Gilbert, Arizona Neely Solar Facility - c.ymcdn.com · •System Size: 2 mega-watts (2,257.92kW DC)...
Transcript of Gilbert, Arizona Neely Solar Facility - c.ymcdn.com · •System Size: 2 mega-watts (2,257.92kW DC)...
Gilbert, Arizona
Neely Solar Facility
2015 Wastewater Treatment Committee Annual Seminar
“Optimizing Wastewater Treatment for the New Normal”
Project Design Details
• Public/Private Partnership
• Located at Gilbert’s Neely Recharge Facility
• System Size: 2 mega-watts (2,257.92kW DC)
• 8000 solar panels - single axis tracker system
• Arrays are constructed over 5 recharge basins
• Solar panels are mounted on beams installed
20 feet underground and having a height
clearance of 6½ feet above ground
• 5 inverters mounted on concrete pads - the
inverters convert solar energy to electricity
• Solar system will help supply power to the
Neely Wastewater Reclamation Plant
• Initial concept discussions about the solar project began with
Severn Trent Services, Gilbert staff and SPG Solar in June, 2010
• Gilbert applied for a renewable energy incentive (Credit Purchase
Agreement) through APS in August, 2010 for the proposed project
• Gilbert was notified by APS that the project had been selected to receive a
renewable energy incentive in September, 2010
• The APS CPA (incentive) provides a 60% contribution towards project
construction in exchange for renewable energy credits
• A Land License Agreement and Power Purchase Agreement (PPA) were
negotiated and approved by the Gilbert Council in November, 2010
• Project design began in December, 2010 followed by construction activity
beginning in February through October, 2011
• The system Interconnection and Operating Agreements with APS were
approved in August, 2011
• The system began producing power at the end of September, 2011
Project Evolution
Power Purchase Agreement
• Sun-Edison (Formally SPG Solar) – Was required to perform project design
and construction, also responsible for system operation and maintenance
throughout agreement term
• Sun-Edison (formally Integrys Energy) is the solar system owner (Investor)
while Gilbert is considered the system host
• PPA has a 20 year term with options at the end for either agreement
renewal, ending the agreement with system removal (at owner’s cost), or
Gilbert can purchase the system at a depreciated value
• PPA requires Gilbert to purchase all of the power generated by the solar
system at a fixed rate structure
• The solar power rate is anticipated to be at or less than the electrical
power rate Gilbert would otherwise pay APS
• Forecasted savings for Gilbert is estimated to be approximately $2 million
over the agreement term (20 years)
Year
Utility Bill
Without Solar
Energy
Annual Solar
kWhsPPA Rate
Forecasted
PPA Annual
Bill
Remaining
Annual Utility
Bill with Solar
Total Annual
PPA Bill +
Utility Bill
Annual
Projected
Savings
1 $1,031,903 4,837,552 0.0750 $362,816 $667,706 $1,030,522 $1,381
2 $1,073,179 4,813,364 0.0769 $370,027 $694,414 $1,064,442 $8,738
3 $1,116,106 4,789,297 0.0788 $377,382 $722,191 $1,099,572 $16,534
4 $1,160,751 4,765,351 0.0808 $384,882 $751,078 $1,135,961 $24,790
5 $1,207,181 4,741,524 0.0828 $392,532 $781,122 $1,173,653 $33,527
6 $1,255,468 4,717,817 0.0849 $400,333 $812,366 $1,212,700 $42,768
7 $1,305,686 4,694,227 0.0870 $408,290 $844,861 $1,253,151 $52,536
8 $1,357,914 4,670,756 0.0892 $416,405 $878,656 $1,295,060 $62,854
9 $1,412,231 4,647,403 0.0914 $424,681 $913,802 $1,338,482 $73,748
10 $1,468,720 4,624,166 0.0937 $433,121 $950,354 $1,383,475 $85,245
11 $1,527,469 4,601,045 0.0960 $441,729 $988,368 $1,430,097 $97,371
12 $1,588,567 4,578,039 0.0984 $450,509 $1,027,903 $1,478,412 $110,156
13 $1,652,110 4,555,149 0.1009 $459,463 $1,069,019 $1,528,482 $123,628
14 $1,718,194 4,532,374 0.1034 $468,595 $1,111,780 $1,580,374 $137,820
15 $1,786,922 4,509,712 0.1060 $477,908 $1,156,251 $1,634,159 $152,764
16 $1,858,399 4,487,163 0.1086 $487,406 $1,202,501 $1,689,907 $168,492
17 $1,932,735 4,464,727 0.1113 $497,093 $1,250,601 $1,747,694 $185,041
18 $2,010,044 4,442,404 0.1141 $506,973 $1,300,625 $1,807,598 $202,446
19 $2,090,446 4,420,192 0.1170 $517,049 $1,352,650 $1,869,699 $220,747
20 $2,174,064 4,398,091 0.1199 $527,326 $1,406,756 $1,934,081 $239,983
Total $30,728,089 92,290,352 0.0958 $8,804,520 $19,883,002 $28,687,522 $2,040,567
Gilbert - Neely Solar Project
Forecasted Savings & Cash Flow Summary
PPA Forecast Inputs:
• Starting Solar Rate of $0.075/kWh with 2.5% Annual Escalator
• Estimated Average Annual Utility Power Inflation Rate of 4%
• Gilbert did not have to pay for any of the project’s capital
costs (~ $10.4 million)
• Gilbert is not required to operate or maintain the solar
system during the agreement term
• The System is off-setting 44% of the Neely Plant’s power needs
with clean renewable energy
• Gilbert’s forecasted savings (~$2 million over 20 years)
• Water recharge operations and wildlife habitat not impacted
• Public/private partnership – economic development
• Community marketability – promotes sustainability
• Gilbert will be contributing to the betterment of the
environment by off-setting an estimated 86 million pounds of
carbon dioxide over the life of the system
• Fits Gilbert’s Strategic Initiatives – “Clean, Safe, Vibrant”
Project Benefits - Gilbert
QUESTIONS?
Mark Horn
Gilbert, Arizona
Wastewater Manager
(480) 503-6420
[email protected] Photos Courtesy of “SPG Solar”
Presentation Templates by “www.animationfactory.com”