Guide to Foundation_7

download Guide to Foundation_7

of 33

Transcript of Guide to Foundation_7

  • 7/28/2019 Guide to Foundation_7

    1/33

    Piling & Deep Foundations 2010

    Geotechnicalnves ga on an

    Design for Piling

    Works

    1

  • 7/28/2019 Guide to Foundation_7

    2/33

    Outline

    You get what you pay for Benefits of Doing More

    Case Studies

    Closing Remarks

    2

  • 7/28/2019 Guide to Foundation_7

    3/33

    Client Moments

    Just do a basic investigation the piling contractors can take the risk

    -

    Can you guys help us out as we have a problem with our foundations ...we have a eotechnical re ort .. but.....?

    The piling contractor cant install the piles to the design depth in the way

    I want them to install them

    Geotechnical advice during construction is an expense I dont need

    the investigation, analysis and design have all been done I dont need

    construction advice

    The piling contractor is claiming latent conditions can you help

    I must have bored piles on this project, and you cant use bentonite or

    polymer to install them

    3

  • 7/28/2019 Guide to Foundation_7

    4/33

    Client Moments

    You pay for geotechnical advice/investigation one way or another

    am a ng a conserva ve approac ....so can go c eap on my

    geotechnical advice/investigation

    I want to spend as little money as I can on the foundations as we never

    ....

    go and get decent geotechnical advice/investigation later on

    get one from Joe for half the price

    We have to take the chea est rice I know we will a for it in the end

    but that is the policy

    With eotechnical advice/investi ation ou et what ou a for4

  • 7/28/2019 Guide to Foundation_7

    5/33

    Levels of Geotechnical Input

    Ground investigation, analysis, design, construction services...

    You et what ou a for...

    Gold

    Silver

    Bronze

    5

  • 7/28/2019 Guide to Foundation_7

    6/33

    You get what you pay for !

    Bronze Silver Gold Platinum

    boreholes > toe de th ofSilver+moreboreholes, Gold+comprehensive

    GroundInvestigation

    shallowboreholesnotestingand/orsampling

    piles

    SPTtestingIndextesting

    someinsitutestingformodulus,laboratory

    testingforpermeability,modulusandstrength

    testingformodulus,

    strengthandpermeability,staticpileloadtesting

    GeotechnicalEngineer

    LimitedexperienceNonexpert ExperiencedLimitedinexpertise ExperiencedExpert ExperiencedExpert

    Desi nParameters

    Guesse Gener c S tespec c En ance s tespec c

    Analysis None EmpiricalSilver+simple

    theoreticalorbasic Gold+advancednumericalmodelling

    Design Rulesofthumb(overlyconservative)

    Empirical,Loadbased,standardindustry ImprovedServiceabilitybased OptimisedServiceabiltybased

    Usuallyover

    designed Usuallyoverdesigned Partiallyoptimiseddesign Optimiseddesign

    Maybeunsafe Safe Safe SafeRisk High Low VeryLow VeryLowCost $50k $80k $120k $250k

    6

  • 7/28/2019 Guide to Foundation_7

    7/33

    Implications of Enhanced Geotechnical Input

    How does enhanced eotechnical in ut hel ou? Relatively small increase in initial cost (as % of total foundation cost)

    Potential significant savings in overall foundation costs due to:i. Improved strength reduction factors (AS2159 2009)

    ii. Improved design parameters

    .

    serviceability)

    iv. Improved confidence (due to ii and iii and reduced risk) allowingoptimisation

    v. Reduced duration for foundation works

    7

  • 7/28/2019 Guide to Foundation_7

    8/33

    Improved Strength Reduction Factors

    8

  • 7/28/2019 Guide to Foundation_7

    9/33

    Hypothetical Example 1

    Simple Geology 30 m compressible soils over weathered rock, highgroun water ta e

    50 No. 1.2 m diameter bored piles, no basement

    Pile working load of 15 MN

    9

  • 7/28/2019 Guide to Foundation_7

    10/33

    Improved Strength Reduction factors

    10

  • 7/28/2019 Guide to Foundation_7

    11/33

    Improved Parameters, Analysis and Design

    11

  • 7/28/2019 Guide to Foundation_7

    12/33

    Pile Construction Time

    12

  • 7/28/2019 Guide to Foundation_7

    13/33

    Hypothetical Example 2

    Complex Geology e.g. Two separate flows of basalt of variablet c ness, qua ty an extent separate y st so over s opngweathered bedrock surface. Bedrock varies in weathering with depth

    and location and is intersected by dykes. High groundwater table.

    50 No. 1.2 m diameter bored piles, 3 level basement, diaphragm wall

    40 m x 40 m in plan

    e wor ng oa s rom o

    13

  • 7/28/2019 Guide to Foundation_7

    14/33

    Example 2 - Risks and Opportunities

    Risks Opportunities

    Excavation

    Optimised retention Groun water/ ewaterng

    Pile founding levels Optimised pile lengths

    Socket lengths - dykes Differential settlement/tilt

    . .

    different levels inbasalt/bedrock

    gn can oppor un es orreducing foundation costs, Longer piles

    Construction difficulties

    Alternative footing

    systems

    construction time and risk

    Delays

    Latent conditions

    Shorter construction time

    14

  • 7/28/2019 Guide to Foundation_7

    15/33

    15

  • 7/28/2019 Guide to Foundation_7

    16/33

    Case Study 1 Royal Domain Towers, Melbourne

    EW-MW siltstone from

    0

    GARSP - as

    0

    GARSP - as

    sur ace - eepweathering

    dykes 10 EW - MWSiltstone/Sandstone

    cons ruc e

    10 EW - MWSiltstone/Sandstone

    cons ruc e

    ~ 85 piles0.75 m to 1.5 m dia

    15

    Depth(m) Traditional

    approach15

    Depth(m) Traditional

    approachGold level investigation provided significantserv cea y oa s

    5 MN to 15 MN

    design pile head

    20

    Saving of 9.5 m

    20

    Saving of 9.5 m

    Benefits - savings

    950 m socket length

    se emen : a2525

    1.2 m dia. ile SL= 15.3 MN

    m concre e

    1400 m3 spoil

    $$ + 42 days

    Addi tional Cost for3030

    Pressuremete testng, UCS

    testing, analysis

    on-site presence

  • 7/28/2019 Guide to Foundation_7

    17/33

    Case Study 2 Freshwater Place, Melbourne

    30 m overburden over

    1.2 m diameter pile, serviceability load = 27 MN

    30

    - s s one(variable)

    70 x 1.2 m dia. Piles 35GARSP - as

    constructed

    pus o ers

    serviceability loads17 MN to 30 MN

    -

    40HW - SW

    Siltstone /

    Gold level investigation provided significant

    design top of socketsettlement : 1 % dia

    900 m socket length 1000 m3 concrete

    1500 m3 spoil

    45

    Depth(m

    )

    Sandstone

    Traditional

    approach Saving of up to 17 m

    ana ys s $$ + 40 days

    Addi tional Cost for

    Pressuremeter testing, UCS

    50

    , ,

    on-site presence55

    60

  • 7/28/2019 Guide to Foundation_7

    18/33

    Case Study 3 SU Building, Melbourne

    Multi storey building

    Subsurface strati ra h weathered siltstone

    Recommended Gold level geotechnical investigation. Client wanted

    only to pay for silver (for about $20 k less) ver carre out, ootngs es gne accor ngy

    Piling contractor engaged on lump sum price design and construct

    Piling contractor requested additional geotech Gold

    Footings redesigned significant savings to piling contractor (>>$20k)

    Original client unhappy !!!!!

    Th ilin ntr t r w th n fit f llevel investigation and reaped the benefits

  • 7/28/2019 Guide to Foundation_7

    19/33

    Case Study 4 - Eureka Tower, Melbourne

    19

  • 7/28/2019 Guide to Foundation_7

    20/33

    Case Study 5 - Eureka Tower, Melbourne

  • 7/28/2019 Guide to Foundation_7

    21/33

    Inferred Stratigraphy Section AA

    Upper basalt

    Siltstone

  • 7/28/2019 Guide to Foundation_7

    22/33

    Inferred Stratigraphy Section BB

    U erbasal

    25m

    35 m

    Lower basalt

    Siltstone

  • 7/28/2019 Guide to Foundation_7

    23/33

    Limits of basalt

    Upper Basalt

    ower asa

  • 7/28/2019 Guide to Foundation_7

    24/33

    CFA and Bored Pile solution

    Gold level investigation provided significant

    cost and time savin s to ro ect and mana edthe risks of complex ground conditions

  • 7/28/2019 Guide to Foundation_7

    25/33

    Case Study 6 Residential Building, Melbourne

    40 level building, small site

    Subsurface strati ra h weathered siltstone shallow footin s/raft

    Recommended Gold level geotechnical investigation.

    Silver (by others) carried out (for $30 k less), piled footingsrecommen e not practca or t s s te.

    Original Gold investigation carried out to estimate deformationro erties

    Raft footing proposed and built

    Silver investigation provided impractical

    solution. Gold rovided ractical footinsolution at reduced cost and construction time.

  • 7/28/2019 Guide to Foundation_7

    26/33

    Case Study 5 Esplanade, Darwin

    Case Study

    Darwin

    Deeply weatheredphyllite

    Bored piles

    Difficult to sample

    UCS not possibleThe original Silver level investigation did not

    Is(50) < 0.05 MPa

    Pressuremetertesting unsuccessful

    .

    identified the risks and resulted in significant

    Slakes

    PDA testing allowed

    Analysis

    Founded on shallowfootings

  • 7/28/2019 Guide to Foundation_7

    27/33

    Case Study 6 Oracle Towers, Gold Coast

    Two x 40 level towers

    Stratigraphy 25 m sand, 8 mclay, 4 m gravel, hard rock

    socketed into rock. Piled raftconsidered but discounted.

    e orgna ver eve nves ga on was nosufficient for alternative design options. Gold

    No bored piling rigs available

    Delay to project startlevel investigation allowed alternative footingo tions to be considered and resulted in

    Piled raft using CFA piles

    Reduction in piling costs and

    significant foundation cost and construction

    construction time

    27

  • 7/28/2019 Guide to Foundation_7

    28/33

    Case Study 6 Nakheel Tower, Dubai

    > 1km high tower

    Mass > 2,000,000 tonnes

    90 m diameter

    20 m deep basement, 120 m diameter High saline groundwate

    Soft calcareous rock to 200 m

  • 7/28/2019 Guide to Foundation_7

    29/33

  • 7/28/2019 Guide to Foundation_7

    30/33

    Platinum Level Investigation

    Initial investigation

    Boreholes to 60 m one borehole to 120 m

    lower standard of drilling, laboratory testing only (disturbed samples)

    Preliminary recommendations piles possibly in excess of 120 mept to mt settements

    Settlement estimate of about 500 mm risk of tilt Subse uent Investi ation

    Boreholes to 300 m, triple tube coring Extensive laboratory testing for strength, stiffness and constitutive

    behavioue a num eve nves ga ongave everyone the confidence that

    Extensive insitu testing including pressuremeter, crosshole seismic,full scale pile load tests and construction trials

    Extensive 3D finite element anal sis lus others

    this could be done

    Settlement estimate of about 80 mm Basement retention no anchors

    30

  • 7/28/2019 Guide to Foundation_7

    31/33

    Footing Layout

    Barrette toe levels

    -55 m DMD

    -60 m DMD

    -79 m DMD

    Barrette s izes

    . .

    1.2m x 2.8 m

    Raft thicknesses

    2.5 m

    4.0 m6.0 m to 8.0 m

  • 7/28/2019 Guide to Foundation_7

    32/33

    Case Study 7 Basement

    2 level basement in alluvium onbeach

    Tertiary clay at about 12 m depth

    Potential buried channels ecant p es to exten mnmum

    3 m into tertiary clay

    Additional investi ation

    The original Silver level investigation identified

    recommended to confirm depthto tertiary clay not done

    .

    difficulties with increased cost and time followed.

    during CFA piling

    Not done - not all pilespenetrated to tertiary clay

    Construction issues

    32

  • 7/28/2019 Guide to Foundation_7

    33/33

    Concluding Comments

    Numerous examples of the value of better geotechnical investigations

    But ... Our clients continue to acce t lower cost investi ations

    The market is competitive you are not being ripped off.

    Dont take bids for geotechnical advice based on price look what theyo er. a prce s g er t ere are pro a y geotec nca rs s t eothers have not forseen or there is opportunity for significant savingson foundations.

    Be open minded - foundation solution, pile type or installation technique.Some piling methods can be impractical for some ground conditions.

    You get what you pay for

    You a for the round investi ation sooner or later

    Thank you

    33