    Sabarmati River Front Development Corporation Limited Page 51

    SECTION VI

    BILL OF QUANTITIES

    Construction of Diaphragm Wall with Reinforced Anchor slab, and Special Fill for Guide bund for a length of1965 m in

    River Sabarmati for the Sabarmati River Front Development Project in Ahmedabad

    Stretch - 01 ( West Side - Between Gandhi Bridge to Ellis Bride )

    SUMMARY SHEET

    Sr. No. Amount

    Note : Bidders may bid for one or both the stretches, but in separate B.O.Q.

  • 8/4/2019 Gandhi Bridge

    2/7

    Amount

    In Figures In Words (in Rs. )

    1 Construction of 600 mm thick diaphragm wall from

    constructed earthen bund above water level in

    R.C.C.grade M-30 of various depth. The rate

    includes construction of guide wall 1200 mm deep

    in R.C.C.grade M-20 of 100 mm thickness made

    from lightly reinforced concrete. Grabbing &

    Trenching for diaphragm wall shall be carried out in

    all type of soil / sand / gravel by adopting approved

    method. Concreting in batching plant, the cost of

    reinforcement for diaphragm wall and earthen bund

    will be paid under saperate item.

    28000 m

    The contractor's rate should include the cost of

    following items

    a Site clearance before starting the work and after

    completion of work including survey work.

    b Construction of guide wall in M20 grade concrete,

    including Earthwork in Excavation and or

    Backfilling. Demolishing and stacking of unused

    material of guide wall after completion of the

    diaphragm wall as directed by the Engineer.cost of

    reinforcement in guide wall.

    cTrenching by approved trenching equipment upto

    desired depth in all sorts of soil except hard and

    soft Rock.

    d Concreting by tremmie in controlled concrete M30

    grade including cost of all materials, bentonite,

    labourers, tools, plants, and equipments etc.

    complete.

    e Overflowing of contaminated concrete of 0.6 m

    height(equivalent volume 0.36 m above cutoff

    level and similutenious finishing the concrete at

    cutoff level in green state(Chipping or dismentalingof contaminated concrete is not allowed instead of

    equivalent overflowing concrete is suggested).

    Sabarmati River Front Development Corporation Limited Page 52

    Rate (In Rs.)UnitDescription of Item

    BILL OF QUANTITIES

    SUB SECTION : 6.1 DIAPHRAGM WALL

    Sr.

    No.

    Qty

    Stretch - 01 ( West Side - Between Gandhi Bridge to Ellis Bride )

  • 8/4/2019 Gandhi Bridge

    3/7

    f Filling and compacting contaminated concrete

    below reinforced earth wall as shown in the

    drawing in green state only.

    g The earthen bund is proposed to be constructed

    above water level and construction of diaphragm

    wall is to be carried out in dry condition from

    constructed earthen bund.The cost of construction

    of earthen bund is to be paid saperately as per

    item no. 6.2(2 and 3). However contractor

    expecting any dewatering for construction of

    diaphragm wall same should be included in the

    item. The cost of dewatering would not be payable

    to contractor.

    h The cost of reinforcement of diaphragm wall will be

    paid separately.

    i The quoted rate shall cover costs towards extra

    concrete consumed due to voids, pockets, bulges,

    side collapse of earth faces etc.The wall shall be

    measured as per drawing dimensions and paid for

    only such square metre of concrete calculated

    from these measurements.

    j providing and fixing 100 mm dia PVC pipe having

    capacity of 6 Kg/cm2 at 1.5 m c/c in grid pattern in

    Diaphragm wall as shown in the drawing.

    k providing and fixing steel shuttering from top of

    bund to river bed level during concreting of

    Diaphragm wall towards River side for form finish

    surface of diaphragm wall upto riverbed

    (Removable form work,Methodology to be decided

    by the contractor).

    2 Supplying, erecting, placing, lowering in position by

    suitable method HYSD(TMT ) Fe 415

    reinforcement confirming to IS 1786 of all

    categories for diaphragm wall at all levels including

    cutting to required length bending, providing hooks

    if any, overlapping, binding with 18 gauge annealed

    wires, welding if any laying in position to ensure

    proper cover specified during concreting etc

    complete as directed. Laps, chairs, hooks for

    lifting, spacers shall not be measured and paid

    for.

    1008 M.ton

    Sabarmati River Front Development Corporation Limited Page 53

    Total (Rs.)

  • 8/4/2019 Gandhi Bridge

    4/7

    Amount

    In Figures In Words (in Rs. )

    1 Cleaning and grubbing , removing and disposing of

    all materials such as trees, bushes, shrubs,

    stumps, roots, grass, weeds, top organic soil,

    garbage, solid waste of any thickness, rubbish etc.,

    which in the opinion of the Engineer are unsuitable

    for incorporation in the works, from the area of river

    front and disposing as instructed engineer in-

    charge including all lift and lead and as per

    specification.

    1750 m

    2 Embankment construction under water: Backfilling

    is to be placed under water, only acceptable

    granular material having angle of internal friction

    more than 30 degree shall be used unless

    otherwise approved by the Engineer. Acceptable

    granular material shall consist of graded, hard

    durable particles with maximum particle size not

    exceeding 75 mm. The material should be non-

    plastic having uniformity coefficient of not less than

    10. The material placed in open water shall be

    deposited by end tipping without compaction.

    346000 m

    3 Backfilling above the water table with selected

    granular materials from selected excavated /

    selected borrow area at OMC to 95 % proctor

    density by using vibratory roller for compaction as

    per the specifications, drawings and as directed by

    the Engineer

    86450 m

    4 Excavation for foundation in sand, gravel clay soft

    soils and murrum etc including strutting and

    dewatering as necessary and disposing or using

    excavated stuff in embankment as directed.

    2750 m

    BILL OF QUANTITIES

    Total (Rs.)

    Sabarmati River Front Development Corporation Limited Page 54

    Sr.

    No.

    Description of Item Qty Unit Rate (In Rs.)

    SUB SECTION : 6.2 SPECIAL FILL FOR GUIDE BUND

    Stretch - 01 ( West Side - Between Gandhi Bridge to Ellis Bride )

  • 8/4/2019 Gandhi Bridge

    5/7

    Amount

    In Figures In Words (in Rs. )

    1 Providing and laying of plain cement concrete ofP.C.C.M15 grade as per the specifications below

    anchor slab as per drawing and as directed by the

    Engineer. Rate shall include cost of formwork if

    any.

    2 Supplying, erecting, placing, lowering in position by

    suitable method HYSD(TMT ) Fe 415

    reinforcement confirming to IS 1786 of all

    categories for anchor slab and cut off wall at all

    levels including cutting to required length bending,

    providing hooks if any, overlapping, binding with 18

    gauge annealed wires, welding if any laying in

    position to ensure proper cover specified during

    concreting etc complete as directed. Laps, chairs,

    hooks for lifting, spacers shall not be measured

    and paid for.

    185 Mton

    3 Providing and laying of cement concrete of

    R.C.C.M25 grade as per the specifications for

    anchor slab and cutoff as per drawing and as

    directed by the Engineer. Rate shall include cost of

    formwork but exclude cost of reinforcement.

    7370 m

    SUB SECTION : 6.3 CONCRETE for ANCHOR SLAB

    BILL OF QUANTITIES

    Sr.

    No.

    Description of Item Qty Rate (In Rs.)

    Sabarmati River Front Development Corporation Limited Page 55

    2950 m

    Total (Rs.)

    Unit

  • 8/4/2019 Gandhi Bridge

    6/7

    Amount

    In Figures In Words (in Rs. )

    1 Excavation for foundation in sand, gravel clay soft

    soils and murrum etc including strutting and

    dewatering as necessary and disposing or using

    excavated stuff in embankment as directed.

    2 Providing and laying of plain cement concrete of

    P.C.C.M15 grade as per the specifications below

    box culvert as per drawing and as directed by the

    Engineer. Rate shall include cost of formwork if

    any.

    80 m

    3 Supplying, erecting, placing, lowering in position bysuitable method HYSD(TMT ) Fe 415

    reinforcement confirming to IS 1786 of all

    categories for box culvert at all levels including

    cutting to required length bending, providing hooks

    if any, overlapping, binding with 18 gauge annealed

    wires, welding if any laying in position to ensure

    proper cover specified during concreting etc

    complete as directed. Laps, chairs, hooks for

    lifting, spacers shall not be measured and paid

    for.

    42 Mton

    4 Providing and laying of cement concrete of

    R.C.C.M25 grade as per the specifications for box

    culvert as per drawing and as directed by the

    Engineer. Rate shall include cost of formwork butexclude cost of reinforcement.

    555 m

    5 Providing and laying of R.C.C. Hume pipes of NP3

    type confirming to IS 458 as per the specifications

    and as per drawing and as directed by the

    Engineer in-charge.

    (a) 1800 mm dia. Pipe 190 rmt

    (a) 250 mm dia. Pipe 675 rmt

    Rate (In Rs.)Sr.

    No.

    Description of Item Qty Unit

    Total (Rs.)

    1575 m

    Stretch - 01 ( West Side - Between Gandhi Bridge to Ellis Bride )

    SUB SECTION : 6.4 RCC HUME PIPE & DRAINAGE BOX CULVERT

    BILL OF QUANTITIES

    Sabarmati River Front Development Corporation Limited Page 56

  • 8/4/2019 Gandhi Bridge

    7/7

    Note :

    1

    2 Unit rates and prices shall be quoted by the bidder in Indian Rupee.

    3 Where there is a discrepancy between the rate in figures and words, the rates in words will govern.

    4 No extra payment shall be paid for material testing, concrete testing of structure and any other tests as required.

    5 The octroi amount paid on the material by the contractor will be reimbersed on actuals.

    6 The royalty exemption is expected from government of gujarat.The contractor unit rate shall exclud all royalties,

    however any royalities paid by contractor will be reiembersed as actual.

    7 The unidentified utilities shall be shifted or reconstructed as per prevailng S.O.R rates of Ahmedabad Municipal

    Corporation.

    Sabarmati River Front Development Corporation Limited Page 57

    Item for which no rate or price has been entered in will not be paid for by the employer when executed and shall be

    deemed covered by the other rates and prices in the bill of quantities.