GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility...
Transcript of GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility...
![Page 1: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/1.jpg)
GSDO Schedule Health Metrics
Antonio Rippe, GSDO JCL Consultant, Tecolote Research, Inc. Bruce Chamberlain, GSDO IAT Senior Schedule Analyst
Darren Elliott, Tecolote Research, Inc.
1
![Page 2: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/2.jpg)
Study Recommendation
With the implementation of cost & schedule joint analysis, two new schedule products have been introduced—the analysis schedule and the JCL model
Analysis schedules are built differently and have separate objectives from the “business-as-usual” schedule—some of the metrics used on one may not be applicable to the other
This study recommends a specific set of criteria to be used for each product—not a comprehensive list—yet it gets the dialogue started that the Health Check metrics are not a "one size fits all" solution
2
![Page 3: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/3.jpg)
Value of Schedule Health Checks
Schedule Health Checks help validate scheduling best practices Minimal standards or recommended metrics exist for JCL models Current guidelines designed primarily focus on detailed schedules
Schedule Health Check Study initiated to determine appropriate best practice metrics for JCL analysis schedule
Evaluate the current schedule assessment guidelines and JCL modeling application in the industry to determine what metrics are used to assess schedule health Group the metrics into the GAO Best Practice Areas and assess consistency across the guidelines/tools Recommend the health check metrics for GSDO use in evaluating schedules at different levels of fidelity and purposes (e.g., detail schedules, IMS, analysis schedules, JCL models)
3
![Page 4: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/4.jpg)
GAO Schedule Best Practice Metrics
GAO conducts Best Practices Reviews to identify public and private sector organizations that are widely recognized for major improvements in their performance in a specific area, such as scheduling
The processes, practices, and systems identified in these organizations are identified as best practices and provide a model for other organizations with similar functions and/or missions GAO develops Best Practices Methodologies by studying these processes, practices, and systems and coordinating with industry practitioners and stakeholders to create a framework for assessing similar programs, operations, or functions
In May 2012, the GAO published GAO published an exposure draft for the GAO Schedule Assessment Guide (GAO-12-120G)
GAO identified ten (10) best practice areas in the GAO Schedule Assessment Guide, outlined in the next slide
GAO guidelines are broader than DCMA DCMA focuses primarily on EVM As such, GAO was determined to be a good foundation for establishing the areas for metrics to be identified
GAO Handbook still DRAFT 4
![Page 5: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/5.jpg)
Best Practice # Best Practice Area Best Practice Description The schedule should reflect all activities as defined in the project's work breakdown structure (WBS)
GAO – 1 Activity Capture
The schedule should be planned so that critical project dates can be met (activities need to be logically sequenced)
GAO – 2 Activity Sequencing
GAO – 3 Resource Assignment The schedule should reflect the resources needed to do the work
Duration Establishment
The schedule should realistically reflect how long each activity will take
GAO – 4
Detailed schedule should be horizontally traceable - should link products and outcomes associated with other sequenced activities IMS should be vertically traceable - varying levels of activities and supporting sub-activities can be traced
Vertical and Horizontal Traceability GAO – 5
GAO – 6 Critical Path Validity The schedule should identify the program critical path
The schedule should identify reasonable float (or slack) so that the schedule's flexibility can be determined
GAO – 7 Float Reasonableness
Ability to predict the level of confidence in meeting a program's completion date, determine the time contingency needed for a level of confidence, and identify high-priority risks and opportunities via statistical simulation
Schedule Risk Analysis GAO – 8
Provide a realistic forecast of start and completion dates for program activities
GAO – 9 Progress Updates
The schedule should be continually monitored so as to reveal when forecasted completion dates differ from planned dates and whether schedule variances will affect downstream work
GAO - 10 Baseline Analysis
5
![Page 6: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/6.jpg)
Comparative Analysis of Metrics
Health check metrics for five separate tools and guidelines were assessed GAO Scheduling Best Practices
Identifies best practice areas and metrics/criteria that schedules should meet to be deemed healthy
DCMA 14 Point Assessment Set of criteria developed by the Defense Contract Management Agency [DCMA] to assess schedule quality
NASA Schedule Test and Assessment Tool (STAT) Tool developed by MSFC to assist the scheduling community in the identification, measurement, and rating of key credibility indicators contained within a project IMS (only supports MS Project)
Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential for conducting a schedule risk analysis
Joint Analysis of Cost and Schedule (JACS) Health Checks Utility within the JACS tool that provides two reports; one report is a DCMA 14 point assessment the other report is a review of over 75 metrics to assess a schedule’s suitability for conducting an integrated cost and schedule risk analysis and to verify that data was properly specified within JACS to run the model appropriately
6
![Page 7: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/7.jpg)
Recommended Health Check Metrics by Product
Review the current health check metrics in use for schedules and determine a sub-set that are applicable to Detail Schedules, Analysis Schedules, and JCL Models
Metrics divided into two sub-sections: 1. Identifies those metrics for which quantifiable values can be generated and
check criteria can be identified 2. Identifies important metrics to review but there should not be any attempt at
developing a scoring to rate goodness/healthiness for the metric
Schedule Type Schedule Objective Important Factors for Health
Detail Schedule Provide detailed identification of work effort and progress status for the ongoing effort at the level that the actual work is performed.
Structural integrity, accurately statused, enable tracking to a baseline, alignment with the WBS, granularity in detail and timespans calculation of earned value, and insight into downstream challenges if work slips occur.
Analysis Schedule
Provide a higher level replication of the schedule effort focused on capturing the major work-flows of the project scope with specific emphasis on integration points and work flows leading to deliverables.
Analysis schedules must be structurally sound with solid logic and be accurately statused. For use in SRAs and JCLs the network must be able to move freely without limitations of constraints.
JCL Model Enables the alignment of project costs and risks so that an integrated cost and schedule risk analysis can be performed.
In addition to factors for an Analysis Schedule a JCL model must have alignment with costs, linked to risks, and proper uncertainty specification.
7
![Page 8: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/8.jpg)
Health Metrics for Scoring a Schedule
GAO Best Practice
Area
GAO Scheduling Best Practices
DCMA 14 Point Assessment
STAT HealthCheck
Oracle PRA Health Check
JACS Health Check
Detailed Schedule
Analysis Schedule
JCL Model
Included in GSDO
Metric Sub-Metric
Activity Capture (GAO - 1)Detail
Manual Tasks N N Y N N H H HTasks and Milestones Needing Updates N N Y N N H H HConstraints Defined Count Y Y Y Y Y H H H
MilestonesMilestone Ratio Y Y Y N N H H H Y
LOE (Long Duration Tasks Whose Durations are not Affected by a Start and Finish Activity)LOE Count N N N N N H H
Activity Sequencing (GAO - 2)Logic
No Predecessors Y Y Y Y Y H H H YNo Successors Y Y Y Y Y H H H YSummary Task with Predecessor Y N Y Y Y H H H YSummary Task with Successor Y N Y Y Y H H H YLead (Negative Lag) Y Y N Y Y H H H YLag Y Y N Y Y H H H Y
Relationship Count SF Relation N Y N Y Y H H HConstraints
Start No Later Than Y Y Y N Y H H HFinish No Later Than Y Y Y N Y H H H YMust Start On Y Y Y N Y H H H YMust Finish On Y Y Y N Y H H H YFinish No Earlier Than Y Y Y N Y H H H
For the most part, the recommended GAO-1 and GAO-2 Health Checks in the study were found across most of the investigated tools
8
![Page 9: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/9.jpg)
Health Metrics for Scoring a Schedule
GAO Best Practice
AreaMetric Sub-Metric
GAO Scheduling Best Practices
DCMA 14 Point Assessment
STAT Health Check
Oracle PRA Health Check
JACS Health Check
Detailed Schedule
Analysis Schedule
JCL Model
Included in GSDO
Resource Assignment (GAO - 3)Cost Specification LOE Task with Cost Loading N N N N Y H
Establishing Durations (GAO - 4)Duration Length
Long Duration Y Y N N N H H H YDuration Specification Tasks with Estimated Duration N N Y N Y H H H
Critical Path Validity (GAO - 6)Critical Tasks
Critical Path Test N Y Y N N H H HLOE tasks on Critical path Y N N N N H H H Y
Float Reasonableness (GAO - 7)Long Float
High Float Tasks (Long Total Float Tasks) N Y N N Y H H H YShort and negative Float
Negative Float Tasks Y Y N N N H H H Y
GAO-5 metrics not recommended for scoring a schedule’s health
9
![Page 10: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/10.jpg)
Health Metrics for Scoring a Schedule
GAO Best Practice
Area
GAO Scheduling Best Practices
DCMA 14 Point Assessment
STAT Health Check
Oracle PRA Health Check
JACS Health Check
Detailed Schedule
Analysis Schedule
JCL Model
Included in GSDO
Metric Sub-Metric
Schedule Risk Analysis (GAO - 8)Duration Uncertainty - Inputs Actual Finish Declared With Uncertainty N N N N Y H
Duration Without Uncertainty (in-Progress or Future) Y N N N Y HHammock With Duration Uncertainty N N N N Y HUncertainty on non-Hammock LOE Task N N N N Y H
Risk Specification - InputsRisk Impact On Actual Finish N N N N Y HRisk Missing Uncertainty Declaration N N N N Y HRisk with Invalid Likelihood N N N N Y HRisk with Negative Likelihood N N N N Y HRisk with Zero Likelihood N N N N Y H
Cost Uncertainty - InputsTD Cost Without Uncertainty N N N N Y HTI Cost Without Uncertainty N N N N Y HTask with TD Cost and Zero Duration N N N N Y H
Correlation- InputsTask without Correlation N N N N Y H
Schedule Progress Updates (GAO - 9)Status
Task Behind of Schedule N N N N Y H H HNo Status Date Defined N N N N Y H H HInvalid Actual Dates N Y N N N H H H
In Progress TasksStarted Activities with no Actual Start Y N N N N H
HH H
Actual Start in the Future N N Y N Y HH
HYY
Actual Finish in the Future N N Y N Y H
H
HCompleted Tasks Finished Activities with no Actual Finish Y N N N N H H
Actual Start With Non-Completed Predecessor Tasks N N N N N H H H
GAO-8 metrics analyze uncertainty/risk inputs and are not found in the majority of the tools investigated 10
![Page 11: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/11.jpg)
Health Metrics for Information on a Schedule
Oracle PRA Health Check
STAT Health Check
DCMA 14 Point Assessment
GAO Scheduling Best Practices
Detailed Schedule
Start No Earlier Than
GAO Best Practice
Area
JACS Health Check
Analysis Schedule
JCL Model
Included in GSDO
Metric Sub-Metric
Activity Capture (GAO - 1)Detail
Task Marked As Margin N N N N Y I I ILOE (Long Duration Tasks Whose Durations are not Affected by a Start and Finish Activity) LOE Task with Successor N N N N Y I IHammocks (Tasks Whose Durations are Directly Affected by a Start and Finish Activity)
Hammock Count Y N N Y N I IActivity Sequencing (GAO - 2)
Logic Mega Hotspot Y N N N N I I I YPositive lags on FS links N N N Y N I ITask with External Links N N N N Y I I
Relationship CountSS Relation Y Y N N N I I YFF Relation Y Y N N N I I Y
ConstraintsY Y Y N Y I I I Y
Resource Assignment (GAO - 3)Cost Specification
TD Cost And No Spending Profile N N N N Y ITI Cost And No Spending Profile N N N N Y IInvalid TD Spending Profile N N N N Y IInvalid TI Spending Profile N N N N Y I
Many GAO-2 metrics that the investigated tools use for scoring are recommended for informational purposes to the schedule analyst
11
![Page 12: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/12.jpg)
Health Metrics for Information on a Schedule
GAO Best Practice
Area
DCMA 14 Point Assessment
GAO SchedulingBest Practices
Vertical Integration I
I
STAT Health Check
Oracle PRA Health Check
JACS Health Check
Detailed Schedule
Analysis Schedule
JCL Model
Included in GSDO
Metric Sub-Metric
Establishing Durations (GAO - 4)Duration Length
Average Duration Y N N N N I IMedian Duration Y N N N N I I
Vertical and Horizontal Traceability (GAO - 5)Vertical Integration Y N N N N I IHorizontal Integration Horizontal Integration Y N N N N I I
Critical Path Validity (GAO - 6)Critical Tasks
Critical Task Count Y Y Y N N I I I YCritical Path Length Index (CPLI) N Y N N N I ICritical High Duration N N N N N I I Y
GAO-5 and GAO-6 metrics used for informational purposes rather than scoring
12
![Page 13: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/13.jpg)
Health Metrics for Information on a Schedule
Y
N
GAO Best Practice
Area
GAO Scheduling Best Practices
DCMA 14 Point Assessment
STAT Health Check
Oracle PRA Health Check
JACS Health Check
Detailed Schedule
Analysis Schedule
JCL Model
Included in GSDO
Metric Sub-Metric
Schedule Risk Analysis (GAO - 8)Duration Uncertainty - Inputs
Duration Outside Uncertainty Range N N N N Y IUncertainty on Margin Task N N N N Y ISummary Task with Duration Uncertainty N N N N Y IBroad Uncertainty Range Y N N N N I
Risk Specification - InputsTask with Multiple Risk Impacts N N N N Y ITask Dependent Upon Multiple Risk Impacts N N N N IRisk with Small Likelihood N N N N Y IRisk without Threat ID N N N N Y IRisk Deactivated N N N N Y I
Cost Uncertainty - InputsTD Cost Outside Uncertainty Range N N N N Y ITI Cost Outside Uncertainty Range N N N N Y I
Critical Path Exposure - Output AnalysisHigh Criticality Y N N N N IHidden Critical Paths Y N N N N I
Uncertainty Range - Output AnalysisNo Downside Y N N N N INo Upside Y N N N N I
IOther - Output Analysis
Schedule Risk Hot Spots Y N N N
GAO-8 metrics analyze uncertainty/risk inputs and are not found in the majority of the tools investigated
13
![Page 14: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/14.jpg)
Health Metrics for Information on a Schedule
GAO Best Practice
Area
GAO Scheduling Best Practices
DCMA 14 Point Assessment
STAT Health Check
Oracle PRA Health Check
JACS Health Check
Detailed Schedule
Analysis Schedule
JCL Model
Included in GSDO
Metric Sub-Metric
Schedule Progress Updates (GAO - 9)Status
Completed Tasks N N N Y N I I I
Underway (In-Progress) Y N N Y N I I ICritical Underway Y N N N N I I IIn-Progress On Schedule Y N N N N I I ITask Ahead of Schedule N N N N Y I I IActual Start Defined N N N N Y I I IActual Finish Defined N N N N
N
Y I I IBaseline Analysis (GAO - 10)
Baseline DataBaseline Execution Index (BEI) Y Y N N I I YScheduled/Baselined to Start Y N N N N I IScheduled/Baselined to Finish Y N N N N I I
GAO-9 metrics for status and GAO-10 metrics used for informational purposes rather than scoring
14
![Page 15: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/15.jpg)
Conclusion
Study evaluated the current schedule assessment guidelines and several JCL modeling applications to determine what metrics are used to assess schedule health
Grouped into the ten (10) GAO best practice areas and a comparative analysis was conducted to determine overlap and gaps between the various guidelines and tools Study identified that although many of the tools and guidelines identify similar metrics, there is a wide variation in the capture of the metrics Detailed review of the metrics in each tool/guideline conducted to make sure that non-duplicate metrics are not identified
Metrics were identified as the recommended list of health check metrics for GSDO to use in evaluating schedules at different levels of fidelity and purposes (e.g., detail schedules, IMS, analysis schedules, JCL models)
Metrics for which criteria could be developed and an overall schedule health rating could be generated Additional metrics that were valuable to provide insight into the schedule structure, topology, and integrity
15
![Page 16: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/16.jpg)
Backup
16
![Page 17: GSDO Schedule Health Metrics - NASA...Oracle Primavera Risk Analysis (OPRA) Health Check Utility within the OPRA tool to conduct a health check on a schedule to assess its potential](https://reader030.fdocuments.net/reader030/viewer/2022040813/5e586027d2c29605bf213f34/html5/thumbnails/17.jpg)
Background
NPR 7120.5 established requirements for program/projects to conduct and assess the cost and schedule joint confidence levels (JCL) expected for their program/project baselines
JCL evaluates the likelihood that a project can achieve planned cost and schedule targets
Central to the concept of a JCL analysis is that costs are directly related to schedule
This concept causes the underlying schedule network and ensuing schedule risk analysis (SRA) to be the core central enablers for conducting a JCL analysis Ensuring that the underlying schedule logic meets a basic level of integrity is a fundamental precursor toward conducting an SRA or JCL
A “healthy” schedule plays an indispensable role in modeling the Joint Confidence Level (JCL)
17