Glass Bottle Manufacturing Plant
Transcript of Glass Bottle Manufacturing Plant
2018/06/21
1
1
Glass Bottle Manufacturing Plant proposed by SAB and partners
SCOPING AND EIA
Public Information Sharing Meeting
20 June 2018
1
2
Agenda
2
1. Welcome and introductions
2. Purpose of the meeting
3. Background and introduction to the project
4. Enviro-legal context
5. Questions and Discussion
6. Way forward
2018/06/21
2
3
Purpose of the meeting
3
• Give you information on/an introduction to:
– the proposed glass bottle manufacturing plant,
– the environmental assessment process,
• Provide you an opportunity to:
– ask questions.
– raise any issues and concerns,
– make input on environmental sensitivities & impacts
4
EIA Background
4
• The project requires:
environmental applications assessment authorisation decisions
• A scoping and environmental impact assessment (EIA) process
informs decision-making by:
– identifying potential impacts on the environment,
• with inputs from public and government departments
– assessing the significance of potential impacts,
• with involvement from specialists
– identifying any mitigation measures or monitoring requirements
should the project be approved.
• SLR Consulting is appointed to plan, manage and co-ordinate
the EIA.
2018/06/21
3
Project Background and Motivation
• Creation of the first majority Black owned industrial glass bottle supplier in SA;
• SAB wishes to create opportunities for the entrance of a new black economic
industrialists;
• Opportunity to contribute to the investment, inclusive growth and transformation
goals of the government and society.
WHAT?
WHY?
5
Key Elements
Investment
• Total investment of approximately R3.0bn
• Equity: c. 80% BO Partner ; c. 20% AB InBev
Plant
Capacity
• ~ 30% of current market volume in SA
Raw Material • Glass is made from non-organic oxides found in
sand, soda ash, limestone and other raw
materials, melted together at high temperature
Plant Design • The facility would be a large industrial
installation, comprising a batch plant, main
manufacturing building and warehouse.
Site • The proposed site (Portion 1/238 of the Farm
Leeuwkuil 596 IQ) is appropriately located in a
developing industrial area in Vereeniging
Plant Volumes
Year 1 Year 3 Year 10
Volume
(tonnes)262 904 292 469 292 469
CAGR 3.62 % 1.07 %
6
2018/06/21
4
Batch
Plant
Warehouse
Cullet
Bays
Main
Manufacturing
Building
SAB Depot
9
Urban Expansion: Emfuleni Local Municipality SDF – 2017 to 2025
2018/06/21
5
Proposed Glass Bottle Manufacturing Plant
11
Proposed Glass Bottle Manufacturing Plant
11
• The batch plant would be used to receive, store and mix the various raw
materials required in glass manufacture. The raw materials are stored in silos,
hoppers and bunds.
• Materials are mixed according to specific recipes for each glass product. Cullet
(crushed glass), from internal and external sources is a key material.
• Once mixed, the raw material batches would be conveyed across to the main
manufacturing building.
• The two furnaces would utilise natural gas or Liquid Petroleum Gas (LPG) as a heat
source.
• In the furnace the raw materials would be melted into glass at temperatures of up
to 1 530°C and degassed.
• The green glass furnace would feed three bottle manufacturing lines.
• The amber glass furnace would feed four bottle manufacturing lines.
2018/06/21
6
12
Proposed Glass Bottle Manufacturing Plant
12
• Molten glass is channelled to a series of glass forming machines that cool and
meter the glass.
• Mechanical and pneumatic means are used to create the specific glass containers.
• The bottles are hot end coated to enhance surface resistance and cooled in an
annealing oven (lehr) to avoid internal stresses.
• Bottles are further coated and subject to inspection for defects by high precision
equipment that measure capacity, dimensions, impact, pressure resistance and
other tests.
• Out-of-spec bottles are crushed and conveyed back to the furnaces, where the
cullet is re-used in the raw material mix.
• Completed bottles are packaged by automated palletizers and moved to the
warehouse for storage and distribution.
• Storage of the bottles would be in plastic wrapped, bulk pallets up to three pallets
high.
Prelim Design Final Design
Construction
Town Planning and approvals
Environmental Authorisation
Commercial and
ownership negotiations
Time
Operations
Corporate Social Investment
Employment and procurement
current
SAB Future Owner
2018/06/21
7
14
Scoping and EIA Process: Why?
14
• The project triggers activities set out in Listing Notice 1 and 2
made in terms of Chapter 5 of the National Environmental
Management Act, (No. 107 of 1998), which may not
commence until approved
• An Environmental Authorisation is required.
• The project triggers waste management activities listed in
terms of Chapter 5 of the National Environmental
Management: Waste Act, (No. 59 of 2008).
• A Waste Management Licence is required.
15
Scoping and EIA Process: What?
15
• A Scoping and Environmental Impact Assessment (EIA)
process as stipulated in the EIA Regulations (GNR 982, 8
December 2014) is required to inform the competent
authorities decision.
• EIA is the “systematic process of identifying, assessing and
reporting on environmental impacts” to inform a decision on
environmental authorisation.
• The GDARD is the competent authority for both the EA and
WML.
• Application to be made for an integrated environmental
authorisation (as provided for in section 24L of the NEMA)
2018/06/21
8
16
Scoping and EIA Process: What2?
16
• The project triggers one of the minimum emission categories
made in terms of Chapter 5 of the National Environmental
Management: Air Quality Act, (No. 39 of 2004).
• An Atmospheric Emissions Licence is required.
• The Atmospheric Emissions Licence application will be
informed by the Environmental Authorisation issued in terms
of the NEMA.
• The Sedibeng District Municipality is the competent
authority.
17
Scoping and EIA Process: Outline
17
Appeal Process
Sco
pe
Issu
es
Stu
die
s &
imp
act
asse
ssm
en
t
S&EIA PROCESST
IME
Make Application (Day 1)
Pre application
GDARD decision on EA (by Day 300)
Submit EIA Report (by Day 194)
GDARD accept/refuse
Scoping Report (Day 88)
Submit Scoping Report (by Day 45)
Pu
blic p
art
icip
ation
inp
ut
Notice to IAPS
Incl. 30 days Public review
Incl. 30 days Public review
2018/06/21
9
18
Public Participation
18
• Aim is to provide information to I&APS (and receive from)
which may influence the decision.
• Adverts, notices, letters, BID & meetings.
• Process is on-going and will continue through the EIA.
• Please submit comments to SLR, c/o Matthew Hemming, via:
– Fax: 011-467-0978
– Postal: PO Box 1956, Cramerview 2060
– Email: [email protected]
19
Scoping phase (current)
19
• Objective is to identify the key issues that need to be
addressed in the assessment phase.
• Document the issues and concerns raised by I&APs.
• Detail what issues will be investigated further, and how.
• I&APs will have 30 days to review the Scoping Report.
2018/06/21
10
20
The Site
Site Photos
From the R28 looking North
From SAB Depot entrance looking south-west
From Lager Road looking North East
21
Specialist Studies
21
• Specialist consultants have been commissioned to undertake
studies on:
– Hydrology - Geohydrology
– Air Quality - Noise
– Visual - Heritage
– Biodiversity - Social and land use
– Economic - Traffic
– Soils and land capability.
• The findings of the these studies will inform the assessment of impacts
and guide recommendations on mitigation and management measures.
2018/06/21
11
22
EIA phase (after Scoping)
22
• Objective is to assess the impacts to determine significance,
and identify measures to avoid, manage or mitigate these.
• Detail impact mitigation and management measures in an
Environmental Management Programme (EMPr).
• I&APs will have 30 days to review the EIA report.
• EIA report will inform the authorities decision.
• EMPr and authorisation conditions are legally binding.
23
EIA Schedule
23
– Apply for Integrated Environmental Authorisation (July 2018)
– Scoping phase (May to September 2018)
• Scoping Report review (August 2018)
– EIA phase (October to February 2019)
– Decision on Integrated Environmental Authorisation (~early
2019)
– Appeal period
– Commence 2 year design/construct programme.
2018/06/21
12
24
QUESTIONS OR COMMENTS
25
Way forward
25
• Notes from this meeting will be included in the environmental reports;
• The Scoping Report will be made available for 30-day public review
(estimated for August). All I&APs will be notified by email or post;
• Please submit comments to SLR, c/o Matthew Hemming, via:
– Fax: 011-467-0978
– Postal: PO Box 1956, Cramerview 2060 (if using post please notify us
telephonically)
– Email: [email protected]
• SLR will update the Scoping Report with comments received, and submit
the Scoping Report to the GDARD.
• I&APs will be notified of GDARD decision on Scoping Report.
• If accepted, the assessment will move onto the EIA phase.
2018/06/21
13
26
Thank you for your time and participation
27
Close
27
1
GLASS BOTTLE MANUFACTURING PLANT PROPOSED BY
SOUTH AFRICAN BREWERIES (PTY) LIMITED SAB AND PARTNERS
MINUTES OF PUBLIC SCOPING MEETING
DATE 20 June 2018, 4pm
VENUE: General Smuts High School, Vereeniging
SLR COMPANY: SLR Consulting (South Africa) (Pty) Ltd (SLR)
PROJECT NUMBER: 720.19124.00005
PURPOSE: The purpose of the meeting was to:
To provide information on/an introduction to:
o the proposed glass bottle manufacturing plant
o the environmental assessment process
Provide attendees an opportunity to:
o ask questions.
o raise any issues and concerns,
o make input on environmental sensitivities & impacts
ATTENDANCE: An attendance register is presented in Appendix 2.
1. OPEN AND INTRODUCTION
Nondumiso Gwala (NG) commenced the meeting and introduced herself as the meeting’s facilitator. She outlined the meeting protocol and requested that questions be asked at the end of the presentation. She stated that the presentation would be conducted in English but that attendees could ask their questions in any South African language. The presentation given at the meeting is included as Appendix 1. Copies of the background information document and comment sheets were made available to attendees at the meeting. Maps, indicating the regional setting and current land use and a conceptual illustration of the plant and manufacturing process of the project were displayed on the walls at the meeting. 2. OVERVIEW OF THE PROJECTS AND ENVIRONMENTAL ASSESSMENT PROCESSES
Matthew Hemming (MH) from SLR introduced himself as the environmental assessment practitioner. He conducted the presentation on the project background and motivation and the Scoping and EIA process. 3. QUESTION SESSION
The floor was opened for attendees to raise any questions, comments or concerns. None were raised by the attendees. 4. WAY FORWARD
The way forward presented at the meeting is outlined below.
2
Notes from this meeting will be included in the environmental reports;
The Scoping Report will be made available for 30-day public review (estimated for August). All I&APs will be notified by email or post;
Please submit comments to SLR, c/o Matthew Hemming, via:
- Fax: 011-467-0978
- Postal: PO Box 1956, Cramerview 2060 (if using post please notify us telephonically)
- Email: [email protected]
SLR will update the Scoping Report with comments received, and submit the Scoping Report to the GDARD.
I&APs will be notified of GDARD decision on Scoping Report.
If accepted, the assessment will move onto the EIA phase.
5. CLOSE
NG thanked attendees for their input and for making the time to attend the meeting. The meeting was closed at 4:30 pm.
3
APPENDIX 1: MEETING PRESENTATION
4
APPENDIX 2: ATTENDANCE REGISTER
5
Project: SAB'S PROPOSED GLASS BOTTLE MANUFACTURING PLANT PROJECT
SLR Company: SLR Consulting (South Africa) (Pty) Ltd
Date: 20 June 2018
Venue: Generaal Smuts School
Meeting: Public information sharing meeting
Name and Surname Community/organisation Postal address Contact numbers E-mail
Jacob Lesemela Lesa and Netsh Holdings 0781270315 [email protected];
Muzi Nhlapo Nampak 0713537694 [email protected];
Danielle Sanderson Nomad 0722598319 [email protected];
Mpho Lesalaisa Lesa and Netsh Holdings 0712210629 [email protected];
Vivian Ferreira 0837037483 [email protected];
Lehlohonolo Netshivhale Lesa and Netsh Holdings 0631887473 netshivholelehlohonolo@g
mail.com;
Note: SLR will use your contact information to communicate future project information and by providing your details on this
attendance register it does not mean that you are giving your consent for the project.
Project: SAB'S PROPOSED GLASS BOTTLE MANUFACTURING PLANT PROJECT SLR Company: SLR Consulting (South Africa) (Pty) Ltd Date: 20 June 2018 Venue: Generaal Smuts School Meeting: Public information sharing meeting
Name and Surname Community/organisation Postal address Contact numbers E-mail
Jacob Lesemela Lesa and Netsh Holdings 0781270315 [email protected];
Muzi Nhlapo Nampak 0713537694 [email protected];
Danielle Sanderson Nomad 0722598319 [email protected];
Mpho Lesalaisa Lesa and Netsh Holdings 0712210629 [email protected];
Vivian Ferreira 0837037483 [email protected];
Lehlohonolo Netshivhale Lesa and Netsh Holdings 0631887473 [email protected];
Note: SLR will use your contact information to communicate future project information and by providing your details on this attendance register it does not mean that you are giving your consent for the project.