get.dexma.com Deliverables/D8_3.pdf · WP8 Project management D.8.3 MANAGEMENT REPORT (SECOND YEAR)...
Transcript of get.dexma.com Deliverables/D8_3.pdf · WP8 Project management D.8.3 MANAGEMENT REPORT (SECOND YEAR)...
This project has received funding from the European
Union’s Horizon 2020 research and innovation
programme under grant agreement No 768619
D8.3 Management report (2nd
year)
The RESPOND Consortium 2019
Integrated Demand REsponse
SOlution Towards Energy
POsitive NeighbourhooDs
WP 8: Project management
T8.2: Project management and EC reporting
Ref. Ares(2019)7362792 - 29/11/2019
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
2 | 155
PROJECT ACRONYM RESPOND
DOCUMENT D8.3 Management report (second year)
TYPE (DISTRIBUTION LEVEL) ☐ Public
☐ Confidential
☐ Restricted
DELIVERY DUE DATE 30/11/2019
DATE OF DELIVERY 29/11/2019
STATUS AND VERSION v1.0
DELIVERABLE RESPONSIBLE FEN
AUTHOR (S) Antonio Colino (FEN), Rodrigo López (FEN),
Agustina Yara (FEN); Francisco Diez (TEK), Iker
Esnaola (TEK); Nikola Tomasevic (IMP), Lazar
Berbakov (IMP); Toke H. Christensen (AAU);
Henrik N. Knudsen (AAU), Laura Martinez
(DEXMA), Andreu Pagès (DEXMA), Federico Seri
(NUIG).
OFFICIAL REVIEWER(S) N/A
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
3 | 155
DOCUMENT HISTORY
ISSUE DATE CONTENT AND CHANGES
v0.0 14/09/2019 Draft version - Table of Contents
v0.1 20/11/2019 First version
v0.2 28/11/2019 Reviewed version
v1.0 29/11/2019 Final version
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
4 | 155
EXECUTIVE SUMMARY
This report constitutes the Deliverable 8.3 Management report (second year). The document has been elaborated by FENÍE ENERGÍA SA, responsible partner for WP8 Project management and Project Coordinator within the RESPOND project. The purpose of this document is to report the activities carried out during the reporting period M13-M24 (October 2018-September 2019).
The present management report (second year) focuses on the description of the current status of
activities, objectives, impact, main results, work progress and achievements for all tasks
scheduled for the reporting period. Complete description of finished tasks and open tasks,
significant results of all tasks, deviation and corrective actions within tasks.
Also, the RESPOND project management report contains an overview of the project meetings,
meetings attendance statistics, description of the project issues founds, amendments to the
agreements, risk assessment, dissemination activities report (website and blog posts,
publications, events, workshops and television broadcast).
Furthermore, it is presented a list of deliverables submitted and milestones achieved. Moreover,
it is reported the use of resources for the period, detailing the costs and efforts per WPs and per
partners. Finally, conclusions are presented.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
5 | 155
TABLE OF CONTENTS
1. INTRODUCTION ............................................................................................................................... 12
2. MANAGEMENT REPORT (SECOND YEAR) .............................................................................. 13
2.1 CURRENT STATUS .................................................................................................................. 13
2.2 OBJECTIVES .............................................................................................................................. 15
2.3 IMPACT........................................................................................................................................ 16
2.4 MAIN RESULTS ......................................................................................................................... 18
2.5 WORK PROGRESS AND ACHIEVEMENTS ........................................................................ 29
2.5.1 WP1: PILOT SITE CHARACTERIZATION ..................................................................... 29
2.5.2 WP2: USE CASE DEPLOYMENT AND FOLLOW-UP ................................................. 33
2.5.3 WP3: USER ENGAGEMNET PROCESS ....................................................................... 41
2.5.4 WP4: ICT ENABLED COOPERATIVE DEMAND RESPONSE MODEL ................... 48
2.5.5 WP5: SYSTEM INTEGRATION AND INTEROPERABILITY ....................................... 77
2.5.6 WP6: VALIDATION AND REPLICATION OF PROJECT RESULTS ......................... 96
2.5.7 WP7: DISSEMINATION AND EXPLOITATION ACTIVITIES ....................................101
2.5.8 WP8: PROJECT MANAGEMENT ..................................................................................112
3. PROJECT MANAGEMENT ...........................................................................................................119
3.1 CONSORTIUM MANAGEMENT TASKS .............................................................................119
3.1.1 PROJECT MEETINGS .....................................................................................................119
3.1.2 PROJECT MEETINGS ATTENDANCE STATISTIC ...................................................125
3.2 PROJECT ISSUES ..................................................................................................................128
3.2.1 AMENDMENTS .................................................................................................................129
3.3 RISK ASSESSMENT ...............................................................................................................130
3.4 MANAGEMENT STRUCTURE ..............................................................................................131
3.4.1 EXTERNAL ADVISORY BOARD (EAB) .......................................................................131
3.5 ADMINISTRATIVE MANAGEMENT TOOLS .......................................................................131
3.6 DISSEMINATION ACTIVITIES ..............................................................................................132
3.6.1 WEBSITE AND BLOG POSTS .......................................................................................132
3.6.2 PUBLICATIONS ................................................................................................................133
3.6.3 EVENTS, WORKSHOPS, TELEVISION .......................................................................135
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
6 | 155
4. DELIVERABLES AND MILESTONES .........................................................................................140
4.1 DELIVERABLES .......................................................................................................................140
4.2 MILESTONES ...........................................................................................................................144
5. USE OF RESOURCES ..................................................................................................................145
5.1 EFFORTS SUMMARY ............................................................................................................145
5.2 COSTS SUMMARY .................................................................................................................148
6. CONCLUSIONS..................................................................................................................................152
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
7 | 155
LIST OF FIGURES
FIGURE 1. GENERAL ENERGY FLOW IN AARHUS, MADRID AND ARAN ISLANDS PILOT SITE ........................................................ 19 FIGURE 2. DATA FLOW IN RESPOND CONTROL LOOP .................................................................................................................. 20 FIGURE 3. EXAMPLE OF DATA POINTS LIST TO MAP MADRID DEVICES ....................................................................................... 20 FIGURE 4. QUESTIONNAIRE FOR PROSPECTIVE PILOT PARTICIPANTS ......................................................................................... 21 FIGURE 5. MOBILE APP MOCKUPS ............................................................................................................................................... 21 FIGURE 6. RESPOND ONTOLOGY'S DOCUMENTATION AVAILABLE ONLINE................................................................................. 22 FIGURE 7. OGEMA GATEWAY IN RESPOND .................................................................................................................................. 22 FIGURE 8. SCHEMA OF DATA PROCESS WITHIN RESPOND PROJECT ........................................................................................... 23 FIGURE 9. EXCERPT OF EXCELL COSTS AND EFFORTS BUDGETED VS ACTUAL USE OF RESOURCES ............................................ 23 FIGURE 10. RESPOND PLATFORM ARCHITECTURE ....................................................................................................................... 24 FIGURE 11. TOPICS OVERVIEW TOPICS COVERED BY THE FIVE INDIVIDUAL FOCUS GROUPS AT THE THREE PILOT SITES .......... 24 FIGURE 12. RESPOND OPTIMIZATION LOOP ................................................................................................................................ 25 FIGURE 13. NOTIFICATION TRANSLATION SERVICE WORKFLOW ................................................................................................. 25 FIGURE 14. WEATHER FORECAST API ........................................................................................................................................... 26 FIGURE 15. MQTT BASED PROTOCOL FOR ACTUATOR CONTROL ................................................................................................ 26 FIGURE 16. T5.4 DESKTOP DASHBOARD AND SMART MOBILE CLIENT ........................................................................................ 27 FIGURE 17. INTEGRATION OF THE ADAPTER INTO ENERGOMONITOR BACKEND ....................................................................... 27 FIGURE 18. RESPOND KPIS ........................................................................................................................................................... 28 FIGURE 19. WP1: PILOT SITE CHARACTHERIZATION GANTT CHART ............................................................................................ 29 FIGURE 20. EQUIPMENT AVAILABLE IN ONE OF THE PILOT HOUSES OF ARAN ISLANDS ............................................................. 30 FIGURE 21. DR ACTION EXAMPLE ................................................................................................................................................. 31 FIGURE 22: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP1 DURING THE 2ND YEAR ................................................... 33 FIGURE 23. WP2: USER CASE DEPLOYMENT AND FOLLOW-UP GANTT CHART............................................................................ 33 FIGURE 24. RESPOND’S MEASURE-FORECAST-OPTIMIZE-CONTROL LOOP .................................................................................. 37 FIGURE 25: EXCERPT OF THE EXCEL DATA POINT LIST FILLED BY PEOPLE IN CHARGE OF RESPOND PILOT SITES ....................... 38 FIGURE 26: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP2 DURING THE 2ND YEAR ................................................... 40 FIGURE 27. WP3: USER ENGAGEMENT PROCESS GANTT CHART ................................................................................................. 41 FIGURE 28. MOBILE APP’S NAVIGATION DIAGRAM ..................................................................................................................... 46 FIGURE 29: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP3 DURING THE 2ND YEAR ................................................... 48 FIGURE 30. WP4: ICT ENABLED COOPERATIVE DEMAND RESPONSE GANTT CHART ................................................................... 48 FIGURE 31. MODULES TO BE DEVELOPED IN DIFFERENT TASKS WITHIN WP4 ............................................................................ 49 FIGURE 32: GENERAL STRUCTURE OF THE ENERGY HUB ............................................................................................................. 50 FIGURE 33. THE OPTIMIZATION PROCESS .................................................................................................................................... 51 FIGURE 34. THE OPTIMIZATION PROCESS .................................................................................................................................... 51 FIGURE 35. PRODUCTION FORECAST MODEL SPECIFICATION ..................................................................................................... 53 FIGURE 36. DEMAND FORECAST OF THE USE CASE OFFICE WITH ARIMA ................................................................................... 55 FIGURE 37. POTENTIAL PERFORMANCE OF DIFFERENT SYSTEMS AND COMPONENTS ............................................................... 57 FIGURE 38. RESPOND PLATFORM'S DATA FLOW ......................................................................................................................... 58 FIGURE 39. RESPOND ONTOLOGY'S MAIN CLASSES AND PROPERTIES ........................................................................................ 59 FIGURE 40. DATA POINT LIST EXCERPT ........................................................................................................................................ 59 FIGURE 41 - ENERGY HUB STRUCTURE FOR DIFFERENT USE CASES ............................................................................................ 61 FIGURE 42 - DR LOAD DEVIATION ................................................................................................................................................ 62 FIGURE 43. PREDICTED AND OPTIMIZED LOAD PROFILES ............................................................................................................ 62 FIGURE 44. PREDICTED AND OPTIMIZED LOAD PROFILES ............................................................................................................ 62 FIGURE 45. SIMPLE ONE-HOUSEHOLD SETUP .............................................................................................................................. 63
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
8 | 155
FIGURE 46. HOMOGENEOUS MULTI-HOUSEHOLD SETUP ........................................................................................................... 64 FIGURE 47. AARHUS PILOT MODEL .............................................................................................................................................. 65 FIGURE 48. ARAN PILOT MODEL .................................................................................................................................................. 65 FIGURE 49. MADRID PILOT MODEL .............................................................................................................................................. 65 FIGURE 50. IMPORTED POWER PROFILES WITH LOAD REDUCTION ............................................................................................ 66
FIGURE 51. AARHUS PV FORCASTER ............................................................................................................................................ 69
FIGURE 52. REAL VS FORECASTED ENERGY CONSUMPTION OF A PREDICTIVE MODEL WITH A GOOD PERFORMANCE ............ 70
FIGURE 53. REAL VS FORECASTED ENERGY CONSUMPTION OF A PREDICTIVE MODEL WITH A BAD PERFORMANCE ................ 70
FIGURE 54. RESIDUALS OF A PREDICTIVE MODEL WITH A GOOD PERFORMANCE. ..................................................................... 70
FIGURE 55. RESIDUALS OF A PREDICTIVE MODEL WITH A BAD PERFORMANCE. ........................................................................ 71
FIGURE 56. FORECASTED VS ACTUAL ELECTRIC CONSUMPTION IN MADRID (NEIGHBOURHOOD LEVEL) .................................. 71
FIGURE 57. HOLISTIC OPTIMIZATION APPROACH ........................................................................................................................ 72
FIGURE 58. ROM MODEL SCHEME ............................................................................................................................................... 73
FIGURE 59: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP4 DURING THE 2ND YEAR ................................................... 77
FIGURE 60: WEATHERBIT.IO JSON FORMAT EXAMPLE ................................................................................................................ 79
FIGURE 61: EMS DASHBOARD INTEGRATION ............................................................................................................................... 81 FIGURE 62 RESPOND PLATFORM ARCHITECTURE ........................................................................................................................ 84 FIGURE 63 APACHE OPENWHISK HIGH LEVEL ARCHITECTURE (SOURCE: CLOUD.IBM.COM) ...................................................... 85 FIGURE 64: RESPOND PLATFORM MODULES DIAGRAM .............................................................................................................. 86 FIGURE 65: HIERARCHICAL TREE OF PILOT SITES IN DEXCELL ...................................................................................................... 87 FIGURE 66: LDAP SERVER FOR RESPOND MOBILE APP'S ACCESS CONTROL. ............................................................................... 90 FIGURE 67: NOTIFICATION FLOW ................................................................................................................................................. 91 FIGURE 68: RESPOND MOBILE APP'S PROXY SERVER. .................................................................................................................. 92 FIGURE 69: RESPOND MOBILE APP'S PUBLICATION IN APP STORE. ............................................................................................ 93 FIGURE 70 DR EVENT DATA FLOW ............................................................................................................................................... 95 FIGURE 71: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP5 DURING THE 2ND YEAR ................................................... 96 FIGURE 72: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP6 DURING THE 2ND YEAR ................................................. 101 FIGURE 73: RESPOND WEB PAGE ............................................................................................................................................... 105 FIGURE 74: RESPOND PUBLIC DELIVARABLES REPOSITORY ....................................................................................................... 106 FIGURE 75: RESPOND PUBLICATIONS SECTION .......................................................................................................................... 106 FIGURE 76: RESPONS ARTICLE EXAMPLE .................................................................................................................................... 106 FIGURE 77: RESPOND WEB ANALYTICS EXAMPLE 1 ................................................................................................................... 108 FIGURE 78: RESPOND WEB ANALYTICS EXAMPLE 2 ................................................................................................................... 108 FIGURE 79: RESPOND WEB ANALYTICS EXAMPLE 3 ................................................................................................................... 109 FIGURE 80: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP7 DURING THE 2ND YEAR ................................................. 112 FIGURE 81: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP8 DURING THE 2ND YEAR ................................................. 118 FIGURE 82: SCREEN SHOT OF RESPOND WEBPAGE: BLOG SECTION.......................................................................................... 133 FIGURE 83: MAGAZINE PUBLICATION ........................................................................................................................................ 134 FIGURE 84: OPEN ACCESS GOVERNMENT PUBLICATION ........................................................................................................... 135 FIGURE 85: RESPOND PROJECT PARTICIPATION AT SUSTAINABLE PLACES 2019 ...................................................................... 136 FIGURE 86: RESPOND PROJECT PARTICIPATION AT LDAC 2019 ................................................................................................. 136 FIGURE 87: EVENTS’ PICTURES: ECEEE SUMMER STUDY 2019, FRANCE .................................................................................... 137 FIGURE 88: RESPOND PROJECT PARTICIPATION AT ETSI IOT 2019 ............................................................................................ 138 FIGURE 89: RESPOND PROJECT PARTICIPATION AT EUROPEAN UTILITY WEEK 2019 ................................................................ 138 FIGURE 90: RESPOND PROJECT FEATURED IN IRISH TV ............................................................................................................. 139 FIGURE 91: TOTAL EFFORTS (ACTUAL AND BUDGET) BY PARTNER IN THE 2ND YEAR ............................................................... 146 FIGURE 92: TOTAL EFFORTS (ACTUAL AND BUDGET) FOR EACH PARTNER IN THE 2ND YEAR................................................... 147 FIGURE 93: TOTAL COSTS (ACTUAL AND BUDGET) BY PARTNER IN THE 2ND YEAR................................................................... 149 FIGURE 94: TOTAL COSTS (ACTUAL AND BUDGET) FOR EACH PARTNER IN THE 2ND YEAR ...................................................... 150 FIGURE 95: TOTAL COSTS (ACTUAL AND BUDGET) FOR EACH TYPE IN THE 2ND YEAR.............................................................. 151
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
9 | 155
LIST OF TABLES
TABLE 1. RESPOND MILESTONES LIST 13 TABLE 2. RESPOND SPECIFIC OBJECTIVES FOR M13-M24 15 TABLE 3. SUMMARY OF DR ACTIONS PER PILOT SITE 32 TABLE 4. STC PRODUCTION PROTOTYPE RESULTS 54 TABLE 5. OBTAINED MAES FOR DEMAND PREDICTION USING DIFFERENT ALGORITHMS 55 TABLE 6: DEXCELL KPIS 89 TABLE 7: RESPOND STAKEHOLDERS 94 TABLE 8: LIST OF PUBLICATIONS 102 TABLE 9: LIST OF ARTICLES 104 TABLE 10. RESPOND PROJECT LIST OF DELIVERABLES SUBMITTED DURING REPORTED PERIOD M1-M24 140 TABLE 11. RESPOND PROJECT MILESTONES 144 TABLE 12: TOTAL EFFORTS (ACTUAL AND BUDGET) BY PARTNER AND WP IN THE 2ND YEAR 145 TABLE 13: PERCENTAGE OF ACTUAL EFFORTS VS BUDGET BY PARTNER AND WP IN THE 2ND YEAR 145 TABLE 14: TOTAL COSTS (ACTUAL AND BUDGET) BY PARTNER AND TYPE IN THE 2ND YEAR 148 TABLE 15: PERCENTAGE OF ACTUAL COSTS VS BUDGET BY PARTNER AND TYPE IN THE 2ND YEAR 148
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
10 | 155
ABBREVIATIONS AND ACRONYMS
AAU AALBORG UNIVERSITET
ALBOA ALMEN BOLIGORGANISATION AARHUS
ARAN COMHARCHUMANN FUINNIMH OILEAIN ARANN
TEORANTA
AURA AURA RADGIVNING AS
D Deliverable
DEV DEVELCO PRODUCTS AS
DEXMA DEXMA SENSORS SL
DoA Description of Action
DR Demand Response
e.g. exempli gratia = for example
EAB External Advisory Board
EASME Executive Agency for Small and Medium-sized
Enterprises
EC European Commission
EM Exploitation Manager
EMS Electronics Manufacturing Services
ENE ENERGOMONITOR S.R.O
EU European Union
FEN FENIE ENERGIA S.A.
GA Grant Agreement
GHG Greenhouse Gas
ICT Information and Communication Technology
KPI Key Performance Indicator
IMP INSTITUT MIHAJLO PUPIN
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
11 | 155
JSON JavaScript Object Notation
iOS iPhone Operative System
IP Internet Protocol
M Month
MQTT Message Queue Telemetry Transport
MS Milestone
NUIG NATIONAL UNIVERSITY OF IRELAND, GALWAY
OpenADR Open Automated Demand Response
PC Project Coordinator
PCC Pilot case Coordinator
PMT Project Management Team
REA Research Executive Agency
RESPOND Integrated Demand REsponse SOlution Towards Energy
POsitive NeighbourhooDs
RV Review
SCADA Supervisory Control and Data Acquisition
SH/SW Software/hardware
ST Steering Committee
TEK FUNDACION TEKNIKER
TL Technical Leaders
UEL User Engagement Leader
WP Work Package
WPL Work package Leader
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
12 | 155
1. INTRODUCTION
The purpose of this document is to provide a complete report of the activities that have been
performed by the RESPOND project Consortium during the second year of the project.
Full descriptions of the tasks carried out during the reported period (M13-M24) are presented.
The aim has been to comply with the scheduled DoA from the Quality Assurance Plan established
at the beginning of the project.
The present document contains the actions and measures performed in order to guarantee an
administrative, financial risk management and also scientific and technology management of the
project.
In the previous Management report (first year) submitted in M14, the work was focused on the
three pilot’s characterization and deployment (namely Madrid, Aarhus and Aran Islands), also on
finding demand response actions for each of the scenarios, design of the system architecture and
platforms setting up. At the same time, the user engagement process was defined and
progressing.
In the present Management report (second year) submitted in M26, the focus has been still on
user engagement process and final deployment in the three pilots, besides on the development
of all the systems and models that integrate the complexity of RESPOND solution. In this phase,
data collection has been crucial to move forward to an integration and interoperability of all
technical components.
All partners have been contributing from the different backgrounds to the realization of the
scheduled tasks, deadlines and milestones assigned for the period.
The document aims to report the activities performed during the first second year of RESPOND
project, M13-M24 (October 2018-September 2019), from an administrative, risk, financial,
scientific & technologic point of view.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
13 | 155
2. MANAGEMENT REPORT (SECOND YEAR)
2.1 CURRENT STATUS
RESPOND project has reached the second year in terms of timing (24 out of 36 months). During this year, the Consortium members worked with the purpose of achieving the phase II, which consists in RESPOND platform integration and advancement, and the beginning of phase III, based on the Project validation and replication.
TABLE 1. RESPOND MILESTONES LIST
Milestone number
Milestone title WP number
Lead beneficiary
Due date (in months)
Means of verification
MS1 Pilots characterization
WP1 FEN 6 Complete pilot descriptions
MS2 First deployment WP2 DEV 12 Early deployment of devices done
MS3 Final deployment WP3, WP4, WP5
TEK 24 Project developments deployed in pilots
MS4 Reporting period midterm
WP6, WP7 DEXMA 30 Midterm of reporting period
MS5 End of pilot demonstration
WP6, WP7, WP8
FEN 34 End of pilot demonstration
During the reporting period, M13-M24, the main goal was the achievement of milestone MS3: Final deployment (M24). Some tasks from WP1, WP2 and WP3 were scheduled to be finished in M12 (September 2018), but it was applied and extra month (approved by the Project Officer) in order to complete the work. Therefore, the following tasks finished in M13 (October 2018):
• WP1 Pilot site characterization:
o T1.4 Demand response actions discovery for each pilot
• WP2 Use case deployment and follow-up:
o T2.2 Seamless integration of RESPOND technology tiers o T2.4 Early deployment at pilot sites
• WP3 User engagement process:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
14 | 155
o T3.1 Criteria and framework for participant recruitment o T3.4 Smart mobile client and personal energy performance assistant design
In parallel, the main activities during M13-M24 pivoted around the progress of the following tasks from WP3, WP4, WP5, WP6, WP7:
• WP2 use Case Deployment and follow-up:
o T2.5 Demand response platform deployment
• WP3 User engagement process:
o T3.3 Detailing the user context and improvements of user interaction
• WP4 ICT enabled cooperative demand response model:
o T4.1 Semantic information model o T4.2 Integration of demand response with supply demand side management o T4.3 Optimal energy dispatching at household and neighbourhood level o T4.4 Energy production and demand forecasting o T4.5 Data analytics and optimized control
• WP5 System integration and interoperability:
o T5.1 Home automation interoperability interfaces o T5.2 Smart grid connectivity o T5.3 RESPOND middleware development o T5.4 Integration with desktop dashboard and smart mobile client o T5.5 Data protection and security measures
• WP6 Validation and replication of project results:
o T6.1 Validation methodology and acceptance criteria o T6.2 Validation analysis and reporting o T6.3 Qualitative evaluation of user experience and recommendations o T6.4 Replication plan development
• WP7 Dissemination and exploitation activities:
o T7.2 Products, services and supporting business model definition o T7.3 data life cycle management
In addition, the following tasks have been running since the beginning of the project, in M1, and will continue until the end of the project, in M36:
o T7.1 Dissemination and communication strategy
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
15 | 155
o T7.6 Contribution to EASME dissemination
o T8.1 Project administration & quality assurance
o T8.2 Project management and EC reporting
In the section 2.5 detailed results and achievements for each work package are presented.
2.2 OBJECTIVES
Overall objectives of RESPOND project:
• Energy costs savings
To deliver an ICT solution for demand response that will result in energy reduction of about 10% and economic cost savings of at least 20% in residential sector by adapting the user behavior to maximize the exploitation of renewable sources.
• Integrated solution for demand response
To design, construct, deploy and validate a system that is able to integrate with any building SW/HW system in relation to energy and comfort, while supporting and facilitating the end user to understand and directly engage with DR activities.
• Integral business model
To design, apply and validate a business model and exploitation plan for a large-scale uptake of the ICT system deployed and integrated in the RESPOND project.
Work package specific objectives for the second year of RESPOND project are shown in table 2:
TABLE 2. RESPOND SPECIFIC OBJECTIVES FOR M13-M24
Specific Objectives for reported period M13-M24
WP OBJECTIVES ACHIEVEMENTS
WP1 Pilot site characterization Successful submission of D1.4 in M13
WP2 Use case deployment and follow-up Successful submission of D2.2 and D2.4 in M13 and D2.5 in M24
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
16 | 155
WP3 User engagement process
Successful submission of D3.1 and D3.4 in M13 and D3.3 in M24
WP4 ICT enabled cooperative demand response model
Successful submission of D4.1 in M18 and D4.2, D4.3 in M24
WP5 System Integration and Interoperability Successful submission of D5.1 in M18 and D5.2, D5.3, D5.4, D5.5 in M24
WP6 Validation and Replication of Project Results D6.1 was delayed and submitted in M26 instead of M24 because additional time for
baseline checking WP7 Dissemination and Exploitation Activities Successful submission of D7.4 in M18
WP8 Project management Successful preparation of Official Periodic Report M1-M18, the submission was delayed
because of amendment process opened
2.3 IMPACT
The project aims to address each of the expected impacts started by EE-12-2017, which sets the specific challenge in terms of integrating the demand response enabling elements into Energy Management Systems (EMS) and achieving full interoperability between smart grids, energy systems and smart home devices. The table 3 shows how RESPOND will contribute to each of the impacts expected by the call.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
17 | 155
TABLE 3. RESPOND IMPACT
Besides the expected impacts mentioned by the work program, the proposal aims to make the following additional impacts:
• Contribution to Europe’s Energy Security RESPOND will have a direct impact not only on the financial (e.g. minimizing costs of energy dispatching, and influencing at energy prices as previously stated), but also on the environmental aspect of energy market (e.g. by lowering GHG emissions).
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
18 | 155
• Generates skilled job opportunities
District energy systems contribute to employment opportunities, ranging from system design, construction, equipment manufacturing, to the operation and maintenance.
• Promotion of cooperative movement
Cooperative movement consist in the association of people to get common objectives by collaboration of everybody involved.
An example of this type of movement is one of the project partners, Aran Islands (ARAN), that thanks to the cooperative association projects increased significantly the use of sustainable energy sources as compared to 2008.
• Open data use
Performance can be improved, which contributes to enhancing the efficiency of public services. Owing to the cross-sectorial sharing of the data, greater efficiency in processes and delivery of public services can be achieved.
Social welfare can also be improved as society benefits from more transparent and accessible information.
Economy can benefit from an easier access to information and knowledge, contributing to the development of innovative services and creation of new business models.
Reutilization of Open Data sources proposed by RESPOND will contribute in raising the awareness and consciousness level of the Open Data.
2.4 MAIN RESULTS
The main results during the reporting period of the project focus on pilot specific demand response strategy, integration of key RESPOND technology tiers, early deployment activities report, criteria and framework for recruiting and engaging, personal energy performance assistance design, semantic information model, energy gateway for home automation interoperability, data life cycle management policy (preliminary), Official Periodic Report M1-M18, deployment of RESPOND cloud-based platform, findings and recommendations from focus groups on user context, demand response optimization model, optimal energy dispatching at neighbourhood level, RESPOND connectivity to smart grid services, RESPOND middleware deployment, desktop dashboard and smart mobile client, data protection and security, RESPOND validation methodology.
Towards pilot specific demand response strategy RESPOND (M13) TEK RESPOND pilot sites are very different between them not only with respect to the location, but more importantly in terms of the climate associated to each of these locations, the type of houses and dwellers habits. Besides, houses in each pilot site count on different appliances and equipment, as well as different renewable energy sources (RES) and exploitation modality. This idiosyncrasy of each RESPOND pilot site makes them unique. Therefore, a plethora of DR actions were envisioned to be implemented in the project, each of them implemented in the site that best fits. All these findings were presented by TEK in D1.4.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
19 | 155
FIGURE 1. GENERAL ENERGY FLOW IN AARHUS, MADRID AND ARAN ISLANDS PILOT SITE
Towards Integration of key RESPOND technology tiers (M13) DEXMA One of the main challenges has been to match the existing systems and underlying technology concepts with system reference architecture designed in T2.1. To do so, the existing technology available in pilot sites has been taken into consideration along with the new MQTT based architecture, which will be able not only to integrate the new RESPOND technology tiers, but also the legacy systems present in the pilot sites. In addition, the inputs from WP1 in terms of exact deployment options and project requirements have been considered for the activities performed in this task. DEXMA reflected all these results in D2.2.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
20 | 155
FIGURE 2. DATA FLOW IN RESPOND CONTROL LOOP
Towards early deployment activities report (M13) ENE The Excel file Data Point List (figure 3) that was created for getting information of all devices deployed in Aarhus (Denmark), in the Aran Islands (Ireland) and in Madrid (Spain), is very important and useful for follow the state of the deployment, map in the system all devices and it is necessary also to create the topological data structure. This data was used to generate the instances of the deployed infrastructure in the semantic repository according to the defined ontology and also to define the data structure in DEXCELL system. ENE reflected these information in D2.4.
FIGURE 3. EXAMPLE OF DATA POINTS LIST TO MAP MADRID DEVICES
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
21 | 155
Towards criteria and framework for recruiting and engaging (M13) AAU
Detailed criteria for the selection of households at the three RESPOND pilot sites (Aarhus, Aran Islands and Madrid) was developed. The aim was to recruit household samples with a relative high diversity with regard to demographic and socio-economic variables such as income level, household size, family type etc. AAU presented in D3.1 how the recruitment went out in practice, present a socio-economic and demographic profile of the recruited households.
FIGURE 4. QUESTIONNAIRE FOR PROSPECTIVE PILOT PARTICIPANTS
Towards personal energy performance assistance design (M13) TEK
The state of the art of existing mobile apps were reviewed, especially the focusing on the ones facing DR problems. TEK reflected in D3.4 the design of RESPOND personal energy performance assistant. The app is in development process.
FIGURE 5. MOBILE APP MOCKUPS
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
22 | 155
Towards semantic information model (M18) TEK
The semantic information model developed for the RESPOND project was presented in D4.1 by TEK. One of the main outputs was the RESPOND Ontology, which is based on the NeOn Methodology and following the best practices of reusing existing well-known ontologies. The reuse is not a trivial task.
FIGURE 6. RESPOND ONTOLOGY'S DOCUMENTATION AVAILABLE ONLINE
Towards energy gateway for home automation interoperability (M18) IMP
The aim was to support integration of RESPOND platform with external hardware and software systems, thus enabling not only acquisition of data, but also providing a way to issue the control actions to be performed under the cooperative demand strategy. To achieve this overarching goal, the concept of energy gateway was deployed in the pilots. The gateway comprises open software platform OGEMA as well as custom developed modules aimed at integrating different RESPOND components and external systems. IMP reflects in D5.1 the work done.
FIGURE 7. OGEMA GATEWAY IN RESPOND
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
23 | 155
Towards data life cycle management policy (preliminary) (M18) FEN
The data life cycle management policies necessary to safeguard at all time both, the privacy of the trials participants in the pilot sites and the unauthorized access to the information in the ICT related environment were addressed. FEN presents in D7.4 a preliminary version of the policies to be used in RESPOND project and therefore this document must be updated with the work done during the second half of project’s lifetime.
FIGURE 8. SCHEMA OF DATA PROCESS WITHIN RESPOND PROJECT
FIGURE 9. EXCERPT OF EXCELL COSTS AND EFFORTS BUDGETED VS ACTUAL USE OF RESOURCES
Towards deployment of RESPOND cloud-based platform (M24) IMP Key activities towards deployment of RESPOND cloud-based platform and its core services at pilot sites were undertaken. First, the RESPOND cloud-based platform architecture with its main building blocks was briefly revisit. Then, deployment of different analytic services was carried out. IMP has reflected all the details in D2.5.
PARTNER UNITRESOURCES /
EXPENSES% SPENT
REMAINING
RESOURCES
M6 M12 M18 M24 M30 M36 Total M6 M12 M18 M24 M30 M36 Total
a1 a2 a3 a4 a5 a6 A b1 b2 b3 b4 b5 b6 B B/A A-B
PMs WP1 37,67 7,33 0,00 0,00 0,00 0,00 45,00 33,62 13,66 1,37 0,00 0,00 0,00 48,64 108% -3,64
PMs WP2 16,50 33,00 9,00 9,00 0,00 0,00 67,50 22,18 26,10 9,29 0,00 0,00 0,00 57,57 85% 9,93
PMs WP3 9,25 22,25 3,00 3,00 0,00 0,00 37,50 6,24 16,86 8,09 0,00 0,00 0,00 31,18 83% 6,32
PMs WP4 0,00 10,17 28,33 23,83 11,67 0,00 74,00 0,78 5,46 16,35 0,00 0,00 0,00 22,59 31% 51,41
PMs WP5 0,00 19,50 19,50 39,00 0,00 0,00 78,00 1,25 16,58 20,60 0,00 0,00 0,00 38,42 49% 39,58
PMs WP6 0,00 0,00 9,00 18,23 23,86 28,90 79,99 0,00 0,00 6,50 0,00 0,00 0,00 6,50 8% 73,49
PMs WP7 3,50 3,50 11,00 11,00 27,00 27,00 83,00 7,30 3,22 7,12 0,00 0,00 0,00 17,65 21% 65,35
PMs WP8 3,83 3,83 3,83 3,83 3,83 3,83 23,00 4,06 4,32 3,59 0,00 0,00 0,00 11,98 52% 11,02
PMs Total 70,75 99,58 83,67 107,90 66,36 59,74 487,99 75,43 86,19 72,91 0,00 0,00 0,00 234,53 48% 253,46
Euros Personnel costs 370.212,09 521.093,34 437.800,70 564.588,71 347.224,58 312.628,58 2.553.548,00 394.338,90 415.375,48 365.369,20 0,00 0,00 0,00 1.175.083,57 46% 1.378.464,43
Euros Subcontracting 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0% 0,00
Euros Other direct costs 66.890,67 66.890,67 66.890,67 66.890,67 66.890,67 66.890,67 401.344,00 31.504,52 52.290,30 133.176,93 0,00 0,00 0,00 216.971,75 54% 184.372,25
Euros Indirect Costs 109.275,69 146.996,00 126.172,84 157.869,84 103.528,81 94.879,81 738.723,00 100.473,43 103.506,40 120.147,56 0,00 0,00 0,00 324.127,40 44% 414.595,60
Euros Total Costs 546.378,44 734.980,01 630.864,21 789.349,22 517.644,06 474.399,06 3.693.615,00 526.316,85 571.172,18 618.693,69 0,00 0,00 0,00 1.716.182,72 46% 1.977.432,28
EurosRequested
EU funding464.749,51 625.173,99 536.613,10 671.420,45 440.308,04 306.444,67 3.044.709,75 435.293,92 480.603,52 507.859,54 0,00 0,00 0,00 1.406.366,81 46% 1.638.342,94
ALL
PARTNERS
BUDGET ACTUAL EXPENSES
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
24 | 155
FIGURE 10. RESPOND PLATFORM ARCHITECTURE
Towards findings and recommendations from focus groups on user context (M24) AAU
Collection of data on the user context from the pilot sites needed for adapting the tested demand response (DR) model to the specific locality and actual users’ everyday practices. The goal was to ensure that RESPOND DR solutions and mobile app will work in actual user context and to avoid unsuitable design features that do not engage users and could cause participant dropout. AAU reflected all the details in D3.3.
FIGURE 11. TOPICS OVERVIEW TOPICS COVERED BY THE FIVE INDIVIDUAL FOCUS GROUPS AT THE THREE PILOT SITES
Towards demand response optimization model (M24) IMP A methodology that employs the Energy Hub modelling concept specifically modified for load management applications was developed. Since RESPOND focuses on the neighbourhood perspective, the loads are managed jointly as an aggregate value (a sum of either individual
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
25 | 155
appliance activations or multiple household’s aggregate load). IMP presented all the details in D4.2.
FIGURE 12. RESPOND OPTIMIZATION LOOP
Towards optimal energy dispatching at neighbourhood level (M24) IMP It was defined an extension to the methodology developed in D4.2 with which the single-user Energy Hub models are extended to form aggregate neighbourhood models of the Aarhus, Madrid and Aran Islands pilot sites of the RESPOND project. The production and demand are scaled up and real-world demand curves are generated from IoT sensor data that is registered in the InfluxDB time-series database. IMP presented all the details in D4.3.
FIGURE 13. NOTIFICATION TRANSLATION SERVICE WORKFLOW
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
26 | 155
Towards RESPOND connectivity to smart grid services (M24) IMP The goal of T5.2 was to support RESPOND platform connectivity through an open Application Programming Interface (API) and enable exploitation of data provided by smart grid and other third-party services (e.g. provision of energy prices, weather forecast data, etc.). Open API is designed to provide single endpoint for programmatic access to RESPOND services such as: DR optimization algorithms, forecasted energy consumption, performance evaluation, global ranking, etc. IMP presented all the details in D5.2.
FIGURE 14. WEATHER FORECAST API
Towards RESPOND middleware deployment (M24) IMP Deployment of service-oriented communication middleware, according to the specifications provided in WP1, in order to ensure integration of RESPOND cores services and system components. For this purpose, open source Message Queuing Telemetry Transport (MQTT) broker and data collection software stack has been deployed with the primary role of providing interconnectivity between different system components.
FIGURE 15. MQTT BASED PROTOCOL FOR ACTUATOR CONTROL
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
27 | 155
Towards desktop dashboard and smart mobile client (M24) DEXMA The results from T5.4 carried out by DEXMA and TEK were presented in a demonstrator D5.4. An easy to use, yet powerful web-based desktop dashboard and smart multifunctional mobile application that will serve as RESPOND cloud platform clients was delivered.
FIGURE 16. T5.4 DESKTOP DASHBOARD AND SMART MOBILE CLIENT
Towards data protection and security (M24) IMP The goal of T5.5 was to undertake proper security measures in order to deal with possible communication threats that RESPOND system may encounter in relation to data collection, transmission and storage. In order to ensure this, a complete end-to-end data protection measures have been designed and implemented. In particular, RESPOND has implemented encryption of communication links and internal data storage as well as implementation of client authorization. IMP presented all the details in D5.5.
FIGURE 17. INTEGRATION OF THE ADAPTER INTO ENERGOMONITOR BACKEND
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
28 | 155
Towards RESPOND validation methodology (M24>M26) NUIG In D6.1 NUIG detailed the list of KPIs and Business Cases, RESPOND validation methodology was defined, based on RESPOND objectives and also taking into account RESPOND framework.
FIGURE 18. RESPOND KPIS
• Renewable total energy consumption
• Energy savings
Energy
• Reduction of greenhouse gas emissions
CO2
• Peak load reduction
• Rescheduled Demand
• Analytical services accuracy
Demand Response
• Capex
• Economic savings during the DR Event
• OPEX
Economic
• Data security control
• GDPR Risk
Security and Privacy
• Coefficient of performance – COP
• Communication performance
System Operation
• DR campaigns penetration
• Number of user manual actions
• Comfort level according to the user
User
• Indoor Air Quality
• Thermal comfort
Comfort
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
29 | 155
2.5 WORK PROGRESS AND ACHIEVEMENTS
This section provides an overview of the progress of the work within the work packages WP1, WP2, WP3, WP4, WP5, WP7 and WP8 during the reporting period M13-M24 (October 2018 - September 2019).
2.5.1 WP1: PILOT SITE CHARACTERIZATION
WP1 started in M1 (October 2017) and finished in M13 (October 2018).
FIGURE 19. WP1: PILOT SITE CHARACTHERIZATION GANTT CHART
The main objectives of WP1 were:
• Technical characterization of pilot sites and their respective neighborhoods. • Definition of operation scenarios and key performance indicators. • Analysis of demand response programs at pilot countries and EU level. • Analysis of interoperability issues and smart grid connectivity. • Identification of possible demand side opportunities.
T1.1, T1.2 and T1.3 finished in M6. Only T1.4 has been carried out during the reporting period.
2.5.1.1 DESCRIPTION OF TASK
T1.4 DEMAND RESPONSE ACTIONS DISCOVERY FOR EACH PILOT. M4-M13 TEK
T1.4 started in M4 according to what it was scheduled, but it was carried out until M13 instead of
M12. An extension of one month was applied for and accepted by the Project Officer.
The resulting DR actions recommended for each pilot have been represented in deliverable D1.4
Pilot specific demand response strategy. This document has been delivered in M13. For these
recommendations, the initial analysis made on D1.2 has been very valuable.
This task had a scheduled duration of nine months; however, it was prolonged one extra month
in order to collect all the complete information about the early deployment that had been
prolonged one extra month.
During the first nine months the main findings learned in this task have been potential DR actions
for each pilot’s, the following information is given:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
30 | 155
• DR Action: The name used to refer to the DR action.
• Description: A brief explanation of the DR action.
• Equipment involved: The equipment and appliances that enable the implementation of the
DR action.
• Pre-condition: The conditions necessary to enable the execution of the DR action.
• Services involved: The RESPOND services that enable the implementation of the DR
action.
• Recommended DR Type: The type of DR action recommended for an optimal operation of
the DR action.
• Feasible DR Type (optional): The type of DR action that may also be applicable for the
operation of the DR action. In case there are more than one DR Type, they are sorted
according to its suitability.
• DR Type Unfeasible (optional): The type of DR action that cannot be applied for the
operation of the DR action.
2.5.1.2 SIGNIFICANT RESULTS
T1.4 DEMAND RESPONSE ACTIONS DISCOVERY FOR EACH PILOT. M4-M13 TEK
During the last extra month, the main results obtained in this task can be summarized as follows:
• The finalization of deliverable D1.4 Pilot specific demand respond strategy.
This task aimed at discovering suitable DR actions for each pilot site. Towards that purpose,
having a clear vision of what are the devices each pilot site counts on played a key role. For that
purpose, information collected in T2.3 Design of the initial deployment plan has been leveraged.
The figure below shows the equipment available in one of the pilot houses in the Aran Islands
(Ireland).
FIGURE 20. EQUIPMENT AVAILABLE IN ONE OF THE PILOT HOUSES OF ARAN ISLANDS
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
31 | 155
The characterization done in T1.1 Operational scenarios and technical characterization of pilot
sites has provided the starting information to clearly identify the possibilities of, on the one hand,
the energy generation and grid distribution and on the other, the significant energy users (SEUs).
The analysis of existing DR done in deliverable D1.2 Demand response programs overview has
allowed the definition of generic DR actions adapted to the environment of the three pilots. These
generic actions are described throughout the deliverable D1.4 as shown in the figure.
FIGURE 21. DR ACTION EXAMPLE
These generic DR actions have been then customized for each pilot site. To do so, first of all,
each pilot site’s available equipment for producing, distributing and consuming energy have been
considered. After that, monitoring, metering and actuating systems’ availability have been
integrated because they are indispensable for knowing both the status and results of the actions.
Furthermore, recommendations made by T3.2 User engagement approach and T3.3 Detailing
the user context and improvements of user interaction have also been key to the discovery and
proposal of the suitable DR actions for each pilot site.
Furthermore, below table shows the recommended DR actions for each pilot site.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
32 | 155
TABLE 3. SUMMARY OF DR ACTIONS PER PILOT SITE
DR Action Aarhus Aran Madrid
Load control switches for smart appliances leveraging PV panels
Load control switches for appliances leveraging PV panels
Load control switches for smart appliances leveraging electricity price
Load control switches for appliances leveraging electricity price
Smart thermostats for heating systems
Ventilation control
Thermal load shifting
Smart load shift control for solar photovoltaic
Load control switches for heat pumps
Neighbourhood electric load shifting
Thermal inertia for optimizing heating systems
Thermal inertia for optimizing cooling systems
Neighbourhood DHW shifting
2.5.1.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
WP1 has achieved its objectives and technical goals for the period with minor deviations.
T1.4 DEMAND RESPONSE ACTIONS DISCOVERY FOR EACH PILOT. M4-M13 TEK
Deviations from GA:
There has been a deviation from GA as the finalizing of T1.4 was delayed by one month due to
the work with recruiting pilot households in the Aran Islands pilot and the early deployment in
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
33 | 155
Aran Islands and Madrid pilot sites being more complicated and time-consuming than originally
anticipated. Thus, T1.4 was prolonged, but finalized at the end of month M13.
Corrective actions:
As described above, an extension of one month of T1.4 was applied for and accepted by the
Project Officer.
2.5.1.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
FIGURE 22: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP1 DURING THE 2ND YEAR
2.5.2 WP2: USE CASE DEPLOYMENT AND FOLLOW-UP
WP2 started in M1 (October 2017) and ended in M24 (September 2019).
FIGURE 23. WP2: USER CASE DEPLOYMENT AND FOLLOW-UP GANTT CHART
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
34 | 155
Specific objectives of WP2 were:
• Specification of system reference architecture. • Specification of interfaces toward legacy systems, smart home devices, and third-party
services. • Definition of pilot deployment plan adapted to each pilot’s topological and functional
perspective. • Configuration of existing energy assets and devices. • Deployment of monitoring and home automation systems for early set up. • Deployment of RESPOND platform with HW/SW systems at project pilot sites.
T2.1 and T2.3 were concluded in the first year. T2.2, T2.4 and T2.5 has been carried out during the reporting period.
2.5.2.1 DESCRIPTION OF TASKS
T2.2 SEAMLESS INTEGRATION OF RESPOND TECHNOLOGY TEARS. M1-M13 DEXMA
T2.2 deals with the communication and integration among the key technology tiers of RESPOND
platform, i.e. the set of technical modules developed in the following working packages. In this
regard, it has been analyzed the integration of all underlying concepts featured by core services
of RESPOND platform, such as DR optimization, energy production models, energy demand
forecasting, etc., and suggest their relations and interaction necessary to conduct cooperative
demand management and optimal control strategy.
This task was carried out during the first thirteen months of the project, an extension of one month
of T2.2 was applied for and approved by the Project Officer.
D2.2 Integration of key RESPOND technology tiers was delivered in M13, ensuring at all time a
proper coordination between other project task related like T2.1, T2.3 and also WP4 about ICT
enabled cooperative demand response model and WP5 about System integration and
interoperability.
T2.4 EARLY DEPLOYMENT AT PILOT SITES. M9-M13 ENE
T2.4 started in M9 and finished in M13 instead of in M12, an extension of one month of T2.2 was applied for and approved by the Project Officer. The activities carried out within this task defined the initial RESPOND deployment plan for each pilot site, adapting to the specific characteristics (topological, functional, technical and users’ requirements) of each of the demonstration areas and were conducted respecting the requirements defined in WP1 and fitting the needs of operation scenarios. The main tasks were:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
35 | 155
• Specification of deployment plan to meet DR requirements at pilot sites and match the system architectural model defined in Task 2.1.
• Identification of the monitoring needs and required measuring points for each pilot in relation to both monitoring of energy data and comfort parameters.
• Definition of corresponding measurement framework, necessary to support the collection of the minimal data.
• Analyses of how the RESPOND database(s) will be partitioned and where that data will be recorded, stored, processed and communicated.
T2.5 DEMAND RESPONSE PLATFORM DEPLOYMENT. M13-M24 IMP
T2.5 started in M13 and will carried out until M24. The activities within T2.5 aimed to perform the deployment of RESPOND cloud-based platform and its core services at pilot sites. The goal of these activities is to ensure the proper assembly of the RESPOND solution’s underlying concepts and their deployment in order to conduct optimized control actions under cooperative demand strategy. Activities within this task have been carried out for all the pilots in parallel, having in mind particularities of each of them. This work has been performed in an iterative manner in order to ensure synchronization of activities of related WPs. In order to stay aligned with the operation scenarios defined for each pilot, this task has been performed in accordance with the overall DR requirements and technical characterization made in WP1.
2.5.2.2 SIGNIFICANT RESULTS
T2.2 SEAMLESS INTEGRATION OF RESPOND TECHNOLOGY TEARS. M1-M13 DEXMA
As a result, the interfaces between internal system components and core services, as well as towards external HW/SW systems (such as smart home devices, legacy systems, third party services, etc.) have been specified. All relevant communication details, among all possible layouts of the RESPOND key technology tiers, have been reported in D2.2 document to allow the seamless integration of RESPOND solution in the following WPs (particularly in WP4 and WP5). One of the main challenges has been to match the existing systems and underlying technology concepts with system reference architecture designed in T2.1. To do so, the existing technology available in pilot sites has been taken into consideration along with the new MQTT based architecture, which will be able not only to integrate the new RESPOND technology tiers, but also the legacy systems present in the pilot sites. In addition, the inputs from WP1 in terms of exact deployment options and project requirements have been considered for the activities performed in this task. Last but not least, one of the key objectives of this task has been the definition of the strategy for integration of RESPOND platform enabling early deployment and interfacing with ICT infrastructure at pilot sites.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
36 | 155
During these thirteen months the main results obtained in this task have been:
• A detailed analysis of the integration of all underlying concepts of each analytical service
in aspects such as:
o Description of the application
o Involved developers
o Inputs
o Outputs
o Functionalities
o Additional comments
• The matching of key technology tiers using the reference architecture done in T2.1, has
also been done.
• The interfaces between internal system components, core services and external HW/SW
systems (such as smart home devices, legacy systems, third party services, etc.) has been
provided.
• The strategy for integration of RESPOND platform that will enable early deployment and
interfacing with ICT infrastructure at pilot sites has been described.
This task has allowed to define the main inputs that will be used for the development of the ICT
architecture, the analytical services and the demand response platform, nevertheless is important
to highlight that some minor changes might be expected during the advance of the project.
T2.4 EARLY DEPLOYMENT AT PILOT SITES. M9-M13 ENE
As a result, the deployment plan designed in this task enabled early deployment activities that
provide baseline period measurements on time. Also, it delivered a plan for integration with ICT
systems and energy assets, and home automation systems, either existing or additionally
installed at pilot sites during the project.
Deliverable 2.4 Early deployment activities report was submitted in M13. The document contained a detailed description of what has been implemented at the three pilot sites as well as the related back-end systems. When any part of the implementation has not gone completely according to the plan, those details were discussed on a case by case basis by detailing any blocking elements and suggested resolutions.
T2.5 DEMAND RESPONSE PLATFORM DEPLOYMENT. M13-M24 IMP
The overall control loop composed of measure-forecast-optimize-control main block can be seen
in 25.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
37 | 155
FIGURE 24. RESPOND’S MEASURE-FORECAST-OPTIMIZE-CONTROL LOOP
First, the monitoring layer collects measurements from various sensors and smart meters
deployed in people home which are connected through a dedicated gateway. The collected data
are stored in time-series database InfluxDB (part of the central Data repository) and made
available to other parts of the RESPOND platform. Furthermore, all the building topological
information, including the location of each device and the properties measured or controlled by
each of them, is stored in an Openlink Virtuoso Semantic Repository. This information is obtained
from some Excel sheets containing data point lists (Figure 255) which are filled by people in
charge of each pilot site. As some devices were replaced and new ones were installed within
these last 6 months, the data point list has been in constant change and the Semantic Repository
content has been updated accordingly. Furthermore, the addition of new devices resulted in the
update of the RESPOND ontology in order to cover such devices. The update of the ontology has
been performed following the NeOn methodology and reusing the existing vocabularies as much
as possible.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
38 | 155
FIGURE 25: EXCERPT OF THE EXCEL DATA POINT LIST FILLED BY PEOPLE IN CHARGE OF RESPOND PILOT SITES
Next, in the forecast stage, production and demand forecasters, which employ historical measurements in addition to weather data, provide production and demand profiles for different types (electricity, heating and cooling).
Based on the forecast results, the optimization seeks to find the optimal control and scheduling
of available energy assets, while also considering other contextual information such as energy
prices, import/export regulation, etc. As a result, the optimization stage provides optimal energy
dispatching in a multi-carrier energy environment. Next, these results are translated into
applicable control actions, which can be applied to existing energy assets. This translation is
performed by employing both building simulation (for cooling and heating) and
Heuristics/Optimization (for other energy assets). The control actions must be approved by the
user. This confirmation is done by user preferences (stored in User Adapter) of explicit
confirmation thanks to the smart mobile assistant. User Adapter component can also provide
stored user preferences to other parts of RESPOND platform, such as constraints on temperature
setpoint, device operation intervals, etc. Finally, the control actions are sent to the installed
actuators by complementing both manual and semi-automatic control approaches.
Some of the aforementioned components have been developed by TEK and tested in their
facilities. Afterwards, these components have been dockerized and sent to IMP for their
deployment in the RESPOND platform. Namely, the list of sent dockers contained:
1. Openlink Virtuoso Semantic Repository
2. Nginx proxy server
3. OpenLDAP
4. phpLDAPadmin
5. PostgreSQL database
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
39 | 155
6. Apache Tomcat and mobile app proxy
7. Apache Tomcat and demand forecasting service
8. Apache Tomcat and user adapter service
9. RServe
2.5.2.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
T2.2 SEAMLESS INTEGRATION OF RESPOND TECHNOLOGY TEARS. M1-M13
Deviations from GA:
There has been a deviation from GA as the finalizing of T2.2 was delayed by one month due to
the work with recruiting pilot households in the Aran Islands pilot and the early deployment in
Aran Islands and Madrid pilot sites being more complicated and time-consuming than originally
anticipated. Thus, T2.2 was prolonged, but finalized at the end of month M13.
Corrective actions:
As described above, an extension of one month of T2.2 was applied for and approved by the
Project Officer.
T2.4 DEMAND RESPONSE PLATFORM DEPLOYMENT. M9-M13
Deviations from GA:
An extension of one moth was applied to this task, that was scheduled to be concluded in M12,
however, was finally finished in M13.
Corrective actions:
The majority of actions were on schedule and going according to plan. However, there were a
few deviations that had to be solved:
Aran islands pilot: the biggest blocker was related to Develco devices shipment delays delivery to Aran islands by DEV. So far, two of the houses on the Aran islands were initially installed due to this issue. In addition, there were a few technical blockers, namely Develco devices technical incompatibilities with Irish electrical domestic system, that need to be remedied. However, they were resolved, as finally, the decision of installing Energomonitor devices in the pilot was consensually agreed. For this step, an amendment was initiated in order to shift devices budget between ENE and DEV. Also, the Irish pilot team was strengthening to ensure the engagement process.
Aarhus pilot: there were some budget considerations due to specifics with the installation namely legal requirements and certifications required when dealing with certain types of infrastructure equipment.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
40 | 155
Madrid pilot: there were a few other minor delays, such as the delay of gas measurement in Madrid due to incompatible hardware which was fixed by the end of 2018.
So far, the consortium managed to start collecting baseline data, as well as some survey results from the initial installation and other than the issues specified, the project deployment and overall initial stages run smoothly.
T2.5 DEMAND RESPONSE PLATFORM DEPLOYMENT. M13-M24 IMP
Deviations from GA:
The task leader of T2.5 changed from DEV to IMP. DEV reduced their efforts. See section X
Amendments for detailed information.
Corrective actions:
The aforementioned deviation from GA has been solved through the amendment submitted to
EC.
2.5.2.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
FIGURE 26: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP2 DURING THE 2ND YEAR
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
41 | 155
2.5.3 WP3: USER ENGAGEMNET PROCESS
WP3 ran from M1 to M24. The overall aim of it was to ensure that the RESPOND pilots would
work in actual user context and avoid unsuitable design features that could cause participant
dropout. This was done through developing practical guidelines and criteria for engaging
households (task T3.1), developing the user engagement approach (T3.2) and collecting data on
the user context of the pilots important for adapting the tested DR model to the specific locality
and the users’ everyday practices (T3.3). Finally, and informed by the previous WP3 tasks, WP3
designed a smart mobile application providing a personal energy performance assistant to the
end users (T3.4). T3.1, T3.2 and T3.4 has been finalized during previous reporting periods, while
T3.3 was completed during M19-M24 (i.e. April-September 2019).
FIGURE 27. WP3: USER ENGAGEMENT PROCESS GANTT CHART
Specific objectives of WP3 were:
• Definition of the framework for participant recruitment. • Specification of user engagement approach. • Design specific feedback mechanism according to different user’s patterns. • Engaging end users and promoting their social interaction. • Design of smart mobile application providing a personal energy performance assistant to
the end users.
T3.2 was concluded in the first year. T3.1, T3.3 and T3.4 has been carried out during the reporting
period.
2.5.3.1 DESCRIPTION OF TASKS
T3.1 CRITERIA AND FRAMEWORK FOR PARTICIPANT RECRUITMENT. M1-M13 AAU
In collaboration with RESPOND pilot partners, criteria and guidelines for the recruitment of pilot
households have been developed. Focus of these criteria was to ensure a minimum degree of
socio-economic and demographic diversity within and between the household pilot samples at
the three pilot sites. On basis of the guidelines, recruitment of households was carried out
throughout 2018 up to time of reporting. At time of reporting, 20 households have been recruited
in Aarhus, 11 in Madrid and 11 on Aran Islands. The recruitment process continuous at the Madrid
and Aran Islands locations. As part of the recruitment process, a survey was carried out to provide
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
42 | 155
insight into the socio-economic and demographic profiles of the household samples. Also,
qualitative data on existing habits in relation to a selected number of energy-consuming everyday
practices (particularly dishwashing and laundering) was collected. The survey results and
qualitative data inform the work with designing the final demand response model (WP6) as well
as the mobile application (T3.4).
T3.3 DETAILING THE USER CONTEXT AND IMPROVEMENTS OF USER INTERACTIONS. M7-M24 AAU
This task started in M7 and a first outline of the upcoming focus groups with pilot households was
developed and presented for discussion within the consortium at the Madrid F2F meeting in
October 2018. Input from this meeting has been incorporated in an elaborated draft of guidelines,
which was used as the basis for carrying out two focus groups at the Aarhus pilots in late January
2019.
• Work carried out before the period reported here: At the beginning of the reporting period
(M19-M24), the general outline (guidelines) for caring out focus groups at pilot sites had
already been developed and discussed among the pilot partners. The final guidelines were
ready by March 2019. Also, two focus groups had been carried out in Aarhus in January
2019; these followed the preliminary version of the guidelines, and experiences from the
focus groups provided input to the final version of the guidelines. One focus group focused
on user habits and demand response in relation to heating, the other on habits and demand
response in relation to electricity (appliance use). The focus groups went well with in total
17 participants representing in total 13 households. The participants represented fairly the
diversity of the Aarhus sample regarding age and household composition (family type).
The focus groups were recorded and detailed summaries have been written. At time of
reporting, these summaries are being analysed and condensed into analytical summaries
that will feed into the further preparation of the RESPOND solutions and design.
Detailed summaries of these focus groups had been written. Also, the preparation of the
focus groups in Madrid and Aran Islands had been started.
• Work carried out during the period reported here: In order to tailor the individual focus
groups to the local context of the pilot sites, the pilot partners prepared the topics to be
discussed in the local focus groups by modifying the topics suggested in the general
guidelines (see Appendix 1 of deliverable D3.3). For instance, DR of heating is less
relevant to discuss in Madrid than in, e.g., Aarhus due to differences in weather and
climate. Instead, it is more relevant to discuss DR of air cooling in Madrid, and therefore
one of the focus groups in Madrid focused on the participants’ view on DR of heating, while
one of the Aarhus focus groups focused on heating instead (cooling is not relevant in a
Danish context). By tailoring the specific focus group topics and questions to the local
settings of the pilots, it was ensured that the focus group discussions would be relevant to
the participants and provide the relevant findings for the final analysis and
recommendations of T3.3. The focus groups in Madrid were carried out in May 2019, while
the focus group on Aran Islands was carried out in July 2019. In total, 37 RESPOND
participants (householders) from the local sites took part in the focus groups; 24 men and
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
43 | 155
13 women. In order to ensure consistency in how the findings from the focus groups were
reported to AAU for the final (comparative) analysis, AAU developed a guideline/template
on how the pilot partners should prepare the summaries of the individual focus groups. On
basis of the summaries from the individual focus groups, AAU prepared the final analysis
and recommendations reported in deliverable D3.3 Findings and recommendations from
focus groups on user context.
In total, the focus groups provided a better understanding of the user context and feed into
the final design of the demand response solution. An important part of the focus groups is
the discussion of the draft version of the DR solution and mobile application for feedback
from pilot households on these.
T3.4 SMART MOBILE CLIENT AND PERSONAL ENERGY PERFORMANCE ASSISTANT. M7-M13 TEK
This task aims at developing an intuitive and simple mobile app towards the engagement of the
users (pilot households).
2.5.3.2 SIGNIFICANT RESULTS
Overall, WP3 is proceeding well and are providing detailed information on the user context at the
pilot sites as well as recommendations for developing user engaging DR designs and mobile
apps.
T3.1 CRITERIA AND FRAMEWORK FOR PARTICIPANT RECRUITMENT. M1-M13 AAU
The findings have been reported in D3.1 Criteria and framework for recruiting and engaging
finalized in M13 (October 2018). Among other things, it is concluded that a sufficient level of
diversity with regard to key socio-economic and demographic variables such as age, gender,
education and family type has been achieved at all places (with the Aarhus sample representing
the highest level of diversity). This diversity is important as this helps ensure representativeness
and validity of the RESPOND findings. Though, there are still some biases that needs to be taken
into account then carrying out the pilots and analysing the results of them. For instance, the Aran
and Madrid household samples have some over-representation of older generations (and less
families with children), which should be considered in the later analysis.
T3.3 DETAILING THE USER CONTEXT AND IMPROVEMENTS OF USER INTERACTIONS. M7-M24 AAU
The following is a brief summarize of the key findings of T3.3 (see D3.3 for details):
• Dishwashing and laundry come up across all sites as the types of electricity consumption that
the focus group participants find most likely and practical to time-shift.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
44 | 155
• The focus groups show that whether people are working or not (i.e. at home or not during
daylight hours) is important for how difficult and realistic it is perceived to time shift
consumption, although this might be less decisive in the Madrid case as many households
here have housekeepers staying at home during the day.
• Regarding automation or remote control of demand response actions (e.g. time shifting
dishwashing), the focus groups come up with mixed results. Many favour the idea of
automation or remote control, but several also find it attractive if they just can get
notifications/recommendations via the mobile app about when it is optimal for them to
consume energy.
• Regarding variable electricity prices (dynamic pricing), the consensus across focus groups is
that real-time pricing is too difficult to follow, while many find the static Time-of-Use pricing
much simpler and easier to follow (e.g. to build daily routines around). Peak Production
Rebates also got a positive reception on general, especially in Aarhus as this scheme could
help them optimise the consumption of their local renewable electricity production (PVs)
• Money saving is in general seen as a key motivational driver for changing daily habits and do
demand response actions. However, also other motivational drivers are mentioned such as
doing something good for the environment or the positive feeling of consuming local renewable
energy. The latter seems to be another important motivational driver that might have a similar
strength as money savings.
• In Madrid, demand response of air cooling was discussed. Consensus was that at least some
of the cooling could be time shifted or peaks could be shaved (e.g. by using less power-
consuming mechanical ventilators instead of air conditioning).
• The Aarhus focus group on heating shows a high diversity between households regarding
heating practices and preferences as well as often idiosyncratic approaches of the individual
households on how to control and adjust heating. This diversity needs to be considered when
designing the RESPOND solution.
• The RESPOND demand response solution for heating, which is going to be trialled in Aarhus,
was overall well-received by the Aarhus focus group participants. There is agreement that the
demand response scheme (temperature set-back in morning hours with a short pre-heating
before set-back) must be automated. Also, it should be easy to “override” the automated
control in cases of deviations in peoples’ daily routines or if they feel the temperature is not as
desired.
• The focus groups provided much feedback on the preliminary RESPOND mobile app design.
Some of the key recommendations and observations are: The app should not be too
complicated to use and navigate in, although it might be a good idea to have “two levels” of
user interfaces to accommodate different user needs (a simple and a more detailed level).
Across focus groups, there was also a widespread interest in getting access to appliance-
specific breakdowns of the electricity consumption of households. The idea of comparing the
energy performance of the individual household to the performance of neighbours got a mixed
reception; comparing the level of individual self-sufficiency was the type of comparison that
attracted most interest. Furthermore, the idea of recommendations and notifications on, e.g.,
optimal demand response actions were in general well-received.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
45 | 155
• The deliverable presents four different usage scenarios. The aim of these scenarios is to
“translate” the findings from the focus groups into a limited number of scenarios with
recommendations on how the design of the RESPOND solutions in general – and the
RESPOND app specifically – can be tailored/adapted to the everyday practices, needs and
wishes of the residents (as reported in the focus groups). Each scenario focuses on one
specific usage (feature/function) of the RESPOND demand response solution and app. The
four scenarios are: 1) demand response of heating; 2) Peak production rebates and local
demand response; 3) demand response of cooling; and 4) Automated and remote control of
appliances.
• Finally, the deliverable concludes with some proposals for competitions that might be set up
at the local pilot sites in order to promote the pilot households’ interest and engagement in the
RESPOND demand response solutions and mobile app.
T3.4 SMART MOBILE CLIENT AND PERSONAL ENERGY PERFORMANCE ASSISTANT. M7-M13 TEK
Existing mobile apps have been analysed, as well as the latest app design techniques and
methodology. Furthermore, latest trends in users experience have been investigated, with views
to proposing a high quality and engaging mobile app. Finally, feedback from RESPOND project
partners have been collected. This information has been valuable, as they cover different areas
of expertise related to the DR in dwellings. On basis of this, the overall design concept for and a
first version of the RESPOND mobile app have been developed, as reported in D3.4 Personal
energy performance assistant design (finalized in M13). This first version of the mobile app will
be subject to further improvements and extension throughout the time up to the final validation
trial, partly based on the outcome of user context analysis in T3.3. Below is the navigation diagram
of the mobile app and two selected screenshots illustrating the real-time neighbourhood
consumption for Android (left) and the neighbourhood energy generation for iOS (right):
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
46 | 155
FIGURE 28. MOBILE APP’S NAVIGATION DIAGRAM
2.5.3.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
T3.1 CRITERIA AND FRAMEWORK FOR PARTICIPANT RECRUITMENT. M1-M13 AAU
Deviations from GA:
There has been a deviation from GA as the finalizing of T3.1 was delayed by one month due to
the work with recruiting pilot households being more complicated and time-consuming than
originally anticipated. Thus, T3.1 was prolonged, but finalized at the end of month M13.
Corrective actions:
As described above, an extension of one month of T3.1 was applied for and approved by the
Project Officer.
T3.3 DETAILING THE USER CONTEXT AND IMPROVEMENTS OF USER INTERACTIONS. M7-M24 AAU
Deviations from GA:
There have been two deviations from GA (both deliberately chosen to optimize the completion of
T3.3):
1) In the GA, it was planned to carry out two focus groups at each pilot site. This was done in
Madrid and Aarhus, but on Aran Islands only one focus group was carried out. This was due to a
combination of fewer pilot households on Aran Islands and the timing of the focus groups (to be
done during the busiest tourist season of the year, which made many of the pilot households
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
47 | 155
having little time for participating in the focus group). It was therefore decided to carry out only
one focus group (with invitation sent to all pilot households) in order to ensure a sufficiently high
turnout for this focus group.
2) In the GA, it is stated that the focus groups should be audio recorded (to provide optimal basis
for the later analysis of the participants’ comments and discussions). However, the pilot partner
in Madrid (FEN) judged – on basis of their close knowledge with the pilot households – that this
would create troubles as the pilot households would not feel comfortable with being recorded.
Therefore, it was decided to have one person from FEN to make detailed notes of comments and
discussion during the focus groups. This provided a good and sufficiently detailed basis for the
later analysis of the Madrid focus groups.
Corrective actions:
See above.
T3.4 SMART MOBILE CLIENT AND PERSONAL ENERGY PERFORMANCE ASSISTANT. M9-M13 TEK
Deviations from GA:
There has been a deviation from Grant Agreement as the finalizing of T3.4 was delayed by one
month due to the work with recruiting pilot households being more complicated and time-
consuming than originally anticipated. Thus, T3.4 was prolonged, but finalized at the end of month
M13.
Corrective actions:
As described above, an extension of one month of T3.4 was applied for and approved by the
Project Officer.
2.5.3.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
48 | 155
FIGURE 29: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP3 DURING THE 2ND YEAR
2.5.4 WP4: ICT ENABLED COOPERATIVE DEMAND RESPONSE MODEL
WP4 runs from M7 (April 2018) to M30 (March 2020). Overall, WP4 is proceeding well. The overall
aim of it is to undertake the key activities that will enable cooperative demand response actions.
Within this WP, task 4.1 built the semantically enriched information model that provides a common
understanding between all components of the system, and concretely, with the smart services
that are being developed in the WP. The rest of the tasks will lead to the development of the smart
analytical services and their integration. As a consequence, this will allow the optimization of the
energy usage at local and neighbourhood level to take advantage of the local RES resources and
to be adapted to the Demand Response targets.
FIGURE 30. WP4: ICT ENABLED COOPERATIVE DEMAND RESPONSE GANTT CHART
Specific objectives of WP4 were:
• Development of semantic information model serving as a common vocabulary. • Intergradation of multi-carrier supply side optimization and demand side management. • Energy dispatch optimization at both household and neighborhood level. • Energy demand and production forecasting. • Energy data analytics empowered by system modelling to perform an optimized control.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
49 | 155
Below image shows the RESPOND services interaction diagram, emphasizing on the modules to
be developed by each Task within the WP. It is worth mentioning that this figure lacks the
Predictive Maintenance module which, due to the scarce data availability, will be implemented in
during the last 6 months of the WP4.
FIGURE 31. MODULES TO BE DEVELOPED IN DIFFERENT TASKS WITHIN WP4
T4.1, T4.2, T4.3, T4.4 and T4.5 has been carried out during the reporting period.
2.5.4.1 DESCRIPTION OF TASKS
T4.1 SEMANTIC INFORMATION MODEL. M7-M18 TEK
T4.1 has been carried out during the months 7 to 18 according to what it was scheduled. The aim
of this model is to provide resources with an explicit and unambiguous semantics. Without this
explicit semantic assignment, different users could refer to the same resource with different
meanings. Furthermore, a semantic information model improves semantic interoperability,
providing both humans and machines with a shared meaning of terms. The proposed semantic
model is based on the RESPOND ontology, which has been developed based on the well-known
NeOn Methodology to ensure its quality. Moreover, a set of related ontologies have been
reviewed and the most adequate have been reused. On top of that, the ontology has been made
online and it is well-documented, which is expected to further foster its understandability and
reusability. The ontology has been then instantiated with information of buildings and installed
devices. This information is extracted from a set of Excel sheets filled by people in charge of the
RESPOND pilot sites. However, the measurements and actuations made by IoT systems is not
used to instantiate the ontology. Instead, this information is stores in InfluxDB and the ontology
instantiation contains the Data Point ID.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
50 | 155
The model development process has been reported in D4.1 Semantic Information Model finalized
in M18.
T4.2 INTEGRATION OF DEMAND RESPONSE WITH SUPPLY/DEMAND SIDE MANAGEMENT. M7-M24 IMP
This task started in M7 and ended in M24. The essential core of the optimization procedure that is essentially described in task T4.2 is the underlying model. For this application, we have selected the Energy Hub depicted in Figure 32, or to be more precise, its linear variant. Such a model represents energy flow through a so-called unit of energy consumption that can either be a household, office, or a larger infrastructure such as a neighborhood, a building and so on.
FIGURE 32: GENERAL STRUCTURE OF THE ENERGY HUB
The Energy Hub models the fundamental processes regarding energy – energy transformation and energy conversion by utilizing matrix multiplication in different stages. In the input stage, we find input storage conversion (𝑆_in, not depicted in the figure), input transformation (𝐹_in), conversion (𝐶), export (𝐷_exp, not depicted in the figure), output transformation (𝐹_out) and output storage conversion (𝑆_out, not depicted in the figure). Out of these, the matrices representing energy conversions (S_in, C and S_out) are essentially diagonal matrices whose coefficient represent the loss factor that is used to model losses when, for example, converting electric energy from AC to DC or vice versa when storing or drawing energy from an electric battery, or otherwise, the losses that occur in a heat exchanger when filling a hot-water tank. Also, these losses also model AC to AC transformations that occur in conventional transformers or DC to DC transformations in adequate scenarios. On the other hand, transformation matrices (𝐹_in and 𝐹_out) depict energy carrier aggregation and disaggregation. For example, if the electric load
can be fulfilled by both energy from the solar PV and the grid, 𝐹_out should model this energy aggregation before the load stage adequately. Conversely, if a single energy carrier, district heating for example, fulfills both thermal demand and domestic hot water (DHW), 𝐹_in should model this disaggregation adequately. The Energy Hub is fully described by its variables (input power 𝑃_in, input storage energy 𝑞_in, power to converters 𝑃_cin, power from converters 𝑃_cout, exported power 𝑃_exp, output power
𝑃_out, output storage energy 𝑞_out, and load 𝐿). Because these variables exist in every time step, they are usually represented by vectors and are optimized using (mixed integer) linear programming. The optimizer, in a process depicted in Figure 33 should maintain two goals in mind when looking for the optimal solution: minimization of consumer costs and minimization the differences between the measured load profile and the required load profile. In order to provide such capabilities, the optimizer receives inputs from the demand forecaster (red line) service in form of an array that describes the predicted load in the next (let’s say) 24
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
51 | 155
hours, the grid requests in form of indicators when a demand response (DR) event will occur in the next 24 hours and what is the requested load profile at that (those) time (times), the production forecaster services in form of an array that describes the predicted availability of renewable sources and finally, the day-ahead (or fixed) pricing scheme. The optimizer then returns an optimized profile (green line) that serves as an input for another service called the rule-based notification engine.
FIGURE 33. THE OPTIMIZATION PROCESS
This service considers the differences in the forecast load and the optimized load profile, potentially checks the statuses of smart appliances (smart plugs, smart cables etc.) and issues adequate notifications and/or recommendations to the end users but can also communicate with visualization dashboards etc. When the user receives a notification, he is presented with the options of dismissing (ignoring) it, choosing to take manual actions (sometimes these are the only ones available) or allowing for an automatic response (if the considered appliance is connected to a smart plug or cable) and giving the system the authorization to act on his behalf.
FIGURE 34. THE OPTIMIZATION PROCESS
Although DR events are most commonly used when referring to electric loads, the assumed model allows for simple and straightforward definitions of DR events for any type of load, be it electric or thermal. Therefore, the considered example, presented in figure 34¡Error! No se
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
52 | 155
encuentra el origen de la referencia., will implement a DR event for all three types of load. The figure shows how the optimizer upholds the requested load profile at times when a DR event is active while simultaneously minimizing overall costs of system operation by shifting the load difference within the appropriate bounds to a period where, in this case, local energy production is present (the time of day where the sun shines the brightest and therefore the PV array outputs the most energy). The same algorithm could also be used when variable tariffs are at play in which case that the load shifting would be executed when the price of importing energy is smaller.
T4.3 OPTIMAL ENERGY DISTPACHING AT HOUSEHOLD AND NEIGHBOURHOOD LEVEL. M13-M24 IMP
This task started in M13 and ends in month 24. This task aims at enabling the application of the
Integrative Energy Optimiser (developed in Task 4.2) both at the household and district levels. A
single Energy hub can be used to model systems of different scale (i.e. small, intermediate and
large scale), from single households to entire flats, neighborhoods or even city blocks as long as
the modelled units share a common topology.
However, if the differences in topology are too significant, or the interconnections and cross-
trading between individual users need to be facilitated, the use of multiple different Energy hub
models should be considered. In this case, additional constraints allow for achieving various
different tasks with the optimization. At the moment of writing this report, the aforementioned
models are being developed.
T4.4 ENERGY PRODUCTION AND DEMAND FORECASTING. M13-M36 TEK
T4.4 started in M13 and ends in month 30.
M13-M18 period:
Production forecast
This part of the T4.4 has been worked on for six months at this point. The aim of this service is to
provide necessary information about renewable sources’ production depending on the weather
conditions for the optimizer in order to adequately reschedule consumer’s consumption.
In the first stage, different state-of-the-art techniques were studied, so as to select the appropriate
methodology for the RESPOND project. Numerous factors were taken into account when the
choice was to be made. The Forecasting horizon, which represents the time interval for which the
forecast should be made, was defined by the optimizer’s specification. Namely, due to the fact
that other inputs that affect optimization process, such as pricing, are available only one day
ahead, it was clear that the forecasting horizon should be 24 hours, as well. Having in mind both
previously discussed, recently published, papers from the field of forecasting the renewable
sources’ production and previous work on FP7 Energy Warden project, as a final decision, data
driven, or precisely machine learning, models were chosen as the most appropriate ones for this
task.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
53 | 155
Strictly speaking, the architecture for the production forecaster was specified, as shown in Figure
35, where sub model m forecasts production in m hours and its inputs correspond to the
characteristics for that same time. So, for every renewable source 24 sub models for forecasting
its production for the next 24 hours in hourly resolution will be provided.
FIGURE 35. PRODUCTION FORECAST MODEL SPECIFICATION
After defining the architecture, analysis on adequate input characteristics was conducted.
Namely, it was indisputable that various weather conditions should be included, nonetheless it
emerged that performance dramatically decreased if solar irradiation was not introduced.
Therefore, weather services which provide this necessary information were explored, and the
Weatherbit.io has been chosen, as it covers the variety of weather data together with irradiation.
Apart from data, analysis on adequate models was carried out with the available data, as well.
Namely, two different scenarios were tested – one considering photovoltaic panel and one
considering solar thermal collector’s production.
Photovoltaic panel
When production of a PV panel is considered, apart from the available historical data from
Weatherbit.io service, we have used data obtained from PUPIN’s local power plant for developing
the prototype and obtained results are shown in ¡Error! No se encuentra el origen de la
referencia. (MAE – mean absolute error, MSE – mean square error, RSE – relative square error,
RAE – relative absolute error). Comparing MSE between different methodologies, neural network
performed the best. However, due to the fact that different methodologies performed similarly and
that performance highly depends on the data, the final decision on which methodology will be
MODEL 1
MODEL 2
MODEL 3
MODEL 24
x(t+1) y(t+1)
x(t+2)
x(t+3)
x(t+24)
y(t+2)
y(t+3)
y(t+24)
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
54 | 155
implemented on each pilot has not been made yet. Namely, different methodologies will be tested,
and the one with the highest performance will be chosen. Moreover, for different pilots, different
models might be picked.
TABLE 4. PV PRODUCTION PROTOTYPE RESULTS
methodology MAE MSE RSE RAE
SVR - RBF 0.73 2.29 0.7 0.41
SVR - RBF 0.68 1.91 0.65 0.34
SVR - linear 0.72 2.1 0.69 0.37
SVR - sigmoid 0.66 1.8 0.64 0.32
Linear regression 0.76 1.6 0.73 0.28
Neural network 0.69 1.46 0.66 0.26
KNN 0.76 2.2 0.73 0.39
KNN weighted 0.71 2.12 0.69 0.38
Random forest 0.67 1.84 0.65 0.33
Solar thermal collector
Similarly to the PV production, a prototype was developed for the STC forecaster, as well. As the
outputs for the training and validation purposes, publicly available data from
www.solarheatdata.eu service was used, whilst the weather data was obtained from the same
service as before, and the results are presented in ¡Error! No se encuentra el origen de la
referencia..
TABLE 4. STC PRODUCTION PROTOTYPE RESULTS
methodology MAE MSE
SVR - RBF 0.115 0.023
SVR - RBF 0.110 0.025
SVR - linear 0.125 0.024
SVR - sigmoid 0.123 0.024
Linear regression 0.118 0.026
Neural network 0.104 0.024
KNN 0.107 0.033
KNN weighted 0.106 0.032
Random forest 0.084 0.023
After developing these prototypes, our next steps are developing the corresponding pilot models
and deploying the service on the web server.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
55 | 155
Energy demand forecast
The main aim of developing this service is to be able to foresee the energy demand of dwellers
ahead of time. Combining this information with the expected production of RES is expected to
enable the suggestion of suitable DR actions, thus reducing peak demands and allowing the
exploitation of renewable energy.
Similar to the energy production forecaster’s development, different state-of-the-art techniques
were analysed as well as related work in existing literature. As for deciding the horizon of the
energy demand forecaster, bearing in mind the factors that affect the optimization process, it was
set to 24 hours. Furthermore, since mathematical or physics-based models may fail at accurately
predicting the energy demand due to the existing gap between the theoretical and real
consumption of the different assets, data-driven models were chosen for this task.
Due to the scarcity of available data coming from RESPOND pilot houses, a prototype of energy
demand forecaster was developed for another use case where similar data was available.
Namely, an energy demand forecaster for an office was developed in order to test the
performance of different machine learning algorithms. Among the variables taken into
consideration for the development of this prototype the dweller’s electric consumption, calendar
and the external weather conditions can be highlighted. Regarding the analysed algorithms, they
include linear regression, SVM, decision trees and time series models ARIMA. ¡Error! No se
encuentra el origen de la referencia. summarizes the obtained MAEs for this use case.
TABLE 5. OBTAINED MAES FOR DEMAND PREDICTION USING DIFFERENT ALGORITHMS
ALGORITHM MAE
Linear regression 0.386
SVM - SMOReg 0.263
Decission Trees 0.287
ARIMA 0.223
In this use case, best results were obtained with ARIMA, as shown in Figure 36.
FIGURE 36. DEMAND FORECAST OF THE USE CASE OFFICE WITH ARIMA
Forecasts from ARIMA(3,1,0)
0 50 100 150 200
1.0
1.5
2.0
2.5
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
56 | 155
The development of this prototype is aimed at being calibrated with data coming from different
pilot houses, thus allowing an accurate estimation of the energy demand both at a house and at
a district level. The most immediate energy demand development of upcoming weeks is for the
Madrid pilot site due to the data availability.
T4.5 DATA ANALYTICS AND OPTIMIZED CONTROL. M13-M36 TEK
T4.5 started in M13 and it ends in M30. This task aims at integrating the outcomes of all previous
tasks of the WP in order to perform actual control actions and influence the load according to
cooperative DR strategies.
M13-M18 period:
During the last six months the main results obtained in this task can be summarized as follows:
• Survey of Aran Island pilot houses to help on the installation of a smart metering system
and collect all the needed information to develop a detailed simulation model of one
residential house
• Development of simulation models of one dwelling in Aran Island
• Identification of potential predictive maintenance task.
For the development of the selected dwelling in the Aran Islands, the IESVE simulation software
has been used. In addition, a dedicated library for grey-box building simulation modelling has
been developed in Modelica language. As a result, the ROM (Reduced Order Model) has been
developed, which is meant to be able to forecast the energy consumption of a single house due
to heating/cooling system with a defined indoor air temperature set point. Moreover, the
development of a dedicated interface for data input collection to generate ROM of a single
residential house has been undertaken. Finally, a preliminary analysis of accuracy comparison
between a detailed IESVE simulation model and a ROM has been performed.
The identification of suitable predictive maintenance tasks to ensure the adequate performance
of systems and equipment has also been performed. Driven by the performance prediction of
different component and assets, early anomalous performances are expected to be identified, in
order to suggest the corresponding maintenance tasks. Figure 37 shows the different scenarios
identified in predictive maintenance tasks regarding performance of different components and
systems.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
57 | 155
FIGURE 37. POTENTIAL PERFORMANCE OF DIFFERENT SYSTEMS AND COMPONENTS
As part of this task, the feasibility of Demand Response scenarios for each pilot test house has
been analyzed. Towards this goal, the analysis made on T1.4: Demand Response actions
discovery for each pilot, and the dedicated conference calls in order to have a clear picture of
data availability for each pilot test case have played a key role. Among the list of potential DR
strategies, focus has been placed on exploiting building inertia and indoor air temperature set-
point adjustment.
The latest work performed in this task is related to the survey performed on other two dwellings
in the Aran Islands in order to the installation of a smart metering systems and for the development
of detailed and ROM building simulation models. The activity is expected to help continuing the
research related to ROM input/output accuracy.
RESPOND platform’s main objective is collecting, storing and processing data obtained from
different field level devices, and sending the control actions to actuators. The collected data is
further processed by means of analytic services which will be developed during RESPOND
project. The platform proposed in deliverable D2.2: Integration of key RESPOND technology tiers
has been modified due to the findings after completing deliverable D1.4: Pilot specific demand
response strategy and tasks performed throughout WP3. Namely, User Adapter and Scheduler
modules have been added. The former enables the adaptation of DR actions to user preferences,
as it gathers concrete occupants’ preferences regarding comfort levels, preferred timetables and
automation possibilities to be considered prior to the execution of a recommended action. The
latter module allows scheduling automatic actions taking into consideration user’s preferences
as well. Therefore, a suitable DR action can be executed in a time slot preferred by the occupant.
These considerations have been captured in the two new modules of the diagram. The resulting
flow of data between different components is shown in Figure 38.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
58 | 155
FIGURE 38. RESPOND PLATFORM'S DATA FLOW
2.5.4.2 SIGNIFICANT RESULTS
T4.1 SEMANTIC INFORMATION MODEL. M7-M18 TEK
The resulting semantic information model, which will be the glue to integrate all the data managed
by the RESPOND platform, has been presented in deliverable D4.1 Semantic Information Model.
During the last six month the main results obtained in this task can be summarized as follows:
• The update and publication of the semantic model
• The development of an ontology instantiation process
• The definition of predefined parametrizable SPARQL queries
Although a first version of the RESPOND ontology was developed by the end of month 12, new
ontology requirements have triggered the need of updating the ontology. For instance, the new
version of the RESPOND ontology reuses another ontology that was not initially reused, namely,
the SEAS Feature of Interest ontology. Therefore, the RESPOND ontology reuses BOT, SAREF
and SEAS Feature of Interest ontologies.
Figure 39 shows the RESPOND ontology's main classes and properties. It is worth mentioning
that every update of the ontology is methodically performed, based on the well-known NeOn Methodology.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
59 | 155
FIGURE 39. RESPOND ONTOLOGY'S MAIN CLASSES AND PROPERTIES
In order to ease the understanding of the semantic model, a documentation with diagrams, human readable descriptions of the ontology terms and a summary of changes with respect to previous versions of the ontology has been created. Furthermore, the ontology has been made online to foster its reusability. The RESPOND ontology’s instantiation, often referred to as the ABox, was generated leveraging the pilot sites data point lists. These data point lists are captured in Excel sheets and contain information regarding the devices installed in pilot sites and include additional information such as their location and the property they measure. Figure 40 shows an excerpt of the pilot sites data point list.
FIGURE 40. DATA POINT LIST EXCERPT
However, the measurements and actuations made by IoT systems is not used to instantiate the ontology. Instead, this information is stores in InfluxDB and the ontology instantiation contains the Data Point ID. Instantiating each and every pilot house or device can become an arduous task. Specially, bearing in mind that new houses can be added at any point, and devices can be added, removed or relocated. Therefore, there is a dire need to automatize this data point list instantiation process. For that purpose, RESPOND has developed a service based on Apache Jena framework.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
60 | 155
Furthermore, the instantiation process has been helpful to detect new ontology requirements and even ontology weaknesses. This has led to the update of the RESPOND ontology, redefining existing concepts and relationships, as well as introducing new ones to fully satisfy existing requirements. Moreover, this allows a more accurate representation of the pilot site status and enables the exploitation of this information.
Thanks to this semantic representation, different information can be queried. To ease this
information query process, a set of predefined and parametrizable SPARQL queries have been
defined. These queries allow the users to retrieve the required information only by adding a few
parameters. For instance, the list of devices installed within a house can be retrieved executing
the SPARQL query shown in
Listing 1, by replacing the wild card $HOUSE_ID is replaced by the target house’s identifier.
PREFIX dc: <http://purl.org/dc/terms/> PREFIX bot: <https://w3id.org/bot#> SELECT DISTINCT ?deviceID WHERE{ {?space bot:hasElement ?device; dc:identifier ?houseID.} UNION {?space bot:hasSpace ?subspace; dc:identifier ?houseID. ?subspace bot:hasElement ?device.} ?device dc:identifier ?deviceID. FILTER( ?houseID = $HOUSE_ID ) }
LISTING 1: SPARQL QUERY TO RETRIEVE THE LIST OF DEVICES INSTALLED WITHIN A HOUSE
T4.2 INTEGRATION OF DEMAND RESPONSE WITH SUPPLY/DEMAND SIDE MANAGEMENT. M7-M24 IMP
With the aim of influencing grid stability and environmental protection through the Demand
Response (DR) events, optimization engine was proposed to be the core of the innovative solution
in the RESPOND platform. The main idea was to provide the optimal profile in accordance with
the forecasted production and demand, day-ahead prices and DR events using demand flexibility.
Therefore, within Task 4.2 the methodology has been developed and potential use cases in which
a DR event is induced using peak pricing in order to force load adaptations.
For the optimization purposes, the Energy Hub model has been used. Its core idea is modelling
energy transformation and conversion through matrix multiplication. Namely, the fundamental
constraints of the Energy Hub system depict energy flow and energy transformations through a
set of stages input (raw) energy storage 𝑄in, input energy transformation 𝐹in, energy conversion
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
61 | 155
𝐶, energy export 𝐸exp, output energy transformation 𝐹out, output (user) energy storage 𝑄out and
loads 𝐿.
Finally, within the Task 4.2, simulations for the Energy Hub optimization for individual households
for each pilot were carried out.
With regards to the topology of each pilot, optimization constraints, synthetized demand profiles
for different load types (electric, thermal, DHW), forecasted renewable energy and prices were
defined. Finally, implicit DR showcase was defined through price adoption. In other words, grid
price has been increased from 4pm to 10pm, while decreased for the rest of the day. Price for the
district heating was decreased from 6am to 5pm and increased during the rest of the day. Results
are shown in Figure and Figure, where it can be seen how consumption is adapted to fit the
pricing scheme. All of these results are deeply analyzed in Deliverable 4.2 which was submitted
on time on September 30th.
𝛥𝐿+ ≤ +𝐼ሺ𝛥𝐿+ሻ ⋅ Δ𝐿max+
𝛥𝐿− ≥ −𝐼ሺ𝛥𝐿−ሻ ⋅ Δ𝐿max−
𝐼ሺ𝛥𝐿+ሻ + 𝐼ሺ𝛥𝐿−ሻ ≤ 1
𝐿ሺ𝑘ሻ
23
𝑘=0
= 𝐿predictedሺ𝑘ሻ
23
𝑘=0
𝐿 + 𝛥𝐿+ + 𝛥𝐿− = 𝐿required
Use case 1
Use case 2
FIGURE 41 - ENERGY HUB STRUCTURE FOR DIFFERENT USE CASES
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
62 | 155
FIGURE 42 - DR LOAD DEVIATION
FIGURE 43. NOMINAL AND OPTIMIZED INDIVIDUAL
FIGURE 44. PREDICTED AND OPTIMIZED LOAD PROFILES
FIGURE 42. EXAMPLE OF LOAD SHIFTING IN TIME FROM NOMINAL LOAD SCHEDULE (TOP) WITH SHIFTING WINDOWS TO THE
OPTIMIZED LOAD SCHEDULE (BOTTOM)
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
63 | 155
T4.3 OPTIMAL ENERGY DISPATCHING AT HOUSEHOLD AND NEIGHBOURHOOD LEVEL. M13-M24 IMP
M13-M18 period:
A very useful feature of the Energy hub model (chosen in T4.2) is its high scalability potential. Namely the same type of model can be used to model a wide variety of different microgrid infrastructures. First of all, the most basic, single-unit system, like a household, apartment or an office can be modeled using one energy hub. However, if a larger multi-unit system is considered, but it is comprised out of different units that share a common topology, such a system, although being multi-unit, can still be represented using one energy hub. On the other hand, if a system is comprised out of units that have different setups, i.e. they do not share a common topology, such a setting requires multiple Energy hubs to be used. When considering optimization complexity, using one hub to represent multiple units yields a model that has a significantly larger number of dimensions than what a single model for one such unit would have. Therefore, if time is an essential factor, a setup where each household is individually represented might give better results against a setup where one big hub is used because the complexity of individual models increases linearly (O(N)) whilst the complexity of solving big unified models grows exponentially (O(N^a)). However, since the Respond projects tackles the optimization from a neighborhood standpoint and individual users are generally not modeled, unified models are preferred. Also, the Energy hub has clearly segregated input and output variables (imported energy P_in, exported energy P_exp and loads L) and therefore allows for simple and easy interconnections between models i.e. placing them in series or in parallel. This behavior can be obtained by specifying adequate constraints over these input/output variables. Having this in mind, modeling a system where besides the traditional energy trading between users and the grid, importing and exporting energy from local production capabilities and peer-to-peer (P2P) trading can be easily achieved. Beginning with a simplest setup, Below image shows a single unit of energy consumption that can import electric energy from the grid or local distributed production and thermal energy from a power plant or, again, local renewable production, but can also sell excess energy back to the grid (this is usually only the case for electric for now). Such a simple setup is easily obtained by using a single energy hub because it supports for all the mentioned features natively.
FIGURE 45. SIMPLE ONE-HOUSEHOLD SETUP
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
64 | 155
Moving on, if we consider a homogeneous system where a neighborhood of households (or a flat
of apartments) share a common topology, such a system, in the below image, can also be easily
modeled with one Energy hub. If individual units require modeling, specific variable ranges are
assigned to each of the units.
FIGURE 46. HOMOGENEOUS MULTI-HOUSEHOLD SETUP
Finally, if a heterogeneous system is considered, where different units have different topologies,
like in the below diagram, such a system should be modeled by using individual Energy hubs per
each different unit because different matrices or constraints need to be applied.
FIGURE 47. HETEROGENEOUS MULTI-HOUSEHOLD SETUP
In conclusion, a single Energy hub can be used to model systems of different scale (small, intermediate and large scale), from single households to entire flats, neighborhoods or even city blocks as long as the modeled units share a common topology. On the other hand, if the differences in topology are too significant, or we want to facilitate interconnections and cross-trading between individual users, we should opt for the use of multiple different Energy hub models. In this case, additional constraints allow for achieving various different tasks with the optimization. In accordance with the given analysis, models of the pilot sites were developed and are presented in the figures below.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
65 | 155
FIGURE 47. AARHUS PILOT MODEL
FIGURE 48. ARAN PILOT MODEL
FIGURE 49. MADRID PILOT MODEL
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
66 | 155
M19-M24 period:
Energy Hub optimization methodology chosen in Task 4.2 has been further exploited within Task
4.3. Namely, its important characteristic being the scalability potential was especially exploited
having in mind that RESPOND project tackles aggregated sets of users, at the so-called
neighbourhood level. Therefore, the main goal of Task 4.3 was the instantiation of the individual
model for each pilot site and developing the optimization as a service.
Two distinct types of models were employed within the RESPOND project for the purposes of
energy flow modelling: one where the pilot consisted of homogeneous units i.e. where each
apartment or house within the neighbourhood has the same topology, input carrier types, pricing
scheme, etc. (used for Aarhus and Madrid pilots) and one in which the pilot consisted of
heterogeneous households and therefore to depict it truthfully, multiple interconnected Energy
Hubs had to be employed to obtain a proper model for simulation (used for Aran Islands).
As the apartments form the Aarhus pilot are situated within two buildings with the shared PV plant,
one Energy Hub model was initialized in consistence with the pilot’s topology. Prices were taken
as the current ones, whilst for the purpose of developing the optimization service, forecasted
demand and production energy has been collected from the MySQL database. Madrid
optimization model consists out of one Energy Hub as well, because of its homogenous structure.
However, electrical energy pricing scheme is dynamically changing, resulting in the optimization
service collecting day-ahead prices from MySQL database.
Figure 51. Modified price profile for load
reduction
Figure 52. Load profile with load reduction
Figure 50. Imported power profiles with load reduction
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
67 | 155
Finally, Aran Islands pilot site’s optimizer was the most complex due to its heterogeneous
structure. Therefore, the model consisted out of three different Energy Hubs – one representing
houses without any renewable energy source generation or storage, one representing houses
with PV panels and without any storage infrastructure and the last one for the home with both PV
panels and battery. Even though this model has been developed, it has not been integrated with
in the platform so far, due to the fact that finalization of the pilot houses is in progress, so the
topology is not finalized yet.
Having developed appropriate optimization models, two different use cases using implicit and
explicit DR were defined. The implicit one is used for Madrid pilot site, as a result of dynamical
pricing, whilst for Aarhus and Aran DR event generator will be developed in order to simulate
explicit DR events depending on the typical demand and forecasted production of the renewable
sources. The example of implicit DR using time-of-use pricing is given in Figure , where price was
modified in order to reduce afternoon energy demand peak, but the average price has not been
modified. The effects that this change has on the load profile and on the imported power profiles
are given in Figure and Figure 50. The results for this case show that around 5% of energy
imported from the grid can be saved with the optimal use of PV energy dispatching and smart
utilization of the battery system. Savings are more significant with regards to the cost, with the
solution being reported as 20% cheaper in this case that the baseline output. Mainly due to the
savings in energy imported from the grid, the carbon footprint is also reduced, by around 13%.
Finally, apart from the simulation engine, optimization service has been deployed in order to
perform real time simulations with in the RESPOND platform. Namely, for each optimization within
the service demand and production forecasts are collected from the MySQL database and pricing
scheme if needed. In the end, results are again stored in MySQL database in order to be further
used for translation of the optimal profile to control actions suggested to the end user.
T4.4 ENERGY PRODUCTION AND DEMAND FORECASTING. M13-M36 TEK
M13-M18 period:
Production forecast
With the aim of improving ecological interest, share of the renewable energy sources (RES) in
the energy production is to be increased. Nonetheless, that growth influences the grid’s instability,
as a result of the dependency between the RES production and weather conditions. Therefore,
with the aim of providing stable energy system, it is necessary to plan the consumption in
advance, with respect to the availability of the RES production. Therefore, the main goal of this
sub-task developing the service which should provide forecast for the RES available on each pilot
site – 2 photo-voltaic (PV) forecasters for Aarhus and Aran pilot and Solar thermal collector (STC)
forecaster for the Madrid one.
Within the workflow five steps were localized – State of the Art research, data collecting,
development of the prototype model, final model development and service deployment and
integration.
During State-of-the-Art review process, numerous potentially suitable techniques for RESPOND
use case were selected. In order to provide as high performance as possible, it was decided to
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
68 | 155
use a data-driven models if possible. Unfortunately, for Aran Island pilot, it might be the case that
not enough data will be available, in which case physical model will be deployed.
The next phase was consisted out of collecting necessary data – weather and production in order
to train models. Weather data was collected from the WeatherBit web service, as data with one-
hour time resolution was available both for the historical and day-ahead forecast, which were
conditions set by optimizer. Production data for Aarhus was collected from the Evishine service,
whilst Madrid’s was from the RESPOND’s InfluxDB. When Aran Island is concerned, only data
from two houses were available at the time this report is written, which is why it might be the case
that physical model will be deployed.
During prototyping, five different data driven techniques were tested (support vector regression
(SVR), linear regression (LR), neural networks (NN), k nearest neighbours (kNN), random forests
(RF)) and results were presented within the previous progress report. The best performance for
the PV production was achieved using NNs, whilst for STC it was the case when using RF, which
is why these models were selected for further use during the final model development phase.
During the development phase, necessary weather inputs were defined. Namely, both for PV and
STC as input parameters relative humidity, wind speed, pressure, UV, wind direction,
temperature, cloud coverage and global horizontal irradiance were used, whilst direct horizontal
irradiance, direct normal irradiance and previous productions were used only in case of STC.
Precisely, for each timestamp in which the forecast was to be given, this set of input parameters
is to be provided during service running phase.
When Aarhus pilot production forecaster is considered, NN has been trained in Python with the
mean absolute error (MAE) of approximately 8.5%. Performance of this model is illustrated in
Figure 51, and it was concluded that the estimation adequately represents the real production.
Therefore, this model was integrated within the RESPOND platform and deployed on the server
using Open Whisk. Integration required developing the component which collects the most recent
weather forecast data for the required timestamps from MySQL database and stores the provided
output back in the database in order to be further used by optimizer.
When Madrid is considered, RF model has been trained in Python and performed with MAE ≈
6.6%. It was then integrated with in the RESPOND platform to communicate with MySQL for
collecting weather data and information about the previous production, and finally for output
storage.
Development of the Aran Island pilot’s forecaster is in progress. Currently, the first version of the
service is deployed and integrated within the platform. This model relies on the Aarhus one, as
for the same type of RES. However, in the following weeks, the physical and data-driven models
will be compared, so in the following month the final more prices model will be deployed
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
69 | 155
.
Demand forecast
Regarding the demand forecaster, data-driven predictive models have been chosen. After
analyzing the performance of different state-of-the-art algorithms, best results were obtained with
Support Vector Machine (SVM) and k-Nearest Neighbours (k-NN) algorithms. After further
analyzing both algorithms, the k-NN was selected as it got the most accurate predictions.
Depending on the data availability, performance of forecasters varies, and three different
categories can be identified. On the one hand, predictive models with a good accuracy which are
able to predict daily schedules and routines, with a mean average error (MAE) below 90kW (see
Figure 52). On the other hand, less accurate predictive models with errors of different magnitudes
with MAEs over 125kW. Last but not least, predictive models that have a bad accuracy (see
Figure 53) with MAEs over 250kWs. These former two type of models don’t adjust well to the
dweller’s routine at certain time intervals, as there is not enough data to learn from them. More
historical data is required to train and adjust the model, which is foreseen to be achieved during
the last six months of the T4.4.
Figure 52 shows a predictive model with good accuracy for predicting the electric consumption of
a dwelling in Madrid. It can be seen that red dots (predicted consumptions) are rather close to
blue dots (real consumption). As for Figure 53, it compares the predictions made by a predictive
model with a worse performance with the real consumption of another house in Madrid. It can be
concluded that these predictions are not as accurate as the ones shown in Figure 52.
FIGURE 51. AARHUS PV FORCASTER
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
70 | 155
FIGURE 52. REAL VS FORECASTED ENERGY CONSUMPTION OF A PREDICTIVE MODEL WITH A GOOD
PERFORMANCE
FIGURE 53. REAL VS FORECASTED ENERGY CONSUMPTION OF A PREDICTIVE MODEL WITH A BAD
PERFORMANCE
Figure 54 and Figure 55 show the residuals of a predictive model with enough data, and a
predictive model developed with scarce data respectively. It can be seen that the quality of the
former model is better than the latter, as most differences between observed and predicted values
are closer to 0.
FIGURE 54. RESIDUALS OF A PREDICTIVE MODEL WITH A GOOD PERFORMANCE.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
71 | 155
FIGURE 55. RESIDUALS OF A PREDICTIVE MODEL WITH A BAD PERFORMANCE.
The neighborhood consumption is also forecasted, leveraging the already developed predictive
models. As it can be seen on Figure 56, the developed predictive models have a good accuracy,
which is expected to be improved as more data is available.
FIGURE 56. FORECASTED VS ACTUAL ELECTRIC CONSUMPTION IN MADRID (NEIGHBOURHOOD LEVEL)
All these predictive models are periodically retrained in an automatic manner. As a matter of fact,
results are expected to be improved as more historical data is available.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
72 | 155
T4.5 DATA ANALYTICS AND OPTIMIZED CONTROL. M13-M36 TEK
This task started in M13 and ends in month 30. This task aims at integrating the outcomes of all
previous tasks of the WP in order to perform actual control actions and influence the load
according to cooperative DR strategies.
M13-M18 period:
Heuristics Optimization
As part of the work performed in the last six months, the holistic optimization approach shown in
Figure 57 has been undertaken. The holistic optimization module is in charge of generating the
adequate DR event for users, leveraging the energy demand and production forecasts (Task
T4.4.) and the optimal demand profile (Task 4.2) generated previously. Furthermore, the holistic
optimization module needs to calculate which is the best period of time to execute the
aforementioned demand side management actions, taking into consideration the previous
profiles.
FIGURE 57. HOLISTIC OPTIMIZATION APPROACH
User Preferences
Within Task 4.5, the user preferences have been collected in terms of the type of actions allowed
by each dweller (e.g. switching on or off), the appliances upon which these actions may be
performed (e.g. dishwasher or washing machines), the periods of time for these actions (e.g. from
19:00 onwards) and the type of notifications preferred by dwellers (e.g. informative, prescriptive
or none) among others. These preferences are used to develop a user profile for each dwelling,
which is leveraged by the User Adapter module to decide which DR events generated by the
Holistic Optimization module are the most suitable for each dwelling.
At the moment of writing this document, recommended actions are sent to users via mobile app
notifications. Then, users need to manually make those recommended actions. The T4.5 is
envisioned to be implemented in an incremental manner. Therefore, after analyzing how users
behave with these recommendations, recommendations with an action triggering option will be
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
73 | 155
sent to users. This way, users will be able to trigger specific actions as recommended by the
RESPOND platform. The final stage of this incremental approach would be the automatized
actions, where user lets the RESPOND platform decide which actions to perform. The last 6
months of this task are expected to enrich the user adapter module by receiving user feedback
on recommended actions, and therefore, for improving the overall performance of the DR event
recommendation system.
Building simulation model
Optimized control services on RESPOND platform is referred to the translation of results from the
optimization service into optimal control actions related to the building heating/cooling systems.
In particular, the developed service is based on a Reduced Order Model (ROM), which is a
simplified model of a building and its energy systems able to reproduce the effect of
heating/cooling control actions on indoor thermal comfort (mean indoor air temperature value).
The Building Reduced Order Model (ROM) is developed using the Modelica language. The
Modelica Standard library and IBPSA Project 1 Library (2018) have been used to develop the
elements of the model. During the last 6 months, further development has been performed to
reach a final version of the ROM.
The ROM is composed of the following four main components:
1) Internal Gains
2) Heating and Cooling
3) Building
4) Weather
FIGURE 58. ROM MODEL SCHEME
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
74 | 155
The methodology to develop the RESPOND service is composed by three main steps:
1. The Tool for the ROM parameters estimation which receives building data as input; 2. A .fmu file of the Modelica models described in the section above; 3. The ROMFit Python script for the model simulation and the automatic calibration.
A Tool has been created to estimate the parameters needed for the model. The information
needed by the Tool can be simply obtained during the tendering phase through data collection
and during on-site site surveys. In case of missing data, standardized packages and
associated parameter values have been provided to support good model parameters
estimation. Since the model considers the main physical dependencies among the variables,
the calibration phase is much simpler compared to a Whole Building Energy model. A
dedicated Python script (ROMFit) has been developed to simplify the parameter insertion and
increase the speed and accuracy of the calibration procedure using a FMU file (Functional
Mock-up Interface,2018) generated from JModelica.org (2018). By using ROMFit the model is
simulated and then, after the first simulation, it adjusts the uncertain parameters and simplifies
the model calibration and its verification using real data collected by the RESPOND platform.
The model is considered calibrated only if the model forecasting performances are within
verified statistical values from comparison with real measured data. The model will use the
inputs to generate several scenarios in terms of heating/cooling control actions (i.e shifting the
heating profile from 6 am to 8 am, instead of 7 am to 9 am) to reproduce the optimized thermal
energy profile for the next day, provided by the optimization service. In case the service is able
to find a proper scenario able to be complaint with both, the hard constrains defined by the
dwelling owner and the optimized thermal energy profile, a message, using the RESPOND
app, will be sent to the dwelling owner to perform (manually or automatically) the DR scenario
during the next day. In case the service is not able to find a successful solution, the DR
scenario will not be performed on the next day.
We are currently testing the ROM model accuracy. In case the ROM model accuracy will not
be sufficient to provide the optimal control actions for the heating/cooling system of the
dwelling, a contingency plan was developed.
A detail simulation model in IESVE simulation software has been developed for one dwelling
in Aran Island pilot. Most of the Aran Island dwellings, which has been retrofitted, have similar
characteristics (envelope, heating/cooling system, pv panels). The simulation model has been
calibrated using data collected from an SD card installed on the dwelling heat pump. The idea
is to generate a simplified version of that model and using it for Optimal control service in
RESPOND platform. The idea is also to extend the methodology to other dwelling with similar
characteristics in the Aran Island.
2.5.4.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
Overall, WP4 is proceeding well.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
75 | 155
Deviations from GA:
Due to the delay of the early deployment of the devices in pilot sites, data coming from these
devices are not as many as expected. This shortage of data may difficult the development of data-
based predictive as well as building simulation models. Furthermore, data from different pilot sites
started to be recorded in different instants. Therefore, we foresee a difference in the performance
of predictive models of each pilot site.
Furthermore, models used for production forecast might differ from the ones used in Energy
Warden project. Having production data from pilot sites available, data driven models outperform
the physical ones.
Corrective actions:
In case the building simulation models based on ROM approach will not reach the requested
accuracy, a parallel methodology based on development/calibration of detail simulation models
in IESVE software is under testing phase as well.
T4.1 SEMANTIC INFORMATION MODEL. M7-M18
Deviations from GA:
Although in the GA ontologies such as BOnSAI and IFC were suggested, after the related
ontology analysis, it was concluded that other ontologies such as SEAS Feature of Interest (for
representing qualities and their features of interest) and BOT (for representing building topological
information) were more adequate.
Corrective actions:
No corrective actions are needed.
T4.2 INTEGRATION OF DEMAND RESPONSE WITH SUPPLY/DEMAND SIDE MANAGEMENT. M7-M24
Deviations from GA:
There are no deviations from GA.
Environmental factors like CO2 emissions reduction have not (yet) been taken into consideration
in the criterion function. The primary focus on the development that has been done is the
monetary aspect (i.e. energy and cost savings, operational costs).
Corrective actions:
The criterion function can easily be modified to include elements that depict the environmental
impact, however if that segment were to be included, it should be carefully specified not to
represent a linearly scaled version of the already included monetary aspect.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
76 | 155
T4.3 OPTIMAL ENERGY DISPATCHING AT HOUSEHOLD AND NEIGHBOURHOOD LEVEL. M13-M24 IMP
Deviations from GA:
There are no deviations from GA.
In cases where the pilot site is represented with a homogeneous set of households and where
the concept of multiple interconnected Energy Hubs could enable interaction between
participating entities (e.g. buildings in a district) in order to deliver an optimised energy exchange
and cooperative energy dispatching but having in mind that energy exchange between users
cannot be performed, modelling such a system (from a neighbourhood point of view) can be
considered redundant and should be avoided to increase performance.
Corrective actions:
Multiple interconnected Energy Hubs can be implemented in a simulated scenario as a research
effort to test the possibilities of peer-to-peer trading and similar concepts.
T4.4 ENERGY PRODUCTION AND DEMAND FORECASTING. M13-M36 TEK
Deviations from GA:
There are no deviations from GA.
Models used for production forecast differs from one used in Energy Warden project due to the
fact that having available data on production form pilot sites, data driven models outperform the
physical ones.
Corrective actions:
No corrective actions.
T4.5 DATA ANALYTICS AND OPTIMIZED CONTROL. M13-M36 TEK
Deviations from GA:
The delay of the early deployment of the devices in pilot sites derives in a shortage of data, which
may in turn hinder the process of developing building simulation models.
Corrective actions:
No corrective actions are needed.
2.5.4.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
77 | 155
FIGURE 59: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP4 DURING THE 2ND YEAR
2.5.5 WP5: SYSTEM INTEGRATION AND INTEROPERABILITY
WP5 which lasts from M7 to M24 comprises 5 tasks related to system integration and
interoperability.
• T5.1 Home automation interoperability interfaces. M7-M18
• T5.2 Smart grid connectivity. M7-M24
• T5.3 RESPOND middleware development. M7-M24
• T5.4 Integration with desktop dashboard and smart mobile client. M19-M24
• T5.5 Data protection and security measures M19-M24
Although only first three tasks have officially started before M18 reporting period, initial work has
also been performed in tasks T5.4 and T5.5, to ensure continuity of other related tasks and work
packages.
In particular T5.4 started to ensure that development of mobile app can be advanced, and ready
for the first review meeting. Besides, T5.5 related to data protection and security was considered
from the beginning of development of all system component. In the sequel, we outline the work
performed in tasks T5.1, T5.2, T5.3 and T5.4.
FIGURE 1 - WP5: SYSTEM INTEGRATION AND INTEROPERABILITY GANTT CHART
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
78 | 155
T5.1, T5.2, T5.3, T5.4 and T5.5 has been carried out during the reporting period.
2.5.5.1 DESCRIPTION OF TASKS
T5.1 HOME AUTOMATION INTEROPERABILITY INTERFACES. M7-M18
T5.1 has been carried out from M13 to M18 of the project according to the schedule. The goal of
this task was to deal with interoperability of RESPOND platform towards home automation and
building management systems, metering equipment (both energy and comfort), and energy
resources. In particular, it aimed to support integration of RESPOND platform with external
hardware and software systems, thus enabling not only acquisition of data, but also providing a
way to issue the control actions to be performed under the cooperative demand strategy. To
achieve this overarching goal, the concept of energy gateway will be deployed in the pilots. The
gateway comprises open software platform OGEMA as well as custom developed modules aimed
at integrating different RESPOND components and external systems: Develco custom firmware,
Energomonitor custom adapter, water consumption parsing service, and interface towards
external systems.
T5.2 SMART AND CONNECTIVITY. M7-M24 IMP
The goal of T5.2 is to support the connectivity of the RESPOND platform through an open
Application Programming Interface (API), enabling exploitation of data provided by smart grid and
third-party services (such as provision of energy prices, weather data, etc.). The current state of
the art has been revisited. In M18, the open API model was in the process of design and
implementation. It will act as a single endpoint for programmatic access to features such as DR
optimisation algorithms, forecasted energy consumption, performance evaluation, global ranking,
etc. and allow reuse of core RESPOND components by interested parties.
The component which integrates with weather API has been realized in CakePHP framework. It
has been configured to fetch the current weather data and weather forecasts from Weatherbit.io
service daily and hourly.
Weatherbit.io service provides http API at the following address:
https://api.weatherbit.io/v2.0/current?city=Raleigh,NC&key=API_KEY
which returns the data in JSON format:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
79 | 155
FIGURE 60: WEATHERBIT.IO JSON FORMAT EXAMPLE
The data are stored in a MySQL database and made available to other components of RESPOND
system.
T5.3 RESPOND MIDDLEWARE DEVELOPMENT. M7-M24 IMP
The goal of this task is to develop a middleware which aims to integrate the core RESPOND
services, system components, deployed field level devices, external services, web dashboard
and mobile application. It will enable plug-and-play connectivity of deployed sensing and actuating
equipment with the rest of the RESPOND system in order to ensure collection, storage and
processing of data obtained by sensing devices, analytic services and external systems. The
RESPOND middleware is based on an open source publicly available software which is
commonly used in other similar systems:
• TICK stack – stack of different standalone software components which enable data
collection, processing and storage in an efficient and scalable manner.
• MQTT broker – supports lightweight MQTT protocol suitable for Internet of Things
applications with publish/subscribe messaging pattern.
The part of the middleware corresponding to data collection has already been deployed and the
data from pilot sites have been collected since Month 11 of the project, as shown in Figure 2. In
M18, deployment and integration of core RESPOND services as well as visualisation layer is
being performed.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
80 | 155
FIGURE 2: RESPOND PLATFORM CHRONOGRAFT INTERFACE
T5.4 INTEGRATION WITH DESKTOP DASHBOARD AND SMART MOBILE CLIENT. M7-M24 DEXMA
As a summary, most of the activities under the Task 5.4 have been carried out according to the
project plan (GA Annex I). These activities can be classified in 2 categories depending on the
target platform they were dedicated. The two categories are: a) DEXCell dashboard, b) Mobile
platform.
DEXCell dashboard activities
EMS dashboard integration with RESPOND MQTT broker:
In this task the DEXMA’s development team has implemented a self-made solution in order to
retrieve the data sent from the pilot sites and insert into DEXCell data base. This was required in
order to work under the project Canonical Data Model. The solution was divided in 2 parts, the
bridge that connects the broker with DEXCell and the DEXCell device definition, according to the
new data origin.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
81 | 155
FIGURE 61: EMS DASHBOARD INTEGRATION
Dwellings configuration plan
As the current project includes a huge number of Dwellings and it is expected to be able to classify
devices in room level a planning and design for the pilot structure has been done. Then helped
by the partners in charge of pilots, the updated list of devices is assigned to each location and
room.
Residential demand response analytic app definition:
The first draft of how the demand response events generated in the Analytic Services and
executed by the End User through the Mobile app should be displayed in the DEXCell dashboard
have been carried out.
KPI definition:
Support was given to the definition of KPI’s that will be used to allow the project partners and the
final users to get an outcome of the project and the product. Some example of these KPI’s are
presented in the list below:
• Consumption per square meter
• Consumption per cubic meter
• Consumption per inhabitant
• Consumption per square meter and inhabitant
• RES energy generated
• Energy generation/consumption balance
• Energy cost per year and inhabitants
• Energy cost per year and square meter
• Energy cost per year
• Electricity energy consumption
• Thermal energy consumption
Mobile platform activities
Infrastructure preparation:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
82 | 155
In order to prepare a smooth integration between. The two platforms several subtasks have been
carried out. Main ones were related to configuration: account settings, permissions, etc
Also, some technical changes were required in the DEXCell’s API in order to share the data
gathered from devices subscribed in the project’s MQTT broker.
Integration support:
DEXCell already has different solutions in order to interact with other apps. To prepare the
integration with the mobile app support has been done to TEKNIKER, the partner in charge of the
app. Both companies have worked hand to hand to design the best approach for the users’ needs.
T5.5 DATA PROTECTION AND SECURITY MEASURES. M19-M24 IMP
The goal of this task was to undertake proper security measures in order to deal with possible
communication threats that RESPOND system may encounter in relation to data collection,
transmission and storage. In order to ensure this, a complete end-to-end data protection
measures have been designed and implemented. In particular, RESPOND has implemented
encryption of communication links and internal data storage as well as implementation of client
authorization. Whenever possible, standard encryption and data protection mechanisms for ICT
systems have been employed. In addition, RESPOND has deployed authorization mechanisms
where user will be given specific access rights depending on user role, whether it be building
inhabitant, building manager or energy provider personnel.
2.5.5.2 SIGNIFICANT RESULTS
T5.1 HOME AUTOMATION INTEROPERABILITY INTERFACES. M7-M18
In the context of the RESPOND project, the project partners have designed the architecture of
the system so that interoperability is supported from the beginning. Besides, the goal of the
RESPOND project is to complement and enhance the existing smart home and building
management systems, with the aim to improve the energy efficiency and optimize the costs by
seamless integration of cooperative DR programs.
In Figure 1, we present the interfaces among different components of RESPOND platform. As
can be seen, field level devices (Develco and Energomonitor), Energy gateway OGEMA, and
water consumption custom adapter use MQTT protocol for monitoring data and control action
transfer from/to RESPOND platform. On the other hand, external systems (weather and energy
pricing services), Energy manager dashboard (Dexcell), and Smart mobile application use
standard HTTP protocol for integration with RESPOND.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
83 | 155
FIGURE 1: RESPOND PLATFORM CONECTIONS
D5.1 was completed and submitted on time successfully.
T5.2 SMART AND CONNECTIVITY. M7-M24
Information regarding energy pricing is crucial in energy management systems and it allows
optimal scheduling of energy consumers by also considering the forecasted energy prices. Based
on this requirement of the RESPOND project, a custom API module has been developed, which
allows the energy providers for all pilot sites to input the current and future energy prices. This
information is stored once a day in a RESPOND platform’s central database, and it is made
available to other platform and external services via secure API.
An example of the request body used to save the energy pricing is given as follows:
0
MQTTbroker
DevelcoGateway
EnergomonitorGateway
MQTT client
MQTT client
Telegraf
InfluxDB
TICK
Kapacitor
Chronograf
MQTT client
0
Analytic services
MQTT client
Production Forecast Demand Forecast
Local Optimization Global Optimization
Building Simulation Optimized Control
Predictive Maintenance
SemanticRepository
AnalyticRepositiory
Energy GatewayOGEMA
Adapter (API)
External Systems (Aggregators,
Weather)
Energomonitor cloud
EnergomonitorBridge service
EMSDesktop Dashboard
Smart Mobile App
EMS Platform (DEXCell EM)
Water consumption custom adapter
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
84 | 155
T5.3 RESPOND MIDDLEWARE DEVELOPMENT. M7-M24 IMP
The goal of this task was to develop a middleware which aims to integrate the core RESPOND
services, system components, deployed field level devices, external services, web dashboard
and mobile application, as it is shown in Figure below:
FIGURE 62 RESPOND PLATFORM ARCHITECTURE
It will enable plug-and-play connectivity of deployed sensing and actuating equipment with the
rest of the RESPOND system in order to ensure collection, storage and processing of data
obtained by sensing devices, analytic services and external systems.
The part of the middleware corresponding to data collection has already been deployed and the
data from pilot sites have been collected since Month 11 of the project. In addition, deployment
and integration of core RESPOND services has been performed by using Apache OpenWhisk
(see Figure below):
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
85 | 155
FIGURE 63 APACHE OPENWHISK HIGH LEVEL ARCHITECTURE (SOURCE: CLOUD.IBM.COM)
T5.4 INTEGRATION WITH DESKTOP DASHBOARD AND SMART MOBILE CLIENT. M7-M24 DEXMA
During the period M19-M24, the following tasks have been carried out according to the plan: Task
5.4 Integration with desktop dashboard and smart mobile client (DEXMA).
During the period M13-18 the preparation and plan for the different activities was carried out. The
requirements for the desktop dashboard and the smart mobile client were defined. During the
period M19-24 these activities were done separately for the two partners: Dexma and Tekniker.
Dexma in charge of desktop dashboard integration and Tekniker of smart mobile client.
The following figure presents the place of each module in the RESPOND platform. It can be
observed that desktop dashboard and smart mobile client are two separated modules, that target
different end users. However, there is shared information between the two modules.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
86 | 155
FIGURE 64: RESPOND PLATFORM MODULES DIAGRAM
The activities carried out during M19-24 period are explained separated between the two modules
here below.
Desktop dashboard integration
In the RESPOND platform (based on DEXCell EMS), the desktop dashboard has two specific
objectives: i) analyse the project results, and ii) allow energy managers to monitor the building
properly so they can help the residents.
According to these two objectives, several functionalities were defined from the DoW (Description
of Work) in the GA (Grant Agreement) and story mapping sessions to understand which would
be the expected user experience. The following activities were carried out according to the
planned tasks on these planning processes. Note that the following mentioned features are
extensively explained in D4.5.
EMS dashboard configuration
The present activity objective was to prepare the RESPOND monitoring platform, which is based
on DEXCell EMS, to be used for the dashboard desktop specific objectives. This includes:
• Device status validation
• Location configuration
• Metadata configuration
• Features configuration
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
87 | 155
This monitoring platform configuration has been possible thanks to the previous development of
tasks in WP1, 2 and 4, that connected DEXCell to the RESPOND platform.
Each of the previous bullets have been done for each of the pilots’ buildings and dwellings and in
collaboration with the pilot coordinators. The following figure shows the current hierarchical tree
of pilot sites:
FIGURE 65: HIERARCHICAL TREE OF PILOT SITES IN DEXCELL
The different features configured for the platform are further explained in D5.4, however here
below are listed and briefly explained:
• Consumption analysis Feature that displays the energy consumption for electrical, gas and thermal. It can also
display water consumption. Different time windows can be displayed and with different time
scales.
• Cost analysis The energy cost can be configured by means of energy supply contracts that are related
to specific devices. From it an accurate economic project analysis can be done.
• Comparison Specific periods for consumption device can be compared in the same chart to compare
specific behaviours or anomalies.
• Comfort Temperature and humidity parameters are displayed in different time windows and with
different time scales.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
88 | 155
• Carbon emissions It allows to track the CO2 footprint for a specific device. The CO2 emission calculation can
be customized depending on the energy source.
• Map rankings Depending on different ratios (previously configured according to the project KPIs) the
project dwellings can be ranked either by pilot site or per building.
• DR event tracking Brand new feature developed for the purpose of tracking the DR events sent through the
RESPOND platform. The DR event will be displayed on a consumption chart, which will
allow to later analyse the impact of the events in the consumption curves.
DR Event tracking functionality definition
According to the module specific objectives and the task’s DoW, it was required to display the DR
event in the platform. The development of this feature has been carried out in task T4.5, however
it was on this task where it was defined. Some meetings and story mapping sessions were done
internally in Dexma, followed by meetings with the rest of consortium partners (under T5.2
activities), ended with the definition of this feature.
Support to pilot coordinators
In order to let the pilot coordinators, use the platform with all its potential individual demos and
tutorials were done. The pilot coordinators where instructed by Dexma support team in how to
analyse the different dwellings and to keep a proactive attitude in the platform maintenance. This
way pilot coordinators can ensure residents are engaged and can give them full support.
Platform KPI preparation
While configuring the platform some meetings were held with some of the technical partners in
order to validate which of the project’s KPIs could be analysed using DEXCell EMS. This was
done under task 6.1 is led by NUIG.
The following table was done by Dexma to explain which of the KPIs are already displayable in
DEXCell, which steps are required to configure them and also which KPIs were not possible or
require further development.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
89 | 155
TABLE 6: DEXCELL KPIS
Type KPI DEXCell Comments
Energy Renewable total energy
consumption Possible
You can visualize this kind of data as a ratio or
create a virtual device to get the % output
Energy Savings
Possible with
developments
If a DP can be send with 1 or -1 values to indicate
when the event takes place, this can be
performed in DEXMA
CO2 Reduction of greenhouse gas
emissions Possible Carbon Emissions App
Demand Peak load reduction Possible Virtual devices App and Advanced Analytics
Rescheduled Demand
Possible with
developments
If a DP can be send with 1 or -1 values to indicate
when the event takes place, this can be
performed in DEXMA
Analytical services accuracy Possible Virtual devices
Economic
Capex – Capital Expenditures Possible
If you want this as a Datapoint, it can be imported
as a turnover (cost parameter)
Economic savings during the
DR Event Possible
If the 2 costs inputs are DPs, this can be achieved
through Virtual Devices App
Economic operational cost
savings - OPEX Difference Possible
If the 2 costs inputs are DPs, this can be achieved
through Virtual Devices App
Security
Data security control
Possible with
developments Specific data point should be created
System
operation
Coefficient of performance –
COP Possible
If the 2 time inputs are DPs, this can be achieved
through Virtual Devices App
Communication performance Possible
If the 2 inputs are DPs, this can be achieved
through Virtual Devices App
User
DR campaigns penetration Possible
If the 2 inputs are DPs, this can be achieved
through Virtual Devices App
Number of user manual
actions Possible
If the 2 inputs are DPs, this can be achieved
through Virtual Devices App
Comfort
Indoor Air Quality - IAQ
Possible with
developments
Not possible unless we add conditions in Virtual
Devices App
Thermal comfort
Possible with
developments Specific data point should be created
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
90 | 155
Deliverable preparation
Deliverable D5.4 - Desktop dashboard and smart mobile client was prepared in collaboration
with Tekniker and presented according to the plan presented on the project plan.
Smart mobile client
In the RESPOND platform, the personal energy performance assistant service is based on a
smart mobile client. This mobile app is aimed at engaging users and involving them in Demand
Response programs, therefore, it is multiplatform (both for Android and iOS) and multilingual (in
English, Spanish and Danish). Thanks to the mobile app, the user not only visualizes energy-
related consumption and generation, but also receives optimal DR strategies proposed by the
optimizer and acts over different devices and appliances.
The following activities were carried out according to the planned tasks on these planning
processes. Note that the following mentioned features are extensively explained in D3.4 and D5.4.
Implementation of security mechanisms
In order to ensure the identification, authentication and authorization within the RESPOND mobile
app, an LDAP hierarchical directory service has been implemented. Namely, an OpenLDAP
server version 1.2.5 has been implemented to manage the access control, that is, to manage
what type of access (e.g. read or write) should each user have with regards to the available
resources. In order to easily configure such access control list, a phpLDAPadmin Server version
0.0.8 has also been deployed, which provides an intuitive graphic interface. Figure 66 shows a
snippet of the RESPOND mobile app’s hierarchical directory service.
FIGURE 66: LDAP SERVER FOR RESPOND MOBILE APP'S ACCESS CONTROL.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
91 | 155
Implementation of notification services
The communication of optimal DR events and other notification messages to users is foreseen to
be made via the RESPOND mobile app. That is, each user will receive (according to the set of
preferences that he/she has defined) notifications in the RESPOND mobile app which may refer,
for example, to of potential energy-saving opportunities. Towards that goal, a notification service
based on Google Firebase Cloud Messaging (FCM) has been implemented. FCM is a cross-
platform solution for delivering messages. In the case of the RESPOND mobile app, these
messages are sent in the form of push notifications. Figure 67 shows the sequence diagram of
module interactions to send a notification to the user.
FIGURE 67: NOTIFICATION FLOW
Users receive the system notifications via “Push” messages received in their smartphones.
Received messages could be also viewed in the RESPOND app’s notification list in case the user
finds it necessary or if they arrived at a time that was not convenient for the user to read it.
User engagement
Task 3.3 “Detailing the user context and improvements of user interaction” deals with the best
way to engage to the users with Demand Response actions. The personal energy performance
assistant is the main tool towards this engagement and its design has been modified to adopt the
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
92 | 155
recommendations concluded in this task. These recommendations address the information
shown to the user, as well as the appearance and understandability of the app.
Development of a proxy server
The proxy server is the intermediary that deals with the calls to different services, thus alleviating
the heavy load that would otherwise be in the mobile app. For example, when a user wants to
visualize the energy consumption of a given appliance, the proxy server is the component that
handles the message exchange between the LDAP directory (to gran user’s authentication), the
Virtuoso semantic repository (to get the appliance’s information) and the InfluxDB time series
database (to retrieve the appliance’s energy consumption). Figure 68 depicts the role of the proxy
server.
FIGURE 68: RESPOND MOBILE APP'S PROXY SERVER.
Mobile app publication in marketplaces
Once the RESPOND mobile app has been developed, it needs to be published so that project
participants can download and install it in their smartphones. Since the app has been developed
both for Android and iOS, it needs to be published in both marketplaces. The publication of the
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
93 | 155
app is an ongoing work. The Android version is already published in the Alfa channels, which is
the previous stage to the publication in Google Play, and the version for iOS is published in
Apple’s Testflight environment, which is the previous step to be published in the App Store (see
Figure 69). The process of publishing a mobile app in each platform differs, and different
requirements needs to be addressed prior to their acceptance.
FIGURE 69: RESPOND MOBILE APP'S PUBLICATION IN APP STORE.
T5.5 DATA PROTECTION AND SECURITY MEASURES. M19-M24 IMP
Security in RESPOND platform is not implemented via particular software component. Instead, it
is implemented with a set of tools and mechanisms already provided by different components that
are part of RESPOND architecture. The components of RESPOND system are deployed in a
private cloud environment, which have many advantages, especially in terms of security. The
communication between different parts of RESPOND platform can be rigorously controlled to
prevent any misuse. Besides, the access point that consortium software developers need for
implementation of RESPOND analytic service (e.g. Secure Shell - SSH) can be completely
separated from the one necessary for public use by external software developers (Open API) or
end-users (mobile application and web dashboard).
In order to be able to identify different security measures to be applied, it is necessary to identify
different stakeholders which provide or consume collected data in RESPOND platform, as it is
shown in Table 7 below:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
94 | 155
TABLE 7: RESPOND STAKEHOLDERS
Stakeholder Notes
Household tenants Household tenants allow installation of home automation
devices in their household. They use services developed by
RESPOND project consortium partners via custom developed
mobile app.
Energy/building managers Energy/building managers access the collected and analysed
data via Dexcell dashboard.
Third-party service providers Provide information necessary for correct functioning of
RESPOND analytics services, such as energy prices, weather
observations and forecast.
Smart grid operators RESPOND platform is connected to smart grid operators that
can exchange information and can send DR signals to
RESPOND platform.
Consortium software
developers
Develop RESPOND analytic services and provide application
program interface (API) to allow other interested stakeholders
to use part or whole RESPOND system.
External Software developers External software developers can use RESPOND analytic
services based on the credentials (e.g. API key) provided by
RESPOND project.
2.5.5.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
T5.1 HOME AUTOMATION INTEROPERABILITY INTERFACES. M7-M18
Deviations from GA:
N/A
Corrective actions:
N/A
T5.2 SMART AND CONNECTIVITY. M7-M24
Deviations from GA:
Currently, in the consortium there exists no connection to DR aggregators.
Corrective actions:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
95 | 155
A custom developed component will be developed as a replacement to DR aggregators. This
component will generate DR signals which will be used as an input for other RESPOND system
components, as shown in Figure below:
FIGURE 70 DR EVENT DATA FLOW
T5.3 RESPOND MIDDLEWARE DEVELOPMENT. M7-M24
Deviations from GA:
N/A
Corrective actions:
N/A
T5.4 INTEGRATION WITH DESKTOP DASHBOARD AND SMART MOBILE CLIENT. M7-M24 DEXMA
Deviations from GA:
N/A
Corrective actions:
N/A
T5.5 DATA PROTECTION AND SECURITY MEASURES. M19-M24 IMP
Deviations from GA:
N/A
Corrective actions:
N/A
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
96 | 155
2.5.5.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
FIGURE 71: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP5 DURING THE 2ND YEAR
2.5.6 WP6: VALIDATION AND REPLICATION OF PROJECT RESULTS
WP6 runs from M13 to M36. This work package develops a specific validation methodology for
RESPOND demonstration results. It is closely related to outcomes from pilot characterization
(WP1) and use case deployment (WP2). To achieve this, verification and validation of the
RESPOND solution at three pilot sites will be conducted by monitoring the performance of
installed and integrated ICT solution for a minimum of 12 months and compared the outcomes
with the baseline period of the previous 12 months.
The main objectives are:
• Development of specific validation methodology and definition of acceptance criteria.
• Verification and validation analysis of obtained results at the project pilot sites.
• Feedback extraction of the user engagement for evaluation non economical aspects.
• Development of replication plan ensuring maximal scalability of project results.
• Reporting on lessons learnt and recommendations for similar activities.
• Demonstration of effective operation scenarios through validation results.
FIGURE 2 - WP6: VALIDATION AND REPLICATION OF PROJECT RESULTS GANTT CHART
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
97 | 155
2.5.6.1 DESCRIPTION OF TASKS
T6.1 VALIDATION METHODOLOGY AND ACCEPTANCE CRITERIA. M13-M18 NUIG
T6.1 started in M13 and it ends in M24. The aim of this task is to define RESPOND validation
methodology able to provide an assessment of project results and related use cases from the
perspective of energy/cost saving, carbon emission reduction and economic sustainability.
The main activities carried on during the first six months of the task can be summarized as follows:
• Literature review to complete the list of relevant KPIs provided as output of WP1; • Update of measurement points and information available for each pilot site to reach the
user requirements defined in Task3.1 and assure the user acceptance considering system performance, indoor thermal comfort, functionality, usability, security and safety;
• Analysis for a further definition of DR scenarios to be applied to the pilot test cases, taking into account available measurement points, control actions and information;
• Literature review related to IPMVP protocol for performance measurement and verification, EU initiatives for energy savings measurements.
• Definition of table of content for D6.1
T6.2 VALIDATION ANALYSIS AND REPORTING. M16-34 NUIG
T6.2 started in M16 and it ends in M34. The aim of the task is to collect and analyse all the data
produced in the pilot tasks and by operation scenarios. Validation analysis will be carried out by
monitoring the performance for installed and integrated RESPOND solution for baseline and
reporting period.
T6.3 QUALITATIVE EVALUATION OF USER EXPERIENCES AND RECOMMENDATIONS. M16-34 AAU
This task runs from M21 to M34. The aim of the task is to report on the overall user engagement
and satisfaction during the RESPOND demonstration activities at pilot sites and in interaction with
system itself. In the last month of the trial, it is planned to carry out two focus groups at each site
with pilot households, which should provide the basis for a detailed qualitative analysis of user
experiences and the users’ own recommendations for possible further improvements. In addition,
a survey targeted all pilot households is carried out to measure general user attitudes and
experiences in relation to the pilot. On basis of the focus group and survey outcomes, this task
uncovers the impact of social competition among end consumers as part of district and residential
communities. The task will also report on best practices and recommendations on how to further
motivate and engage end users to participate in DR activities, the role of social norm compliance
in end user engagement, and document project findings and statistical results regarding the user
engagement.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
98 | 155
T6.4 REPLICATION AND DEVELOPMENT. M23-M34 FEN
T6.4 begins in M23 and ends in M34. The goal of this task is to clearly identify and analyse all
possible RESPOND opportunities for replicating of its products and services.
In this regard, the tasks that have been started are:
• Market analysis in order to exploit the real needs for DR services
• Analysis of involved stakeholders
The following tasks will be performed during the third year of the project:
• Alternative business models for energy services taking into account main RESPOND
functionalities
• Incentives and identification of potential non-technical barriers and risks for new business
and service models
2.5.6.2 SIGNIFICANT RESULTS
During the last six months (M19-M24) the main activities of WP4 have been:
T6.1 VALIDATION METHODOLOGY AND ACCEPTANCE CRITERIA. M13-M18 NUIG
The aim of this task is to define RESPOND validation methodology able to provide an assessment
of project results and related use cases from the perspective of energy/cost saving, carbon
emission reduction and economic sustainability.
To do so, the following sub-tasks has been performed:
• Review of the state of art of Measurement & Verification (M&V) methodologies, focused
Demand Response (DR) application;
• Review of current Key Performance Indicator (KPI) already validated in other ongoing EU
DR projects;
• Final selection and definition of KPIs;
• Development of a specific M&V methodology, using RESPOND services from data
collection to baseline definition;
• Definition of specific DR use cases per pilots in terms of RESPOND validation
methodology: data monitoring, RESPOND services involved, KPIs calculus;
• Definition of a recovery plan for RESPOND solution testing and application, due to missing
data for late deployment of monitoring equipment on pilot site;
• The D6.1 due to M24, but it is still under finalization due to baseline checking and recovery
plan definition;
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
99 | 155
T6.2 VALIDATION ANALYSIS AND REPORTING. M23-34 NUIG
Due to delay on T6.1 for baseline checking and recovery plan definition, the task is still on the
phase of optimization of the data flow inside the RESPOND platform for validation purpose, in
order to collect and analyse all the data in best way.
T6.3 QUALITATIVE EVALUATION OF USER EXPERIENCES AND RECOMMENDATIONS. M21-34 AAU
The task commenced a few months before the time of reporting, and activities have so far been
limited. This is due to that the detailed planning of the task should be based on first experiences
from the pilot demonstrations that begin around the time of reporting. However, within the coming
2-3 months, detailed plans and guidelines for carrying out the focus groups will be prepared, and
the questionnaire will be set up.
As part of this, it might be considered if it would be relevant and more informative to combine the
focus groups with qualitative interviews of individual households – perhaps by combining one
focus group at each site (instead of two) with a few qualitative in-depth interviews. The benefit of
doing qualitative interviews could be to get a deeper insight into how the individual
residents/households experience the RESPOND demand response solutions on a day-to-day
level and how it affects their energy consumption practices.
T6.4 REPLICATION AND DEVELOPMENT. M23-34 FEN
At this stage of the project there are not substantial results yet. In a later stage, during the third
year of the project, when RESPOND solution will be completed defined, the replication plan will:
• capture all pertinent project knowledge that supports the adoption and utilisation of
RESPOND solution by non-consortium members
• ensure maximum possible scalability of project results.
• include the methodology, approach, analysis and benchmarking of DR solution, parts of
the software development, interoperability design, and all practical and technical
information for design, engineering, installing and commissioning RESPOND compliant
solutions learned from the pilot activities.
The design and development of sustainable and coherent business models is mandatory in order to guarantee the address of the effective exploitation of the delivered results. The following tasks will be performed:
• Risk management methods and mitigation in delivering a RESPOND solution to buildings and households will be analysed.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
100 | 155
• Guidelines will be defined to assure the dissemination of the replication plan to all relevant private and public organizations identified over the course of the project.
2.5.6.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
T6.1 VALIDATION METHODOLOGY AND ACCEPTANCE CRITERIA. M13-M18 NUIG
Deviations from GA:
The T6.1 supposed to finish in M24, the task continued due to late deployment of measurement
and control devices in pilot sites. The delay produced the need of additional time for baseline
checking and recovery plan definition.
Corrective actions:
A recovery plan will be included in D6.1, taking into account RESPOND solution testing period
and application.
T6.2 VALIDATION ANALYSIS AND REPORTING. M16-34 NUIG
Deviations from GA:
The T6.1 supposed to finish in M24, the task continued due to late deployment of measurement
and control devices in pilot sites. The delay produced the need of additional time for baseline
checking and recovery plan definition.
Corrective actions:
A recovery plan will be included in D6.1, taking into account RESPOND solution testing period
and application.
T6.3 QUALITATIVE EVALUATION OF USER EXPERIENCES AND RECOMMENDATIONS. M16-34 AAU
Deviations from GA:
N/A
Corrective actions:
N/A
T6.4 REPLICATION AND DEVELOPMENT. M16-34 FEN
Deviations from GA:
N/A
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
101 | 155
Corrective actions:
N/A
2.5.6.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
FIGURE 72: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP6 DURING THE 2ND YEAR
2.5.7 WP7: DISSEMINATION AND EXPLOITATION ACTIVITIES
During the period M13-M24, the following tasks have been carried out according to the schedule:
• Task 7.1 Dissemination and communication strategy (DEXMA)
• Task 7.2 Products, services and supporting business model definition (FEN)
• Task 7.3 Data life cycle management (FEN)
• Task 7.6 Contributions to EASME dissemination activities (FEN)
FIGURE 3 - WP7: DISSEMINATION AND EXPLOITATION ACTIVITIES GANTT CHART
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
102 | 155
2.5.7.1 DESCRIPTION OF TASKS
T7.1 DISSEMINATION AND COMMUNICATION STRATEGY. M1-M36 DEXMA
As a summary, dissemination about Respond Project has been carried out according to the plan
defined on deliverable 7.1 (submitted in M6) using also the project website (defined on deliverable
7.2).
a. Targets of dissemination
The different stakeholder groups have been identified, such as General public,
commercial/industrial stakeholders, scientific community, together with the conferences,
workshops and events. Besides the dissemination KPIs have been defined together with the
collaboration with other projects.
b. Project identity
b.1. RESPOND Blog
The following articles have been published in the second year of work:
• RESPOND in the News: Alboa Magazine spotlights the project • 4 differences between Demand Side Management & Demand Response • The role of DR in Smart Cities • Meet the Madrid Pilot Site • The key points of Respond Project in 2018 • Demand Response and Space Heating Practices in Homes • Semantic Technologies for Integrating Demand Response Data • RESPOND Events: RESPOND was at Sustainable Places 2019 • Project News: Devices deployed at the Aran pilot Site • Integrating Building and IoT data in Demand Response solutions • Optimising the energy demand of neighbourhoods under DR umbrella • RESPOND Events: We were at the ECEE Summer study 2019 • RESPOND Events: We were at ETSI IoT Week 2019
The updated 2019 publication list and publication plan can be observed on the following table.
TABLE 8: LIST OF PUBLICATIONS
Publication Date Forecast
Proposed Blog Posts Topics Responsible Partner
Suggested Partners Accepted Status Contact
Name
March Project Update: Project RESPOND Looks Back on 2018 DEXMA yes Published Andreu
April Demand response and heating practices in homes AAU (Aalborg University)
yes Published Henrik & Toke
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
103 | 155
May Semantic repository. Potential to enhance management of DR programs
TEKNIKER yes Published Iker
May Article written by TEKNIKER: LDAC TEKNIKER yes Published Iker
June RESPOND Events: Meet us at our Workshop in LDAC2019 DEXMA TEKNIKER yes Published
June RESPOND Events: RESPOND was at Sustainable Places 2019 DEXMA yes Published
June Project News: Devices deployed at the Aran Pilot Site ARAN yes Published Avril
July Integrating Building and IoT data in Demand Response solutions DEXMA yes Published Elodie
July Optimizing the energy demand of neighborhoods under DR umbrella PUPIN yes Published Marko
Jelić
August
ECEEE Summer Study 2019 - https://www.eceee.org/summerstudy/ And here’s the reference:Christensen, T. H., Larsen, S. P. A. K., & Knudsen, H. N. (2019).
AAU (Aalborg University)
yes Published Toke
August Measures of Demand Response in isolated countries (comparison in europe)
ENERGOMONITOR Never replied
September NEWSLETTER TEKNIKER - http://www.newtek-tech.es/newtek/boletin/28/proyecto4.php
TEKNIKER Yes Email Sent Francisco Javier Díez
September Utilities becoming more customer-centric FENIE yes
Sent reminders 26/09 + 21/10
Agustina
October ETSI IoT Week 2019.I will present the ontology-based approach we are using in RESPOND to integrate Building and Sensor Data.
TEKNIKER yes Iker
October Demand Flexibility TEKNIKER yes Iker
b.2. RESPOND in the Press
Within our aim to reach general and technical public, the project has also had some buzz on the
press. These press articles are included in the blog whenever possible:
• Energiwatch (Denmark) • Energysupply (Denmark) • Europapress (Spain) • El Economista (Spain) • Energias Renovables (Spain) • Teinteresa.es (Spain)
During this period an article and dissemination campaign was launched in Open Access
Government online magazine. The following table summarizes the campaign actions.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
104 | 155
TABLE 9: LIST OF ARTICLES
Open Access Government
June 2019
Stakeholder page + display banner
https://www.openaccessgovernment.org/category/stakeholders/energy-stakeholders/ . // . https://www.openaccessgovernment.org/respond-project-active-demand-management/67203/
- 2 pages article - 1 stakeholder page - 1 online banner => 3000€
Published
Open Access Government
October 2019
Article published in their online magazine
http://edition.pagesuite-professional.co.uk/html5/reader/production/default.aspx?pubname=&edid=0d5ad7a6-fb33-40ea-b275-9a1234b94ddb&pnum=362
Published
b.3. RESPOND Social Media
RESPOND Twitter
We have been working with official RESPOND project twitter account to spread the news about
the project and other news related to it.
RESPOND LinkedIn
Same as above, all materials related to the project have been shared on the official LinkedIn
group of the project.
RESPOND Facebook
We have also used Facebook as another channel to share the news about the project.
RESPOND Video
A 1-minute video that explains the project scope in a simple and direct way has been done in
English, Spanish and Danish. It will be done by the end of April to be used on social media,
events, etc.
b.4. RESPOND Materials
RESPOND Roll Up
A roll up that will be used in events has been done.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
105 | 155
FIGURE 4 - RESPOND ROLL UP
b.5. RESPOND Website
A website was built in the first period for RESPOND Project, to serve as the main platform for
dissemination and communication to interested stakeholder: http://project-respond.eu/.
FIGURE 73: RESPOND WEB PAGE
RESPOND Repository
A dedicated section for the deliverables has been included within RESPOND website. Thus, the
whole list of public reports and deliverables can be downloaded by everyone.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
106 | 155
FIGURE 74: RESPOND PUBLIC DELIVARABLES REPOSITORY
Also, further publications such as scientific articles, will be added to the website:
FIGURE 75: RESPOND PUBLICATIONS SECTION
RESPOND SEO
Search Engine Optimization has been reviewed for each page of RESPOND website.
• Meta descriptions • Meta Titles • Keywords • Internal links
This helps the website to get visibility on Google Search Engine for Demand Response focus
keyword, and thus appear in the first positions of the results page.
FIGURE 76: RESPONS ARTICLE EXAMPLE
b.6. Respond Events
The attendance to the following events has been arranged by DEXMA:
• Sustainable places 2019 -> 05/06/19.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
107 | 155
• EU Sustainable Energy Week + Article publication in the European Energy Innovation Magazine -> 18/06/19.
• Energy Utility week -> 12/11/19.
T7.2 PRODUCTS, SERVICES AND SUPPORTING BUSINESS MODEL DEFINITION. M13-M36 FEN
This task investigates innovative business models for the services that RESPOND can enable.
• The value system and the target market sectors involved in the potential business
opportunities for the outcomes of the project have been studied.
• Collaboration opportunities are being studied and will be exploited with a focus on scaling
to commercialization.
• A deep market analysis and a competitive analysis have been started to performed to get
a clear insight of market size, potential market growth rate, actors, as well as potential
competitors.
• The technical and non-technical barriers to enter the market and the regulatory restrictions
are being investigated.
• A SWOT analysis has been done, based on Canvas Business Model
T7.3 DATA LIFE CYCLE MANAGEMENT. M13-M36 FEN
This task will address a usual problem that recently has gained importance because the increased value of the data due to the new exploitation possibilities. In this project a several types of data are being monitored. This data includes data related to the participant’s behaviour and this type of data is very sensitive because their privacy considerations. This project is an integration project and therefore several companies are involved in the data life cycle. The technical solution for secured and anonymized data is defined in T5.5 but this solution has been complemented with a clear agreement of how all the data is managed in their life cycle starting at the time that is acquired and following by their management including sharing until the data must be destroyed. Considering that this is a European project, legislation of different countries has been taken in account and European directives in this area. An important input was the Big Data Value public private partnership (BDVA PPP). The task has followed the recommendations produced by the task force 5: Legal (Policy and Regulation) of this association for creating a framework that allow the adequate data treatment without invading the household habitant’s rights.
T7.6 CONTRIBUTION TO EASME DISSEMINATION ACTIVITIES. M1-M36 FEN
This task contributes, upon invitation by the EASME, to common information and dissemination activities to increase synergies between, and the visibility of H2020 supported actions. Moreover, this task envisions participation in the activities organized by EASME, such as training for coordinators, exchange meetings with other H2020 contractors, making presentations in high level conferences, and giving feedback on the impact of projects.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
108 | 155
2.5.7.2 SIGNIFICANT RESULTS
T7.1 DISSEMINATION AND COMMUNICATION STRATEGY. M1-M36 DEXMA
RESPOND Google Analytics (updated)
Comments M13-M18: Clear increase of the traffic at the beginning of March, thanks to the
optimisation of the Google Analytics parameters.
On 12th of March, Google released a new algorithm called Florida2 that affected a lot of websites
in terms of ranking, what explains the drop.
Bounce rate is a little high and could definitely improve through the new publications.
Session duration has a good average.
FIGURE 77: RESPOND WEB ANALYTICS EXAMPLE 1
FIGURE 78: RESPOND WEB ANALYTICS EXAMPLE 2
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
109 | 155
Comments M13-M18: we acquire most of our audience through Organic & Direct Search.
Funnels by order:
• Organic: our content appears on Search Navigators after a user looked for keywords such as: Demand Response, Residential Energy efficiency, etc.
• Direct: users search RESPOND on the Navigators. Also, a bit of Organic Search appears in that section.
• Social: posts published on FCBK + Twitter + LinkedIn. • Referral: websites that talk about RESPOND. • Other: Include repository, deliverables, referral campaigns
Spain is where most of our audience comes from followed by India and the UK.
FIGURE 79: RESPOND WEB ANALYTICS EXAMPLE 3
The page that receives more traffic talks about the difference between Demand Side Management
and Demand Response: http://project-respond.eu/4-differences-between-demand-side-
management-demand-response/ .
The top device used to visit the website is the desktop, with 550 users over the last 90 days
versus 98 users with mobile.
RESPOND Social Media Statistics M13-M19: Statistics about members, subscribers, visits, open rates, click trough rates have been tracked in Social Media activities (Facebook, Twitter, LinkedIn, Youtube) and in direct marketing (Mailing campaigns).
• Facebook (22 followers, 9 posts) • Twitter (78 followers, 24 publications, 2810 impressions per month, 320 visits) • Youtube (45 followers) • LinkedIn (21 members)
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
110 | 155
M19-M24: Statistics about members, subscribers, visits, open rates, click trough rates have been tracked in Social Media activities (Facebook, Twitter, LinkedIn, Youtube) and in direct marketing (Mailing campaigns).
• Facebook (30 followers, 41 posts) • Twitter (107 followers, 114 publications, 2810 impressions per month, 320 visits) • Youtube (45 followers) • LinkedIn (30 members)
T7.2 PRODUCTS, SERVICES AND SUPPORTING BUSINESS MODEL DEFINITION. M13-M36 FEN
After, the firsts tasks of T7.2 described in section Description of tasks, which result in a Minimum Valuable Product, the focus have moved on the development of innovative and adequate business models. This task aims at providing the basis for sustainability of the RESPOND results after the end of the project and future exploitation. Besides, it will optimize the impact of the project in the EU and beyond. Discussions of the strategies for further use of the RESPOND results with designated stakeholders will be conducted and particular attention will be paid in the identification of the main procurement channels in order to foster the market uptake.
T7.3 DATA LIFE CYCLE MANAGEMENT. M13-M36 FEN
The main activities from T7.3 have been focus on:
• Description of data types used during the project: sensitive and non-sensitive data. • Pilot countries data protection policies and legislation (Ireland, Denmark and Spain) before
and after the General Data Protection Regulation (GDPR) which entries into force on 25 May 2018.
• Analysis of common EU policies. • Definition of RESPOND GDPR approach. Objectives, pilots and participants. Treatment of
personal data (data life cycle management for each pilot, treatment activities registry, risk analysis, security measures), authorization model of personal data.
• Definition of ICT security measures. Backend infrastructure, desktop front-end, mobile-app.
• Analysis of other entities recommendations (Open Access, Research data).
The work carried out has been reflected in Deliverable 7.4 Data life cycle management policy (Preliminary) that was submitted in M18. It contains both, sensitive personal data protection (GDPR issues) in one hand, and the ITC protection measures in the other. Nevertheless, this second part will be fully addressed in the deliverable D5.5 Data protection and security which task starts according to the Gantt chart in M19 although, the ITC security measures have been already designed and implemented to start protecting the information since the very first day.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
111 | 155
T7.6 CONTRIBUTION TO EASME DISSEMINATION ACTIVITIES. M1-M36 FEN
The RESPOND project has attended to Sustainable Places, Aix-Le-Bains, France, in May 2018,
upon invitation by our Project Officer, Pierre Antoine, who had contacted us. At first, the project
was intended to participate in the event as a dissemination activity, with the representation of
NUIG partner, anyhow after the invitation by the EASME, FEN partner attended also, as
coordinator of the project.
2.5.7.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
T7.1 DISSEMINATION AND COMMUNICATION STRATEGY. M1-M36 DEXMA
Deviations from GA:
There have been no deviations from the GA.
Corrective actions:
Any corrective action has been required.
T7.2 PRODUCTS, SERVICES AND SUPPORTING BUSINESS MODEL DEFINITION. M13-M36 FEN
Deviations from GA:
There have been no deviations from the GA.
Corrective actions:
Any corrective action has been required.
T7.3 DATA LIFE CYCLE MANAGEMENT. M13-M36 FEN
Deviations from GA:
There have been no deviations from the GA.
Corrective actions:
Any corrective action has been required.
T7.6 CONTRIBUTION TO EASME DISSEMINATION ACTIVITIES. M1-M36 FEN
Deviations from GA:
There have been no deviations from the GA.
Corrective actions:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
112 | 155
Any corrective action has been required.
2.5.7.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
FIGURE 80: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP7 DURING THE 2ND YEAR
2.5.8 WP8: PROJECT MANAGEMENT
WP8 runs from M1 (October 2017) to M36 (September 2020). The overall objectives of WP8 are to guarantee the coordination and work between interacting partners that integrate the Consortium and also a fluid communication with the European Commission, with efficient administrative, financial and contractual management. Also, it ensures that the decision-making processes and quality assurance procedures specific to the RESPOND project are established and followed.
Tasks T8.1 Project administration & quality assurance and T8.2 Project management and EC
reporting started in M1 and run along the project duration.
D
FIGURE 5 - WP8: PROJECT MANAGEMENT GANTT CHART
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
113 | 155
During the second year (M13-M24) the main activities within T8.1 and T8.2 have been the
following.
2.5.8.1 DESCRIPTION OF TASK
T8.1 PROJECT ADMINISTRATION & QUALITY ASSURANCE. M1-M36 FEN
This task sets the basis for the project management. The aim is to facilitate and promote the use
of a performance-based management process in the RESPOND project, according to the Grant
Agreement [2] and its Annexes and the Consortium Agreement [3].
FEN, on behalf of Project Coordinator of RESPOND, kept under control all the procedures
stablished in D8.1. FEN worked in close cooperation with the individual WP leaders and rest of
partners. The consortium run regular meetings to monitor progress and coordinate the
development of specific WPs and associate Deliverables, call conferences and/or face-to-face
meetings.
T8.2 PROJECT MANAGEMENT AND EC REPORTING. M1-M36 FEN
This task also sets the basis for the project management. The specific objectives are: • Administrative, risk & financial management • Scientific & technology management
2.5.8.2 SIGNIFICANT RESULTS
T8.1 PROJECT ADMINISTRATION & QUALITY ASSURANCE. M1-M36
The actions and main results obtained in this task have been:
• Collection of significant information to create internal periodic reports for periods M13-M18 and M19-M24 with the purpose of monitoring and recording the progress in line of the Project with specified project milestones. Every six months, all partners provided contributions to the Project Coordinator, in order to report description of tasks executed, main results, deviations and corrections and fulfillment of efforts and costs Excel.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
114 | 155
These documents have been used to create the present deliverable D8.3. Management
report (second year). Also, the information contained in the internal reports are valuable
for the Official Reports that the consortium has to submit to the European Commission.
• Redaction of Official Periodic Report for the first three semesters of the project (M1-M6, M7-M12, M13-M18). The document contains follow up of partners accountability (costs and efforts) and also summaries of tasks carried out during the periods. It couldn’t be submitted to EC because the amendment process that had been opened was not concluded yet at the time of Official Reporting M19-M20 (April 2019-May 2019). The Project Officer informed that once the amendment was concluded the consortium would be able to report.
• Follow up of the tasks that have been carried out during the reporting period, M13-M24:
TABLE 2. TASKS LIST FOR SECOND YEAR (M13-M24 PERIOD)
WP Task Description Lead beneficiary
Status
WP1 T1.4 Demand response platform deployment TEK Finished
WP2 T2.2 Seamless integration of RESPOND technology tiers DEXMA Finished
T2.4 Early deployment at pilot sites ENE Finished
T2.5 Demand Response platform deployment IMP Finished
WP3 T3.1 Criteria and framework for participant recruitmement AAU Finished
T3.3 Detailling the user context and improvements of user interaction
AAU Finished
T3.4 Smart mobile client and personal Energy performance assistant design
TEK Finished
WP4 T4.1 Semantic information model TEK Finished
T4.2 Integration of demand response with supply/demand side management
IMP Finished
T4.3 Optimal Energy dispatching at household and neighbourhood level
IMP Finished
T4.4 Energy production and demand forecasting IMP Open until M30
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
115 | 155
T4.5 Data analytics and optimized control TEK Open until M30
WP5 T5.1 Home automation interoperability interfaces IMP Finished
T5.2 Smart grid connectivity IMP Finished
T5.3 RESPOND middleware development IMP Finished
T5.4 Integration with desktop dashboard and Smart mobile client
DEXMA Finished
T5.5 Data protection and security measures IMP Finished
WP6 T6.1 Validation methodology and acceptance criteria NUIG Finished
T6.2 Validation analysis and reporting NUIG Open until M34
T6.3 Qualiative evaluation of user experiences and recommendations
AAU Open until M34
T6.4 Replication plan development FEN Open until M34
WP7 T7.1 Dissemination and communication strategy DEXMA Open until M36
T7.2 Products, services and supporting business model definition
FEN Open until M36
T7.3 Data life cycle management FEN Open until M36
T7.6 Contribution to EASME dissemination activities FEN Open until M36
WP8 T8.1 Project administration & qualitity assurance FEN Open until M36
T8.2 Project management and EC reporting FEN Open until M36
• On-time preparation and delivery of the following Deliverables:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
116 | 155
TABLE 2. DELIVERABLES LIST FOR SECOND YEAR (M13-M24 PERIOD)
Specific Objectives for reported period M13-M24
WP OBJECTIVES ACHIEVEMENTS
WP1 Pilot site characterization Successful submission of D1.4 in M13
WP2 Use case deployment and follow-up Successful submission of D2.2 and D2.4 in M13 and D2.5 in M24
WP3 User engagement process
Successful submission of D3.1 and D3.4 in M13 and D3.3 in M24
WP4 ICT enabled cooperative demand response model
Successful submission of D4.1 in M18 and D4.2, D4.3 in M24
WP5 System Integration and Interoperability Successful submission of D5.1 in M18 and D5.2, D5.3, D5.4, D5.5 in M24
WP6 Validation and Replication of Project Results D6.1 was delayed and submitted in M26 instead of M24 because additional time for
baseline checking WP7 Dissemination and Exploitation Activities Successful submission of D7.4 in M18
WP8 Project management Successful preparation of Official Periodic Report M1-M18, the submission was delayed
because of amendment process opened
• Guidance to consortium members for defining the initial versions, reviewing or updating
any output in the progress of work, with a common format of project delivery.
• Coordination of external advisory boards approach.
T8.2 PROJECT MANAGEMENT AND EC REPORTING. M1-M36
• Handling of project correspondence and day-to-day requests from partners and external bodies.
• Implementing and maintaining the project management infrastructure. The tools used are
efficient and have facilitated the execution of the project objectives: the internal platforms
for information exchange as Google Drive document sharing infrastructure and Adobe
Connect for remote meetings, distribution mail list, long-term calendar, to do’s list, etc.
• Implementing and maintaining a project-specific database for reporting and controlling, including the adaptation of the structure after changes in the work plan and the Consortium.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
117 | 155
• Preparing, executing and post-processing the major project meetings (tasks: agendas, invitations, location of meeting places, organization of rooms and equipment, preparation and distribution of materials, minutes and action lists).
• Designing and maintaining specific templates for collecting input to the required EC
documents.
• Checking the dissemination and exploitation plan versus the EC’s requirements.
• Preparing and post-processing of EC reviews from the consortium-side including support
in the implementation of recommendations from the EC and reviewers.
• Handling of legal issues, Data protection issues, IPR issues and maintenance of the
consortium agreement, if necessary.
• Preparing and executing internal and project level quality assurance measures.
2.5.8.3 DEVIATIONS AND CORRECTIVE ACTIONS IN TASKS
T8.1 PROJECT ADMINISTRATION & QUALITY ASSURANCE AND T8.2 PROJECT MANAGEMENT AND EC
REPORTING. M1-M36 FEN AND T8.2 PROJECT MANAGEMENT AND EC REPORTING. M1-M36 FEN
Deviations from GA:
The deviations are described in section 3.2 Project issues and 3.2.1 Amendments.
Corrective actions:
Submission of amendment.
2.5.8.4 USE OF RESOURCES
Below you can see the efforts performed in this work package by each partner, both, the initial
budget figures and the real efforts carried out.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
118 | 155
FIGURE 81: EFFORTS BY PARTNER (BUDGET AND REAL) IN THE WP8 DURING THE 2ND YEAR
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
119 | 155
3. PROJECT MANAGEMENT
3.1 CONSORTIUM MANAGEMENT TASKS
3.1.1 PROJECT MEETINGS
The consortium run regular meetings to monitor progress and coordinate the development of
specific WPs and associate Deliverables. The following meetings have been held during the
second year, M13-M24.
During the reporting period the following face-to-face meetings (3 meetings per year, as
stipulated by Consortium Agreement) have been held:
• Spanish pilot visit, Oct. 24&25, 2018, Madrid
Agenda:
Wednesday 24 Oct
Time What Who Where
7:45-08:30 Bus to FEN Headquarters
8:30-09:00 WP8 - Housekeeping FEN
Feníe Energía headquarters
9:00-09:30 PMT conclusions FEN
9:30-10:30 WP7 FEN, DEXMA
10:30-11:00 Coffee break
11:00-12:30 WP2 DEV, TEK, ENE
12:30-13:30 Bus to city centre
13:30-15:30 Lunch La Esquina
Restaurant
16:00-17:00 Pilot Visit Madrid Pilot
Site
19:30 Dinner Lateral
Castellana 89 Restaurant
Thursday 25 Oct
Time What Who Where
7:45-08:30 Bus to FEN headquarters
8:30-09:00 WP1 TEK
9:00-11:00 WP4 TEK, IMP
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
120 | 155
11:00-11:30 Coffee Break Feníe Energía headquarters 11:30-13:00 WP5 IMP
13:00-14:00 Lunch
14:00-14:30 WP6 NUIG
14:30-15:30 WP3 AAU, TEK
15:30-16:00 Coffee break
16:00-16:30 WP3 (Cont.) AAU, TEK
16:30-17:00 Wrap up FEN
17:00-18:00 Bus to hotel
19:30 Dinner Tapas
FIGURE 6. RESPOND CONSORTIUM AT MADRID MEETING
• IK-4Tekniker, Mar. 13&14, 2019, Eibar
Agenda:
Wednesday 13 March
Time What Who Where
8:00-08:30 Transport to TEK Headquarters
8:30-09:30 WP8 - Housekeeping FEN
Tekniker
9:30-10:30 Pilot status FEN, ARAN, AURA
10:30-11:00 Coffee break
11:00-12:00 WP3 AAU, TEK
12:00-13:00 WP6 NUIG
13:00-14:00 Lunch
14:00-15:00 Tekniker Visit TEK
15:00-15:30 Coffee break
15:30-16:30 WP7 DEXMA
16:30-17:00 WP4 status TEK
17:00-17:30 WP5 status IMP
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
121 | 155
17:30-18:00 Wrap up FEN
19:00-20:00 Cider house visit TEK Cider house restaurant 20:00 Dinner
Thursday 14 March
Time What Who Where
8:00-08:30 Transport to TEK Headquarters
8:30-10:30 WP4 workshop TEK, IMP, DEXMA,
NUIG
Tekniker
10:30-11:00 Coffee Break
11:00-13:00 WP4 workshop (Cont.) TEK, IMP, DEXMA,
NUIG
13:00-14:00 Lunch
14:00-16:00 WP5 workshop TEK, IMP, DEXMA
15:30-16:00 Coffee break
16:00-17:00 WP5 workshop (Cont.) TEK, IMP, DEXMA
17:00-17:30 Wrap up FEN
19:00 Pintxos
FIGURE 7. RESPOND CONSORTIUM AT IK4-TEKNIKER
• Institute Mihajlo Pupin, Oct. 23&24, 2019, Belgrade (It will also be reported in D8.4 in M34 as it was held in M25 and it corresponds to the third year period).
Agenda:
Wednesday 23 October
Time What Who Where
8:30-09:00 WP8 - Housekeeping FEN INSTITUTE MIHAJLO
PUPIN
9:00-10:00 Pilot status FEN, ARAN, AURA
10:00-11:00 Review preparation
▪ WP1 status FEN, IMP, AURA, AAU, NUIG
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
122 | 155
▪ WP2 status ▪ WP3 status
Volgina 15, Belgrade,
Serbia 11:00-11:30 Coffee break
11:30-12:30 Review preparation (Cont.)
▪ WP4 status ▪ WP5 status
WP leaders
12:30-13:30 External Advisory Board feedback
13:30-14:30 Lunch
14:30-16:00 Review preparation (Cont.) LIVE DEMO
WP leaders
16:00-16:30 Coffee break
16:30-17:30 Steering Committee ALL
17:30-18:00 Wrap up FEN
20:00 Dinner
Belgrade Kalemegdan
Fortress Restaurant
Thursday 24 October
Time What Who Where
8:30-10:00
Review preparation (Cont.)
▪ WP6 status ▪ WP7 status ▪ WP8 status
TEK, IMP
INSTITUTE MIHAJLO
PUPIN Volgina 15, Belgrade,
Serbia
10:00-10:30 WP4 workshop
10:30-11:00 Coffee Break
11:00-13:00 WP4 workshop (Cont.) TEK, IMP
13:00-13:30 WP5 workshop IMP, DEXMA
13:30-14:30 Lunch
14:30-16:00 WP5 workshop (Cont.) IMP, DEXMA
16:00-16:30 Coffee Break
16:30-17:00 WP5 workshop (Cont.) ALL
17:00-17:30 Wrap up FEN
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
123 | 155
FIGURE 8. RESPOND CONSORTIUM AT BELGRADE
During the reporting period the following general call conferences meetings have been held
(with a periodicity of fifteen days, as stipulated by the Consortium Agreement):
• Oct. 19, 2018 • Nov. 16, 2018 • Nov. 30, 2018 • Dec. 14, 2018 • Jan. 11, 2019 • Jan. 25, 2019 • Feb. 08, 2019 • Feb. 22, 2019 • Mar. 08, 2019 • Mar. 29, 2019 • Apr. 12, 2019
• Apr. 26, 2019 • May 10, 2019 • May 24, 2019 • Jun. 07, 2019 • Jun. 21, 2019 • Jul. 05, 2019 • Jul. 19, 2019 • Aug. 30, 2019 • Sep. 13, 2019 • Sep. 27, 2019
During the reporting period the Project Management Team have met twice per year (as stipulated by the Consortium Agreement, the Project Management Team, constitutes the supervisory body for the execution of RESPOND Project, is led by the Project Coordinator (FEN) and also composed by the Technical Leaders (IMP & TEK) and the Exploitation Manager (DEXMA)):
• Third PMT meeting, Dec. 13, 2018, Call Conference Agenda:
Time What Who
12:00 – 13:00
1. Approval of the agenda and minutes of 22 Oct 2018 (PMT meeting) ALL
2. Amendments ALL
3. AOB ALL
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
124 | 155
• Fourth PMT meeting, Sep. 19, 2019, Call Conference (It will be reported in D8.3 in M26 as well as it was celebrated in M13). Agenda:
Time What Who
09:30 – 10:00
1. Approval of the agenda and minutes of 13 Dec. 2018 (PMT meeting) ALL
2. Official Periodic Report ALL
3. AOB ALL
During the reporting period the Steering Committee, with representatives of nine partners from the eleven (ALBOA and ARAN didn’t attended) held the annual SC meeting (as stipulated by the Consortium Agreement: once per year with the participation of all partners).
• Second year Steering Committee during Institute Mihajlo Pupin face-to-face meeting,
Oct. 23, 2019, Belgrade.
Agenda:
1. Consortium pending issues. Amendment.
During the reporting period the following specific technical meetings have been held:
• Calorimeters-Building simulator call conference meeting, Mar. 28, 2019, Call Conference
• Demo plan + deployment status plan call conference meeting, Sept. 12, 2019, Call Conference
• Energy production measurements call conference meeting, Oct. 08, 2019, Call Conference
• DEXCell tutorial call conference meeting, Oct. 16, 2019, Call Conference
• Pilots next steps call conference meeting, Oct. 29, 2019, Call Conference
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
125 | 155
• Validation scenarios call conference meeting, Nov. 15, 2019, Call Conference
Besides, technical points have been included in the agenda of the general call conferences along
the whole project.
3.1.2 PROJECT MEETINGS ATTENDANCE STATISTIC
FEN, on behalf of Project Coordinator, has done attendance statistics for the different types of meetings that the Consortium holds.
• Face-to-face meetings statistics for the first year M1-M12 (October 2017 - September 2018) and second year M13-M24 (October 2018 - September 2019). Also, aggregated for the period of two years M1-M24.
FIGURE 9. F2F meetings attendance per partner graphic for 1st year
100,00% 100,00%
66,67%
100,00% 100,00% 100,00% 100,00% 100,00% 100,00%
66,67%
100,00%
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
70,00%
80,00%
90,00%
100,00%
FEN TEK ALBOA AURA AAU ARAN NUIG IMP DEV ENE DEXMA
F2F Meetings attendance RESPOND Project 1st year, M1-M12
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
126 | 155
FIGURE 10. F2F MEETINGS ATTENDANCE PER PARTNER GRAPHIC FOR 2ND YEAR
FIGURE 11. F2F MEETINGS ATTENDANCE PER PARTNER GRAPHIC AGGREGATED FOR M1-M24 PERIOD
All partners, TEK, AURA, AAU, ARAN, NUIG, IMP, DEV, ENE, DEXMA, FEN have actively
attended to the F2F meetings.
ALBOA, has progressively reduced their involvement within the project. This change has been
implemented with the submission of the amendment, in which there is a transference of ALBOA
100,00% 100,00%
0,00%
100,00% 100,00%
66,67%
100,00% 100,00%
66,67%
100,00% 100,00%
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
70,00%
80,00%
90,00%
100,00%
FEN TEK ALBOA AURA AAU ARAN NUIG IMP DEV ENE DEXMA
F2F Meetings attendance RESPOND Project2nd year, M13-M24
100,00% 100,00%
33,33%
100,00% 100,00%
83,33%
100,00% 100,00%
83,33% 83,33%
100,00%
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
70,00%
80,00%
90,00%
100,00%
FEN TEK ALBOA AURA AAU ARAN NUIG IMP DEV ENE DEXMA
F2F Meetings attendance RESPOND Project M1-M24
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
127 | 155
PMs. However, this partner remains in the Consortium as their association is still represented by
the users (inhabitants of the Danish pilot).
• General call conference meetings (remote via Adobe Connect platform) statistics for
the reporting period: two semesters M13-M18 and M19-M24 of the second year (October 2018 - September 2019). Also, aggregated for the period of two years M1-M24.
FIGURE 12. CALL CONFERENCES MEETINGS ATTENDANCE PER PARTNER GRAPHIC FOR SEMESTER M13-M18
FIGURE 13. CALL CONFERENCES MEETINGS ATTENDANCE PER PARTNER GRAPHIC FOR SEMESTER M19-M24
100,00%
90,00%
0,00%
70,00%
80,00%
90,00%
100,00% 100,00%
10,00%
70,00%
100,00%
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
70,00%
80,00%
90,00%
100,00%
FEN TEK ALBOA AURA AAU ARAN NUIG IMP DEV ENE DEXMA
Meetings attendance RESPOND Project 2nd year, semester M13-M18
100,00% 100,00%
0,00%
72,73%
100,00%
63,64%
72,73%
81,82%
27,27%
9,09%
100,00%
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
70,00%
80,00%
90,00%
100,00%
FEN TEK ALBOA AURA AAU ARAN NUIG IMP DEV ENE DEXMA
Meetings attendance RESPOND Project 2nd year, semester M19-M24
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
128 | 155
FIGURE 14. CALL CONFERENCES MEETINGS ATTENDANCE PER PARTNER GRAPHIC AGGREGATED FOR M1-M24
PERIOD
All partners, TEK, AURA, AAU, ARAN, NUIG, IMP, DEV, ENE, DEXMA, FEN have actively
attended to the general call conferences meetings (remote via Adobe Connect platform) held
regularly every fifteen days. Although, DEV and ENE have a lower percentage of attendance to
these meetings, there has been a constant communication via email with them and their technical
tasks have been fulfilled.
3.2 PROJECT ISSUES
During the previous reporting period we had identified the following issues. At the moment of this report those issues have been solved:
• AURA Raadgivning termination and addition of AURA A/S.
• ALBOA effort reduction (reallocation to other partners)
• DEVELCO effort reduction (reallocation to other partners)
• Increase of PMs and advance of the task’s beginning for TEK’s mobile App.
• DEXMA PMs internal reallocation within WP4.
• Reduce of PMs in T6.5 IMP’s efforts due to a mistake.
• Correction of typo in the deadline of deliverables D8.2 and D8.3.
• Equipment for pilot sites: Reduction of Develco’s budget for Irish pilot and increase of
Energominor’s to step in that pilot.
SUMMARY: Efforts increased 4.2 PMs; total cost decreased 135,17 €
• ALBOA: Non-profit status validation: Its funding ratio increases from 70% to 100%
100,00% 97,50%
7,50%
72,50%
87,50%
67,50%
92,50% 92,50%
30,00%
60,00%
92,50%
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
70,00%
80,00%
90,00%
100,00%
FEN TEK ALBOA AURA AAU ARAN NUIG IMP DEV ENE DEXMA
General call conferences meetings attendance RESPOND Project M1-M24
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
129 | 155
3.2.1 AMENDMENTS
As explained in the previous section 3.2, the Project Coordinator submitted, following the EC
procedures, the Amendment Reference No AMD-768619-14 to the Grant Agreement, to solve
the issues aforementioned.
The amendment encompasses several changes of different nature such us mistakes in deadlines
of some deliverables, advance of the beginning of one task, change of efforts between partners,
change of budget between devices providers and change of organization taking part in the project
between a corporate group.
All these changes have been explained to the consortium and agreed by all and also explained
for feedback and guidance to the Project Officer.
The changes were:
• ALBOA has been validated as Non-profit organization after the kick-off of the project. • AURA Raadgivning termination and addition of new participant AURA A/S (PIC
907660720). There was a mistake within the organization as the employees taking part in the project are part of the new partner although their office is in the previous partner building.
• ALBOA effort reduction: Agreed between ALBOA and AURA to shift some PMs from one company to the other. ALBOA doesn’t have enough human resources for the project since the employees taking part have leave the company. AURA as a local partner with very good relationship will step in for these tasks. Furthermore, the travel budget for ALBOA has been also reduced.
• DEVELCO effort reduction: Agreed with them and the involved partners to shift some PMs to TEK, PUP, AURA, ENE and DEXMA. The necessary effort has been higher than they can afford and they will like to share with another partner with enough resources to not affect the performance of the project.
• DEXMA PMs internal reallocation within WP4 due to errors in the original planning. Mistake in proposal regarding the internal distribution of DEXMA effort along tasks in WP4.
• Increase of PMs for TEK in T5.4 as the mobile App was proposed to be developed only for Android and it was assessed that also iOS version will be necessary to promote engagement which implies more efforts.
• Advance of the beginning of the task T5.4. To allow enough time to develop iOS version and the integration with related tasks.
• Reduction of PMs for IMP in T6.5 as the original number of PMs was to high according to the DoA for that action. During the amendment proposal it raised that to many PMs were allocated to IMP according to the description of the action.
• Changes in equipment devices for pilot sites: Reduction of Develco’s budget for Irish pilot and increase of Energominor’s to step in that pilot. During the early deployment it was realized that the Develco’s equipment wasn’t compatible with the peculiarities of the Irish electrical system. As Energomonitor’s equipment are compatible (after a test) it was agreed to replace one provider for another one.
• Correction of the deadline of deliverables D8.2 and D8.3. A mistake was detected as it is not possible to submit the yearly management report the same date that the period to be reported, it is necessary 2 extra month to collect all the information and prepare the deliverable. In the case of D8.3 it was scheduled by mistake in the medium of the period to be reported.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
130 | 155
After the changes, as a summary, the efforts in the project will increase by 4.2 PMs while the total
cost will decrease by 135.17 €.
3.3 RISK ASSESSMENT
In the proposal phase of the project the following main critical risks related to the project were
listed:
• Management risks
• Functional risks
• Technical risks
• Visibility risks
• Business risks
A Risk Register was created with the purpose of monitoring the main potential risks and the
response action performed to avoid it.
The procedure that has been carried out to maintain it updated is the following: after a potential
risk is identified, the Risk Register is updated and finally a response action is implemented with
the consensus of the Consortium members, usually during a meeting. The excel contains fields
for the following concepts:
• Description of the risk
• Potential impact: low, medium or high
• Responsible
• Response action taken to avoid it
• Status
During the first two years of RESPOND project, the following resolutive actions were performed:
• iOS application development to guarantee the compatibility with the users engaged
devices in addition to the initial idea of android development.
• Aran islands pilot particularities: Irish pilot team strengthening to ensure the
engagement process, Develco fabric and shipment delays, Develco devices technical
incompatibilities with Irish electrical domestic system.
• Amendment submission
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
131 | 155
3.4 MANAGEMENT STRUCTURE
The Management Structure for RESPOND Consortium has remained as it was articulated. There are two organization levels:
• An Operational level:
The operational level of the management is constituted by the Project Management Team (PMT): led by the Project Coordinator (PC) and also composed by the Technical Leaders (TL) and the Exploitation Manager (EM).
• A Strategy level:
The strategy level is represented by the Steering Committee (SC): composed by one
representative per partner and is chaired by the Project Coordinator.
The Project Management is composed by two different bodies that will assure the correct orientation of the project to the expected results and that will be supported by:
• Work Packages Leaders (WPL)
• User Engagement Leader (UEL)
• Pilot Case Coordinator (PCC)
• External Advisory Board (EAB)
3.4.1 EXTERNAL ADVISORY BOARD (EAB)
In this reporting period, the Consortium consulted some External Advisory Board experts and got
feedback from them. The feedback obtained will be presented at the 1st Review (scheduled for 4-
5 Dec. 2019 in Brussels).
The idea is to schedule a meeting with the following EAB members in Brussels in 2020.
• Milos Banjac, National Energy DSO (IMP)
• NorthQ, Smart home provider, and AVA, District Heat provider (AURA)
• Bianca Barth, German Association of Energy Market Innovators BNE (FEN)
3.5 ADMINISTRATIVE MANAGEMENT TOOLS
During this reporting period, the same administrative management tools have been used by the
Consortium:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
132 | 155
• Document sharing infrastructure
• To do’s
• Partner Pictures Directory
• Distribution Mail List
• Long-term calendar
3.6 DISSEMINATION ACTIVITIES
3.6.1 WEBSITE AND BLOG POSTS
A website for RESPOND project was developed, to serve as the main platform for dissemination and communication for interested stakeholders ( www.project-respond.eu ). It was set up in M3 and has been maintained actively over the reporting period. The design of RESPOND project website focuses on following objectives:
• To present RESPOND to the world and provide a means of contact for interested stakeholders.
• To share project objectives and describe each of the pilot demonstration sites.
• To provide updates on project progress, events, articles and final results.
We have been publishing information about partners, pilots, publications of deliverables submitted
and news.
The project news page functions as a blog, with a tone adapted for a more general audience,
avoiding institutional or scientific jargon. It also includes news stories that have been produced
during the course of the reported period as well as information about the events where the
RESPOND partners have participated.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
133 | 155
FIGURE 82: SCREEN SHOT OF RESPOND WEBPAGE: BLOG SECTION
3.6.2 PUBLICATIONS
• Our partner from Institute Mihajlo Pupin (IMP: Lazar Berbakov, Nikola Tomašević, Marko
Batić) published the following article:
“Architecture and implementation of IoT system for energy efficient living,” Proceedings
of 26th Telecommunications forum TELFOR 2018, ISBN: 978-1-5386-7171-9, pp. 265-
268, Serbia, Belgrade, November 20-21, 2018. DOI: 10.1109/TELFOR.2018.8611888
• Our Partner from Aalborg University (AAU: Toke H. Christensen, Henrik N. Knudsen) published an article in ECEEE Summer Study 2019. The paper is available at AAU depository on the following page:
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
134 | 155
https://vbn.aau.dk/da/publications/how-to-engage-households-in-energy-demand-response-solutions
• Our partner from Fundación Tekniker (TEK: Francisco Díez, Iker Esnaola) published an article in the European Energy Innovation Magazine. The paper is available in:
FIGURE 83: MAGAZINE PUBLICATION
• Our partner from National University of Ireland, Galway (NUIG: Federico Seri) wrote two papers, the proceedings/DOI are not available yet, but these are the information:
1) 4th Annual APEEN 2019 - Energy Demand-Side Management and Electricity Markets
University of Beira Interior - Covilhã - Portugal. October 17-18th 2019
Paper: Demand Response for residential buildings: case studies and DR program design
by the RESPOND project.
2) AICS2019 - 27th AIAI Irish Conference on Artificial Intelligence and Cognitive Science
for Sustainability
NUI Galway - Galway - Ireland. December 5-6th 2019
Paper: Machine Learning Methods Applied to Building Energy Production and
Consumption Prediction
3) he 16th IBPSA International Conference and Exhibition, Building Simulation 2019,
Rome, Italy, from September 2 – 4, 2019.
Paper: Development Of A Reduced Order Model For Standard-Based Measurement And
Verification To Support ECM
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
135 | 155
• Several Open Access Government publications:
Our partner from Feníe Energía (FEN: Rodrigo López) wrote the article “Demand
Response 101: how to get paid to cut power use for Utilities”.
FIGURE 84: OPEN ACCESS GOVERNMENT PUBLICATION
3.6.3 EVENTS, WORKSHOPS, TELEVISION
For dissemination activities, RESPOND project has participated at the following events during the
reporting period:
• Sustainable places 2019, Cagliari, Italy
https://www.sustainableplaces.eu/
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
136 | 155
FIGURE 85: RESPOND PROJECT PARTICIPATION AT SUSTAINABLE PLACES 2019
• LDAC 7th Linked Data in Architecture and Construction Workshop, Lisbon, Portugal
http://linkedbuildingdata.net/ldac2019/?utm_content=92663726&utm_medium=social&utm_source=facebook&hss_channel=fbp-1752724508354974
FIGURE 86: RESPOND PROJECT PARTICIPATION AT LDAC 2019
• EU Sustainable Energy Week 2019, Brussels, Belgium
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
137 | 155
https://ec.europa.eu/info/events/eu-sustainable-energy-week-2019-jun-18_en
FIGURE 15. RESPOND PROJECT PARTICIPATION AT EU SUSTAINABLE ENERGY WEEK 2019
• ECEEE Summer Study 2019 – Is efficient sufficient? – from the 3rd to 8th of June 2019, in France https://www.eceee.org/summerstudy/
FIGURE 87: EVENTS’ PICTURES: ECEEE SUMMER STUDY 2019, FRANCE
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
138 | 155
• ETSI IoT Week 2019, 21-25 October 2019, Sophia Antipolis, France. ( https://www.etsi.org/events/1601-etsi-iot-week-2019 )
FIGURE 88: RESPOND PROJECT PARTICIPATION AT ETSI IOT 2019
• Energy Utility week 2019, 12 November 2019, Paris, France
( https://www.smarten.eu/european-utility-week-2019/ )
FIGURE 89: RESPOND PROJECT PARTICIPATION AT EUROPEAN UTILITY WEEK 2019
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
139 | 155
• The RESPOND Project has been featured on a current affairs programme, on a National
Irish Language broadcaster TG4. The broadcast took place in the Aran islands, which is
one of the 3 RESPOND pilot sites.
Link to the video of the TV coverage (from 0:51 to 5:10), and you’ll see some of the
equipment we installed: https://dex.ma/305yCF3
FIGURE 90: RESPOND PROJECT FEATURED IN IRISH TV
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
140 | 155
4. DELIVERABLES AND MILESTONES
4.1 DELIVERABLES
Table below shows the deliverable that have been submitted from the beginning of the project
until the end of this period M1-M24, according to the DoA.
TABLE 10. RESPOND PROJECT LIST OF DELIVERABLES SUBMITTED DURING REPORTED PERIOD M1-M24
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
141 | 155
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
142 | 155
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
143 | 155
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
144 | 155
4.2 MILESTONES
Table below shows the project Milestones that have been scheduled for completion from the
beginning of the project until the end of this period M1-M12, according to the DoA.
TABLE 11. RESPOND PROJECT MILESTONES
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
145 | 155
5. USE OF RESOURCES
Within this section a wider vision of the figures related to efforts and costs of the project will be presented, both looking RESPOND as a whole with the aim to check if the project is in track and also a detailed view per partner. Together with the data, an explanation is provider in the situation of big differences between the budget and actual expenses and efforts. The below information regarding real values have been provided by each partner according to their best knowledge without audit from the project coordinator that, in addition to define the guidelines and templates for reporting, provide help or clarifications when demanded and ask for further explanations in the case of sensitive differences according to the expected values, is just a mere aggregator of the information. During the second year of RESPOND project (October-18 to September-19) under review in this deliverable there has not been changes in the initial Grant Agreement subscribed by all partners and the commission and therefore no new budgets have been put in place.
5.1 EFFORTS SUMMARY
The following paragraphs reflects the current situation of the project after their second year of live
focusing on the efforts performed by the consortium as a whole and partner by partner.
TABLE 12: TOTAL EFFORTS (ACTUAL AND BUDGET) BY PARTNER AND WP IN THE 2ND YEAR
TABLE 13: PERCENTAGE OF ACTUAL EFFORTS VS BUDGET BY PARTNER AND WP IN THE 2ND YEAR
[PMs] BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL
01-FEN 18,22 18,30 0,00 0,00 4,00 4,01 0,67 0,67 0,00 0,00 0,00 0,00 4,57 4,60 4,67 4,68 4,32 4,33
02-TEK 37,79 40,59 0,00 0,00 0,00 3,22 0,00 1,38 15,00 13,30 13,50 20,58 6,12 0,25 2,84 1,54 0,33 0,32
03-ALBOA 1,20 0,42 0,00 0,07 0,00 0,06 1,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,15 0,20 0,14
04-AURA 9,75 9,56 0,00 1,04 2,20 1,85 1,00 4,24 0,00 0,00 0,00 0,12 2,00 1,16 4,00 0,49 0,55 0,66
05-AAU 9,60 7,03 0,00 0,00 0,00 0,00 7,00 6,38 0,50 0,00 0,00 0,00 1,00 0,00 0,80 0,63 0,30 0,02
06-ARAN 4,83 3,50 0,00 0,00 1,00 1,50 0,50 0,50 0,00 0,00 0,00 0,00 2,00 0,50 1,00 0,67 0,33 0,34
07-NUIG 11,50 14,75 0,00 0,00 0,00 0,00 0,00 0,00 3,50 6,50 0,00 0,00 8,00 8,25 0,00 0,00 0,00 0,00
08-IMP 44,60 46,27 0,00 0,00 0,00 4,00 0,00 0,00 14,00 9,51 24,00 27,21 5,00 3,79 1,30 1,20 0,30 0,56
09-DEV 18,30 9,92 0,00 0,00 4,00 3,30 0,00 0,00 0,00 0,00 8,00 3,70 2,00 0,74 4,00 1,99 0,30 0,19
10-ENE 10,20 1,10 0,00 0,00 4,00 0,00 0,00 0,00 0,00 0,00 2,00 0,61 1,00 0,00 3,00 0,00 0,20 0,49
11-DEXMA 29,15 30,26 1,70 1,76 6,70 7,20 1,95 2,14 5,00 5,07 7,80 7,67 0,00 0,00 6,00 6,37 0,00 0,03
TOTAL 195,15 181,69 1,70 2,87 21,90 25,15 12,12 15,31 38,00 34,38 55,30 59,89 31,69 19,29 27,60 17,72 6,84 7,08
WP8WP3 WP4 WP5 WP6 WP7TOTAL WP1 WP2
TOTAL WP1 WP2 WP3 WP4 WP5 WP6 WP7 WP8
[%] ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD
01-FEN 100% 100% 100% 100% 100% 100% 101% 100% 100%
02-TEK 107% 100% 100% 100% 89% 152% 4% 54% 96%
03-ALBOA 35% 100% 100% 0% 100% 100% 100% 100% 70%
04-AURA 98% 100% 84% 424% 100% 100% 58% 12% 120%
05-AAU 73% 100% 100% 91% 0% 100% 0% 79% 5%
06-ARAN 72% 100% 150% 100% 100% 100% 25% 67% 101%
07-NUIG 128% 100% 100% 100% 186% 100% 103% 100% 100%
08-IMP 104% 100% 100% 100% 68% 113% 76% 92% 187%
09-DEV 54% 100% 83% 100% 100% 46% 37% 50% 63%
10-ENE 11% 100% 0% 100% 100% 30% 0% 0% 247%
11-DEXMA 104% 103% 108% 110% 101% 98% 100% 106% 100%
TOTAL 93% 169% 115% 126% 90% 108% 61% 64% 104%
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
146 | 155
FIGURE 91: TOTAL EFFORTS (ACTUAL AND BUDGET) BY PARTNER IN THE 2ND YEAR
As it is shown, in general terms, all partners are aligned with the expected amount of efforts encompassed in the original Grant Agreement description of action. Below it is a compilation of individual graphs per partner.
FEN TEK
ALBOA AURA
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
147 | 155
FIGURE 92: TOTAL EFFORTS (ACTUAL AND BUDGET) FOR EACH PARTNER IN THE 2ND YEAR
AAU ARAN
NUIG IMP
DEV ENE
DEXMA
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
148 | 155
5.2 COSTS SUMMARY
The following paragraphs reflects the current situation of the project after their second year of live
focusing on the cost incurred by the consortium as a whole and partner by partner.
TABLE 14: TOTAL COSTS (ACTUAL AND BUDGET) BY PARTNER AND TYPE IN THE 2ND YEAR
TABLE 15: PERCENTAGE OF ACTUAL COSTS VS BUDGET BY PARTNER AND TYPE IN THE 2ND YEAR
[€] BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL
01-FEN 240992,58 247053,47 48198,52 49410,69 74333,34 99603,27 118460,72 98039,50 168694,81 172937,43 0,00 0,00
02-TEK 234686,34 231233,14 46937,27 46246,63 6416,67 9150,91 181332,41 175835,60 234686,34 231233,14 0,00 0,00
03-ALBOA 13950,00 3655,83 2190,00 731,17 0,00 0,00 8760,00 2924,66 9765,00 2559,08 3000,00 0,00
04-AURA 110900,31 82112,90 22180,06 16422,58 8000,00 2603,15 80720,25 63087,17 77630,22 57479,03 0,00 0,00
05-AAU 105942,00 57752,13 21188,40 0,00 5400,00 4740,17 79353,60 53011,96 105942,00 57752,13 0,00 0,00
06-ARAN 27493,33 21239,23 5498,67 4247,85 2666,67 2991,38 19328,00 14000,00 27493,33 21239,23 0,00 0,00
07-NUIG 67285,51 75177,80 13457,10 15035,56 3714,28 3360,90 50114,13 56781,34 67285,51 75177,80 0,00 0,00
08-IMP 172686,66 172234,11 34537,33 34446,82 6133,33 5963,42 132016,00 131823,87 172686,66 172234,11 0,00 0,00
09-DEV 232837,50 118578,11 46567,50 23715,62 60000,00 15066,66 126270,00 79795,83 162986,25 83004,68 0,00 0,00
10-ENE 70075,00 11356,72 14015,00 2271,34 2000,00 3262,00 54060,00 5823,38 49052,50 7949,70 0,00 0,00
11-DEXMA 156962,50 170185,65 31392,50 34037,13 14800,00 10625,77 110770,00 125522,75 109873,75 119129,95 0,00 0,00
TOTAL ######### ######### 286162,35 226565,39 183464,28 157367,63 961185,11 806646,05 ######### ######### 3000,00 0,00
TOTAL Indirect Costs Other direct costs Personnel costs Requested EU funding Subcontracting
[%] ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD ACT/BUD
01-FEN 103% 103% 134% 83% 103% 100%
02-TEK 99% 99% 143% 97% 99% 100%
03-ALBOA 26% 33% 100% 33% 26% 0%
04-AURA 74% 74% 33% 78% 74% 100%
05-AAU 55% 0% 88% 67% 55% 100%
06-ARAN 77% 77% 112% 72% 77% 100%
07-NUIG 112% 112% 90% 113% 112% 100%
08-IMP 100% 100% 97% 100% 100% 100%
09-DEV 51% 51% 25% 63% 51% 100%
10-ENE 16% 16% 163% 11% 16% 100%
11-DEXMA 108% 108% 72% 113% 108% 100%
TOTAL 83% 79% 86% 84% 84% 0%
Requested
EU fundingSubcontracting
Indirect
Costs
Other direct
costs
Personnel
costsTOTAL
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
149 | 155
FIGURE 93: TOTAL COSTS (ACTUAL AND BUDGET) BY PARTNER IN THE 2ND YEAR
As it is shown, in general terms, all partners are aligned with the expected amount of budget encompassed in the original Grant Agreement description of action. Below it is a compilation of individual graphs per partner.
FEN TEK
ALBOA AURA
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
150 | 155
FIGURE 94: TOTAL COSTS (ACTUAL AND BUDGET) FOR EACH PARTNER IN THE 2ND YEAR
AAU ARAN
NUIG IMP
DEV ENE
DEXMA
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
151 | 155
FIGURE 95: TOTAL COSTS (ACTUAL AND BUDGET) FOR EACH TYPE IN THE 2ND YEAR
PERSONNEL COSTS REQUESTED EU FUNDING
SUBCONTRACTING TOTAL COSTS
INDIRECT COSTS OTHER DIRECT COSTS
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
152 | 155
6. CONCLUSIONS
During the present reported period M13-M24 (October 2018 – September 2019) the global picture
regarding the status of RESPOND project is positive.
The Consortium overcame the real-world challenges, which constitute a natural part of working
on field. From the multidisciplinary backgrounds involved in the project (technical, sociological,
aspects), those difficulties have been solved with effective solutions.
In order to achieve RESPOND project objectives, all the available resources have been used, we
have been constantly checking over if the results of the tasks converge towards the same
direction.
The scheduled deliverables have been reported on time focusing on a high-quality level. The
scheduled tasks have been accomplished and milestones achieved.
As in the previous management report (first year), the management structure for RESPOND
governance (Project Coordinator, technical Leaders, Exploitation Manager) with its different
bodies (Work Packages Leaders, User Engagement Leader, Pilot Case Coordinator) still works
effectively at both, operational level and strategy level. The Consortium has been ensuring the
effective execution of the technical work in order to achieve the main goals for the progress of the
project.
The management procedures and administrative tools have been functional and useful.
The same meetings structures performed during the first year of project have been kept.
Overall, the project execution is progressing well. From the three phases scheduled, namely:
1) Phase I: Project set up and early deployment 2) Phase II: RESPOND platform integration and advancement 3) Phase III: Project validation and replication
The third phase, project validation and replication, will be crucial to wrap up the tasks performed
in the period of 24 months, 1st and 2nd years.
The efforts from the third year onwards are in the following work packages:
WP4, ICT enabled cooperative demand response model, in particular for tasks:
• T4.4 Energy production and demand forecasting
• T4.5 data analytics and optimized control
WP6, Validation and replication of project results.
WP7, Dissemination and exploitation activities: the dissemination activities keep promoting the
project in order to build opportunities within the market.
Deliverables D6.5 Best practices and lessons learnt (M36) and D7.2 RESPOND business model
(M36) will be key for the final definition of RESPOND project.
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
153 | 155
The project keeps adapting to obtain a final result in the real world that accomplish with actual
technology completed and qualified trough test and demonstrations (TRL 8).
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
154 | 155
REFERENCES
RESPOND DOCUMENTS
Consortium Agreement, version 1.5, 2017-09-22
Grant Agreement number: 768619 – RESPOND integrated demand REsponse Solution towards energy POsitive NeighbourhooDs (RESPOND) – H2020-EE-2016-2017/H2020-EE-2017-PPP Amendment Reference No AMD-768619-14
D1.1 Pilot technical characterization and operation scenarios
D1.2 Demand response programs overview
D1.3 RESPOND strategy to support interoperability
D1.4 Pilot specific demand response strategy
D2.1 RESPOND system reference architecture
D2.2 Integration of key RESPOND technology tiers
D2.3 Initial Deployment Plan
D2.4 Early deployment activities report
D3.1 Criteria and framework for recruiting and engaging
D3.2 RESPOND use engagement strategy
D3.3 Findings and recommendations from focus groups on user context
D3.4 Personal energy performance assistant design
D4.1 Semantic information model
D4.2 Demand response optimization model
D4.3 Optimal energy dispatching at neighborhood level
D5.1 Energy gateway for home automation interoperability
D5.2 RESPOND connectivity to smart grid services
D5.3 RESPOND middleware deployment
D5.4 Desktop dashboard and smart mobile client
D5.5 Data protection security
WP8 Project management
D.8.3 MANAGEMENT REPORT (SECOND YEAR)
155 | 155
D6.1 RESPOND Validation methodology
D7.1 Dissemination and communication plan
D7.2 RESPOND dissemination and project website (preliminary)
D7.4 Data life cycle management policy (Preliminary)
D7.8 RESPOND dissemination and project website (final)
D8.1 Quality assurance plan
D8.2 Management report (first year)