GCS - APPENDIX 20 · 2019. 7. 15. · Construction Work Method Statement: Watercourse Crossings 7 |...

19
APPENDIX 20 METHOD STATEMENT

Transcript of GCS - APPENDIX 20 · 2019. 7. 15. · Construction Work Method Statement: Watercourse Crossings 7 |...

  • APPENDIX 20

    METHOD STATEMENT

  • i | P a g e

    Construction Work Method Statement

    Project: Mngeni Shaft

    Activity: Type 1, 2, 3, 4, 5 Watercourse Crossings (Mvalo River, Umfolozi River, Umngeni River and

    various non-perennial streams)

  • ii | P a g e

    Table of Contents

    TABLE OF CONTENTS .............................................................................................................................................. II

    LIST OF APPENDICES .............................................................................................................................................. II

    LIST OF MAPS ......................................................................................................................................................... II

    1 DESCRIPTION OF ACTIVITY .............................................................................................................................. 1

    2 PROGRAMME ................................................................................................................................................. 6

    3 METHODOLOGY .............................................................................................................................................. 6

    3.1 TYPICAL CONSTRUCTION SEQUENCE .......................................................................................................................... 6

    3.2 PLANT AND RESOURCES REQUIRED ........................................................................................................................... 6

    3.3 ENVIRONMENTAL IMPACT MANAGEMENT ................................................................................................................. 7

    3.4 MONITORING AND REVIEW STRATEGY .................................................................................................................... 11

    4 RESPONSIBILITIES AND PRESCRIBED OCCUPATIONS ..................................................................................... 13

    5 DECLARATIONS ............................................................................................................................................. 15

    5.1 DESIGN ENGINEER .............................................................................................................................................. 15

    5.2 SITE MANAGER .................................................................................................................................................. 15

    5.3 ENVIRONMENTAL CONTROL OFFICER ..................................................................................................................... 15

    APPENDICES......................................................................................................................................................... 16

    List of Appendices

    APPENDIX A: ENGINEERING DRAWINGS

    List of Maps

    Map 1: Power Line Crossings............................................................................................................................................ 2

    Map 2: Clean and Dirty Water Pipeline Crossings (ZAC Plant to Mngeni Shaft) ... Error! Bookmark not defined.

    Map 3: Dirty Water Pipelien Crossings ( Mngeni to Ngwabe PCD) ......................... Error! Bookmark not defined.

  • Construction Work Method Statement: Watercourse Crossings

    1 | P a g e

    1 Description of Activity

    The project consists of three pipelines Watercourse crossings through the existing culverts, a new culvert as

    well as one below the stream bed. The first pipeline will be carrying clean water from the existing ZAC Plant

    to the newly proposed Mngeni Adit, the second carrying dirty water from the Mngeni Adit to the ZAC

    Process Plant and the third one carrying dirty water from Mngeni Adit to an existing Pollution Control Dam

    (PCD) at the Ngwabe Shaft.

    The process will involve the excavation of the soil to an approximate depth of 1,500 meters (m), laying of

    the pipe and the subsequent infilling of the trench. The

    The project also includes the installation of electricity power lines that will traverse from the substation at

    ZAC offices, across the Mvalo River, across various non-perennial streams and across Umfolozi River to

    Umngeni Adit. This will involve digging approximately to a depth of a 1.2m for the wooden poles to be

    installed on the ground and carry electricity wiring above ground. The poles will be in pairs along the

    longest sections of Umvalo River as well as Umfolozi river crossings.

    A new access road will also be constructed across a non-perennial stream that is a tributary of the Black

    Umfolozi River.

    The pipelines cross a total of 7 watercourses with extent and localities indicated in Map 2. Start and end

    coordinates are summarized in Table 1.

    The crossings are categorized as follows (refer Maps 1 to 3):

    Type 1: Applicable where the pipeline crosses the watercourse attached to an existing culvert/bridge with

    minimal disturbance to the watercourse or wetland

    Type 2: Applicable where the pipeline crosses the watercourse attached to a new culvert with minimal

    disturbance to the watercourse or wetland

    Type 3: Pipeline crosses the watercourse below the ground/river bed, with minor environmental impacts

    during construction only.

    Type 4: Powerline crossings where the power line crosses the watercourse or wetland above ground with

    no significant impact on the environment except during construction particularly for the poles that will have

    to be unavoidable installed within the wetland or watercourse. All effort will be made to ensure all the

    powerline poles are positioned outside the sensitive areas like watercourse or wetlands, but where this

    cannot be avoided, measures will be taken to ensure the poles have minimal impact on the watercourse.

    Type 5: Applicable where the access road crosses a non-perennial watercourse with minimal disturbance

    to the watercourse or wetland during construction.

    This Work Method Statement pertains to all the above mentioned pipeline and power line crossings.

  • Construction Work Method Statement: Watercourse Crossings

    2 | P a g e

    Map 1: Powerline crossings

    Map 2: Clean & Dirty Water pipeline crossings

  • Construction Work Method Statement: Watercourse Crossings

    3 | P a g e

    Map 3: Dirty Water pipeline Crossings from Mngeni to ZAC Plant

    Map 4: Road Crossings

  • Construction Work Method Statement: Watercourse Crossings

    4 | P a g e

    Table 1: Schedule of Crossings

    Type of Crossing Crossing Name Crossing type River Type Material Type Start Coordinates End Coordinates

    Powerline Mvalo crossing Type 4 Perennial Stream

    Wooden Electricity Pole 28013'19.94"S 31040'52.06"E

    28013'18.66"S 31040'53.73"E

    Powerline Existing Culvert1 Type 4 Non-perennial Stream

    Wooden Electricity Pole 28013'01.29"S 31041'18.07"E

    28012'59.80"S 31041'19.49"E

    Powerline Stream Crossing 1 Type 4 Non-perennial Stream

    Wooden Electricity Pole 28012'51.75"S 31041'27.49"E

    28012'50.08"S 31041'28.65"E

    Powerline Existing Culvert 2 Type 4 Non-perennial Stream

    Wooden Electricity Pole 28012'24.95"S 31041'48.33"E

    28012'24.17"S 31041'50.34"E

    Powerline Umfolozi River Bridge Type 4 Perennial Stream

    Wooden Electricity Pole 28011'11.87"S 31043'01.02"E

    28011'10.26"S 31043'02.97"E

    Powerline Proposed Culvert 3 - Access Road

    Type 4 Non-perennial Stream

    Wooden Electricity Pole 28011'06.71"S 31043'08.44"E

    28011'07.15"S 31043'10.58"E

    Access Road Proposed Culvert 3 Type 5 Non-perennial Stream

    Concrete Culvert Pipes 28011'07.12"S 31043'9.22"E

    Clean Water Pipeline Existing Culvert1 Type 1 Non-perennial Stream

    HDPE Pipe in PVC Sleeve

    28011'10.94"S 31043'01.76"E

    Clean Water Pipeline Stream Crossing 1 Type 1 Non-perennial Stream

    HDPE Pipe Encased in Concrete

    28012'24.30"S 31041'48.99"E

    Clean Water Pipeline Existing Culvert 2 Type 1 Non-perennial Stream

    HDPE Pipe in PVC

    Sleeve

    28012'51.31"S 31041'27.82"E

    Clean Water Pipeline Umfolozi River Bridge Type 1 Perennial Stream

    HDPE Pipe in PVC

    Sleeve

    28012'59.41"S 31041'17.68"E

    Clean Water Pipeline Proposed Culvert 3 - Access Road

    Type 2 Non-perennial Stream

    HDPE Pipe in PVC Sleeve

    28010'46.58"S 31042'51.79"E

    Dirty Water Pipeline 1 Existing Culvert1 Type 1 Non-perennial Stream

    HDPE Pipe in PVC Sleeve

    28011'10.94"S 31043'01.76"E

    Dirty Water Pipeline 1 Stream Crossing 1 Type 3 Non-perennial Stream

    HDPE Pipe Encased in Concrete

    28012'24.30"S 31041'48.99"E

  • Construction Work Method Statement: Watercourse Crossings

    5 | P a g e

    Dirty Water Pipeline 1 Existing Culvert 2 Type 1 Non-perennial Stream

    HDPE Pipe in PVC

    Sleeve

    28012'51.31"S 31041'27.82"E

    Dirty Water Pipeline 1 Umfolozi River Bridge Type 1 Perennial Stream

    HDPE Pipe in PVC

    Sleeve

    28012'59.41"S 31041'17.68"E

    Dirty Water Pipeline 2 Mngeni River Type 1 Perennial Stream

    HDPE Pipe in PVC

    Sleeve

    28010'46.58"S 31042'51.79"E

  • Construction Work Method Statement: Watercourse Crossings

    6 | P a g e

    2 Programme

    The start and closure dates for construction activities will be confirmed after the issuance of a Water Use

    Licence.

    3 Methodology

    Works will be carried out in compliance with the design drawings and the environmental management

    reports and in accordance with the following Work Method Statement (WMS):

    The WMS will be brought to the attention of all persons associated with the undertaking of these

    activities and such measures as necessary will be taken to bind such persons to the requirements

    herein.

    A copy of the WMS and all the relevant documents will be available on site at all times.

    3.1 Typical construction sequence

    A typical construction sequence is summarized below:

    Conduct a comprehensive site investigation to build up an informed picture of the task.

    Conduct a topographical survey of the area to be crossed and the pipeline routes.

    Provide construction drawings for all the stages of construction.

    Excavate to the trenches in accordance with the approved pipeline route

    Lay the pipes and backfill and compact the trenches in accordance with the engineering

    drawings

    Clean and rehabilitate the construction area

    All Environmental and Health and Safety requirements and good practice to be adhered to.

    3.2 Plant and resources required

    The plant and resources required for the construction of the watercourse crossings will include, inter alia:

    Dozer for clearing of the area affected by the crossing including clearing of vegetation and

    stockpiling of topsoil for future top soiling and grassing of new road batters.

    Excavators.

    Crane of sufficient lifting capacity and reach for pipe laying of precast concrete pipes.

    Tipper trucks for the delivery of bedding material and road fill material to be placed over the

    pipes.

    Small Compaction equipment for pipe bedding and restricted fill around the pipe culvert.

    Heavy compaction equipment for compaction of the bulk fill for the road prism.

    On-site concrete batching plant for the concrete apron slabs for the pipe culvert.

    Concrete delivery vehicles for wet concrete.

    Formwork, reinforcing steel and the necessary equipment and tools for assembly.

    Equipment for the construction of the brick headwalls as detailed.

    Equipment and labour for the positioning and packing of gabion and reno-mattress baskets or

    stone pitching, as appropriate and as agreed with the Environmental Consultant, to control and

    obviate any erosion.

    Light equipment and labour to dress backfill, topsoil and re-vegetate all exposed areas.

    Road building equipment for the construction of road layers over the road prism (Fill) once it has

    been successfully placed and compacted to a predetermined level above the overt of the pipe

    culvert.

    Equipment for this final operation will include tippers, graders, rollers as well as necessary

    equipment for kerb laying and ultimately prime applicators and premix pavement laying

    equipment.

  • Construction Work Method Statement: Watercourse Crossings

    7 | P a g e

    3.3 Construction method for pipes laid in trenches

    This method will be used where pipes are conventionally laid in trenches and backfilled to natural ground

    level.

    Remove topsoil and stockpile for later use.

    Excavate trench for pipeline to the design level.

    If the material is firm, normal excavation techniques will apply. In soft material shoring of the trench

    sides may be required. In hard rock material trench excavation may require the use of pneumatic

    breakers or blasting.

    Install temporary dewatering pumps to keep the excavation dry (if required due to groundwater

    ingress).

    Construct storm water diversion berms where required.

    Place concrete encasement if required. The top level will be determined by the storm water

    channel level.

    Place bedding, lay pipe, place and compact selected fill over the pipeline.

    Construct manholes, where required. Manholes will be constructed along the pipeline route at

    changes in grade and direction.

    Backfill to specification.

    Dress backfill, topsoil and re-vegetate all exposed areas.

    Table 2: Schedule of Drawings (Refer Appendix A)

    Description Plan Number Date

    Umfolozi Bridge crossing ME-ZAC-010 April 2019

    Mngeni River Bridge Crossing ME-ZAC-011 April 2019

    Crossing over Culvert Bridge No1 ME-ZAC-011 April 2019

    Crossing over Culvert Bridge No2 ME-ZAC-011 April 2019

    Crossing over Culvert Bridge No3 ME-ZAC-011 April 2019

    Environmental Management Strategy

    3.3 Environmental Impact Management

    Changes and impacts to hydrology at landscape level; alteration of stream flow; increased erosion and

    deterioration of water quality (turbidity) are addressed in the design of the road and watercourse crossings

    (refer to design drawings set out in Table 3) by the incorporation of sound environmental design principles

    as set out in the Brief Report. Integrated Water Licence Application for the proposed Mngeni Shaft Project.

    Nevertheless, certain activities and aspects associated with the actual construction of the road according

    to these designs may still cause impacts as a result of how these activities are undertaken, where, when

    and the duration thereof. These include:

    Clearing of the road footprint (including extending activities beyond the maximum impact foot print)

    Establishment and management of the construction camp/s

    Management of construction materials (movement, storage, preparation/handling)

    Management of machinery (movement, storage, maintenance)

    Management of sanitation and waste (movement, storage)

    Management of storm water

    Management of sediment (structures and containment)

    Rehabilitation

  • Construction Work Method Statement: Watercourse Crossings

    8 | P a g e

    Possible impacts associated with these activities are listed in Table 5 below along with environmental

    significance ratings pre and post mitigation (i.e. indicating effectiveness of the mitigation measures set out

    in Table 6).

    Table 3: Impacts and Significance Ratings

    Impact Environmental Significance

    Before Mitigation After Mitigation

    Alteration of flow regimes, including but not limited to:

    Concentrated flows Moderate Low

    Temporary river diversions Moderate Low

    Deterioration of water quality (mainly turbidity), including but not limited to:

    Sedimentation High Moderate

    Accidental spills (hydrocarbons, other hazardous

    chemicals) Low Low

    Contamination via stormwater runoff Moderate Low

    Disturbance of riparian an instream habitat (i.e. changes to the physical structure of the watercourses as well as

    vegetation), including but not limited to:

    ~ Erosion Moderate Low

    ~ Soil compaction Moderate Low

    ~ Damage to vegetation Moderate Moderate

    ~ Alien species establishment Moderate Low

    The measures to manage the above impacts as derived from the documents set out in Table 4 are

    presented in Table 6.

  • Construction Work Method Statement: Watercourse Crossings

    9 | P a g e

    Table 4: Mitigation Measures

    Impact Measures (What and Where) When, Duration Responsibility Uncertainties

    General (relevant to all impacts) Environmental awareness training must

    be provided for all contractors and

    workers, appropriate to the activity and

    addressing the mitigation measures

    contained in the documents listed in

    Table 4 as well as in this work method

    statement

    Before construction

    commences ECO None

    A maximum impact footprint (15m width

    along the routing of the road) must be

    appropriately delineated and sign

    posted

    Before construction

    commences Contractor None

    Sensitive areas not within the impact

    footprint must be clearly demarcated

    and sign posted “No Go”

    Before construction

    commences

    Contractor

    ECO

    Wetland Specialist

    None

    Construction activities shall begin

    upstream and proceed downstream

    Ongoing (duration of

    construction phase) Contractor None

    Construction camps shall be located

    outside the extent of any watercourse

    and must be recovered and removed

    shortly after construction has been

    completed

    Ongoing

    (Removal within 3

    weeks of completion of

    construction)

    Contractor None

    Machinery and equipment must be kept

    in good working order

    Ongoing (duration of

    construction phase) Contractor None

    Alteration of flow regimes

    Concentrated flows

    Temporary river diversions

    Downstream flows must be maintained

    during construction of crossings

    Ongoing (duration of

    construction phase) Contractor None

    Temporary instream diversions must allow

    for adequate flow and a dry works area

    must be maintained – diversions must be

    located within the active channel and

    may not breach the historical terraces

    Duration of crossing

    construction

    Contractor None

    Deterioration of water quality (mainly

    turbidity), including but not limited to:

    Sedimentation

    Accidental spills (hydrocarbons,

    other hazardous chemicals)

    Contamination via stormwater

    runoff

    Standard best environmental practice

    housekeeping rules must be applied with

    regards to refuse management,

    ablutions, fire prevention etc.)

    Ongoing (duration of

    construction and

    Operational phase)

    ECO

    Contractor

    None

    Storage, washing and maintenance of

    equipment and machinery must be

    undertaken outside the extent of any

    watercourse and only in demarcated

    areas where runoff and spills are

    managed in an environmental sound

    manner

    Ongoing (duration of

    construction phase)

    Contractor None

  • Construction Work Method Statement: Watercourse Crossings

    10 | P a g e

    Impact Measures (What and Where) When, Duration Responsibility Uncertainties

    Sanitation and waste management

    facilities must be located outside of the

    extent of a watercourse and must be

    managed in an environmental sound

    manner

    Ongoing (duration of

    construction phase)

    Contractor None

    Materials must be stored outside the

    extent of any watercourse, and

    transported and prepared/handled in an

    environmentally sound manner, in

    compliance with relevant legislation -

    discharges into watercourses must be

    prevented as far as reasonably possible

    and stockpiles must be protected from

    erosion

    Ongoing (duration of

    construction phase)

    Contractor None

    An emergency plan (i.e. measures for

    prevention, detection, management and

    reporting) must be prepared for dealing

    with accidental spills and leaks in

    compliance with relevant legislation and

    regulations

    Ongoing (duration of

    construction phase)

    ECO

    Environmental

    Superintendent

    None

    Sediment traps and fencing must be

    utilised to prevent excess levels of

    sediments entering watercourses from

    work areas and afterwards disposed of in

    a lawful manner

    Ongoing (duration of

    construction phase)

    Contractor None

    Berms or porous structures?

    Contamination of stormwater runoff must

    be prevented

    Ongoing (duration of

    construction phase)

    Contractor None

    Stormwater must be diverted into

    vegetated buffer zones and not directly

    into surface water – concentrated flows

    must be prevented and velocities may

    not exceed 0.5m/s

    Ongoing (duration of

    construction phase)

    Contractor None

    Trench breakers?

    Disturbance of riparian an instream

    habitat (i.e. changes to the physical

    structure of the watercourses as well as

    vegetation), including but not limited to:

    ~ Erosion ~ Soil compaction ~ Damage to vegetation ~ Alien species establishment

    Vegetation must not be cleared beyond

    the impact footprint (it is recognised that

    loss of habitat within this footprint is

    inevitable)

    Ongoing (duration of

    construction phase)

    Contractor None

    The breeding, nesting and feeding

    habitats and natural movement patterns

    of aquatic biota within and along the

    impact foot print of the road must be

    identified and demarcated and all

    reasonable measures must be taken not

    to disturb these

    Before construction

    commences

    Ongoing (duration of

    construction phase)

    Contractor

    ECO

    Wetland Specialist

    None

  • Construction Work Method Statement: Watercourse Crossings

    11 | P a g e

    Impact Measures (What and Where) When, Duration Responsibility Uncertainties

    Equipment and machinery must only be

    operated within the delineated impact

    footprint

    Ongoing (duration of

    construction phase)

    Contractor None

    Mechanical vibrations must be minimised

    in the vicinity of stream banks

    Ongoing (duration of

    construction phase)

    Contractor None

    Dust must be suppressed in the vicinity of

    sensitive areas

    Ongoing (duration of

    construction phase)

    Contractor None

    Slope and bank stabilisation measures

    must be implemented where appropriate

    Ongoing (duration of

    construction phase)

    Contractor None

    Rehabilitation of work areas must

    commence immediately after

    construction is completed of designated

    work packages (i.e. crossings, refer Table

    2) – refer CEMP, P10)

    Refer construction

    programme

    Contractor None

    Gravel removed during construction must

    be replaced with similar consistency and

    diameter after construction is completed

    of designated work packages

    Refer construction

    programme

    Contractor None

    Soils that become compacted must be

    loosened to an appropriate depth to

    allow for seed germination once

    construction activities are completed (i.e.

    crossings, refer Table 2)

    Refer construction

    programme

    Contractor None

    Disturbed areas must be re-vegetated

    with only indigenous vegetation

    Refer construction

    programme

    Contractor None

    Alien vegetation recruitment must be

    eradicated and controlled using

    standard methods approved by DWA

    Ongoing (lifetime of

    road)

    Contractor None

    3.4 Monitoring and Review Strategy

    Monitoring and reporting will be undertaken as set out in the reports listed in Table 4. Specific provisions are set out in Table 5 below. Steps for non-

    compliance with this method statement is set out on P29-30 of the CEMP.

    Table 5: Monitoring and Review Measures

    What Where When Responsibility Reporting Requirements

    Benthic diatoms Crossings with flowing water During the wet and dry season Aquatic Specialist National Water Act

    Invertebrates Crossings with flowing water During the wet and dry season Aquatic Specialist National Water Act

    Fish Crossings with flowing water During the wet and dry season Aquatic Specialist National Water Act

    Alien Vegetation All sites Quarterly in a year ECO National Water Act/NEMA

    Turbidity Crossings with flowing water;

    10m downstream

    1st measurement, before

    construction commences, 2nd

    not later than 3hrs after

    ECO

    National Water Act

  • Construction Work Method Statement: Watercourse Crossings

    12 | P a g e

    What Where When Responsibility Reporting Requirements

    activities commenced

    Habitat All sites Prior to and post construction ECO NEMA Closure cost assessment

    Wetland crossings Prior to and post construction Wetland specialist Refer WUL, P7 and 8

    Emergency and pollution

    incidents1

    All sites At all times Contractor

    ECO

    Section 19 and 20 of the

    National Water Act

  • Construction Work Method Statement: Watercourse Crossings

    13 | P a g e

    4 Responsibilities and Prescribed Occupations

    Occupation Role/Responsibility

    Project Engineer (PE) Ensure that the proposed design of the structures takes into

    consideration the location and existing environmental conditions at

    the site.

    Ensure that all facets of environmental protection are properly

    addressed during the design.

    Project Manager (PM) Appoint appropriately qualified contractors to co-ordinate, supervise and

    expedite different tasks.

    [Note: Appointment of contractors will be subject to scrutiny and final approval

    of the Project Engineer as will numerous other facets of the work undertaken on

    site i.e. the PM will not act alone or independently of the Project Engineer in this

    regard.]

    Ensure adherence to any laws and standards relevant to the

    construction of the facility.

    Ensure all facets of the work undertaken are properly and competently

    directed, guided and executed.

    Ensure adherence to statutory safety, health and environment (SHE)

    standards and ensuring the construction activities comply with the

    EMP.

    Overall responsibility and accountability for the site during the

    construction phase.

    Construction of the facility to contractual specifications.

    Contractors and Sub-

    Contractors

    Manage and operate their activities with due care and diligence.

    Comply with the requirements of the EMP.

    Avoid and/or limit any adverse impacts they may have on the

    environment by the proper design and construction of the proposed

    development.

    Report back to the PM on issues / non-conformances.

    Control predicted impacts that may occur so as to meet acceptable

    standards, both as a legal and a moral responsibility to the

    environment within which they operate.

    Ensure transparency in their operation and environmental

    management of the site.

    Ensure that all facets of the work undertaken are properly and

    competently directed, guided and executed during construction.

    Ensure construction of the facility is to contractual specifications.

    Ensure adherence to laws and standards relevant to the construction

    of the facility.

    Ensure adherence to statutory SHE standards during construction and

    ensuring the construction activities comply with the EMP. Any new or

    amendments to existing mitigation measures to address areas of

    concern notified by the EM are to be acted on as necessary by the

    contractor.

    Environmental

    Manager (EM)

    Determination of the conformance of the site with the EMP criteria and

    compliance with the DAEA conditions of authorization.

    Liaison person with the DAEA, ECA and IAPs, if required.

    Identification of possible areas of improvement.

    Assessment of the suitability or effectiveness of the EMP.

    Undertake ongoing monitoring of the site through regular site visits and

    record key findings. This includes photographic monitoring.

    Monitor implementation of the EMP by the contractor/s.

    Advise the PM on actions or issues impacting on the environment and

    provide appropriate recommendations to address and rectify these

  • Construction Work Method Statement: Watercourse Crossings

    14 | P a g e

    matters.

    Ensure that the contractor/s has a copy of the EMP and all agreed

    Method Statements.

    Ensure that the conditions stipulated in the DAEA conditions of

    authorization and any other laws and standards relevant to the project

    are being complied with.

    Update and revise the EMP as necessary in liaison with IAPs and other

    affected parties and authorities as required.

    The EM shall advise the PM to suspend part or all of the works if the

    contractor and/or any sub-Contractor, suppliers, etc. fail to comply

    with both the EMP and establishment procedures supplied (which are

    to be agreed upon between the contractor and PM prior to

    construction).

    Environmental

    Compliance Auditor

    (ECA)

    A suitably qualified and experienced independent environmental

    consultant/auditor to undertake audits of construction activities to

    ensure compliance with this EMP, the environmental authorization and

    any other relevant legislation.

    Submission of audit reports to the DEAT and DAEA.

    Advise the EM, PM and/or ZAC on actions or issues impacting on the

    environment and provide appropriate recommendations to address

    and rectify these matters.

    Assess suitability of the EMP’s effectiveness and identify possible areas

    of improvement.

    Health and Safety

    Officer (HSO)

    Provide support to the EM in monitoring the execution of the EMP by

    maintaining a presence on the site.

    Undertake routine site inspections and provide information to EM.

    Monitoring activities as specified by the EM.

    Maintain incident register and report back at monthly meetings.

  • Construction Work Method Statement: Watercourse Crossings

    15 | P a g e

    5 Declarations

    5.1 Design Engineer

    The work described in this Work Method Statement, if carried out according to the methodology described,

    is satisfactorily mitigated to prevent avoidable environmental harm.

    Signed Print Name

    Date

    5.2 Site Manager

    I understand the contents of the Work Method Statement and the scope of works required from me.

    Signed Print Name

    Date

    5.3 Environmental Control Officer

    The works described in this Work Method Statement are approved.

    Signed Print Name

    Date

  • Construction Work Method Statement: Watercourse Crossings

    Appendices

    APPENDIX A: CONSTRUCTION DRAWINGS

    APPENDIX B: WATER USE LICENCE

    APPENDIX C: BRIEF REPORT. INTEGRATED WATER LICENCE APPLICATION FOR THE MNGENI ADIT PROJECT

    APPENDIX D: ENVIRONMENTAL MANAGEMENT PLAN FOR THE MNGENI ADIT PROJECT

    APPENDIX E: SPECIALIST STUDY. IMPACTS OF STREAM CROSSINGS ON AQUATIC ECOSYSTEMS AND

    AQUATIC MONITORING PLAN

    APPENDIX F: PROJECT [ADD]. DRAFT CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN

    Appendix 20.pdf (p.1)Work Method Statement GB.pdf (p.2-19)