Jenessa Dilley Ryan Simpson Adrian Smalley THE BALI BOMBINGS OF 2002.
GEOTHERMAL PROJECT COST ESTIMATING By Lorie M. Dilley.
-
Upload
miranda-fox -
Category
Documents
-
view
216 -
download
1
Transcript of GEOTHERMAL PROJECT COST ESTIMATING By Lorie M. Dilley.
GEOTHERMAL PROJECT COST ESTIMATING
By
Lorie M. Dilley
Exploration – chemical, geophysical, aerial photos
Drilling Costs
• Wells – Wells – Determine # of wells based on temperature, flow rate, and production required.
• MW/well = F/50 – 3.5 (temp. > 175 F)– 200 F: 0.5 MW– 400 F: 4.5 MW
• Low temperature 0.1 to 0.4 MW/well
• Drilling success rate 25% to 80% increase as knowledge of field increases
Temperature “Gradient” holes
Drilling Costs
• Slim hole/temperature gradient Drilling: 3 to 4 inch– 3,000 ft: $1.5 to $2 M
• Production Drilling: 9 to 12 inch– 3,000 ft : $3.9 to $4.3 M– 5,000 ft: $4.5 M – 30 to 40 days of drilling– 8,000 ft: $7.5 M
• Alaska Factor: 1.25 to 2 times
Infrastructure Needs
• Construction – camp, access, skilled workforce• Plant – power generation, piping, geothermal
wells, waste fluid disposal – trained operators• Support Facilities – transmission line, road, living
quarters, water supply & storage, wastewater treatment, maintenance shop, drilling equipment/ core shop,
• Facilities: greenhouses, pools, rooms
Power Production
Plant Costs
UTC System : 200 to 250 kW is about $1,300 per KW UTC System : 200 to 250 kW is about $1,300 per KW $260,000 $260,000Binary System: $1,600 to $2,400 per kW : Binary System: $1,600 to $2,400 per kW :
1 MW to 5 MW -$1.6M to $2.4M1 MW to 5 MW -$1.6M to $2.4MSteam Plants: $1,500 per kWSteam Plants: $1,500 per kW
5 MW to 25 MW - $7.5M to $37.5M5 MW to 25 MW - $7.5M to $37.5M
Support Facilities• Roads – equipment, access wells,:
gravel sources estimated cost is $30 to $250 per cubic yard depending upon material source location and quality – route selection critical
• Site Development – pads for plant, shops, living quarters, greenhouses – gravel, placement
• Transmission line – route selection – closer to village – power use $200,000 to $400,000+ per mile
Costs
• < 1 MW: UTC - $7M to $30M
• 1 MW to 10 MW : Binary - $40M to $100M
• Greater than 10 MW: Steam - $100M to $400M
Based on drilling depths, gravel costs, temperature of resource, flow, size of project.