Global Aggregation - Recap

21
2 Global Aggregation - Recap What is Global Aggregation? Process of providing an aggregation for all registered Suppliers Includes aggregation of Host Suppliers Current implementation means Host Supplier calculated by difference Error Supplier Unit in the SEM Not just Host Supplier volumes but also other errors included

description

Global Aggregation - Recap. What is Global Aggregation? Process of providing an aggregation for all registered Suppliers Includes aggregation of Host Suppliers Current implementation means Host Supplier calculated by difference Error Supplier Unit in the SEM - PowerPoint PPT Presentation

Transcript of Global Aggregation - Recap

Page 1: Global Aggregation - Recap

2

Global Aggregation - Recap

What is Global Aggregation?

Process of providing an aggregation for all registered Suppliers

Includes aggregation of Host Suppliers

Current implementation means Host Supplier calculated by difference

Error Supplier Unit in the SEM

Not just Host Supplier volumes but also other errors included

Page 2: Global Aggregation - Recap

Data Aggregation

NHH Meters(STS only)

Readings

AUFs and EUFs

Profiled Demand for NHH

customers

Generator Output

Tran Loss factors

Units delivered to

BSP in Each

Jurisdiction

HHM metered

units

Meter data processing

Meter data processing

HH Meters

ReadingsDifference

Residual volume assigned to NIEES /ESBN using Error Supplier Units

Metered or profiled volumes are uplifted in DA to reflect distribution line losses

Global Aggregation - Recap

Page 3: Global Aggregation - Recap

Data Aggregation

Readings

AUFs and EUFs

Profiled Demand for NHH

customersInclude DN

LLFs

Generator Output

HHM metered

unitsInclude DN

LLFs

Meter data processing

Meter data processing

HH Meters

Readings

Variance is ‘smeared’ across Suppliers, method to be determined through SEMO

Metered or profiled volumes are uplifted in DA to reflect distribution line losses (reports show both vols)

Variance

Tran Loss factors

Units delivered to

BSP in Each

Jurisdiction

Global Aggregation - Recap

Page 4: Global Aggregation - Recap

5

Global Aggregation - Recap

Causes of imbalance?

Power Stations &interconnectors

Transmission Network Distribution Networks Customers(end users)

Physical inaccuracyBack door suppliesInterconnector lossesMeter errors

Meter errorsUmetered embedded generationTheftLine losses

Transformer losses

Page 5: Global Aggregation - Recap

6

Global Aggregation - Recap

Causes of imbalance?

Power Stations &interconnectors

Transmission Network Distribution Networks Customers(end users)

Data Errors

Umetered SupplyProfilesEnergisation StatusTLAFs DLAFs

Station aggregation rules

Page 6: Global Aggregation - Recap

7

Global Aggregation - Recap

Causes of imbalance?

Elexon experience of Global Aggregation;

Incorrect profiles of non-interval meters considered chief contributor;

Modification 34_09 developed with a view to smearing residual volume

across all suppliers, taking account of each suppliers share of non-interval

metered consumers;

Page 7: Global Aggregation - Recap

8

Global Aggregation - Recap

Mod 34.09 raised by ESB CS

Mod proposed separation of SU into Interval SU and Non-Interval SU

Raised at Mods Meeting 24 (29.09.09)

Mods Panel recommended setting up Working Group to explore further

Terms of reference for Working Group circulated, Nov 2009

Page 8: Global Aggregation - Recap

9

Global Aggregation - Recap

Working Group 1, held on 19th November 2009.

Presentations & Discussion –

ESB CS suggested assigning ESU to non-competing Party under the Code;

MDPs presented on impact on systems;

Actions –

SEMO & RA to meet to further develop options;

ESB CS & NIE to provide estimation of error;

Mods Panel to decide if impact assessments should be sought;

Page 9: Global Aggregation - Recap

10

Global Aggregation - Recap

SEMO & RA met December 1st to develop options paper;

Four options written up and circulated –

Option A – recovered through SEMO balancing cost;

Option B – smear across Suppliers based on annual factors;

Option C – smear across Supplier based on monthly factors;

Option D – as set out in modification proposal;

Page 10: Global Aggregation - Recap

11

Global Aggregation - Recap

Working Group 2, held on 23rd February 2010.

Presentations & Discussion –

Suppliers presented on magnitude of actual error;

SEMO & MDPs presented results of impact assessments;

MRSO proposed option E, further enhancement on option C;

Actions –

SEMO & MDPs to meet to further review options D and E;

SEMO to impact assess options A+ and E;

Page 11: Global Aggregation - Recap

12

Meeting between MRSO, NIE T&D and SEMO took place on March 5th;

Further review of Options D and E;

Option E confirmed as

Aggregation for Supplier Units as normal;

Inclusion of a % value for each Trading Period;

% value will indicate at a MW level the proportion of the aggregation that is

made up of non-interval metering;

Global Aggregation - Recap

Page 12: Global Aggregation - Recap

13

Global Aggregation - Recap

Working Group 3, held on 27th April 2010.

Presentations & Discussion –

SEMO presented on MDP meetings and further impact assessments;

EirGrid presented on TUoS impacts;

Actions –

SEMO to issue consultation on options A+ and E;

TSO to review implementation of Option A for TUoS;

Page 13: Global Aggregation - Recap

14

Global Aggregation - Recap

Consultation document issued on June 17th;

Participants asked to express preference between Option A+ and Option E;

Responses welcomed on discarded options B, C and D;

Nine responses received to Consultation

Five responses favoured Option E (2 Participants, 3 service providers)

Three responses favoured Option A+

One response recommended either option

Page 14: Global Aggregation - Recap

15

Global Aggregation - Recap

Working Group 4, held on 26th August 2010.

Presentations & Discussion –

Recap and review of consultation responses;

Full impact assessment on SEMO systems is approx 1200 hours or €210 K

Noted flexibility in Option E to allow for implementation in one jurisdiction

ahead of the other;

Stressed importance of decision;

Consensus reached on recommendation of Option E;

Page 15: Global Aggregation - Recap

16

Global Aggregation - Recap

Metered Generation Loss Adjusted

Metered Demand by Supplier Unit

MGLF - NDLF Error Supplier Unit

Current Design

Page 16: Global Aggregation - Recap

17

Global Aggregation - Recap

Metered Generation Loss Adjusted

Metered Demand by Supplier Unit

MGLF - NDLF Error Supplier Unit

Option E Design

Metered Generation Loss Adjusted

Metered Demand by Supplier Unit

MGLF - NDLFResidual Meter

Volume & Smearing

Page 17: Global Aggregation - Recap

Global Aggregation - Recap

ANINDeh

NIEPvhNDvhRMVIPy

AINDeh

NIEPvhNDvhRMVIPyREVLFehNDAvh 1

1

After calculation of residual error volume;

Allocated across all Suppliers in the SEM;

Residual Meter Volume Interval Proportion – sets how much of the error

volume is allocated based on a Suppliers interval metered customers;

Non-Interval Energy Proportion – advises what portion of the aggregated

Metered Demand is based on non-interval metered customers;

Page 18: Global Aggregation - Recap

Global Aggregation - Recap

Version 2 of modification before Committee today;

Meeting with subgroup of Participants to review detail;

Further discussions with RAs on Version 2;

A number of changes are proposed for legal drafting;

Intent of the modification is not impacted by proposed changes;

Page 19: Global Aggregation - Recap

Global Aggregation - Recap

Version 2 used the following as paragraph 4.91;

NIJIehMDLFvhMGLFuhhNDLFveinveinu

'

e uine

einu

v vu u

einveinu

MGuh

NIJIehMGuh

MDvhMDLFvhMGLFuhMGuh

NIJIehMDvhMGuhNDLFeh

)(

)()()()(

)()(

Legal suggestion is to retain current 4.91, changing NDLFv’h to NDLFeh;

Page 20: Global Aggregation - Recap

Global Aggregation - Recap

NIJIehMDLFvhMGLFuhNDLFeheinveinu

Paragraph 7.12 updated also;

Creation of NDLFeh allows the value to be allocated to either the Error

Supplier Unit or the Residual Error Volume

Paragraph 4.91A

Paragraph 4.91 B

NDLFehhNDLFv '

If no Error Supplier Unit is registered in Jurisdiction e in accordance with paragraph 2.59,

NDLFehREVLFeh

Page 21: Global Aggregation - Recap

Global Aggregation - Recap

ANINDeh

NIEPvhNDvhRMVIPy

AINDeh

NIEPvhNDvhRMVIPyREVLFehNDAvh 1

1

ANINDeh

NIEPvhNDvhRMVIPy

AINDeh

NIEPvhNDvhRMVIPyNDAFvh 1

1

Paragraph 4.92C separated out to two sections to provide Net Demand

Adjustment percentage for Suppliers.

NDAFvhREVLFehNDAvh