GC Pre-Qualification BRIEFING A359 FAA NextGen / ATC Tower Space Consolidation Project Boston Logan International Airport East Boston, MA October 18, 2017

Transcript of GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150...

Page 1: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

GC Pre-Qualification BRIEFING

A359 FAA NextGen / ATC Tower Space Consolidation Project Boston Logan International Airport East Boston, MA October 18, 2017

Page 2: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

• Create new space to consolidate FAA program – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure – Central Garage, Level 4

• Facility Scope – Office areas and associated work areas, – Create new space for relocation of existing simulator training equipment, – Create new space for relocation of existing FAA telecommunication equipment, – Support areas, building systems areas and storage.

• Construction Requirements – 2 phases –

• Phase 1 build-out for relocated FAA telecommunication equipment • Phase 2 build-out remaining areas.

– All existing operations, security and communication systems must remain operational through construction.

– Phase 1 is anticipated to be an expedited design process with fast pace delivery

A359 FAA NextGen/ATC Tower Space Consolidation Project PROJECT SCOPE

Page 3: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

Site Location

A359 FAA NextGen/ATC Tower Space Consolidation Project

Page 4: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

A359 FAA NextGen/ATC Tower Space Consolidation Project PLANNING DIAGRAM

Central Garage Level 4

Page 5: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

• Contractors agree to follow BIM and Lean Construction approaches as defined in Massport BIM Guidelines found at www.massport.com

• Cover letter • All Application Schedules identified in RFQ • One (1) original and five (5) bound copies of Qualification

Submittals

• Due: 12:00 noon on Friday, 3 November 2017

A359 FAA NextGen/ATC Tower Space Consolidation Project RFQ Submission Requirements Highlights

Page 6: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

Questions are to be sent via email to: [email protected]

Questions due:

Friday, October 27, 2017, 12:00 noon

Official answers will be published: Friday, October 30, 2017 (Estimated)

Solicitation: Close Date/Submission Deadline

Friday, November 3, 2017, 12:00 noon

A359 FAA NextGen/ATC Tower Space Consolidation Project Schedule Milestones

Page 7: GC Pre-Qualification BRIEFING FAA NextGen / ATC Tower ... · – Build out of approximately 6,150 SQFT, one level, – New light weight construction supported by existing structure

Questions?

A359 FAA NextGen/ATC Tower Space Consolidation Project