GEORANGE Är Järn Guld för Pajala ? 2 april 2009
description
Transcript of GEORANGE Är Järn Guld för Pajala ? 2 april 2009
April 2, 2009 1
GEORANGEÄr Järn Guld för Pajala ?
2 april 2009Planned Iron Ore Mining in
the Pajala/Kolari Region
Karl-Axel WaplanMD of European Operations
April 2, 2009 2
Key events
2
Infrastructure
• MOU signed with operator as well as port authorities to develop Kemi port for the initial tonnage
• MOU signed with GIIC on long term shipment of concentrate from the Pajala/Kolari area
• Consortium organized to support the development of the Rail transportation to port; NRI, Bombardier and VR
• EPA Filed April 1, 2009
• Application to the Border River Commission to be filed May/April
April 2, 2009 3
MoU with GIIC
Contractual Year Annual Basic Quantity (in WMT)
2011 250,0002012 1,500,0002013 2,000,0002014 onwards 3,000,000
April 2, 2009 4
• Focus on Tapuli, Hannukainen, Stora Sahavaara and Pellivuoma
• Management priority is developing early cash flow
– start up of Tapuli mine with Kaunisvaara mill
• Existing infrastructure support early production of up to 2-3 Mt pa
• Resource base growing
• Staged growth of production up to 8-10 Mt pa of iron ore products
Investment Highlights
4
Investment Highlights
April 2, 2009 5
●KaunisvaaraKaunisvaara
April 2, 2009 6
Tapuli: Fast Track to Cash Flow• Open-pittable resource
• Existing infrastructure can take Tapuli’s full production with minor upgrades
• Preliminary studies suggest lowest CapEx, highest IRR and quickest payback
• Synergies with nearby Stora Sahavaara and Pellivuoma projects
Fast Track Tapuli
April 2, 2009 7
Tapuli mine• Open cast mine• Minimum operation time 10 years• Verified resource 65 Mton (NI 43-101)• Additional reserves ca 40 Mton• Blasting daytime, ca 1-4 times/week
April 2, 2009 8
Gråbergsupplag
Sandmagasin
1:32 000 (A3)
Temporär sedimenteringsbassäng och översilningsyta
ProcessvattenbassängKaunisvaaraanrikningsverk
Klarningsmagasin
Planned industry layout:•Mine•Mill•Service facilities•Office•Waste rock deposit•Tailings storage facility•Access & transportation roads
April 2, 2009 9
Artists impression of the mine during operation
April 2, 2009 10
Waste rock• A total of 250 Mton will be mined
• May be used for construction purposes
• Area ca 330 ha
• Height ca 75 m
April 2, 2009 11
Anrikningsprocess• Planerad genomsnittlig produktion
År 1: 3 Mton malm, motsvarande ca 1 Mton SligÅr 2-10: 10 Mton malm, motsvarande ca 3 Mton SligAnsökan avser 20 Mton per år
• Process Krossning, malning, magnetseparering, avvattning och möjligen torkningInget flotationssteg
Storage ore
Storage crushedore
Thickeners
Concentratestorage
DewateringMagnetic separatorsGrinding
April 2, 2009 12
Mill tailings storage• Total tonnage c. 70 Mton• Total area c. 340 ha• Final height c. 60 m
ca 2-3 m
April 2, 2009 13
Efterbehandling• Byggnader tas bort och vägar återställs. Ledningar kvar i marken.
• Gråberg täcks med morän och vegeteras. Sandmagasin vegeteras. Gödningsmedel kan behöva tillföras.
• Dagbrottet bildar en sjö
April 2, 2009 14
Transport• Initially truck (60 ton net) to Kolari – rail to Kemi• Extension of railroad to Kaunisvaara being investigated• 290 return transports per day (c. 12 per hour)
April 2, 2009 15
Transloading station alternatives
April 2, 2009 16
Tentative production schedule
01000200030004000500060007000800020
11
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
production year
kt/y
ear
Hannukainen
Sahavaara
Pellivuoma
Tapuli
April 2, 2009 1717
KemiLuleå
Kalix
Narvik
Rail & Port Options
KolariPajala
Existing rail link
April 2, 2009 18
Logistics – Key issues
18
Infrastructure
• Initial transportation Kaunisvaara – Kolari on road • Long term solution Kaunisvaara – Kolari to be railroad• Increase capacity on rail from Kolari region to Tornio up
to 10 Mt• Develop Kemi port initially for 3 Mt and up to 10 Mt in
case Kemi is the only port going forward• Kemi port dredging to enable access by feasible vessels
April 2, 2009 19
Transportation from Kaunisvaara/Tapulito Finnish Rail
19
Infrastructure
• 2011 – 2013 trucking • Rail alternative is studied • Alternative studies on pipeline and conveyor belt in
progress• Future solution operational from 2012/13• Loading station south of Kolari, land available• Rail – Necassary
April 2, 2009 20
Production Timeline Estimate
1-2 Mt/y 3 Mt/y 8-10 Mt/yProduction:
2010
2012
2013 / 2014
• Tapuli – Begin construction
• Tapuli – ramp up production to 1.5Mt Concentrate
• Pellivuoma – begin production of Concentrate
• Tapuli at full production 1.5 Mt Concentrate
• Pellivuoma – ramps up production to 1.5 Mt of Concentrate
• Stora Sahavaara – begin production of 2 Mt of Concentrate
• Hannukainen begins production and ramps up to 2-3 Mt of DR pellet feed
2011
• Tapuli – Begin production of Concentrate
20
Northland’s Future Growth
April 2, 2009 21
Summary NRI projects
• Staged development to build the assets in Sweden and Finland
• Initial cash flow will be the base to increase production and employment
• Joint effort necessary - NO “Finnkamp”• The projects will create employment within
NRI as well as support structures, services etc• Employment will be created in the whole
region – in both countries
April 2, 2009 22
Summary Logistics
• Rail Kaunisvaara – Tornio with capacity + 8 Mt necessary for development of the projects
• Rail from Kaunisvaara to be operational from 2013
• Port development Kemi ready 2011• Dredging Kemi ready 2011/12• Ice breaker capacity must be expanded