Golden Ears Bridge Report - June 23, 2008

20
Project Update Township of Langley June 23, 2008

description

An update on the Golden Ears Bridge construction given to Township of Langley Council at its June 23, 2008 meeting.

Transcript of Golden Ears Bridge Report - June 23, 2008

Page 1: Golden Ears Bridge Report - June 23, 2008

Project UpdateTownship of Langley

June 23, 2008

Page 2: Golden Ears Bridge Report - June 23, 2008

Presentation Outline

• Main Bridge• Langley components• Noise mitigation• Public information

Page 3: Golden Ears Bridge Report - June 23, 2008

Project

Plan

Page 4: Golden Ears Bridge Report - June 23, 2008

Main Bridge status

• On track for opening summer 2009• First span closed from Fraser River pier M2 to

south approach (Langley)• Second span (M2 to M3) to be closed about

August 1• M2 tower is completed to full height• Deck panel installation and concrete pouring to

continue through 2008.

Page 5: Golden Ears Bridge Report - June 23, 2008

Main Bridge from Langley Shore June 18 2007

Page 6: Golden Ears Bridge Report - June 23, 2008

Main Bridge Linked to South Approach

At Langley Dyke, June 18 2007

Page 7: Golden Ears Bridge Report - June 23, 2008

Main Bridge Deck Looking South June 18 2007

Page 8: Golden Ears Bridge Report - June 23, 2008

M2 and M3 from Barnston Island June 18 2007

Page 9: Golden Ears Bridge Report - June 23, 2008

Langley Components

Page 10: Golden Ears Bridge Report - June 23, 2008

Westcon Section

Westcon Overpass Substantially Complete

Telegraph Trail Realignment

Under Construction

Page 11: Golden Ears Bridge Report - June 23, 2008

Southern Bridge Approach and Ramps

Southern Bridge Approach Deck Pouring 201 Street On-Ramp

Deck Pouring

199 Street RampDeck Panels

Page 12: Golden Ears Bridge Report - June 23, 2008

South Approach from Main Bridge with Colossus Theatre

June 18 2008

Page 13: Golden Ears Bridge Report - June 23, 2008

Northwest Langley Streets

200 St Improvements/ Re-Laning

July-August 2008

96 Avenue areaTop Lift Paving

Underway

201 St. North UpgradeOpen to Traffic by end of

July

96 Avenue areaTop Lift Paving

Underway

96 Avenue areaTop Lift Paving

Underway

Page 14: Golden Ears Bridge Report - June 23, 2008

201 Street North of CN TracksJune 18 2008

Page 15: Golden Ears Bridge Report - June 23, 2008

96 Avenue – New Median Island June 18 2007

Page 16: Golden Ears Bridge Report - June 23, 2008

Paving, 200 Street June 18 2007

Page 17: Golden Ears Bridge Report - June 23, 2008

Noise mitigation

• TransLink & GCCJV are committed to construction of noise barriers near:– 200 Street - Forest Green Estates (Langley) – 201 Street at Telep Avenue (Maple Ridge) – Wildwood Crescent (Pitt Meadows)

• TransLink has accepted GCCJV noise study concluding that, asied from above areas, no further noise mitigation is required under project agreement.

Page 18: Golden Ears Bridge Report - June 23, 2008

Noise mitigation

– 200 Street,

Langley

Page 19: Golden Ears Bridge Report - June 23, 2008

Interpretive Panel,

Main Bridge Pathway

Page 20: Golden Ears Bridge Report - June 23, 2008

Public Information • Average 60 calls/e-mails per month to public information line;

about a third are related to construction issues

• Mailings to residences and businesses with contact information

• Traffic bulletins to news media, local governments and police;

advisories in community papers