Government Of India
Executive Summary
Power Sector
February-16
Ministry of Power
Central Electricity Authority
New Delhi
SN Section A - Highlights of Power Sector Page
1 Electricity Generation for February 2016 (BU) 1
2 Generating Capacity Addition for February 2016 (MW) 2
3 List of Projects Commissioned in February 2016 3
4 All India Installed Capacity (MW) Region-wise as on 29022016 3
5 All India Installed Capacity (MW) Sector-wise as on 29022016 4
6 Transmission Lines Added during February 2016 (Ckms) 5
7 Transformation Capacity Addition during February 2016 (MVA) 6
8 Power Supply Position (Energy amp Peak) in February 2016 7
9 Peak Shortage of Power Supply (MW) in Different Regions 8-9
10 All India PLF Sector-wise for February 2016 10
11 T amp D and AT amp C Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
13 Average cost of Power amp Average Realisation
14 All India per capita consumption of Electricity (KWh)
15 All India Coal consumption for Power Generation (MT)
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during February 2016 and April 2015 to February 2016 13
3 Installed Capacity in various Regions including their shares 14-19
1 Programme and Achievements of Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
2 List of Transmission Lines CommissionedReady for commissioning during February 2016
1 Programme and Achievements of Sub-Stations in Feb 2016 and during April 2015 to Feb 2016
2 List of Sub Stations commissionedready for commisssioning during February 2016
1 Electricity Generation (MU) Targets and Achievements for 2015-16 22
1 Power Supply Position (Provisional) for February 2016 and April 2015 to February 2016 23
2 Peak Demand and Peak Met (Provisional) for February 2016 and April 2015 to February 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during February 2016 27
6 Power Supply to Agricultural Sector during February 2016 28
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since 2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA upto February 2016
1 Rate of sale of power for the year 2013-2014 33-41
Section E - Electricity Generation
Section F - Power supply position
Contents
Section G - Growth of Power Sector
Section H - Rate of sale of power for the year 2013-2014
Executive Summary for the Month of February 2016
32
11
20
21
31
Section B - Capacity Addition
Section C - Transmission Lines
Section D - Sub Stations
SN Contents Page
1 Electricity Generation for February 2016 (BU) 1
2 Generating Capacity Addition for February 2016 (MW) 2
3 List of Projects Commissioned in February 2016 3
4 All India Installed Capacity (MW) Region-wise as on 29022016 3
5 All India Installed Capacity (MW) Sector-wise as on 29022016 4
6 Transmission Lines Added during February 2016 (Ckms) 5
7 Transformation Capacity Addition during February 2016 (MVA) 6
8 Power Supply Position (Energy amp Peak) in February 2016 7
9 Peak Shortage of Power Supply (MW) in Different Regions 8-9
10 All India PLF Sector-wise for February 2016 10
11 T amp D and AT amp C Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
13 Average cost of Power amp Average Realisation
14 All India per capita consumption of Electricity (KWh)
15 All India Coal consumption for Power Generation (MT)
Section A - Highlights of Power Sector
11
Achievement
Feb-16
Thermal 79611 1238
Hydro 6075 -1100
Nuclear 2977 -1497
Bhutan Import 0032 -1579
All India 88695 922
Type
Thermal
Hydro
Nuclear
Bhutan Import
All India
1
Electricity Generation During April 2014 to Feb 2015 amp April 2015 to Feb 2016 (BU)
6826
3415
Targets
804513 85762
33804
660
80208
Change
wrt 2015
81204
01250038
90722
Apr 14 - Feb 15 Apr 15 - Feb 16
120599
32276
Change
473
5191 495
114379
5061010994962334
4946
-516
3501
1 Electricity Generation for February 2016 (BU)
Feb-16Type
Achievement
Feb-15
6974
70839
81204
88695
76000
78000
80000
82000
84000
86000
88000
90000
BU
Feb 15 Feb 16
9623341010994
0000
200000
400000
600000
800000
1000000
1200000
BU
Apr 14 to Feb 15 Apr 15 to Feb 16
Achievement Targets Achievement
Feb-15
Thermal 2305 855 620 -73
Hydro 0 40 40 NA
Nuclear 0 0 0 NA
All India 2305 895 660 -71
Apr 14 - Feb 15 Apr 15 - Feb 16 Change
Thermal 145994 127456 -13
Hydro 33601 1436 327
Nuclear 1000 0 NA
All India 1593541 141816 -11
2
2 Generating Capacity Addition for February 2016 (MW)
Generating Capacity Addition during April 14 to Feb 15 amp April 15 to Feb 16 (MW)
Change wrt 2015TypeFeb-16
2305
660
0
500
1000
1500
2000
2500
1Feb 15 Feb 16
1593541
141816
12500
13000
13500
14000
14500
15000
15500
16000
16500
17000
1Apr 14 to feb 15 Apr 15 to Feb 16
(i) Thermal
(ii) Hydro
(iii) Nuclear
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
Northern 4319350 533126 000 4852476 162000 1824677 816692 7655845
Western 6849901 1081541 000 7931442 184000 744750 1369815 10230007
Southern 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
Eastern 3003287 19000 000 3022287 000 424912 46954 3494153
North-East 31000 169830 3600 204430 000 124200 26262 354892
Islands 000 000 4005 4005 000 000 1110 5115
ALL INDIA 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
3
2 Ind Barath Energy Pvt Ltd TPP U-I (350MW) was commissioned on 25022016
NIL
Note Captive Genaration is not included in the total
Thermal
3 List of Projects Commissioned During February 2016
4 All India Installed Capacity (MW) Region-wise as on 29022016
1 Teesta Low dam Stage-IV U-1 (40 MW) was commisioned on 14022016
1 Goindwal Sahib TPP U-1 (270 MW) was commssioned on 14022016
20136004
578000
4270342 3882151
28866497
40726
000
5000000
10000000
15000000
20000000
25000000
30000000
35000000
Thermal Nuclear Hydro RES Total Captive
Thermal Nuclear Hydro RES Total Captive
Total = 28866497
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Section A - Highlights of Power Sector Page
1 Electricity Generation for February 2016 (BU) 1
2 Generating Capacity Addition for February 2016 (MW) 2
3 List of Projects Commissioned in February 2016 3
4 All India Installed Capacity (MW) Region-wise as on 29022016 3
5 All India Installed Capacity (MW) Sector-wise as on 29022016 4
6 Transmission Lines Added during February 2016 (Ckms) 5
7 Transformation Capacity Addition during February 2016 (MVA) 6
8 Power Supply Position (Energy amp Peak) in February 2016 7
9 Peak Shortage of Power Supply (MW) in Different Regions 8-9
10 All India PLF Sector-wise for February 2016 10
11 T amp D and AT amp C Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
13 Average cost of Power amp Average Realisation
14 All India per capita consumption of Electricity (KWh)
15 All India Coal consumption for Power Generation (MT)
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during February 2016 and April 2015 to February 2016 13
3 Installed Capacity in various Regions including their shares 14-19
1 Programme and Achievements of Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
2 List of Transmission Lines CommissionedReady for commissioning during February 2016
1 Programme and Achievements of Sub-Stations in Feb 2016 and during April 2015 to Feb 2016
2 List of Sub Stations commissionedready for commisssioning during February 2016
1 Electricity Generation (MU) Targets and Achievements for 2015-16 22
1 Power Supply Position (Provisional) for February 2016 and April 2015 to February 2016 23
2 Peak Demand and Peak Met (Provisional) for February 2016 and April 2015 to February 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during February 2016 27
6 Power Supply to Agricultural Sector during February 2016 28
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since 2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA upto February 2016
1 Rate of sale of power for the year 2013-2014 33-41
Section E - Electricity Generation
Section F - Power supply position
Contents
Section G - Growth of Power Sector
Section H - Rate of sale of power for the year 2013-2014
Executive Summary for the Month of February 2016
32
11
20
21
31
Section B - Capacity Addition
Section C - Transmission Lines
Section D - Sub Stations
SN Contents Page
1 Electricity Generation for February 2016 (BU) 1
2 Generating Capacity Addition for February 2016 (MW) 2
3 List of Projects Commissioned in February 2016 3
4 All India Installed Capacity (MW) Region-wise as on 29022016 3
5 All India Installed Capacity (MW) Sector-wise as on 29022016 4
6 Transmission Lines Added during February 2016 (Ckms) 5
7 Transformation Capacity Addition during February 2016 (MVA) 6
8 Power Supply Position (Energy amp Peak) in February 2016 7
9 Peak Shortage of Power Supply (MW) in Different Regions 8-9
10 All India PLF Sector-wise for February 2016 10
11 T amp D and AT amp C Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
13 Average cost of Power amp Average Realisation
14 All India per capita consumption of Electricity (KWh)
15 All India Coal consumption for Power Generation (MT)
Section A - Highlights of Power Sector
11
Achievement
Feb-16
Thermal 79611 1238
Hydro 6075 -1100
Nuclear 2977 -1497
Bhutan Import 0032 -1579
All India 88695 922
Type
Thermal
Hydro
Nuclear
Bhutan Import
All India
1
Electricity Generation During April 2014 to Feb 2015 amp April 2015 to Feb 2016 (BU)
6826
3415
Targets
804513 85762
33804
660
80208
Change
wrt 2015
81204
01250038
90722
Apr 14 - Feb 15 Apr 15 - Feb 16
120599
32276
Change
473
5191 495
114379
5061010994962334
4946
-516
3501
1 Electricity Generation for February 2016 (BU)
Feb-16Type
Achievement
Feb-15
6974
70839
81204
88695
76000
78000
80000
82000
84000
86000
88000
90000
BU
Feb 15 Feb 16
9623341010994
0000
200000
400000
600000
800000
1000000
1200000
BU
Apr 14 to Feb 15 Apr 15 to Feb 16
Achievement Targets Achievement
Feb-15
Thermal 2305 855 620 -73
Hydro 0 40 40 NA
Nuclear 0 0 0 NA
All India 2305 895 660 -71
Apr 14 - Feb 15 Apr 15 - Feb 16 Change
Thermal 145994 127456 -13
Hydro 33601 1436 327
Nuclear 1000 0 NA
All India 1593541 141816 -11
2
2 Generating Capacity Addition for February 2016 (MW)
Generating Capacity Addition during April 14 to Feb 15 amp April 15 to Feb 16 (MW)
Change wrt 2015TypeFeb-16
2305
660
0
500
1000
1500
2000
2500
1Feb 15 Feb 16
1593541
141816
12500
13000
13500
14000
14500
15000
15500
16000
16500
17000
1Apr 14 to feb 15 Apr 15 to Feb 16
(i) Thermal
(ii) Hydro
(iii) Nuclear
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
Northern 4319350 533126 000 4852476 162000 1824677 816692 7655845
Western 6849901 1081541 000 7931442 184000 744750 1369815 10230007
Southern 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
Eastern 3003287 19000 000 3022287 000 424912 46954 3494153
North-East 31000 169830 3600 204430 000 124200 26262 354892
Islands 000 000 4005 4005 000 000 1110 5115
ALL INDIA 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
3
2 Ind Barath Energy Pvt Ltd TPP U-I (350MW) was commissioned on 25022016
NIL
Note Captive Genaration is not included in the total
Thermal
3 List of Projects Commissioned During February 2016
4 All India Installed Capacity (MW) Region-wise as on 29022016
1 Teesta Low dam Stage-IV U-1 (40 MW) was commisioned on 14022016
1 Goindwal Sahib TPP U-1 (270 MW) was commssioned on 14022016
20136004
578000
4270342 3882151
28866497
40726
000
5000000
10000000
15000000
20000000
25000000
30000000
35000000
Thermal Nuclear Hydro RES Total Captive
Thermal Nuclear Hydro RES Total Captive
Total = 28866497
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Contents Page
1 Electricity Generation for February 2016 (BU) 1
2 Generating Capacity Addition for February 2016 (MW) 2
3 List of Projects Commissioned in February 2016 3
4 All India Installed Capacity (MW) Region-wise as on 29022016 3
5 All India Installed Capacity (MW) Sector-wise as on 29022016 4
6 Transmission Lines Added during February 2016 (Ckms) 5
7 Transformation Capacity Addition during February 2016 (MVA) 6
8 Power Supply Position (Energy amp Peak) in February 2016 7
9 Peak Shortage of Power Supply (MW) in Different Regions 8-9
10 All India PLF Sector-wise for February 2016 10
11 T amp D and AT amp C Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
13 Average cost of Power amp Average Realisation
14 All India per capita consumption of Electricity (KWh)
15 All India Coal consumption for Power Generation (MT)
Section A - Highlights of Power Sector
11
Achievement
Feb-16
Thermal 79611 1238
Hydro 6075 -1100
Nuclear 2977 -1497
Bhutan Import 0032 -1579
All India 88695 922
Type
Thermal
Hydro
Nuclear
Bhutan Import
All India
1
Electricity Generation During April 2014 to Feb 2015 amp April 2015 to Feb 2016 (BU)
6826
3415
Targets
804513 85762
33804
660
80208
Change
wrt 2015
81204
01250038
90722
Apr 14 - Feb 15 Apr 15 - Feb 16
120599
32276
Change
473
5191 495
114379
5061010994962334
4946
-516
3501
1 Electricity Generation for February 2016 (BU)
Feb-16Type
Achievement
Feb-15
6974
70839
81204
88695
76000
78000
80000
82000
84000
86000
88000
90000
BU
Feb 15 Feb 16
9623341010994
0000
200000
400000
600000
800000
1000000
1200000
BU
Apr 14 to Feb 15 Apr 15 to Feb 16
Achievement Targets Achievement
Feb-15
Thermal 2305 855 620 -73
Hydro 0 40 40 NA
Nuclear 0 0 0 NA
All India 2305 895 660 -71
Apr 14 - Feb 15 Apr 15 - Feb 16 Change
Thermal 145994 127456 -13
Hydro 33601 1436 327
Nuclear 1000 0 NA
All India 1593541 141816 -11
2
2 Generating Capacity Addition for February 2016 (MW)
Generating Capacity Addition during April 14 to Feb 15 amp April 15 to Feb 16 (MW)
Change wrt 2015TypeFeb-16
2305
660
0
500
1000
1500
2000
2500
1Feb 15 Feb 16
1593541
141816
12500
13000
13500
14000
14500
15000
15500
16000
16500
17000
1Apr 14 to feb 15 Apr 15 to Feb 16
(i) Thermal
(ii) Hydro
(iii) Nuclear
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
Northern 4319350 533126 000 4852476 162000 1824677 816692 7655845
Western 6849901 1081541 000 7931442 184000 744750 1369815 10230007
Southern 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
Eastern 3003287 19000 000 3022287 000 424912 46954 3494153
North-East 31000 169830 3600 204430 000 124200 26262 354892
Islands 000 000 4005 4005 000 000 1110 5115
ALL INDIA 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
3
2 Ind Barath Energy Pvt Ltd TPP U-I (350MW) was commissioned on 25022016
NIL
Note Captive Genaration is not included in the total
Thermal
3 List of Projects Commissioned During February 2016
4 All India Installed Capacity (MW) Region-wise as on 29022016
1 Teesta Low dam Stage-IV U-1 (40 MW) was commisioned on 14022016
1 Goindwal Sahib TPP U-1 (270 MW) was commssioned on 14022016
20136004
578000
4270342 3882151
28866497
40726
000
5000000
10000000
15000000
20000000
25000000
30000000
35000000
Thermal Nuclear Hydro RES Total Captive
Thermal Nuclear Hydro RES Total Captive
Total = 28866497
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Achievement
Feb-16
Thermal 79611 1238
Hydro 6075 -1100
Nuclear 2977 -1497
Bhutan Import 0032 -1579
All India 88695 922
Type
Thermal
Hydro
Nuclear
Bhutan Import
All India
1
Electricity Generation During April 2014 to Feb 2015 amp April 2015 to Feb 2016 (BU)
6826
3415
Targets
804513 85762
33804
660
80208
Change
wrt 2015
81204
01250038
90722
Apr 14 - Feb 15 Apr 15 - Feb 16
120599
32276
Change
473
5191 495
114379
5061010994962334
4946
-516
3501
1 Electricity Generation for February 2016 (BU)
Feb-16Type
Achievement
Feb-15
6974
70839
81204
88695
76000
78000
80000
82000
84000
86000
88000
90000
BU
Feb 15 Feb 16
9623341010994
0000
200000
400000
600000
800000
1000000
1200000
BU
Apr 14 to Feb 15 Apr 15 to Feb 16
Achievement Targets Achievement
Feb-15
Thermal 2305 855 620 -73
Hydro 0 40 40 NA
Nuclear 0 0 0 NA
All India 2305 895 660 -71
Apr 14 - Feb 15 Apr 15 - Feb 16 Change
Thermal 145994 127456 -13
Hydro 33601 1436 327
Nuclear 1000 0 NA
All India 1593541 141816 -11
2
2 Generating Capacity Addition for February 2016 (MW)
Generating Capacity Addition during April 14 to Feb 15 amp April 15 to Feb 16 (MW)
Change wrt 2015TypeFeb-16
2305
660
0
500
1000
1500
2000
2500
1Feb 15 Feb 16
1593541
141816
12500
13000
13500
14000
14500
15000
15500
16000
16500
17000
1Apr 14 to feb 15 Apr 15 to Feb 16
(i) Thermal
(ii) Hydro
(iii) Nuclear
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
Northern 4319350 533126 000 4852476 162000 1824677 816692 7655845
Western 6849901 1081541 000 7931442 184000 744750 1369815 10230007
Southern 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
Eastern 3003287 19000 000 3022287 000 424912 46954 3494153
North-East 31000 169830 3600 204430 000 124200 26262 354892
Islands 000 000 4005 4005 000 000 1110 5115
ALL INDIA 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
3
2 Ind Barath Energy Pvt Ltd TPP U-I (350MW) was commissioned on 25022016
NIL
Note Captive Genaration is not included in the total
Thermal
3 List of Projects Commissioned During February 2016
4 All India Installed Capacity (MW) Region-wise as on 29022016
1 Teesta Low dam Stage-IV U-1 (40 MW) was commisioned on 14022016
1 Goindwal Sahib TPP U-1 (270 MW) was commssioned on 14022016
20136004
578000
4270342 3882151
28866497
40726
000
5000000
10000000
15000000
20000000
25000000
30000000
35000000
Thermal Nuclear Hydro RES Total Captive
Thermal Nuclear Hydro RES Total Captive
Total = 28866497
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Achievement Targets Achievement
Feb-15
Thermal 2305 855 620 -73
Hydro 0 40 40 NA
Nuclear 0 0 0 NA
All India 2305 895 660 -71
Apr 14 - Feb 15 Apr 15 - Feb 16 Change
Thermal 145994 127456 -13
Hydro 33601 1436 327
Nuclear 1000 0 NA
All India 1593541 141816 -11
2
2 Generating Capacity Addition for February 2016 (MW)
Generating Capacity Addition during April 14 to Feb 15 amp April 15 to Feb 16 (MW)
Change wrt 2015TypeFeb-16
2305
660
0
500
1000
1500
2000
2500
1Feb 15 Feb 16
1593541
141816
12500
13000
13500
14000
14500
15000
15500
16000
16500
17000
1Apr 14 to feb 15 Apr 15 to Feb 16
(i) Thermal
(ii) Hydro
(iii) Nuclear
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
Northern 4319350 533126 000 4852476 162000 1824677 816692 7655845
Western 6849901 1081541 000 7931442 184000 744750 1369815 10230007
Southern 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
Eastern 3003287 19000 000 3022287 000 424912 46954 3494153
North-East 31000 169830 3600 204430 000 124200 26262 354892
Islands 000 000 4005 4005 000 000 1110 5115
ALL INDIA 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
3
2 Ind Barath Energy Pvt Ltd TPP U-I (350MW) was commissioned on 25022016
NIL
Note Captive Genaration is not included in the total
Thermal
3 List of Projects Commissioned During February 2016
4 All India Installed Capacity (MW) Region-wise as on 29022016
1 Teesta Low dam Stage-IV U-1 (40 MW) was commisioned on 14022016
1 Goindwal Sahib TPP U-1 (270 MW) was commssioned on 14022016
20136004
578000
4270342 3882151
28866497
40726
000
5000000
10000000
15000000
20000000
25000000
30000000
35000000
Thermal Nuclear Hydro RES Total Captive
Thermal Nuclear Hydro RES Total Captive
Total = 28866497
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(i) Thermal
(ii) Hydro
(iii) Nuclear
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
Northern 4319350 533126 000 4852476 162000 1824677 816692 7655845
Western 6849901 1081541 000 7931442 184000 744750 1369815 10230007
Southern 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
Eastern 3003287 19000 000 3022287 000 424912 46954 3494153
North-East 31000 169830 3600 204430 000 124200 26262 354892
Islands 000 000 4005 4005 000 000 1110 5115
ALL INDIA 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
3
2 Ind Barath Energy Pvt Ltd TPP U-I (350MW) was commissioned on 25022016
NIL
Note Captive Genaration is not included in the total
Thermal
3 List of Projects Commissioned During February 2016
4 All India Installed Capacity (MW) Region-wise as on 29022016
1 Teesta Low dam Stage-IV U-1 (40 MW) was commisioned on 14022016
1 Goindwal Sahib TPP U-1 (270 MW) was commssioned on 14022016
20136004
578000
4270342 3882151
28866497
40726
000
5000000
10000000
15000000
20000000
25000000
30000000
35000000
Thermal Nuclear Hydro RES Total Captive
Thermal Nuclear Hydro RES Total Captive
Total = 28866497
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Sector
Coal Gas Diesel Total
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
All India 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Central 7484675
State 9795059
Private 11586763
Hydro RES
5 All India Installed Capacity (MW) Sector-wise as on 29022016
4
Grand TotalTHERMAL
Nuclear
Central 7484675 26
State 9795059 34
Private 11586763 40
All India Installed Capacity(MW) as on 29-02-2016 (Sector-Wise)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 500 KV HVDC
+- 800 KV HVDC
765 KV
400 KV
220 KV
All India
5
17780
0
Apr 14 - Feb 15
5429
10059
6727
25721
8441
0 3506
6 Transmission Lines Added during February 2016 (Ckms)
3612
417
1176
317
1132
5727
Transmission Lines Added during April 14 to Feb 15 amp April 15 to Feb 16 (Ckms)
Feb-16
0
Feb-15
0
Apr 15 - Feb 16
0
531
284
0
759
0 0
17780
25721
0
5000
10000
15000
20000
25000
30000
ck
ms
Apr 14 to Feb 15 Apr 15 to Feb 16
1132 1176
0
200
400
600
800
1000
1200
1400
1
ckm
s
Feb 15 Feb 16
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
Voltage Level
+- 800 KV HVDC
+- 500 KV HVDC
765 KV
400 KV
220 KV
All India
6
0 1500
All India Transformation Capacity Addition during April 14 to Feb 15 amp April
15 to Feb16 (MVA)
43956
0
13500
11785
17171
55359
29500
14655
11204
0
Feb-15 Feb-16
April 14 to Feb 15 April 15 to Feb 16
11430
0
0
815
1300
7 Transformation Capacity Addition During February 2016 (MVA)
2115
0
9000
315
2115
0 0
11430
2115
0
2000
4000
6000
8000
10000
12000
14000
MV
A
Transformation Capacity Addition during February 2016
Feb 15 Feb 16
55359
43956
0
74520
1
MV
A
April 14 to Feb 15 April 15 to Feb 16
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 23549 25115 22371 23926 -50 -47
Western 23457 28603 23269 28579 -08 -01
Southern 23035 24443 22567 24232 -20 -09
Eastern 8417 9515 8310 9493 -13 -02
North Eastern 1044 1111 982 1087 -59 -22
All India 79502 88787 77499 87317 -25 -17
Feb 15 Feb 16 Feb 15 Feb 16 Jan 14 Jan 15
Northern 40474 41547 38586 39842 -47 -41
Western 42966 45110 42750 45070 -05 -01
Southern 37602 37053 35818 37053 -47 00
Eastern 16020 17456 15892 17456 -08 00
North Eastern 2318 2401 2155 2328 -70 -30
All India 139380 142146 135201 140346 -30 -13
7
Region
Power (MW)
8 Power Supply Position (Energy amp Peak) in February 2016
Peak Demand Peak Met
Requirement Availability
Energy (MU)Region Deficit ()
Deficit ()
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Chandigarh Delhi Haryana HP JampK Punjab Rajasthan UP UtrakhandFeb 16 0 4 0 0 363 0 0 905 70
Feb 15 0 0 0 0 356 0 0 975 0
Chattisgarh Gujarat MP Maharashtra Daman amp Diu Dadar Nagar Haveli Goa
Feb 16 368 10 6 21 0 0 0
Feb 15 151 4 0 330 0 0 2
AP Telengana Karnataka Kerala Tamil Nadu Puducherry Lakshyadeep
Feb 16 0 0 574 3 5 0 0
Feb 15 12 201 461 123 644 0 0
8
9 Peak Shortage of Power Supply (MW) in Different Regions
0 0 0 0
35
6
0 0
97
5
00 4 0 0
36
3
0 0
90
5
70
0
400
800
1200
Ch
and
iga
rh
De
lhi
Ha
ryan
a
HP
JampK
Pu
nja
b
Ra
jast
han
UP
Utr
akh
an
d
MW
Northern States (MW)Feb 15 Feb 16
151
4 0
330
0 0 2
368
10
6 21
0 0 0
0
50
100
150
200
250
300
350
400
Ch
att
isga
rh
Guja
rat
MP
Mah
ara
shtr
a
Da
man
amp D
iu
Da
da
r N
aga
rH
aveli G
oa
MW
Western States (MW) Feb 15 Feb 16
12
20
1
46
1
12
3
64
4
0 00 0
57
4
3 5 0
0
1000
AP
Tele
nga
na
Ka
rnata
ka
Ke
rala
Tam
il N
adu
Pu
du
cherr
y
Laksh
yad
eep
MW
Southern States (MW)Feb 15 Feb 16
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Bihar DVC Jharkhand Odisha West Bengal Sikkim AampN Island
Feb 16 0 0 0 0 0 0 8
Feb 15 100 40 22 35 15 0 8
Arunachal Assam Manipur Meghalaya Mizoram Nagaland Tripura
Feb 16 4 6 0 0 2 1 0
Feb 15 15 165 4 4 1 0 23
9
10
0
40
22 3
5
15
0
8
0 0 0 0 0 0
8
0
2040
6080
100
120
Bih
ar
DV
C
Jhark
hand
Odis
ha
West B
en
gal
Sik
kim
Aamp
N I
sland
MW
Eastern States (MW)Feb 15 Feb 16
15
16
5
4 4 1 0
23
4 6 0 0 2 1 0
0
50
100
150
200
Aru
nachal
Assam
Man
ipu
r
Meg
hala
ya
Miz
ora
m
Na
gala
nd
Tripura
MW
North-Eastern States (MW) Feb 15 Feb 16
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Sector Feb 15 Feb 16
Central 7898 7647
State 6264 5589
Private 5696 6540
ALL INDIA 6572 6495
Month 2014-15 2015-16
April 6864 6205
May 6706 6427
June 6631 5943
July 6380 5836
August 5958 5760
September 5907 6363
October 6501 6686
November 6569 6034
December 6514 6175
January 6479 6320
February 6572 6495
March
For Coal and Lignite based Power Plants
10
PLF
All India PLF Month-wise
10 All India PLF Sector-wise for February 2016
78
98
62
64
56
96
65
72
764
7
558
9
654
0
649
5
000100020003000400050006000700080009000
Central State Private ALL INDIA
P
LF
Sector-Wise Plant Load Factor for February 2015 and February 2016
FEb 15 Feb 16
68
64
67
06
66
31
63
80
59
58
59
07
65
01
65
69
65
14
64
79
65
72
62
05
64
27
59
43
58
36
57
60
63
63
66
86
60
34
61
75
63
20
64
95
40
60
80
April
May
Jun
e
July
Augu
st
Septe
mber
Octo
ber
Nove
mb
er
Dece
mb
er
Jan
uary
Febru
ary
Marc
hAll India PLF Month-wise
2014-15 2015-16
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
2010-11 2011-12 2012-13 2013-14
TampD Losses 2397 2365 2304 2146(P)
ATampC Losses 2635 2663 2538 2270(P)
Note As per PFC for utilities selling directly to consumers P Provisional
Total Number of Villages
597464
Pump sets Energised as on
31-03-2015
20120972
Note From the year 2004-05 onwards Definition of Village Electrification-
A village would be declared Electrified if
Including
Agriculture
Only
Agriculture2012-13 376 14867
Source- PFC Reports on the performance of State Power Utilities
2012-13 91441
2013-14 957
(Gross Generation+Net Import) Mid Year Population Provisional
2013-14 4894
2014-15 5315
Provisional 11
15 All India Coal consumption for Power Generation (MT)
501
14 All India per capita consumption of Electricity ( KWh)
Realization(paiseunit)
20429404
Pump sets Energised as on 29-02-2016
cost of supply (paiseunit)
i) Basic Infrastructure such as Distribution Transformer and Distribution lines are provided in the
inhabited locality as well as Dalit Basti hemlet where it exists (For electrification through Non-
Conventional Energy Sources a Distribution Transformer mat not be necessary)
Figures are based on the data received from REC Nodal Agency for DDUGJY
11 Tamp D and ATampC Losses ()
12 All India Village Electrification amp Pumpsets Energised as on 29022016
Villiages Electrified (Nos) as on 07032016
9790585097
Villages electrified
Year
ii) Electricity is provided to Public places like Schools Panchayat Office Health Centre
Dispensaries Community Centres etc and
iv) Mandatory Certification from Gram Panchayat regarding the completion of village electrification
should be obtained
13 Average cost of Power amp Average Realisation
iii) The number of households electrified should be at least 10 of the total number of households in
the village
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to
October 2015 was Updated every month based on the information received from
statesdistribution utilities as and when reported but the data for all the states for a particular
month was generally not made available simultaneously to reflect the countrywide picture for a
particular month Number of total villages and number of electrified villages have also been
adjusted for changes observed from Census 2011 data As such each monthly report of Village
electrification of CEA is independent of the earlier published reports
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Contents Page
1 Capacity Addition Targets and Achievements in 12th Plan 12
2 Capacity Addition Targets amp Achievements during Feb 2016 and April 2015 to Feb 2016 13
3 Installed Capacity in various Regions including their shares 14-19
Section B - Capacity Addition
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(i) Targets
(MW)
TypeSector Central State Private Total
Thermal 1487800 1392200 4354000 7234000
Hydro 600400 160800 328500 1089700
Nuclear 530000 000 000 530000
Total 2618200 1553000 4682500 8853700
(ii)
(MW)
TypeSector Central State Private Total
Thermal 1122810 1456910 4466750 7046470
Hydro 246402 67200 59500 373102
Nuclear 100000 000 000 100000
Total 1469212 1524110 4526250 7519572
Acievement 5612 9814 9666 8493
1 Capacity Addtion Targets and Achievements in the 12th Plan
12
Achievement of Capacity Addition during the Current Plan upto Feb 2016
Achievements upto February 2016 during the 12th Plan
723
400
0
108
970
0
53
000
0
704
647
0
37
310
2
10
000
0
000
1000000
2000000
3000000
4000000
5000000
6000000
7000000
8000000
9000000
Thermal Hydro Nuclear
12th Plan Target 88537 MW Achieved so far 7519572 MW
Target Achievement
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(MW)
Deviation
Target Achievement Target Achievement (+) (-)
Central 21061 195 0 21061 18856 -2205
State 8120 660 0 6460 2450 -4010
Pvt 7120 0 620 6025 8410 2385
Total 173461 855 620 145911 127456 -18455
Central 590 40 40 440 440 0
State 575 0 0 170 570 400
Pvt 526 0 0 478 426 -52
Total 1691 40 40 1088 1436 348
Nuclear Central 1000 0 0 1000 0 -1000
Central 36961 235 40 35461 23256 -12205
State 8695 660 0 6630 3020 -3610
Pvt 7646 0 620 6503 8836 2333
Total 200371 895 660 166791 141816 -24975
13
2 Capacity Addition Targets Achievements During Feb 2016 amp April 2015 to Feb 2016
Feb 16 Apr 15 - Feb 16Schemes Sector
Target
2015-16
Hydro
All India
Capacity Addition TargetsAchievements during the Month of Februray 2016
Thermal
85
5
40
0
89
5
62
0
40
0
66
0
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during February 2016 Target
Achievement
14
59
1
10
88
10
00
16
67
9
12
74
6
14
36
0
14
18
2
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Thermal Hydro Nuclear Total
MW
Targets and Achievement during 2015-16 Target
Achievement
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Coal Gas Diesel Total
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Sub Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Sub Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Sub Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Sub Total 3003287 19000 000 3022287 000 424912 46954 3494153
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Sub Total 31000 169830 3600 204430 000 124200 26262 354892
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Sub Total 000 000 4005 4005 000 000 1110 5115
State 6055050 697530 43857 6796437 000 2805200 193422 9795059
Private 6532738 997800 55496 7586034 000 312000 3688729 11586763
Central 4998000 755533 000 5753533 578000 1153142 000 7484675
Total 17585788 2450863 99353 20136004 578000 4270342 3882151 28866497
Figures at decimal may not tally due to rounding off
Note -
(As per latest information available with MNRE)
Break up of RES all India as on 31122015 is given below (in MW)
417682 2508819 487887 3882151
2 Installed capacity of Andhra Pradesh has been bifurcated in the ratio of 5389 and 4611 among Telangana and
New Andhra Pradeh respectively Except the installed capacity of Thamminapatnam (300 MW) Simhapuri (450 MW)
and Tanir Bhavi (220 MW) are shown in the state of New Andhra pradesh
3 Koldam (1000 MW four units) shares are provisional
4 Two units of Kondapall Stg-II of 371 MW each taken in private sector in AP
5 IPP Panipuram (2x660=1320 MW) Tied capacity of 270 MW with Telangana and balance capacity of 1050 MW has
been shown in Andhara pradesh
14
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 29022016)
(UTILITIES)
RegionOwnership
Sector
Modewise breakup
Grand TotalThermalNuclear Hydro
RES
(MNRE)
Northern
Region
Western Region
Southern
Region
Eastern Region
North Eastern
Region
Islands
ALL INDIA
Abbreviation-SHP=Small Hydro Project (le 25 MW) BP=Biomass Power UampI=Urban amp Industrial Waste Power RES=Renewable Energy Sources
1RES include SHP BP UampI Solar and Wind Energy Installed capacity in respect of RES (MNER) as on 31122015
Small
Hydro PowerWind Power
Bio-PowerSolar Power
Total
CapacityBM PowerCogen Waste to Energy
455055 12708
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Coal Gas Diesel Total
State 13500 205040 000 218540 000 000 000 218540
Private 44550 10800 000 55350 000 000 3471 58821
Central 442137 20761 000 462898 12208 82205 000 557311
Sub-Total 500187 236601 000 736788 12208 82205 3471 834672
State 316000 2500 000 318500 000 88451 5930 412881
Private 216550 000 000 216550 000 000 7930 224480
Central 120203 53529 000 173732 10916 57232 000 241880
Sub-Total 652753 56029 000 708782 10916 145683 13860 879241
State 000 000 000 000 000 39360 24560 63920
Private 000 000 000 000 000 174800 50920 225720
Central 15202 6188 000 21390 3408 127991 000 152789
Sub-Total 15202 6188 000 21390 3408 342151 75480 442429
State 000 17500 000 17500 000 123000 10653 151153
Private 000 000 000 000 000 000 5000 5000
Central 32932 12914 000 45846 7700 102521 000 156067
Sub-Total 32932 30414 000 63346 7700 225521 15653 312220
State 263000 2500 000 265500 000 223023 12780 501303
Private 408400 000 000 408400 000 000 38067 446467
Central 66088 26392 000 92480 20804 91490 000 204774
Sub-Total 737488 28892 000 766380 20804 314513 50847 1152544
State 519000 60380 000 579380 000 98796 2385 680561
Private 319600 000 000 319600 000 000 524199 843799
Central 101472 22123 000 123595 57300 73134 000 254029
Sub-Total 940072 82503 000 1022575 57300 171930 526584 1778389
State 542300 000 000 542300 000 52410 2510 597220
Private 466500 000 000 466500 000 000 103350 569850
Central 290995 54997 000 345992 33572 164420 000 543984
Sub-Total 1299795 54997 000 1354792 33572 216830 105860 1711054
State 000 000 000 000 000 125215 6288 131503
Private 9900 000 000 9900 000 73000 18145 101045
Central 30050 6935 000 36985 2228 45967 000 85180
Sub-Total 39950 6935 000 46885 2228 244182 24433 317728
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 504 504
Central 3254 1532 000 4786 884 6232 000 11902
Sub-Total 3254 1532 000 4786 884 6232 504 12406
97719 29035 000 126754 12980 75430 000 215164
State 1653800 287920 000 1941720 000 750255 65106 2757081
Private 1465500 10800 000 1476300 000 247800 751586 2475686
Central 1200050 234406 000 1434456 162000 826622 000 2423078
Grand Total 4319350 533126 000 4852476 162000 1824677 816692 7655845
15
Delhi
Haryana
Himachal
Pradesh
Jammu amp
Kashmir
Punjab
Total (Northern
Region)
Rajasthan
Uttar
Pradesh
Uttrakhnad
Chandigarh
(As on 29022016)
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTHERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Central - Unallocated
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(As on 29022016)
Coal Gas Diesel Total
State 000 000 000 000 000 000 005 005
Private 000 4800 000 4800 000 000 000 4800
Central 33135 000 000 33135 2580 000 000 35715
Sub-Total 33135 4800 000 37935 2580 000 005 40520
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 400 400
Central 4058 420 000 4478 738 000 000 5216
Sub-Total 4058 420 000 4478 738 000 000 5616
State 497000 232182 000 729182 000 77200 800 807182
Private 864200 406000 000 1270200 000 000 496515 1766715
Central 274172 42427 000 316599 55932 000 000 372531
Sub-Total 1635372 680609 000 2315981 55932 77200 497315 2946428
State 432000 000 000 432000 000 170366 8396 610762
Private 455000 000 000 455000 000 000 184687 639687
Central 238425 25718 000 264143 27324 152000 000 443467
Sub-Total 1125425 25718 000 1151143 27324 322366 193083 1693916
State 278000 000 000 278000 000 12000 1105 291105
Private 964300 000 000 964300 000 000 37903 1002203
Central 153069 000 000 153069 4752 000 000 157821
Sub-Total 1395369 000 000 1395369 4752 12000 39008 1451129
State 956000 67200 000 1023200 000 288484 20812 1332496
Private 1179600 18000 000 1197600 000 44700 619192 1861492
Central 346216 262393 000 608609 69014 000 000 677623
Sub-Total 2481816 347593 000 2829409 69014 333184 640004 3871611
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 4992 2710 000 7702 846 000 000 8548
Sub-Total 4992 2710 000 7702 846 000 000 8548
169735 19691 000 189426 22814 000 000 212240
State 2163000 299382 000 2462382 000 548050 31118 3041550
Private 3463100 428800 000 3891900 000 44700 1338697 5275297
Central 1223801 353359 000 1577160 184000 152000 000 1913160
Grand Total 6849901 1081541 000 7931442 184000 744750 1369815 10230007
16
Dadra amp Nagar
Naveli
Central - Unallocated
Total (Western
Region)
Goa
Daman amp Diu
Gujarat
Madhya
Pradesh
Chhattisgarh
Maharashtra
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
WESTERN REGION
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(As on 29022016)
Coal Gas Diesel Total
State 308591 000 000 308591 000 175887 8950 493428
Private 247000 318265 1697 566962 000 000 210310 777272
Central 147330 000 000 147330 12716 000 000 160046
Sub-Total 702921 318265 1697 1022883 12716 175887 219260 1430747
State 420659 000 000 420659 000 209566 000 630225
Private 27000 169775 1983 198758 000 000 9145 207903
Central 172188 000 000 172188 14862 000 000 187050
Sub-Total 619847 169775 1983 791605 14862 209566 9145 1025178
State 272000 000 12792 284792 000 359980 13725 658497
Private 206000 000 10650 216650 000 000 468163 684813
Central 162846 000 000 162846 47586 000 000 210432
Sub-Total 640846 000 23442 664288 47586 359980 481888 1553742
State 000 000 23460 23460 000 188150 13892 225502
Private 000 17400 000 17400 000 000 10713 28113
Central 103869 35958 000 139827 22860 000 000 162687
Sub-Total 103869 53358 23460 180687 22860 188150 24605 416302
State 477000 52408 000 529408 000 218220 12270 759898
Private 235000 50310 41166 326476 000 000 874147 1200623
Central 415510 000 000 415510 98650 000 000 514160
Sub-Total 1127510 102718 41166 1271394 98650 218220 886417 2474681
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 000 000
Central 10017 000 000 10017 000 000 000 10017
Sub-Total 10017 000 000 10017 000 000 000 10017
State 000 3250 000 3250 000 000 000 3250
Private 000 000 000 000 000 000 003 003
Central 24932 000 000 24932 5278 000 000 30210
Sub-Total 24932 3250 000 28182 5278 000 003 33463
152308 000 000 152308 30048 000 000 182356
State 1478250 55658 36252 1570160 000 1151803 48837 2770800
Private 715000 555750 55496 1326246 000 000 1572481 2898727
Central 1189000 35958 000 1224958 232000 000 000 1456958
Grand Total 3382250 647366 91748 4121364 232000 1151803 1621318 7126485
17
Karnataka
Kerala
Tamil Nadu
NLC
Puducherry
Central - Unallocated
Andhra Pradesh
Telangana
Grand TotalThermal
NuclearHydro
(Renewable)
RES
(MNRE)
State Ownership
Sector
Modewise breakup
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
SOUTHERN REGION
Total (Southern
Region)
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(As on 29022016)
Coal Gas Diesel Total
State 21000 000 000 21000 000 000 7070 28070
Private 000 000 000 000 000 000 4342 4342
Central 230624 000 000 230624 000 12943 000 243567
Sub-Total 251624 000 000 251624 000 12943 11412 275979
State 119000 000 000 119000 000 13000 405 132405
Private 90000 000 000 90000 000 000 1600 91600
Central 31493 000 000 31493 000 7093 000 38586
Sub-Total 240493 000 000 240493 000 20093 2005 262591
State 572000 10000 000 582000 000 97700 9195 688895
Private 194138 000 000 194138 000 000 3976 198114
Central 92245 000 000 92245 000 31130 000 123375
Sub-Total 858383 10000 000 868383 000 128830 13171 1010384
State 000 000 000 000 000 000 000 000
Private 105000 000 000 105000 000 000 000 105000
Central 671066 9000 000 680066 000 19326 000 699392
Sub-Total 776066 9000 000 785066 000 19326 000 804392
State 42000 000 000 42000 000 206192 630 248822
Private 500000 000 000 500000 000 000 14525 514525
Central 168304 000 000 168304 000 10501 000 178805
Sub-Total 710304 000 000 710304 000 216693 15155 942152
State 000 000 000 000 000 000 5211 5211
Private 000 000 000 000 000 19500 000 19500
Central 9210 000 000 9210 000 7527 000 16737
Sub-Total 9210 000 000 9210 000 27027 5211 41448
157207 000 000 157207 000 000 000 157207
State 754000 10000 000 764000 000 316892 22511 1103403
Private 889138 000 000 889138 000 19500 24443 933081
Central 1360149 9000 000 1369149 000 88520 000 1457669
Grand Total 3003287 19000 000 3022287 000 424912 46954 3494153
18
Central - Unallocated
Total (Eastern
Region)
NuclearHydro
(Renewable)
RES
(MNRE)
Odisha
Bihar
Jharkhand
West Bengal
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
DVC
State
Sikkim
Ownership
Sector
Modewise breakup
Grand TotalThermal
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(As on 29022016)
Coal Gas Diesel Total
State 6000 27620 000 33620 000 10000 3001 46621
Private 000 2450 000 2450 000 000 410 2860
Central 12700 41792 000 54492 000 32972 000 87464
Sub-Total 18700 71862 000 90562 000 42972 3411 136945
State 000 000 000 000 000 000 10461 10461
Private 000 000 000 000 000 000 027 027
Central 1235 4306 000 5541 000 9757 000 15298
Sub-Total 1235 4306 000 5541 000 9757 10488 25786
State 000 000 000 000 000 28200 3103 31303
Private 000 000 000 000 000 000 000 000
Central 1770 10514 000 12284 000 7458 000 19742
Sub-Total 1770 10514 000 12284 000 35658 3103 51045
State 000 16950 000 16950 000 000 1601 18551
Private 000 000 000 000 000 000 500 500
Central 1870 40492 000 42362 000 6237 000 48599
Sub-Total 1870 57442 000 59312 000 6237 2101 67650
State 000 000 3600 3600 000 000 545 4145
Private 000 000 000 000 000 000 000 000
Central 1570 6798 000 8368 000 8098 000 16466
Sub-Total 1570 6798 3600 11968 000 8098 545 20611
State 000 000 000 000 000 000 2967 2967
Private 000 000 000 000 000 000 000 000
Central 1070 4635 000 5705 000 5332 000 11037
Sub-Total 1070 4635 000 5705 000 5332 2967 14004
State 000 000 000 000 000 000 3647 3647
Private 000 000 000 000 000 000 000 000
Central 1035 3829 000 4864 000 3431 000 8295
Sub-Total 1035 3829 000 4864 000 3431 3647 11942
3750 10444 000 14194 000 12715 000 26909
State 6000 44570 3600 54170 000 38200 25325 117695
Private 000 2450 000 2450 000 000 937 3387
Central 25000 122810 000 147810 000 86000 000 233810
Grand Total 31000 169830 3600 204430 000 124200 26262 354892
(As on 29022016)
Coal Gas Diesel Total
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 510 510
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 4005 4005 000 000 1035 5040
State 000 000 000 000 000 000 000 000
Private 000 000 000 000 000 000 075 075
Central 000 000 000 000 000 000 000 000
Sub-Total 000 000 000 000 000 000 075 075
State 000 000 4005 4005 000 000 525 4530
Private 000 000 000 000 000 000 585 585
Central 000 000 000 000 000 000 000 000
Grand Total 000 000 4005 4005 000 000 1110 5115
19
Hydro
(Renewable)
RES
(MNRE)
Andaman amp
Nicobar
lakshadweep
Total (Islands)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
ISLANDS
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
State Ownership
Sector
Modewise breakup
Grand TotalThermal
Nuclear
Mizoram
Central - Unallocated
Total (North-
Eastern Region)
Assam
Arunachal
Pradesh
Meghalaya
Tripura
Manipur
Nagaland
State Ownership
Sector
Modewise breakup
Grand TotalThermalNuclear
Hydro
(Renewable)
RES
(MNRE)
INSTALLED CAPACITY (IN MW) OF POWER UTILITIES IN THE STATESUTS LOCATED IN
NORTH-EASTERN REGION
INCLUDING ALLOCATED SHARES IN JOINT amp CENTRAL SECTOR UTILITIES
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
RVPNL
1500
0
0
11072
11072
47832
18000
17260
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
1 Programme amp Achievement of sub- stations in Feb 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
230
220
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Programme
2015-16 Programme Achievement Programme Achievement
Central Sector 0 0 0 0 3506
State Sector 0 0 0 0 0
Total 0 0 0 0 3506
Central Sector 0 0 0 0 0
JVPrivate Sector 0 0 0 0 0
Total 0 0 0 0 0
Central Sector 4204 0 0 4204 4152
State Sector 0 0 0 0 0
JVPrivate Sector 1257 0 0 1257 1277
Total 5461 0 0 5461 5429
Central Sector 3943 808 0 3943 4899
State Sector 3759 861 759 3520 4035
JVPrivate Sector 1466 0 0 1156 1125
Total 9168 1669 759 8619 10059
Central Sector 867 0 0 867 363
State Sector 8216 562 417 7755 6364
JVPrivate Sector 0 0 0 0 0
Total 9083 562 417 8622 6727
Grand Total 23712 2231 1176 22702 25721
Voltage Level
(kV)
Name of the
Transmission LineType
Executing
Agency
Line Length
(CKM)
400 LILO of Chandrapur- Parli ckt-II at Kumbhargaon (Nanded) SS DC MSETCL 88
400 Mundra (Adani) - Zerda line 2 DC GETCO 671
220 LILO of Narendrapur- Mendhasal at Attri (Old Karadagadia) DC OPTCL 5
220 Peeragarhi- Wazirpur UG 1000 mm 200 MW DC DTL 17
220 Pulivendula- Hindupur DC APTRANSCO 250
220 Teesta LDP - IV - new Jalpaiguri (NJP) DC WBSETCL 145
20
400 kV
220kV
2 List of Transmission Line CommissionedReady for commissioning During Feb 2016
STATE SECTOR
1 Programme and Achievementsof Transmission Lines in Feb 2016 and during April 2015 to Feb 2016
+- 800 kV HVDC
+- 500 kV HVDC
765 kV
Apr 15 to Feb 16Feb 16
(Figs in ckms)
Voltage Level
Sector
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Contents Page
1Programme and Achievements of Sub-Stations in Febuary 2016 and during April
2015 to Febuary 2016
2 List of Sub Stations commissionedready for commisssioning during Febuary 2016
Section D - Sub Stations
21
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Sl
NoExecuting Agency
Installed
Capacity (MW)Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
15455554
2314176
322968331020397343611750
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification
since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
585097 20429404
557439
NIL
Cummulative as on 07032016
86293726
46708
18423975
499150557976840909
010411 to 310312
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Programme
2015-16 Programme Achievement Achievement
Central Sector 1500 0 0 1500
State Sector 0 0 0 0
JVPrivate Sector 0 0 0 0
Total 1500 0 0 1500
Central Sector 16500 0 0 13500
State Sector 1500 0 0 0
JVPrivate Sector 0 0 0 0
Total 18000 0 0 13500
Central Sector 7830 3000 0 3005
State Sector 11560 2160 815 7150
JVPrivate Sector 0 0 0 1630
Total 19390 5160 815 11785
Central Sector 0 0 0 340
State Sector 11652 1120 1300 16831
JVPrivate Sector 0 0 0 0
Total 11652 1120 1300 17171
Grand Total 50542 6280 2115 43956
Name of
Sub-StationType
Capacity Added
(MWMVA)
STATE SECTOR
Mundka ss (3rd 400220 kV ICT) 400220 315
Nanded (Kumbhargaon) SS 400220 500
Gurubarapally SS 230110 100
Vyasarpadi 230110 200
Atri (Karadagadia) Ist ICT SS 220132 160
Chonkarwada SS (Bharatpur Distt) 220132 160
NPH (Jaipur) (GSS) (AUG) 220132 160
Pattiseema SS 22011 60
Rachagunneri SS (in Chitoor distt) 220132 100
Ramgarh (GSS) (AUG) 220132 160
Wazirpur (GIS) 22033 200
21
230
230
MSETCL
APTRANSCO
APTRANSCO
RVPNL
Voltage Level
(kV)Executing Agency
0
220
220
220
400
220
230 TANTRANSCO
1 Programme amp Achievement of sub- stations in Jan 2016 and during April 2015 to Jan 2016
2 List of Sub-Stations CommissionedReady for commissioning during Feb 2016
plusmn 800 kV HVDC
220 kV
6700
0
400 kV
0
1500
Apr 15 - Feb 16
Programme
(Fig in MVA)
Voltage Level
Sector
10560
0
16500
1500
Feb-16
765 kV
TANTRANSCO
OPTCL
DTL
220
220 RVPNL
DTL
400
RVPNL
1500
0
0
11072
11072
47832
18000
17260
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Programme Achievement Ach Programme Achievement Ach
Central Sector 31987800 2676900 2695527 10070 29128200 28626839 9828
State Sector 33532000 2794100 2368721 8478 30500100 26624785 8729
PvtIPP Sector 29027300 2406800 2740463 11386 26367800 28610837 10851
PvtUTL Sector 2122900 143000 156390 10936 1941700 1899542 9783
Total 96670000 8020800 7961101 9926 87937800 85762003 9753
Central Sector 4892500 230800 247413 10720 4584200 5368816 11712
State Sector 6650500 429500 326766 7608 6161400 4951954 8037
PvtIPP Sector 1112000 27600 23399 8478 1071100 1016890 9494
PvtUTL Sector 145000 9500 9970 10495 133000 100323 7543
Total 12800000 697400 607548 8712 11949700 11437983 9572
Central Sector 3800000 341500 297719 8718 3436000 3380422 9838
Total 3800000 341500 297719 8718 3436000 3380422 9838
Bhutan Import 480000 12500 3210 2568 465300 519125 11157
Central Sector 40680300 3249200 3240659 9974 37148400 37376077 10061
State Sector 40182500 3223600 2695487 8362 36661500 31576739 8613
Pvt Sector 32407200 2586900 2930222 11327 29513600 31627592 10716
Total 113750000 9072200 8869578 9777 103788800 101099533 9741
Provisional based on actual-cum-Assesment
Figs in MU
Cummulative
Achievement
Cummulative
Achievement
Jan-16 Jan-15 Upto Jan-16 Upto Jan-15
437784 445421 5555073 5256849
22
Febuary 16
1 Electricity Generation (MU) Targets and Achievememts for 2015-16
All India Energy Generation During April 2015 to Febuary 2016 (MU)
Target
(2015-16)
April 15 to Febuary 16Sector
Hydro
Thermal
Nuclear
Renewable Energy Generation
Achievement
879378
119497
34360
1037888
857620
114380
33804
1010995
0
200000
400000
600000
800000
1000000
1200000
Thermal Hydro Nuclear Total
Programme
Achievement
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Contents Page
1 Power Supply Position (Provisional) for Feb 2016 and April 2015 to Feb 2016 23
2 Peak Demand and Peak Met (Provisional) for Feb 2016 and April 2015 to Feb 2016 24
3 Power Supply Position (Revised) for January 2016 25
4 Peak Demand and Peak Met (Revised) for January 2016 26
5 Notified Power cuts Restrictions on Industries during Feb 2016 27
6 Power Supply to Agricultural Sector during Feb 2016 28
Section F - Power supply position
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 101 101 0 00 1505 1505 0 00
-दल0 Delhi 1770 1769 -1 -01 27692 27652 -40 -01
ह5रयाणा Haryana 3448 3448 0 00 44274 44205 -69 -02
-हमाचल दश Himachal Pradesh 723 721 -2 -03 8096 8034 -62 -08
जम कमीर Jammu amp Kashmir 1432 1219 -214 -149 15090 12780 -2310 -153
प जाब Punjab 2954 2954 0 00 46740 46728 -12 00
राजHथान Rajasthan 5853 5846 -7 -01 61788 61577 -211 -03उरउरउरउर दश Uttar Pradesh 7826 6865 -961 -123 98025 85589 -12436 -127उराखडउराखडउराखडउराखड Uttarakhand 1008 1004 -4 -04 11902 11690 -212 -18उरीउरीउरीउरी Northern Region 25115 23926 -1189 -47 315112 299758 -15354 -49छीसगढ़ Chhattisgarh 2009 1988 -21 -10 23342 23003 -339 -15
गजरात Gujarat 8136 8136 0 00 94455 94451 -4 00
मPय दश Madhya Pradesh 5768 5768 0 00 56976 56976 0 00
महाराRS Maharashtra 11604 11601 -3 00 129122 128666 -456 -04
दमन और -दउ Daman amp Diu 185 185 0 00 2128 2128 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 491 491 0 00 5406 5406 0 00
गोवा Goa 409 409 0 00 4693 4692 -1 00
पिचमी Western Region 28603 28579 -24 -01 316123 315323 -800 -03
आYZ दश Andhra Pradesh 4237 4237 0 00 45553 45484 -69 -02
तलगाना Telangana 4030 4030 0 00 45563 45258 -305 -07
कना]टक Karnataka 5944 5733 -211 -35 58013 54966 -3047 -53
करल Kerala 1916 1916 0 00 20961 20847 -114 -05
तमल नाड Tamil Nadu 8132 8132 0 00 87649 86961 -688 -08
पडचर0 Puducherry 184 184 0 00 2203 2195 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 44 44 0 0
दणी Southern Region 24443 24232 -211 -09 259942 255710 -4232 -16
cबहार Bihar 1901 1888 -13 -07 21939 21671 -268 -12
दामोदर घाट0 13नगम DVC 1411 1410 -1 -01 16939 16767 -172 -10
झारखiड Jharkhand 592 588 -4 -07 7021 6890 -131 -19
ओkडशा Odisha 2011 2009 -2 -01 24273 24109 -164 -07
पिचम बगाल West Bengal 3546 3544 -2 -01 42938 42803 -135 -03
सिpकम Sikkim 54 54 0 00 377 377 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 220 165 -55 -250
पव Eastern Region 9515 9493 -22 -02 113487 112617 -870 -08
अrणाचल दश Arunachal Pradesh 59 58 -1 -16 564 530 -34 -60
असम Assam 636 618 -18 -29 8068 7604 -464 -58
मsणप र Manipur 69 68 -1 -15 769 741 -28 -36
मघालय Meghalaya 156 156 0 00 1690 1582 -108 -64
मज़ोरम Mizoram 42 41 -1 -17 429 414 -15 -35
नागालvड Nagaland 61 60 -1 -16 693 678 -15 -22
cwप रा Tripura 88 87 -2 -18 1079 1026 -53 -49उरउरउरउर-पव North-Eastern Region 1111 1087 -23 -21 13291 12572 -719 -54
सपण+ भारत All India 88787 87317 -1469 -17 1017954 995980 -21974 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
23
रा3यState
5व6यत आप9त + िथ9त (पवा+वलोकन) Power Supply Position (Provisional)
Surplus Deficit (-) Surplus Deficit (-)
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh197 197 0 00 342 342 0 00
दलamp Delhi3849 3845 -4 -01 5846 5846 0 00
ह+रयाणा Haryana 6799 6799 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1457 1457 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2397 2034 -363 -151 2544 2158 -386 -152
पजाब Punjab 5974 5974 0 00 10852 10852 0 00
राजAथान Rajasthan 10190 10190 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13463 12558 -905 -67 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 1964 -70 -34 2034 2034 0 00उरीउरीउरीउरी Northern Region41547 39842 -1705 -41 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3932 3564 -368 -94 3932 3757 -175 -45
गजरात Gujarat 12745 12735 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10130 10124 -6 -01 10902 10902 0 00
महाराLM Maharashtra 19015 18994 -21 -01 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli726 726 0 00 740 740 0 00
गोवा Goa 428 428 0 00 583 552 -31 -53
पिचमी Western Region45110 45070 -40 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 7104 7104 0 00 7104 7104 0 00
तलगाना Telangana 6398 6398 0 00 6854 6849 -5 -01
कनाYटक Karnataka 9971 9397 -574 -58 9971 9397 -574 -58
करल Kerala 3710 3706 -3 -01 3762 3706 -56 -15
त[मल नाड Tamil Nadu 14176 14171 -5 00 14176 14171 -5 00
पडचरamp Puducherry 322 322 0 -01 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37053 37053 0 00 37801 37053 -748 -20
aबहार Bihar 3289 3289 0 00 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2219 2219 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1020 1020 0 00 1151 1127 -24 -21
ओjडशा Odisha 4055 4055 0 00 4055 4055 0 00
पि9चम बगाल West Bengal 7374 7374 0 00 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17456 17456 0 00 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh139 135 -4 -29 139 135 -4 -29
असम Assam 1333 1327 -6 -05 1491 1378 -113 -76
मqणपर Manipur 158 158 0 00 168 167 -1 -06
मघालय Meghalaya 322 322 0 00 400 377 -23 -58
[मज़ोरम Mizoram 101 99 -2 -20 102 101 -1 -10
नागालtड Nagaland 119 118 -1 -08 140 138 -2 -14
auपरा Tripura 227 227 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2401 2328 -73 -30 2573 2356 -217 -84
सपण+ भारत All India142146 140346 -1800 -13 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
Surplus Deficit (-) Surplus Deficit (-)
अ4धकतम माग और अ4धकतम उपलिध (पवा+वलोकन) Peak Demand and Peak Met (Provisional)
राEयState
आकड़ मगा वाट नट Figures in MW net
24
फरवर 2016 February2016 अल2015 - फरवर 2016 April2015 to February2016
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
आकड़ मलयन य13नट नट Figures in MU net
आवयकता उपलधता अधशष कमी (-) आवयकता उपलधता अधशष कमी (-)
णाल System Requirement Availability Requirement Availability
Region ( MU ) ( MU ) ( MU ) ( ) ( MU ) ( MU ) ( MU ) ( )
चडीगढ़ Chandigarh 116 116 0 00 1404 1404 0 00
-दल0 Delhi 1970 1965 -4 -02 25922 25883 -39 -02
ह5रयाणा Haryana 3644 3644 0 00 40826 40757 -69 -02
-हमाचल दश Himachal Pradesh 775 768 -7 -09 7373 7313 -60 -08
जम कमीर Jammu amp Kashmir 1587 1350 -238 -150 13658 11561 -2097 -154
प जाब Punjab 3073 3073 0 00 43786 43774 -12 00
राजHथान Rajasthan 6568 6476 -92 -14 55935 55731 -204 -04उरउरउरउर दश Uttar Pradesh 8340 7384 -955 -115 90199 78724 -11475 -127उराखडउराखडउराखडउराखड Uttarakhand 1135 1105 -31 -27 10894 10686 -208 -19उरीउरीउरीउरी Northern Region 27208 25880 -1327 -49 289997 275832 -14165 -49छीसगढ़ Chhattisgarh 2044 2023 -21 -10 21333 21015 -318 -15
गजरात Gujarat 8437 8437 0 00 86319 86315 -4 00
मPय दश Madhya Pradesh 6358 6358 0 00 51208 51208 0 00
महाराRS Maharashtra 11297 11255 -42 -04 117518 117065 -453 -04
दमन और -दउ Daman amp Diu 198 198 0 00 1943 1943 0 00
दादर व नगर हवल0 Dadra amp Nagar
Haveli 501 501 0 00 4915 4915 0 00
गोवा Goa 434 434 0 00 4284 4283 -1 00
पिचमी Western Region 29269 29206 -63 -02 287520 286744 -776 -03
आYZ दश Andhra Pradesh 4122 4122 -1 00 41316 41247 -69 -02
तलगाना Telangana 4030 4030 -1 00 41533 41228 -305 -07
कना]टक Karnataka 5719 5495 -224 -39 52069 49233 -2836 -54
करल Kerala 1931 1931 0 00 19045 18931 -114 -06
तमल नाड Tamil Nadu 7887 7886 -1 00 79517 78829 -688 -09
पडचर0 Puducherry 189 189 0 00 2019 2011 -8 -04
ल^-ीप Lakshadweep 4 4 0 0 40 40 0 0
दणी Southern Region 23878 23652 -226 -09 235499 231478 -4021 -17
cबहार Bihar 2141 2133 -8 -04 20038 19783 -255 -13
दामोदर घाट0 13नगम DVC 1510 1476 -34 -22 15528 15357 -171 -11
झारखiड Jharkhand 706 661 -45 -63 6429 6302 -127 -20
ओkडशा Odisha 2074 2073 -1 -01 22262 22100 -162 -07
पिचम बगाल West Bengal 3477 3475 -2 -01 39392 39259 -133 -03
सिpकम Sikkim 39 39 0 -01 323 323 0 00
अडमान-13नकोबार Andaman- Nicobar 20 15 -5 -25 200 150 -50 -250
पव Eastern Region 9947 9857 -89 -09 103972 103124 -848 -08
अrणाचल दश Arunachal Pradesh 61 60 -1 -16 505 472 -33 -65
असम Assam 683 669 -14 -20 7432 6986 -446 -60
मsणप र Manipur 80 78 -2 -28 700 673 -27 -39
मघालय Meghalaya 185 167 -18 -97 1534 1426 -108 -70
मज़ोरम Mizoram 46 45 -1 -22 387 373 -14 -36
नागालvड Nagaland 67 65 -2 -30 632 618 -14 -22
cwप रा Tripura 53 52 -1 -19 991 939 -52 -52उरउरउरउर-पव North-Eastern Region 1175 1136 -39 -33 12180 11485 -695 -57
सपण+ भारत All India 91476 89731 -1745 -19 929167 908663 -20504 -22
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
25
रा3यState
5व6यत आप9त + िथ9त (सशोधत) Power Supply Position (Revised)
Surplus Deficit (-) Surplus Deficit (-)
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
अधकतम माग अधकतम उपलिध अधशष कमी (-) अधकतम माग अधकतम उपलिध अधशष कमी (-)
णाल System Peak Demand Peak Met Peak Demand Peak Met
Region ( MW ) ( MW ) ( MW ) ( ) ( MW ) ( MW ) ( MW ) ( )
चडीगढ़ Chandigarh248 248 0 00 342 342 0 00
दलamp Delhi4176 4125 -51 -12 5846 5846 0 00
ह+रयाणा Haryana 7045 7045 0 00 9113 9113 0 00
हमाचल 1दश Himachal Pradesh 1480 1480 0 00 1488 1488 0 00
ज7म क9मीर Jammu amp Kashmir 2544 2158 -386 -152 2544 2158 -386 -152
पजाब Punjab 6118 6118 0 00 10852 10852 0 00
राजAथान Rajasthan 10720 10720 0 00 10961 10961 0 00उरउरउरउर 1दश Uttar Pradesh 13862 11625 -2237 -161 16988 14503 -2485 -146उराखडउराखडउराखडउराखड Uttarakhand 2034 2034 0 00 2034 2034 0 00उरीउरीउरीउरी Northern Region44124 42109 -2015 -46 54474 50622 -3852 -71छीसगढ़ Chhattisgarh 3472 3377 -95 -27 3929 3757 -172 -44
गजरात Gujarat 12892 12882 -10 -01 14495 14448 -47 -03
मJय 1दश Madhya Pradesh 10796 10796 0 00 10902 10902 0 00
महाराLM Maharashtra 18188 18156 -32 -02 20973 20594 -379 -18
दमन और दउ Daman amp Diu 301 301 0 00 307 307 0 00
दादर व नगर हवलamp Dadra amp Nagar
Haveli729 729 0 00 740 740 0 00
गोवा Goa 427 427 0 00 583 552 -31 -53
पिचमी Western Region45267 45204 -63 -01 48640 48199 -441 -09
आUV 1दश Andhra Pradesh 6868 6850 -18 -03 7032 6913 -119 -17
तलगाना Telangana 6370 6348 -22 -03 6854 6849 -5 -01
कनाYटक Karnataka 9734 9137 -597 -61 9734 9335 -399 -41
करल Kerala 3537 3537 0 00 3762 3632 -130 -35
त[मल नाड Tamil Nadu 13207 13207 0 00 13580 13505 -75 -06
पडचरamp Puducherry 320 319 -1 -02 368 350 -18 -49
ल-ीप Lakshadweep 8 8 0 0 8 8 0 0
दणी Southern Region37412 36745 -667 -18 37801 36786 -1015 -27
aबहार Bihar 3634 3484 -150 -41 3735 3484 -251 -67
दामोदर घाटamp dनगम DVC 2421 2421 0 00 2814 2794 -20 -07
झारखhड Jharkhand 1117 1117 0 00 1151 1127 -24 -21
ओjडशा Odisha 3739 3739 0 00 4015 4015 0 00
पि9चम बगाल West Bengal 6261 6240 -21 -03 7905 7885 -20 -03
[सिnकम Sikkim 109 109 0 00 109 109 0 00
अडमान-dनकोबार Andaman- Nicobar 40 32 -8 -20 40 32 -8 -20
पव Eastern Region17213 17043 -170 -10 18076 17972 -104 -06
अpणाचल 1दश Arunachal Pradesh118 117 -1 -08 138 132 -6 -43
असम Assam 1339 1330 -9 -07 1491 1378 -113 -76
मqणपर Manipur 168 166 -2 -12 168 167 -1 -06
मघालय Meghalaya 379 377 -2 -05 400 377 -23 -58
[मज़ोरम Mizoram 102 101 -1 -10 102 101 -1 -10
नागालtड Nagaland 122 122 0 00 140 138 -2 -14
auपरा Tripura 219 219 0 00 300 269 -31 -103उरउरउरउर-पव North-Eastern
Region 2367 2332 -35 -15 2573 2356 -217 -84
सपण+ भारत All India137790 135383 -2407 -17 153366 148463 -4903 -32
Lakshadweep and Andaman amp Nicobar Islands are stand- alone systems power supply position of thesedoes not form part of regional requirement and availability
26
जनवर 2016 January2016 अल2015 -जनवर 2016 April2015 to January2016
Surplus Deficit (-) Surplus Deficit (-)
अधकतम माग और अधकतम उपलिFध (सशोधत) Peak Demand and Peak Met (Revised)
राPयState
आकड़ मगा वाट नट Figures in MW net
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
राय State Region ऊजा कटौती Energy Cut माग कटौती Demand cutउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi NIL NIL
हरयाणा Haryana NIL NIL
हमाचल दश Himachal Pradesh NIL NIL
ज+म कमीर Jammu amp Kashmir
प जाब Punjab NIL NIL
राज7थान Rajasthan NIL NILउरउरउरउर दश Uttar Pradesh NIL NILउराखडउराखडउराखडउराखड Uttarakhand 0049 MU cut on HTLT industries 140 MW cut on HTLT industries
पि)चमी Western Regionछीसगढ़ Chhattisgarh NIL NIL
गजरात Gujarat
मAय दश Madhya Pradesh NIL NIL
महाराCD Maharashtra NIL NIL
गोवा Goa NIL NIL
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry
पव0 Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
27
फरवर2 2016 म8 इडlt2ज पर =वgtयत कटौती का =ववरण Notified Power CutsRestrictions on Industries during February 2016
Nil
Nil
Nil
All industries are allowed to run their units on all days of week and if they want to avail staggered holiday then they
have to be staggered on notified day only and cannot avail as per their choice All industries are required to keep their
recess timings staggered
Nil
Nil
Data not received
Nil
No Notified Cuts
No Notified Cuts
No Notified Cuts
No Notified Cuts
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
राय State Regionउरीउरीउरीउरी Northern Region
चडीगढ़ Chandigarh
दल Delhi
हरयाणा Haryana
हमाचल दश Himachal Pradesh
ज+म कमीर Jammu amp Kashmir
पजाब Punjab
राज7थान Rajasthanउरउरउरउर दश Uttar Pradeshउराखडउराखडउराखडउराखड Uttarakhandपिचमी Western Regionछीसगढ़ Chhattisgarhगजरात Gujarat
मAय दश Madhya Pradesh
महाराCD Maharashtra
गोवा Goa
दणी Southern Region
आHI दश Andhra Pradesh
तलगाना Telangana
कनाLटक Karnataka
करल Kerala
तNमल नाड Tamil Nadu
पडचर Puducherry No Restrictions
पव Eastern Region
Pबहार Bihar
झारखSड Jharkhand
ओUडशा Odisha
पिचम बगाल West Bengal
28
फरवरीफरवरीफरवरीफरवरी 2016 2016 2016 2016 किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण किष को िवत आपत का िववरण Power Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during FebruaryPower Supply to Agricultural Sector during February2016201620162016Three Phase Supply 9 hrsday (Average) Single phase Supply 18 hrsday (Average)
There is no agricultural load in Delhi
Three Phase Supply 1010 hrsday (Average)
HPSEBL has only 2 agriculture consumers and uninterrupted power is being supplied to agriculture sector
Three Phase Supply 18 hrsday
Three Phase Supply 645 hrsday (Average) Single phase Supply( FRPNon FRP Feeders) 2400 hrsday (Average)
औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म औसत िवत आपत13 घट म Average Hours of SupplyAverage Hours of SupplyAverage Hours of SupplyAverage Hours of Supply
About 18 hrs
About 20 hrs
Three Phase Supply 1033 hrsday (Average) Single phase Supply 2400 hrsday (Average)
Three Phase Supply 07 hrsday
Three Phase Supply(Mixed) 2321 hrs day (Average)
Only 08 hours power supply in staggered form in rotation of day and night is given to Agriculture Single Phase supply
during rest of 16 hours Jyotigram Yojana 24 hrs
Data not received
24 hrs
Three Phase Supply 6 hrsday Single Phase Supply 6 - 12 hrsday
Three Phase Supply 1051 hrsday (Average) Single phase Supply 1318 hrsday (Average)
Three Phase Supply 2321 hrsday (Average) Single phase Supply 2321 hrsday (Average)
Three Phase Supply 07 hrsday
No restriction
About 23 hrs
No Restrictions
Three Phase Supply 9 hrsday is ensured (6 hrs during day time and 3 hrs during night time)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Contents Page
1 Growth of Installed Capacity since 6th Plan 29
2 Growth of Transmission Sector since 6th Plan 30
3 All India Yearly Coal consumption for Power Generation (Utilities)
4 All India Annual Per Capita Consumption of Electricity since -2006
5 Average cost of power supply amp Average realisation (Paisakwh)
6 Growth of Rural Electrification amp Pump Sets Energisation
7 Status of Hydro Schemes Cleared by the CEA in February 2016
Section G - Growth of Power Sector
31
32
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
(In MW)
Coal Gas Diesel Total
End of 6th Plan 2631083 54150 17737 2702970 1095 1446002 0 4258472
End of 7th Plan 4123748 234300 16509 4374557 1565 1830763 1814 6363634
End of 8th Plan 5415448 656190 2939 6101028 2225 2165808 90201 8579537
End of 9th Plan 6213088 1116310 113483 7442881 2720 2626876 162839 10504596
End of 10th Plan 7112138 1369171 120175 8601484 3900 3465377 77606 13232921
End of 11th Plan 11202238 1838105 119975 13160318 4780 389904 2450345 19987703
End of Feb 2016 17585788 2450863 99353 20136004 5780 4270342 3882151 28866497
Captive Generation Capacity in Industries having demand of 1 MW and above grid interactive (as on 31-03-13) = 40 726 MW
Coal Gas Diesel Nuclear Hydro Res Total
17585788 2450863 99353 578000 427034 3882151 22925174
29
1 Growth of Installed Capacity Since 6th Plan
All India Generating Installed Capacity ( MW ) (As on 2922016 )
RES (MNRE) TotalPlan Year NuclearThermal
Hydro
Total Installed Capacity 28866497 MW
Coal Gas Diesel Nuclear Hydro Res
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Transmission
System Type
Voltage
(KV) levelUnit
Ach At
the end
of 6th
Plan
Ach At
the end
of 7th
Plan
Ach At the
end of 8th
Plan (as
on
3131997)
Ach At the
end of 9th
Plan (as
on
3132002)
Ach as on
31032007
(End of 10th
Plan)
Ach as
on
31032012
(End of
11th Plan)
Ach as on
29022016
Target
31032017
(End of 12th
Plan)
765 ckm 0 0 0 1160 2184 5250 24073 32250
400 ckm 6029 19824 36142 49378 75722 106819 146008 144819
220 ckm 46005 59631 79600 96993 114629 135980 156139 170980
Total ckm 52034 79455 115742 147531 192535 248049 326220 348049
HVDC ckm 0 0 1634 4738 5872 9432 12938 16872
Total
(AC+HVDC)ckm 52034 79455 117376 152269 198407 257481 339158 364921
765 MVA 0 0 0 0 0 25000 135000 174000
400 MVA 9330 21580 40865 60380 92942 151027 204207 196027
220 MVA 37291 53742 84177 116363 156497 223774 285849 299774
Total AC MVA 46621 75322 125042 176743 249439 399801 625056 669801
HVDC MW 0 0 0 5200 8200 9750 15000 22500
AC+HVDC 46621 75322 125042 181943 257639 409551 640056 692301
Inter-regional
transmission
Capacity
MW 14050 27750 55350 65550
30
AC
Transmission
lines
AC Substations
Transformation
Capacity
2 Growth of Transmission Sector Since 6th Plan
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
2004-05 27800
2005-06 28100
2006-07 30200
2007-08 33000
2008-09 35500
2009-10 36700
2010-11 38700
2011-12 41756
2012-13 45460
2013-14 48940
2014-15 53148
Provisional
Year
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2004-05 254 209 7568
2005-06 260 221 7636
2006-07 276 227 7423
2007-08 293 239 7727
2008-09 340 263 8713
2009-10 355 268 8870
2010-11 398 303 11975
2011-12 455 330 13514
2012-13 501 376 14867
Source- PFC Reports on the performance of State Power Utilities
31
6719
7171
3 All India yearly Coal Consumption for Power Generation (Utilities)
YEARCoal Consumption
Million Tonnes
4 All India Annual per Capita consumption of Electricity Since 2006
Per Capita Consumption ( kWh)
6314
(GrossGen+ Net Import) Mid-year population Provisional
5 Average cost of power supply amp average realization ( paiseKWH )
Yearcost of supply
(paiseunit)
Realization(paiseunit)
Including AgricultureOnly
Agriculture
957
7335
7786
91441
8188
88363
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Sl
NoExecuting Agency Installed Capacity (MW) Cost (Rs crore)
Date of
Clearance
32
7 Status of Hydro Schemes Cleared by the CEA in January 2016
Name of Scheme
2093
5743
9769
Cumu upto End of 10th
Plan
311060316074
010407 to 310308
6 Growth Of Rural Electrification amp Pumpsets Energisation
Plan Year
9th Plan
2002-0313409
2626
4111
Pump Sets Energised Villages Electricfied (Nos)
2001-02
284064367244
1218
27801997-981998-991999-002000-01
297594
010408 to 310309010409 to 310310010410 to 310311
10th Plan
3207
482864
12632
1576036
44517
2005-062006-07 22594
2003-042004-05
65109527813884
557439
15455554
2314176
322968331020397343611750
010411 to 310312
412667
No of villages electrified is reduced due to revision of data by states as per new definition of villiage electrification since 2004-05
65291374575 296361511th Plan
Cumu upto End of 11th Plan
583738 20420861
Disclaimer The data included in monthly Progress reports of Village electrification published by
CEA is provisional in nature as Indicated in all the reports The data in the report prior to October
2015 was Updated every month based on the information received from statesdistribution
utilities as and when reported but the data for all the states for a particular month was generally
not made available simultaneously to reflect the countrywide picture for a particular month
Number of total villages and number of electrified villages have also been adjusted for changes
observed from Census 2011 data As such each monthly report of Village electrification of CEA
is independent of the earlier published reports
NIL
Commulative upto Jan 16
8629372646708
18423975
499150557976840909
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SN Contents Page
1 Rate of sale of power for the year 2013-2014 33 - 41
RATE OF SALE OF POWER FOR THE YEAR 2013-2014
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
Name of UtilityPower Station UTILITY
Energy Source-
CoalGas
NapthaLSHS
DieselHydro
Net Gen
(Mkwh)
Rate of Sale of Power
as approved by
CERCSERC
(PaiseKwh) iii=( i+ii)
NORTHERN REGION
CENTRAL SECTOR
BHAKRA (RB+LB)+GANGUWAL+KOTLA Ω BBMB HYDRO-HYDRO 716351 2763
DEHAR H P S Ω BBMB HYDRO-HYDRO 311597 5992
PONG H P S Ω BBMB HYDRO-HYDRO 175078 1797
BAIRA SIUL HPS NHPC LTD HYDRO-HYDRO 62600 15440
CHAMERA- I HPS NHPC LTD HYDRO-HYDRO 234400 20120
CHAMERA- II HPS NHPC LTD HYDRO-HYDRO 139200 27400
CHAMERA- IIi HPS NHPC LTD HYDRO-HYDRO 93100 37660
PARBATI - IIi HPS NHPC LTD HYDRO-HYDRO 500 74100
DHAULI GANGA HPS NHPC LTD HYDRO-HYDRO 27900 29060
CHUTAK NHPC LTD HYDRO-HYDRO 3300 62560
DULHASTI HPS NHPC LTD HYDRO-HYDRO 212900 61580
SALAL HPS NHPC LTD HYDRO-HYDRO 323800 9580
TANAKPUR HPS NHPC LTD HYDRO-HYDRO 37800 22980
URI HPS NHPC LTD HYDRO-HYDRO 251600 16100
URI HPS - II NHPC LTD HYDRO-HYDRO 40100 33340
NIMMO-BAZGO NHPC LTD HYDRO-HYDRO 6900 98520
SEWA - II NHPC LTD HYDRO-HYDRO 49600 43280
ANTA CCPP NTPC LTD THERMAL-GAS 194824 36000
AURAIYA CCPP NTPC LTD THERMAL-GAS 175636 43700
BADARPUR TPS NTPC LTD THERMAL-COAL 380810 46900
DADRI COAL- I (NCTPP) NTPC LTD THERMAL-COAL 543508 41200
DADRI COAL - II (NCTPP) NTPC LTD THERMAL-COAL 720196 46700
DADRI CCPP NTPC LTD THERMAL-GAS 340586 42100
FARIDABAD CCPP NTPC LTD THERMAL-GAS 169820 35600
RIHAND STPS I NTPC LTD THERMAL-COAL 690904 21500
RIHAND STPS ii NTPC LTD THERMAL-COAL 680289 22400
RIHAND STPS III NTPC LTD THERMAL-COAL 340774 27500
SINGRAULI STPS NTPC LTD THERMAL-COAL 1480981 17100
TANDA TPS NTPC LTD THERMAL-COAL 314024 39400
UNCHAHAR TPS I NTPC LTD THERMAL-COAL 299729 35700
UNCHAHAR TPS II NTPC LTD THERMAL-COAL 290114 35800
UNCHAHAR TPS III NTPC LTD THERMAL-COAL 138847 40500
NARORA APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR236268 24856
RAJASTHAN APS 2345 amp6 NPCILNUCLEAR-
NUCLEAR836174 34339
NJHPS SJVNL HYDRO-HYDRO 713153 28740
TEHRI HPP THDC HYDRO-HYDRO 402152 46200
KOTESHWAR HEP THDC HYDRO-HYDRO 150541 36800
NEYVELI BARSINGSAR NEYVELI LIGNITE CORP LTD THERMAL-LIG 138041 38331
STATE SECTOR
PANIPAT TPS - I (Unit 1 to 4) HPGCL THERMAL-COAL 33016 50100
PANIPAT TPS - II (Unit 5) HPGCL THERMAL-COAL 41546 37300
PANIPAT TPS - II (Unit 6) HPGCL THERMAL-COAL 76970 41400
PANIPAT TPS - II (Unit 7) HPGCL THERMAL-COAL 157374 39500
PANIPAT TPS - II (Unit 8) HPGCL THERMAL-COAL 157001 39500
DCRTPP (UNIT 1 TO 2) Y NAGAR HPGCL THERMAL-COAL 315789 33800
RGTPP (UNIT 1TO 2) KHEDAR HISSAR HPGCL THERMAL-COAL 412600 36300WYC HYDEL STATION amp KAKROI HYDEL
PLANT HPGCL HYDRO-HYDRO 20291 11100
GIRI POWER HOUSE HPSEB HYDRO-HYDRO 23066 7200
ANDHRA POWER HOUSE HPSEB HYDRO-HYDRO 7755 10100
GUMMA HPSEB HYDRO-HYDRO 000 27100
BHABA POWER HOUSESANJAY P HOUSE HPSEB HYDRO-HYDRO 53417 6600
P-33
RATE OF SALE OF POWER FOR THE YEAR 2013-14
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
GHANVI POWER HOUSE HPSEB HYDRO-HYDRO 7602 12300
BASSI POWER HOUSE HPSEB HYDRO-HYDRO 22785 9700
BINWA POWER HOUSE HPSEB HYDRO-HYDRO 1924 20400
GAJ POWER HOUSE HPSEB HYDRO-HYDRO 4648 29900
BANER POWER HOUSE HPSEB HYDRO-HYDRO 4254 138700
HOLI POWER HOUSE HPSEB HYDRO-HYDRO 830 19500
THIROT POWER HOUSE HPSEB HYDRO-HYDRO 1385 27300
KHAULI POWER HOUSE HPSEB HYDRO-HYDRO 4545 25500
LARJI POWER HOUSE HPSEB HYDRO-HYDRO 59755 39000
NOGLI POWER HOUSE HPSEB HYDRO-HYDRO 593 22100
CHABA POWER HOUSE HPSEB HYDRO-HYDRO 478 27400
CHAMBA POWER HOUSE HPSEB HYDRO-HYDRO 149 10800
SAL-II POWER HOUSE HPSEB HYDRO-HYDRO 665 10500
GAS TURBINE POWER STATION IPGCL THERMAL-GAS 100679 39640
RAJGHAT POWER HOUSE IPGCL THERMAL-COAL 32300 48830
PPS-I PPCL THERMAL-COAL 235911 31410
PPS-III PPCL THERMAL-GAS 61732 42590
LOWER JHELUM JampKPDD HYDRO-HYDRO 51607 6100
UPPER SINDH -I SUMBAL KANGAN JampKPDD HYDRO-HYDRO 9092 6000
UPPER SINDH -II KANGAN JampKPDD HYDRO-HYDRO 21421 8300
GANDHARBAL JampKPDD HYDRO-HYDRO 2286 4200
BAGLLIHAR HEP JampKPDD HYDRO-HYDRO 276414 30000
KARNAH MPH JampKPDD HYDRO-HYDRO 562 29000
CHENANI I JampKPDD HYDRO-HYDRO 7831 7100
CHENANI II JampKPDD HYDRO-HYDRO 679 9400
CHENANI III UDHAMPUR JampKPDD HYDRO-HYDRO 1750 13700
SEWA-III JampKPDD HYDRO-HYDRO 488 19400
IQBAL MHP KARGIL JampKPDD HYDRO-HYDRO 419 17700
HUNDER MHP JampKPDD HYDRO-HYDRO 077 25100
SUMOOR JampKPDD HYDRO-HYDRO 008 33200
BAZGO MHP JampKPDD HYDRO-HYDRO 035 31800
IGO MERCELLONG JampKPDD HYDRO-HYDRO 230 45100
PAHALGAM MHP JampKPDD HYDRO-HYDRO 425 52000
MARPACHOO JampKPDD HYDRO-HYDRO 088 46900
HAFTAL JampKPDD HYDRO-HYDRO 129 45400
BADERWAH POWER HOUSE JampKPDD HYDRO-HYDRO 253 14600
STAKNA JampKPDD HYDRO-HYDRO 011 4000
GNDTPLANT BATHINDA PUNJAB STATE POWER COR
LTDTHERMAL-COAL 145289 51000
GGSSTPLANT ROOP NAGAR PUNJAB STATE POWER COR
LTDTHERMAL-COAL 734046 51000
GHTPLANT LEHRA MOHABAT PUNJAB STATE POWER COR
LTDTHERMAL-COAL 611743 51000
SHANAN POWER HOUSE JOGINDER NGR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 35122 51000
UBDCPATHANKOT MALIKPUR PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 36163 51000
ASHP ANANDPUR SAHIB PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 73439 51000
MUKERIAN HYDEL TALWARA PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 124674 51000
RANJIT SAGAR Dam(RSD) SHAPUR
KANDI
PUNJAB STATE POWER COR
LTDHYDRO-HYDRO 157060 51000
KOTA THERMAL POWER STATION RRVUNL THERMAL-COAL 852628 34240
SURATGARH THERMAL POWER STATION RRVUNL THERMAL-COAL 855632 42125
CHHABRA TPS RRVUNL THERMAL-COAL 258295 36707
RAMGARH GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 48550 46368
DHOLPUR GAS THERMAL POWER STATION RRVUNL THERMAL-GAS 99307 42330
MAHI HYDEL POWER STATION RRVUNL HYDRO-HYDRO 22558 9611
MINI MICRO HYDEL (MMH) POWER STATION RRVUNL HYDRO-HYDRO 1020 37800
GIRAL -II RRVUNL THERMAL-COAL 16128 30500
KHARA HEP UPJVNL HYDRO-HYDRO 41588 7200
MATATILLA HEP UPJVNL HYDRO-HYDRO 11555 5500
OBRA HEP UPJVNL HYDRO-HYDRO 20292 5300
RIHANDPIPRA HEP UPJVNL HYDRO-HYDRO 50265 5500UGC PS(NIRGAJINI CHITORA SALAWA
BHOLA)UPJVNL HYDRO-HYDRO 1926 21300
P-34
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
ANPARA A TPS UPRVUNL THERMAL-COAL 335192 18586
ANPARA B TPS UPRVUNL THERMAL-COAL 713263 23461
HARDUAGANJ TPS UPRVUNL THERMAL-COAL 7378 44469
HARDUAGANJ EXTN TPS UPRVUNL THERMAL-COAL 237568 54697
OBRA A TPS UPRVUNL THERMAL-COAL 48284 28640
OBRA B TPS UPRVUNL THERMAL-COAL 306577 23911
PANKI TPS UPRVUNL THERMAL-COAL 62700 43434
PARICHHA TPS UPRVUNL THERMAL-COAL 41241 39411
PARICHHA EXTNTPS UPRVUNL THERMAL-COAL 226278 36628
PARICHHA EXTN ST 2 TPS UPRVUNL THERMAL-COAL 111717 44596
CHIBRO (YAMUNA) HPS UTTARAKHAND JVNL HYDRO-HYDRO 93760 5842
CHILLA HPS UTTARAKHAND JVNL HYDRO-HYDRO 48603 6625
DHAKRANI HPS UTTARAKHAND JVNL HYDRO-HYDRO 5717 6837
DHALIPUR HPS UTTARAKHAND JVNL HYDRO-HYDRO 12365 8429
KHATIMA HPS UTTARAKHAND JVNL HYDRO-HYDRO 9329 6290
KHODRI HPS UTTARAKHAND JVNL HYDRO-HYDRO 21207 7568
KULHAL HPS UTTARAKHAND JVNL HYDRO-HYDRO 6724 6393
TILOTH HPS UTTARAKHAND JVNL HYDRO-HYDRO 43661 10305
MANERI BHALI - II HPS UTTARAKHAND JVNL HYDRO-HYDRO 114267 14144
RAMGANGA HPS UTTARAKHAND JVNL HYDRO-HYDRO 17733 7652
PRIVATE SECTOR
INDIRA GANDHI STPP(IGSTPP) ARAVALI POWER CO PVT THERMAL-COAL 492362 50932MAHATMA GANDHI THERMAL POWER
PLANT JHAJJAR POWER LTD THERMAL-COAL 581305 39180
BASPA-II HEP J P POWER VENTURES HYDRO-HYDRO 134532 23200
VISHNU PRAYAG HEP J P POWER VENTURES HYDRO-HYDRO 178673 20300
KARCHAM WANGTOO HEP J P POWER VENTURES HYDRO-HYDRO 490638 31500
MALANA HPS MALANA PCL HYDRO-HYDRO 23861 27992
MALANA - II HPS EVEREST PPL HYDRO-HYDRO 27762 41940
ALLAIN DUHANGAN HEP AD HYDRO POWER LTD HYDRO-HYDRO 57350 53107
RENUSAGAR DIVISION HINDALCO IND LTD THERMAL-COAL 613385 000
RAJ WESTPOWER LTD RAJASTHAN JSW ENERGY LTD THERMAL-LIG 369734 37540
RITHALA COMBI CYCLE POWER PLANT TATA POWER DDL THERMAL-GAS 030 000
ROJA THERMAL POWER PLANT PH-I ROJA POWER SCL THERMAL-COAL 741400 52300
KHAMBERKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46521 22400
BARKHERA BAJAJ ENERGY PVT LTD THERMAL-COAL 46902 22300
MAQSOODAPUR BAJAJ ENERGY PVT LTD THERMAL-COAL 48375 22300
UTRAULA BAJAJ ENERGY PVT LTD THERMAL-COAL 50228 23200
KUNDARKHI BAJAJ ENERGY PVT LTD THERMAL-COAL 46464 22400
WESTERN REGION
CENTRAL SECTOR
INDIRA SAGAR HPS NHDC LTD HYDRO-HYDRO 404891 17981
OMKARESHWAR HPS NHDC LTD HYDRO-HYDRO 161995 30306
GANDHAR CCPP NTPC LTD THERMAL-GAS 124377 32100
KAWAS CCPP NTPC LTD THERMAL-GAS 131439 29300
KORBA I amp II NTPC LTD THERMAL-COAL 1579249 15200
KORBA III NTPC LTD THERMAL-COAL 361664 25800
SIPAT STPS I NTPC LTD THERMAL-COAL 1184432 29400
SIPAT STPS II NTPC LTD THERMAL-COAL 631123 28400
VINDHYACHAL STPS I NTPC LTD THERMAL-COAL 854994 22100
VINDHYACHAL STPS II NTPC LTD THERMAL-COAL 732972 21200
VINDHYACHAL STPS III NTPC LTD THERMAL-COAL 752721 26000
VINDHYACHAL STPS IV NTPC LTD THERMAL-COAL 350633 30500
MOUDA i NTPC LTD THERMAL-COAL 71866 46000
KAKRAPARA 1 amp 2 NPCIL NUCLEAR-
NUCLEAR337293 23731
TARAPUR 1 amp 2 NPCIL NUCLEAR-
NUCLEAR196830 9679
TARAPUR 3 amp 4 NPCIL NUCLEAR-
NUCLEAR699895 28511
RGPPL ANJANVEL NTPC+GAIL) RATNAGIRI GPPL THERMAL-GAS 146474 43008
STATE SECTOR
KORBA TPS EAST CSPGCL THERMAL-COAL 189873 22496
P-35
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
DSPM TPS KORBA EAST CSPGCL THERMAL-COAL 243116 23640
KORBA-WEST EXTENSION TPS CSPGCL THERMAL-COAL 158509 26500
HASDEO TPS KORBA WEST CSPGCL THERMAL-COAL 548553 16850
GANGREL HEP CSPGCL HYDRO-HYDRO 4285 37650
BANGO HEP CSPGCL HYDRO-HYDRO 23609 8880
MINI HYDEL (SHP KW) CSPGCL HYDRO-HYDRO 825 42010
SIKASAR HEP CSPGCL HYDRO-HYDRO 991 27120
DHUVARAN CCPP-1 GSECL THERMAL-GAS 3821 162285
DHUVARAN CCPP-2 GSECL THERMAL-GAS 14826 82554
GANDHI NAGAR TPS 1-4 GSECL THERMAL-COAL 61350 82249
GANDHI NAGAR TPS 5 GSECL THERMAL-COAL 109652 38625
KUTCH LIG TPS 1-3 GSECL THERMAL-LIG 125156 31275
KUTCH LIG TPS 4 GSECL THERMAL-LIG 30140 44736
SIKKA TPS GSECL THERMAL-COAL 52514 64562
UKAI 1-5 GSECL THERMAL-COAL 324942 34959
UKAI TPS 6 GSECL THERMAL-COAL 124316 37645
WANAKBORI TPS 1-6 GSECL THERMAL-COAL 358832 42987
WANAKBORI TPS 7 GSECL THERMAL-COAL 94977 38361
KADANA HPS GSECL HYDRO-HYDRO 40661 14139
UKAI HPS GSECL HYDRO-HYDRO 83428 2860
TONS HYDRO POWER STATION MPPGCL HYDRO-HYDRO 165454 11600
BANSAGAR-II MPPGCL HYDRO-HYDRO 14126 10100
BANSAGAR- III MPPGCL HYDRO-HYDRO 12960 11700
JHINNA HPS MPPGCL HYDRO-HYDRO 12473 15100
RANI AVANTI BAI-BARGI HPS MPPGCL HYDRO-HYDRO 53743 3600
GANDHI SAGAR HPS MPPGCL HYDRO-HYDRO 40469 4100
SANJAY GANDHI HPS MPPGCL HYDRO-HYDRO 4756 14800
MADHIKHERA HPS MPPGCL HYDRO-HYDRO 13566 30900
PENCH HPS MPPGCL HYDRO-HYDRO 42631 8000
RAJGHAT HPS MPPGCL HYDRO-HYDRO 6053 16700
AMARKANTAK PH II MPPGCL THERMAL-COAL 114098 23500
AMARKANTAK PH III MPPGCL THERMAL-COAL 150134 33000
SANJAY GANDHI TPHSGTPS PH-I MPPGCL THERMAL-COAL 206390 38700
SANJAY GANDHI TPHSGTPS PH-II MPPGCL THERMAL-COAL 178326 38700
SANJAY GANDHI TPHSGTPS PH-III MPPGCL THERMAL-COAL 346052 38400
SATPURA TPH STPS PH II MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH III MPPGCL THERMAL-COAL 166734 28100
SATPURA TPH STPS PH IV MPPGCL THERMAL-COAL 43551 39700
BHUSAWAL TPS MSPGCL THERMAL-COAL 263700 36100
CHANDRAPUR(MAHARASHTRA) STPS MSPGCL THERMAL-COAL 1274100 22700
KHAPERKHEDA MSPGCL THERMAL-COAL 680700 32900
KORADI TPS MSPGCL THERMAL-COAL 215200 40300
NASIK TPS MSPGCL THERMAL-COAL 377700 42400
PARLI TPS MSPGCL THERMAL-COAL 369100 35600
PARAS MSPGCL THERMAL-COAL 266700 33200
URAN CCPP MSPGCL THERMAL-GAS 365700 27000
KOYANAPOPHALI MSPGCL HYDRO-HYDRO 341000 2600
VAITARANA MSPGCL HYDRO-HYDRO 26000 7900
YELDARI MSPGCL HYDRO-HYDRO 2400 27000
BHATGHAR MSPGCL HYDRO-HYDRO 12200 16500
PANSHET MSPGCL HYDRO-HYDRO 9300 15900
BHIRA MSPGCL HYDRO-HYDRO 9600 5800
TILLARI MSPGCL HYDRO-HYDRO 14400 5800
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 521600 20500
SARDAR SAROVAR PROJECT SSNNL HYDRO-HYDRO 66016 20500
PRIVATE SECTOR
BINA TPP J P POWER VENTURES THERMAL-COAL 156264 48200
MUNDRA TPP GUJARAT ADANI POWER LTD THERMAL-COAL 2712500 28355
TIRODA TPP MAHARASHTRA ADANI POWER LTD THERMAL-COAL 959300 33816
KAWAI TPPRAJASTHAN ADANI POWER LTD THERMAL-COAL 343000 33764
P-36
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
ABHIJEET MADC NAGPUR ENERGY PVT ABHIJEET MADC NAGPUR THERMAL-COAL 602 29200
WPCL-WARORA SAI WARDHA POWER LTD THERMAL-COAL 258607 49500SABARMATI THERMAL POWER STAN
SABARMATITORRENT POWER LTD THERMAL-COAL 246553 32700
ESSAR POWER GUJARAT(EPGL) ESSAR POWER GUJARAT LTD THERMAL-COAL 503200 27190
GOA ENERGY PRIVATE LTD GOA ENERGY THERMAL-GAS 14054 24000
PONTEMOL DIV -VII CURCHOREM GOA SPONGE amp POWER THERMAL-COAL 6562900 24000
165 MW POWER PLANT (STATION- II) GUJARAT INDUSTRIES PCL THERMAL-GAS 15659 88192
145 MW POWER PLANT (STATION- I) GUJARAT INDUSTRIES PCL THERMAL-GAS 85876 54789SURAT LIG POWER PLANT (SLPL
STATION -I)GUJARAT INDUSTRIES PCL THERMAL-LIG 129284 24692
SURAT LIG POWER PPANT (SSPP
STATION -II)GUJARAT INDUSTRIES PCL THERMAL-LIG 133626 32342
AKRIMOTA THERMAL POWER STATION GUJARAT MINERAL DCL THERMAL-LIG 98539 21000
PAGUTHAN CCPP CLP INDIA PVT LTD THERMAL-GAS 24682 286100
MUNDRA UMPPCOASTAL GUJARAT POWER
LTD THERMAL-COAL 2197200 24094
CGPL MUNDRA TATA POWER COM LTD THERMAL-COAL 2197200 24100
LANCO AMARKANTAK TPP PATHADIH LANCO AMARKAN PLTD THERMAL-COAL 206700 30700
BHILAI EXPANSION POWER PLANT NTPC-SAIL POWER COMPRIV
LTD THERMAL-COAL 331861 39772
4X250 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 743600 32800
4X600 MW O P JINDAL STPS JINDAL POWER LTD TAMNAR THERMAL-COAL 5000 20500
RINFRA-GOA RELIANCE INFRAS LTD THERMAL-N 24143 133800
DAHANU TPS RELIANCE INFRAS LTD THERMAL-COAL 373881 34600
TROMBAY UNIT 5 TATA POWER COM LTD THERMAL-COAL 353500 42000
TROMBAY UNIT 6 TATA POWER COM LTD THERMAL-GAS 45400 190600
TROMBAY UNIT 7 TATA POWER COM LTD THERMAL-GAS 124200 37300
TROMBAY UNIT 8 TATA POWER COM LTD THERMAL-COAL 140900 46700
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIRA TATA POWER COM LTD HYDRO-HYDRO 48450 14300
BHIVPURI TATA POWER COM LTD HYDRO-HYDRO 30500 26400
KHOPOLI TATA POWER COM LTD HYDRO-HYDRO 32300 33500
SBU 3 JSW(JINDAL) ENERGY LTD JSW ENERGY LTD THERMAL-COAL 677000 36900
SOTHERN REGION
CENTRAL SECTOR
NEYVELI TPS I NEYVELI LIGNITE CORP LTD THERMAL-LIG 359455 33743
NEYVELI TPS- I EXPN NEYVELI LIGNITE CORP LTD THERMAL-LIG 301359 31429
NEYVELI TPS-II NEYVELI LIGNITE CORP LTD THERMAL-LIG 1010437 26383
R GANDHI (KAYAMKULAM) NTPC LTD THERMAL-N 94715 129800
RAMAGUNDEM STPS I amp II NTPC LTD THERMAL-COAL 1488082 27100
RAMAGUNDEM STPS III NTPC LTD THERMAL-COAL 385728 36500
SIMHADRI I NTPC LTD THERMAL-COAL 717656 34100
SIMHADRI II NTPC LTD THERMAL-COAL 682910 40800
KAIGA 123 amp 4 NPCILNUCLEAR-
NUCLEAR593317 30196
MADRAS APS 1 amp 2 NPCILNUCLEAR-
NUCLEAR189800 20539
STATE SECTOR
APGAS POWER CORPORN
LTD(VIJJESWARAM - I)
ANDHRA PRADESH GPCL THERMAL-GAS 3833 30260
APGAS POWER CORPORN
LTD(VIJJESWARAM -II)
ANDHRA PRADESH GPCL THERMAL-GAS 6337 32830
Dr NTTPS (VIJAYAWADA TPS) APGENCO THERMAL-COAL 814206 35600
Dr NTTPS - IV (VIJAYAWADA TPS - 4) APGENCO THERMAL-COAL 359941 35600
RAYALASEEMA THERMAL POWER
PROJECT-I
APGENCO THERMAL-COAL 230795 35600
RAYALASEEMA THERMAL POWER
PROJECT-II
APGENCO THERMAL-COAL 275620 35600
RAYALASEEMA THERMAL POWER
PROJECT-III
APGENCO THERMAL-COAL 128300 35600
KOTHAGUDEM THERMAL POWER
STATION (OampM)
APGENCO THERMAL-COAL 380420 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-V)
APGENCO THERMAL-COAL 323854 35600
KOTHAGUDEM THERMAL POWER
STATION (KTPS-VI)
APGENCO THERMAL-COAL 324071 35600
RAMAGUNDEM THERMAL POWER
STATION
APGENCO THERMAL-COAL 40072 35600
KAKATHIYA TPP (KTPP) APGENCO THERMAL-COAL 293827 35600
SRISAILAM (OampM0 APGENCO HYDRO-HYDRO 147191 35600
SRISAILAM LEBT BANK HES(SLBHES) APGENCO HYDRO-HYDRO 132521 35600
NAGARJUNASAGAR APGENCO HYDRO-HYDRO 164042 35600
UPPER SILERU APGENCO HYDRO-HYDRO 45142 35600
LOWER SILERU APGENCO HYDRO-HYDRO 124763 35600
DONKARAYI APGENCO HYDRO-HYDRO 11533 35600
P-37
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
PENNA AHOBILAM (PABRHES)) APGENCO HYDRO-HYDRO 478 35600
POCHAMPAD APGENCO HYDRO-HYDRO 8342 35600
SINGUR APGENCO HYDRO-HYDRO 429 35600
NIZAMSAGAR APGENCO HYDRO-HYDRO 1256 35600
PEDDAPALLI MINI HYDELS APGENCO HYDRO-HYDRO 459 35600
CHETTIPETA APGENCO HYDRO-HYDRO 265 35600
MUCHKUND APGENCO HYDRO-HYDRO 31072 35600
TUNGABHADRA HES amp HAMPI PH (AP
Share)
APGENCO HYDRO-HYDRO 15306 35600
PRIYADARSHINI JURALA APGENCO HYDRO-HYDRO 26645 35600
BELLARY TPS KPCL THERMAL-COAL 564935 40103
RAICHUR TPS KPCL THERMAL-COAL 880141 39881
YELHANKA (DG) KPCL THERMAL-DIESEL 1958 216206
ALMATTI DPH HPS KPCL HYDRO-HYDRO 49362 13569
BHADRA HPS KPCL HYDRO-HYDRO 6154 25111
GERUSUPPA HPS KPCL HYDRO-HYDRO 60128 10645
GHAT PRABHA HPS KPCL HYDRO-HYDRO 8034 12967
MGHE JOGFALLS HPS KPCL HYDRO-HYDRO 25660 8392
KADRA HPS KPCL HYDRO-HYDRO 35179 14451
KALINADI HPSNAGJHARI KPCL HYDRO-HYDRO 258317 4940
SUPA HPS KPCL HYDRO-HYDRO 46303 4940
KODASALLI HPS KPCL HYDRO-HYDRO 31594 11133
LIGANAMAKKI HPS KPCL HYDRO-HYDRO 26209 2436
MUNIRABAD HPS KPCL HYDRO-HYDRO 9984 6494
SHARAVATHY HPS KPCL HYDRO-HYDRO 547332 2436
SIVASAMUNDRUM HPS KPCL HYDRO-HYDRO 21371 11053
VARAHI (UG) HPS KPCL HYDRO-HYDRO 128272 9093
MANI DAM POWER HOUSE KPCL HYDRO-HYDRO 3240 9093
SHIMSHAPURA KPCL HYDRO-HYDRO 6665 11053
IDAMALAYAR HPS KSEB HYDRO-HYDRO 38576 46800
IDUKKI HPS KSEB HYDRO-HYDRO 272776 46800
KAKKAD HPS KSEB HYDRO-HYDRO 24661 46800
KALLADA HPS KSEB HYDRO-HYDRO 6734 46800
KUTTIYADI amp KTR KSEB HYDRO-HYDRO 84004 46800
LOWER PERIYAR HPS KSEB HYDRO-HYDRO 59923 46800
MALANKARA HPS KSEB HYDRO-HYDRO 3009 46800
NERIAMANGLAM amp NES KSEB HYDRO-HYDRO 36505 46800
PALLIVASAL HPS KSEB HYDRO-HYDRO 20676 46800
PANNIAR HPS KSEB HYDRO-HYDRO 16956 46800
PORINGALKUTHU+PLBE KSEB HYDRO-HYDRO 23624 46800
SABARIGIRI HPS KSEB HYDRO-HYDRO 163120 46800
SENGULAM HPS KSEB HYDRO-HYDRO 14172 46800
SHOLAYAR HPS KSEB HYDRO-HYDRO 23232 46800
BRAHMAPURAM DG(BDPP) KSEB THERMAL-LSHS 2729 46800
KOZHIKODE DG (KDPP) KSEB THERMAL-LSHS 18677 46800
MINICOY Ω LAKSHADEEP THERMAL-DIESEL 725 286900
KAVARATTI Ω
LAKSHADEEP THERMAL-DIESEL 983 286900
AMINI Ω
LAKSHADEEP THERMAL-DIESEL 464 286900
ANDROTT Ω
LAKSHADEEP THERMAL-DIESEL 628 286900
KALPENI Ω
LAKSHADEEP THERMAL-DIESEL 316 286900
AGATTI Ω
LAKSHADEEP THERMAL-DIESEL 491 286900
KADMAT Ω
LAKSHADEEP THERMAL-DIESEL 376 286900
KILTAN Ω
LAKSHADEEP THERMAL-DIESEL 250 286900
CHETLET Ω
LAKSHADEEP THERMAL-DIESEL 153 286900
BITRA Ω
LAKSHADEEP THERMAL-DIESEL 022 286900
BANGARAM Ω
LAKSHADEEP THERMAL-DIESEL 005 286900
KARAIKAL CCGPP PUDDUCHERRY THERMAL-GAS 24122 38120
ENNORE TN GEN amp DIS CORP LTD THERMAL-COAL 101089 49852
METTUR TN GEN amp DIS CORP LTD THERMAL-COAL 790640 49852
NORTH CHENNAI TN GEN amp DIS CORP LTD THERMAL-COAL 584618 49852
TUTICORIN TN GEN amp DIS CORP LTD THERMAL-COAL 725262 49852
P-38
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
KOVILKALAPPAL TN GEN amp DIS CORP LTD THERMAL-GAS 45662 49852
VALUTHUR TN GEN amp DIS CORP LTD THERMAL-GAS 117871 49852
KUTTALAM TN GEN amp DIS CORP LTD THERMAL-GAS 59415 49852
PYKARA TN GEN amp DIS CORP LTD HYDRO-HYDRO 6211 49852
PYKARA MICRO TN GEN amp DIS CORP LTD HYDRO-HYDRO 918 49852
MOYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14790 49852
MARAVAKANDY TN GEN amp DIS CORP LTD HYDRO-HYDRO 084 49852
KUNDAH-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 26931 49852
KUNDAH-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 65985 49852
KUNDAH-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 37961 49852
KUNDAH-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 14234 49852
KUNDAH-V TN GEN amp DIS CORP LTD HYDRO-HYDRO 7337 49852
KUNDAH-VI (PARSON VALLEY) TN GEN amp DIS CORP LTD HYDRO-HYDRO 4251 49852
METTUR DAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 10441 49852
METTUR TUNNEL TN GEN amp DIS CORP LTD HYDRO-HYDRO 35606 49852
BARRIAGE-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 7321 49852
BARRIAGE-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 6584 49852
BARRIAGE-III TN GEN amp DIS CORP LTD HYDRO-HYDRO 6401 49852
BARRIAGE-IV TN GEN amp DIS CORP LTD HYDRO-HYDRO 5214 49852
BHAVANI SAGAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 2482 49852
POONACHI TN GEN amp DIS CORP LTD HYDRO-HYDRO 496 49852
SATHANOOR TN GEN amp DIS CORP LTD HYDRO-HYDRO 184 49852
MUKURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 191 49852
THIRUMURTHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 051 49852
PERIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 45258 49852
VAIGAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 2712 49852
SURULIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 10010 49852
PAPANASAM TN GEN amp DIS CORP LTD HYDRO-HYDRO 13685 49852
SERVALAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 5004 49852
SARKARPATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 13787 49852
ALIYAR TN GEN amp DIS CORP LTD HYDRO-HYDRO 14371 49852
KADAMPARAI TN GEN amp DIS CORP LTD HYDRO-HYDRO 50120 49852
SHOLAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 19483 49852
SHOLAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 7159 49852
KODAYAR-I TN GEN amp DIS CORP LTD HYDRO-HYDRO 11231 49852
KODAYAR-II TN GEN amp DIS CORP LTD HYDRO-HYDRO 4596 49852
ALIYAR MINI TN GEN amp DIS CORP LTD HYDRO-HYDRO 489 49852
PYKARA ULTIMATE TN GEN amp DIS CORP LTD HYDRO-HYDRO 39648 49852
AMARAVATHY TN GEN amp DIS CORP LTD HYDRO-HYDRO 462 49852
PERUNCHANI TN GEN amp DIS CORP LTD HYDRO-HYDRO 097 49852
BHAVANI RBC TN GEN amp DIS CORP LTD HYDRO-HYDRO 1370 49852
BHAVANI KATTALAI (BKB) TN GEN amp DIS CORP LTD HYDRO-HYDRO 13190 49852
PRIVATE SECTOR
LANCO TANJORE POWER COMPANY LTD LANCO TANJORE PCL THERMAL-GAS 73263 000
BSES KERALA POWER LTD BSES KERALA THERMAL-N 33668 129500GMR BARGE MOUNTED CCP PLANT GMR
ENERGYGMR BMCC POWER PLANT THERMAL-GAS 040 44900
JEGURUPADU CCPP PH-I GVK INDUSTRIS LIMITED THERMAL-GAS 95856 36200
JEGURUPADU CCPP PH-II GVK INDUSTRIS LIMITED THERMAL-GAS 54224 45600
GVK GAUTAMI POWER LIMITED GVK GAUTAMI THERMAL-GAS 000 000SBU 1 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 202900 52700
SBU 2 JSW(JINDAL) ENERGY LTD
VIJAYANAGARJSW ENERGY LTD THERMAL-COAL 456400 52500
LANCO KONDAPALLI POWER LTD PH-ILANCO KONDAPALLI POWER
LTDTHERMAL-GAS 139963 000
LANCO KONDAPALLI POWER LTD PH-IILANCO KONDAPALLI POWER
LTD THERMAL-GAS 000 000
SIMHAPURI ENERGY LTD PH-I SIMHAPURI ENERGY LTD THERMAL-COAL 220400 55400
MADURAI POWER MADURAI POWER CORP THERMAL-LSHS 35450 139700
PPN POWER PPN POWER POWER THERMAL-GAS 145600 000
RINFRA-SPS RELIANCE INFRAS LTD THERMAL-GAS 46630 53600
SAMALPATTI POWER PLANT SAMALPATTI PCPL THERMAL-LSHS 30623 130367
KONASEEMA GAS POWER LTD KONASEEMA GAS THERMAL-GAS 000 31400
UDUPI POWER CORPORATION LTD LANCO UDUPI POWER THERMAL-COAL 637182 44724
P-39
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
SPECTRUM POWER GENERATION LTD SPECTRUM PG LTD THERMAL-GAS 106543 36426
VALLUR THERMAL POWER PLANT NTECL THERMAL-COAL 353531 44213GMR VEMAGIRI POWER GENERATION
LTD GMR VEMAGIRI PGL THERMAL-GAS 17197 118200
EASTERN REGION
CENTRAL SECTOR
BOKARO `B` TPS DVC THERMAL-COAL 152029 41900
CHANDRAPURA(DVC) TPS DVC THERMAL-COAL 434806 41900
DURGAPUR TPS DVC THERMAL-COAL 167885 43278
DURGAPUR STEEL TPS DVC THERMAL-COAL 415723 43278
MEJIA TPS DVC THERMAL-COAL 1195338 43278
KODERMA TPS DVC THERMAL-COAL 139150 41900
MAITHON HPS DVC HYDRO-HYDRO 9757 43278
PANCHET HPS DVC HYDRO-HYDRO 12650 41900
TILLAYA HPS DVC HYDRO-HYDRO 456 41900
RANGIT HPS NHPC LTD HYDRO-HYDRO 34700 29040
TEESTA V HPS NHPC LTD HYDRO-HYDRO 227300 23380
TLDP - III NHPC LTD HYDRO-HYDRO 18900 000
FARAKKA STPS I amp II NTPC LTD THERMAL-COAL 970344 39600
FARAKKA STPS III NTPC LTD THERMAL-COAL 297195 47800
KAHALGAON TPS I NTPC LTD THERMAL-COAL 544944 37600
KAHALGAON TPS II NTPC LTD THERMAL-COAL 846271 38500
TALCHER TPS NTPC LTD THERMAL-COAL 340799 17900
TALCHER KANIHA I NTPC LTD THERMAL-COAL 676567 23500
TALCHER KANIHA II NTPC LTD THERMAL-COAL 1373163 22800
MTPS STAGE - I KANTI BIJLEE UTPADAN N LTD THERMAL-COAL 28198 51140
STATE SECTOR
ANDMAN amp NIC ISLAND ED(53 Stns) ANDMAN amp NIC ISLAND TH-
DIESEL+H+SOLAR27499 185900
Barauni T P S BIHAR STATE POWER GENCO THERMAL-COAL 000 000
EG CANAL HEP V Nagar BIHAR STATE HEPCL HYDRO-HYDRO 2276 24900
SONE EAST CANAL HPS Barun BIHAR STATE HEPCL HYDRO-HYDRO 564 24900
SONE WEST CANAL HPS Dehri BIHAR STATE HEPCL HYDRO-HYDRO 82800 24900
PATRATU TPS Ω JHARKHAND BVNL THERMAL-COAL 73113 76332
SIKIDIRI Ω HYDEL(SUBERNREKHA) JHARKHAND BVNL HYDRO-HYDRO 10951 19869
BALIMELA HPS ODISHA HPCL HYDRO-HYDRO 163196 7112
HIRAKUD HEP ODISHA HPCL HYDRO-HYDRO 68601 9253
CHIPLIMA HEP ODISHA HPCL HYDRO-HYDRO 30617 5219
RENGALI HPS ODISHA HPCL HYDRO-HYDRO 88547 7846
UPPER INDRAVATI HPS ODISHA HPCL HYDRO-HYDRO 244511 8052
UPPER KOLAB HPS ODISHA HPCL HYDRO-HYDRO 85231 3535
MACHHKUND HEP ODISHA HPCL HYDRO-HYDRO 23512 3080
IB VALLEY TPS ODISHA PGCL THERMAL-COAL 254712 20940
J P H Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 099 34100
RIMBI - I Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 003 34100
MEYONGCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 440 34100
RIMBI - II Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 001 34100
KALEZ Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 059 34100
RABOMCHU Ω
GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 074 34100
D P H (GANGTOK DG) Ω
GOVT OF SIKKIM EPDEPTT THERMAL-DIESEL 005 34100
TENUGHAT THERMAL POWER STATION TENUGHAT VIDYUT NIGAM LTD THERMAL-COAL 200143 30764
DURGAPUR PROJECTS LIMITED DPL THERMAL-COAL 169575 44091
KOLAGHAT THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 559229 30349
BAKRESHWAR THERMAL POWER PLANT WEST BENGAL PDCL THERMAL-COAL 628193 32069
BANDEL THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 118825 33822
SANTHALDIH THERMAL POWER STATION WEST BENGAL PDCL THERMAL-COAL 246733 35822
SAGARDIGHI THERMAL POWER PROJECT WEST BENGAL PDCL THERMAL-COAL 295427 32115
P-40
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)
JALDHAKA H E P WEST BENGAL SEDCL HYDRO-HYDRO 15900 65900
RAMAM H E P WEST BENGAL SEDCL HYDRO-HYDRO 26600 65900
TEESTA CANAL FALLS WEST BENGAL SEDCL HYDRO-HYDRO 9900 65900
PURULIA PUMPED STORAGE PROJECT WEST BENGAL SEDCL HYDRO-HYDRO 78500 65900
MINI MICRO WEST BENGAL SEDCL HYDRO-HYDRO 2500 65900
PRIVATE SECTOR
LACHUNG HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 375 30000
MANGLAY HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 384 30000
RONGLI HEP GOVT OF SIKKIM EPDEPTT HYDRO-HYDRO 509 40000
CALCUTTA ELECTRIC SCL CALCUTTA ELECTRIC SCL THERMAL-COAL 817500 61100
DISHERGARH POWER STATION INDIA POWER THERMAL-COAL 1411 42400
RAJRAPPA EASTERN (I) POWERTECH THERMAL-WR 2118 000
GIDI EASTERN (I) POWERTECH THERMAL-WR 2191 000
HIRAKUD POWER HINDALCO IND LTD THERMAL-COAL 289404 27500
JOJOBERA UNIT 1 TATA POWER COM LTD THERMAL-COAL 38500 49100
JOJOBERA UNIT 2 TATA POWER COM LTD THERMAL-COAL 74800 39100
JOJOBERA UNIT 3 TATA POWER COM LTD THERMAL-COAL 66900 38400
JOJOBERA UNIT 4 TATA POWER COM LTD THERMAL-COAL 74200 39900
MAITHON UNIT 1 TATA POWER COM LTD THERMAL-COAL 275900 37600
MAITHON UNIT 2 TATA POWER COM LTD THERMAL-COAL 320500 37600
HALDIA UNIT 1 TATA POWER COM LTD THERMAL-WHR 32600 27700
HALDIA UNIT 2 TATA POWER COM LTD THERMAL-WHR 31900 27700
HALDIA UNIT 3 TATA POWER COM LTD THERMAL-WHR 22500 27700
NORTH EASTERN REGION
CENTRAL SECTOR
LOKTAK HPS NHPC LTD HYDRO-HYDRO 62300 27840
AGARTALA GT NEEPCO THERMAL-GAS 64165 37138
ASSAM GAS BASED P PRO NEEPCO THERMAL-GAS 172642 34221
DOYANG HPS NEEPCO HYDRO-HYDRO 24574 41546
KOPILI + KOPILI II +KHANDONG NEEPCO HYDRO-HYDRO 97317 9505
RANGANADI HPS NEEPCO HYDRO-HYDRO 98091 24376
STATE SECTOR
KARBI LANGPI HPS ASSAM POWER GENCO HYDRO-HYDRO 42040 14250
LAKWA TPS ASSAM POWER GENCO THERMAL-GAS 81747 36477
NAMRUP TPS ASSAM POWER GENCO THERMAL-GAS 49498 37967
LIKIMRO HEP GOVT OF NAGALAND HYDRO-HYDRO 10400 44800
LANG MHP GOVT OF NAGALAND HYDRO-HYDRO 061 44800
UMIAM ST I MEGHALAYA ENE COR LTD HYDRO-HYDRO 6854 9700
UMIAM ST II MEGHALAYA ENE COR LTD HYDRO-HYDRO 4123 13780
UMIAM ST III MEGHALAYA ENE COR LTD HYDRO-HYDRO 13320 13500
UMIAM ST IV MEGHALAYA ENE COR LTD HYDRO-HYDRO 17451 9100
UMTRU MEGHALAYA ENE COR LTD HYDRO-HYDRO 2091 9000
SONAPANI MEGHALAYA ENE COR LTD HYDRO-HYDRO 539 11400
LESHKA MEGHALAYA ENE COR LTD HYDRO-HYDRO 41228 28300
SERLUI-A MIZORAM POWER ELECT HYDRO-HYDRO 057 35900
KHAWIVA MIZORAM POWER ELECT HYDRO-HYDRO 156 35900
TUIPUI MIZORAM POWER ELECT HYDRO-HYDRO 064 35900
MAICHARM -I MIZORAM POWER ELECT HYDRO-HYDRO 206 35900
TEIREI MIZORAM POWER ELECT HYDRO-HYDRO 120 35900
KAU TLABUNG MIZORAM POWER ELECT HYDRO-HYDRO 671 35900
SERLUI -B MIZORAM POWER ELECT HYDRO-HYDRO 4149 35900
LENGPUI DG SET(AIRPORT) MIZORAM POWER ELECT THERMAL-DIESEL 002 35900
BARAMURA GT TRIPURA SECL THERMAL-GAS 27224 51494
ROKHIA GT TRIPURA SECL THERMAL-GAS 44967 51494
GUMTI HPS TRIPURA SECL HYDRO-HYDRO 3428 51494
Note
P-41
LIG Lignite MMH Mini Micro Hydel N Naptha 000 Not given WHR Waste Heat Recovery amp WR Washery Rejects
Punjab State Power Corporation Ltd not given Rate of Sale of Power hence Rate of Sale of Power taken from 2012-13 data
Ω COD = ROSP(Concerned Utilities not given ROSOP)