Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand...
Transcript of Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand...
Project: Analysis of Indian distribution systems for the integration of high shares of rooftop PV
INTEGRATION OF RENEWABLE ENERGIES IN THE INDIAN ELECTRICITY SYSTEM (I-RE)
Final Workshop, 29 August 2017
Dr. Thomas Ackermann
Dr.-Ing. Eckehard Tröster
Grid Integration Study Methodology, Scenarios & Assumptions
Day 1, 10:45, 45 mins
Delhi Grid
• Introduction
• Scenarios investigated
Bhopal Grid
• Introduction
• Scenarios investigated
Solutions for enhancing the hosting capacity
CONTENT
2
3
INTRODUCTION TO THE DELHI GRID
Urban Feeder Characteristics:
• LV Network modelled with 2-5 400 V feeders per Distribution Transformer
• Min. length: 36 m
• Max. length: 719 m
• 8 Distribution Transformers (5.4 MVA total)
• Mostly of 630 kVA size
Rural Feeder Characteristics:
• Two 11kV feeders
• Feeder 1 length: 12.26 km
• Feeder 2 length: 12.3 km
• 40 Distribution Transformers in Feeder 1 (5.2 MVA total)
• Mostly of 100 kVA size
• 28 Distribution Transformers in Feeder 2 (4.6 MVA total)
• Mostly of 100 kVA size
FEEDERS INVESTIGATED
4
Two networks from Delhi were investigated
• Urban Feeder
• Rural Feeder
GRID STRUCTURE – URBAN FEEDER
5
033kV_Vasant..
011kV_Vasant..
External Grid
T01
_T
310
32
T01
_T
310
32
_2
0M
VA
_3
3/1
1kV
33/11kV Urban Feeder grid substation
11kV network Urban Feeder
400V Example networks
GRID STRUCTURE – RURAL FEEDER
6
Feeder 2
Feeder 1
PV Connection
towards Rawta
PV Connection
towards JhulJhuli
~
3.5 MW PV plant
66/11 kV substation Rural Feeder
66/11 kV substation Rural Feeder
7
DELHI: SCENARIOS
• Load:
• Measurement at DT is available
• Divvied up based on loading information of feeders
• Equally distributed along the feeder every ca. 25m
• PV:
• Connected at every household
• Aggregated PV generation is proportional to DT’s rating
Example: 100 kVA DT
URBAN FEEDER SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD
8
Load PV
Load PV
Load PV
Load PV
11 kV
400 V
PV equal distribution
Load PV
Load PV
Load PV
Load PV
Penetration Level PV(inverter) rating
30 % 30 kW
50 % 50 kW
75 % 75 kW
100 % 100 kW
150 % 150 kW
• Load:
• Measurement at DT is available
• Divvied up based on loading information of feeders
• Equally distributed along the feeder every ca. 25m
• PV:
• Connected at every household starting at half of the line
• Aggregated PV generation is proportional to DT’s rating, but individual size doubles
URBAN FEEDER SCENARIO 2: PV WITH HIGHER PV PENETRATION AT THE END OF FEEDER WITH NORMAL LOAD
9
Load
Load
Load PV
Load PV
11 kV
400 V
PV at end of LV feeder
Load
Load
Load PV
Load PV
Larger individual
size
• Load:
• Additional AC load is added to every household
URBAN FEEDER SCENARIO 3: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
10
Load PV
Load PV
Load PV
Load PV
11 kV
400 V
PV equal distribution
Load PV
Load PV
Load PV
Load PV
0
0.2
0.4
0.6
0.8
1
01:
00
02:
00
03:
00
04:
00
05:
00
06:
00
07:
00
08:
00
09:
00
10:
00
11:
00
12:
00
13:
00
14:
00
15:
00
16:
00
17:
00
18:
00
19:
00
20:
00
21:
00
22:
00
23:
00
00:
00
load
in p
u
time of day
Additional AC Load
Exchange with
adapted load
SCENARIO 3: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
11
Nearly sinusoidal characteristic on aggregating household AC demand
A/C electricity demand of individual houses and their average in a low-income area with hot climate in Florida 1996. Source: Florida Solar Energy Center
• Load:
• Additional AC load is added to every household
• PV:
• Connected at every household starting at half of the line
• Aggregated PV generation is proportional to DT’s rating, but individual size doubles
URBAN FEEDER SCENARIO 4: PV WITH HIGHER PV PENETRATION AT THE END OF FEEDER WITH ADAPTED LOAD
12
Load
Load
Load PV
Load PV
11 kV
400 V
PV at end of LV feeder
Load
Load
Load PV
Load PV
Larger individual
size
Exchange with
adapted load
• Load:
• Measurement at DT is available
• Divvied up based on loading information of feeders
• Equally distributed along the feeder every ca. 25m
• PV:
• Connected at every household starting at half of the line
• Aggregated PV generation is proportional to DT’s rating, but individual size doubles
• Network:
• Cable cross section gets reduced from 300 mm² to 150 mm²
URBAN FEEDER SCENARIO 5: PV WITH CABLES CONVERTED TO CABLES WITH LOWER CROSS-SECTION
13
Load
Load
Load PV
Load PV
11 kV
400 V
PV at end of LV feeder
Load
Load
Load PV
Load PV
Larger individual
size
Lower cable cross section
Lower cable cross section
Two feeders are included: Feeder 1 and
Feeder 2
• Load:
• Measurements known at some DT‘s, unknown data was taken from similar DT‘s
• PV:
• At 11 kV, aggregated PV Generation is proportional to DT’s rating and connected at every DT
RURAL FEEDER SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD
14
Penetration Level PV(inverter) rating
30 % 30 kW
50 % 50 kW
75 % 75 kW
100 % 100 kW
150 % 150 kW
Load PV
Load PV
Load PV
Load PV
66 kV
11kV Feeder 1
Load PV
Load PV
Load PV
Load PV
11kV
66 kV
Feeder 2
Additional AC load is added with the assumption that there would be a 25% energy consumption (kWh) increase in the load (5% per year for 5 years, 2016 to 2022), typically with regard to Air-Conditioning, where a high evening peak is considered
RURAL FEEDER SCENARIO 2: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
15
Load PV
Load PV
Load PV
Load PV
66 kV
11kV Feeder 1
Load PV
Load PV
Load PV
Load PV
11kV Feeder 2
66 kV
0
0.2
0.4
0.6
0.8
1
01:
00
02:
00
03:
00
04:
00
05:
00
06:
00
07:
00
08:
00
09:
00
10:
00
11:
00
12:
00
13:
00
14:
00
15:
00
16:
00
17:
00
18:
00
19:
00
20:
00
21:
00
22:
00
23:
00
00:
00
load
in p
u
time of day
Additional AC Load
Two feeders are included: Feeder 2 and
Feeder 1
• Load:
• Measurements known at some DT‘s, unknown data was taken from similar DT‘s
• PV:
• At 11 kV, aggregated PV Generation is proportional to DT’s rating and connected at every DT
• 3.5 MW PV power plant gets connected to Feeder 2 (worst case)
RURAL FEEDER SCENARIO 3: PV ON ALL FEEDERS WITH A PV POWER PLANT CONNECTED
16
Load PV
Load PV
Load PV
Load PV
66 kV
11kV Feeder 2
PV power plant
Switch on
Two feeders are included: Feeder 1 and
Feeder 2
• Load:
• Measurements known at some DT‘s, unknown data was taken from similar DT‘s
• PV:
• At 11 kV, aggregated PV Generation is proportional to DT’s rating and connected at every DT
• 3.5 MW PV power plant not connected
• Network:
• Standard cables with cross-section close to the existing over-head-lines was chosen
RURAL FEEDER SCENARIO 4: PV WITH OVER-HEAD-LINES CONVERTED TO CABLES WITH SIMILAR CROSS-SECTION
17
Load PV
Load PV
Load PV
Load PV
66 kV
11kV Feeder 2
Use cables instead of OHL
PV power plant
Switched off
18
INTRODUCTION TO THE BHOPAL GRID
Two networks from Bhopal were investigated
• An Urban Feeder
• A Rural Feeder
Urban Feeder Characteristics:
• 11 Distribution Transformers
• Mostly of 200 kVA size
• Sum of all Distribution Transformer Ratings: 2.2 MVA
• Length of line (Longest line)
• 33 kV : 700 meters – from 132 kV Ss to 33 kV Ss
• 11 kV : 2.4 km – from 33 kV Ss to furthest DT
Rural Feeder Characteristics:
• 33 Distribution Transformers
• Mostly of 100 kVA size
• Sum of all Distribution Transformer Ratings:
3.7 MVA
• Length of Lines (Longest line)
• 33 kV : 10 km – from 132 kV Ss to 33 kV Ss
• 11 kV : 4.5 km – from 33 kV Ss to furthest DT
FEEDERS INVESTIGATED
19
GRID STRUCTURE – URBAN FEEDER
20
Upstream (33 kV Network)
Urban Feeder (11 kV Network)
33/11 kV Ss
GRID STRUCTURE – RURAL FEEDER
21
Upstream (33 kV Network) Rural Feeder (11
kV Network)
33/11 kV Ss
22
BHOPAL: SCENARIOS
SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG FEEDER WITH NORMAL LOAD
23
• At 33 kV, aggregated PV Generation is proportional to power transformer rating
• Example: PT rating = 5 MVA
• At 11 kV, aggregated PV Generation is proportional to DT’s rating
• Example: DT rating = 100 kVA
Load PV
Load PV
Load PV
Load PV
11 kV
33 kV
132 kV
33 kV
Load PV
Load PV
Penetration Level PV(inverter) rating
30 % 1.5 MW
50 % 2.5 MW
75 % 3.75 MW
100 % 5 MW
150 % 7.5 MW
Penetration Level PV(inverter) rating
30 % 30 kW
50 % 50 kW
75 % 75 kW
100 % 100 kW
150 % 150 kW
SCENARIO 2: PV EQUALLY DISTRIBUTED ALONG FEEDER WITH AC ADAPTED LOAD
24
Load PV
Load PV
Load PV
Load PV
11 kV
33 kV
132 kV
33 kV
Load PV
Load PV
Exchange with adapted load
Exchange with adapted load
• Additional Load is added with the assumption that there would be a 25% energy consumption (kWh) increase in the load (5% per year for 5 years, 2016 to 2022), typically with regard to Air-Conditioning, where a high evening peak is considered
0
0.2
0.4
0.6
0.8
1
01:
00
02:
00
03:
00
04:
00
05:
00
06:
00
07:
00
08:
00
09:
00
10:
00
11:
00
12:
00
13:
00
14:
00
15:
00
16:
00
17:
00
18:
00
19:
00
20:
00
21:
00
22:
00
23:
00
00:
00
load
in p
u
time of day
Additional AC Load
SCENARIO 3 (URBAN): PV IN-FEED HIGHER AT THE END OF THE FEEDER
25
• Only PV Generators are moved to the end of MV Feeder, NOT the loads
• The total rated PV in-feed remains the same i.e.
• In the Urban Feeder, sum of all Distribution Transformer Ratings is 2.2 MVA, total PV in-feed rating remains the same
• In the Rural Feeder, sum of all Distribution Transformer Ratings is 3.7 MVA, total PV in-feed rating remains the same
• The equivalent 33 kV network remains the same
Load
Load
Load PV
Load PV
11 kV
33 kV
132 kV
33 kV
Load PV
Load PV
Moved to the end of the feeder
Larger installed individual capacity
Installed sum stays the same
SCENARIO 3 (RURAL): PV EQUALLY DISTRIBUTED ALONG FEEDER WITH AN ADDITIONAL PV PLANT
26
• PV plant of 2.5 MWp rating is added to either:
• Start of Feeder
• Middle of Feeder
• End of Feeder
Load PV
Load PV
Load PV
Load PV
11 kV
33 kV
132 kV
33 kV
Load PV
Load PV
2.5 MW PV
SCENARIO 4 (RURAL) AND 5 (URBAN): NETWORK FULLY CABLED OR CABLED WITH LOWER CROSS-SECTION
27
• Both the 33 kV and the 11 kV network are fully cabled
• Cable diameters were chosen to be similar to the existing diameter
• In the case of the Urban feeder, the cable diameters were chosen to be the smallest available diameters available in the IEC standard cable models in DIgSILENT PowerFactory
• In the case of the Rural Feeder, standard cables with cross-section as close to the existing over-head-lines was chosen Load PV
Load PV
Load PV
Load PV
11 kV
33 kV
132 kV
33 kV
Load PV
Load PV
Fully cabled / lower cross-section
Fully cabled / lower cross-section
28
SOLUTIONS FOR ENHANCING THE HOSTING CAPACITY
SOLUTION 1: ON LOAD TAP CHANGER WITH AUTOMATIC VOLTAGE REGULATION AT MV LEVEL
29
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
Load PV
Load PV
Load PV
Load PV
OLTC
11 kV
33 kV 33 kV to 11 kV Transformers are controlled with discrete on load tap changers which control voltage at LT side between 1.02 and 0.98 pu
SOLUTION 2: WIDE AREA CONTROL
Load PV
Load PV
Load PV
Load PV
66/33 kV to 11 kV Transformer is controlled with discrete on load tap changers which control voltage at a specific node of the feeder. The node can be at 11 kV or 400 V level
OLTC
30
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 3: SHUNT COMPENSATORS FOR VOLTAGE CONTROL
31
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
Load PV
Load PV
Load PV
Load PV
11 kV
33 kV
Shunts are voltage controlled to maintain 1.0 p.u. Voltage.
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 4: FIXED POWER FACTOR
Load PV
Load PV
Load PV
Load PV
PV Units generate reactive power based on constant power factor
32
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 5: ACTIVE VOLTAGE CONTROL BY PV INVERTERS (Q(U) CHARACTERISTIC)
Load PV
Load PV
Load PV
Load PV
PV Units generate reactive power based on voltage, to reduce voltage rise
33
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 6: ON-LOAD TAP CHANGING DT
Load PV
Load PV
Load PV
Load PV
11 kV to 400 V Transformer is controlled with discrete on load tap changers which control voltage at a specific node of one of the 400 V feeders
OLTC
34
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 7: PV CAP AT CERTAIN PERCENTAGE OF INSTALLED PANEL CAPACITY
Load PV
Load PV
Load PV
Load PV
PV Units cap active power generation
35
SOLUTION 7: PV CAP AT CERTAIN PERCENTAGE OF INSTALLED PANEL CAPACITY
Load PV
Load PV
Load PV
Load PV
PV Units cap active power generation
36
base
cap pv
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 8: GRID REINFORCEMENT
Load PV
Load PV
Load PV
Load PV
Build new lines, reinforce existing ones and increase transformer size to compensate overloading and voltage problems
37
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 9: PV STORAGE BATTERY DEPLOYMENT – OWN CONSUMPTION
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
38
PV Battery optimized for own consumption gets added to every PV system
SOLUTION 9: PV STORAGE BATTERY DEPLOYMENT – OWN CONSUMPTION
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
39
PV Battery optimized for own consumption gets added to every PV system
base
owncon
Storage charging
Storage discharging
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 10: PV STORAGE BATTERY DEPLOYMENT - PEAK SHAVING
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
40
Battery optimized for peak shaving gets added to every PV system
SOLUTION 10: PV STORAGE BATTERY DEPLOYMENT – PEAK SHAVING
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
Load PV &
Battery
41
PV Battery optimized for peak shaving gets added to every PV system
peakshave
Storage charging
Storage discharging
base
Measure Abbreviation
No Solution/ Base case base
OLTC with automatic voltage
regulation at MV level mvoltc
Wide area control wide area control
Shunt compensators for voltage
control shuntvcontrol
PV inverters with fixed non-unity
power factor fixed PF
Active voltage control by PV
inverters (Q(U) characteristic) qvchar
On-load tap changing DT oltc
PV cap at certain percentage of
installed panel capacity cap pv
Reinforcements of lines, cables
transformers grid
reinforcement
PV storage battery deployment -
own consumption storage
ownConsumption
PV storage battery deployment -
peak shaving storage
peakShaving
Demand side management dsm
SOLUTION 11: DEMAND SIDE MANAGEMENT
Load PV
Load PV
Load PV
Load PV
42
AC loads shifted to mid-day peak
SOLUTION 11: DEMAND SIDE MANAGEMENT
Load PV
Load PV
Load PV
Load PV
43
AC loads shifted to mid-day peak
44
THANK YOU FOR YOUR ATTENTION!