Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014...

10
Submarine Evacuation System for Offshore Structures Group Members: Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey

Transcript of Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014...

Page 1: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

Submarine Evacuation System for Offshore Structures

Group Members: Ajanthan AsokanWilliam BarkhouseMatthew BrowneStephen Handrigan

February 4, 2014

Client: Dr. Michael Hinchey

Page 2: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

2

AgendaProject Overview

Problem Statement

Strategy

Current Progress

Upcoming Milestones

Presentation 2 Deliverables

QuestionsFebruary 4, 2014

Page 3: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

3

Project Overview

February 4, 2014

Previous IncidentsCurrent SolutionsOutstanding Risks

Fire IceWavesWind

Page 4: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

4

Problem Statement

To provide a solution for evacuation of an

offshore structure through the development of a

fully-submersible vessel deployable from the

topsides of an offshore structure

February 4, 2014

Page 5: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

5

StrategyPhase 1

Prototype Development Deployment Strategies

Phase 2Submarine FabricationPrototype Commissioning Deployment Testing

Phase 3Option A: Preliminary Full-scale DesignOption B: Revisit Prototype Design

February 4, 2014

Page 6: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

Current Progress – Phase 1

February 4, 2014 6

Design of the prototype modelStructural DesignMechanical DesignElectrical Design

Motion analysis – In Progress

Circuit Board Thruster

Stepper Motor BatteryBallast Tank

Page 7: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

7

Deployment Strategies

February 4, 2014

Page 8: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

8

Upcoming Development- Phase 201. Submarine Fabrication

Dave Snook – Tech Services Andrew Bazeley – Tecnadyne Paul Sirois – Clark Solutions Brian Pretty – Manufacturing Technology Centre

02. Prototype Verification Michael Hinchey – Client

03. Deployment Method Testing Leonard Lye – DOE Specialist

February 4, 2014

Page 9: Group Members:Ajanthan Asokan William Barkhouse Matthew Browne Stephen Handrigan February 4, 2014 Client: Dr. Michael Hinchey.

9

Presentation 2 DeliverablesTest analysis completed Phase 3 Project Direction Finalized

February 4, 2014