Green Telecom & IT Workshop by IISc and Bell labs: Prof. Ashok Jhunjhunwala : Telecom Tower Energy

18
Powering the Remote Rural Base Station Can it make Indian telcos profitable? ashok Jhunjhunwala, IITM [email protected] N. Sriram, IITM 04-04-2012 Green Telecom & IT workshop, Bangalore 1

Transcript of Green Telecom & IT Workshop by IISc and Bell labs: Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Page 1: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Powering the Remote Rural Base Station Rural Base Station Can it make Indian telcos profitable?

ashok Jhunjhunwala, IITM [email protected]

N. Sriram, IITM

04-04-2012

Green Telecom & IT workshop, Bangalore 1

Page 2: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

India’s 15% average power deficit is deceiving

As evident from the fluctuating prices at Power Markets

• Day variation of Rs 2000 to 4500 per MWh

• Prices vary from Rs 2000 to 12000 per MWh in one week

• Huge power shortage during peak hours• rural / remote areas have huge cuts • rural / remote areas have huge cuts

04-04-2012

Green Telecom & IT workshop, Bangalore 2

Page 3: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

04-04-2012

Green Telecom & IT workshop, Bangalore ‹#›

Page 4: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Some statistics from ACME• 1.5 to 3% energy in developed countries consumed by telecom

operators and data centers• Energy consumed by wireless operator doubles every 3 -5 years• Cooling infrastructure consumes > 50%

• DG operation average 6 hours per day• India grid availability varies between states

1 unit BTS consumption: 1.5 units consumed by AC, SMPS loss, PIU loss, battery leakage• India grid availability varies between states

• Battery maintenance neglected• 15% batteries are non-functional

• 1800 MHz TRX consume more power

• Passive site equipment dominates CAPEX• $25K for active (electronics) and $62.5K for passive• Tower, shelter, Power system, Battery (VLRA),

AC unit, Earthing

04-04-2012

Green Telecom & IT workshop, Bangalore

by AC, SMPS loss, PIU loss, battery leakage

4

Page 5: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

• Batteries are expensive proposition for back-up• Lead acid battery: 1500 cycles if operated between 60 to 100% capacity

• 1 kWh back-up will cost Rs 14/ kWh assuming single charge / discharge per day

• Assuming Rs 6000 per kWh battery and 10% interest rate

• LiFePo battery: 5000 cycles if operated between 10% to 90% capacity• 1 kWh back-up will cost Rs 16 per kWh assuming single charge per day

Energy Storage

• 1 kWh back-up will cost Rs 16 per kWh assuming single charge per day• Assuming Rs 25000 per kWh battery and 10% interest

Battery cost (per kWh) Rs. 6,000.00 Battery cost (to deliver 1kWh) Rs. 15,000.00discharge 40% depreciation (years) 4.11Number of cycles 1500 Storage cost per unit -Rs. 14.09interest rate 10%cycles used per day 1Losses 10%

Lead acid battery

04-04-2012

Green Telecom & IT workshop, Bangalore 5

Page 6: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Diesel generator

• Diesel generator generates 3 kWh of power per litre of diesel

• But this is true only if generator is working at 80% load• Efficiency drops significantly at lower loads

• Increasing costs of diesel power

• DC diesel generator doesnot have this problem• Fuel consumption is almost

linear with load• For charging battery and driving

BTS, why not use DC generator?• Why convert to ac at all?

04-04-2012

Green Telecom & IT workshop, Bangalore 6

Page 7: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

• India can certainly use solar energy, as capital goods prices fall• Solar photo-voltaic provides DC power for about six hours a day

• Rs 60 per W capital cost: with 10% interest and payback in 20 years, amounts to Rs 7per year (not computing costs of land)

• Total Cost of Ownership gives a little over Rs 4.35 / kWh assuming 10% losses assuming no land cost

• Installation costs may add another 10% to costs

Sun shines brightly over India

Installation costs may add another 10% to costs

• As opposed to Rs 3 to 7 per kWh for grid power

04-04-2012

Green Telecom & IT workshop, Bangalore

Solar PV power price computation

PV cost per kWp 60000 sun-hours per day 6

interest rate % 10% sun-days / year 300

depreciation (yrs) 20 total units gen per year 1800

yearly payment Rs. -7,047.58 Losses 10%

price per unit Rs. 4.35

7

Page 8: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Strategy• What are the sources?

• at what costs and available when?

• What are the Loads?• Can we reduce some loads?

Grid: Rs 5 per unitSolar: Rs 5 per unitBattery back-up: Rs 15 per unitDiesel Generator: Rs 15 per unit

BTSAir-conditionerBattery-cooling• Can we reduce some loads?

• In existing installations• In new installations, for example

• reduction of BS power: 147W -> 130W -> 120 W Diet-BTS• Reducing / eliminating Air-conditioner requirement

• Use of battery chiller

• Will require one to optimize usage of sources to minimize total cost of operation

• OPEX + CAPEX converted into EMI

04-04-2012

Green Telecom & IT workshop, Bangalore

Battery-coolingBattery-charging

8

Page 9: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

IITM Simulator• Designed to compute

• Battery, PV current, Total Loadcurrent as a function of ambienttemperature at different point of time

• When do DG and grid turn on and off?• What happens to battery charging / discharging?

• Assumptions in simulations• Assumptions in simulations• Grid Availability: 4 h• Diesel Generator Sizes: 15 kVA• Load Power factor: 0.8• Diesel Cost per liter: 45 Rs• BTS Load: 0.8kW • BTS Cooling Load: 1.8kW• Battery Cooling Load: 0.5kW• Total Peak Load excluding Battery Charging: 3.1kW at 48V• PV and battery CAPEX built into energy costs as EMI

• DG CAPEX and fuel-pilferage not included

04-04-2012

Green Telecom & IT workshop, Bangalore 9

Page 10: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

15kVA Generator, No PV, NO Battery, 4 hours grid availability

04-04-2012

Green Telecom & IT workshop, Bangalore 10Rs 35 per unit

Page 11: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

600Ah, 48V Lead Acid 600Ah, 48V Lead Acid 600Ah, 48V Lead Acid 600Ah, 48V Lead Acid BatteryBatteryBatteryBattery, 4 Hours grid , 4 Hours grid , 4 Hours grid , 4 Hours grid availability, 15kVA availability, 15kVA availability, 15kVA availability, 15kVA DGDGDGDG

Linear Battery Charging Model

04-04-2012

Green Telecom & IT workshop, Bangalore 11Rs 23 per unit

Page 12: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Non-linear Battery Charging Model

600Ah, 48V Lead Acid 600Ah, 48V Lead Acid 600Ah, 48V Lead Acid 600Ah, 48V Lead Acid BatteryBatteryBatteryBattery, 4 Hours grid , 4 Hours grid , 4 Hours grid , 4 Hours grid availability, 15kVA availability, 15kVA availability, 15kVA availability, 15kVA DGDGDGDG

04-04-2012

Green Telecom & IT workshop, Bangalore 12Rs 23 per unit

Page 13: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

150Ah, 48V Lithium 150Ah, 48V Lithium 150Ah, 48V Lithium 150Ah, 48V Lithium Polymer batteriesPolymer batteriesPolymer batteriesPolymer batteries, 4 Hours , 4 Hours , 4 Hours , 4 Hours grid availability, 15kVA grid availability, 15kVA grid availability, 15kVA grid availability, 15kVA DGDGDGDGLinear Battery Charging Model

04-04-2012

Green Telecom & IT workshop, Bangalore 13Rs 22 per unit

Page 14: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

600Ah, 48V Lead Acid Battery + 5kW PV + 15kVA DG + 4 Hours grid availability

Non-linear Battery Charging Model

04-04-2012

Green Telecom & IT workshop, Bangalore 14Rs 15 per unit

Page 15: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

150Ah, 48V Lithium Polymer 150Ah, 48V Lithium Polymer 150Ah, 48V Lithium Polymer 150Ah, 48V Lithium Polymer battery + battery + battery + battery + 5kW PV 5kW PV 5kW PV 5kW PV +4 Hours +4 Hours +4 Hours +4 Hours grid availability+15kVa grid availability+15kVa grid availability+15kVa grid availability+15kVa DGDGDGDGLinear Battery Charging Model

04-04-2012

Green Telecom & IT workshop, Bangalore 15Rs 14 per unit

Page 16: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

Simulation Conclusions

• Use of proper battery reduces daily energy OPEX by one-thirdby one-third

• Use of PV panel further reduces daily energy OPEX by one third

04-04-2012

Green Telecom & IT workshop, Bangalore 16

Page 17: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

But one can optimize much more 700Ah, 48V Lead Acid Battery + 7kW PV + 15kVA DG + 4 Hours grid availability

Non-linear Battery Charging Model

04-04-2012

Green Telecom & IT workshop, Bangalore Rs 10 per unit

Page 18: Green Telecom & IT Workshop by IISc and Bell labs:  Prof. Ashok Jhunjhunwala : Telecom Tower Energy

How does one go forward?• For new sites

• Reduce power consumption in BS and associated electronics• Eliminate air-conditioner (make systems workable at 500c ambient)• Place Battery in chiller• Use dc diesel generator of right sizing -- critical

• But more important (for existing and new sites)• But more important (for existing and new sites)• Add solar panels

• Revitalize batteries – choose Lead Acid or Lithium Polymer• Balance current load and power-sources

• Optimize when to use what based on simulations• Have powerful remote management

• With the aim of using diesel generator only as an exception

• Key is to reduce total cost of operation of towers• Taking CAPEX / OPEX• Much can be done today

04-04-2012

Green Telecom & IT workshop, Bangalore 18