G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council...

11
Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007 (was Feb. 2006) At the moment no further details on “physics run” (was August 2006) Access to hall until that date but when pipe under vacuum detector cannot be opened (safety) No SPS in 2005 (only PS test beam) In this meeting we have to review and readjust our milestones (in particular the “official” ones) some of them have already been missed some others risk to be missed, however: perhaps we have been too optimistic with the one-year LHC delay they don’t make much sense today In readjusting we should be as accurate and conservative as possible, avoiding to frequent corrections The updated milestones will be presented to the referees at the next LHCC

Transcript of G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council...

Page 1: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

Muon Meeting

• LHC schedule is now official (Council Committee)

• First protons (Pilot run) delayed to 1.04.2007 (was Feb. 2006) • At the moment no further details on “physics run” (was August 2006)• Access to hall until that date

but when pipe under vacuum detector cannot be opened (safety)• No SPS in 2005 (only PS test beam)

• In this meeting we have to review and readjust our milestones (in particular the “official” ones)• some of them have already been missed• some others risk to be missed, however:

• perhaps we have been too optimistic• with the one-year LHC delay they don’t make much sense today

• In readjusting we should be as accurate and conservative as possible, avoiding too frequent corrections

•The updated milestones will be presented to the referees at the next LHCC

Page 2: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

2001 Dec Engineering design completed CARIOCA+DIALOG chip design and test completed

Muon Detector Major Milestones

2002 Jul-Oct Full chain electronics

test

2002 Jul-Oct Full chain electronics

test

MWPC Detectors RPC Detectors Electronics

2003 Oct

2003 Jan Start chamber construction

2004 Dec Chamber construction completed Electronics assembled and tested

2003 May Start chamber construction

2002 Jun SYNC chip designand test completed

Start FE-board production

2003 Oct Muon filter inst.

2003 Oct Muon filter inst.

2004 Jun Support structure inst.

2004 Jun Support structure inst.

2004 Jul Start installation at CERNStart installation at CERN

2005 Aug Commissioning completed

Start IMB, SB and ODE production

2001

2002

2003

2004

2005

2002 MarAs presented with

the TDR

July 2001

2002 Jul

Moved to July

Moved to Nov.

Page 3: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

Microsoft Project Document

Present (official) milestones

Page 4: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

Jan02 apr jul oct Jan03

Definition of constr. Elements XConstr. Of proto 0 (1) X X X XConstr. Of proto 0 (2) X X X X XPreseries Production X X X XPRR XX

Preparation of Prod. Centers X X X X X X Each center shouldclean areas show a detailed

wiring machine schedulesoldering machine

quality controlsCR test stand

Setup of Prod. Centers X X X XTests of Proto 0 X X X X X

Tooling for panels (1) XTooling for panels (2) X X XPreproduction of panels XEnd of panel qualification X X XXPanel production (Honeyc.) X X X X X X X XEDR XX

Material Procurements X X X X X X

Planning for 2002 as presented by Pierluigi in Dec. 2001

MWPC construction

EDR

Page 5: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

Muon Electronics Project Schedule for 2002

25/1 Definition of IB detailed scheme (DONE)(DONE)20/2 Choice on Low Voltage regulators 31/3 definition of ODE board detailed scheme and components procurement15/4 DIALOG- submission30/4 F/E Low Voltage board prototype 30/6 DIALOG- test completed1/7 IB prototype (2 boards + back-plane)31/7 ODE- board prototype:

96 or 192 inputsTTCRxTLK/GOL transmitter (according to availability)SYNC prototype (OTIS - Chip-- FPGA)

SB- prototype: ELMB for I2C control (at least 4 channels)TTCRx + F/E pulsing system

DIALOG F/E complete board ( version)CARIOCA F/E complete board ( version)

1/9 Start of prototypes standalone tests and debugging30/10 DC- version1/11 Start of full chain tests. The full chain contains:

1 MWPCn F/E boards (CARIOCA, DIALOG, LV)1 SB prototype2 IB + back-plane1 ODE1 DC (added subsequently)

December LHCb week Presentation of results (!)

Page 6: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

PNPI 14 planned for MarchLNF Final design

FE/LNFDesign in progress

Status of V0.0 prototypes: testing from May (RPC), July (MWPC)

CERN

Page 7: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

• One-year shift of the various completion dates is unavoidable: Dec. 2004 -> Dec. 2005

• It was suggested at last TB (HJ) to delay the start of installation not more than 6 months

• goal: terminate installation by end July 2006, then start commissioning

• plan installation in a way to minimize cost of hired manpower (cranes, cabling...)

• Fine-tuning according to

• parts of the detector (stations, regions)

• construction sites (institutes)

• “interference” during installation

• Should we have a fine-structure of milestones?

• different milestone on sub-detectors/regions? When?

• What do we mean (e.g.) by “10% production?”: need to clarify terms

• Finally, milestones should be reflected in financial planning

Proposed framework for the milestones discussion

We can access the detector until 12.2006 and (with restrictions) until 3.2007

We can access the detector until 12.2006 and (with restrictions) until 3.2007

Page 8: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

Microsoft Project Document

New proposed milestones

Page 9: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

• The TDR requests for rate and cluster size must of course be met• We should anyhow feel free to review them critically:

Plateau Efficiency – redundancy - number of gaps

• Additional parameters should be considered also. For example:

1. GIF test

2. Efficiency/plateau uniformity over the sensitive area

3. ...........

4. ............

How to proceed towards the choice for the inner part

Page 10: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

Why GIF testing?

Rates at GIF are most likely too small for rate tests of chambers for the inner regions of M1, however very meaningful aging studies can still be performed at GIF:

For M1R1 the dose expected in LHCb is 90 kRad/y or 900 Gy/year (See Note 97-017 by V. Talanov).

Placing a detector at 50 cm from the source, the dose (ABS=1) is: Dose(Gy) = 11 T(days)

80 days provide 1-year LHCb equivalent meaningful test

Complements the high-rate tests (PSI) cm 50at 217

m

cms102.1

Dose

E

cm 50at 217

m

cms102.1

Dose

E

Page 11: G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

G. Carboni – Muon Meeting – 22-23 April 2002

The proponents of the various solutions should address these

items soon, with notes describing the subsystem as a whole and

indicating the appropriate milestones of the project.

The proponents of the various solutions should address these

items soon, with notes describing the subsystem as a whole and

indicating the appropriate milestones of the project.

The proposed approach

• Final aspects (last but not least)•Simplicity of construction•Standardization•Cost