2999 Oak Road Walnut Creek, CA 94597 (925) 256.4700 www.ccta.net Geary Road Reconstruction – Phase 3 PROJECT # 24007 Geary Road links Pleasant Hill Road with Treat Boulevard and serves as the only arterial connection between northwest Walnut Creek and the Pleasant Hill BART station. Currently, left turning vehicles create long queues for through traffic, and pedestrians/bicyclists are forced to use the existing roadway shoulders. This proposed reconstruction is the third and last phase of a corridor improvement project along Geary Road. The purpose of this project is to increase operations and pedestrian/bicycle safety through the construction of continuous dual left-turn lanes and exclusive bike lanes and pedestrian sidewalks. Adjacent segments of Geary Road have already been reconstructed; this improvement provides connectivity and continuity with Phase 1 and Phase 2 constructed by the City of Walnut Creek and Pleasant Hill. Did You Know? The project will be constructed in two phases. Phase 3A will improve pedestrian/bike access and include landscaping and gateway enhancements at the Geary/Pleasant Hill Road Intersection. Phase 3B consists of traffic signal improvements, street lighting, traffic striping, and necessary drainage and pavement improvements. B-91

Transcript of Geary Road Reconstruction – Phase 3 - CCTA · Geary Road Reconstruction – Phase 3 ... Final...

2999 Oak Road Walnut Creek, CA 94597 (925) 256.4700 www.ccta.net

Geary Road Reconstruction – Phase 3 PROJECT # 24007

Geary Road links Pleasant Hill Road with Treat Boulevard and serves as the only arterial connection between northwest Walnut Creek and the Pleasant Hill BART station. Currently, left turning vehicles create long queues for through traffic, and pedestrians/bicyclists are forced to use the existing roadway shoulders. This proposed reconstruction is the third and last phase of a corridor improvement project along Geary Road. The purpose of this project is to increase operations and pedestrian/bicycle safety through the construction of continuous dual left-turn lanes and exclusive bike lanes and pedestrian sidewalks. Adjacent segments of Geary Road have already been reconstructed; this improvement provides connectivity and continuity with Phase 1 and Phase 2 constructed by the City of Walnut Creek and Pleasant Hill.

Did You Know? The project will be constructed in

two phases. Phase 3A will improve

pedestrian/bike access and include

landscaping and gateway

enhancements at the

Geary/Pleasant Hill Road

Intersection.

Phase 3B consists of traffic signal

improvements, street lighting,

traffic striping, and necessary

drainage and pavement

improvements.

B-91

2999 Oak Road Walnut Creek, CA 94597 (925) 256.4700 www.ccta.net

Project Geary Road Improvements – Phase 3 (# 24007)Sponsor City of Pleasant Hill/City of Walnut Creek Subregion Central County March 16, 2016

Scope Reconstruct Geary Road from Putman Boulevard/BuenaVista Avenue to approximately 1,000 feet west ofPleasant Hill Road, add an exclusive 6-foot bike lane,street parking and sidewalks in each direction, andincorporate lighting, drainage, landscaping andirrigation improvements, as well as traffic signalmodifications at Buena Vista Avenue and Pleasant HillRoad, including geometric improvements at thePleasant Hill Road/Geary Road intersection. Phase 3 improvements will be completed in two stages.The first stage eliminates the free right turn ontoPleasant Hill Road (going west) and constructs astandard right turn pocket, a new ADA pedestrianpathway, and new entryway monument signs withenhanced landscaping and pedestrian lighting. Thesecond stage includes the reconstruction of theroadway with new continuous left turn lanes, new bikelanes, new pedestrian sidewalks, landscaping anddecorative lighting between Pleasant Hill Road andPutnam Boulevard.

Status Construction of the first stage was completed in

late 2013. Construction of the second stage was completed in

December 2015. Final landscaping and punch list items to be

completed by Spring 2016.

Issues/Areas of Concern None.

Location

Schedule

Dates Phase 3A Phase 3B

Preliminary Studies/ Planning

Complete Complete

Environmental Clearance Complete CompleteDesign Complete CompleteRight of Way and Utilities Complete CompleteConstruction Complete 2014-2015Landscaping — 2015-2016

AmountPhase 3A Phase 3B

Measure J $470 $9,410HSIP 317 —TDA 53 —Local Funds 289 200Total $1,129 $9,610

Funding by Source ($ 000s)

CONSTRUCTED