GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b)...

14
GEOELEC Project Meeting WP 1 Philippe DUMAS European Geothermal Energy Council Pisa, 7/10/2013

Transcript of GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b)...

Page 1: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

GEOELEC Project Meeting

WP 1

Philippe DUMAS

European Geothermal Energy Council Pisa, 7/10/2013

Page 2: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

Management

• Presentation of project progress: Planning, Deliverables, Reports

• Project monitoring: Indicators

• Advisory Committee: Progress, Composition, Meetings

Page 3: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

Project phase / Duration of

the project (in months)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Work package 1:

Management

Work package 2:

Prospective

Work package 3: Finance

Work package 4:

Regulations & environment

Work package 5: Training &

employment

Work package 6:

Communication

Work package 7: IEE

Dissemination Activities

Project meetings x x x x x x

Project reports to EACI PR IR FRc

Project Information Sheet &

Slides to EACI X X X X

Project Webpage/site

creation and update X

Project deliverables D1.1

D6.4 D1.1

D6.1

D6.4

D6.9

D7.1

D2.1

D2.2

D2.4

D1.1

D3.2

D3.3

D6.4

D1.1

D3.1

D3.4

D3.5

D4.1

D5.3

D5.4

D6.4

D6.5

D2.3

D2.5

D2.6

D4.2

D5.1

D5.2 D1.1

D1.2

D4.3

D4.4

D4.5

D4.6

D6.4

D5.5

D5.6

D6.2

D6.3

D1.1

D6.4

D6.5

D6.6

D6.7

D6.8

D6.9

D7.1

Planning: Project Schedule

October 2013 = month 29

Page 4: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

General Reporting: The reporting scheme is the following: • First Progress report (covering months 1-9): month 10 (march 2012) • Interim project technical and financial report to EC (covering months 1-16): month 17 (october 2012) • Final project technical and financial report to EC (covering months 1-30): month 30-32 (Dec 2013) • Final publishable report in English: month 32 – see WP6

Page 5: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

Finance: Payments: -30 % in June 2011 -ca.30% in March 2013 ! -ca. 40% around March 2014

Cost Statements •Staff costs: -Monthly Timesheet completion and submission -Hourly rate •Travel: receipts, boarding passes, air fare tickets etc. •Subcontracting and Other Specific Costs

Page 6: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

b) Description of the tasks:

1.1. Project Meetings (EGEC)

EGEC invited partners to the kick-off meeting in Brussels ( 20 & 21 June 2011)

and APPA organized the 2nd project meeting on 11/11/11 ; and TNO the 3rd one in

Utrecht (11 & 12 June 2012); BRGM the 4th one in Strasbourg (6/11/2012); GFZ the

5th one in Postdam (16/4/2013).

CNR organizes today the 6th project meeting (7/10/2013).

Page 7: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

1.2. Project reports (EGEC)

EGEC coordinates the managerial and financial reporting.

•First Progress report (covering months 1-9): month 10 > March 2012

•Interim project technical and financial report to EC (covering months 1-16):

month 17 > October 2012: submitted in December 2012, approved in

February 2013, paid in March 2013

•Final project technical and financial report to EC (covering months 1-30):

month 32 > December 2013

•Final publishable report in English: month 32 – see WP6

Page 8: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

1.3. Project monitoring (EGEC)

The consortium monitors the impact of the project through the number of new

geothermal power projects as performance indicators: (see slide: Performance indicators and targets)

> Based on EGEC Deep geothermal market reports

The project has a set of ambitious targets and indicators to measure the impact and

performance of the action. In order to ensure that these indicators are effectively

monitored during the project implementation a monitoring plan had to be

discussed and agreed by the consortium at the Kick-off meeting and reviewed

in each project meeting.

Monitoring plan

A factsheet “Geothermal electricity market” will present the monitoring of the

Geoelec targets.

Page 9: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

1.3. Project monitoring (EGEC)

a monitoring plan

Methodology

Page 10: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

D1.2: Factsheet on Geothermal electricity market (month 7-19-30)

A factsheet “Geothermal electricity market” will present the monitoring of the

Geoelec targets in Dec 2011, Dec 2012, Sept 2013.

Page 11: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

Main Performance indicators and targets within the project duration

• 4 more EU countries with geothermal power plant projects: Czech Rep., Hungary, Spain, UK, Romania, Belgium, Slovakia, Lithuania • Corresponding to 100 MWe new capacity installed: tbc • 10 oil and gas companies and utilities with concrete project ideas to build geothermal plants in Europe: Shell, Statoil, ES, MOL, Eon, PPC res, Sorgenia, ENEL GP, EnBW, Geopetrol, Moore… • 5 new regional/national regulatory frameworks on geothermal electricity: Hungary, Belgium, Italy-regions, UK, NL, … • Minimise opposition from people of neighbouring regions against geothermal power plants: tbd • 50 project developers use the protocol for public acceptance: quid

Page 12: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

Targets beyond the project duration until 2020 Strategic Objective(s) of your proposal Target by 2020:

Help member states in

reaching their national

target of the new RES

Directive

More than 12 EU member states produces

electricity from geothermal energy

The total European installed capacity is more

than 4 GWe in 2020

Obtain the support of the

general public

Environmental impact of geothermal

development is minimized

Public acceptance is not anymore a barrier

Create the necessary

skilled workforce to install

geothermal electricity

plants

3 more countries launch similar training

courses

100 new engineers/technicians are trained

every year

The geothermal sector employs more than 20

000 new workers by 2020

Reduce the costs of

geothermal electricity

production

Have a cost less than 0,10 €/KWh by 2030

Page 13: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

1.4 Advisory committee (EGEC & CRES)

GEOELEC ADVISORY COMMITTEE MEMBERS

Name Affiliation Country email group

1 Gunter Siddiqi SFOE Energy Economy Division Switzerland [email protected] Policy makers

2 Carmen Lopez Ocon IDAE Spain [email protected] Policy makers

3 Alex Richter Thinkgeoenergy Canada [email protected] Developers/Operators/Consultants

4 Santo Bains BP UK [email protected] Developers/Operators/Consultants

5 Rugerro Bertani ENEL Italy [email protected] Developers/Operators/Consultants

6 Paul Younger Glasgow Univ. UK [email protected] Developers/Operators/Consultants

7 Roberto Lacal-Arantegui EC-JRC Institute for Energy in Petten EU [email protected] EC/EEA/JRC

8 Victor Van Heekeren STICHTING PLATFORM GEOTHERMIE Netherlands [email protected], Developers/Operators/Consultants

9 Marcel Rosca University of Oradea Romania [email protected] Developers/Operators/Consultants

10 Fausto Battini Magma energy italia Italy [email protected],

Developers/Operators/Consultants

11 Celestino García de la Noceda

IGME Spain [email protected] Policy makers

12 Peter Seibt GTN Germany [email protected] Developers/Operators/Consultants

13 Paul Ramsak NL Agency Netherlands [email protected] Policy makers 14 Carme Puig IGC Spain [email protected] Policy makers

15 Manuel Fernandez Instituto de Ciencias de la Tierra Jaume Almera - CSIC Spain [email protected] Developers/Operators/Consultants

16 Christian Oeser Ministry of Ecology, Energy, Sustainable Development & Sea France [email protected] Policy makers

17 Philippe Laplaige ADEME France [email protected] Policy makers

Page 14: GEOELEC Project Meeting WP 1N° Managementof work package: 1 Duration in months: 30 EGEC b) Description of the tasks: 1.1. Project Meetings (EGEC) EGEC invited partners to the kick-off

N° of work package: 1 Management

Duration in months: 30 EGEC

IIb. Deliverable(s):

The deliverables of this work are associated with the management of the

project and on-going reporting to the Commission. These are:

D1.1: Minutes of the 6 Project meetings & 3 Advisory Committee

meetings (month 1, 6, 12, 18, 24, 30)

D1.2: Factsheet on Geothermal electricity market (month 7-19-30)