Fusion Nuclear Technology Development and the Role of CTF (and ITER TBM) Mohamed Abdou (web: ...
-
Upload
alan-russell -
Category
Documents
-
view
214 -
download
0
Transcript of Fusion Nuclear Technology Development and the Role of CTF (and ITER TBM) Mohamed Abdou (web: ...
Fusion Nuclear Technology Development and the Role of CTF
(and ITER TBM)
Mohamed Abdou (web: www.fusion.ucla.edu/abdou/)
Distinguished Professor of Engineering and Applied ScienceDirector, Center for Energy Science and Technology (CESTAR)
(www.cestar.seas.ucla.edu/)Director, Fusion Science and Technology Center (www.fusion.ucla.edu/)
University of California, Los Angeles (UCLA)
Presented at Workshop on CTF, Culham Conference Centre
Culham, United Kingdom, May 22-23, 2007
Fusion Nuclear Technology Development and the Role of CTF/VNS (and ITER TBM)
Outline1. What is Fusion Nuclear Technology?2. Brief Statement of Technical Issues and Role of Fusion Testing3. Framework for FNT Development and Requirements
- Stages- Parameters
4. Role of ITER TBM5. Top Level Issues for FNT Development Facilities
- Reliability / Maintainability / Availability (and Reliability Growth Strategy)
- Tritium Consumption and Supply6. Technical Details on Parameters Required for VNS/CTF
- Wall Load- Steady State Plasma- Fluence- Test Area
7. Issues yet to be resolved for CTF
Fusion Nuclear Technology (FNT)
FNT Components from the edge of the Plasma to TF Coils (Reactor “Core”)
1. Blanket Components (includ. FW)
2. Plasma Interactive and High Heat Flux Components
3. Vacuum Vessel & Shield Components
4. Tritium Processing Systems
5. Instrumentation and Control Systems
6. Remote Maintenance Components
7. Heat Transport and Power Conversion Systems
a. divertor, limiter
b. rf antennas, launchers, wave guides, etc.
Other Components affected by the Nuclear Environment
Fusion Power & Fuel Cycle Technology
• The Vacuum Vessel is outside the Blanket (/Shield). It is in a low-radiation field.
• Vacuum Vessel Development for DEMO should be in good shape from ITER experience.
• The Key Issues are for Blanket / PFC.
• Note that the first wall is an integral part of the blanket (ideas for a separate first wall were discarded in the 1980’s). The term “Blanket” now implicitly includes the first wall.
• Since the Blanket is inside of the vacuum vessel, many failures (e.g. coolant leak from module) require immediate shutdown and repair/replacement. Adaptation from ARIES-AT Design
Notes on FNT:
Pillars of a Fusion Energy System
1. Confined and Controlled Burning Plasma (feasibility)
2. Tritium Fuel Self-Sufficiency (feasibility)
3. Efficient Heat Extraction and Conversion (attractiveness)
4. Safe and Environmentally Advantageous (feasibility/attractiveness)
5. Reliable System Operation (attractiveness)
Yet, No fusion blanket has ever been built or tested!
The Blanket is THE KEY component and determines the critical path to DEMO
R&D Tasks to be Accomplished Prior to Demo
1) Plasma
2) Plasma Support Systems
3) Fusion Nuclear Technology Components and Materials
4) Systems Integration
- Confinement/Burn- Disruption Control
- Current Drive/Steady State- Edge Control
- Superconducting Magnets - Heating- Fueling
- Materials combination selection and configuration optimization
[Blanket (including First Wall), Divertors, rf Launchers]
- Performance verification and concept validation- Show that the fuel cycle can be closed (tritium self-sufficiency)- Failure modes and effects- Remote maintenance demonstration- Reliability growth- Component lifetime
Where Will These Tasks be Done?!• Burning Plasma Facility (ITER) and other plasma devices will address 1, 2, & much of 4• How and Where Will Fusion Nuclear Technology (FNT) be developed?
FNT Development Issues and Pathways Numerous technical studies were performed over the past 30 years in the US and
worldwide to study issues, experiments, facilities, and pathways for FNT development. (This is probably the most studied subject in fusion development)
This is an area where the US has played a major leadership role in the world program and provided major contributions such as engineering scaling laws for testing, VNS/CTF concept, and blanket designs
These studies involved many organizations (universities, National Labs, Industry, and utilities) and many scientists, engineers, and plasma physicists. Industry participation was particularly very strong from Fission and Aerospace and they provided substantial contributions.
Examples of Major Studies on FNT/Blanket– Blanket Comparison and Selection Study (1982-84, led by ANL)
– FINESSE Study (1983-86, led by UCLA)
– IEA Study on VNS/CTF (1994-96 US, EU, J, RF)
– ITER TBM (1987-2007) , US ITER TBM (2003-2007)
Other studies that provided important input: DEMO Study (led by ANL 1981-1983) and many Power Plant Studies (UWMAKs, STARFIRE, ARIES, others in EU,J,RF)
Many Planning activities discussed FNT and provided input (TPA, FESAC, etc)
These Studies resulted in important conclusions and illuminated the pathways for FNT and fusion development
1. D-T fuel cycle tritium self-sufficiency in a practical system depends on many physics and engineering parameters / details: e.g.
fractional burn-up in plasma, tritium inventories, FW thickness, penetrations, passive coils, doubling time
2. Tritium extraction and inventory in the solid/liquid breeders under actual operating conditions
3. Thermomechanical loadings and response of blanket and PFC components under normal and off-normal operation
4. Materials interactions and compatibility5. Identification and characterization of failure modes,
effects, and rates in blankets and PFC’s6. Engineering feasibility and reliability of electric (MHD)
insulators and tritium permeation barriers under thermal / mechanical / electrical / magnetic / nuclear loadings with high temperature and stress gradients
7. Tritium permeation, control and inventory in blanket and PFC
8. Remote maintenance with acceptable machine shutdown time.
9. Lifetime of blanket, PFC, and other FNT components
Summary of Critical R&D Issues for Fusion Nuclear Technology
Blanket systems are complex and have many integrated functions, materials, and interfaces
Tritium BreederLi2TiO3 (<2mm)
First Wall(RAFS, F82H)
Neutron MultiplierBe, Be12Ti (<2mm)
Surface Heat FluxNeutron Wall Load
[18-54] mm/s
PbLi flow scheme
[0.5-1.5] mm/s
Fusion environment is unique and complex:multi-component fields with gradients
Neutrons (fluence, spectrum, temporal and spatial gradients)
• Radiation Effects (at relevant temperatures, stresses, loading conditions)
• Bulk Heating• Tritium Production• Activation
Heat Sources (magnitude, gradient)• Bulk (from neutrons and gammas)• Surface
Synergistic Effects• Combined environmental loading conditions• Interactions among physical elements of components
A true fusion environment is ESSENTIAL to activate mechanisms that cause prototypical coupled phenomena and integrated behavior
Particle Flux (energy and density, gradients)
Magnetic Field (3-component with gradients)
• Steady Field• Time-Varying Field
Mechanical Forces• Normal/Off-Normal
Thermal/Chemical/Mechanical/ Electrical/Magnetic Interactions
Multi-function blanket in multi-component field environment leads to:- Multi-Physics, Multi-Scale Phenomena Rich Science to Study
- Synergistic effects that cannot be anticipated from simulations & separate effects tests. Even some key separate effects in the blanket can not be produced in non-fusion facilities (e.g. volumetric heating with gradients)
Theory/Modeling
BasicSeparateEffects
MultipleInteractions
PartiallyIntegrated
Integrated
Property Measurement
Phenomena Exploration
Non-Fusion Facilities
Types of experiments, facilities and modeling for FNT
Design Codes
Component
•Fusion Env. Exploration•Concept Screening•Performance Verification
Design Verification & Reliability Data
Testing in Fusion Facilities
(non neutron test stands, fission reactors and accelerator-based neutron sources)
• Non fusion facilities (e.g. non-neutron test stands, fission reactors and neutron sources) have important roles
• Testing in Fusion Facilities is NECESSARY for multiple interactions, partially integrated, integrated, and component tests
• Initial exploration of coupled phenomena in a fusion environment
• Uncover unexpected synergistic effects, Calibrate non-fusion tests
• Impact of rapid property changes in early life
• Integrated environmental data for model improvement and simulation benchmarking
• Develop experimental techniques and test instrumentation
• Screen and narrow the many material combinations, design choices, and blanket design concepts
• Uncover unexpected synergistic effects coupled to radiation interactions in materials, interfaces, and configurations
• Verify performance beyond beginning of life and until changes in properties become small (changes are substantial up to ~ 1-2 MW · y/m
2)
• Initial data on failure modes & effects
• Establish engineering feasibility of blankets (satisfy basic functions & performance, up to 10 to 20 % of lifetime)
• Select 2 or 3 concepts for further development
• Identify lifetime limiting failure modes and effects based on full environment coupled interactions
• Failure rate data: Develop a data base sufficient to predict mean-time-between-failure with confidence
• Iterative design / test / fail / analyze / improve programs aimed at reliability growth and safety
• Obtain data to predict mean-time-to-replace (MTTR) for both planned outage and random failure
• Develop a database to predict overall availability of FNT components in DEMO
Stages of FNT Testing in Fusion Facilities
Sub-Modules/Modules
Stage I
Fusion “Break-in” & Scientific Exploration
Stage II Stage III
Engineering Feasibility & Performance
Verification
Component Engineering Development &
Reliability Growth
Modules Modules/Sectors
D E M O
1 - 3 MW-y/m2 > 4 - 6 MW-y/m2
0.5 MW/m2, burn > 200 s1-2 MW/m2,
steady state or long pulseCOT ~ 1-2 weeks
1-2 MW/m2,steady state or long burn
COT ~ 1-2 weeks
0.1 – 0.3 MW-y/m2
Initial exploration of coupled phenomena in a fusion environment
Uncover unexpected synergistic effects, Calibrate non-fusion tests
Impact of rapid property changes in early life
Integrated environmental data for model improvement and simulation benchmarking
Develop experimental techniques and test instrumentation
Screen and narrow the many material combinations, design choices, and blanket design concepts
Sub-Modules/Modules
0.1 – 0.3 MW-y/m2,
Stage I
Fusion “Break-in” & Scientific Exploration
0.5 MW/m2, burn > 200 s
Uncover unexpected synergistic effects coupled to radiation interactions in materials, interfaces, and configurations
Verify performance beyond beginning of life and until changes in properties become small (changes are substantial up to ~ 1-2 MW · y/m2)
Initial data on failure modes & effects
Establish engineering feasibility of blankets (satisfy basic functions & performance, up to 10 to 20 % of lifetime)
Select 2 or 3 concepts for further development
Modules
1 - 3 MW-y/m2, 1-2 MW/m2, steady state or long pulse, COT ~ 1-2 weeks
Stage II
Engineering Feasibility & Performance Verification
Identify lifetime limiting failure modes and effects based on full environment coupled interactions
Failure rate data: Develop a data base sufficient to predict mean-time-between-failure with confidence
Iterative design / test / fail / analyze / improve programs aimed at reliability growth and safety
Obtain data to predict mean-time-to-replace (MTTR) for both planned outage and random failure
Develop a database to predict overall availability of FNT components in DEMO
Modules/Sectors
> 4 - 6 MW-y/m2, 1-2 MW/m2, steady state or long burn, COT ~ 1-2 weeks
Stage III
Component Engineering Development & Reliability Growth
- These requirements have been extensively studied over the past 20 years, and they have been agreed to internationally (FINESSE, ITER Testing Blanket Working Group, IEA-VNS, etc.)
- Many Journal Papers published (>35), e.g. IEA-VNS Study Paper (Fusion Technology, Vol. 29, Jan 1996)
Parameter Value
Neutron wall loada (MW/m2)
Plasma mode of operation
Minimum COT (periods with 100% availability) (weeks)
Neutron fluence at test module (MW·y/m2)
Stage IC: initial fusion break-in (less demanding requirements than II & III)
Stage II: concept performance verification (engineering feasibility)
Stage IIId: component engineering development and reliability growth
Total “cumulative” neutron fluence experience (MW·y/m2)
Total test area (m2)
Total test volume (m3)
Magnetic field strength (T)
1 to 2
Steady Stateb
1 to 2
~0.1- 0.3
1 to 3
4 to 6d
>6
>10
>5
>4
FNT Requirements for Major Parameters for Testing in Fusion Facilities with Emphasis on Testing Needs to Construct DEMO Blanket
a - Prototypical surface heat flux (exposure of first wall to plasma is critical)b - For stages II & III. If steady state is unattainable, the alternative is long plasma burn with plasma duty cycle >80%c - Initial fusion break-in has less demanding requirements than stages II & IIId - Note that the fluence is not an accumulated fluence on “the same test article”; rather it is derived from testing “time” on “successive” test articles dictated by “reliability growth” requirements
• Initial exploration of coupled phenomena in a fusion environment
• Uncover unexpected synergistic effects, Calibrate non-fusion tests
• Impact of rapid property changes in early life
• Integrated environmental data for model improvement and simulation benchmarking
• Develop experimental techniques and test instrumentation
• Screen and narrow the many material combinations, design choices, and blanket design concepts
• Uncover unexpected synergistic effects coupled to radiation interactions in materials, interfaces, and configurations
• Verify performance beyond beginning of life and until changes in properties become small (changes are substantial up to ~ 1-2 MW · y/m
2)
• Initial data on failure modes & effects
• Establish engineering feasibility of blankets (satisfy basic functions & performance, up to 10 to 20 % of lifetime)
• Select 2 or 3 concepts for further development
• Identify lifetime limiting failure modes and effects based on full environment coupled interactions
• Failure rate data: Develop a data base sufficient to predict mean-time-between-failure with confidence
• Iterative design / test / fail / analyze / improve programs aimed at reliability growth and safety
• Obtain data to predict mean-time-to-replace (MTTR) for both planned outage and random failure
• Develop a database to predict overall availability of FNT components in DEMO
ITER TBM is a Necessary First Step in Fusion Environment Testing to enable future Engineering Development
Sub-Modules/Modules
Stage I
Fusion “Break-in” & Scientific Exploration
Stage II Stage III
Engineering Feasibility & Performance
Verification
Component Engineering Development &
Reliability Growth
Modules Modules/Sectors
D E M O
1 - 3 MW-y/m2 > 4 - 6 MW-y/m2
0.5 MW/m2, burn > 200 s1-2 MW/m2,
steady state or long pulseCOT ~ 1-2 weeks
1-2 MW/m2,steady state or long burn
COT ~ 1-2 weeks
0.1 – 0.3 MW-y/m2
Role of ITER TBM
18
Critical Factors in Deciding where to do Blanket / FNT Fusion Testing
• Tritium Consumption / Supply Issue
• Reliability / Maintainability / Availability Issue
• Cost, Risk, Schedule
• The Key FNT Testing Requirements are :
- Fusion Power only 20-30 MW
- Over about 10m2 of surface area (with exposure to plasma)
- With Steady State Plasma Operation (or plasma cycle >80%)
- Testing Time on successive test articles equivalent to neutron fluence “experience” of ~ 6 MW • y/m2
What is CTF (VNS)?
• The idea of CTF is to build a small size, low fusion power DT plasma-based device in which Fusion Nuclear Technology experiments can be performed in the relevant fusion environment: 1- at the smallest possible scale, cost, and risk, and 2- with practical strategy for solving the tritium consumption and supply issues for FNT development.
- In MFE: small-size, low fusion power can be obtained in a low-Q plasma device.
- Equivalent in IFE: reduced target yield and smaller chamber radius.
• This is a faster, much less expensive approach than testing in a large, ignited/high Q plasma device for which tritium consumption, and cost of operating to high fluence are very high (unaffordable!, not practical).
Tritium Consumption in Large and Small Power DT Devices
AND Tritium Supply Issue
AND Impact on the Path to FNT Development
Note: Projections of world tritium supply available to fusion for various scenarios were generated by Scott Willms, including information from Paul Rutherford’s 1998 memo on “Tritium Window”, and input from M. Abdou and D. Sze.
0
5
10
15
20
25
30
2000 2010 2020 2030 2040
Year
Pro
ject
ed O
ntar
io (
OP
G)
Trit
ium
In
ven
tory
(kg
)
CANDU Supply w/o Fusion
Projections for World Tritium Supply Available to Fusion Reveal Serious Problems
World Max. tritium supply is 27 kg
Tritium decays at a rate of 5.47% per year
Tritium Consumption in Fusion is HUGE! Unprecedented!55.8 kg per 1000 MW fusion power per year
Production & Cost:
CANDU Reactors: 27 kg from over 40 years, $30M/kg (current)
Fission reactors: 2–3 kg per year, at a cost of ~$200M/kg It takes tens of fission reactors to supply one fusion reactor.
$84M-$130M per kg, per DOE Inspector General*
*DOE Inspector General’s Audit Report, “Modernization of Tritium Requirements Systems”, Report DOE/IG-0632, December 2003, available at www.ig.doe.gov/pdf/ig-0632.pdf
• Large Power DT Fusion Devices are not practical for blanket/PFC development.
• We need 5-10 kg of tritium as “start-up” inventory for DEMO (can be provided from CTF operating with TBR > 1 at later stage of operation)
• Blanket/PFC must be developed in the near term prior to DEMO (and we cannot wait very long for blanket/PFC development even if we want to delay DEMO).
Projections for World Tritium Supply Available to Fusion for Various Scenarios (Willms, et al)
• World Tritium Supply would be Exhausted by 2025 if ITER were to run at 1000 MW fusion power with 10% availability
0
5
10
15
20
25
30
1995 2000 2005 2010 2015 2020 2025 2030 2035 2040 2045Year
Pro
jecte
d O
nta
rio
(O
PG
) T
ritiu
m I
nve
nto
ry (
kg
)
Candu Supply w/o Fusion
ITER-FEAT(2004 start)
ITER-FEAT (2004 start) + CTF
CTF5 yr, 100 MW, 20% Avail, TBR 0.65 yr, 120 MW, 30% Avail, TBR 1.1510 yr, 150 MW, 30% Avail, TBR 1.3
1000 MW Fusion, 10% Avail, TBR 0.0
See calculation assumptions in Table S/Z
Updated projections of Canadian + Korean tritium supply and consumption using ITER current schedule. (From Scott Willms [March 2007]). Notes & assumptions given on a separate slide.
Canadian + Korean Inventory with ITER
Canadian + Korean Inventory without supply to fusion
ITER Impact on Canadian/Korean Candu Tritium Inventory (March 2007) (from Scott Willms, LANL)
• Following the methodology developed for the Snowmass and 35-year fusion development plan exercises, the impact of ITER (the seven party agreement signed 11/07) on tritium available from both Canada and Korea was analyzed .
• The assumptions were:– Use the same assumption for Canadian tritium as was used for the 35-yr development plan– In addition to the Canadian tritium, Korean tritium is available for fusion (about a 25% additional amount of tritium)– ITER has a 2 kg tritium working inventory which is built up over two years beginning in 2018– ITER first plasma is 2016 with 3 yr HH, 1 yr DD following by tritium operations– ITER tritium operations are 6 yr followed by 1 year maintenance (no tritium burned) followed by 10 year tritium– The first 10 year campaign includes three yr HH, 1 yr DD and then builds to 1.08 kg tritium burned per year over a five year period,
then remains flat to the end of the first 10 years (modification of scenario communicated by Janeschitz at Snowmass 2002)– The second 10 years burns 1.43 kg tritium per year for each of the 10 years. This builds the wall irradiation to 0.3 MW-yr/m2
(neutrons) average over a 680 m2 wall– Between the two 10-yr campaigns there is a one year maintenance phase which presumably includes a first wall replacement. The
first 10 year would not irradiate the first wall to 0.3 MW-yr/m2. The new first wall installed at the beginning of the second 10-yr increases from 0 to 0.3 MW-yr/m2 linearly over the second 10 yr.
– At the end of ITER a total of 1 kg of tritium is lost to waste and 1 kg of tritium is returned to Canada/Korea– The only demand on the Canadian/Korean tritium is 0.1 kg/yr for sales and ITER. That is, there is no accounting for other demands
on this tritium such as CTF or Demo.– There is no tritium breeding in ITER– Note: There has been no signaling from Korea that they will supply tritium to ITER. They are only recovering tritium to get it out of
their heavy water. Canada assisted Korea with the installation of their tritium recovery system, and it is not known what contractual agreements they may have. Korean tritium sales, if they took place, would be in competition with Canada.
• The results on the following figure show:– Upper Curve: The Canadian/Korean tritium inventory without fusion. This assumes the only demand on this tritium is decay and 0.1
kg/yr sales.– Middle Curve: The Canadian/Korean tritium inventory with the above + ITER– Lower Curve: The yearly ITER transactions with the Canadian/Korean tritium due to ITER tritium inventory build up (down) + decay
+ burn
• Observations:– With these assumptions there is enough tritium for ITER, and about 5 kg of tritium would remain at the end of ITER– The tritium supply would not accommodate any significant extension of ITER, loss of tritium or significant fusion
experiment requiring tritium– There is a marginal amount of tritium remaining to startup one Demo, and tritium breeding on that one machine would
have to work “out of the box”
Reliability / Maintainability / AvailabilityCritical Development Issues
Unavailability = U(total) = U(scheduled) + U(unscheduled)
Scheduled Outage:
Unscheduled Outage: (This is a very challenging problem)
Planned outage (e.g. scheduled maintenance of components, scheduled replacement of components, e.g. first wall at the end of life, etc.).
This tends to be manageable because you can plan scheduled maintenance / replacement operations to occur simultaneously in the same time period.
Failures do occur in any engineering system. Since they are random they tend to have the most serious impact on availability.
This is why “reliability/availability analysis,” reliability testing, and “reliability growth” programs are key elements in any engineering development.
This you design for This can kill your DEMO and your future
MTBF = mean time between failures = 1/failure rate
MTTR = mean time to repair
- MTTR depends on the complexity and characteristics of the system (e.g. confinement configurations, component blanket design and configuration, nature of failure). Can estimate, but need to demonstrate MTTR in fusion test facility.
- MTBF depends on reliability of components.
Availability: = i
Risk Outage1
1represents a componenti
(Outage Risk) = (failure rate) • (mean time to repair) = i
i
MTBF
MTTR
One can estimate what MTBF is NEEDED from “availability allocation models” for a given availability goal and for given (assumed) MTTR.But predicting what MTBF is ACHIEVEABLE requires real data from integrated tests in the fusion environment.
ii i
Availability (Due to Unscheduled Events)
• A Practical Engineering System must have:
1. Long MTBF: have sufficient reliability
2. Short MTTR: be able to recover from failure in a short time
Reliability/Maintainability/Availability is one of the remaining “Grand Challenges” to Fusion Energy Development.
FNT R&D is necessary to meet this Grand Challenge.
t timereplacemenrate failure/1
)rate failure/1(
Need Low Failure Rate:- Innovative Chamber Technology
Need Short Maintenance Time:- Simple Configuration Confinement- Easier to Maintain Chamber Technology
Need LowFailure Rate
EnergyMultiplication
Need High Temp.Energy Extraction
Need High Power Density/Physics-Technology Partnership
- - High-Performance Plasma- Chamber Technology Capabilities
thfusion MPMOiC
COE
Availability&replacement cost
Need High Availability / Simpler Technological and Material Constraints
Component Number
Failure rate in hr-1
MTBF in years
MTTR for Major failure, hr
MTTR for Minor failure, hr
Fraction of failures that are Major
Outage Risk Component Availability
Toroidal Coils
16 5 x10-6 23 104 240 0.1 0.098 0.91
Poloidal Coils
8 5 x10-6 23 5x103 240 0.1 0.025 0.97
Magnet supplies
4 1 x10-4 1.14 72 10 0.1 0.007 0.99
Cryogenics 2 2 x10-4 0.57 300 24 0.1 0.022 0.978
Blanket 100 1 x10-5 11.4 800 100 0.05 0.135 0.881
Divertor 32 2 x10-5 5.7 500 200 0.1 0.147 0.871
Htg/CD 4 2 x10-4 0.57 500 20 0.3 0.131 0.884
Fueling 1 3 x10-5 3.8 72 -- 1.0 0.002 0.998
Tritium System
1 1 x10-4 1.14 180 24 0.1 0.005 0.995
Vacuum 3 5 x10-5 2.28 72 6 0.1 0.002 0.998
Conventional equipment- instrumentation, cooling, turbines, electrical plant --- 0.05 0.952
TOTAL SYSTEM 0.624 0.615
Assuming 0.2 as a fraction of year scheduled for regular maintenance. Demo Availability = 0.8* [1/(1+0.624)] = 0.49 (Blanket Availability must be .88)
An Example Illustration of Achieving a Demo Availability of 49%(Table based on information from J. Sheffield’s memo to the Dev Path Panel)
0
200
400
600
800
MT
BF
per
Bla
nk
et S
egm
ent(
FP
Y)
0
5
10M
TB
F p
er B
lan
ket
Sys
tem
(FP
Y)
0 1 2 3
MTTR (Months)
Neede
d (R
)
Expected AC
A = Expected with extensive R&D (based on mature technology and no fusion-specific failure modes
C = Potential improvements with aggressive R&D
The reliability requirements on the Blanket/FW (in current confinement concepts that have long MTTR > 1 week) are most challenging and pose critical concerns. These must
be seriously addressed as an integral part of the R&D pathway to DEMO. Impact on ITER is predicted to be serious. It is one of the key DRIVERS for CTF/VNS.
Reliability/Availability is a challenge to fusion, particularly blanket/PFC, development
• There is NO data for blanket/PFC (we do not even know if any present blanket concept is feasible)
• Estimates using available data from fission and aerospace for unit failure rates and using the surface area of a tokamak show:
Need Aggressive “Reliability Growth” Program
We must have an aggressive “reliability growth” program for the blanket / PFC (beyond demonstrating engineering feasibility)
1) All new technologies go through a reliability growth program
2) Must be “aggressive” because extrapolation from other technologies (e.g. fission) strongly indicates we have a serious CHALLENGE
• Fusion System has many major components (TFC, PFC, plasma heating, vacuum vessel, blanket, divertor, tritium system, fueling, etc.)
• All systems except the reactor core (blanket/PFC) will have reliability data from ITER and other facilities
- Each component is required to have high availability
PROBABLE MTBF for Blanket ~ 0.01 to 0.2 yrcompared to REQUIRED MTBF of many years
Component Technology Facility (CTF)
MISSIONMISSION
The mission of CTF is to test, develop, and qualify Fusion Nuclear Technology Components (fusion power and fuel cycle technologies) in prototypical fusion power conditions.
The CTF facility will provide the necessary integrated testing environment of high neutron and surface fluxes, steady state plasma (or long pulse with short dwell time), electromagnetic fields, large test area and volume, and high neutron fluence.
The testing program and CTF operation will demonstrate the engineering feasibility, provide data on reliability / maintainability / availability, and enable a “reliability growth” development program sufficient to design, construct, and operate blankets, plasma facing and other FNT components for DEMO.
YEAR: 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
R&DExperiments in Non-Fusion Facilities: Thermal, MHD, Tritium, Fission, Accelerator Neutron Sources, etc.
Theory, Modeling and Computer Simulation
ITERMachine Construction
TBM Preparation
Phase I: H-H/D-D/D-T
TBM (Fusion “break-in”)
?? Extended Phase ??
CTF Exploration & Decision
Engr. Design
Construction H-HFNT Testing
Engineering Feasibility and Reliability Growth
Demo
System Analysis / Design Studies
Engr. Design Construction Operation
Arrows indicate major points of FNT information flow
Major Activities and Example Timeline for Fusion Nuclear Technology Development
ITER TBM Provides Timely Information to CTF R&D Activities are critical to support effective FNT/Blanket
testing in ITER and CTF
Quantification of Test RequirementsGeneral Observations of FINESSE Study Results
• In many cases, a true integrated test in the strictest sense cannot be performed under significantly scaled-down conditions for certain parameters (e.g., power density, surface heat load, geometry)
• Under scaled-down environmental conditions, the function of an integrated test module has to be divided into two or more “act-alike” tests. Each act-alike test emphasizes a group of issues/phenomena.
• While an overlap among the various act-alike tests can be included to account for certain interfaces, a concern about possibly missing some phenomena remains.
• Perfect quantitative engineering scaling is not possible because it requires complete quantitative models for all (including interactive) phenomena.
• If fusion testing will have to be carried out under scaled-down conditions, then:
- Engineering scaling needs to continue to be nourished as a key technical discipline in fusion.
- The need for a more thorough understanding of phenomena and more analytical modeling will become more critical.
How Many Modules/Submodules Need to Be Tested For Any Given One Blanket Concept?
• Never assume one module, because engineering science for testing shows the need to account for:1. Engineering Scaling 2. Statistics3. Variations required to test operational limits and design/configuration/material options
• US detailed analysis indicates that a prudent medium risk approach is to test the following test articles for any given One Blanket Concept:- One Look-Alike Test Module- Two Act-Alike Test Modules- (Engineering Scaling laws show that at least two modules are
required, with each module simulating a group of phenomena)- Four supporting submodules (two supporting submodules
for each act-alike module to help understand/analyze test results)
- Two variation submodules (material/configuration/design variations and operation limits)
These requirements are based on “functional” and engineering scaling requirements. There are other more demanding requirements for “Reliability Growth” (See separate section on this)
Importance• Neutron wall load is a primary source of both heating and nuclear
reactions in the blanket– Bulking heating– Surface heating– Reaction rate (e.g., tritium production)– Fluence
Neutron wall load requirements determined by:
• Engineering scaling requirements (conclusion: should not scale down by more than a factor of 2-3
• Tradeoffs between device availability and wall load for a given testing fluence and testing time
Wall Load and Availability Required to Reach 6 MW•y/m2 Goal Fluence in 12 Calendar Years
Wall Load (MW/m2) Availability
1
1.5
2
2.5
50%
33%
25%
20%
For pulsed plasma operation, this becomes the product of availability and plasma duty cycle. Therefore, at any given wall load, higher availability would be required.
Neutron Wall Load Requirements
Importance of Steady State Operation for
Nuclear Testing
• To substantially increase the capability for meaningful nuclear technology testing
• To reduce the failure rate and improve the availability of the testing device
- Many papers and presentations on this topic from
the last 20 years. It is well understood and accepted (see, for example, www.fusion.ucla.edu/abdou)
• Time-Dependent Changes in Environmental Conditions for Testing– Nuclear (volumetric) heating– Surface heating– Poloidal magnetic field– Tritium production rate
• Result in Time-Dependent Changes and Effects in Response of Test Elements that:
– Can be more dominant than the steady-state effects for which testing is desired
– Can complicate tests and make results difficult to model and understand
Examples of Effects– Thermal conditions– Tritium concentration profiles– Failure modes/fracture mechanism– Time to reach equilibrium
Effects of Pulsed Plasma Operation on
Nuclear Technology Testing
• Test Schedule Issues
– It is desirable to complete a test campaign before the machine is shut down for a significant period of time
– The objective of design/test/fix iterative program requires timely data acquisition as input to redesign and construction of new test modules. It is therefore desirable to complete test campaigns as quickly as possible.
• Requirements on Environmental Control
– The level of control over conditions within test modules and ancillary systems during shutdown is uncertain.
Recommended COT for FNT:
1-2 weeks
COT Requirements
Device Fluence vs Test Module Fluence
• Must make a distinction between:
- Fluence achievable at test module ( modules will fail and will be replaced. Module Fluence is the “cumulative” experience accumulated on successive test articles, in “reliability growth” terminology)
- Test facility “lifetime fluence” (The device itself will need to have a longer lifetime than the test articles. The blanket is an exception because it is the “object of testing”, depending on testing strategy)
• Benefits to FNT testing as a function of neutron fluence have been recognized:
- Many issues show continuous increase in benefits at higher fluences
- Some issues show distinct fluence regions of highest benefit
• There is inevitably a long period of fail/replace/fix for test modules
• Time required to perform the three testing stages: The reliability growth testing phase is the most demanding on fluence requirements.
• In this study, we derive fluence directly for each of the three stages of fusion testing
Stage I: Scoping (~ 0.1 - 0.3 MW • y/m2)Just enough time to explore environment, develop instrumentation, and get initial data
Stage II: Concept Verification (1-3 MW • y/m2)1 MW • y/m2 is barely enough to establish engineering feasibility (~10% of minimum life)
Stage III: Engineering Development & Reliability Growth (4-6 MW • y/m2)This fluence is derived from detailed analysis of reliability growth testing
Testing Fluence
Upper statistical confidence level as a function of test time in multiples of MTBF for time terminated reliability tests (Poisson
distribution). Results are given for different numbers of failures.
5.04.54.03.53.02.52.01.51.00.50.00.0
0.2
0.4
0.6
0.8
1.0
Test Time in Multiplies of Mean-Time-Between-Failure (MTBF)
Con
fide
nce
Lev
el
Number of Failures 0
1
2
3
4
Reference: M. Abdou et. al., "FINESSE: A Study of the Issues, Experiments and Facilities for Fusion Nuclear Technology Research & Development, Chapter 15 (Figure 15.2-2.) Reliability Development Testing Impact on Fusion Reactor Availability", Interim Report, Vol. IV, PPG-821, UCLA,1984. It originated from A. Coppola, "Bayesian Reliability Tests are Practical", RADC-TR-81-106, July 1981.
TYPICAL TEST SCENARIO
“Reliability Growth”
Example,
To get 80% confidence in achieving a particular value for MTBF, the total test time needed is about 3 MTBF (for case with only one failure occurring during the test).
Achievable DEMO Reactor and Blanket System Availabilities (for a given confidence level) depend on:
• Testing Fluence at the Blanket Test Module & No. of test modules
• Achievable Mean Time to Replace (MTTR) for Blankets
Findings of Testing Fluence Requirements on Achievable Reactor Availability Analyses
• Achieving a “ cumulative” fluence of ~ 5-6 MW • y/m2 at the test modules with ~ 6-12 test modules is crucial to achieving DEMO reactor availability on the 40% to 50% range with 90% confidence,
• Achieving DEMO reactor availability of 60% with 90% confidence may not be possible for any practical blanket test program,
• The mean downtime (MTTR) to recover (or replace) from a random failure in the blanket must be on the order of one week or less in order to achieve the required blanket and reactor system availabilities, and
• Determining (and shortening) the length of the MTTR (how long it takes to replace a failed blanket module) must be by itself one of the critical objectives for testing in fusion facilities (e.g. in CTF).
Obtainable Blanket System Availability with 50% Confidence for Different Testing Fluences and Test Areas
Test Area (m2)
Obta
inable
Bla
nke
tS
yste
mA
vaila
bili
ty(%
)
0 2 4 6 8 100
10
20
30
40
50
60
70 6 MW.yr/m2
3 MW.yr/m2
1 MW.yr/m2
MTTR = 1 month
1 failure during the test
80 blanket modules in blanket system
Experience factor =0.8
Neutron wall load = 2 MW/m2
Level of Confidence based on Figure 15-2.2 in "FINESSE: A Study of the Issues, experiments and Facilities for Fusion NuclearTechnology Research & Development, Chapter 15 Reliability Development Testing Impact on Fusion Reactor Availability", Interimreport, Vol. IV, PPG-821, UCLA, 1984.
• No. of Modules per Specific Design Concept
– Need for Engineering Scaling and Statistics.– A large number of test modules lead to a faster reliability growth and a higher
precision level.
• Full scale test preferable
– There are many problems that were solved only after setting up a full scale test.– There are also many problems that surfaced only in the full scale test but did not
show in the reduced scale.– Account for neutron flux spatial variation in poloidal direction.
• If each module first wall area is about 1 m2
– Test area required = (6 – 12) x A (for engineering scaling) m2 per concept.
• If test 3 concepts, use 6 modules per concept; or 2 concepts use 12 modules per concept.
Total test area at the first wall required: > 10 m2
Device Surface Area Requirements
Level of Confidence Obtainable for Different Testing Scenarios
Test Fluences = 1 MWyr/m2
Test Fluences = 3 MWyr/m2
Test Fluences = 6 MWyr/m2
Test Area (m2)
# of Test Articles
0 failure during the
test
1 failure during the
test
0 failure during the
test
1 failure during the
test
0 failure during the
test
1 failure during the
test 0.5 1 1.5% ~0% 5% ~0% 10% 0.5% 1 2 3.6% ~0% 9.5% 0.5% 17% 1.5% 5 10 10.9% 0.7% 30% 5.5% 51.5% 16% 10 20 17.8% 1.7% 47% 14% 72% 36%
Neutron wall load = 2 MW/m2MTBF per module = 26 yearsExperience factor = 0.8(*test fluence of 0.1 MWyr/m2 is too low to consider)
Note1) Assuming that the reactor has 16 sectors, 80 blanket modules (each module is about 1(toroidal) x 8 (poloida) m2).
“Engineering scaling” is applied to the test article design in order to have meaningful data extrapolated from a 0.5 m22) The irradiation effects on material properties are not considered in the estimation. 3) Level of Confidence based on Figure 15-2.2 in "FINESSE: A Study of the Issues, experiments and Facilities for Fusion
Nuclear Technology Research & Development, Chapter 15 Reliability Development Testing Impact on Fusion Reactor Availability", Interim report, Vol. IV, PPG-821, UCLA, 1984.
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0 2 4 6 8 10
CTF base machine avaialbility =30% (MTTR blanket = 2 weeks)Demo base machine availability =30% (MTTR blanket = 2 weeks)Demo base machine availability 50% (MTTR blanket = 2 weeks)Demo base machince availability 50% (MTTR blanket= 1 week)
Blanket Module MTBF (year)
The base machine includes 10 major components.CTF FW area 100 m2 with 64 blanket modulesDemo (ITER like FW area 680 m2 and 440 blanket modules)
Reliability/Availability is a challenge to fusion, particularly FW/blanket, development
• Fusion System has many major components (TFC, PFC, plasma heating, vacuum vessel, blanket, divertor, tritium system, fueling, etc.)
All components except the reactor core (FW/blanket) will have reliability data from ITER and other facilities
The reliability requirements on the FW/Blanket are most challenging and pose critical concerns (due to a large number of modules). These must be seriously addressed as an integral part of the R&D pathway to DEMO.
Predicting Achievable MTBF (mean-time-between-failure) requires real data from integrated tests in the fusion environment.
Availability decreases due to the number of module increases
Availability increases due to improved base machine
availability Availability increases due to a shortened MTTR for blanket
1
2
31
2
3
Lifetime of Demo FW/blanket 10 years
Conclusions on Blanket and PFC Reliability Growth
• Blanket and PFC tests in ITER alone cannot demonstrate DEMO availability higher than 4%
• Blanket and PFC testing in VNS (CTF) allows DEMO blanket system and PFC system availability of > 50%, corresponding to DEMO availability > 30%
- Set availability goal for initial operation of DEMO of ~ 30% (i.e. defer some risk)
- Operate CTF and ITER in parallel, together with other facilities, as aggressively as possible
- Realize that there is a serious decision point with serious consequences based on results from ITER and CTF
• If results are positive proceed with DEMO• If not, then we have to go back to the drawing board
Recommendations on Availability/Reliability Growth Strategy and Goals
BACKUP SLIDES
Examples of possible Failure Modes in Blanket/First Wall (for solid and liquid breeder blanket concepts)
• Cracking around a discontinuity/weld• Crack on shutdown (with cooling)• Solid breeder loses functional capability due to extensive cracking • Cracks in electrical insulators (for liquid metal blankets)• Cracks, thermal shock, vaporization, and melting during disruptions• First wall/breeder structure swelling and creep leading to excessive
deformation or first wall/coolant tube failure• Environmentally assisted cracking• Excessive tritium permeation to worker or public areas• Cracks in electrical connections between modules
Our concern is that failure rates may be much higher in fusion blankets because they appear to be much more complex than steam generators and the core of fission reactors because of the following points:
• Larger numbers of subcomponents and interactions (tubes, welds, breeder, multiplier, coolant, structure, insulators, tritium recovery, etc.).
• More damaging, higher energy neutrons.• Other environmental conditions: magnetic field, vacuum, tritium, etc. (for example, a leak
from the first wall or blanket module walls into the vacuum system results in failure, while in steam generators and fission reactors, continued operation with leaks is often possible).
• Reactor components must penetrate each other; many penetrations have to be provided through the blanket for plasma heating, fueling, exhaust, etc.
• Ability to have redundancy inside the blanket / first wall system is practically impossible.
td = doubling time
Current physics and technology concepts lead to a “narrow window” for attaining Tritium self-sufficiency
td=10 yr
td=5 yr
td=1 yr
“Window” for Tritium self sufficiency
Max achievable TBR ≤ 1.15
Req
uire
d T
BR
Fractional burn-up [%]
Fusion power 1.5GWReserve time 2 daysWaste removal efficiency 0.9(See paper for details)
Tritium Consumption in ITER
Here is from a summary of the final design report. Link is:http://fusion.gat.com/iter/iter-ga/images/pdfs/cost_estimates.pdf
9.4.3 Fuel CostsThe ITER plant must be operated, taking into account the available tritium externally supplied. The net tritium consumption is 0.4 g/plasma pulse at 500 MW burn with a flat top of 400 s
“The total tritium received on site during the first 10 years of operation, amounts to 6.7 kg.”
“whereas the total consumption of tritium during the plant life time may be up to 16 kg to provide a fluence of 0.3 MWa/m2 in average on the first wall”
“This corresponds, due to tritium decay, to a purchase of about 17.5 kg of tritium. This will be well within, for instance, the available Canadian reserves.”
ITER TBM is also of great benefit to CTF/VNS
Exactly the same R&D and qualification testing for ITER TBM will be needed for CTF
– Ferritic steel, Ceramic FCI and Breeder, Be development– MHD flow and heat transfer simulation capabilities– Tritium permeation and control technologies– Other safety, fabrication, and instrumentation R&D
But in ITER costs can be shared with international partners
ITER should be used for Concept screening and fusion environment break-in
– Spending years doing screening in CTF will cost hundreds of millions in operation. ITER operation costs are already paid for, and shared internationally
– CTF should be used for engineering development and reliability growth on the one or two concepts that look most promising following screening in ITER
TBM tests in ITER will have prototypical Interactions between the FW/Blanket and Plasma, thus complementing tests in CTF (if CTF plasma and environment are not exactly prototypical, e.g. highly driven with different sensitivity to field ripple, low outboard field with different gradients)
International studies and experts have concluded that extensive testing of fusion nuclear components in FUSION
testing facilities is REQUIRED prior to DEMO
- However, non-fusion facilities cannot fully resolve any of the critical issues for blankets
- There are critical issues for which no significant information can be obtained from testing in non-fusion facilities (An example is identification and characterization of failure modes, effects and rates). Even some key separate effects in the blanket can not be produced in non-fusion facilities (e.g. volumetric heating with gradients)
- The Feasibility of Blanket Concepts can NOT be established prior to testing in fusion facilities
- Non-fusion facilities can and should be used to narrow material and design concept options and to reduce the costs and risks of the more costly and complex tests in the fusion environment. Extensive R&D programs on non-fusion facilities should start now.
Example: Interactions between MHD flow and FCI behavior are highly coupled and require fusion
environment PbLi flow is strongly influenced by MHD interaction with
plasma confinement field and buoyancy-driven convection driven by spatially non-uniform volumetric nuclear heating
Temperature and thermal stress of SiC FCI are determined by this MHD flow and convective heat transport processes
Deformation and cracking of the FCI depend on FCI temperature and thermal stress coupled with early-life radiation damage effects in ceramics
Cracking and movement of the FCIs will strongly influence MHD flow behavior by opening up new conduction paths that change electric current profiles
Simulation of 2D MHD turbulence in PbLi flow
FCI temperature, stress and deformation
Similarly, coupled phenomena in tritium permeation, corrosion, ceramic breeder
thermomechanics, and many other blanket and material behaviors
Separate Devices for Burning Plasma and FNT Development, i.e. ITER + CTF are more Cost Effective and Faster than a Single Combined
Device(to change ITER design to satisfy FNT testing requirements is very expensive
and not practical. To do it in “DEMO” is impossible)
NWL Fusion Power
Fluence
(MW·y/m2)
Tritium Consumption
(TBR = 0)
Tritium Consumption (TBR = 0.6)
Two Device Scenario
1) Burning Plasma (ITER) 0.55 500 MW 0.1 5 kg 2 kg
2) FNT Testing (CTF) >1 < 100 MW > 6 33 kg 13 kg
Single Device Scenario (Combined Burning Plasma + FNT Testing), e.g. ITER with major modifications (double the capital cost)
>1 910 MW >6 >305 kg >122 kg
FACTS- World Maximum Tritium Supply (mainly CANDU) available for Fusion is 27 kg- Tritium decays at 5.47% per year- Tritium cost now is $30M / kg. More tritium will cost $200M / kg.
Conclusion:
- There is no external tritium supply to do FNT testing development in a large power DT fusion device. FNT development must be in a small fusion power device.
Engineering Scaling in “Act-Alike” Test Modules
has Limitations
Engineering scaling laws must be followed
• Preserve important Phenomena
Not all parameters can be scaled down simultaneously
• Simulation is never perfect
• Trade-offs among parameters results
Complex engineering issues are involved
• Large uncertainties in individual issues
• Value judgements on relative importance of different issues and environmental conditions