GRP PROGRAM CONSTRUCTION PROGRESS
SJRA Board of Directors
MeetingMarch 28,
2013
GRP Review Committee Meeting March 26,
2013
![Page 2: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/2.jpg)
SURFACE WATER FACILITY CONSTRUCTION ADMINISTRATION
Project Data Thru 02/28/2013 - Early Work Package 3
Project Budget: $191,000,000.00
Contracted Amount: $90,331,558.00
Change Orders: $0.00
Estimate to Complete: $191,000,000.00
Amount Invoiced: $16,591,685.62
Budget Remaining: $174,408,314.38
Percent In-Place Work: 18.40%
Completion Date: June 1, 2015
![Page 3: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/3.jpg)
Placement of 75 feet long precast concrete bridge girders
RAW WATER INTAKE AND PUMP STATION
March 06, 2013
![Page 4: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/4.jpg)
Placement of 75 feet long precast concrete bridge girders
RAW WATER INTAKE AND PUMP STATION
March 06, 2013
![Page 5: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/5.jpg)
Overview of precast concrete girders – Dam to Bent 3
RAW WATER INTAKE AND PUMP STATION
March 15, 2013
![Page 6: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/6.jpg)
Metal decking installation at Raw Water Intake bridge
RAW WATER INTAKE AND PUMP STATION
March 12, 2013
![Page 7: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/7.jpg)
Grade-beam installation at Raw Water Intake building structure
RAW WATER INTAKE AND PUMP STATION
March 15, 2013
![Page 8: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/8.jpg)
HIGH SERVICE PUMP STATION
Flowable fill installation beneath Pump Room
March 04, 2013
![Page 9: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/9.jpg)
HIGH SERVICE PUMP STATION
Plumbing installation at Pump Room
March 13, 2013
![Page 10: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/10.jpg)
GROUND STORAGE TANKS
February progress photo at GST2
February 15, 2013
![Page 11: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/11.jpg)
GROUND STORAGE TANKS
Rebar installation at GST2
March 01, 2013
![Page 12: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/12.jpg)
GROUND STORAGE TANKS
Concrete placement at GST2 – 625 CYDS
March 06, 2013
![Page 13: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/13.jpg)
February progress photo at Granulated Activated Carbon Building
WATER TREATMENT PLANT
February 01, 2013
![Page 14: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/14.jpg)
Process piping installation at Granulated Activated Carbon Building
WATER TREATMENT PLANT
March 15, 2013
![Page 15: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/15.jpg)
Process piping installation at Granulated Activated Carbon Building
WATER TREATMENT PLANT
March 13, 2013
![Page 16: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/16.jpg)
February progress photo at Membrane Building
WATER TREATMENT PLANT
February 08, 2013
![Page 17: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/17.jpg)
Lower trench drain foundation for the Membrane Building
WATER TREATMENT PLANT
March 11, 2013
![Page 18: GRP Program Water Line Construction Progress](https://reader036.fdocuments.net/reader036/viewer/2022081401/556ae89cd8b42a86218b4b0f/html5/thumbnails/18.jpg)
Mass excavation and seal slabs for the Pre-Treatment Structure
WATER TREATMENT PLANT
March 15, 2013