Gas Holder Station Dewatering and Desludging – North London · 2015. 12. 15. · Surrey KT16 8BE...
Transcript of Gas Holder Station Dewatering and Desludging – North London · 2015. 12. 15. · Surrey KT16 8BE...
-
Gas Holder Station Dewatering and Desludging – North London
Region: North London
Client: Coleman & Co. Ltd /National Grid Property Holdings Ltd Involved Units: Eneotech Environmental Ltd
Execution Time: May 2010 – September 2010
Contract Value: £250,000
Projektdaten
Site setup
Dewatering of gas holders
Confined space entry in to gas holders
Desludging of gas holders
Cleaning of structures
Dewatering and management of recovered sludge
Ausgeführte Arbeiten
Tank Dewatering and Desludging
Industrial Waste Services
Project Data
Work Performed
-
Gas Holder Dewatering & Desluudging Works - North London
Eneotech Environmental Ltd. were asked by Coleman &
Company Ltd to fulfil the role of dewatering and
desludging subcontractor on the demolition works at a
National Grid Property former gas holder station site in
North London. Eneotech Environmental Ltd. are term
contractors to National Grid Property Holdings Ltd for
specialist groundwater remediation project. This project
marked a first in providing specialist subcontractor skills
to another facet of the former gasworks regeneration
programme.
The subcontract package was to firstly dewater 3no.
redundant gas holders. This water was to be pumped out
through a bespoke water treatment plant and disposed of
to sewer. Once access had been gained to the holder the
sludge had to be removed to allow the demolition
programme progress. The prime aim of the sludge
treatment was to reduce volumes to allow waste disposal
at another time.
The water treatment plant was designed to be able to
treat massive volumes of water (2000m3/day) which were
specified within a temporary discharge to sewer consent.
The treatment plant consisted of oil and sediment
separator tanks, air stripping tank, sand filters and
activated carbon filter. The plant was controlled by a
bespoke control panel with integrated level sensors,
motor starters and inline methane detector. This sensor
was calibrated for the discharge consent and ensured
real time confidence of the air stripping stage of the
treatment plant which was designed to remove the
methane from the dissolved phase.
Upon completing dewatering of the below ground gas
holder the roof was removed and a risk assessment was
carried out to determine the confined space entry options
with respect to site conditions. Primary access was to be
formed by a specialist system scaffold staircase tied into
the remaining structure. Secondary emergency access
was provided by a traditional pole and grip scaffold tower
with mid riding tripod sited at the top. Prior to use a full
mock emergency was carried out to ensure all operative
were aware of the risks posed by confined space and the
adopted evacuation procedure.
Eneotech Environmental Ltd had determined the most
effective way to reduce waste volumes, which the client
would have to dispose of, was via centrifuge treatment
which had never been used successfully on similar
projects until now. The basal sludge were pumped via
hydraulic pump back to sludge holding lagoons (below
ground holder) or were tipped into the lagoons by a road
sweeper (above ground holders). These materials were
normally tankered offsite for disposal, in this case the
material was to be the feed stock for the centrifuge. The
sludge was then pumped through the mobile sludge
dewatering centrifuge to produce a dewatered and
stackable sludge suitable for disposal. The water fraction
produced by the process was passed through the
established treatment plant prior to discharge to sewer.
Bilfinger Berger Environmental Ltd. reduced waste
volume by 75%.
Eneotech operates in Europe as a certified waste
disposal business with our own technical facilities and a
license to recycle or eliminate wastes of all kinds. We
offer a comprehensive range of modern services covering
every aspect of the treatment and disposal of
contaminated bulk materials. In many instances, we are
able to accelerate the official regulatory processes, all
with disposal security and integrity you can rely on.
We offer services to remove and dispose of difficult and
hazardous wastes from current and former production
facilities. These include specialist dewatering and sludge
removal services.
Our company Eneotech Environmental Ltd. ranks as one
of the most highly skilled and dependable services
providers specialising in site rehabilitation, waste disposal
and service platform preparation.
Head Office
Head Office Eneotech Environmental Ltd. 10 Station Road Chertsey Surrey KT16 8BE Tel: +44 (0)1932 577290 Fax: +44 (0)1932 571917 For more information email: [email protected] www.eneotech.co.uk
Northern Regional Office Eneotech Environmental Ltd. 7400 Daresbury Park Daresbury Warrington WA4 4BS Tel: +44 (0) 1928 737500 Fax: +44 (0) 1928 737699
Scotland Office Eneotech Environmental Ltd. Lochside House, 3 Lochside Way, Edinburgh EH12 9DT Tel: +44 (0)131 4522047 Fax: +44 (0)131 4522518