project planning cycle and decisionmaking for project approval
- environmental impacts of a project areconsidered right
9
1. EIA Guiding Principles
c. Transparent
• clear, concise, easily understood andtransparent.
• provide sufficient information includingquantitative, well defined and explicit basis, inproducing quality EIA Report.
10
1. EIA Guiding Principlesd. Credible
• integrity, rigor, fairness and objectivity.
• process should apply “best practicable”science, employing methodologies andappropriate techniques - address key areas ofenvironmental concerns.
• study should comprehensive and comply withstatutory requirements to guarantee thequality of the EIA Report.
11
1. EIA Guiding Principlese. Cost-effective
• environmental cost is accounted for in thetotal project cost and must be reflected in thecontract documents between projectproponent and its contractors or suppliers.
12
1. EIA Guiding Principles
f. Practical
• information and outputs provided by theenvironmental assessment process are readilyusable in decision making and planning.
13
1.EIA Guiding Principlesg. Social Accountability
The project proponent is a driver of socialaccountability for legal compliance of his projectat all times. Project proponent shall appoint aqualified person to conduct the EIA report andpreparation of its report. In addition to which, adedicated environmental officer (EO) shall beappointed on a full time basis to be responsiblefor all environmental management mattersrelated to the project.
14
1. EIA Guiding Principlesh. Quality Control
• In this spirit, the prepared EIA report must bethoroughly vetted through and it’s pledgedcommitment principally agreed by projectproponent prior to submission to DOE,bearing in mind that responsibility ofsubmitting an optimal quality report lies withthe project proponent.
15
1. EIA Guiding Principles
i. Self-Regulatory
• The practice of Self-regulation by projectproponent is a driver to cultivate a positiveculture in the day-to-day management of theproject paving the way for excellence inenvironmental regulatory compliance.
16
1. EIA Guiding Principles
j. Ethics of EIA Practitioners
• EIA Practitioners should uphold hisprofessional ethics to fulfil his professionalobligations with extreme sense ofresponsibility, professionalism and integrity.
17
1. EIA Guiding Principlesk. Participatory
• EIA is a multi-disciplinary study onenvironmental component such as waterquality, air quality, waste management,environmental sensitive area and naturalresources.
• participation of government agencies, non-governmental organisation, academicians, andexperts, environmental practitioners includingqualified and competent persons, industriesand public at large.
18
1. EIA Guiding Principles
l. Sustainability
• The project proponent shall be accountable toensure the proposed project subjectdevelopment subject to EIA is sustainable.
• EIA should be sustainability of throughout thecause of lifelong Project Planning.
19
20
2
21
2
•Policy and legislations relating to EIA Procedures in Malaysia
Federal Legislation
•Environmental Quality Act, 1974
State Legislation
• Environmental Protection Enactment, 2002 (Sabah) – by EPD
• Natural Resources and Environment Ordinance, 1993 (Sarawak) – by NREB
22
2
•Policy and legislations relating to EIA Procedures in Malaysia
Main highlights of EIA Provisions
• Section 34A (2) – qualified person to conduct EIA
• Section 34A (2)(A) – DG shall maintain list of qualified person
• Section 34A (2)(B) – qualified person responsible for EIA
• Section 34A (2)(C) – EIA report in accordance with guidelines
23
2•Policy and legislations relating to
EIA Procedures in Malaysia
Main highlights of EIA Provisions
• Section 34A (3) – Director General can approve the EIA report with conditions and inform relevant approving authority
• Section 34A (4) – Director General may not approved the EIA report if not consistent with physical plan or fulfill the guidelines
• Section 34A(5) – Director General can require the submission of additional reports other than EIA report
• Section 34A(6) – Any person intending to carry out a prescribed activity shall not carry out such activity until the report required under this section to be submitted to the Director General has been submitted and approved
24
2•Policy and legislations relating to EIA
Procedures in Malaysia
Main highlights of EIA Provisions
• Section 34A (3) – Director General can approve the EIA report with conditions and inform relevant approving authority
• Section 34A (4) – Director General may not approved the EIA report if not consistent with physical plan or fulfill the guidelines
• Section 34A(5) – Director General can require the submission of additional reports other than EIA report
• Section 34A(6) – Any person intending to carry out a prescribed activity shall not carry out such activity until the report required under this section to be submitted to the Director General has been submitted and approved
25
2•Policy and legislations relating to EIA
Procedures in Malaysia
Main highlights of EIA Provisions
• Section 34A(7) - Responsibility of the proponent to provide proof of compliance to conditions of approval
• Section 34A (8) – Fine not exceeding five hundred thousand or imprisonment for contravention
• 3. PRE- SUBMISSION OF EIA REPORT PROCEDURE
• (SCREENING AND SCOPING)
26
27
3
•PRE- SUBMISSION OF EIA REPORT PROCEDURE -SCREENING
Screening process - determine whether aproposed project is a prescribed activity underthe Environmental Quality (PrescribedActivities) (Environmental Impact Assessment)Order, 2015
Poject fall under both Schedules, theprescribed activity is subject to the SecondSchedule of the Environmental Quality(Prescribed Activities)(Environmental ImpactAssessment) Order, 2015
3. SCOPING
• Scoping is an early stage of EIA study process
• Determines extent of key project activitieshaving significant impacts
• Issues on environment that should be coveredin the EIA study.
• Very important steps in EIA which act as ameans of controlling the extent, and hencethe cost of an EIA study.
PK EIA AWAL Keluaran 03 Pindaan 00
Kuatkuasa 11 Okt 201028
3. SCOPING
Four criteria should be applied in scoping :Magnitude;- refers to the quantum (size) of change thatwill be experienced
Extent;- extent of an impact denotes the area which will be
affected
Significance (important);- an impact looks beyond the magnitude to the
actual effects
Sensitivity areas
-affect an area of environmental sensitive areas
• Checklist for Scoping
• Checklists that can be used include:
• - details describing the project characteristics
• - details of project environment characteristics
• - susceptible to significant adverse effects, or
30
3. SCOPING
3. SCOPING
Checklist of information :
30
If the activity is likely to occur – Yes
If the activity is not expected to occur – No
If it is uncertain whether the activity will occur or not – Maybe or no answer
Project Phase
Project Activity Potential Impact Yes No Possibly Observations
Land-based exploration
Site clearing/ access roads
Soil erosion is significant?
Downstream water use is affected?
Sensitive forest to be cleared?
Need verification
Seismic investigation (explosive charge method)
Noise and vibration is of concern?
Dust emission and air quality
Safety concern to public due to fly rocks?
Further investigation required
3. Application of Scoping for First Schedule
• identify critical issues (potential adversesignificant environmental impacts) for EIAstudy.
• scoping is not necessary to be endorsed byDOE.
• EIA report should be submitted to the relevantDOE state office for approval.
• prescribe activity that traverses two or morestates, the EIA report must be submitted tothe DOE Headquarters for approval.
PK EIA AWAL Keluaran 03 Pindaan 00
Kuatkuasa 11 Okt 201032
3. Application of Scoping for Second Schedule
• prepare and submit the Terms of Reference (TOR) forthe EIA study to the DOE Headquarters forendorsement.
• incorporating inputs from relevant competent technicalagencies and expert review panels
• itemize the potential environmental impacts
• outline the environmental data collections
• determine the assessment methodology and samplingto be applied
• identify the appropriate methodologies for impactprediction and assessment.
33
3. Site Suitability Assessment (PAT)• PAT comments : component in the EIA report
• Take into accounts for sufficient buffer and sitecompatibility to the development plan orphysical plan (National Physical Plan), andGuidelines for the Siting and Zoning ofIndustry and Residential Areas (SZIRA) or anyguidelines prescribed by the Director Generalof Environment relevant to the proposedproject.
34
• Not in-line with the development plan, the EIAreport will be rejected.
• Projects are part of overall developmentmaster plan which have been approved inprincipal from the relevant approvingauthorities, and subject to the EnvironmentalQuality (Prescribed Activities) (EnvironmentalImpact Assessment) Order, 2015, EIA Reporthas to be submitted to DOE for approval.
35
3. Site Suitability Assessment (PAT)
Roles and responsibility
• Project Proponent
• Assessor
• Environmental Related Agencies and Specialist
• Review Panel
• Approving Authority
Client Charter
First Schedule
Second Schedule
EIA Preparation
Submission of EIA
EIA Review Process 36
4• Requirements during submission of EIA Report
(review process)
37
4• Requirements during submission of EIA Report
(review process)
DOE Practices During
EIA Report Review
Process
Role and Responsibility of Project Proponent /EIA Consultant to First and Second Schedule
Activities
First Schedule Activities Second Schedule Activities
Submission of EIA
Report
Submit to DOE State Submit to DOE Headquarters
Review Committee Attending A Technical Review Committee which is chaired by
the Director of DOE State Office (for 5 weeks procedure).
The technical review committee are Government agencies
and experts (if needed).
Attending an EIA Review Panel which may
be chaired by the Director General of
Environment. The technical review
committee are Government agencies,
experts and NGOs.
Public display &
participation
No public display required Public display of EIA Report is required for
comments and feedback.
Web display of EIA report Submit softcopy of the EIA Report to DOE State Submit softcopy of the EIA Report to
DOE Headquarters
Advertisement of EIA
Report for public
participation
No advertisement required Project Proponent is required to advertise
the availability of the report for public review
Client charter* for review & decision by DOE
First Schedule Activities Second Schedule Activities
(i) 15 working days (3 weeks)
(ii) 25 working days (5 weeks)
60 working days (12 weeks)
38
5
•Requirements on procedural steps for First Schedule prescribe activities
Qualified Person –Registered EIA Consultant
Scoping and methodology
Process Flow chart
Qualified Person – Registration Scheme
Terms of Reference (TOR)
Public display
Process Flow Chart
39
6• Requirements on procedural steps for Second Schedule
prescribe activities
40
7• Specifications and format of EIA Report
41
8• Specifications and format of report on EMP and Performance
Monitoring
42
9• Self regulatory practice
43