Guide to Foundation_7
-
Upload
rc-dela-roca -
Category
Documents
-
view
215 -
download
0
Transcript of Guide to Foundation_7
-
7/28/2019 Guide to Foundation_7
1/33
Piling & Deep Foundations 2010
Geotechnicalnves ga on an
Design for Piling
Works
1
-
7/28/2019 Guide to Foundation_7
2/33
Outline
You get what you pay for Benefits of Doing More
Case Studies
Closing Remarks
2
-
7/28/2019 Guide to Foundation_7
3/33
Client Moments
Just do a basic investigation the piling contractors can take the risk
-
Can you guys help us out as we have a problem with our foundations ...we have a eotechnical re ort .. but.....?
The piling contractor cant install the piles to the design depth in the way
I want them to install them
Geotechnical advice during construction is an expense I dont need
the investigation, analysis and design have all been done I dont need
construction advice
The piling contractor is claiming latent conditions can you help
I must have bored piles on this project, and you cant use bentonite or
polymer to install them
3
-
7/28/2019 Guide to Foundation_7
4/33
Client Moments
You pay for geotechnical advice/investigation one way or another
am a ng a conserva ve approac ....so can go c eap on my
geotechnical advice/investigation
I want to spend as little money as I can on the foundations as we never
....
go and get decent geotechnical advice/investigation later on
get one from Joe for half the price
We have to take the chea est rice I know we will a for it in the end
but that is the policy
With eotechnical advice/investi ation ou et what ou a for4
-
7/28/2019 Guide to Foundation_7
5/33
Levels of Geotechnical Input
Ground investigation, analysis, design, construction services...
You et what ou a for...
Gold
Silver
Bronze
5
-
7/28/2019 Guide to Foundation_7
6/33
You get what you pay for !
Bronze Silver Gold Platinum
boreholes > toe de th ofSilver+moreboreholes, Gold+comprehensive
GroundInvestigation
shallowboreholesnotestingand/orsampling
piles
SPTtestingIndextesting
someinsitutestingformodulus,laboratory
testingforpermeability,modulusandstrength
testingformodulus,
strengthandpermeability,staticpileloadtesting
GeotechnicalEngineer
LimitedexperienceNonexpert ExperiencedLimitedinexpertise ExperiencedExpert ExperiencedExpert
Desi nParameters
Guesse Gener c S tespec c En ance s tespec c
Analysis None EmpiricalSilver+simple
theoreticalorbasic Gold+advancednumericalmodelling
Design Rulesofthumb(overlyconservative)
Empirical,Loadbased,standardindustry ImprovedServiceabilitybased OptimisedServiceabiltybased
Usuallyover
designed Usuallyoverdesigned Partiallyoptimiseddesign Optimiseddesign
Maybeunsafe Safe Safe SafeRisk High Low VeryLow VeryLowCost $50k $80k $120k $250k
6
-
7/28/2019 Guide to Foundation_7
7/33
Implications of Enhanced Geotechnical Input
How does enhanced eotechnical in ut hel ou? Relatively small increase in initial cost (as % of total foundation cost)
Potential significant savings in overall foundation costs due to:i. Improved strength reduction factors (AS2159 2009)
ii. Improved design parameters
.
serviceability)
iv. Improved confidence (due to ii and iii and reduced risk) allowingoptimisation
v. Reduced duration for foundation works
7
-
7/28/2019 Guide to Foundation_7
8/33
Improved Strength Reduction Factors
8
-
7/28/2019 Guide to Foundation_7
9/33
Hypothetical Example 1
Simple Geology 30 m compressible soils over weathered rock, highgroun water ta e
50 No. 1.2 m diameter bored piles, no basement
Pile working load of 15 MN
9
-
7/28/2019 Guide to Foundation_7
10/33
Improved Strength Reduction factors
10
-
7/28/2019 Guide to Foundation_7
11/33
Improved Parameters, Analysis and Design
11
-
7/28/2019 Guide to Foundation_7
12/33
Pile Construction Time
12
-
7/28/2019 Guide to Foundation_7
13/33
Hypothetical Example 2
Complex Geology e.g. Two separate flows of basalt of variablet c ness, qua ty an extent separate y st so over s opngweathered bedrock surface. Bedrock varies in weathering with depth
and location and is intersected by dykes. High groundwater table.
50 No. 1.2 m diameter bored piles, 3 level basement, diaphragm wall
40 m x 40 m in plan
e wor ng oa s rom o
13
-
7/28/2019 Guide to Foundation_7
14/33
Example 2 - Risks and Opportunities
Risks Opportunities
Excavation
Optimised retention Groun water/ ewaterng
Pile founding levels Optimised pile lengths
Socket lengths - dykes Differential settlement/tilt
. .
different levels inbasalt/bedrock
gn can oppor un es orreducing foundation costs, Longer piles
Construction difficulties
Alternative footing
systems
construction time and risk
Delays
Latent conditions
Shorter construction time
14
-
7/28/2019 Guide to Foundation_7
15/33
15
-
7/28/2019 Guide to Foundation_7
16/33
Case Study 1 Royal Domain Towers, Melbourne
EW-MW siltstone from
0
GARSP - as
0
GARSP - as
sur ace - eepweathering
dykes 10 EW - MWSiltstone/Sandstone
cons ruc e
10 EW - MWSiltstone/Sandstone
cons ruc e
~ 85 piles0.75 m to 1.5 m dia
15
Depth(m) Traditional
approach15
Depth(m) Traditional
approachGold level investigation provided significantserv cea y oa s
5 MN to 15 MN
design pile head
20
Saving of 9.5 m
20
Saving of 9.5 m
Benefits - savings
950 m socket length
se emen : a2525
1.2 m dia. ile SL= 15.3 MN
m concre e
1400 m3 spoil
$$ + 42 days
Addi tional Cost for3030
Pressuremete testng, UCS
testing, analysis
on-site presence
-
7/28/2019 Guide to Foundation_7
17/33
Case Study 2 Freshwater Place, Melbourne
30 m overburden over
1.2 m diameter pile, serviceability load = 27 MN
30
- s s one(variable)
70 x 1.2 m dia. Piles 35GARSP - as
constructed
pus o ers
serviceability loads17 MN to 30 MN
-
40HW - SW
Siltstone /
Gold level investigation provided significant
design top of socketsettlement : 1 % dia
900 m socket length 1000 m3 concrete
1500 m3 spoil
45
Depth(m
)
Sandstone
Traditional
approach Saving of up to 17 m
ana ys s $$ + 40 days
Addi tional Cost for
Pressuremeter testing, UCS
50
, ,
on-site presence55
60
-
7/28/2019 Guide to Foundation_7
18/33
Case Study 3 SU Building, Melbourne
Multi storey building
Subsurface strati ra h weathered siltstone
Recommended Gold level geotechnical investigation. Client wanted
only to pay for silver (for about $20 k less) ver carre out, ootngs es gne accor ngy
Piling contractor engaged on lump sum price design and construct
Piling contractor requested additional geotech Gold
Footings redesigned significant savings to piling contractor (>>$20k)
Original client unhappy !!!!!
Th ilin ntr t r w th n fit f llevel investigation and reaped the benefits
-
7/28/2019 Guide to Foundation_7
19/33
Case Study 4 - Eureka Tower, Melbourne
19
-
7/28/2019 Guide to Foundation_7
20/33
Case Study 5 - Eureka Tower, Melbourne
-
7/28/2019 Guide to Foundation_7
21/33
Inferred Stratigraphy Section AA
Upper basalt
Siltstone
-
7/28/2019 Guide to Foundation_7
22/33
Inferred Stratigraphy Section BB
U erbasal
25m
35 m
Lower basalt
Siltstone
-
7/28/2019 Guide to Foundation_7
23/33
Limits of basalt
Upper Basalt
ower asa
-
7/28/2019 Guide to Foundation_7
24/33
CFA and Bored Pile solution
Gold level investigation provided significant
cost and time savin s to ro ect and mana edthe risks of complex ground conditions
-
7/28/2019 Guide to Foundation_7
25/33
Case Study 6 Residential Building, Melbourne
40 level building, small site
Subsurface strati ra h weathered siltstone shallow footin s/raft
Recommended Gold level geotechnical investigation.
Silver (by others) carried out (for $30 k less), piled footingsrecommen e not practca or t s s te.
Original Gold investigation carried out to estimate deformationro erties
Raft footing proposed and built
Silver investigation provided impractical
solution. Gold rovided ractical footinsolution at reduced cost and construction time.
-
7/28/2019 Guide to Foundation_7
26/33
Case Study 5 Esplanade, Darwin
Case Study
Darwin
Deeply weatheredphyllite
Bored piles
Difficult to sample
UCS not possibleThe original Silver level investigation did not
Is(50) < 0.05 MPa
Pressuremetertesting unsuccessful
.
identified the risks and resulted in significant
Slakes
PDA testing allowed
Analysis
Founded on shallowfootings
-
7/28/2019 Guide to Foundation_7
27/33
Case Study 6 Oracle Towers, Gold Coast
Two x 40 level towers
Stratigraphy 25 m sand, 8 mclay, 4 m gravel, hard rock
socketed into rock. Piled raftconsidered but discounted.
e orgna ver eve nves ga on was nosufficient for alternative design options. Gold
No bored piling rigs available
Delay to project startlevel investigation allowed alternative footingo tions to be considered and resulted in
Piled raft using CFA piles
Reduction in piling costs and
significant foundation cost and construction
construction time
27
-
7/28/2019 Guide to Foundation_7
28/33
Case Study 6 Nakheel Tower, Dubai
> 1km high tower
Mass > 2,000,000 tonnes
90 m diameter
20 m deep basement, 120 m diameter High saline groundwate
Soft calcareous rock to 200 m
-
7/28/2019 Guide to Foundation_7
29/33
-
7/28/2019 Guide to Foundation_7
30/33
Platinum Level Investigation
Initial investigation
Boreholes to 60 m one borehole to 120 m
lower standard of drilling, laboratory testing only (disturbed samples)
Preliminary recommendations piles possibly in excess of 120 mept to mt settements
Settlement estimate of about 500 mm risk of tilt Subse uent Investi ation
Boreholes to 300 m, triple tube coring Extensive laboratory testing for strength, stiffness and constitutive
behavioue a num eve nves ga ongave everyone the confidence that
Extensive insitu testing including pressuremeter, crosshole seismic,full scale pile load tests and construction trials
Extensive 3D finite element anal sis lus others
this could be done
Settlement estimate of about 80 mm Basement retention no anchors
30
-
7/28/2019 Guide to Foundation_7
31/33
Footing Layout
Barrette toe levels
-55 m DMD
-60 m DMD
-79 m DMD
Barrette s izes
. .
1.2m x 2.8 m
Raft thicknesses
2.5 m
4.0 m6.0 m to 8.0 m
-
7/28/2019 Guide to Foundation_7
32/33
Case Study 7 Basement
2 level basement in alluvium onbeach
Tertiary clay at about 12 m depth
Potential buried channels ecant p es to exten mnmum
3 m into tertiary clay
Additional investi ation
The original Silver level investigation identified
recommended to confirm depthto tertiary clay not done
.
difficulties with increased cost and time followed.
during CFA piling
Not done - not all pilespenetrated to tertiary clay
Construction issues
32
-
7/28/2019 Guide to Foundation_7
33/33
Concluding Comments
Numerous examples of the value of better geotechnical investigations
But ... Our clients continue to acce t lower cost investi ations
The market is competitive you are not being ripped off.
Dont take bids for geotechnical advice based on price look what theyo er. a prce s g er t ere are pro a y geotec nca rs s t eothers have not forseen or there is opportunity for significant savingson foundations.
Be open minded - foundation solution, pile type or installation technique.Some piling methods can be impractical for some ground conditions.
You get what you pay for
You a for the round investi ation sooner or later
Thank you
33