Gas Holder Station Dewatering and Desludging – North London · 2015. 12. 15. · Surrey KT16 8BE...

2
Gas Holder Station Dewatering and Desludging – North London Region: North London Client: Coleman & Co. Ltd /National Grid Property Holdings Ltd Involved Units: Eneotech Environmental Ltd Execution Time: May 2010 – September 2010 Contract Value: £250,000 Projektdaten Site setup Dewatering of gas holders Confined space entry in to gas holders Desludging of gas holders Cleaning of structures Dewatering and management of recovered sludge Ausgeführte Arbeiten Tank Dewatering and Desludging Industrial Waste Services Project Data Work Performed

Transcript of Gas Holder Station Dewatering and Desludging – North London · 2015. 12. 15. · Surrey KT16 8BE...

  • Gas Holder Station Dewatering and Desludging – North London

    Region: North London

    Client: Coleman & Co. Ltd /National Grid Property Holdings Ltd Involved Units: Eneotech Environmental Ltd

    Execution Time: May 2010 – September 2010

    Contract Value: £250,000

    Projektdaten

    Site setup

    Dewatering of gas holders

    Confined space entry in to gas holders

    Desludging of gas holders

    Cleaning of structures

    Dewatering and management of recovered sludge

    Ausgeführte Arbeiten

    Tank Dewatering and Desludging

    Industrial Waste Services

    Project Data

    Work Performed

  • Gas Holder Dewatering & Desluudging Works - North London

    Eneotech Environmental Ltd. were asked by Coleman &

    Company Ltd to fulfil the role of dewatering and

    desludging subcontractor on the demolition works at a

    National Grid Property former gas holder station site in

    North London. Eneotech Environmental Ltd. are term

    contractors to National Grid Property Holdings Ltd for

    specialist groundwater remediation project. This project

    marked a first in providing specialist subcontractor skills

    to another facet of the former gasworks regeneration

    programme.

    The subcontract package was to firstly dewater 3no.

    redundant gas holders. This water was to be pumped out

    through a bespoke water treatment plant and disposed of

    to sewer. Once access had been gained to the holder the

    sludge had to be removed to allow the demolition

    programme progress. The prime aim of the sludge

    treatment was to reduce volumes to allow waste disposal

    at another time.

    The water treatment plant was designed to be able to

    treat massive volumes of water (2000m3/day) which were

    specified within a temporary discharge to sewer consent.

    The treatment plant consisted of oil and sediment

    separator tanks, air stripping tank, sand filters and

    activated carbon filter. The plant was controlled by a

    bespoke control panel with integrated level sensors,

    motor starters and inline methane detector. This sensor

    was calibrated for the discharge consent and ensured

    real time confidence of the air stripping stage of the

    treatment plant which was designed to remove the

    methane from the dissolved phase.

    Upon completing dewatering of the below ground gas

    holder the roof was removed and a risk assessment was

    carried out to determine the confined space entry options

    with respect to site conditions. Primary access was to be

    formed by a specialist system scaffold staircase tied into

    the remaining structure. Secondary emergency access

    was provided by a traditional pole and grip scaffold tower

    with mid riding tripod sited at the top. Prior to use a full

    mock emergency was carried out to ensure all operative

    were aware of the risks posed by confined space and the

    adopted evacuation procedure.

    Eneotech Environmental Ltd had determined the most

    effective way to reduce waste volumes, which the client

    would have to dispose of, was via centrifuge treatment

    which had never been used successfully on similar

    projects until now. The basal sludge were pumped via

    hydraulic pump back to sludge holding lagoons (below

    ground holder) or were tipped into the lagoons by a road

    sweeper (above ground holders). These materials were

    normally tankered offsite for disposal, in this case the

    material was to be the feed stock for the centrifuge. The

    sludge was then pumped through the mobile sludge

    dewatering centrifuge to produce a dewatered and

    stackable sludge suitable for disposal. The water fraction

    produced by the process was passed through the

    established treatment plant prior to discharge to sewer.

    Bilfinger Berger Environmental Ltd. reduced waste

    volume by 75%.

    Eneotech operates in Europe as a certified waste

    disposal business with our own technical facilities and a

    license to recycle or eliminate wastes of all kinds. We

    offer a comprehensive range of modern services covering

    every aspect of the treatment and disposal of

    contaminated bulk materials. In many instances, we are

    able to accelerate the official regulatory processes, all

    with disposal security and integrity you can rely on.

    We offer services to remove and dispose of difficult and

    hazardous wastes from current and former production

    facilities. These include specialist dewatering and sludge

    removal services.

    Our company Eneotech Environmental Ltd. ranks as one

    of the most highly skilled and dependable services

    providers specialising in site rehabilitation, waste disposal

    and service platform preparation.

    Head Office

    Head Office Eneotech Environmental Ltd. 10 Station Road Chertsey Surrey KT16 8BE Tel: +44 (0)1932 577290 Fax: +44 (0)1932 571917 For more information email: [email protected] www.eneotech.co.uk

    Northern Regional Office Eneotech Environmental Ltd. 7400 Daresbury Park Daresbury Warrington WA4 4BS Tel: +44 (0) 1928 737500 Fax: +44 (0) 1928 737699

    Scotland Office Eneotech Environmental Ltd. Lochside House, 3 Lochside Way, Edinburgh EH12 9DT Tel: +44 (0)131 4522047 Fax: +44 (0)131 4522518