Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV...

31
Future Network Requirements May 2017 Presenters: Mahesh Narotam, Manager Portfolio Planning and Optimisation Daniel Andersen, Manager Network Strategy Roslyn Stewart, Senior Portfolio Planning Engineer

Transcript of Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV...

Page 1: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Future Network

Requirements

May 2017

Presenters:

• Mahesh Narotam, Manager Portfolio Planning

and Optimisation

• Daniel Andersen, Manager Network Strategy

• Roslyn Stewart, Senior Portfolio Planning

Engineer

Page 2: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

• Background

• Central Queensland to South Queensland Area

• North Queensland Area

• Gold Coast Area

• Questions

Agenda

Page 3: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Disclaimer

• The views outlined in the presentation are

Powerlink’s best view at the time of

publication and may be subject to change.

• While care has been taken to prepare and

provide this information in good faith,

Powerlink accepts no responsibility for liability

or loss or damage that may be incurred by

persons acting in reliance on this information

or assumptions drawn from it.

Page 4: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Previous feedback received

Powerlink presented the Non-Network

Feasibility Study process at the 2016

Transmission Annual Planning (TAPR) Forum.

Feedback was received that non-network

providers are keen to:

• Engage and understand Powerlink’s future

requirements (noting it is an iterative two-

way learning process)

• Receive information in a timely manner to

assist with the assessment of potential

solutions.

Page 5: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Current operating environment

Powerlink

Consumer response

Emerging technologies

Economic outlook

Electricity demand

Page 6: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Webinar purpose

• Given these complexities in the external

environment, Powerlink acknowledges the

importance of engaging early on with our

stakeholders

• Non-network solutions are a proven and

effective method of managing uncertainty,

providing flexibility and improving network

utilisation

• Assists with achieving the right balance

between reliability and cost.

Page 7: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Avenues for engagement

• Formal consultation as defined under the

National Electricity Rules (NER):

– Transmission Annual Planning Report (TAPR)

– Regulatory Investment Test for Transmission (RIT-T)

• Powerlink’s Non-Network Feasibility Study

process

• Forums and webinars

• Non-Network Engagement Stakeholder Register

(NNESR)

• Email [email protected].

Page 8: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

• Central Queensland to South Queensland Area

(Daniel Anderson)

• North Queensland Area (Roslyn Stewart)

• Gold Coast Area (Roslyn Stewart)

Focus areas

Page 9: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to

South Queensland Area

Page 10: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to South Queensland Area

Description and characteristics

• The 275kV corridor between Calliope

River (Gladstone) and South Pine

(Brisbane) was progressively

developed as single circuit feeders in

the 1970s and 1980s.

• Provides an important connection

between generation in the Gladstone

region and the load centres in South

Queensland, as well as interconnection

to NSW.

Calliope River

Wurdong

Gin Gin

Teebar Creek

Woolooga

Palmwoods

South Pine

Calvale

Larcom Creek

Boyne Island

Bouldercombe

Tarong

Rocklea Mt England Blackwall

Legend

275kV Transmission

line 275kV Substation

Teebar Creek

Woolooga

Gin Gin

Palmwoods

South Pine

Mt England

Blackwall

Rocklea

Wurdong

Calvale

Bouldercombe

Boyne Island

Calliope River

Larcom Creek

Legend

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Tarong

Page 11: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to South Queensland Area

Description and characteristics

• With varying distances from the ocean,

and localised industrial pollution, these

transmission lines are subject to

different environmental and

atmospheric conditions.

• Over time, they have experienced

structural degradation at different rates.

Calliope River

Wurdong

Gin Gin

Teebar Creek

Woolooga

Palmwoods

South Pine

Calvale

Larcom Creek

Boyne Island

Bouldercombe

Tarong

Rocklea Mt England Blackwall

Legend

275kV Transmission

line 275kV Substation

Teebar Creek

Woolooga

Gin Gin

Palmwoods

South Pine

Mt England

Blackwall

Rocklea

Wurdong

Calvale

Bouldercombe

Boyne Island

Calliope River

Larcom Creek

Legend

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Tarong

Page 12: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to South Queensland Area

Description and characteristics

• The interconnector’s transfer capability

is highly dependent on the location of

generation.

Calliope River

Wurdong

Gin Gin

Teebar Creek

Woolooga

Palmwoods

South Pine

Calvale

Larcom Creek

Boyne Island

Bouldercombe

Tarong

Rocklea Mt England Blackwall

Legend

275kV Transmission

line 275kV Substation

Teebar Creek

Woolooga

Gin Gin

Palmwoods

South Pine

Mt England

Blackwall

Rocklea

Wurdong

Calvale

Bouldercombe

Boyne Island

Calliope River

Larcom Creek

Legend

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Tarong

Page 13: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to South Queensland Area

Description and characteristics

• Future changes in generation and load

profiles will impact the transfer

capability requirements from Central to

Southern Queensland.

• In its current form, the intraconnector

offers a great deal of flexibility for

possible generation dispatches, seldom

imposing any constraints to market

operation.

Calliope River

Wurdong

Gin Gin

Teebar Creek

Woolooga

Palmwoods

South Pine

Calvale

Larcom Creek

Boyne Island

Bouldercombe

Tarong

Rocklea Mt England Blackwall

Legend

275kV Transmission

line 275kV Substation

Teebar Creek

Woolooga

Gin Gin

Palmwoods

South Pine

Mt England

Blackwall

Rocklea

Wurdong

Calvale

Bouldercombe

Boyne Island

Calliope River

Larcom Creek

Legend

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Tarong

Page 14: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to South Queensland Area

Description and characteristics

• In October 2015, Powerlink engaged

with relevant stakeholders to broaden

input and gain feedback on future

reinvestment of the CQ-SQ

intraconnector.

• Feedback indicated that Powerlink

adopt an incremental approach to

reinvestment such that future

alternative options were not eliminated.

Calliope River

Wurdong

Gin Gin

Teebar Creek

Woolooga

Palmwoods

South Pine

Calvale

Larcom Creek

Boyne Island

Bouldercombe

Tarong

Rocklea Mt England Blackwall

Legend

275kV Transmission

line 275kV Substation

Teebar Creek

Woolooga

Gin Gin

Palmwoods

South Pine

Mt England

Blackwall

Rocklea

Wurdong

Calvale

Bouldercombe

Boyne Island

Calliope River

Larcom Creek

Legend

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Tarong

Page 15: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Central Queensland to South Queensland Area

Future requirements

• The current reinvestment strategy looks

to balance economic cost whilst

preserving a transfer capability that

delivers appropriate market benefits.

• A number of transmission lines will

reach their end of life over the next five

to 20 years.

Transmission Line Estimated

Reinvestment

Period (years) Palmwoods to South Pine 5-10

Calliope River to Gin Gin 5-10

Calliope River to Wurdong Tee 10-20

Wurdong Tee to Gin Gin 10-20

Gin Gin to Woolooga 10-20

Gin Gin to Teebar Creek 10-20

Teebar Creek to Woolooga 10-20

Page 16: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

North Queensland Area

Page 17: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

275kV & 132kV Transmission Corridor

Page 18: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

NQ Transmission Corridor Network Development

1960s

• 132kV circuit

• Collinsville Power Station to Townsville.

`

Townsville South

Clare

Collinsville

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

1960

Clare

Collinsville

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Legend

132kV transmission line

132kV substation

Townsville South

Page 19: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

NQ Transmission Corridor Network Development

1980s

• 275kV single circuit transmission lines

established between Collinsville and

Ross

• Ross 275/132kV Substation established

with one transformer initially (there are

now three).

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

`

Ross

Townsville South

Clare

Strathmore Collinsville

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

1970-80

Clare

Collinsville

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Legend

Strathmore

Townsville South

132kV transmission line

132kV substation

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Page 20: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

NQ Transmission Corridor Network Development

2000 onwards

275kV supply into NQ upgraded

• New double circuit transmission line

from Strathmore to Ross

• Two existing single circuit transmission

lines from Strathmore to Ross are

paralleled for higher capacity

• Strathmore 275/132kV Substation

established with one transformer.

`

Ross

Invicta

Mill

Townsville South

Clare

South

King Creek

Strathmore Collinsville

North

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

1990-Present

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Clare

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Legend

Strathmore

132kV transmission line

132kV substation

275kV transmission line

275kV substation

Ross

Invicta

Mill

Townsville

South

Clare

South

King

Creek

Bowen

North

Strathmore Collinsville

North

Proserpine

Legend

132kV transmission line

275kV substation

132kV substation

275kV transmission line

Invicta Mill

King Creek

Ross

Collinsville

North

Page 21: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

NQ Transmission Corridor Network Development

2000 onwards

• Replacement of original substations at

Clare and Collinsville at adjacent sites

• Connection of major customers

• Decommissioning of assets:

- Collinsville Power Station connections

- Mackay to Proserpine transmission line.

Page 22: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

NQ Transmission Corridor Network Development

Characteristics

• 275kV

– provides intra-regional

transfers

• 132kV

– provides back-up supply to

Townsville and voltage

support to Strathmore /

Northern Bowen Basin

– provides connections to King

Creek, Invicta Mill and Clare

South

– Not much headroom

New generation

• High-level interest renewable

generation

Page 23: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

NQ Transmission Corridor Network Development

Future network requirements

• Existing transfer capability is sufficient

and seldom constrains market

operation

• May change with generation mix and

types of loads.

Assets reaching end of life

• 132kV network: 5-10 years

• 275kV single circuit lines: 10-20 years

• Near term issue with inland 132kV

circuit.

Flexibility to reshape the footprint to

respond to evolved requirements

Page 24: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Gold Coast Area

Page 25: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Greenbank Loganlea

Swanbank E

Blackwall

Molendinar

Mudgeeraba

Blackstone

Middle Ridge

Belmont

Cades County

Southport

Merrimac Nerang

Robina

Terranora

Legend

275kV transmission line 110kV transmission line

275kV substation

110kV substation

Energex asset boundary

Regional boundary

Surfers Paradise

Varsity Lakes

Burleigh

Heads

Gold Coast Area

• The main transmission system

supporting power transfers to

the Gold Coast consists of the

Greenbank to Molendinar and

Greenbank to Mudgeeraba

275kV transmission lines.

• The Molendinar and

Mudgeeraba 275/110kV

substations are the major

injection points into the area.

Legend

Loganlea

Cades County

Southport

Surfers Paradise

Belmont

Swanbank E

Greenbank

Merrimac

Varsity Lakes

Burleigh

Heads

Mudgeeraba

Robina

Nerang

Molendinar

Middle Ridge

Blackstone

Blackwall

Terranora

275kV transmission line

110kV transmission line

275kV substation

110kV substation

Energex asset boundary

Regional boundary

Page 26: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

• Currently three 275/110kV transformers at Mudgeeraba

Substation

• With the existing three transformer configuration, there is

no load at risk during the 10 year outlook period

• Replacement or decommissioning needs to be

considered for one of the transformers in the next three to

five years

• Joint planning would need to be done between Powerlink,

Energex, Transgrid, Essential Energy and Directlink.

Mudgeeraba Third Transformer

Page 27: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

• Existing transmission network supplying the Gold Coast

has adequate capacity 10 year load outlook and

Directlink export capability

• Any major reinvestment or network reconfiguration

involving these single circuit transmission lines will

include consultation with a large number of stakeholders

– complex joint planning, community consultation and

RIT-T consultation

• Due to complexity and potential staging requirements, it

has been identified that an optimised end of life strategy

should be agreed within three to five years.

Greenbank to Mudgeeraba Transmission Lines

Page 28: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Greenbank Loganlea

Swanbank E

Blackwall

Molendinar

Mudgeeraba

Blackstone

Middle Ridge

Belmont

Cades County

Southport

Merrimac Nerang

Robina

Terranora

Legend

275kV transmission line 110kV transmission line

275kV substation

110kV substation

Energex asset boundary

Regional boundary

Surfers Paradise

Varsity Lakes

Burleigh

Heads

Gold Coast Area

Emerging issues

Three to five years

• Mudgeeraba 275kV secondary

systems

• No. 3 275/110kV transformer at

Mudgeeraba

Five to 10 years

• 2 x single circuit 275kV Greenbank

to Mudgeeraba transmission lines

• Molendinar 275/110kV secondary

systems

• Mudgeeraba 110kV Substation

• Greenbank secondary systems

and SVC secondary systems

• Mudgeeraba to STR-1731 (NSW

Boarder Terranora) 110kV double

circuit transmission line

Legend

Loganlea

Cades County

Southport

Surfers Paradise

Belmont

Swanbank E

Greenbank

Merrimac

Varsity Lakes

Burleigh

Heads

Mudgeeraba

Robina

Nerang

Molendinar

Middle Ridge

Blackstone

Blackwall

Terranora

275kV transmission line

110kV transmission line

275kV substation

110kV substation

Energex asset boundary

Regional boundary

Page 29: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Questions?

Page 30: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

• Thank you for attending today’s webinar

• We encourage you to contact Powerlink for any

more details

• Information on the RIT-T/non-network solutions

can be found on our website

• For further questions or to join Powerlink’s

Non-Network Engagement Stakeholder

Register (NNESR) please email

[email protected].

Conclusion

Page 31: Future Network Requirements - Powerlink Queensland · 132kV transmission line Tarong 275kV substation 132kV substation 275 kV transmission line . Central Queensland to South Queensland

Thank you

www.powerlink.com.au

[email protected]