G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council...
-
Upload
valentine-norman -
Category
Documents
-
view
215 -
download
0
Transcript of G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council...
G. Carboni – Muon Meeting – 22-23 April 2002
Muon Meeting
• LHC schedule is now official (Council Committee)
• First protons (Pilot run) delayed to 1.04.2007 (was Feb. 2006) • At the moment no further details on “physics run” (was August 2006)• Access to hall until that date
but when pipe under vacuum detector cannot be opened (safety)• No SPS in 2005 (only PS test beam)
• In this meeting we have to review and readjust our milestones (in particular the “official” ones)• some of them have already been missed• some others risk to be missed, however:
• perhaps we have been too optimistic• with the one-year LHC delay they don’t make much sense today
• In readjusting we should be as accurate and conservative as possible, avoiding too frequent corrections
•The updated milestones will be presented to the referees at the next LHCC
G. Carboni – Muon Meeting – 22-23 April 2002
2001 Dec Engineering design completed CARIOCA+DIALOG chip design and test completed
Muon Detector Major Milestones
2002 Jul-Oct Full chain electronics
test
2002 Jul-Oct Full chain electronics
test
MWPC Detectors RPC Detectors Electronics
2003 Oct
2003 Jan Start chamber construction
2004 Dec Chamber construction completed Electronics assembled and tested
2003 May Start chamber construction
2002 Jun SYNC chip designand test completed
Start FE-board production
2003 Oct Muon filter inst.
2003 Oct Muon filter inst.
2004 Jun Support structure inst.
2004 Jun Support structure inst.
2004 Jul Start installation at CERNStart installation at CERN
2005 Aug Commissioning completed
Start IMB, SB and ODE production
2001
2002
2003
2004
2005
2002 MarAs presented with
the TDR
July 2001
2002 Jul
Moved to July
Moved to Nov.
G. Carboni – Muon Meeting – 22-23 April 2002
Microsoft Project Document
Present (official) milestones
G. Carboni – Muon Meeting – 22-23 April 2002
Jan02 apr jul oct Jan03
Definition of constr. Elements XConstr. Of proto 0 (1) X X X XConstr. Of proto 0 (2) X X X X XPreseries Production X X X XPRR XX
Preparation of Prod. Centers X X X X X X Each center shouldclean areas show a detailed
wiring machine schedulesoldering machine
quality controlsCR test stand
Setup of Prod. Centers X X X XTests of Proto 0 X X X X X
Tooling for panels (1) XTooling for panels (2) X X XPreproduction of panels XEnd of panel qualification X X XXPanel production (Honeyc.) X X X X X X X XEDR XX
Material Procurements X X X X X X
Planning for 2002 as presented by Pierluigi in Dec. 2001
MWPC construction
EDR
G. Carboni – Muon Meeting – 22-23 April 2002
Muon Electronics Project Schedule for 2002
25/1 Definition of IB detailed scheme (DONE)(DONE)20/2 Choice on Low Voltage regulators 31/3 definition of ODE board detailed scheme and components procurement15/4 DIALOG- submission30/4 F/E Low Voltage board prototype 30/6 DIALOG- test completed1/7 IB prototype (2 boards + back-plane)31/7 ODE- board prototype:
96 or 192 inputsTTCRxTLK/GOL transmitter (according to availability)SYNC prototype (OTIS - Chip-- FPGA)
SB- prototype: ELMB for I2C control (at least 4 channels)TTCRx + F/E pulsing system
DIALOG F/E complete board ( version)CARIOCA F/E complete board ( version)
1/9 Start of prototypes standalone tests and debugging30/10 DC- version1/11 Start of full chain tests. The full chain contains:
1 MWPCn F/E boards (CARIOCA, DIALOG, LV)1 SB prototype2 IB + back-plane1 ODE1 DC (added subsequently)
December LHCb week Presentation of results (!)
G. Carboni – Muon Meeting – 22-23 April 2002
PNPI 14 planned for MarchLNF Final design
FE/LNFDesign in progress
Status of V0.0 prototypes: testing from May (RPC), July (MWPC)
CERN
G. Carboni – Muon Meeting – 22-23 April 2002
• One-year shift of the various completion dates is unavoidable: Dec. 2004 -> Dec. 2005
• It was suggested at last TB (HJ) to delay the start of installation not more than 6 months
• goal: terminate installation by end July 2006, then start commissioning
• plan installation in a way to minimize cost of hired manpower (cranes, cabling...)
• Fine-tuning according to
• parts of the detector (stations, regions)
• construction sites (institutes)
• “interference” during installation
• Should we have a fine-structure of milestones?
• different milestone on sub-detectors/regions? When?
• What do we mean (e.g.) by “10% production?”: need to clarify terms
• Finally, milestones should be reflected in financial planning
Proposed framework for the milestones discussion
We can access the detector until 12.2006 and (with restrictions) until 3.2007
We can access the detector until 12.2006 and (with restrictions) until 3.2007
G. Carboni – Muon Meeting – 22-23 April 2002
Microsoft Project Document
New proposed milestones
G. Carboni – Muon Meeting – 22-23 April 2002
• The TDR requests for rate and cluster size must of course be met• We should anyhow feel free to review them critically:
Plateau Efficiency – redundancy - number of gaps
• Additional parameters should be considered also. For example:
1. GIF test
2. Efficiency/plateau uniformity over the sensitive area
3. ...........
4. ............
How to proceed towards the choice for the inner part
G. Carboni – Muon Meeting – 22-23 April 2002
Why GIF testing?
Rates at GIF are most likely too small for rate tests of chambers for the inner regions of M1, however very meaningful aging studies can still be performed at GIF:
For M1R1 the dose expected in LHCb is 90 kRad/y or 900 Gy/year (See Note 97-017 by V. Talanov).
Placing a detector at 50 cm from the source, the dose (ABS=1) is: Dose(Gy) = 11 T(days)
80 days provide 1-year LHCb equivalent meaningful test
Complements the high-rate tests (PSI) cm 50at 217
m
cms102.1
Dose
E
cm 50at 217
m
cms102.1
Dose
E
G. Carboni – Muon Meeting – 22-23 April 2002
The proponents of the various solutions should address these
items soon, with notes describing the subsystem as a whole and
indicating the appropriate milestones of the project.
The proponents of the various solutions should address these
items soon, with notes describing the subsystem as a whole and
indicating the appropriate milestones of the project.
The proposed approach
• Final aspects (last but not least)•Simplicity of construction•Standardization•Cost