gpcb.gujarat.gov.in · Shree Digvijay Cement Company Ltd. 161 Prepared by J.M EnviroNet Pvt. Ltd....
Transcript of gpcb.gujarat.gov.in · Shree Digvijay Cement Company Ltd. 161 Prepared by J.M EnviroNet Pvt. Ltd....
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 160 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER–IV
ANTICIPATED ENVIRONMENTAL IMPACTS
AND MITIGATION MEASURES
4.1 INTRODUCTION
The environmental parameters likely to be affected by mining are related to many factors, i.e.
physical, social, economic, agriculture and aesthetic. Opencast mining involves drilling,
blasting, excavation, loading, transportation, unloading etc. After mining, limestone will be
transported to the Cement plant of the company by hired trucks/ dumpers.
All the operations can disturb environment of the a/rea in various ways such as removal of
mass, change of landscape, displacement of human settlement, impact on flora and fauna of
the area and on surface drainage and change in air, water and soil quality. While for purpose
of development and economic upliftment of people, there is need for establishment of
industries and mining, but these have to be environmental friendly. Therefore, it is essential
to assess the impact of mining on different environmental parameters, before starting the
mining operations, so that abatement measures could be planned in advance for minimizing
the impacts wherever feasible.
The likely impacts on different environmental parameters due to this mining project are
discussed below:
4.2 ENVIRONMENTAL IMPACT ASSESSMENT & MITIGATION MEASURES
The mining activities may disturb environment in various ways such as degradation of land,
dust generation, deterioration of water and soil quality, affecting the biological and socio-
economic environment of the area. The impacts of mining on various environmental
parameters were assessed and are given below:
4.2.1 IMPACT ON AIR QUALITY AND MITIGATION MEASURES
The mining project includes various mining operations involving development of benches,
approach roads, excavation and transportation of mineral. These operations generally result
in generation of dust and thereby pose health hazards. The drilling and Blasting shall be
eliminated by use of Ripper – Dozer / Surface Miner for excavation of Limestone from
Pachhtardi Limestone Mining Project., thereby fugitive dust emission during drilling and Sox
& NOx generation due to Blasting operations are totally curbed by adoption of Eco-Friendly
Mining Techniques.
However, adequate control measures will be provided at every stage of operation such as
water sprinkling on haul roads to reduce fugitive dust emissions caused due to transport and
loading operations.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 161 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.1.1 AIR POLLUTION DUE TO LIMESTONE MINING PROJECT
(i) Gaseous Pollution
The gaseous pollutants (SO2 & NO2) are anticipated by HEMM like, excavator, dumpers,
dozer and other transport vehicles.
(ii) Particulate Matter
The generation of dust is anticipated from various mining activities like excavation,
loading and transportation, and other mining related activities. The ambient air quality
monitored during Winter Season (December, 2017 to February, 2018) shows that the PM
concentration in the surrounding villages is well within the prescribed limits.
4.2.1.2 AMBIENT AIR QUALITY IMPACT PREDICTION MODELING
Impact Prediction is an important part of Environmental Impact Assessment Study. There are
various techniques available to predict the impacts. Mathematical modeling is an established
and accepted technique for the same.
The present study assesses the impact on air environment due to the mining project of
Limestone Mine (Area 18.03.88 ha) Near Village: Pachhtardi, Taluka: Bhanvad, District:
Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat).
This report gives the cumulative peak incremental concentration of Particulate Matter up to a
distance of 10 km from the lease boundary, due to the mining activity. The concentrations
have been predicted in all directions covering all study period. Spatial distributions of all the
pollutants are also presented in the form of Isopleths.
4.2.1.3 EMISSION RATE AS PER MATERIAL HANDLED
The emissions in the present case have been computed using empirical factor given in “Indian
Mining and Engineering Journal”. The details of emissions computed from mining operations
are given below:
Table: 4.1
Emission rate as per material handled
Limestone Million TPA 0.35
Total Working Days Number 300 days
Activity rate (Limestone) t/hr 72.91
Uncontrolled emission
Emission factor
Kg per thousand tonnes of material
handled 23.6
Emission Rate gm/sec 0.47
Area of influence Sq.m 180388
Area Source Emission rate gm/sec/Sq.m 0.0000026054
Controlled Emissions gm/sec/Sq.m 0.0000008685
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 162 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.1.4 MODELING PROCEDURE
Prediction of incremental ground level concentrations (GLC’s) due to Limestone Mine has been
made by AERMOD version 8.1 as per CPCB guidelines. It is US-EPA approved model for
prediction of the air quality. The model uses rural dispersion and regulatory default options as
per guidelines on air quality models (PROBES/70/1997-1998). For this study, uniform polar
receptors on flat terrain have been assumed.
Meteorological inputs required are hourly wind speed and direction, ambient temperature,
stability class and mixing height. The model details are as follows:
4.2.1.5 METEOROLOGICAL DATA
Data recorded at the weather monitoring station on wind speed, direction, and temperature
at one-hour interval for the monitoring period has been used as meteorological input.
4.2.1.6 STABILITY CLASSIFICATION
Hourly stability is determined by wind direction fluctuation method as suggested by Slade (1965)
and recommended by CPCB (PROBES/70/1997-1998).
σa = Wdr/6
σa, is standard deviation of wind direction fluctuation, Wdr is the overall wind direction
fluctuation or width of the wind direction in degrees. The table for stability classes is given as
under:
Stability Class σσσσa (degree) Stability Class σσσσa (degree)
A > 22.5 D 12.4 – 7.5
B 22.4 – 17.5 E 7.4 – 3.5
C 17.4 – 12.5 F < 3.5
4.2.1.7 DISPERSION PARAMETERS
Dispersion parameters σy and σz for open country conditions (Briggs, 1974) are used as the
project is located in a rural area. Atmospheric dispersion coefficients vary with downwind
distance (x) from emission sources for different atmospheric stability conditions. (CPCB –
PROBES/70/1997-98).
Table 4.2
Rural Conditions
Stabilit
y Class
σσσσy σσσσaz Stability Class σσσσy σσσσaz
A 0.22x(1+0.0001x)-.5 0.20x D 0.08x(1+0.0001x)-.5 0.06(1+0.0015x).5
B 0.16x(1+0.0001x)-.5 0.12x E 0.06x(1+0.0001x)-.5 0.03x(1+0.0003x)-1
C 0.11x(1+0.0001x)-.5 0.08x(1+0.
0002x).5
F 0.04x(1+0.0001x)-.5 0.16x(1+0.0003x)-1
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 163 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.1.8 MIXING HEIGHT
Mixing Height is an important parameter to be considered for air quality impact prediction as it
significantly affects the dispersion of pollutants in the atmosphere. As site specific mixing
heights were not available, mixing heights based on IMD publication, “Atlas of Hourly Mixing
Height and Assimilative Capacity of Atmosphere in India”, has been considered for Industrial
Source Complex model to establish the worst case scenario.
Table - 4.3
Mixing Height Winter Season (December, 2017 to February, 2018)
Time (Hours) Mixing Height (m)
0700 40-60
0800 60-80
0900 150-200
1000 350-450
1100 500-800
1200 850-1000
1300 1150-1250
1400 1250-1400
1500 1350-1500
1600 1250-1350
1700 1100-1200
1800 825-925
1900 500-550
Source: IMD publication, “Atlas of Hourly Mixing Height and Assimilative Capacity of Atmosphere
in India”
4.2.1.9 AMBIENT AIR QUALITY STANDARDS
Ambient air quality standards promulgated by National Ambient Air Quality Standards for
different areas are as follows:
Table - 4.4
AMBIENT AIR QUALITY STANDARDS
Area Time Weighted
Average
Concentration (µg/m3)
PM10 SO2 NO2
Industrial Area, Residential Rural and
Other Areas
Annual Average *
24 hours **
60 50 40
100 80 80
Ecologically Sensitive Area (Notified by
Central Govt.)
Annual Average *
24 hours **
60 20 30
100 80 80
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 164 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.1.10 PRESENTATION OF RESULTS
In the present case, model simulations have been carried out for mining project to obtain an
optimum description of variations in concentration over the site in 10 km radius covering 16
directions.
The incremental concentrations have been estimated based on mathematical emission data
based modeling. For each time scale, i.e. for 24 hrs, the model computes the maximum GLC
observed during the period over all the measurement points. Existing value has been covered in
the Background Ambient Air Quality Monitoring. The Ground level incremental concentrations
are estimated for the monitoring period. For each time scale, i.e. for 24 hr the model
computes the highest concentrations observed during the period over all the measurement
points.
The maximum incremental GLCs due to the mining project for PM10, is superimposed on the
maximum baseline PM10, concentration recorded at the monitoring locations during the field
monitoring period. The maximum incremental GLCs due to the Limestone Mining Project for
Particulate Matter is 1.03 µg/m3, for NO2 is 2.56 µg/m3, for SO2 is 0.48 µg/m3, and for CO is 22.56
µg/m3. Due to the topography and micrometeorological pattern of the study area, the impacts
identified are not cumulative.
Presently limestone requirement of cement plant is met by its Gop, Chorbedi & Pachhtar
limestone mines. Due to scarcity of reserves in its captive mines, limestone is also being
procured through third Parties Mines in the vicinity. Same travel through SH-95. After
commencment of this Pachhtardi Limestone Mine (Area- 18.03.88 ha), material will be
transpoarted from this mine in place of third party mines. Same transportation route will be
used for transportation of limestone from mine to plant (SH-95). Therefore, there will be no
change in pollution load due to transportation from mine to plant.
Due to the inception of mining project in the area, there will be a slight increase in pollution
levels, but the same will be controlled by adopting proper mitigation measures, as described
in the next para.
4.2.1.11 MITIGATION MEASURES
The following mitigation measures will be adopted to mitigate air pollution generated due to
the mining activities:
Drilling & blasting will not be carried out in the Mine area.
Haul roads & loading area will be regularly sprayed with water to arrest dust from being
air- borne.
Proper maintenance (preventive as well as scheduled maintenance) of vehicles will be
carried out regularly for minimization of generation of gaseous pollutants.
No overloading of material will be done during transportation.
Personal Protective Equipments (PPEs) such as dust masks will be provided to employees
working in dust prone areas.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 165 Prepared by J.M EnviroNet Pvt. Ltd.
Greenbelt along the Mining Lease periphery will be developed.
Periodical air quality monitoring will be carried out.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 166 Prepared by J.M EnviroNet Pvt. Ltd.
Figure 4.1: Isopleth showing Maximum GLC of PM10 Due to Mining Activity
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 167 Prepared by J.M EnviroNet Pvt. Ltd.
Figure 4.2: Isopleth showing Maximum GLC of SO2 Due to Mining Activity
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 168 Prepared by J.M EnviroNet Pvt. Ltd.
Figure 4.3: Isopleth showing Maximum GLC of NO2 Due to Mining Activity
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 169 Prepared by J.M EnviroNet Pvt. Ltd.
Figure 4.4: Isopleth showing Maximum GLC of CO Due to Mining Activity
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 170 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.2 IMPACT OF NOISE / VIBRATIONS AND MITIGATION MEASURES
4.2.2.1 IMPACT OF NOISE ON WORKING ENVIRONMENT
With the mining operations for mine development, excavation and transportation of
limestone, it is imperative that noise levels would increase.
However, the expected noise levels are not likely to have any adverse effect from the
occupational health point of view.
1. Noise Generated due to Drilling, Excavation, Transportation and Crushing
Drilling is not proposed in this mining project. However, the noise levels in the working
environment will be maintained within the standards prescribed by Occupational Safety
and Health Administration (OSHA). These standards were established with the emphasis
on reducing the hearing loss. The permissible limits, as laid down by CPCB, are presented
in following table.
Table 4.5
Permissible Exposure in Cases of
Continuous Noise (CPCB, Govt. of India)
Duration Per Day (hours) Sound Level in dB(A)
8 90
4 93
2 96
1 99
½ 102
Source: CPCB (Govt of India)
2. Noise Generated Due to Blasting
Blasting is not proposed to be carried out for this mining project.
3. Noise Impact Analysis on Community
High noise levels will be confined to work zone areas only. It can be seen that noise levels
get diffused rapidly with distance. Noise level in the study area varied from 51.4 to 53.8
Leq dB(A) during day time and from 41.1 to 43.9 Leq dB(A) during night time. The
predicted noise levels indicate that there will be no significant increment to the ambient
noise levels.
In summary, it can be stated that the impact on the present noise levels due to mining
operations will be restricted to the work zone areas only. The impact on the ambient
noise levels is not felt at the settlement areas due to proposed development of greenbelt
and masking effect with the existing noise levels. Hence, the noise levels impact due to
mining operations on community will be insignificant.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 171 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.2.2 MITIGATION MEASURES TO REDUCE NOISE LEVEL
The following control measures will be adopted to keep the ambient noise levels well below
the limits.
No drilling & blasting will be carried out in the Mine area.
All the HEMMs will be equipped with acoustic cabins for operators.
In order to reduce the effect of noise pollution, personal protective equipments like ear
plugs, ear muffs will be provided to workers exposed to high noise levels.
Scheduled & preventive maintenance of all the machinery will be carried out regularly.
Green belt will be developed around periphery of the mining lease to attenuate noise
level.
Regular monitoring of ambient noise level will be carried out.
4.2.2.3 IMPACT OF VIBRATION DUE TO BLASTING
Blasting is not proposed to be carried out for this mining project. Hence, there will be no
impact of vibration due to blasting.
4.2.3 IMPACT ON WATER ENVIRONMENT & MITIGATION MEASURES
4.2.3.1 IMPACT ON SURFACE WATER AND MITIGATION MEASURES
There is no surface water body i.e. nalla (s), streams or perennial river within the lease
area.
Along northern boundary and outside the lease area, there is one seasonal nallah, which
flows during rains only in East-West direction. During most part of the year this nallah
remains dry.
Water bodies like Vartu River and Vartu Dam also exists in the study area.
At the conceptual stage, 13.8690 ha area will be converted into water reservoir which will
serve as recharge pit.
4.2.3.2 IMPACT ON GROUND WATER AND MITIGATION MEASURES
General Ground level of the Lease area is 92 m AMSL. According to groundwater monitoring
Water level varies from 72 to 67 m AMSL (20 to 25 m bgl) and Ultimate working depth of the
mining operation will be 72 m AMSL (20 mbgl). As per the above details, Water table will not
be intersected due to mining activities.
Detailed Hydro-Geological Study has been carried out and same is given as Annexure VIII with
this Draft EIA/EMP Report.
4.2.3.3 WASTE WATER MANAGEMENT
Following measures will be adopted for waste water management:
There will be no waste water generation during mining process.
Domestic wastewater generated from mines office will be disposed off in soak pit via
septic tank.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 172 Prepared by J.M EnviroNet Pvt. Ltd.
Disposal of waste water from workshop will be treated by oil-water separator before its
use for dust suppression.
Periodical Ground water level & quality monitoring will be carried out.
4.2.3.4 WATER CONSERVATION MEASURES
A. Water Recycling
Waste water generated from workshop will be used for dust suppression after
separation of Oil & grease content.
B. Rain Water Harvesting
Rain Water harvesting Techniques will be implemented for conservation of water.
This technique will recharge the ground water table level of the area.
Total quantity of rainwater accumulated in mine pits during five year mine plan
period and up to conceptual year has been calculated using year wise pit
development plans, year wise pit sections for proposed mining and average annual
rainfall in the area. This entire water will be available in excess amount which may be
utilized for various purposes in mine activities i.e. dust suppression, green belt
development and domestic purposes other than drinking or can be discharged
through pump for usage of local villagers.
Total rainwater accumulated in the mine pits during next five years works out to be
0.15 mcm respectively. The daily water availability shall be minimum 13 cubic meters
in 1st year and maximum 65 cubic meters in 5th year respectively. The total water
requirement for mine activities shall be 22 KLD which shall amount to 0.006 mcm.
After 2nd year of mining operations, rainwater accumulated in mine pits shall be able
to cater the needs of overall water requirement i.e. 22 KLD even after reduction of
annual losses in the form of Evaporation and Groundwater recharge (up to 50%). At
the end of life of mine/conceptual stage, rainwater accumulated in area left for water
reservoir will be approximately 0.10 mcm/annum.
Year Excavated Area (m2)
Depth (m bgl)
Average Annual
Rainfall (m)
Annual Rain water Stored
(Cum)
Annual Losses (50%) {i.e. Evaporation -30%
& Groundwater Recharge - 20%)
Daily Available
Rainwater (Cum)
Five Year Mine Plan Period
I Year 1.28 15 0.752 9,626 4,813 13
II Year 2.7 15 0.752 20,304 10,152 28
III Year 3.95 15 0.752 29,704 14,852 41
IV Year 5.09 15 0.752 38,277 19,138 52
V Year 6.32 15 0.752 47,526 23,763 65
Total
1,45,437 72,718
Conceptual Stage (Water Reservoir)
1,36,240 20 0.752 1,02,452 51,226 140
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 173 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.4 IMPACT ON SOIL / LAND USE PATTERN & MITIGATION MEASURES
4.2.4.1 IMPACT ON SOIL ENVIRONMENT
Negligible amount of top soil will be generated which will be utilized concurrently for
plantation purpose. There is no proposal for stacking the top soil.
4.2.4.2 LANDSCAPE AND LAND USE PATTERN
Land use pattern of the lease area during operational, pre-operational and post-operational
phases have been given in following table:
TABLE 4.6
STAGE WISE LAND USE AND RECLAMATION AREA (Ha)
S. No Land Use Category
Pre
operational
(Present)
Operational
(At the end
of 5th Year)
Post Operational
(At the end of
life of mine)
1. Top Soil Dump - - -
2. Waste Dump - - -
3A. Excavation (Voids only) 1.1700 6.2390 13.8690
3B. Reclamation (Backfilled) - - -
4. Road - - -
5. Infrastructure (Admin building & roads etc.) 0.3000 0.4000 0.5500
6. Township Area - - -
7. Green belt - 2.0150 2.0150
8. Mineral Storage - - -
9. Undisturbed area 16.5688 9.3848 1.6048
Total 18.0388 18.0388 18.0388
Source: Approved Mining plan & Progressive Mine Closure Plan, page no.63
4.2.4.3 RECLAMATION PLAN FOR LAND
At the conceptual stage, total excavated area will be 13.8690 ha which will be converted
into water reservoir.
Green belt will be developed along the mine boundary on 2.0150 ha area.
1.6048 ha area will be covered under undisturbed area.
Conceptual plan showing impact of change of land use is given as Annexure IXB with this
Draft EIA/EMP report.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 174 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.4.4 IDENTIFICATION OF IMPACTS ON LAND USE PATTERN DUE TO THE MINING ACTIVITY
a) Impact on Core Zone
The proposed limestone mining activities will be carried out within the 18.0388 ha.
area which is a Government waste land.
The land use of the lease area will alter from waste land to mining area including pits,
greenbelt, water reservoir etc.
At the conceptual stage, total excavated area will be 13.8690 ha which will be
converted into water reservoir. Green belt will be developed along the mine
boundary on 2.0150 ha area.
b) Impact on Buffer Zone:
There will be no change in land use of buffer zone due to proposed mining activity.
Awareness for new methodologies of agricultural practices viz. mixed farming, crop
rotation and agricultural cropping pattern suitable for the study area will also be
carried out under ESC to increase the agricultural productivity of the study area.
Mining activity will be confined to the mineralized zone and proper pollution control
measures will be adopted to restrict the pollution load within the active zone in order
to prevent any negative impact on nearby areas. There will be no change in land use
of buffer area. Adequate measures will be taken to control the pollutants within
active mine area. Therefore, no adverse impact is envisaged in the study area.
Recommendations:
Greenbelt will be developed along the mine periphery so that dust emission impacts
can be minimized on surrounding agriculture fields.
Awareness for new methodologies of the agricultural practices viz. mixed farming,
crop rotation and agricultural cropping pattern suitable for the lease area.
Providing seeds, manure and fertilizers from different sources.
Rainwater harvesting practices will be encouraged which will lead to ground water
recharge and ultimately increased productivity in the study area.
4.2.5 SOCIO – ECONOMIC ENVIRONMENT
The potential impact on socio-economic environment due to this mining project is given in
following heads.
4.2.5.1 POSITIVE IMPACTS
Employment:
Direct and indirect employment opportunities will be generated during mining operation and
other allied activities. Employment generated by SDCCL will provide a safe working
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 175 Prepared by J.M EnviroNet Pvt. Ltd.
environment for workers. Preference for employment will be given to locals based on need,
eligibility and qualification.
Community Skills Development:
The local community will be benefitted from the training programmes that will be instituted
by SDCCL to enable the community labour force to work for their livelihood/Self-growth. This
training will improve their skill sets that will not only benefit SDCCL but also the community at
large during and after the project life.
Improved Standard of Living:
Employment opportunities created by the project will increase income of local community
and therefore improve the overall standard of living in the area.
Economic Exposure and Development:
Implementation of the project will make opportunities for sustainable livelihood, better
infrastructure facilities and services available to the people. This will expose and introduce
the local population to factors of economic development including the banking system,
financial services and credit and investment schemes. The exposure will enable community
members to invest their income and prevent dependency or living a life with a view of
“tomorrow will take care of itself”.
Impact on Civic Amenities
The impact of the proposed limestone project on the civic amenities will be positive. With
improved transportation facilities, educational facilities and other recreational facilities etc.
there will be improvement in civic amenities. The communication facilities will also improve in
the area.
4.2.5.2 ADVERSE SOCIAL IMPACTS
Health Impacts
The project may trigger negative health impacts through increased dust, creation of breeding
grounds for disease vectors, population influx which might introduce new diseases in the
area and pressure on sanitation facilities.
Livelihood Change
Due to the labour intensity of the mining sector, the project will attract the more able-bodied
persons from the community which in turn will lead to low labour availability in other sectors
of the economy including agricultural, labour intensive jobs etc. project will have insignificant
impact on livelihood change.
Population Growth
This project will not have any substantial impact on the population growth. The proposed
limestone project will generate employment opportunities for the people of nearby villages
and rehabilitated families rendering positive impact on the area on the whole.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 176 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.5.3 MITIGATION MEASURES
Mitigation Health Impacts
As mentioned in 4.2.1, the incremental GLCs for various air pollutants will be restricted within
the lease area and the impacts will be negligible on the nearby villages. Nevertheless,
Awareness programmes on health hazards will be conducted to create awareness amongst
the employees as well as the local population. SDCCL will do CER activities in the area of
Health facilities by means of providing primary health services covering nearby villages
through health extenders, in conjunction with Government and NGOs. The health issues can
be monitored and addressed in this manner. SDCCL will consider Health facilities under its
CER activities.
Health Care Facilities
Proper health care facilities will be provided to the employees of limestone Mine along with
their families. The medical facilities in form of primary medical camps will also be extended to
local people in the nearby areas under CER activities.
Managing Loss of Livelihood and Income:
To cushion the population against impacts of mine closure, adequate advance intimation will
be given to employees and contractors to allow them to source alternative opportunities.
Skills development programmes will also be undertaken by SDCCL to ensure sustainable
livelihood for people of the nearby areas.
4.2.6 IMPACT ON HUMAN SETTLEMENT
The proposed limestone mining activities will be carried out within the 18.0388 ha. area which
is a Government waste land.
By carrying out detailed geological exploration and computation of reserves and
subsequently in mine planning, maximum effort has been given to keep the village
settlements outside by a safe margin as per the safety provisions. Nearest Village is pachhtar
about 50 m far in West direction from mine site. Greenbelt will be developed on 7.5 m wide
belt all around the lease periphery. Due to the soft nature of the mineral, drilling and blasting
is not proposed for this mining project. However, Following Protection measures will be
taken to mitigate the impact of mining activities on nearest habitation:
Mining will be carried out as per the provisions outlined in mining plan approved by
Indian Bureau of Mines (IBM).
Regular ambient air quality monitoring and noise monitoring will be done.
All measures will be adopted to control fugitive dust emission during mining operation.
Water sprinkling will be done on the haul roads to suppress the dust.
4.2.7 PUBLIC HEALTH IMPLICATIONS
As per the survey carried out in the study area, common diseases in the region are Diarrhoea,
Viral fever, Typhoid, Dermatitis, Urinary tract infections, Conjunctivitis, Cataract, Arthritis,
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 177 Prepared by J.M EnviroNet Pvt. Ltd.
Gastrointestinal disease, malaria etc. None of these can be related to the project and relied
activities of project.
Greenbelt will be developed in safety zone.
Air quality modelling has been carried out & incremental value, i.e. 1.03 µg/m3 due to mine
within the lease area.
No waste water will be generated due to mining operations.
Pollution control measures for ambient air, water, noise will be taken to maintain within
the prescribed standards.
Regular Ambient air quality monitoring, noise monitoring & water quality analysis will be
done.
Efforts will be made under CER to improve the hygiene, sanitation, education and
infrastructure of the nearby villagers.
All the employees when inducted will be medically examined. Further, they will also be
medically examined at periodical interval.
4.2.8 IMPACT ON LOCAL TRANSPORT INFRASTRUCTURE
SDCCL have an existing Cement Plant situated at Digvijaygram (Sikka), District- Jamnagar,
Gujarat which is about 86.95 km far away from mine site (By road distance).
About 1167 Tonnes per day mineral will be transported from mine site to cement plant.
Transportation of limestone from mine site to plant will be done by hired Trucks /
dumpers via SH – 95 (Within 10 km radius study area).
Traffic survey has been done as per Indian Roads Congress Guidelines for the mine at one
survey point marked on transportation route map given below:
Table 4.7
Details of traffic survey Point
Survey Point Coordinates Landmark Aerial distance &
direction from mine site
SH-95 21° 53' 04.72"N 69° 41' 33.12"E
Near Bhavneshwar Village ~2.8 km in North direction
Source: Filed Survey
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88 ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 178 Prepared by J.M EnviroNet Pvt. Ltd.
Table 4.8
Traffic Volume Count Survey (Hourly)
Name of the Road: SH -95 (Porbandar to Jamnagar Road) Date of Survey: 01.02.2018 to 02.02.2018
Fast Vehicles Slow Vehicles
Time of
Monitoring
Motor Cycle or
Scooter
Passenger Car,
Pick up van or
Auto Rickshaw
CAR/VANS BUSES Trucks CYCLES CYCLE
RIKSHAW
Up Dn Up Dn Up Dn Up Dn Up Dn Up Dn Up Dn
6-7 AM 17 12 23 6 8 12 3 2 17 23 2 3 Nil Nil
7-8 AM 32 28 13 7 13 19 4 6 19 19 Nil Nil Nil Nil
8-9 AM 48 62 11 9 22 17 5 3 7 22 Nil Nil Nil Nil
9-10 AM 84 72 21 16 18 17 2 5 20 17 1 2 Nil Nil
10-11 AM 76 83 18 21 21 21 1 2 18 24 Nil Nil Nil Nil
11-12 PM 52 47 27 28 22 18 2 3 21 24 Nil Nil Nil Nil
12-1 PM 62 77 17 22 16 24 3 2 26 18 1 Nil Nil Nil
1-2 PM 78 85 19 27 18 13 4 1 18 28 Nil Nil Nil Nil
2-3 PM 102 88 36 31 13 21 1 3 21 17 Nil Nil Nil Nil
3-4 PM 98 71 42 38 23 16 3 5 32 26 2 1 Nil Nil
4-5 PM 73 82 29 32 11 17 2 1 22 27 2 Nil Nil Nil
5-6 PM 72 80 30 20 10 15 2 1 20 32 Nil Nil Nil Nil
6-7 PM 67 75 28 17 8 10 1 Nil 17 30 Nil Nil Nil Nil
7-8 PM 63 70 26 12 5 7 Nil 1 14 32 Nil Nil Nil Nil
8-9 PM 62 58 21 Nil 5 12 Nil Nil 12 27 Nil Nil Nil Nil
9-10 PM 59 47 18 Nil 4 11 Nil Nil 7 17 Nil Nil Nil Nil
10-11 PM 2 1 3 5 8 4 5 3 10 21 Nil Nil Nil Nil
11-12 AM 1 1 2 3 7 4 2 1 12 15 Nil Nil Nil Nil
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88 ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 179 Prepared by J.M EnviroNet Pvt. Ltd.
12-1 AM Nil Nil Nil 1 Nil Nil Nil Nil 5 9 Nil Nil Nil Nil
1-2 AM Nil Nil 2 Nil Nil Nil Nil Nil 13 16 Nil Nil Nil Nil
2-3 AM Nil Nil Nil Nil Nil Nil Nil Nil 19 22 Nil Nil Nil Nil
3-4 AM 2 1 5 7 3 2 Nil Nil 10 8 Nil Nil Nil Nil
4-5 AM 7 8 13 11 5 3 2 1 17 15 Nil Nil Nil Nil
5-6 AM 12 15 20 22 18 15 4 5 24 20 Nil Nil Nil Nil
Table 4.9
No of Vehicles per day for SH-95
S. No. VEHICLES DISTRIBUTION NUMBER OF VEHICLES
DISTRIBUTION/DAY
PASSENGER CAR
UNIT (PCU)
TOTAL NUMBER OF VEHICLE (PCU)/DAY
1 Two wheelers 2132 0.5 1066
2 Three wheelers 761 1.0 761
3 Car/Vans 536 1.0 536
4 Buses 96 3.0 288
5 Trucks/Tipper 910 3.0 2730
Total 4435 - 5381/24= 224.20 PCU/hr
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 180 Prepared by J.M EnviroNet Pvt. Ltd.
Table 4.10
Existing Traffic Scenario & LOS for traffic survey point
S.
No
ROAD V (VOLUME IN
PCU/HR)
RECOMMENDED
SERVICE VOLUME
(CAPACITY IN PCU/HR)
EXISTING
VEHICLE/VELOCITY
(V/C) RATIO
LEVEL OF
SERVICE
(LOS)
1 SH-95 (Porbandar to
Jamnagar Road)
224.20 625* 0.35 B
*Recommended service volume for two lane road as per IRC guidelines for capacity of roads in
rural areas (IRC: 64-1990)
Table 4.11
Capacity as per IRC: 64-1990
V/C LOS PERFORMANCE
0.0-0.2 A Excellent
0.2-0.4 B Very Good
0.4-0.6 C Good/Average/Fair
0.6-0.8 D Poor
0.8-1.0 E Very Poor
During Mine Operation
Total Capacity of mine: 3,50,000 TPA
No. of working days: 300 Days
Extraction & Transportation of mineral: 1167 TPD
Working hours per day: 16 hours in 2 shifts
Number of dumpers deployed per day = 10
Capacity of dumpers = 20 tonnes
Number of trips/Frequency of Dumper deployed/day (up & down) = 12
Number of trips/Frequency of Dumper deployed/hr (up & down) = 0.75
Increase in PCU/hr: (No. of trips per/hour X PCU) = 0.75 x 3= 2.25
Table 4.12
Modified Traffic Scenario & LOS
S.
No
ROAD INCREASED
PCUS/ STATE
HIGHWAY
V (VOLUME IN
PCU/HR)
C (CAPACITY
IN PCU/HR)
MODIFIED
V/C RATIO
LOS
1 SH-95
(Porbandar to
Jamnagar Road)
2.25 X 100% 224.20 +2.25=
226.45
625* 0.36
B
*Recommended service volume for two lane road as per IRC guidelines for capacity of roads in rural areas
(IRC: 64-1990)
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88 ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 181 Prepared by J.M EnviroNet Pvt. Ltd.
Fig 4.5: Transportation Route Map
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 182 Prepared by J.M EnviroNet Pvt. Ltd.
4.2.8.1 CONCLUSION
The LOS value is “Good” for State Highway i.e., SH-95 (Porbandar to Jamnagar road) So the
additional load on the carrying Capacity of the concern roads is not likely to have any change
in the LOS value.
4.2.8.2 MEASURES FOR TRANSPORTATION
Following mitigation measures will be adopted to reduce the impact on local transport
infrastructure:
Only vehicles with PUC certificate will be allowed to transport the mineral from mine to
plant.
Mineral transported through vehicles will not be overloaded.
Dust suppression will be done by regular sprinkling of water on haul roads.
Proper maintenance of transportation vehicles helps in reducing fugitive pollution due to
exhaust fumes.
4.2.9 IMPACT ON BIOLOGICAL ENVIRONMENT
Barda Wildlife Sanctuary is found at an aerial distance of 1.5 km from the mine site and ESZ of
Barda Wildlife Sanctuary is at an aerial distance of 1.18 km from the mine site.
Certificate along with map has been obtained from the State Forest Department vide their
letter No A/JMN/TE.7/282/2017-18 dated 07.10.2017 and vide letter no vide their letter No
K/JMN/T.7/359/2018-19 dated 04.08.2018 with regard to the exact distance of the mine lease
(in kilometer) from the boundary of wild life sanctuary. (Copy of the same is enclosed as
Annexure IVB). As final notification is published by MoEFCC declaring Eco-Sensitive zone
around Barda Wildlife Sanctuary dated 28.04.2017 and according to that, our mine site not
falling in ESZ of Barda Wildlife Sanctuary. Therefore, NBWL Clearance is not required.
This is a Limestone mining project and No forest land falls within the lease area. At the
conceptual stage, an area of about 2.015 ha in the Area will be covered under greenbelt which
will improve the green cover and aesthetic environment of the area.
4.2.9.1 IMPACT ON FLORA
No adverse impact is envisaged on the existing flora, as there will be no deforestation by
mining operation. Plantation will be developed in the lease area as per plantation
programme. These activities will help to improve the floral cover of the area. The greenbelt
and plantation development will eventually attract micro fauna, birds etc. in the area.
Assistance will be taken from local forest department in selection of species of plants so that
green coverage could improve very fast. The varieties would include those plants, which are
suitable to the area.
4.2.9.2 IMPACT ON FAUNA
Authentication of list of flora & fauna has been done by State Forest Dept vide their letter No
K/JMN/T.7/204/2018-19 dated 28.06.2018 (Copy enclosed as Annexure IVC). As per the survey
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 183 Prepared by J.M EnviroNet Pvt. Ltd.
report, Three Schedule –I species i.e. Peafowl, Monitor Lizard and Leopard were observed
within the study area. Conservation Plan along with the Budget has been prepared. (Copy of
the same is enclosed as Annexure IV-D).
Proper Environment mitigation measures will be adopted; therefore, mining will not cause
any adverse impact on existing wildlife.
Adequate measures for keeping noise level well within permissible limit will be taken to
prevent disturbance to wild life. Mine lease area will be fenced for preventing the entry of
wildlife into the mine area.
4.2.9.3 MEASURES FOR MINIMIZING IMPACT ON FAUNA
Following measures will be adopted to minimize the impact of mining on faunal environment
of the area.
Measures will be taken and environment management plan will be implemented to curb
pollution of air, water, land and noise environment.
Greenbelt development and plantation helps in creating habitats for local faunal species
and to create better environment for various fauna.
Creating and developing awareness for nature and wildlife in the nearby villages.
4.2.10 OCCUPATIONAL HEALTH AND SAFETY
Occupational health and safety (OHS) is a multidisciplinary field concerned with the safety,
health and welfare of people at work. The goal of occupational safety and health programs
includes fostering a safe and healthy work environment. OHS may also protect co-workers,
family members, employers, customers, and many others who might be affected by the
workplace environment.
Occupational Health & Safety is based on the following three aspects:-
• Hazard identification
• Risk assessment
• Determination of applicable controls
A Hazard Identification and Risk (HIRA) Analysis is a systematic way to identify and analyze
hazards to determine their scope, impact and the vulnerability of the built environment to
such hazards and its purpose is to ensure that there is a formal process for hazard
identification, risk assessment and control to effectively manage hazards that may occur
within the workplaces. Details regarding occupational health hazards as well as mitigation
measures have been discussed as under:
S.
No
Hazards and
Sources
Anticipated
impacts
Preventive Measures Control Measures
1. Exposure to heat
due to:
Sun exposure
Working
temperature
Dehydration,
Fatigue,
Headache
Training and awareness to
workers
Implementation of safety
standards and awareness.
Adequate drinking water
Onsite emergency preparedness
Rest shelter in M.L. area
Personal Protective Equipment viz.
helmet, boots.
Onsite emergency preparedness
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 184 Prepared by J.M EnviroNet Pvt. Ltd.
supply.
Use of HEMM having A.C
cabins.
2. Physical hazards
due to :-
Slips and falls
Contact with, or
capture in,
moving
machinery
Physical
injury
Use of reflective jackets
and other PPEs
Implementation of safety
standards and awareness.
Training & education
No loose fitting clothes will
be permitted within the
Mine
Personal Protective Equipment viz.
helmet, boots
Onsite emergency preparedness
3. Exposure to Noise
& Vibration due to
:-
HEMM
operations
Transportation
Over
exposure
may lead to
hearing
impairment
HEMMs provided with
ergonomically designed
operator’s cabin
Regular maintenance of
HEMMs
Regular Noise level survey
Use of silencers & mufflers, sound
proof cabins,
Personal hearing protection like
ear plugs/muffs.
Limited/discontinuous exposure to
noise HEMM operations & job
rotation.
4. Exposure to dust
due to :-
Excavation
Loading
Transportation
Breathing
problem &
lung
disorders
Control of dust at
generation point through
water/mist spraying
Maintenance of HEMM
Use of HEMM having A.C
cabins.
Green belt development
Use of PPEs, as necessary (e.g.
dust masks).
Onsite emergency preparedness
4.2.10.1 OCCUPATIONAL HEALTH AND RELATED DISEASE
The following table depicts the potential effects due to limestone mining.
S NO. EFFECT SYMPTOMS FIRST AID MEASURES
1. Eyes Contact can cause irritation of eyes. Immediately flushing of eyes with generous
amounts of water. Pulling back of eyelid while
flushing to ensure that all limestone dust has
been washed out. Seeking medical attention
promptly if the initial flushing of the eyes does
not remove the irritant. No rubbing of eyes.
2. Skin Contact can cause mild irritation of skin. Brushing off or removing as much dry
limestone as possible. Washing of exposed
area with large amounts of water.
3. Inhalation It can cause mild irritation of the
respiratory system. Long-term exposure
may cause permanent damage. Limestone
is not listed by Mine Safety and Health
Administration (MSHA), OSHA, or
International Agency for Research on
Moving victim to fresh air. Seeking medical
attention.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 185 Prepared by J.M EnviroNet Pvt. Ltd.
Cancer (IARC) as a carcinogen. However,
It may contain trace amounts of
crystalline silica in the form of quartz or
crystobalite, which has been classified by
IARC as a Group I carcinogen to humans
when inhaled. Inhalation of free silica can
also cause a chronic lung disorder,
silicosis.
4.2.10.2 IMPLEMENTATION OF OCCUPATIONAL HEALTH AND SAFETY MEASURES
Occupational Health and Safety measures result in improving the conditions under which
workers are employed. It improves not only their physical efficiency but also provides
protection to their life. SDCCL will adopt the following safety measures:
Continuous monitoring for compliance of SOPs.
Pit Safety Committee will be formed and recommendations given by committee will be
implemented.
Awareness for safety and occupational health will be implemented like posters, safety
films, etc.,
Safety clauses in contract order.
To depute Environment Health & Safety team
Medical exam for fitness before employment as per standards in Form P-1 of Mines Rules
1955.
Periodical medical examination as per Mines Rule 1955- will be done every 5 years as per
standards laid down in Form P.
The persons working in dusty environment will be examined every year as per the DGMS
circular No. 01 of 21.01.2010.
All employees will undergo medical examination as per the recommendation of 10
National Conference of safety in Mines.
Besides that, to avoid any adverse effect on the health of workers due to various
pollutants, sufficient measures relating to safety and health will also be practiced.
Provision of rest shelters for mine workers with amenities like drinking water etc.
Training of employees for use of safety appliances and first aid in vocational training
center.
Removal of unsafe conditions and prevention of unsafe acts
Detailed analysis of each and every incident
Periodic inspection by internal and external safety experts
Celebrations of various safety events for awareness
An effective and clearly audible means of giving warning, in case of fire, to every person
are provided at the site. A free passage–way giving access to each means of escape in
case of fire will be maintained for the use of all workers.
Regular maintenance and testing of all equipment as per manufacturers’ guidelines.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA / EMP Report
Shree Digvijay Cement Company Ltd. 186 Prepared by J.M EnviroNet Pvt. Ltd.
Close surveillance of the factors in working environment and work practices which may
affect environment and workers health.
Working of mine will be done as per approved mining plan and environmental plans.
Implementation of comprehensive Hearing Conservation Programs. The hearing
conservation program requires employers to monitor noise exposure levels in a way that
accurately identifies employees exposed to noise at or above 85 decibels (dB) averaged
over 8 working hours, or an 8-hour time-weighted average (TWA). Employers must
monitor all employees whose noise exposure is equivalent to or greater than a noise
exposure received in 8 hours where the noise level is constantly 85 dB. Project specific
Hearing Conservation Plan to be prepared covering the aspects of monitoring, testing,
evaluation and protection of noise.
All safety measures will be taken which includes the use of safety appliances such as:
Mask for protection from dust (DGMS approved design, dust free disposable facial
mask as per IS: 9473)
Ear Muffs
Safety Helmets
Reflective jackets
Safety Belts
Safety Shoes
Goggles etc.
Availability of Medical facilities for proposed mine and establishment of first aid stations
equipped with first aid boxes in the mine premises.
Conduction of internal audits and evaluation of legal compliance.
In order to ensure adequate implementation of the OHS measures suggested, SDCCL will
adhere to the pre & periodical medical examination program. Details of the same are given in
Chapter X, Para 10.5 of this Draft EIA/EMP Report.
4.3 CONCLUSION
As discussed above, it is safe to say that the project will not cause any significant impact on
the environment of the area, as adequate preventive measures will be adopted to contain
various pollutants generated due to the mining project within permissible limits. Continuous
development of Green belt around the mining lease boundary will minimize the environment
pollution and improve the aesthetic beauty. Further the development of water ponds and
greenbelt will remain useful for local community. The project will also increase employment
benefit and revenue to the Government.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area-
18.03.88 ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 187 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER-V
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
5.1 GENERAL
A comparison of alternatives helps to determine the best method of achieving the project
objectives with minimum environmental impacts or indicates the most environment friendly
and cost effective options.
Every mine needs to be planned in a way that the mineral is extracted to the maximum extent
without causing severe irreversible environmental damages.
5.2 ANALYSIS OF SITE
The minerals are site specific and they are mined where they are situated. The area i.e. mine
site is found suitable one as existence of mineral is proved in accordance of the Mineral
(Evidence of Mineral Contents) Rules- 2015. In order to cater the limestone requirement for
the existing captive cement plant having production capacity of 1.20 Million TPA cement,
located at Digvijaygram (Sikka), District –Jamnagar, Gujrat, SDCCL has proposed a Pachhtardi
Limestone Mine (ML area- 18.03.88 ha) with Limestone Production Capacity 0.35 Million TPA
At survey No 78, Village- Pachhtardi, Taluka- Bhanvad, District- Devbhumi Dwarka (Erstwhile
Jamnagar) (Gujarat).
5.3 ANALYSIS OF TECHNOLOGY
The Proposed mining method is Opencast Fully Mechanized Eco-friendly mining method.
Without drilling & blasting, excavation will be done either by deployment of Surface Miner &
Loader combination or by Ripper dozer and Excavator combination with maximum bench
height of 7.5 meters and minimum working bench width of 7.5 Meters. Loading operations
will be carried out by loaders/Excavator. Transportation of limestone from working face to
cement plant will be carried out by hired Trucks / dumpers.
5.4 CONCLUSION
This limestone mine is a captive mine of SDCCL. The mineral mined at this mine will be used
for the manufacture of clinker/cement at the integrated cement plant. From the nature &
extent of the deposit, the reserves & the quality has been proved with adequate degree of
reliability. As the minerals are site specific and they are mined where they are situated, no
alternative site has been considered. Hence, no Change in site and technology envisaged.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 188 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER–VI
ENVIRONMENTAL MONITORING PROGRAMME
6.1 INTRODUCTION
Post Project Monitoring is an essential part to check the impact of project related activity.
Hence monitoring of various environmental parameters will be carried out on a regular basis
to ascertain the following:
Status of Pollution within the mine site and in its vicinity.
To generate data for predictive or corrective purpose in respect of pollution.
To examine the efficiency of pollution control system adopted at the site.
To assess environmental impacts.
Monitoring will be carried out at the site as per the norms of CPCB.
Environmental Monitoring Programme will be conducted for various environmental
components as per conditions stipulated in Environmental Clearance Letter issued by
MoEFCC & Consent to Operate issued by SPCB.
Six monthly compliance reports will be submitted every year to Regional Office by 1st of June,
& 1st of December. Quarterly compliance Report for conditions stipulated in Consent to
Operate will be submitted to SPCB on regular basis.
6.2 FORMATION OF ENVIRONMENTAL MANAGEMENT CELL (EMC)
In order to maintain the environmental quality within the standards, regular monitoring of
various environmental components is necessary. Shree Digvijay Cement Company Ltd.
(SDCCL) will have an Environmental Management Cell (EMC) for environmental monitoring
and control. The EMC team takes care of pollution monitoring aspects and implementation of
control measures.
A group of qualified and efficient engineers with technicians will be deputed for
maintenance, up keeping and monitoring the pollution control equipment, to keep them in
working mode at the best of their efficiencies. The Organizational structure of EMC is given in
Chapter – X of this Draft EIA/EMP Report.
6.2.1 RESPONSIBILITIES OF EMC
The responsibilities of the EMC include the following:
Environmental monitoring.
Commissioning of pollution control equipment.
Specification and regulation of maintenance schedules for pollution control equipment.
Ensuring that standards are maintained.
Developing the Green Belt.
Ensuring water use will be minimized.
Implementation of the Environmental Management Plan.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 189 Prepared by J.M EnviroNet Pvt. Ltd.
6.3 MEASUREMENT METHODOLOGIES
6.3.1 INSTRUMENTS TO BE USED
The following instruments will be used for data collection work in the monitoring schedule:
1. Respirable Dust Sampler (RDS)
2. Fine Particulate Smapler (FPS)
3. Sound Level Meter
4. Micro Meteorological Station
5. Water level indicator
6.3.2 MONITORING PROGRAMME
The post project Monitoring includes details of any major/ minor impact in the core zone and
area within buffer zone for the following parameters: -
Micro - Meteorological data
Ambient Air Quality Monitoring
Noise Level Monitoring
Water quality and level monitoring
Medical check-up of the employees.
6.3.2.1 MONITORING SCHEDULE
Details of Environmental Monitoring schedule, which will be undertaken for various
environmental components, are detailed below:
TABLE: 6.1
Post Project Monitoring
S. No. DESCRIPTION FREQUENCY OF MONITORING
1. Meteorological Data Daily
2. Ambient Air Quality at mine site Quarterly/ Half Yearly
3. Water Quality Quarterly/ Half Yearly
4. Noise Level Monitoring Quarterly/ Half Yearly
5. Soil Quality Half Yearly/Yearly
6. Socio – economic status of nearby area Yearly
6.3.3 METHODOLOGY ADOPTED
Post project monitoring will be carried out as per conditions stipulated in Environmental
Clearance Letter issued by MoEFCC, Consent issued by SPCB as well as according to CPCB
guidelines. The mine site is considered as core zone and the area lying within 10 km radius
from the mine site is considered as the buffer zone where some impacts may be observed on
physical and biological environment. In the Buffer zone slight impact may be observed and
that too it may be occasional.
The following table is showing details of Post Project Monitoring programme:
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 190 Prepared by J.M EnviroNet Pvt. Ltd.
TABLE: 6.2
POST PROJECT MONITORING PROGRAMME
Attributes Sampling Measurement
Method
Test Procedure
A. Air Environment Network Frequency
Meteorological
• Wind speed
• Wind direction
• Dry bulb
temperature
• Wet bulb
temperature
• Relative humidity
• Rainfall
Minimum 1
at project
site
Regularly in
one season
by Weather
Monitoring
Station
Mechanical/automatic
weather station
-
Pollutants
• PM10
4 locations
at mine
boundary
As per
Revised
National
Ambient Air
Quality
Standards
(NAAQS)
vide MoEF
circular,
dated
16.11.2009
Gravimetric method -
• PM2.5 Gravimetric method -
• SO2 Improved West &
Gaeke method
Absorption in Potassium
Tetra Chloromercurate
followed by Colorimetric
estimation using P-
Rosaniline hydrochloride
and Formaldehyde (IS:
5182 Part - II).
• NO2 Modified Jacob &
Hochheiser (Na-
Arsenite) Method
Absorption in dill NaOH
and then estimated
colorimetrically with
sulphanilamide and N (I-
Nepthyle) Ethylene
diamine Dihydro-chloride
and Hydrogen Peroxide
(IS: 5182 Part 6)
B. Water Environment
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 191 Prepared by J.M EnviroNet Pvt. Ltd.
pH, Turbidity, Colour,
Odour, Taste,
TDS, Total Hardness,
Calcium hardness,
Magnesium hardness,
Chloride, Fluoride,
Sulphate, Nitrates,
Alkalinity,
Iron, Manganese,
Set of
grab
samples
during pre
and post-
monsoon
for ground
water
Diurnal and
Season wise
As per IS 10500-2012 Samples for water quality
should be collected and
analyzed as per: IS: 2488
(Part 1-5) methods for
sampling and testing of
Industrial effluents
Standard methods for
examination of water and
wastewater analysis
published by American
Public Health Association.
C. Noise
Noise levels at Day &
night time -Leq dB (A)
Mine
Boundary,
High noise
generating
areas
within the
lease area
Quarterly /
Half yearly
As per CPCB norms
As per CPCB norms
6.3.4 LOCATIONS OF MONITORING STATIONS
The location of the AAQM monitoring stations are selected on the basis of prevailing micro –
meteorological conditions of the area like; Wind Direction & Wind Speed, Relative Humidity,
Temperature. 4-6 AAQM stations will be selected to assess the ambient air quality of the area.
Noise level is also to be measured in core area as well as study area. Water & Soil monitoring
locations will be decided on the basis of general slope of the area & drainage pattern.
Locations for the post project monitoring are as under.
TABLE: 6.3
LOCATIONS OF MONITORING STATIONS
S. No. Description Location
1. Ambient Air Quality Mine site, Villages in down Wind direction of the mine site
2. Meteorological data Mine site
3. Noise Level
Monitoring
Mine Boundary, High noise generating areas within the Mine
boundary
4. Water Level & Quality Surface & Ground water sources (Study area)
5. Socio–economic
status
Study area (on yearly basis)
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 192 Prepared by J.M EnviroNet Pvt. Ltd.
6.3.5 DATA ANALYSIS
Monitoring data analysis will be done by MoEFCC approved laboratory and as per CPCB
guidelines & will be submitted to concerned authority (specified in Environment Clearance
Letter issued by MoEFCC & Consent issued by CPCB) on regular basis.
6.4 DETAILED BUDGET-
The budget proposed for this Limestone Mining Project is as follows:
Capital Cost of the Project: Rs. 5.0 Crore/-
Capital Cost for EMP: Rs. 0.50 Crore/-
Recurring Cost for EMP: Rs 0.10 Crore per annum/-
Table - 6.4
EMP Cost Breakup (in Lac)
S.
No Particulars
Capital cost Annual recurring cost
Proposed Proposed
1. Pollution Control
(Separately provide break-up) 33.0 5.0
2. Pollution Monitoring
(Separately provide break-up) - 1.0
3. Occupational Health 5.0 2.0
4. Green Belt/Mine/Township 12.0 1.0
5. Reclamation / Rehabilitation of mined out area - 1.0
6. Others (specify) - -
Total 50.0 10.0
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area-
18.03.88 ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 193 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER–VII
ADDITIONAL STUDIES
7.0 INTRODUCTION
As per EIA Notification dated 14th September, 2006 as amended on time to time, MoEFCC,
New Delhi has suggested Terms of References (ToRs) for the preparation of the
Environmental Impact Assessment (EIA) Report and Environmental Management Plan (EMP)
vide their letter no. J-11015/240/2016-IA.II (M) dated 9th January, 2018.
The following Additional Studies were carried out in reference to the additional Terms of
References:
1. Public Consultation
2. Hydro-geological Study & Rain Water Harvesting Plan
3. Risk Assessment & Disaster Management Plan
7.1 PUBLIC CONSULTATION
Public hearing is yet to be conducted for the Pachhhtardi limestone mining project.
7.2 HYDRO-GEOLOGICAL STUDY & RAINWATER HARVESTING PLAN
Detailed Hydro- Geological Study and rainwater harvesting Report has been prepared and
copy of the same is enclosed as Annexure VIII.
7.3 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN
7.3.1 DEFINITION
A major emergency in a work is one which has the potential to cause serious injury or loss of
life. It may cause extensive damage to property and serious disruption both inside and
outside the work. It would normally require the assistance of emergency services to handle it
effectively.
7.3.2 SCOPE
An important element of mitigation is emergency planning i.e. recognizing that accidents are
possible, assessing the consequences of such accidents and deciding on the emergency
procedures, both on site and off site that needs to be implemented in the event of an
emergency.
Emergency planning is just one aspect of safety and cannot be considered in isolation.
7.3.3 OBJECTIVE
The objective of onsite disaster management plan for the captive mine is to be in a state of
perpetual readiness through training and development to immediately control and arrest any
emergency situation so as to avert a full fledged disaster and the consequence of human and
property damage and in the event of a disaster still occurring, to manage the same so that
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area-
18.03.88 ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 194 Prepared by J.M EnviroNet Pvt. Ltd.
the risk of the damage to life and property is minimized. SDCCL will make Emergency
Preparedness & Responses. The overall objectives of the emergency plan are:
(a) To localize the emergency and, if possible eliminate it; and
(b) To minimize the effect of the accident on people and property.
(c) Elimination of hazards by local/supervisory personnel and minimizing effects include
rendering first aid, evacuation, hospitalization, rehabilitation
(d) To seek help from outside sources, if required
(e) Notice/information to authorities
7.3.4 IDENTIFICATION OF HAZARDS
The possibility of the following may be there for such projects:
(a) Inundation of pit during excessive rains.
(b) Falling of the persons in the pit.
(c) Accidents due to machinery.
7.3.5 DISASTER MANAGEMENT
For the systematic working of open cast mine, benching will be made. During any of the
above hazards, the incharge on duty will immediately inform the mines manger and
remove all the persons from the disaster site.
The mines manager will make the arrangements to deal with disaster.
If the disaster is of higher magnitude, he will inform the same to Police, District Collector,
DGMS and IBM. The following arrangements will be made at the mine.
a. Availability of high capacity pumps, firefighting equipment, ambulances etc.
b. Formation of team to deal with the hazards.
c. Arrangements for removal of employed persons from disaster site.
d. Display of Telephone Nos. of District Collector, Police and Hospital and contacting
them, if required.
7.3.6 PRECAUTIONS
To avoid all these disasters at working place and to minimize their effects following
precautions shall be taken and arrangement shall be made at the working place.
(i) Periodical maintenance of mine machineries.
(ii) The persons shall be trained properly to handle the situation.
(iii) Detailed warning system, implementation procedure, emergency control centre shall
be maintained at the mine with names of trained persons.
(iv) Details and availability of heavy machinery, fire-fighting equipment shall be available at
the site.
(v) Proper arrangements shall be made for treatment of injured person, if any.
(vi) All the safety equipment shall be available at the mine.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area-
18.03.88 ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 195 Prepared by J.M EnviroNet Pvt. Ltd.
7.3.7 POST DISASTER ANALYSIS AND EVALUATION
When the emergency is over, the team will carry out a detailed analysis of cause of
accident/occurrence, evaluate the influence of various factors and find out the procedures to
minimize them in future. At the same time adequacy of disaster management plan will be
evaluated and shortcomings will be rectified to improve the plan.
7.3.8 OFF-SITE EMERGENCY PLANNING
7.3.8.1 INTRODUCTION
The off-site emergency plan is an integral part of any hazard control system. It would be
based on those accidents identified by the works management, which could affect people
and the environment outside the works. Thus, the off-site plan follows logically from the
analysis that took place to provide the basis for the on-site plan and the two plans should,
therefore, complement each other. The key feature of a good off-site emergency plan is
flexibility in its application to emergencies other than those specifically included in the
formation of the plan. The roles of the various parties that may be involved in the
implementation of an off-site plan are described below. The responsibility for the off-site plan
will be likely to rest either with the works management or with the local authority.
Either way, the plan must identify an emergency coordinating officer who would take overall
command of the off-site activities. As with the on-site plan, an emergency control center will
be required within which the emergency coordinating officer can operate. An early decision
will be required in many cases on the advice to be given to people living “within range” of the
accident –in particular whether they should be evacuated or told to go indoors. Consideration
of evacuation may include the following factors:
a. In the case of a major fire but without explosion risk (e.g. an oil storage tank), only
persons close to the fire are likely to need evacuation, although a severe smoke hazard
may require this to be reviewed periodically.
b. But if the fire escalates it might be necessary to evacuate people nearby, but only if there
is time; if insufficient time exists, people would be advised to stay indoors and shield
themselves from the fire while measures are taken by those outside to deal with it.
7.3.8.2 ASPECTS TO BE INCLUDED IN AN OFF-SITE EMERGENCY PLAN
Some of the aspects to be included in off-site emergency plan are as follows:
1. Organization
Details of command structure, warning systems, implementation procedures, emergency
control centers, name and appointments of incident controller, site main controller, their
deputies and other key personnel.
2. Special Emergency Equipment
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area-
18.03.88 ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 196 Prepared by J.M EnviroNet Pvt. Ltd.
Details of availability and location of heavy lifting gear, bulldozers, specified fire-fighting
equipment, fireboats.
3. Voluntary Organizations
Details of organizers, telephone numbers, resources, etc.
4. Meteorological information
Arrangements for obtaining details of weather conditions prevailing at the time and
weather forecasts will be made.
5. Humanitarian Arrangements
Transport, evacuation centers, emergency feeding, treatment of injured, first aid,
ambulances, temporary mortuaries.
6. Public Information
Arrangements for: -
(i) Dealing with the media-press office
(ii) Informing relatives, etc.
7. Assessment
Arrangements for: -
(i) Collecting information on the causes of the emergency
(ii) Reviewing the efficiency and effectiveness of all aspects of the emergency plan.
7.3.8.3 ROLE OF THE EMERGENCY COORDINATING OFFICER
The various emergency services will be coordinated by an Emergency Coordinating Officer
(ECO) who is likely to be a senior police officer but, depending on the circumstances, could be
a senior fire officer. The ECO will liaise closely with the site main controller. Again depending
on local arrangements, for very severe incidents with major or prolonged off-site
consequences, the external control may pass to a senior local authority administrator or even
an administrator appointed by the Central or State Government.
7.3.8.4 ROLES OF MAJOR HAZARD MANAGEMENTS
Where the local authority has the organization to formulate the plan, the role of
management in off-site emergency planning will be to establish liaison with those preparing
the plans and to provide information appropriate to such plans. This will include a description
of possible on-site accidents with potential for off-site harm, together with their
consequences and an indication of the relative likelihood of the accidents.
Advice should be provided by the Mine Management to all the outside organizations which
may become involved in handling the emergency off-site and which will need previously to
have familiarized themselves with some of the technical aspects of the works activities, e.g.
emergency services, medical departments, etc.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area-
18.03.88 ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 197 Prepared by J.M EnviroNet Pvt. Ltd.
7.3.8.5 ROLE OF THE LOCAL AUTHORITY
In some places the duty to prepare the off-site plan lies with the local authorities. They may
have appointed an emergency planning officer (EPO) to carry out all this duty as part of the
EPO’s roles in preparing for a whole range of different emergencies within the local authority
area. The EPO will need to obtain the information to provide the basis for the plan.
Rehearsals for off-site plans are important for the same reasons as on-site plans and will need
to be organized by the EPO.
7.3.8.6 ROLE OF THE POLICE
The police normally assume the overall control of an emergency, with a senior officer
designated as emergency coordinating officer.
Formal duties of the police during an emergency include protecting life and property and
controlling traffic movements.
The functions include controlling bystanders, evacuating the public, identifying the dead and
dealing with casualties and informing relatives of dead or injured.
7.3.8.7 ROLE OF THE FIRE AUTHORITIES
The control of a fire is normally the responsibility of the senior fire brigade officer who would
take over the handling of the fire from the site incident controller on arrival at the site. The
senior fire brigade officer may also have a similar responsibility for other events. Fire
authorities having major hazard works in their area should have familiarized themselves with
the location on site of all stores of flammable materials, water and foam supply points and
fire-fighting equipment.
7.3.8.8 ROLE OF THE HEALTH AUTHORITIES
Health authorities, including doctors, surgeons, hospitals, ambulances and so on, have a vital
part to play following a major accident and they should form an integral part of any
emergency plan.
For major fires, injuries will be the result of the effects of thermal radiation to a varying
degree and the knowledge and experience to handle this in all, but extreme cases may be
generally available in most hospitals.
7.3.8.9 ROLES OF THE GOVERNMENT SAFETY AUTHORITY
The Inspectors of Director General of Mines Safety may want to satisfy themselves that the
organization responsible for including the off-site plan has made adequate arrangements for
handling emergencies of all types including major emergencies.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 198 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER–VIII
PROJECT BENEFITS
8.1 INTRODUCTION
Shree Digvijay Cement Company Limited (SDCCL) has proposed a Pachhtardi Limestone Mine
(M.L. Area 18.03.88 ha) with Production capacity of 0.35 Million TPA at Survey No 78, Village-
Pachhtardi, Taluka- Bhanvad, Dist.- Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat).
The company is conscious of its obligations to society at large. The company will contribute in
overall socio economic development of the area.
SDCCL believes holistic socioeconomic development of the local community is the need of
the hour. It truly believes that a company’s prosperity is linked with that of its neighboring
communities.
As per ToR Point no. 43, benefits of the project clearly indicating the environmental, social,
economic, employment potential etc are to be spelt out.
8.2 ENVIRONMENTAL BENEFITS: Proposed project will be beneficial for environment in following
ways:
At the conceptual stage, total excavated area will be 13.8690 ha which will be converted
into water reservoir. The development of water reservoir will increase the availability of
surface water in the area. Water stored in reservoirs can also be used by the villagers for
other purposes like agriculture etc.
Out of total area, about 2.0150 ha area will be covered by Greenbelt which will increase
bio diversity and green belt in the area.
Hence conceptual land use will present a better land use of the Area.
8.3 SOCIAL BENEFITS:
Proposed project will result in growth of the surrounding areas by increased direct and
indirect employment opportunities in the region including ancillary development and
supporting infrastructure. Besides this, Royalty and other taxes would be additional benefit
and it will be utilized by local administration for the development of socio-economic
infrastructure and well being of the local population. The various activities proposed through
CER (Corporate Environment Responsibility) would help in upgradation of basic
infrastructure, amenities.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 199 Prepared by J.M EnviroNet Pvt. Ltd.
8.4 EMPLOYMENT BENEFITS
The project will have positive direct and indirect employment. Manpower is required for
mining operations and other mining related activities such as transportation, day to day
operations etc. Further, additional employment opportunities will be generated.
The total manpower required for the proposed mining project will be around 73 persons.
Preference will be given to the local people for employment based on their qualification and
eligibility in the mines.
8.5 ECONOMIC BENEFITS
The proposed project will contribute additional revenue to the State and Central Govt. in the
form of royalty, cess and other taxes etc.
TABLE – 8.1
Economic Benefits of the Project (in 50 years mining lease period)
S.NO. DESCRIPTION Rs (Cr)
1. Royalty @ Rs 80/- Per Ton (Present / prevailing Rate) 2.80
2. District Mineral Foundation @ 10% of the Royalty 0.28
3. National Mineral Exploration Trust@ 2% of the Royalty 0.056
4. Environment Cess 0.00
5. Development Cess 0.00
Total 3.316
Revenue generation per year (@ 0.35 Million TPA)
8.6 CORPORATE ENVIRONEMNT RESPONSIBILITY (CER)
The proposed project will help in improving the socio-economic status of the near-by villages
by generating direct or indirect employment opportunities. The project will also induce the
development of ancillary and related small-scale industries in the adjoining areas.
The project will contribute additional revenue to the State and Central Govt. in the form of
royalty, cess and other taxes etc. Job opportunities to the local people will improve the
earning and spending capacity of the people. The people in area will be able to utilize
improved facilities with regard to education, health care, hygiene, recreational opportunities,
small business opportunities etc.
The Company has allocated Rs 10.0 Lacs towards CER activities for the proposed mining
project as per MoEFCC OM No 22-65/2017-IA.II (M) dated 1st May, 2018.
8.7 CONCLUSION
The project activity and the management will provide assistance for the development of
public amenities in the region.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 200 Prepared by J.M EnviroNet Pvt. Ltd.
The mine management will recruit semi-skilled & unskilled eligible workers from the nearby
villages depending upon requirement in the mines and the eligibility, qualification and
experience of local persons.
The overall effect will result in higher standard of living viz. better education, improved health
and sanitation facilities, housing and acquisition of consumer durables. Housing, transport,
medical, educational and other civic amenities will get improved in the future. This is
envisaged as a major positive benefit.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar)(Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 201 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER–IX
ENVIRONMENTAL COST BENEFIT ANALYSIS
9.1 ENVIRONMENTAL COST BENEFIT ANALYSIS
As per EIA Notification dated 14th Sept., 2006, the Chapter on the ‘Environmental Cost Benefit
Analysis’ is applicable only if the same is recommended at the Scoping stage.
As per the ToR points issued by MoEFCC, New Delhi vide letter no. J-11015/240/2016-IA.II (M)
dated 9th January, 2018 for the mining project activity, the ‘Environmental Cost Benefit
Analysis’ is not required.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 202 Preparedby J.M EnviroNet Pvt. Ltd.
CHAPTER – X
ENVIRONMENTAL MANAGEMENT PLAN
10.1 INTRODUCTION
The environmental management plan (EMP) is required to minimize adverse environmental
impacts by implementing suggested mitigation measures with timelines and responsibilities
during the project life cycle. An environmental management system (EMS) is a dynamic,
continuous process initiated by management and involving communication between the
client, its workers, and the local communities directly affected by the project. Drawing on the
elements of the established business management process of “plan, implement, check and
Act (Management review)” the system entails the thorough assessment of potential
environmental, social impacts and risks from the projects. EMS provides order and
consistency for mitigating and managing these on an ongoing basis.
10.2 ELEMENTS OF EMP
EMP includes four major elements: -
1. Planning: This includes identification of environmental impacts, legal requirement,
commitments and policies, setting environmental objectives and environment, health,
safety and social compliance requirements;
2. Implementation: This comprises of resources available for the project, accountability of
employees , contractors and documentation of measures to be taken ;
3. Checking: Measurement & Evaluation: This includes regular inspection, audits, monitoring
corrective actions and record keeping ; and
4. Management Review: Actions are taken to continually improve the environment, health,
safety, and social performance of the organization.
The following Policy & programs have been developed to ensure proper implementation of
EMP for the proposed mining project:
Formulating Corporate Environment Policy (CEP)
Formation of Environment Management Cell (EMC)
Greenbelt Development /plantation programme
Occupational Health and Safety
Budgeting of Environmental mitigation measures
10.3 CORPORATE ENVIRONMENT POLICY
Corporate Environment Policy (CEP) has been formulated and adopted by the Board of
Directors of Shree Digvijay Cement Company Ltd. to provide a framework to become an
environmentally sustainable company. The hierarchical system or administrative order of the
company to deal with the environmental issues and for ensuring compliance with the EC
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 203 Preparedby J.M EnviroNet Pvt. Ltd.
conditions etc. has been given in the Environmental Policy of the company. Copy of CEP has
been given in this Draft EIA/EMP report as Annexure II.
10.4 FORMATION OF ENVIRONMENTAL MANAGEMENT CELL (EMC)
In order to maintain the environmental quality within the standards, regular inspections,
audits & monitoring of various environmental components is necessary. Environmental
Management Cell (EMC) of Shree Digvijay Cement Company Ltd. (SDCCL) will carry
environmental monitoring and control. The EMC team will be responsible for pollution
monitoring aspects and implementation of control measures as discussed in Chapter II & IV of
this Draft EIA/EMP Report.
A group of qualified and efficient engineers with technicians will be deputed for
maintenance, up keeping and monitoring the pollution control equipment, to keep them in
working mode at the best of their efficiencies. The Organizational structure of EMC is given
below:
Figure no. 10.1 (Structure of EMC)
10.4.1 RESPONSIBILITIES OF EMC
The responsibilities of the EMC include the following:
Environmental monitoring.
Procurement and commissioning of Pollution Control and Monitoring Equipment
Specification and regulation of maintenance schedules for pollution control equipment.
Ensuring that prescribed standards are maintained.
Ensuring optimum water usage.
Implementation of the mitigation measures suggested in EIA/EMP Report.
Ensuring development of greenbelt development & its maintenance.
GM (Mines)
Mines Manager Manager (Safety & Environment)
Resident Geologist Mining Engineer
Mines Foreman
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 204 Preparedby J.M EnviroNet Pvt. Ltd.
10.5 GREENBELT DEVELOPMENT & PLANTATION PROGRAMME
Greenbelt development programme has been designed for preventing the soil erosion,
improving the greenery and aesthetic beauty of the area. While selection of species, care is
being taken so as the developed forest will remain useful for habitations. About 2.0150 ha
area will be under greenbelt at the conceptual stage.
Greenbelt development and plantation is necessary:
1. To check soil erosion
2. Landscaping and providing shelter
3. Improvement in aesthetic environment of site
4. Air purification by generation of oxygen and allowing PM to settle on the leaves.
5. To attenuate noise generated by movement of vehicles and other machinery.
10.5.1 GENERAL GUIDELINES FOR GREEN BELT DEVELOPMENT
i. Trees growing up to 5 m or more in height is being planted around the installation.
ii. Plantation of trees is being done along road side and mine office.
iii. Trees are being planted along roadsides, to arrest auto-exhaust and noise pollution, and
in such a way that there is no direct line of sight to the mine when viewed from a point
outside the foliage perimeter.
iv. Since tree trunks are normally devoid of foliage (upto 3 m), it is appropriate to have
shrubbery in form of such trees to give coverage to trunk portion of these trees.
v. Fast growing trees with thick perennial foliage will be grown, as it takes many years for
trees to grow to their full height.
SDCCL will raise greenbelt all along the lease periphery etc.
The following characteristics have been taken into consideration while selecting plant species
for green belt development and tree plantation.
I. Local, indigenous and drought resistant species.
II. Fast growing and tall trees.
III. Perennial and evergreen.
IV. Thick canopy cover.
V. Trees are selected so as to maintain regional ecological balance and conform to soil and
hydrological conditions.
VI. Plantation will be done as per guidelines.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 205 Preparedby J.M EnviroNet Pvt. Ltd.
10.5.2 PLANTATION PROGRAMME
Table- 10.1
Phase wise Plan of greenbelt development (On Lease Boundary)
Year Un-worked Area Plant species
Area (ha) No. of trees
1st Year 1.0000 2000 Mango (Mangifera indica), Jamun (Syzygium cumini), Khair (Acacia
catechu), Kaner (Nerium indicum), Gum arabic tree (Acacia
Senegal), Sitaphal (Annona Squamosa), Gugal (Commiphora
wightii), Shatut (Morus alba), Neem (Azadirachta indica), Pipal
(Ficus religiosa)
or
As suggested by Local Social Forestry Deptt.
2nd year 1.0150 2030
Total 2.0150 4030
Reference: Approved Mining Plan with Progressive Mine Closure Plan
At the end of the life of mine, out of total area i.e. 18.03.88 ha, about 2.0150 ha area will
be covered by Green belt on 7.5 m lease periphery.
Greenbelt on 7.5 m lease periphery will be done @2000 saplings per ha of land.
About Rs. 8.06 lacs have been earmarked for greenbelt @ Rs. 200 /sapling (including Rs.
80/- plantation cost + Rs. 30/- *3 maintenance cost for three years). The budget includes
the cost of Saplings, Watering facilities, Labour Charge, Organic manure, Bio-fertilizers,
Maintenance etc.
Map showing greenbelt on 7.5 m lease boundary is given below:
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 206 Preparedby J.M EnviroNet Pvt. Ltd.
10.5.3 SPECIES SELECTION FOR GREEN BELT DEVELOPMENT
The plants and saplings suitable for the existing soil and site conditions will be considered.
Preference will be given for fast growing local plant species, which can adapt to the local
climate.
Some fruit bearing & native Species proposed for greenbelt development are Mango
(Mangifera indica), Jamun (Syzygium cumini), Khair (Acacia catechu), Kaner (Nerium indicum),
Gum arabic tree (Acacia Senegal), Sitaphal (Annona Squamosa), Gugal (Commiphora wightii),
Shatut (Morus alba), Neem (Azadirachta indica), Pipal (Ficus religiosa) in consultation with
local Forest Dept. & as per guidelines.
10.6 OCCUPATIONAL HEALTH & SAFETY
Occupational health and safety (OHS) is a multidisciplinary field concerned with the safety,
health and welfare of people at work. The goal of occupational safety and health programs
includes fostering a safe and healthy work environment. OHS may also protect co-workers,
family members, employers, customers, and many others who might be affected by the
workplace environment.
Occupational Health & Safety is based on the following three aspects:-
• Hazard identification
• Risk assessment
• Determination of applicable controls
A Hazard Identification and Risk (HIRA) Analysis is a systematic way to identify and analyze
hazards to determine their scope, impact and the vulnerability of the built environment to
such hazards and its purpose is to ensure that there is a formal process for hazard
identification, risk assessment and control to effectively manage hazards that may occur
within the workplaces. Details regarding occupational health hazards as well as mitigation
measures have been discussed in Chapter IV of this Draft EIA/EMP Report.
In order to ensure adequate implementation of the OHS measures suggested, Shree Digviajy
Cement Company Ltd. will adhere to the pre placement & periodical medical examination
program. Details of the same are given as under:
10.6.1 PRE PLACEMENT & PERIODICAL MEDICAL EXAMINATION SCHEDULE
Ideally, the pre-employment medical examination (also referred to as a pre-placement
examination) strives to place and maintain employees in an occupational environment
adapted to their physiological and psychological capacities. The goal of the pre-employment
examination is to determine whether an individual is fit to perform his or her job without risk
to himself or others. This is also conceptualized within the practice of occupational medicine
– it is assumed that the examiner is required to have detailed knowledge of both working and
health conditions.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 207 Preparedby J.M EnviroNet Pvt. Ltd.
Parameters to be monitored:
The fresh employees when taken are thoroughly medically examined under initial medical
examination and thereafter during continuation of employment; the periodic medical
examination is being done suggested by DGMS. The medical examination includes the
following parameters -
Height, weight, body mass index (BMI)
Cardiovascular examination (heart check, blood pressure, pulse)
Full musculoskeletal examination including comprehensive range of movement
Central nervous system examination
Examination for hernias and other abdominal abnormalities
Urinalysis for diabetes or kidney / bladder disorders
Respiratory examination
Vision assessment including color blindness
Fitness to work medicals
Drivers Medicals
Instant testing for drugs and Alcohol
Spirometry - (Lung Function Test)
Audiometry (Hearing Test)
Vision tests, color vision
ECG
CXR (Chest Radiograph)
Blood glucose
The medical records of the employees will be maintained. Under initial vocational training,
the workers will be given training related to all safety and health aspects pertaining to their
vocation and thereafter, special training courses/ awareness programme for Malaria
eradication, STDs and health effects on exposure to mineral dust will be organized regularly
for employed persons as well as for nearby villagers.
Frequency of Medical Examination
a. Pre Placement Medical examination: Prior to joining
b. Periodical Medical examination:
• Age of workers < 45 years: After every 5 years
• Age of workers > 45 years: After every 3 years
Budget for implementation of Occupational Health & safety measures & medical examination
has been given in table no. 10.1 of this chapter.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Surevy No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 208 Preparedby J.M EnviroNet Pvt. Ltd.
10.7 DETAILED BUDGET FOR EMP
The budget proposed for implementation of the pollution control & impact mitigation
measures as suggested for this Limestone Mining Project is given as under:
Capital cost of the project: Rs. 5.0 crore/-
Capital cost for EMP: Rs. 0.50 crore/-
Recurring cost for EMP: Rs 0.10 Crores per annum/
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 209 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER–XI
SUMMARY & CONCLUSION
11.1 INTRODUCTION
Shree Digvijay Cement Company Limited (SDCCL) has proposed a Limestone Mining Project
with Production Capacity of 0.35 Million TPA located at Village: Pachhtardi, Taluka: Bhanvad,
District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat).
As per EIA Notification dated September 14, 2006, as amended from time to time; the project
falls under Category “A”, Project or Activity ‘1(a) - 5, as general condition applicable due to
proximity of Barda Wildlife Sanctuary from the mine site.
11.2 JUSTIFICATION FOR THE PROJECT
SDCCL has an existing cement plant having production capacity of 1.20 Million TPA Cement
located at Digvijaygram (Sikka), District- Jamnagar, Gujarat.
Presently limestone requirement of the existing Cement Plant is met by its Gop, Chorbedi
& Pachhtar Limestone Mines.
Due to scarcity of reserves in its captive Mines, limestone is also being procured through
‘mines of third parties’ Mines in the vicinity.
To fully meet the limestone requirement of the integrated cement plant, SDDCL has
proposed Pachhtardi Limestone Mine (Area- 18.03.88 ha), Production Capacity 0.35 million
TPA (ROM) Near Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka
(Erstwhile Jamnagar) (Gujarat).
Mining being site specific, the project cannot be located at any other place. The area has been
explored and total mineral reserves are calculated as 5.40 Million tonnes out of which the
present extractable/ mineable reserves are calculated as 4.02 Million Tonnes. Mining activities
will be done in a systematic manner with appropriate pollution prevention / abatement
measures in practice to ensure clean and green environment.
Development of green belt as dust preventive barrier all along the 7.5 m lease periphery.
Barda Wildlife Sanctuary is about ~1.5 km and ESZ of Barda Wildlife Sanctuary is about
~1.18 km from mine site.
The project will generate direct & indirect employment opportunities in the mine.
Preference will be given to the local people based on their skill and educational
qualification.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 210 Prepared by J.M EnviroNet Pvt. Ltd.
11.3 PROJECT DETAILS
TABLE: 11.1
Project Details
S.NO. PARTICULARS DETAILS
A. Nature of the Project Proposed Limestone Mine
B. Size of the Project
1. Area 18.03.88 ha (Govt Waste land)
2. Proposed Production capacity 0.35 Million TPA
C. Location Details
1. Survey No 78
2. Village Pachhtardi
3. Taluka Bhanvad
4. District Devbhumi Dwarka (Erstwhile Jamnagar)
5. State Gujarat
6. Latitude 21° 51' 16.39"N to 21° 51' 38.11"N
7. Longitude 69° 40' 58.74"E to 69° 41' 33.83"E
8. Survey of India Toposheet no. Restricted (Restricted for being close to National boundary)
D. Environmental Setting Details (with approx. aerial distance & direction from the mining lease
boundary)
1. Nearest Highway SH-95 (Adjacent to the Mine Site)
SH-27 (~9.0 Km in ENE direction)
2. Nearest Railway Station Bhanvad (~12.0 Km in NE direction)
3. Nearest Airport Porbandar Airport, Gujarat (~26.0 km in SSW direction)
4. Nearest Habitation Village Pachhtar (Adjacent in West Direction)
5. National Park, Wild Life
Sanctuaries, Biosphere Reserves,
Wildlife corridors, Tiger/Elephant
Reserves etc. within 10 km radius
study area
• Barda Wild life Sanctuary (~1.5 km from mine site)
• ESZ of Barda Wild life Sanctuary (~1.18 km from mine site)
6. Reserve/Protected Forest within 10
km radius study area
SOI Toposheet not available due to closeness of National
Boundary.
Location of any Reserved/Protected Forests will be obtained
from Forest Department
7. Water Bodies within 10 km radius • One seasonal nallah adjacent to the lease area
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 211 Prepared by J.M EnviroNet Pvt. Ltd.
S.NO. PARTICULARS DETAILS
of the mine site • Vartu River (~5.0 km in NNW direction)
• Vartu Dam (~7.0 km in NNE direction)
8. Seismic Zone Zone – III as per IS: 1893 (Part-I) : 2002
9. Aravalli range within 10 km radius
of the study area
None
10. CRZ within 10 km radius of the
study area
None
Source: Site Visit & Pre- Feasibility Report
11.4 MINING DETAILS
TABLE: 11.2
MINING DETAILS
S. No. Particulars Details
1. Method of mining Opencast Mechanized mining without Drilling & Blasting
2. Total Geological Reserves 5400000 Tonnes
3. Total Mineable reserves 4018680 Tonnes
4. Proposed Life of the Mine ~12 years
5. Bench Height 7.5 m
6. Bench Width 7.5 m
7. Overall Pit Slope 50°
8. Elevation Range 80 m AMSL to 102 m AMSL
9. General Ground Level 92 m AMSL
10. Water Table 67 to 72 m AMSL (20 to 25 m bgl)
11. Ultimate Working Depth 77 m AMSL (15 mbgl)
12. Number of Working Days 300 Days
13. Number of shifts per day 2 Shifts
Source: Approved Mining Plan & Progressive Mine Closure Plan
11.5 MITIGATION MEASURES
11.5.1 AIR POLLUTION CONTROL MEASURES
Following measures will be taken to control air/fugitive pollution during mining operation.
Drilling & blasting will not be carried out in the Mine.
Haul roads & loading area will be regularly sprayed with water to arrest dust from being
air- borne.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 212 Prepared by J.M EnviroNet Pvt. Ltd.
Proper maintenance (preventive as well as scheduled maintenance) of vehicles will be
carried out regularly for minimization of generation of gaseous pollutants.
No overloading of material will be done during transportation.
Personal Protective Equipments (PPEs) such as dust masks will be provided to employees
working in dust prone areas.
Greenbelt along the Mining Lease periphery will be developed.
Periodical air quality monitoring will be carried out.
11.5.2 WATER QUALITY MANAGEMENT
There will be no waste water generation during mining process.
Domestic wastewater generated from mines office will be disposed off in soak pit via
septic tank.
Disposal of waste water from workshop (if any) will be treated by oil-water separator
before its use for dust suppression.
Periodical Ground water level & quality monitoring will be carried out.
11.5.3 NOISE POLLUTION CONTROL
No drilling & blasting will be carried out in the Mine area.
All the HEMMs will be equipped with acoustic cabins for operators.
In order to reduce the effect of noise pollution, personal protective equipments like ear
plugs, ear muffs will be provided to workers exposed to high noise levels.
Scheduled & preventive maintenance of all the machinery will be carried out regularly.
Green belt will be developed around periphery of the mining lease to attenuate noise
level.
Regular monitoring of ambient noise level will be carried out.
11.5.4 GREEN BELT DEVELOPMENT/ PLANTATION
At the end of the life of mine out of total area i.e. 18.03.88 ha, about 2.0150 ha area will
be covered by Green belt along 7.5 m lease periphery.
Some fruit bearing & native Species proposed for greenbelt development are Mango
(Mangifera indica), Jamun (Syzygium cumini), Khair (Acacia catechu), Kaner (Nerium
indicum), Gum arabic tree (Acacia Senegal), Sitaphal (Annona Squamosa), Gugal
(Commiphora wightii), Shatut (Morus alba), Neem (Azadirachta indica), Pipal (Ficus
religiosa) in consultation with local Forest Dept. & as per guidelines.
The trees will be planted @ 2000 saplings per ha of land.
11.5.5 RECLAMATION PLAN FOR LAND USE
At the conceptual stage, total excavated area will be 13.8690 ha which will be converted
into water reservoir.
Green belt will be developed along the 7.5 m lease periphery on 2.0150 ha area
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of Limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 213 Prepared by J.M EnviroNet Pvt. Ltd.
11.6 PROJECT BENEFITS
The project activity will help in meeting the growing demand of cement & hence help in the
economic growth of the country. It will be helpful in the development of basic needs of the
local area like education, Health & family welfare, women empowerment, Natural resource
management, water conservation, roads etc. It will result in growth of the surrounding areas
by increasing direct and indirect employment opportunities in the region including ancillary
development and supporting infrastructure.
11.7 CONCLUSION
The limestone Mine project will prove beneficial to the local people as direct and indirect
employment opportunity will be generated. There will be increase in revenue generation to
the government by way of royalty, excise and government taxes etc. Further improvement in
infrastructure will take place like education, roads, availability of drinking water, medical
facilities in adjacent villages.
There will be no significant pollution of air, water, soil and noise. Regular monitoring of all the
components of environment will be done. Increased social welfare measures taken by the
company will bring development in the near-by villages.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 214 Prepared by J.M EnviroNet Pvt. Ltd.
CHAPTER-XII
DISCLOSURE OF CONSULTANTS ENGAGED
12.0 DISCLOSURE OF CONSULTANTS ENGAGED
J.M. EnviroNet Pvt. Ltd. (JMEPL), one of the companies of JM Group, was established in the
year 1993. ‘JM’ in the name of the Company is derived from the name of ‘Lord Shiva’ - the
Temple of ‘Jharkhand Mahadev’ (JM). The Temple is located at Queens Road, Vaishali Nagar,
Jaipur.
The Registered office of JMEPL is at 7-CH-10, Jawahar Nagar, Jaipur. Its Delhi-NCR Corporate
office is at 202, ABW Tower, Gurgaon (Haryana).
J.M. EnviroNet Pvt. Ltd. is accredited with ISO-9001: 2008 for EIA Division. EIA Division is also
approved by National Accreditation Board for Education & Training (NABET) formerly NRBPT
(Quality Council of India), Certificate no. NABET/EIA/1619/RA 0069 dated 16th August, 2017.
The EIA consultancy organisation of JMEPL is approved by NABET/QCI and is listed at s.no. 90
of Accredited EIA Consultant Organizations (ACOs) - as on August 06th, 2018 displayed on web
site of MoEFCC. NABET-QCI certificate for accreditated consultant is enclosed as Annexure XI
with this Draft EIA/EMP Report.
JMEPL is offering Environmental Consultancy Services in various sectors viz Industrial
Projects / Chemical Industries / Cement Plants / Thermal Power Plants / Mining Projects/ Coal
Washery Projects/ Real Estate Projects / Distilleries / Steel Plants/Chemical Fertilizers/Mineral
Beneficiation plants etc.
In the Mining sector, JMEPL have covered mines of minerals viz. Limestone, Bauxite,
Chromite, Coal, Zinc Ore, Copper ore, Gypsum, Soapstone, Iron & Manganese ore, Clay, Silica
Sand, Marble, Khanda, Gitti, boulders, Feldspar, Quartz, lignite, magnesite and other minor
minerals etc.
JMEPL has a highly qualified team of Subject Experts. As Faculty Heads of the EIA Division, we
have Retd. General Managers of the Reputed Cement Companies, Ex-Head EIA Division of big
Business Group, STP & ETP Designing Experts, Retd. Mining & Geology Experts with vast
experience in their respective fields.
JM Group’s business is spread over 22 States viz.:- Andhra Pradesh, Kerala, Gujarat,
Maharashtra, Orissa, Tamil Nadu, Goa, Jammu & Kashmir, Himachal Pradesh, Punjab,
Haryana, Delhi, Rajasthan, Uttar Pradesh, Madhya Pradesh, Chhattisgarh, Assam, West
Bengal, Karnataka, Jharkhand, Bihar & Uttarakhand.
The JM Group has its own Environmental Laboratory at Gurgaon (Haryana) approved under
EPA (Environment Protection Act) by the Ministry of Environment & Forests, Govt. of India,
New Delhi.
Besides this, its MoEF approved Environmental Laboratory of JM Group is also providing
Analytical Laboratory Services of various elements and environmental parameters.
Draft Environment Impact Assessment Report of Shree Digvijay Cement Company Ltd. For Proposed Pachhtardi Limestone Mine (Area- 18.03.88
ha) with Production Capacity of limestone 0.35 Million TPA
At Survey No 78, Village: Pachhtardi, Taluka: Bhanvad, District: Devbhumi Dwarka (Erstwhile Jamnagar) (Gujarat)
Draft EIA/EMP Report
Shree Digvijay Cement Company Ltd. 215 Prepared by J.M EnviroNet Pvt. Ltd.
Annual monitoring as per MoEF / CPCB / SPCB guidelines, Risk Assessment and Disaster
Management Plan, Rain Water Harvesting Plan, Detailed Hydro-geological Study, Preparation
of Environmental Statement Reports (Environmental Clearance Compliance Conditions) etc.
are amongst the various other consultancy services offered by the Company.