Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom:...
Transcript of Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom:...
1
Granite Hills CCC Project Update
Meeting 5 – May 22, 2018
2
1. Project Update
2. Outstanding Community
Items
3. Approximate Critical
Works Schedule
4. Impacts Discussion
5. Wind Farm Design Basics
6. Going Forward
Project Update – Items for Discussion
3
1. Granite Hills Project Update
Project Management Change
Community Status –> Overhaul of Community
Engagement
Permitting and Technical –
EIS Progress and SMEC Introduction – Sophie Olsen
Commonwealth Referral Submitted
Constraints – Telecommunications, Water etc. ongoing.
Project Documentation Update
4
2. Outstanding Community Items
Stakeholder Management Plan –
Working internally and externally to move this forward
to provide to community.
Critical Works Plan –
Schedule to be presented, discussion to follow
surrounding expectations;
Community Projects/Requests–
5
3. Approximate Critical Works Plan
The following table defines the approximate dates for critical project works for Granite Hills:
NOTE: Dates provided are estimates according to best current estimate and may be subject to change depending on project conditions.
Activity Expected Date
Submission of Comm. Referral May 2018 - Done
Finalisation of EIS Studies Q4 2018
Submission of EIS Q4 2018/Q1 2019
Period for Public Comment (60 Days) Q1 2019
EIS Approval Q3 2019
Financial Close Q4 2019/Q1 2020
Start Construction (18-24 Months) Q1 2020
Commercial Operation Date (COD) Q1 2022
6
6
4. Brainstrom: Impacts Discussion -
What are your concerns?
7
7
5. Wind Farm
Design Basics
8
8
6. A Better Way
Forward…
9
9
Questions???