Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand...

44
Project: Analysis of Indian distribution systems for the integration of high shares of rooftop PV INTEGRATION OF RENEWABLE ENERGIES IN THE INDIAN ELECTRICITY SYSTEM (I-RE) Final Workshop, 29 August 2017 Dr. Thomas Ackermann Dr.-Ing. Eckehard Tröster Grid Integration Study Methodology, Scenarios & Assumptions Day 1, 10:45, 45 mins

Transcript of Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand...

Page 1: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Project: Analysis of Indian distribution systems for the integration of high shares of rooftop PV

INTEGRATION OF RENEWABLE ENERGIES IN THE INDIAN ELECTRICITY SYSTEM (I-RE)

Final Workshop, 29 August 2017

Dr. Thomas Ackermann

Dr.-Ing. Eckehard Tröster

Grid Integration Study Methodology, Scenarios & Assumptions

Day 1, 10:45, 45 mins

Page 2: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Delhi Grid

• Introduction

• Scenarios investigated

Bhopal Grid

• Introduction

• Scenarios investigated

Solutions for enhancing the hosting capacity

CONTENT

2

Page 3: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

3

INTRODUCTION TO THE DELHI GRID

Page 4: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Urban Feeder Characteristics:

• LV Network modelled with 2-5 400 V feeders per Distribution Transformer

• Min. length: 36 m

• Max. length: 719 m

• 8 Distribution Transformers (5.4 MVA total)

• Mostly of 630 kVA size

Rural Feeder Characteristics:

• Two 11kV feeders

• Feeder 1 length: 12.26 km

• Feeder 2 length: 12.3 km

• 40 Distribution Transformers in Feeder 1 (5.2 MVA total)

• Mostly of 100 kVA size

• 28 Distribution Transformers in Feeder 2 (4.6 MVA total)

• Mostly of 100 kVA size

FEEDERS INVESTIGATED

4

Two networks from Delhi were investigated

• Urban Feeder

• Rural Feeder

Page 5: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

GRID STRUCTURE – URBAN FEEDER

5

033kV_Vasant..

011kV_Vasant..

External Grid

T01

_T

310

32

T01

_T

310

32

_2

0M

VA

_3

3/1

1kV

33/11kV Urban Feeder grid substation

11kV network Urban Feeder

400V Example networks

Page 6: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

GRID STRUCTURE – RURAL FEEDER

6

Feeder 2

Feeder 1

PV Connection

towards Rawta

PV Connection

towards JhulJhuli

~

3.5 MW PV plant

66/11 kV substation Rural Feeder

66/11 kV substation Rural Feeder

Page 7: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

7

DELHI: SCENARIOS

Page 8: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

• Load:

• Measurement at DT is available

• Divvied up based on loading information of feeders

• Equally distributed along the feeder every ca. 25m

• PV:

• Connected at every household

• Aggregated PV generation is proportional to DT’s rating

Example: 100 kVA DT

URBAN FEEDER SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD

8

Load PV

Load PV

Load PV

Load PV

11 kV

400 V

PV equal distribution

Load PV

Load PV

Load PV

Load PV

Penetration Level PV(inverter) rating

30 % 30 kW

50 % 50 kW

75 % 75 kW

100 % 100 kW

150 % 150 kW

Page 9: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

• Load:

• Measurement at DT is available

• Divvied up based on loading information of feeders

• Equally distributed along the feeder every ca. 25m

• PV:

• Connected at every household starting at half of the line

• Aggregated PV generation is proportional to DT’s rating, but individual size doubles

URBAN FEEDER SCENARIO 2: PV WITH HIGHER PV PENETRATION AT THE END OF FEEDER WITH NORMAL LOAD

9

Load

Load

Load PV

Load PV

11 kV

400 V

PV at end of LV feeder

Load

Load

Load PV

Load PV

Larger individual

size

Page 10: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

• Load:

• Additional AC load is added to every household

URBAN FEEDER SCENARIO 3: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD

10

Load PV

Load PV

Load PV

Load PV

11 kV

400 V

PV equal distribution

Load PV

Load PV

Load PV

Load PV

0

0.2

0.4

0.6

0.8

1

01:

00

02:

00

03:

00

04:

00

05:

00

06:

00

07:

00

08:

00

09:

00

10:

00

11:

00

12:

00

13:

00

14:

00

15:

00

16:

00

17:

00

18:

00

19:

00

20:

00

21:

00

22:

00

23:

00

00:

00

load

in p

u

time of day

Additional AC Load

Exchange with

adapted load

Page 11: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SCENARIO 3: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD

11

Nearly sinusoidal characteristic on aggregating household AC demand

A/C electricity demand of individual houses and their average in a low-income area with hot climate in Florida 1996. Source: Florida Solar Energy Center

Page 12: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

• Load:

• Additional AC load is added to every household

• PV:

• Connected at every household starting at half of the line

• Aggregated PV generation is proportional to DT’s rating, but individual size doubles

URBAN FEEDER SCENARIO 4: PV WITH HIGHER PV PENETRATION AT THE END OF FEEDER WITH ADAPTED LOAD

12

Load

Load

Load PV

Load PV

11 kV

400 V

PV at end of LV feeder

Load

Load

Load PV

Load PV

Larger individual

size

Exchange with

adapted load

Page 13: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

• Load:

• Measurement at DT is available

• Divvied up based on loading information of feeders

• Equally distributed along the feeder every ca. 25m

• PV:

• Connected at every household starting at half of the line

• Aggregated PV generation is proportional to DT’s rating, but individual size doubles

• Network:

• Cable cross section gets reduced from 300 mm² to 150 mm²

URBAN FEEDER SCENARIO 5: PV WITH CABLES CONVERTED TO CABLES WITH LOWER CROSS-SECTION

13

Load

Load

Load PV

Load PV

11 kV

400 V

PV at end of LV feeder

Load

Load

Load PV

Load PV

Larger individual

size

Lower cable cross section

Lower cable cross section

Page 14: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Two feeders are included: Feeder 1 and

Feeder 2

• Load:

• Measurements known at some DT‘s, unknown data was taken from similar DT‘s

• PV:

• At 11 kV, aggregated PV Generation is proportional to DT’s rating and connected at every DT

RURAL FEEDER SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD

14

Penetration Level PV(inverter) rating

30 % 30 kW

50 % 50 kW

75 % 75 kW

100 % 100 kW

150 % 150 kW

Load PV

Load PV

Load PV

Load PV

66 kV

11kV Feeder 1

Load PV

Load PV

Load PV

Load PV

11kV

66 kV

Feeder 2

Page 15: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Additional AC load is added with the assumption that there would be a 25% energy consumption (kWh) increase in the load (5% per year for 5 years, 2016 to 2022), typically with regard to Air-Conditioning, where a high evening peak is considered

RURAL FEEDER SCENARIO 2: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD

15

Load PV

Load PV

Load PV

Load PV

66 kV

11kV Feeder 1

Load PV

Load PV

Load PV

Load PV

11kV Feeder 2

66 kV

0

0.2

0.4

0.6

0.8

1

01:

00

02:

00

03:

00

04:

00

05:

00

06:

00

07:

00

08:

00

09:

00

10:

00

11:

00

12:

00

13:

00

14:

00

15:

00

16:

00

17:

00

18:

00

19:

00

20:

00

21:

00

22:

00

23:

00

00:

00

load

in p

u

time of day

Additional AC Load

Page 16: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Two feeders are included: Feeder 2 and

Feeder 1

• Load:

• Measurements known at some DT‘s, unknown data was taken from similar DT‘s

• PV:

• At 11 kV, aggregated PV Generation is proportional to DT’s rating and connected at every DT

• 3.5 MW PV power plant gets connected to Feeder 2 (worst case)

RURAL FEEDER SCENARIO 3: PV ON ALL FEEDERS WITH A PV POWER PLANT CONNECTED

16

Load PV

Load PV

Load PV

Load PV

66 kV

11kV Feeder 2

PV power plant

Switch on

Page 17: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Two feeders are included: Feeder 1 and

Feeder 2

• Load:

• Measurements known at some DT‘s, unknown data was taken from similar DT‘s

• PV:

• At 11 kV, aggregated PV Generation is proportional to DT’s rating and connected at every DT

• 3.5 MW PV power plant not connected

• Network:

• Standard cables with cross-section close to the existing over-head-lines was chosen

RURAL FEEDER SCENARIO 4: PV WITH OVER-HEAD-LINES CONVERTED TO CABLES WITH SIMILAR CROSS-SECTION

17

Load PV

Load PV

Load PV

Load PV

66 kV

11kV Feeder 2

Use cables instead of OHL

PV power plant

Switched off

Page 18: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

18

INTRODUCTION TO THE BHOPAL GRID

Page 19: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Two networks from Bhopal were investigated

• An Urban Feeder

• A Rural Feeder

Urban Feeder Characteristics:

• 11 Distribution Transformers

• Mostly of 200 kVA size

• Sum of all Distribution Transformer Ratings: 2.2 MVA

• Length of line (Longest line)

• 33 kV : 700 meters – from 132 kV Ss to 33 kV Ss

• 11 kV : 2.4 km – from 33 kV Ss to furthest DT

Rural Feeder Characteristics:

• 33 Distribution Transformers

• Mostly of 100 kVA size

• Sum of all Distribution Transformer Ratings:

3.7 MVA

• Length of Lines (Longest line)

• 33 kV : 10 km – from 132 kV Ss to 33 kV Ss

• 11 kV : 4.5 km – from 33 kV Ss to furthest DT

FEEDERS INVESTIGATED

19

Page 20: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

GRID STRUCTURE – URBAN FEEDER

20

Upstream (33 kV Network)

Urban Feeder (11 kV Network)

33/11 kV Ss

Page 21: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

GRID STRUCTURE – RURAL FEEDER

21

Upstream (33 kV Network) Rural Feeder (11

kV Network)

33/11 kV Ss

Page 22: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

22

BHOPAL: SCENARIOS

Page 23: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG FEEDER WITH NORMAL LOAD

23

• At 33 kV, aggregated PV Generation is proportional to power transformer rating

• Example: PT rating = 5 MVA

• At 11 kV, aggregated PV Generation is proportional to DT’s rating

• Example: DT rating = 100 kVA

Load PV

Load PV

Load PV

Load PV

11 kV

33 kV

132 kV

33 kV

Load PV

Load PV

Penetration Level PV(inverter) rating

30 % 1.5 MW

50 % 2.5 MW

75 % 3.75 MW

100 % 5 MW

150 % 7.5 MW

Penetration Level PV(inverter) rating

30 % 30 kW

50 % 50 kW

75 % 75 kW

100 % 100 kW

150 % 150 kW

Page 24: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SCENARIO 2: PV EQUALLY DISTRIBUTED ALONG FEEDER WITH AC ADAPTED LOAD

24

Load PV

Load PV

Load PV

Load PV

11 kV

33 kV

132 kV

33 kV

Load PV

Load PV

Exchange with adapted load

Exchange with adapted load

• Additional Load is added with the assumption that there would be a 25% energy consumption (kWh) increase in the load (5% per year for 5 years, 2016 to 2022), typically with regard to Air-Conditioning, where a high evening peak is considered

0

0.2

0.4

0.6

0.8

1

01:

00

02:

00

03:

00

04:

00

05:

00

06:

00

07:

00

08:

00

09:

00

10:

00

11:

00

12:

00

13:

00

14:

00

15:

00

16:

00

17:

00

18:

00

19:

00

20:

00

21:

00

22:

00

23:

00

00:

00

load

in p

u

time of day

Additional AC Load

Page 25: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SCENARIO 3 (URBAN): PV IN-FEED HIGHER AT THE END OF THE FEEDER

25

• Only PV Generators are moved to the end of MV Feeder, NOT the loads

• The total rated PV in-feed remains the same i.e.

• In the Urban Feeder, sum of all Distribution Transformer Ratings is 2.2 MVA, total PV in-feed rating remains the same

• In the Rural Feeder, sum of all Distribution Transformer Ratings is 3.7 MVA, total PV in-feed rating remains the same

• The equivalent 33 kV network remains the same

Load

Load

Load PV

Load PV

11 kV

33 kV

132 kV

33 kV

Load PV

Load PV

Moved to the end of the feeder

Larger installed individual capacity

Installed sum stays the same

Page 26: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SCENARIO 3 (RURAL): PV EQUALLY DISTRIBUTED ALONG FEEDER WITH AN ADDITIONAL PV PLANT

26

• PV plant of 2.5 MWp rating is added to either:

• Start of Feeder

• Middle of Feeder

• End of Feeder

Load PV

Load PV

Load PV

Load PV

11 kV

33 kV

132 kV

33 kV

Load PV

Load PV

2.5 MW PV

Page 27: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SCENARIO 4 (RURAL) AND 5 (URBAN): NETWORK FULLY CABLED OR CABLED WITH LOWER CROSS-SECTION

27

• Both the 33 kV and the 11 kV network are fully cabled

• Cable diameters were chosen to be similar to the existing diameter

• In the case of the Urban feeder, the cable diameters were chosen to be the smallest available diameters available in the IEC standard cable models in DIgSILENT PowerFactory

• In the case of the Rural Feeder, standard cables with cross-section as close to the existing over-head-lines was chosen Load PV

Load PV

Load PV

Load PV

11 kV

33 kV

132 kV

33 kV

Load PV

Load PV

Fully cabled / lower cross-section

Fully cabled / lower cross-section

Page 28: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

28

SOLUTIONS FOR ENHANCING THE HOSTING CAPACITY

Page 29: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 1: ON LOAD TAP CHANGER WITH AUTOMATIC VOLTAGE REGULATION AT MV LEVEL

29

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

Load PV

Load PV

Load PV

Load PV

OLTC

11 kV

33 kV 33 kV to 11 kV Transformers are controlled with discrete on load tap changers which control voltage at LT side between 1.02 and 0.98 pu

Page 30: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 2: WIDE AREA CONTROL

Load PV

Load PV

Load PV

Load PV

66/33 kV to 11 kV Transformer is controlled with discrete on load tap changers which control voltage at a specific node of the feeder. The node can be at 11 kV or 400 V level

OLTC

30

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

Page 31: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 3: SHUNT COMPENSATORS FOR VOLTAGE CONTROL

31

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

Load PV

Load PV

Load PV

Load PV

11 kV

33 kV

Shunts are voltage controlled to maintain 1.0 p.u. Voltage.

Page 32: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 4: FIXED POWER FACTOR

Load PV

Load PV

Load PV

Load PV

PV Units generate reactive power based on constant power factor

32

Page 33: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 5: ACTIVE VOLTAGE CONTROL BY PV INVERTERS (Q(U) CHARACTERISTIC)

Load PV

Load PV

Load PV

Load PV

PV Units generate reactive power based on voltage, to reduce voltage rise

33

Page 34: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 6: ON-LOAD TAP CHANGING DT

Load PV

Load PV

Load PV

Load PV

11 kV to 400 V Transformer is controlled with discrete on load tap changers which control voltage at a specific node of one of the 400 V feeders

OLTC

34

Page 35: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 7: PV CAP AT CERTAIN PERCENTAGE OF INSTALLED PANEL CAPACITY

Load PV

Load PV

Load PV

Load PV

PV Units cap active power generation

35

Page 36: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 7: PV CAP AT CERTAIN PERCENTAGE OF INSTALLED PANEL CAPACITY

Load PV

Load PV

Load PV

Load PV

PV Units cap active power generation

36

base

cap pv

Page 37: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 8: GRID REINFORCEMENT

Load PV

Load PV

Load PV

Load PV

Build new lines, reinforce existing ones and increase transformer size to compensate overloading and voltage problems

37

Page 38: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 9: PV STORAGE BATTERY DEPLOYMENT – OWN CONSUMPTION

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

38

PV Battery optimized for own consumption gets added to every PV system

Page 39: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 9: PV STORAGE BATTERY DEPLOYMENT – OWN CONSUMPTION

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

39

PV Battery optimized for own consumption gets added to every PV system

base

owncon

Storage charging

Storage discharging

Page 40: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 10: PV STORAGE BATTERY DEPLOYMENT - PEAK SHAVING

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

40

Battery optimized for peak shaving gets added to every PV system

Page 41: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 10: PV STORAGE BATTERY DEPLOYMENT – PEAK SHAVING

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

Load PV &

Battery

41

PV Battery optimized for peak shaving gets added to every PV system

peakshave

Storage charging

Storage discharging

base

Page 42: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

Measure Abbreviation

No Solution/ Base case base

OLTC with automatic voltage

regulation at MV level mvoltc

Wide area control wide area control

Shunt compensators for voltage

control shuntvcontrol

PV inverters with fixed non-unity

power factor fixed PF

Active voltage control by PV

inverters (Q(U) characteristic) qvchar

On-load tap changing DT oltc

PV cap at certain percentage of

installed panel capacity cap pv

Reinforcements of lines, cables

transformers grid

reinforcement

PV storage battery deployment -

own consumption storage

ownConsumption

PV storage battery deployment -

peak shaving storage

peakShaving

Demand side management dsm

SOLUTION 11: DEMAND SIDE MANAGEMENT

Load PV

Load PV

Load PV

Load PV

42

AC loads shifted to mid-day peak

Page 43: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

SOLUTION 11: DEMAND SIDE MANAGEMENT

Load PV

Load PV

Load PV

Load PV

43

AC loads shifted to mid-day peak

Page 44: Grid Integration Study Methodology, Scenarios & … · models in DIgSILENT PowerFactory ... Demand side management dsm Load PV Load PV Load PV Load PV OLTC 11 kV 33 kV 33 kV to 11

44

THANK YOU FOR YOUR ATTENTION!