Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE...

36
Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan

Transcript of Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE...

Page 1: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Game Day BuildingPost Tensioned Redesign

AE Senior Thesis Spring 2009Matthew Haapala

BAE/MAE Structural OptionFaculty Consultant: Dr. Hanagan

Page 2: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Presentation Outline Existing Conditions

Thesis Proposals and Goals

Gravity System Redesign

Lateral System Redesign

Foundation Optimization

Cost & Schedule Analysis

Lighting Redesign

Conclusions

Question and Answer

Page 3: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Building Name: Foreman Field Game Day BuildingProject Team:

Owner - Old Dominion University General Contractor - S.B. Ballard Construction Company Architect - Ellerbe Becket Engineer - Clark Nexsen

Size : Gross Floor Area = 54,877 sq. ft. , Height = 47 ft. 1st Floor = 16,500 sq. ft. 2nd Floor = 16,100 sq. ft. 3rd Floor = 11,500 sq. ft. 4th Floor = 10,800 sq. ft.

Construction: Dates of February 22, 2008 thru July 22, 2009Cost: $11.9 millionProject Delivery Method: Design-Building

Location: The Game Day building is currently under construction in the south end zone of Foreman Field on the campus of Old Dominion University in Norfolk Virginia.

Building Statistics

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Building StatisticsGame Day BuildingPost Tensioned Redesign

Page 4: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Cast in Place Reinforced Concrete Flat Plate Typical bay size 31’-6” x 17’-0” Typical slab depth 12” No shear caps or drop panels Shear stud rails used to resist punching shear

Cast in Place Reinforced Concrete Beams Located around openings and seating

Cast in Place Concrete Columns 18” x 18” typical

Existing Gravity System 3rd Floor Structural Plan

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Blue: Beam LocationRed: Column or Load Bearing Wall Location

Game Day BuildingPost Tensioned Redesign

Page 5: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Seven Cast in Place Reinforced Concrete Shear Walls Located in Architecturally Convenient Locations

Capacity Significantly Exceeds Lateral Loading Demands Column & Slab Moment Frames’ Stiffness not Considered

Existing Lateral System Existing Lateral System

Shear Wall Location Plan ETABS Model of Existing Lateral SystemBy: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

Game Day BuildingPost Tensioned Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Page 6: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Square Precast Prestressed Concrete (SPPC) Piles 100’ long from Tip to Cutoff 183 Piles Total Typically Driven in Clusters of 4 Below Most Columns Clusters of Up to 18 Below Shear Walls Topped With 36” - 40” Deep Pile Caps Grade Beams Below Exterior Walls & Between Pile Caps

Existing Foundations Existing Foundations

Average Depth (ft.) Description0 to 1 Topsoil or Asphalt0 to 4 Fill of fibrous organics and wet sand2 to 18 Sand with varying amounts of silt and clay18 to 53-84 Gray, wet clay with varying amounts of sand and

marine shell fragments53-84 to 110 Gray, wet, silty, fine sand with marine shell fragments

and varying amounts of clay

Sub-Surface Soild Conditions

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Foundation Plan

Page 7: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Study 1 Gravity System RedesignProblem: Two-way flat plate is structurally inefficient floor systemSolution: Replace with one-way slabs on post tensioned beamsGoals:

Reduce slab depth Develop understanding of post tensioned concrete design Use post tensioning to minimize beam depth Reduce self weight of the structure

Study 2 Lateral System RedesignProblem: Shear walls’ excess capacity suggests reduction possibleSolution: Consider Moment Frames in Lateral Design and Remove

Existing Shear Walls Where PracticalGoals: Utilize Post Tensioned Beams in Ordinary Concrete Moment

Frames Reduce The Number of Shear Walls

Study 3 Foundation OptimizationProblem: With poor soils extensive deep foundations required Solution: Analyze foundation requirements of redesigned structure

to determine possible foundation reductionsGoal: Reduce the number of piles

Structural Depth Proposal

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Structural Depth Proposal

Page 8: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Problem: Unknown cost, constructability, and construction schedule impacts of structural redesign

Solution: Conduct cost and schedule analyses comparing of the original and redesigned structure

Goals: Lower the price of the structure Develop a construction sequence that satisfies the unique

demands of post tensioning Do not Increase the Overall Project Duration

C.M. Breadth Proposals

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

C.M. Breadth Proposals

Page 9: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Problem: Original lighting design predominantly inexpensive troffers and cans

Solution: Create an alternate lighting scheme for the scholarship lounge

Goals: Integrate the structural redesign into the redesigned lighting

scheme Make the room seem more spacious have emphasizing the

peripherals by having a high luminance on the Walls and Ceiling.

Increase flexibility by specifying dimmable fixtures Satisfy ASHRE 90.1 and IESNA Lighting Handbook

requirements Use attractive or concealed luminaries

Lighting Breadth Proposal

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Lighting Breadth Proposal

Page 10: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Original Design Code Substitutions2003 Virginia Uniform Statewide Building Code 2006 IBC

ASCE 7-02 ASCE 7-05

ACI 318-02 ACI 318 08

Reference Design Codes and Standards

Gravity System Redesign

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Concrete Material Properties

Location f'c (psi)Cement Type f'c (psi)

Cement Type

Pile Caps and Grade Beams 3000 I 3000 ISlabs on Grade 3000 I 3000 IStructural Slabs and Beams 5000 I 6000 IIIWalls and Columns 5000 I 6000 III

Original New

Page 11: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Gravity Loading Assumptions

LoadingDead LoadsNormal Weight Concrete 150 pcfMasonry Walls 40 psfCurtin Walls 15 psfMechanical/Electrical/Plumbing 5 psf100% Outdoor Air Handling Unit 750 lbsVariable Refrigerant Volume Heat Pump 350 lbsGas Fired DX Package Roof top Unit 500 lbsDX Split System Heat Pump 250 lbsLive LoadsROOF 20 psf 20 psfSTAIRS 100 psf 100 psfCORRIDORS 100 psf 100 psfTERRACES 100 psf 100 psfSEATING 100 psf 60 psfSTORAGE 125 psf 125 psfMECH./ELEC. ROOMS 125 psfSnow LoadsPg 10 psf 10 psfPf 11 psf 11 psf

Design Value ASCE 7-05 Req'd

GRAVITY LOADING DESIGN VALUES

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 12: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Trial Layout Development Trial Layout Development

= Post Tensioned Concrete Beam

= Reinforced Concrete Beam

= Support Column or Wall

= Post Tensioned Concrete Beam

= Reinforced Concrete Beam

= Support Column or Wall

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 13: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

PCA Slab Unit Strip 2nd Floor Between Gridlines 3.8 and 4.1 w/ Initial Beam Layout

Total Deflection = 1.789”

Unit Strip Plan Unit Strip Isometric View

Unit Strip Deflection Diagram

PCA Slab Analysis & Design PCA Slab Analysis & Design

Unit Strip Plan Unit Strip Isometric View

Total Deflection = 0.224”

Unit Strip Deflection Diagram

PCA Slab Unit Strip 2nd Floor Between Gridlines 3.8 and 4.1 w/ Final Beam Layout

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 14: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Calculations Designed in accordance with ACI 318-08 for:

Flexural serviceability Ultimate flexural strength Shear and torsion Deflection

Every post tensioned beam analyzed at supports and midspan Member loads determined by iterative moment distribution

Pattern loading not critical Moment redistribution not performed

et>.0075 (ACI 318-08 Sect. 8.4.2) Beam/Slab effective T beams considered

PT Beam Hand Calculations PT Beam Hand Calculations

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 15: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Interior beams Depth: 14” = 2x slab depth of 7” Width: 12” - 40”, typ. 28” # Tendons: (5) - (13), typ. (6) Longitudinal Rebar: (3) - (5) #8 Top & Bottom , typ. (4)

Perimeter beams: depth 18” Depth 18” - 29” Width 12” - 24”, typ. 18” # Tendons: (4) - (6), typ. (4) Longitudinal Rebar : (2) - (4) #8 Top & Bottom, typ. (2)

On average76% dead load balanced after losses Average Compressive Stress 164psi – 475psi, typ. 250 psi

> Code required 125psi < 500psi reasonable maximum

PT Beam Hand Calculations PT Beam Hand Calculations

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 16: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

RAM Concept Analysis

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 17: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Torsion & Deflection Design

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

9’-6”

31’-6”

29”

12”18”

18”x18” Edge Beams

Page 18: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Torsion & Deflection Design

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Typical Long Term Deflection Plan

Page 19: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

2ND Floor Shear Reinforcement Plan

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 20: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

2ND Floor FlexuralReinforcement Plan

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System

Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 21: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Lateral System Redesign

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 22: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Wind Loading Wind Loading

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign Basic Wind Speed 110MPH

Wind Importance Factor 1.15Wind Exposure Category BGust Response Factor 0.85Internal pressure Coefficients +/-0.18

Wind Loading Design Values

Page 23: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Seismic Loading Seismic Loading

Site Class D

Importance Factor, I 1.25

Ss 0.118

S1 0.048

Fa 1.6

Fv 2.4

SDS=(2/3)*Fa*Ss 0.126

SD1 =(2/3)*Fv*S1 0.0768

Seismic Design Category B

Building Height, h 47'

Ct 0.02

x 0.75

Ta = Ct*hx 0.359

Cu 1.7

CuTa 0.61

TL 8

Seismic Design Values

Seismic Force Resisting SystemResponse Modification Coefficient, R

Deflection Amplification Factor, Cd

Ordinary Reinforced Concrete Moment Frames

3 2.5

Ordinary Reinforced Concrete Shear Walls

5 4.5

Ordinary Reinforced Concrete Moment Frames and Ordinary Reinforced Concrete Shear Walls

4.5 4

Design Coefficients for Seismic Force Resisting SystemsBy: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 24: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Shear Wall 7 Removal Shear Walls 1 & 3 Removal

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 25: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Lateral System Plan

= Columns Sections Increased

= Plan East/West Direction Lateral System Components

= Plan North/South Direction Lateral System Components

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 26: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

South Wind Deflected Shape Seismic Deflected Shape

Story Max Deflection X Max Deflection Y h/600 Deflection Check(in.) (in.) (in.) (OK or NG)

Roof 0.0686 0.0868 0.2133 OKFloor 4 0.0709 0.0401 0.2133 OKFloor 3 0.0707 0.0376 0.2133 OKFloor 2 0.0684 0.0340 0.3000 OK

Max Deflections Caused By Wind Loading

Story Cd Average Diaphragm Drift Max Diaphragm Drift Seismic Drift Limit Drift Limit Exceded Torsional IrregularityRoof 2.5 0.002915 0.002953 0.02 No NoFloor 4 2.5 0.003378 0.003418 0.02 No NoFloor 3 2.5 0.003383 0.003418 0.02 No NoFloor 2 2.5 0.002220 0.002245 0.02 No No

Story Cd Average Diaphragm Drift (Y) Max Diaphragm Drift (Y) Seismic Drift Limit Drift Limit Exceded Torsional IrregularityRoof 4 0.001120 0.001204 0.02 No NoFloor 4 4 0.000816 0.000960 0.02 No NoFloor 3 4 0.000816 0.000884 0.02 No NoFloor 2 4 0.000396 0.000472 0.02 No No

East/West Direction

North South Direction

Seismic Drift Analysis

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 27: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Loading

Load Combo 1.2D+1.6W+L 0.9D+1.6W 1.2D+1.0E+L 0.9D+1.0E

Pu (Kips) 1127 606 1128 606

Vu (Kips) 174 201 27 54

Mu (K-ft) 8001 7965 3370 3333

Shear Wall Design

P (kip)

My (k-ft)

16000

-2000

50000-50000

(Pmax)

(Pmin)

fs=0.5fy

fs=0

fs=0.5fy

fs=0

123456 7 89 10

11 121314

F Design Values

F Tension 0.9

F Shear 75

F Comp. 0.65

Geometry

lw (in) 222

h (in) 18

hw (in) 180

d % 80.00%

A (in^2) 3996

S (in^3) 147852

I (in^4) 16411572

Material Properties

f'c 6000

fy 60000

Shear Reinforcement Req'd# of Curtains Req'd 1

As min (in^2/ft) 0.54

Max Spacing (in) 13.78

Shear Reinforcement Design# of Curtains 2

Bar Size #5

Bar Spacing (in) 12

ac 3

rt 0.006

FVn (Kips) 268

Vu/FVn 75%

Flexural Reinforcement Req'dBoundary Zone No

Flexural Reinforcement Design# of Bars 7

Bar Size #9

FMn>Mu,FPn>Pu Yes

Flexural Reinforcement Detail

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 28: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Foundation Optimization Foundation Optimization

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Wall Critical Comp. Load Critical Tensile Load Critical Shear Load P<PAllowab

le

V<VAllowable Uplift Original Final(K/Pile) (K/Pile) (K/Pile) # of Piles # of Piles

22 0SW 2 77 -29 9 OK OK YES 10 10SW 4 142 -27 12 OK Fail* YES 10 10SW 6 61 -21 8 OK OK YES 12 12

SW 1, SW 3, SW 5, & SW7

Shear Wall Foundation Analysis

Seismic Wind(Kips) (Kips) (Kips) % Orig. (Kips) % Orig.

72 99 62 86% 95 96%129 162 106 82% 158 98%102 81 67 66% 77 95%

Original Base Shear New Design Base ShearSeismic Wind

Shear Wall Base Shear Comparison ChartOriginal Final

Crit. Comp.

Load

Crit.Ten Load

P<PAllowable Uplift # of Piles # of Piles

Location (K/Pile) (K/Pile)1,0.A 23.44 4.08 OK NO 2 21.1,0.A 18.94 -8.73 OK YES 1 11.2,0.A 35.74 13.68 OK NO 2 21,E.5 25.95 6.22 OK NO 2 21,F 22.11 4.36 OK NO 2 21.1,E.5 28.08 -7.90 OK YES 1 11.2,E.6 40.21 11.64 OK NO 2 21.2,F 17.60 -12.54 OK YES 2 21.8,A.1 71.42 25.39 OK NO 3 31.9,A.2 60.31 18.72 OK NO 3 31.9,E.6 61.40 19.37 OK NO 0 31.9,F 26.07 6.13 OK NO 0 32,B 81.21 21.10 OK NO 4 32,C 75.67 12.85 OK NO 4 33,B 139.86 51.23 OK NO 4 33,C 140.71 43.60 OK NO 4 34,B 135.67 49.40 OK NO 4 34,C 116.36 34.70 OK NO 4 36,B 135.87 48.43 OK NO 4 36,C 99.79 32.19 OK NO 4 36,D 73.63 20.05 OK NO 3 37,B 143.35 52.21 OK NO 4 37,C 105.38 28.12 OK NO 4 37,D 56.94 16.09 OK NO 2 28,B 105.22 31.83 OK NO 4 38,C 89.12 16.24 OK NO 4 38,D 36.57 8.11 OK NO 2 28.1,0.A 39.82 12.16 OK NO 4 49,0.A 29.72 11.91 OK NO 3 39,B 49.91 2.17 OK NO 0 32.1,F 58.74 17.69 OK NO 2 23.1,F 37.33 13.45 OK NO 2 23.8,F 43.99 9.24 OK NO 3 34.1,E 92.81 26.85 OK NO 3 34.1,F 59.06 22.06 OK NO 3 35,E 80.78 32.39 OK NO 3 34.9,F 55.53 16.46 OK NO 3 35.5,E 98.69 28.55 OK NO 3 35.5,F 94.03 25.37 OK NO 3 36.6,E 91.55 29.70 OK NO 3 36.6,F 60.48 24.83 OK NO 3 3

Column Foundation Requirement Analysis3 Piles

Supporting Original # of Piles Final # of Piles DifferenceColumns 113 110 -3Shear Walls 54 32 -22Façade 16 16 0Total 183 158 -25

Foundation Redesign Summary

Page 29: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Cost Analysis

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Original Design New Design$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

$851,525 $738,506

$132,684$120,328

$77,776$77,776

$520,323$497,533

$596,631

$404,878

$0

$16,188

$336,597

$298,460

$49,331

$47,675

Structural System Cost Comparison

Deep Foundations Shallow Foundations Slab on Grade Concrete Formwork Reinforcing steel

Prestressing Steel Concrete Concrete Placing

$1,502,882$30.33/sq.-ft.

$1,264,735$25.52/sq.-ft.

Cost Savings$238,147 $4.80/sq.-ft16% Reduction in Structure Cost2% Reduction in Overall Project Cost

Page 30: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Original Design Schedule

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 31: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

New Design Schedule Construction Sequence

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Sequence 2 Sequence 1 Sequence 3

Page 32: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Lighting Redesign

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 33: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Pseudo Color Rendering

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 34: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Gravity System Redesign Slab depth reduced by 5” Floor depth increase at beams only 2” Buildings weight reduced by 36%

Lateral System Redesign 4 out of 7 shear walls removed Lateral loading does not control beam design

Foundation Optimization Number of Piles Reduced by 15%

Cost and Schedule Analysis $238,000 in savings Structural erection expedited

Lighting Redesign Non uniform floor depth can improve aesthetics

Conclusions

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 35: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Professional Consultants Rich Apple Holbert Apple Associates Peter A. Allen Clark Nexsen Brian M. Barna Clark Nexsen Alicia B, Udovich Clark Nexsen John Wilson Clark Nexsen

AE Dept. Faculty Dr. Walter Schneider III Dr. Andres Lepage Dr. Linda Hanagan Dr. Ali Memari Dr. John Messner

Classmates, Friends, and Family

Acknowledgements

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign

Page 36: Game Day Building Post Tensioned Redesign AE Senior Thesis Spring 2009 Matthew Haapala BAE/MAE Structural Option Faculty Consultant: Dr. Hanagan.

Questions?

By: Matthew Haapala

•Existing Conditions

•Thesis Proposal & Goals

•Gravity System Redesign

•Lateral System Redesign

•Foundation Optimization

•Cost & Schedule Analysis

•Lighting Redesign

•Conclusions

Game Day BuildingPost Tensioned Redesign