Griha presentation. for project managers..

57
Why Rate Buildings ? Buildings consume: 1. 40% Energy..... 2. 42% Water....... 3. 50% Raw materials … (TERI Griha Manual Vol.1)

Transcript of Griha presentation. for project managers..

Page 1: Griha presentation. for project managers..

Why Rate Buildings ?

Buildings consume:1. 40% Energy.....2. 42% Water.......3. 50% Raw materials …

(TERI Griha Manual Vol.1)

Page 2: Griha presentation. for project managers..

Building Activity contributes to :1. 50% Air Pollution......2. 42% Green House Gas....3. 50% Water Pollution......4. 48% Solid Waste Generated....5. 50% CFC.....

Page 3: Griha presentation. for project managers..

We Architects and Engineers

Seem like some “Villains”.... :(Following “Ratings” will make us less of so.. :):)

Ratings – evaluation Tool for Ecological Perfomance through Life Cycle of a Building..

Page 4: Griha presentation. for project managers..

Ratings- What do they do?

1. Look at various parameters ofa)Design....b) Construction...c) Operation 2.Criterion with assigned Points3.A project gets points...points add up...4.Voluntary in nature...

Page 5: Griha presentation. for project managers..

Some other rating systems:

BREEAM:Building Establishments Environmental Assessment Method.

One of the earliest developed in 1990 in UK.

CASBEE: Comprehensive Assessment System for Building Environment Efficiency.

Developed in Japan 2001.

Page 6: Griha presentation. for project managers..

GB Tools: Green Building Tools developed by International Framework committee of 25 countries . Developed in 1998 and constantly updated

HK BEAM: Developed in1996 in Hong Kong

LEED: Leadership in Energy and Environmental Design developed in US 1998.

Page 7: Griha presentation. for project managers..

GRIHA

Green Rating for Integrated Habitat Assessment.Developed by TERI and endorsed by MNRE.

Page 8: Griha presentation. for project managers..

Salient points

GRIHA has been developed for the different agro-climatic Zones of India.

Developed particularly for non-ac spaces or partially ac building.

Evaluators are experts from different fields connected to the buildings and are from specific region where the building is situated

Page 9: Griha presentation. for project managers..

Stresses on optimization of visual and thermal indoor comfort.

Integrates all relevant Indian Codes and Standards to act as tools for implementation

Page 10: Griha presentation. for project managers..

Emphasis:

Minimise --resource consumption-waste generation-overall ecological impact By Five R philosophy--Refuse-Reduce-Reuse-Recycle-Reinvent.

Page 11: Griha presentation. for project managers..

Broad categories: Site selection and Planning Building Planning and Construction Building Operation and Maintenance Innovation(34 Criteria---for this presentation 19 criteria

taken up)

Page 12: Griha presentation. for project managers..

Criterion 2: Preserve existing Vegetaion/or plant as per

Griha (1 point)Proper timing of Construction w.r.t. Rains

(optional clause no points) Confine Const. Activity (1 point) Erosion and sedimentation control (1 pt.)Preserve topsoil (1 point)TOTAL 4 POINTS.....

Page 13: Griha presentation. for project managers..
Page 14: Griha presentation. for project managers..

details

Protect by making tree guards Tree guards to extend beyond the drip line

Page 15: Griha presentation. for project managers..

Detention pond

Page 16: Griha presentation. for project managers..

Do not-----

Page 17: Griha presentation. for project managers..

Do not

Page 18: Griha presentation. for project managers..

Criterion 3:Soil Conservation:Very important oft overlooked.It takes 100 years for 25 mm of soil to form (Griha manual:Vol 2)

In India we have different types of soil, identify them, study fertility, pH,saline levls.,

Store it at site...Avoid carting fertile soil from elsewhere..

Page 19: Griha presentation. for project managers..
Page 20: Griha presentation. for project managers..

Check this site : http://ceds.org/esp.html gives vary comprehensively cost incurred when soil is left un-conserved.

Involve Landscape Architect from the beginning of the design as well as all the time during construction.

Total Points -2

Page 21: Griha presentation. for project managers..

Criterion 8:Health and Well being.Follow NBC guideline 2005 for safety/sanitation.Maintain Machinery..Signages at appropriate locations.Provide Safety Equipemnts, fire extinguishres..Light for Night work..Double earthing for Hand tools.(Point 1) ...oodles of social points...

Page 22: Griha presentation. for project managers..

Criterion 9:.Control Air Pollution during Construction.Clear minimal vegetation where needed..Provide hoarding around..Veg/Mulch where vehicles do not ply..Limit Vehicle movement-speed to10km/hr..Hard pave vehicle circulation path..Cover/ Enclose all loose materials, dusty loads.(Points 2)..oodles of economic points...

Page 23: Griha presentation. for project managers..
Page 24: Griha presentation. for project managers..

Criterion 12

.Slag cement uses 1-10% less water.(Griha manual Vol.4)

.Employ Moist Curing better still Membrane Curing..

.Use Superplaticizers

.Use Precast construction Technology.

.Partitions of Dry walling.

(Points 1)...oodles of ecological points...

Page 25: Griha presentation. for project managers..
Page 26: Griha presentation. for project managers..

Criterion 15

Speaks mainly on---- Utilization of Fly Ash in construction andUse of Pozzolana Cement

(Points 6)

Page 27: Griha presentation. for project managers..

Criterion 16

.Low Embodied Energy Materials and Methods.

.Pre-stressing/Pre- casting.

.Rat Trap brickwork/ Jali brickwork.

.Stabilized Mud Block To name a few....

(Points 4)...oodles of Ecological points...

Page 28: Griha presentation. for project managers..

Walls

Bricks EE 3(MJ/Kg)Concrete block EE 0.87(MJ/Kg)

Plaster EE1.8(MJ/Kg)

Paint EE67.5(MJ/Kg) CSEB EE 0.275(MJ/Kg)

Brick wall Mud wall.

Page 29: Griha presentation. for project managers..
Page 30: Griha presentation. for project managers..
Page 31: Griha presentation. for project managers..

Criterion 17:

Use of Low energy materials in Interiors.Though a subject closer to design still Project

Manager are important players..Renewable..Use waste products.Use of waste as raw material in different

stages..Durable/Low-maintenance.Products which generate min. waste during

production(Points:4)

Page 32: Griha presentation. for project managers..
Page 33: Griha presentation. for project managers..

Built in furniture

Page 34: Griha presentation. for project managers..

Criterion 20:

Decide on the suitable Waste Water Treatment systems.

.Many new ecological systems available:1.DEWATS2.SBT. 3.Use of Additives like Bio-sanitizers and EMResponsibility is to carry out regular wastewater

treatment testing.(Points 2)

Page 35: Griha presentation. for project managers..

DEWATS

Page 36: Griha presentation. for project managers..

Soil Bio Technology (SBT)

Page 37: Griha presentation. for project managers..

Criterion 21

Water Recycle and Reuse:Rainwater Harvesting is its key requirement..Need inputs on Rainfall patern..Soil type..Level of underground water..Pollution field..Per capita need/ Production need..Dual Plumbing

(Points 2)...oodles of ecological/economical points

Page 38: Griha presentation. for project managers..
Page 39: Griha presentation. for project managers..

through6” PVC Pipe in to The open well.

Road Drain Water Diverting

Water is collected In the open well &Same will be allowed to percolates through the ground

During Rain,Water flowThrough theValley, will beCollected inThe open well

Check Dam ConstructedTo check theRain water& allow theWater to Percolate intoThe groundTo increase The Ground Water Table.

Page 40: Griha presentation. for project managers..
Page 41: Griha presentation. for project managers..
Page 42: Griha presentation. for project managers..

Criterion 22:

Waste Management:.Waste reduction during construction:.Safe disposal of waste within the site—

achieve/strive for zero debris.Waste prevention strategy:.Std. Dimensions..Consider using used bldg.materials

(Points1)...oodles of eco logical/economical points

Page 43: Griha presentation. for project managers..
Page 44: Griha presentation. for project managers..

Criterion 23:

Waste Segregation:.Though a use parameter--This should be attempted as part of the design

as well as project management.

(Points1)...oodles of eco logical/economical points

Page 45: Griha presentation. for project managers..

Criterion 24:

Storage and Disposal of waste:

Allocate a separate space where disposal of collected waste can happen safely

(Points1)...oodles of eco logical/economical points

Page 46: Griha presentation. for project managers..

Criterion 25:

Resource recovery from waste:

.Waste can be fuel

.Waste can be manure

(Points1)...oodles of eco logical/economical points

Page 47: Griha presentation. for project managers..
Page 48: Griha presentation. for project managers..
Page 49: Griha presentation. for project managers..

Criterion 26:

Use low VOC Paints-Strive for

No Paints No sealants

(Points 3)

Page 50: Griha presentation. for project managers..

Criterion 27

MinimizeOzone depletingSubstances:Live with Solar Cycle.In the design Introduce courtyards

(Point 1)

Page 51: Griha presentation. for project managers..

Criterion 28

Ensure Water quality asper Indian Standards..Work with water optimization plan..Provide water quality results before and after

treatment..Check quality frequently.

(Points 2)

Page 52: Griha presentation. for project managers..

Criterion 29

Acceptable outdoor and indoor noise levels..Work with Noise reduction/sound transferrability

coefficients and decide on materials .Strategies outdoor noise control..Reduced use of noise creating equipments

during construction

(Points 2)

Page 53: Griha presentation. for project managers..

Criterion 30:

Non Smoking Policy

(Point 1)

Page 54: Griha presentation. for project managers..

Criterion 31:

Universal design

Page 55: Griha presentation. for project managers..

Criterion 32/33:

Energy audit and Validation:Energy audit report to be prepared by approved

auditors of BEE and Govt.Of India.(Points 0)C33:Building Operation and maintenance:Validate and maintain Green performancesProvide for O and M manuals..(Points 2)

Page 56: Griha presentation. for project managers..

Criterion 34:

Innovation:Lots to consider and no limit............

(Points 4)