PROGRAM PROCESSES
V2.0 - 2019
Program Processes
2 of 18
Program Processes
3 of 18
CONTENTS
1. PROJECT PROCESS ................................................................................................ 5
1.1. PROJECT REGISTRATION .......................................................................... 5
1.1.1. Initial Submission and Completeness Check ............................... 5
1.1.2. Call for Inputs for Global Stakeholder Consultation ..................... 5
1.1.3. Project Verification ........................................................................ 7
1.1.4. Submission of Request for Registration and Review ................... 7
1.2. ACR ISSUANCE PROCESS.......................................................................... 9
1.2.1. Initial Submission and Completeness Check ............................... 9
1.2.2. Emission Reduction Verification ................................................... 10
1.2.3. Submission of Request for Issuance and Review ........................ 10
2. BASELINE AND MONITORING METHODOLOGY DEVELOPMENT ..................... 14
2.1. SCREENING MITIGATION OPPORTUNITIES ............................................. 14
2.1.1. Applicability of Standardized Methodologies ................................ 14
2.1.2. Emission Reduction Potential and Environmental Integrity .......... 14
2.1.3. Replicability ................................................................................... 14
2.1.4. Data/ Information Availability ........................................................ 14
2.2. DEVELOPMENT OF METHODOLOGY ........................................................ 14
2.3. STEERING COMMITTEE APPROVAL.......................................................... 16
2.4. METHODOLOGY REVISION......................................................................... 16
2.4.1. Policy Revisions ............................................................................ 16
2.4.2. Program Revisions ........................................................................ 16
2.4.3. Grace Period ................................................................................. 16
Program Processes
4 of 18
ACRONYMS
CAR Climate Action Reserve
CDM Clean Development Mechanism
GHG Greenhouse Gas
GORD Gulf Organisation for Research and Development
GCC Global Carbon Council
GS Gold Standard
GSC Global Stakeholder Consultation
VCS Verified Carbon Standard
Program Processes
5 of 18
1. PROJECT PROCESS
1. For GCC Program, a third-party independent external verification of project documentation
is required to be conducted by GCC Verifiers before two stages in the GCC Project cycle.
The two stages are:
(a) GCC Project Registration Stage; and
(b) GCC ACR Issuance Stage.
1.1. PROJECT REGISTRATION
1.1.1. Initial Submission and Completeness Check
2. Project owners shall prepare the Project Submission Form (PSF) for the project activity,
after conducting local stakeholder consultation.
3. Project owners shall submit, via online IT-platform of GCC (https://www.gctprojects.qa/),
the project documentation required for conducting Global stakeholder consultation (GSC)
of the project as per the requirements of ‘Project Standard’ requiring submission of:
(a) Completed Project Submission Form (PSF) as per the latest template of GCC;
(b) Emission reduction calculation spread sheets required as per the approved baseline
and monitoring methodology;
(c) Investment Analysis spread sheets (if mentioned in the PSF);
(d) Other relevant documents as required.
4. The completeness check of the submission (including completeness and consistency of
documents as well as project´s preliminary eligibility under GCC program) by GCC
Operations Team is conducted within 5 days1.
5. A project activity is considered “submitted” when all of the appropriate forms are deemed
complete and submitted through the GCC website and a unique reference ‘submission
number’ (following format of ‘SXXX’) is assigned to the project activity.
6. Projects must be submitted before the start date of the project which is defined as the date
when the project starts to reduce or avoid GHG emissions.
7. While assessing the submission for its preliminary eligibility and completeness, the GCC
Operations Team may request the project owner for additional information, or revision of
the submission.
8. Upon receiving re-submission, the completeness check and eligibility check is again
performed and only completed submissions are uploaded on GCC website, except those
documents which are requested to be kept confidential by project owners.
1.1.2. Call for Inputs for Global Stakeholder Consultation
9. Once the submitted project documentation is deemed complete, GCC Operations Team
shall make it available on GCC website for Global Stakeholder Consultation (GSC) for 15
calendar days and invite comments from stakeholders.
1 ‘days’ mean ‘calendar days’
Program Processes
6 of 18
Figure 1: Flow chart for Project submission and Registration process
Program Processes
7 of 18
10. While uploading the complete documentation, the inputs are invited from the stakeholders
globally. The inputs can be about any technical, social, environmental, economic,
regulatory and policy aspects related to the submitted project activity.
1.1.3. Project Verification
11. A GCC-approved verifier is appointed by project owner.
12. After the end of GSC period, the GCC verifier shall conduct verification and review the
project submission documentation and comments obtained during GSC process, perform
a site visit (where necessary), raise non-conformities and invite the corrective actions from
project owners (if applicable).
13. Upon successful closure of non- conformities, the GCC verifier shall verify that the project
has fully complied with the information provided in the project submission document as
required by GCC Rules including Verification Standard.
14. The verifier shall then submit a Project Verification Report using Project Verification Report
Form to GCC.
15. The GCC Verifier’s Verification Report may either recommend the GCC Steering
Committee to ‘register’ or ‘not-register’ the project activity.
16. If the GCC Verifier’s Verification Report recommends the GCC Steering Committee to
‘not-register’ the project activity, the request for registration cannot be submitted.
17. If the project does not meet GCC rules even after raising corrective actions within a period
of 2 years, the verifier shall communicate to GCC accordingly.
1.1.4. Submission of Request for Registration and Review
18. Project owners shall submit, via online IT-platform, the project documentation required for
registration of the project with GCC Program as per the requirements of ‘Project Standard’
including:
(a) Verified Project Submission Form (PSF) as per the latest template of GCC;
(b) Verified Emission reduction calculation spread sheets required as per the approved
baseline and monitoring methodology;
(c) Verified Investment Analysis spread sheets (if mentioned in the PSF);
(d) Other relevant verified documents as required;
(e) Proof of payment of USD 500 as registration fee; and
(f) GCC Verifier’s Project Verification Report (PVR), as per the latest template of GCC,
recommending the GCC Steering Committee to ‘register’ the project activity.
19. The completeness check of the submission is conducted within 5 days and the submission
is assessed by GCC Operations Team to check completeness, consistency of documents,
and project´s eligibility under GCC program.
20. A ‘request for registration’ of a project activity is considered “submitted” when all of the
appropriate forms have been deemed complete and submitted through the GCC website
and the registration fee is received by GCC Program.
Program Processes
8 of 18
21. While assessing the submission for its eligibility and completeness, the GCC Operations
Team may request the project owner for additional information, or revision of the
submission.
22. Upon receiving submission, the completeness check and eligibility check is again
performed and only completed submissions are uploaded on GCC website, except those
documents which are requested to be kept confidential by project owners.
23. After the submission is deemed complete, the GCC Operations team shall conduct
detailed assessment of the project activity within 10 days.
24. In case, the project documentation meets all requirements of the GCC Program including
Project Standard and applicable Baseline & Monitoring Methodology, GCC Operations
Team shall prepare a ‘recommendation’.
25. In case the recommendation of the GCC Operations Team and that of the GCC Verifier is
matching/coinciding and in the same direction, which can be to ‘register’ the project
activity, a notification is sent to the Steering Committee informing them of the ‘Automatic
Registration’ of the project activity, unless three members of Steering Committee submit
objections, within 10 days.
26. In case the recommendation of the GCC Operations Team and that of the GCC Verifier is
not matching/coinciding i.e. either to ‘register’ or ‘not-register’ the project activity or more
than 50% of the members of Steering Committee have submitted objections to the
‘automatic registration notification’, within 10 days; the GCC Operations Team shall place
the particular project case for Steering Committee’s consideration and decision, either
through electronic means or in a physical meeting.
27. Once a particular project case has been placed under the consideration of the Steering
Committee, the GCC Operations Team shall appoint Steering Committee member for
his/her assessment and recommendation.
28. The Steering Committee member shall conduct the assessment and provide its
recommendation, within 10 days, which can be either to ‘register’ or ‘not-register’ the
project activity.
‘Decision Criteria’ for Project Registration
S.No. GCC Verifier Report
GCC Operations Team
Recommendation
Steering Committee Member
Recommendation
Steering Committee Decision
Final Decision
1 Register Register - - Register the Project
2 Register Do-not-Register Register Decision by Steering
Committee
Decision by Steering
Committee
3 Register Do-not-Register Do-not-Register Do-not-Register
Do-not-Register the Project
Program Processes
9 of 18
29. After considering Steering Committee member’s inputs, GCC Operations Team shall
submit the ‘Summary Note’, containing the short summary of all the three
recommendations and a final recommendation, for Steering Committee’s consideration
through electronic means.
30. Each Steering Committee member shall consider the ‘Summary Note’ and provide their
individual decision to GCC Operations Team within 10 days, taking into account the
‘Decision Criteria’ (given above) and inform the GCC Operations Team. If the Steering
Committee member does not provide any response or communicate its decision within
allotted time, it will mean that the member is in agreement with the recommendation in the
‘Summary Note’.
31. The final decision shall be made based on by consensus or majority vote (more than 50%).
In case of a tie during voting, the recommendation of GCC Operations Team shall be
considered as final.
32. The decision to Register the project or not shall be made available transparently by the
GCC Operations Team on GCC website within 3 days.
33. The GCC Operations Team shall coordinate with the IHS Markit’s team to inform them of
the decision to Register the project activity and transfer the Registered project documents
to IHS Markit Website within 3 days. After this stage, all the subsequent project
documents shall be submitted directly on IHS Markit website.
1.2. ACR ISSUANCE PROCESS
1.2.1. Initial Submission and Completeness Check
34. Project owners shall implement and operate the project and measure and monitor the
required parameters as per the requirements and as mentioned in the registered project
documentation including the PSF.
35. For the chosen monitoring period, the Project owners shall and prepare the Project
Monitoring Report (PMR), as per the latest template. The Project Monitoring Report (PMR)
will need to be submitted to GCC Program so as to enable the GCC Verifier to start
Emission Reduction Verification of the project activity.
36. Project owners shall submit, via online IT-platform of IHS Markit, the project
documentation prior to starting Emission Reduction Verification as per the requirements
of ‘Verification Standard’ requiring submission of:
(a) Project Monitoring Report (PMR) as per the latest template of GCC, for the chosen
monitoring period;
(b) Emission reduction calculation spread sheets, which shall contain actual achieved
emission reductions, its calculations, measured and monitored parameters and the
data, for the chosen monitoring period; and
Program Processes
10 of 18
(c) Other relevant documents as required.
37. The completeness check of the submission is conducted within 5 days and the submission
is assessed by GCC Operations Team to check completeness, consistency of documents
and project´s eligibility under GCC program.
38. A project activity is considered “submitted” when all of the appropriate forms have been
deemed complete and submitted through the GCC website and a unique reference
‘submission number’ (such as ‘MXXX’) is assigned to the chosen monitoring period of the
project activity.
39. While assessing the submission for its eligibility and completeness, the GCC Operations
Team may request the project owner for additional information, or revision of the
submission.
40. Upon receiving re-submission, the completeness check and eligibility check is again
performed and only completed submissions are uploaded on GCC webpage of IHS Markit
website, except those documents which are requested to be kept confidential by project
owners.
1.2.2. Emission Reduction Verification
41. A GCC-approved verifier is appointed by project owner.
42. After the Project Monitoring Report (PMR) for the chosen monitoring period is available
on the GCC webpage of IHS Markit website, the GCC verifier shall conduct verification
and review the submitted project documentation, by performing a site visit, raising non-
conformities and inviting the corrective actions from project owners (if applicable).
43. Upon successful closure of non- conformities, the GCC verifier shall verify that the project
has fully complied with the information provided in the project submission document as
required by GCC Rules including Verification Standard.
44. The verifier shall then submit an Emission Reduction Verification Report by completing
Emission Reduction Verification Report Form to GCC.
45. The GCC Verifier’s Verification Report may either recommend the GCC Steering
Committee to ‘issue ACRs’ or ‘not- issue ACRs’ to the project activity, for the chosen
monitoring period.
46. If the GCC Verifier’s Verification Report recommends the GCC Steering Committee to
‘not-issue ACRs’ to the project activity, the request for issuance cannot be submitted.
47. If the project does not meet GCC rules even after raising corrective actions within a period
of 2 years, the verifier shall communicate to GCC accordingly.
1.2.3. Submission of Request for Issuance and Review
48. Project owners shall submit, via online IT-platform of IHS Markit, the project
documentation required for issuance of ACRs to the project activity, for the verified
monitoring period, as per the requirements of ‘Verification Standard’ requiring submission
of:
(a) Verified Project Monitoring Report (PMR) as per the latest template of GCC, for the
verified monitoring period;
Program Processes
11 of 18
Figure 2: Flow chart for ACR Issuance process
Program Processes
12 of 18
(b) Emission reduction calculation spread sheets, which shall contain actual achieved
emission reductions, its calculations, measured and monitored parameters and the data,
for the verified monitoring period; and
(c) GCC Verifier’s Emission Reduction Verification Report (ERVR), as per the latest template
of GCC, with recommendation to ‘issue ACRs’ to the project activity, for the verified
monitoring period.
49. The completeness check of the submission is conducted within 5 days and the submission
is assessed by GCC Operations Team to check completeness, consistency of documents,
and project´s eligibility under GCC program.
50. A ‘request for issuance’ of a project activity, for the verified monitoring period, is considered
“submitted” when all of the appropriate forms have been deemed complete and submitted
through the IHS Markit website.
51. While assessing the submission for its eligibility and completeness, the GCC Operations
Team may request the project owner for additional information, or revision of the submission.
52. Upon receiving submission, the completeness check and eligibility check is again performed
and only completed submissions are uploaded on IHS Markit website, except those
documents which are requested to be kept confidential by project owners.
53. After the submission is deemed complete, the GCC Operations team shall conduct detailed
assessment of the project activity within 10 days. In case, the project documentation meets
all requirements of the GCC Program including Project Standard and applicable Baseline &
Monitoring Methodology, GCC Operations Team shall prepare a ‘recommendation’.
54. In case the recommendation of the GCC Operations Team and that of the GCC Verifier is
matching/coinciding i.e. ‘issue ACRs’ to the project activity, a notification is sent to the
Steering Committee informing them of the ‘Automatic Issuance of ACRs’ to the project activity,
unless more than 50% members of Steering Committee submit objections, within 10 days.
55. In case, the recommendation of the GCC Operations Team and that of the GCC Verifier is
not matching/coinciding i.e. either to ‘issue ACRs’ or ‘not- issue ACRs’ to the project activity
or three members of Steering Committee have submitted objections, within 10 days; the GCC
Operations Team shall place the particular project case for Steering Committee’s
consideration and decision, will be made through electronic means.
56. Once a particular project case has been placed under the consideration of the Steering
Committee, the GCC Operations Team shall appoint Steering Committee member for his
assessment and recommendation. The Steering Committee member shall conduct the
assessment and provide its recommendation, within 10 days, which can be either to ‘issue
ACRs’ or ‘not- issue ACRs’ to the project activity.
57. After considering Steering Committee member’s inputs, GCC Operations Team shall submit
the ‘Summary Note’, containing the short summary of all the three recommendations and a
final recommendation, for Steering Committee’s consideration through electronic means.
Program Processes
13 of 18
58. Each Steering Committee member shall consider the ‘Summary Note’ and provide their
individual decision to GCC Operations Team within 10 days, taking into account the ‘Decision
Criteria’ (given below). If the Steering Committee member does not provide any response or
communicate its decision within allotted time, it will mean that the member is in agreement
with the recommendation in the ‘Summary Note’.
59. The final decision shall be made based on by consensus or majority vote (more than 50%).
In case of a tie during voting, the recommendation of GCC Operations Team shall be
considered as final.
60. The decision to ‘Register’ or ‘Not Register’ the project shall be made available by the GCC
Operations Team, within, 3 days, on GCC website transparently.
61. The GCC Operations Team shall coordinate with the IHS Markit’s team to inform them of the
decision to ‘Issue ACRs’ to the project activity and reflect this decision on the IHS Markit
Website within 3 days.
62. After this stage, all the subsequent transactions, including transferring or retiring credits, shall
be executed directly on IHS Markit website as per its procedures.
‘Decision Criteria’ for ACR Issuance
S.No. GCC Verifier Report
GCC Operations Team
Recommendation
Steering Committee Member
Recommendation
Steering Committee Decision
Final Decision
1 Issue Issue - - Issue ACRs
2 Issue Do-not-Issue Issue Decision by Steering
Committee
Decision by Steering
Committee
3 Issue Do-not-Issue Do-not-Issue Do-not-Issue Not-Issue ACRs
Program Processes
14 of 18
2. BASELINE AND MONITORING METHODOLOGY DEVELOPMENT
63. Project owners can either use methodologies developed under the GCC Program or use
baseline and monitoring methodologies (hereinafter referred as “methodologies”) of
international GHG programs namely CAR, CDM, GS or VCS for their projects. GCC Program
methodologies are developed by GCC applying the process described below.
2.1. SCREENING MITIGATION OPPORTUNITIES
64. GCC uses an internal screening process to identify suitable project categories and associated
methodologies. It takes into account a number of aspects when developing a new
methodology or revising existing international methodology to adapt to regional
circumstances. These aspects are as follows:
2.1.1. Applicability of Standardized Methodologies
65. Project categories shall allow the application of standardized concepts and therefore not be
technically too complex or specific. For complex project categories, where standardized
concepts cannot be adopted, either GCC will revise the methodologies of international carbon
standards (CDM, CAR, Gold Standard, or VCS) to simplify them and make them fit for regional
use, or project owners may directly use these methodologies for submission of project
documentation to GCC.
2.1.2. Emission Reduction Potential and Environmental Integrity
66. In general, GCC methodologies will focus on standardized default factors to reduce the
transaction costs for project development. Although, the methodologies will be scale-neutral
(no differentiation between large-scale and small-scale projects), for larger projects higher
level of stringencies shall be applied to safeguard the environmental integrity.
2.1.3. Replicability
67. The GCC program will prioritize project types which are important for the sustainable
development of the region and can be replicated.
2.1.4. Data/ Information Availability
68. Credible and current data/information on default emission factors, penetration rates of
technologies/fuels/feedstocks etc. should be available for GCC to be able to develop
methodologies.
2.2. DEVELOPMENT OF METHODOLOGY
69. The following figure-1 summarizes the methodology development process.
Program Processes
15 of 18
Figure-3: Flow chart for Methodology development.
70. To initiate the project methodology development process, GCC will conduct research and
develop initial draft and put together a diversified team consisting of internal experts for its
development. GCC’s “Standard for Key Project Requirements and Development of
Methodologies” shall be followed in the methodology development process.
71. Where required, external experts (e.g. sectoral experts) will be involved for specific inputs by
invitation. The internal experts shall lead the process by conducting background research,
collecting all relevant information and preparing the draft methodology.
72. First draft of methodology shall be prepared, with or without consultation of external expert,
within 2 months of decision to develop a methodology.
Program Processes
16 of 18
73. The Methodology is made available on GCC website for public inputs for 15 days. GCC team
revises the methodology taking into account the public inputs at the end of public consultation
period.
2.3. STEERING COMMITTEE APPROVAL
74. GCC shall forward the “draft methodology” to an appointed member of Steering Committee.
75. Steering Committee member shall provide his/her comments within 10 days which are taken
into account by GCC in developing the final draft of methodology that shall be forwarded for
Steering Committee’s consideration and approval within 20 days of receiving Steering
Committee member comments.
76. The Steering Committee shall discuss the “final draft methodology” either electronically or in
a physical meeting and will provide its approval, subject to amendments/changes, if any.
77. GCC shall revise the methodology based on amendment suggested by steering committee
and publish it on the GCC program website, with appropriate version numbering (e.g. Version
1.0). It is immediately available for use.
2.4. METHODOLOGY REVISION
78. As shown in figure 3, depending upon the project requirements, GCC team revises, simplifies,
streamlines, expands or corrects the provisions of methodology. The revised version is
prepared and uploaded on GCC website in maximum 2 months’ time following due
procedure, depending upon the nature of revision, as given below.
2.4.1. Policy Revisions
79. Policy revisions are significant revisions that affect project definitions or eligibility, or that
involve changes/ adjustments to baseline estimations, quantification of emission
reductions/removals, monitoring requirements, or contents of positive lists. Depending on the
extent of the revision, GCC may involve external expert/s. All policy revisions require approval
from the Steering Committee. When adopted, a policy revision creates a new version of the
methodology.
2.4.2. Program Revisions
80. Program revisions are editorial in nature and do not require approval from the Steering
Committee. Program revisions create a new sub-version of the methodology. For policy and
technical revision, the version number is incremented by 1, e.g. from 1.0 to 2.0. For editorial
revision, the version number is incremented by 0.1, e.g. from 1.0 to 1.1.
2.4.3. Grace Period
81. A project using previous version of methodology can be submitted by project owner to GCC
within 30 days from the date on which a revised methodology is adopted. After this date the
use of latest version of methodology shall be compulsory to make the project submission.
Program Processes
17 of 18
DOCUMENT HISTORY
Version Date Comment
V 2.0 25/06/2019 ▪ Revised version released for approval by GCC Steering Committee.
▪ This version contains details and information to be provided, consequent to latest developments world-wide (e.g., CORSIA EUC).