Hal Tompkins FEE/FEL Commissioning [email protected] .edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy Presentation to the Facility Advisory Committee June 16, 2008
  • date post

    19-Dec-2015
  • Category

    Documents

  • view

    218
  • download

    3

Transcript of Hal Tompkins FEE/FEL [email protected] June 16, 2008 1 FEE/FEL Commissioning...

Page 1: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20081

FEE/FEL Commissioning Overview

By Hal Tompkins

Photon Beam Systems Deputy

Presentation to the Facility Advisory Committee

June 16, 2008

Page 2: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20082

Outline

Commission FEE Instruments

Offset mirror commissioning

SASE optimization

AMO experiment alignment

User Operations at ~4 GeV

Page 3: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20083

Related Presentations

Paul Emma, Commissioning Results and Plans

H.D. Nuhn, LTU and Undulator Commissioning Plans

Richard Bionta, FEE Diagnostics and Commissioning

John Bozek, AMO Instrument

Page 4: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20084

LCLSLCLS Installation and Commissioning Time-Line Installation and Commissioning Time-Line

LTU/Und/Dump

LTU/Und/Dump

Install

Install

LTU/UndLTU/UndComm. Comm.

Re-Re-commission commission Inj/BC2 to Inj/BC2 to

SL2SL2

First LightFirst Lightin FEEin FEE

PEP-II run

PEP-II run

ends

ends

FEE/NEH

FEE/NEH

Install

Install

PPS Cert.

PPS Cert.

LTU/Dump

LTU/Dump

FEH Install

FEH Install

CD-4

CD-4

(7/31/2010)

(7/31/2010)

X-Rays in NEH

X-Rays in NEH

First First LightLightin FEHin FEH

NEH NEH Operations/ Operations/ CommissioningCommissioning

JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA

2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDown

PPS

PPS

AAMM

no

wn

ow

Linac/BC2 Linac/BC2 CommissioninCommissionin

g g FEEFEE

Comm. Comm. June 16, 2008June 16, 2008

FEH Hutch BO

FEH Hutch BO

Und

. S

eg.

Inst

all

Page 5: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20085

Page 6: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20086

Readiness Reviews

FEE/NEH Beam Readiness Reviews to be held in March-April 2009 time frame

AMO Experiment Readiness Review in June-July 2009

X-Ray Tunnel/FEH Beam Readiness Reviews to be held in November-December 2009 time frame

Page 7: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20087

FEE Commissioning - Initial Conditions

Start with single undulator

13.6 GeV electrons

0.2 nanocoulombs

10 Hz

Page 8: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20088

FEE Instrument Commissioning5/15 to 6/25

Conduct FEE Beam readiness review in Mar.-Apr., 2009

Open Dump stoppers, RP initial survey (1-2 d)

Insert Direct Imager, check upstream apertures (1-2 d)

Commission adjustable slits (1-2 d)

Insert all undulators, 13.6 GeV electrons, RP survey (2-3 d)

Insert gas attenuator apertures, check alignment (1-2 d)

Commission gas attenuator/solid attenuators (1-2 d)

Center reticule on beam, project through C1 (1-2 d)

Decide if OMS realignment is necessary (+/- 1mm range) (0-5 d)

Page 9: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 20089

FEE Instrument Commissioning (cont.)

Commission gas detectors (2-4 d) apertures insertedadd gaspower magnetcompare APD & PMT response to attenuation

Commission K-monochromator (4-6 d)Transmit beam through 4 bounces (~8.172 eV)Checkout quadrant photodiode (keep intensity low)Measure x-ray energy, undulator bandwidth

Measure photon flux (part of CD4 goals) (1 d)

Page 10: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200810

Offset Mirrors6/26 to 7/16

Tune linac for appropriate energyBegin with soft x-ray offset mirror system (SOMS)Insert M1S, use P1 to set angle, translation (2-4 d)Insert M2S, use P2S to set angle, translation (1-2 d)Insert M3S2, use P3S2 to set angle, translation (1-2 d)Retract M3S2 and insert M3S1, use P3S1 to set angle, translation (1-2 d)Retract M1S and apply same procedure to HOMS (3-5 d)Priority is SOMS for hutch 2 - delivers beam to AMO experiment

Page 11: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200811

Page 12: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200812

Page 13: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200813

Offset Mirrors (cont.)

Open hutch stoppers to AMO experiment

RP surveys - insure full intensity through C4S2

Begin AMO experiment alignment

Page 14: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200814

SASE Optimization7/17 to 8/13

Change linac to 4.52 GeV (nominal 908 eV), check beam center with K-mono (keep intensity low, 1-2 d)Switch to direct imager, look for FEL (should be able to see signals ≥100 nJ)If unable to find FEL, measure undulator K values

Change linac back to 13.56 GeV, 10 HzUse K-mono to measure spectrum (3-5 d)

Optimize SASE (vary bunch compression, emittance, RF, BBA, etc.)Above 50 J, imager saturates, need gas attenuator

Page 15: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200815

SASE Optimization (cont.)

If FEL reaches ~0.1-1.0 mJ, commission calorimeter (3-5 d)

Need to limit linac to 10 Hz

Once calorimeter is commissioned, cross-calibrate the gas detectors and the direct imager (2-3 d)

Measure position stability

Electron energy stability already < 0.1% (at end of linac)

During off-hours, deliver beam to AMO experiment

Page 16: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200816

AMO Experiment

HF Physics chamber will be in place by May 1, 2009

Laser will be ready at the same time

Commissioning of laser transport to AMO exp. begins

Diagnostics chamber to be in place June, 2009

KB optics delivered in May or June, 2009

Begin aligning KB optics, HF physics chamber, and diagnostics chamber in mid-July

Page 17: Hal Tompkins FEE/FEL CommissioningTompkins@slac.stanford.edu June 16, 2008 1 FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.

Hal Tompkins

FEE/FEL Commissioning [email protected]

June 16, 200817

Summary

Very tight schedule between first beam to FEE and User Run - driven by FY08 budget limitations.

Very tight schedule between AMO experiment installation and User Run - driven by FY08 budget limitations.

We think the goal of achieving lasing at 1.5 nm by Aug.-Sep., 2009 is reasonable