Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom:...

9
1 Granite Hills CCC Project Update Meeting 5 – May 22, 2018

Transcript of Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom:...

Page 1: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

1

Granite Hills CCC Project Update

Meeting 5 – May 22, 2018

Page 2: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

2

1. Project Update

2. Outstanding Community

Items

3. Approximate Critical

Works Schedule

4. Impacts Discussion

5. Wind Farm Design Basics

6. Going Forward

Project Update – Items for Discussion

Page 3: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

3

1. Granite Hills Project Update

Project Management Change

Community Status –> Overhaul of Community

Engagement

Permitting and Technical –

EIS Progress and SMEC Introduction – Sophie Olsen

Commonwealth Referral Submitted

Constraints – Telecommunications, Water etc. ongoing.

Project Documentation Update

Page 4: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

4

2. Outstanding Community Items

Stakeholder Management Plan –

Working internally and externally to move this forward

to provide to community.

Critical Works Plan –

Schedule to be presented, discussion to follow

surrounding expectations;

Community Projects/Requests–

Page 5: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

5

3. Approximate Critical Works Plan

The following table defines the approximate dates for critical project works for Granite Hills:

NOTE: Dates provided are estimates according to best current estimate and may be subject to change depending on project conditions.

Activity Expected Date

Submission of Comm. Referral May 2018 - Done

Finalisation of EIS Studies Q4 2018

Submission of EIS Q4 2018/Q1 2019

Period for Public Comment (60 Days) Q1 2019

EIS Approval Q3 2019

Financial Close Q4 2019/Q1 2020

Start Construction (18-24 Months) Q1 2020

Commercial Operation Date (COD) Q1 2022

Page 6: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

6

6

4. Brainstrom: Impacts Discussion -

What are your concerns?

Page 7: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

7

7

5. Wind Farm

Design Basics

Page 8: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

8

8

6. A Better Way

Forward…

Page 9: Granite Hills CCC Project Updategranitehillswindfarm.com/wordpress/wp-content/... · Brainstrom: Impacts Discussion - What are your concerns? 7 7 5. Wind Farm Design Basics. 8 8 6.

9

9

Questions???