Full page photo - Gujarat Pollution Control...
Transcript of Full page photo - Gujarat Pollution Control...
ACKNOWLEDGEMENT
We are very much thankful to M/s Shree Renuka Sugars Ltd. by assigning the
preparation of Environment Impact Assessment report for proposed 45 MW
Power Plant at Village. Bharapar, Ta. Gandhidham, Dist. Kutch.
We sincerely acknowledge the efforts made by Mr. Rajesh Rawat (V.P. –
Projects) & other team member of company for co- ordination & logistic
support during this assignment. We are very much thankful to Mr. S. K.
Maheshwari (Group Executive Director & C.O.O.) and Mr. Nitin Puranik
(Executive Director) for giving us an opportunity to work with M/s Shree
Renuka Sugar Ltd.
HARDIKSHAHSECRETARY
State Level Expert Appraisal Committee
Ref. No. : EIA-10-2009- 626-E
~
'hri Nitin Puranik [Executive Director]
Shree Renuka Sugars Limited
Vill Bharapar, Tal Gandhidham,
Dist Kutch
STATE LEVEL EXPERT APPRAISAL
COMMITTEE, GUJARAT.
Forests & Environment Department
Block No. 14/8, SachivalayaGandhinagar-382 010, GUJARAT.
Phone : 079 -23251071, 23252655.Fax: 079 -23251071.Email: [email protected]
Date: May 18, 2010.
Sub:Environment Clearance under the EIA Notification 2006 for your proposed project
at Vill Bharapar, Tal Gandhidham, Dist Kutch
Dear Sir,
This refers to your application on the subject mentioned above and the meeting held with the
State Level Expert Appraisal Committee, Gujarat, on 29th March, 2010. The relevant information
furnished in Form I and presentation made before the SEAC was considered and the additional
TOR's were communicated to you by the SEAC immediately after the said presentation.
However, a copy of the same is attached herewith for further necessary action at your end. You
may please furnish the desired information / documents to enable us to process the application
further.
With regards,
(Har 1 Shah)
Secretary, State Level Expert Appraisal Committee
End :As above.
Shree Renuka Sugars Ltd, Viii Bharapar Tal Gandhidham, Dist Kutch.
It is proposed to install thermal power plant of 45 MW capacity. Expected cost of the
proposed project is Rs. 160 Crores. Land requirement for the proposed power plant will be
@ 56340 sq.m. Requirement of fresh water will be 600 KLD, which will be sourced from
Gujarat Water Infrastructure Ltd. Industrial effluent generation from the proposed power
plant will be 386 KLlday, which will be treated in ETP and treated wastewater will be utilized
for plantation / gardening within the factory premises. Domestic wastewater generation will
be 20 KLlday, which will be disposed off through soak pit. To generate 45 MW power, total
250 TPH steam will be required. It is proposed to install three steam boilers; two boilers
having capacity of 70 TPH and one boiler having capacity of 110 TPH. The proposed power
plant will be operated with DCS technology. Indian Coal - 29816 Kg/Hour and Imported
Coal - 21822 Kg/Hour will be used as fuel in power plant. It is proposed to install one ESP
for two boilers of 70 TPH and one ESP for boiler of 110 TPH with three number of operating
fields. The ESPs have been designed to achieve outlet dust concentration of 100 mg/Nm3
with full load capacity. It is proposed to install opacity meter at the stack for online
continuous monitoring of particulate matter concentration. Bottom ash generation will be 1.3
TPH & 0.15 TPH from each boiler for Indian Coal and Imported Coal respectively. Fly ash
generation will be 5.5 TPH & 0.5 TPH from each boiler for Indian Coal and Imported Coal
respectively. One silo of 30 m3capacity is proposed for storage of bottom ash and one silo
of 400 m3capacity is proposed for storage of fly ash. The ash will be sold to cement
manufacturers. ETP sludge generation will be @ 1 to 1.5 MT/day and it will be disposed at
TSDF site. Used Oil - 1 MT/Month and Waste Oil - 1 MT/Month will also generate as
hazardous wastes. The company has obtained Consent to Establish from the Gujarat
Pollution Control Board on 25/1/2010 for manufacturing of Refined Sugar, Molasses &
Waste Lime.
Technical presentation by the project proponent included introduction of the company,
products of the company, legal requirement for environmental clearance, purpose of the
project, salient features of the project, satellite image showing plant location, on site
meteorology, capacity of power plant, manufacturing process, water consumption,
wastewater generation, fuel consumption, analysis of Indian & Imported Coal, details of
stack & APCM, boilers & auxiliaries, ESP, ash management plan, ash generation and
disposal, proposed TOR etc.
After deliberations on various aspects of the proposed power plant, the TOR proposed by
the project proponent were accepted and the project proponent was asked to include the
following additional TOR for the EIA study to be done covering 10 km radius from the project
boundary of the proposed site:
1. Project site specific details such as distance of the project site from the nearest (1)
Village (2) Water Body : Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National
Highway (4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life
Sanctuary / Reserve Forest shall be included in the rapid EIA report to be prepared
covering one season (other than monsoon) data.
2. Present land use pattern of the study area as well as the project area shall be given
based on satellite imagery.
3. Status of the sugar refinery plant for which Consent to Establish has been obtained from
the GPCB.
4. Layout plan of the factory premises. Provision of continuous unobstructed peripheral
open path within the project area for unobstructed easy movement of the emergency
vehicle / fire tenders without reversing back. Mark the same in the plant layout.
5. Technical details of the proposed power plant alongwith details of strategy for
implementation reuse / recycle and other cleaner production options for reduction of
wastes. Generation of waste gases and utilization of waste heat have to be set out.
6. Assessment of source of the water supply with adequacy of the same to meet with the
requirements for the project. Copy of letter of permission / commitment obtained from
GWIL / GWSSB for supply of fresh water for the proposed power plant.
7. Detailed water balance (including reuse-recycle, if any) alongwith qualitative and
quantitative analysis of the each waste stream to be generated from all sources
including Boilers, Cooling Towers, D.M. Plant etc. Details of methods to be adopted for
the water conservation. Explore feasibility for complete waste water recycling / reuse to
achieve zero discharge.
8. Characteristics of untreated and treated wastewater. A detailed effluent treat ability
study vis-a-vis the adequacy and efficacy of the treatment facilities proposed for the
wastewater to be generated alongwith adequacy and efficacy report. The characteristic
on which treatability is based shall also be stated.
9. Details of the ETP units including its capacity, size of each unit, retention time and other
technical parameters and details about up-gradation in the existing ETP (if any
proposed) to take care of the increased wastewater generation due to the proposed
CPP.
10. Application wise break-up of treated effluent quantity to be recycled / reused in various
applications like sprinkling on roads, storage yard and green belt development etc.
Details about availability of open land for utilizing increased quantum of effluent due to
the proposed power plant for plantation / gardening. How it will be ensured that treated
effluent won't flow outside the premises linked with storm water during high rainy days.
11. One season site-specific meteorological data including temperature, relative humidity,
hourly wind speed and direction and rainfall shall be provided
12. One complete season AAQ data (except monsoon) to be given along with the dates of
monitoring. The parameters to be covered shall include PM1O, PM25, S02, NOx and Hg.
The location of the monitoring stations should be so decided so as to take into
consideration the pre-dominant downwind direction, population zone and sensitive
receptors including reserved forests. There should be at least one monitoring station in
the upwind direction. There should be at least one monitoring station in the pre
dominant downwind direction at a location where maximum ground level concentration is
likely to occur.
13. Impact of the project on the AAQ of the area. Details of the model used and the input
the parameters used for modeling should be provided. The air quality contours may be
plotted on a location map showing the location of project site, habitation, sensitive
receptors, if any. The wind roses should also be shown on this map.
14. Quantity of fuel required, its source and transportation. Fuel analysis to be provided
(sulphur, ash content and heavy metals including Pb, Cr, As and Hg). A confirmed fuel
linkage should be provided.
15. Specific details of (i) Details of the utilities required (ii) Flue gas emission rate from each
utility (iii) Air Pollution Control Measures proposed to each of the utility along with its
adequacy.
16. The ESPs have been to be get redesigned to achieve outlet dust concentration of 50
mg/Nm3with full load capacity instead of 100 mg/Nm3. Technical details of ESP along
with its adequacy, details of its operational controls with DCS, system for online
monitoring of the pollutants from the stack etc. Details of provisions to be kept in ESP to
ensure that in any case the air emission does not cross the GPCB norms including
provision of standby field in the ESP, preventive maintenance, failure / tripping control
system, guarantee from the ESP supplier, alternative arrangements in case of the failure
/ tripping of the ESP etc.
17. List of all the sources of fugitive emission. Detailed plan for prevention and control of
fugitive emission / dusting at each and every stage of fuel handling including unloading /
loading at port, transportation from port to plant, unloading / loading / stacking /
conveyance / transfer at plant etc. Detailed specifications and schematic diagram of
water sprinkling system including number of sprinklers to be installed, pipe diameter and
nozzle diameter of the sprinklers, quantity of water to be consumed by sprinklers etc.
18. Impact of the project on local infrastructure of the area such as on road network due to
transportation of fuel, ash etc. Proposal to construct @ 1 Km long asphalted road for
approach to the factory. and whether any additional infrastructure would need to be
constructed and the agency responsible for the same with time frame.
19. Details of flora and fauna duly authenticated should be provided. In case of any
scheduled fauna, conservation plan should be provided.
20. Details of management of the hazardous wastes to be generated from the project stating
detail of storage area for each type of waste, its handling, its utilization and disposal etc.
How the manual handling of the hazardous wastes will be minimized.
21. Detailed plan of ash evacuation, handling and utilization should be provided.
Undertaking stating that ash pond shall not be constructed and it shall be stored in
closed silos only should be incorporated.
22. Copy of membership certificate of Common Environmental Infrastructure like TSDF, if
any taken, should be incorporated. Copies of MOU / agreements done with actual
consumers regarding utilization of fly ash, bottom ash etc. should also be incorporated.
23. Details of measures proposed for the noise pollution abatement and its monitoring.
24. A detailed EMP including the protection and mitigation measures for impact on human
health and environment as well as detailed monitoring plan and environmental
management cell proposed for implementation and monitoring of EMP. The EMP should
also include the concept of waste-minimisation, recycle/reuse/recover techniques,
energy conservation, and natural resource conservation. Total capital cost and recurring
cost/annum earmarked for environment pollution control measures.
25. Occupational health impacts on the workers and mitigation measures proposed to avoid
the human health hazards along with the personal protective equipment to be provided
to the workers. Provision of industrial hygienist and monitoring of the occupational injury
to workers as well as impact on the workers. Plan for periodic medical check up of the
workers exposed. Details of work zone ambient air quality monitoring plan as per
Gujarat Factories Rules.
26. Risk assessment including prediction of the worst-case scenario and maximum credible
accident scenario related to fire and explosion issues due to storage and use of fuel
should be carried out. The worst-case scenario should take into account the maximum
inventory of storage at site at any point in time. The risk contours should be plotted on
the plant layout map clearly showing which of the activities would be affected in case of
an accident taking place. Based on the same, proposed safeguard measures including
On-Site / Off-Site emergency plan should be provided. Measures to guard against fire
hazards including details of automatic fire detection and control system & detailed fire
control plan showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey
pump, toxic gas detectors etc. should also be provided.
27. Submit checklist in the form of Do's & Don'ts of preventive maintenance, strengthening
of HSE, manufacturing utility staff for safety related measures.
28. Detailed five year greenbelt development program including annual budget, types &
number of trees to be planted, area under green belt development [with map], budgetary
outlay; along with commitment of the management to carry out the tree plantation
activities outside the premises at appropriate places in the nearby areas and elsewhere.
29. Proposal for socio-economic development activities including community welfare
program most useful in the project area for the overall improvement of the environment.
Submit a detailed plan for social corporate responsibilities, with appropriate budgetary
provisions for the next five years and activities proposed to be carried out; specific to the
current demographic status of the area.
30. A tabular chart for the issues raised and addressed during public hearing/consultation
and commitment of the project proponent on the same should be provided. An action
plan to address the issues raised during public hearing and the necessary allocation of
funds for the same should be provided.
31. Details of scheme for surface as well as roof top rain water harvesting and ground water
recharge should be included.
32. Plan for compliance of the CREP guidelines for the proposed power plant.
33. Point wise compliance of the specific and general conditions stipulated in the Consent to
Establish order issued by the GPCB for the sugar refinery.
34. Any litigation pending against the project and / or any direction / order passed by any
Court of Law against the project, if so, details thereof.
These additional TORs should be considered for the preparation of the draft EIA report in
addition to all the relevant information as per the generic structure of EIA given in Appendix III in
the EIA Notification, 2006. The draft EIA report shall be submitted to the Gujarat Pollution
Control Board for conducting the public consultation process as per the provisions of the EIA
Notification, 2006. The project shall be appraised on receipt of the final EIA report.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |TOR.1
COMPLIANCE OF TOR
TOR Point No. Reference Documents Page no.
1 Chapter 2 point no. 2.2 Chapter 3 point no. 3.1.1
Page No. 2.1 Page No. 3.2
2 Chapter 3 Point no. 3.1.1 Figure 3.1
Page No. 3.2 Page No. 3.3
3 Annexure- A Copy of NOC issued by GPCB
---
4 Annexure –C Layout plan of Company
---
5 Chapter 2 Page no. 2.1 to 2.18
6
Source of water supply will be company’s own Desalination plant having capacity of 5000 KLD. The company has applied for 1.5-2 MLD water permission from GWIL .
7 Chapter 2 point no. 2.4.5.3 (ii) Page no. 2.5
8 Chapter 2 point no. 2.5.2 Page No. 2.12, 2.13,2.14
9 Chapter 2 point no. 2.5.2.2 Page No. 2.15, 2.16 10 Chapter 2 Point no. 2.4.5.3 (ii) Page No. 2.6 11 Chapter 3, point 3.3.2 Page no. 3.14 to 3.19 12 Chapter 3, Point 3.4 Page no. 3.20 to 3.24 13 Chapter 3, point 3.5 Page no. 3.25 to 3.30 14 Chapter2, point 2.4.5.2 Page no. 2.4 15 Chapter 5, Point no. 5.1(B) Page no. 5.2 16 Chapter 6, Point no. 6.5.4 Page no. 6.23
17 Chapter 5 , Point no. 5.1 A & B Chapter 4 , Point no. 4.2, 4.3
Page no. 5.1, 5.2 Page no. 4.4, 4.5, 4.7,4.8
18 Chapter 7, Point no. 7.2 Page no. 7.1 19 Chapter 3 , Point no. 3.7 Page no. 3.35 to 3.61 20 Chapter 4, Point no. 4.3.4 Page no. 4.10, 4.11
21 Chapter 5, Point no. 5.5 Annexure 2.3
Page no. 5.5 to 5.7
22
Company will apply for membership of TSDF it and will done agreement with consumers regarding flyash, bottom ash, used oil and waste oil after getting NOC from GPCB.
N.A.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |TOR.2
23 Chapter 5 point no. 5.10.4 & Table no. 5.10
Page no. 5.10, 5.11
24 Chapter 5 Page no. 5.1 to 5.11 25 Chapter 5 Page no. 5.1 to 5.11
26 Chapter 6. point no. 6.4 Point no. 6.9
Page no. 6.14 to 6.21 Page no. 6.30 to 6.35
27 Chapter 5, Point no. 5.10.5 Page No. 5.12 28 Chapter 5, Point no. 5.8 Page no. 5.7 , 5.8 29 Chapter 7 Page no. 7.1, &7.2 30 Will be added after public hearing. N.A.
31 Chapter 8 Page no. from 8.1 to 8.30
32 All the CREP guidelines will be followed by the company.
-------
33 Annexure B- compliance of NOC 34 No
INDEX
Sr. No. Description Page no. CHAPTER-1 INTRODUCTION OF THE COMPANY
1.1 Introduction of the company 1.1 1.2 Location of the project 1.1 1.3 Scope of the study 1.2 1.3.1 Project Description 1.2 1.3.2 Description of Environment 1.2 1.3.3 Meteorology 1.3 1.3.4 Air quality 1.3 1.3.5 Water quality 1.3 1.3.6 Soil quality 1.3 1.3.7 Noise 1.3 1.3.8 Environmental Monitoring Programme 1.3 1.3.9 Project Benefit 1.4 1.3.10 Environment Management Plan 1.4 1.3.11 Risk Assessment 1.4
CHAPTER-2 PROJECT DESCRIPTION 2.1 Purpose of the project 2.1 2.2 Location & silent features of the project 2.1 2.3 Proposed schedule for approval and
implementation 2.2
2.4 Analysis of alternative for site and technology 2.2 2.4.1 Site alternative 2.3 2.4.2 Technology Alternative 2.3 2.4.3 Brief Project Details 2.3 2.4.4 Details of Project Facilities 2.4 2.4.5 Description of Proposed power plant 2.4 2.4.5.1 Capacity 2.4 2.4.5.2 Fuel Details for proposed power plant 2.5 2.4.5.3 Process Detail 2.9 2.4.5.4 List of equipments and its capacity 2.10 2.5 Sources of pollution and control measures 2.10 2.5.1 Air pollution & Control Measures 2.10 2.5.1.1 Sources of Air pollution 2.12 2.5.1.2. Air pollution control measures 2.12 2.5.2 Water pollution & Control Measures 2.12 2.5.2.1 Sources of Waste water generation 2.12 2.5.2.2 Water pollution control measures 2.14
2.5.3 Solid waste Management 2.17 2.5.3.1 Solid waste generation 2.17 2.5.3.2 Solid Waste disposal 2.17 2.5.4 Noise pollution & control Measures 2.18
CHAPTER 3: DESCRIPTION OF ENVIRONMENT 3.0 Site & Surrounding area 3.1 3.1 Land Use 3.1 3.1.1 Land use classification based on satellite
imaginary 3.2
3.1.2 Land Use classification based on census Data 2001
3.3
3.2 Demography and Socio- Economics 3.6 3.2.1 Demographic profile of the study area 3.6 3.2.1.1 House holds/ Occupied residential houses and
total population 3.6
3.2.1.2 Sex Ratio 3.7 3.2.1.3 Scheduled castes and schedule tribes 3.7 3.2.1.4 Literacy 3.7 3.2.2 Socio Economic Profile of the study area 3.7 3.2.2.1 Distribution of work participation rate 3.7 3.2.3 Availability of Infrastructure facilities and
Amenities 3.10
3.3 Meteorology & Climatology 3.13 3.3.1 Past Records 3.13 3.3.1.1 Data Collected 3.13 3.3.1.2 Analysis of climatologically Data 3.14 3.3.1.3 Rainfall 3.14 3.3.1.4 Temperature 3.14 3.3.2 On-site meteorology 3.15 3.3.2.1 Wind Speed and Direction 3.19 3.3.2.2 Temperature 3.19 3.3.2.3 Relative Humidity 3.20 3.3.2.4 Rain Fall 3.20 3.4 Ambient Air Quality 3.20 3.4.1 Methodology Adopted for the study 3.20 3.4.2 Criteria for selection of monitoring Locations 3.20 3.4.3 Frequency and parameter for monitoring 3.21 3.4.4 Details of the monitoring locations 3.21 3.4.5 Instrument used for sampling 3.21 3.4.6 Method for sampling and analytical Technique 3.22 3.4.7 Presentation of result 3.22 3.4.8 Observation based on Monitoring Data 3.23
3.4.8.1 Suspended Particulate Matter(PM10) 3.23 3.4.8.2 Suspended Particulate Matter(PM2.5) 3.23 3.4.8.3 Sulfur Dioxide 3.23 3.4.8.4 Oxide of Nitrogen 3.23 3.4.9 Conclusion 3.24 3.5 Air modeling 3.25 3.5.1 Details of Process stack 3.25 3.5.2 Assessment of Impact based on ISCST3 model 3.25 3.5.3 Model Input 3.26 3.5.4 Presentation of Result 3.26 3.5.5 Meteorological data input 3.26 3.6 Land Environment 3.27 3.6.1 Topography of the study Area 3.31 3.6.2 Baseline Data for soil 3.31 3.6.3 Methodology 3.32 3.6.4 Physical Characteristics 3.33 3.6.5 Conclusion 3.33 3.7 Biological Environment 3.35 3.7.1 Terrstrial Environment 3.35 3.7.2 Period of the study and area 3.35 3.7.3 Methodology 3.35 3.7.4 Terrestrial floral and faunal components of the
study area 3.35
3.7.5 Floral Diversity of the study area 3.37 3.7.5.1 Trees 3.38 3.7.5.2 Shrubs 3.38 3.7.5.3 Herbs 3.40 3.7.5.4 Climbers and Twiners 3.41 3.7.6 Cultivated Plants in the study area 3.42 3.7.6.1 Major Crops 3.42 3.7.6.2 Minor Crops 3.42 3.7.6.3 Pulses 3.42 3.7.6.4 Vegetables 3.43 3.7.7 Horticultural practices and fruits grown 3.43 3.7.8 Medicinal Plants of the study area 3.43 3.7.9 Ethanobotaniclal important plants and
practices prevailing in the area 3.47
3.7.10 Endemic Plants of the study area 3.48 3.7.11 Faunal biodiversity of the study area 3.48 3.7.12 Birds of the study area 3.49 3.7.13 Endemic Fauna of the study area 3.55 3.7.14 Migratory birds as winter visitors in the study 3.56
area 3.7.15 Status of the forest, their category in the study
area 3.56
3.7.16 Recommended plants for green belt development
3.56
3.7.16.1 Selection of plants for green belts 3.57 3.7.16.2 Plantation along road sides 3.57 3.7.17 Impact on flora and fauna in the region due to
the project activities 3.59
3.8 Water Environment 3.61 3.8.1 Methodology for Water quality Monitoring 3.62 3.8.2 Details of analysis method and instrument used 3.63 3.8.3 Physico-chemical Characteristics 3.64 3.8.4 Conclusion 3.65 3.9 Noise Environment 3.66 3.9.1 Methodology for Noise Environment 3.66 3.9.2 Noise Level 3.67 3.9.3 Conclusion 3.68
CHAPTER 4: ANTICIPATED ENVIRONEMNTAL IMPACT & MITIGATION MEASURES
4.1 Impact & Measures 4.1 4.2 Mitigation measures during construction phase 4.4 4.2.1 Air Environment 4.4 4.2.2 Noise Environment 4.5 4.2.3 Water Environment 4.5 4.2.4 Land Environment 4.5 4.2.5 Biological Environment 4.6 4.2.6 Impact on Health & Safety 4.6 4.2.7 Risk and Safety 4.6 4.2.8 Socio- Economic Environment 4.6 4.3 Mitigation measures during operation &
Maintenance 4.7
4.3.1 Air Environment 4.7 4.3.2 Noise Environment 4.9 4.3.3 Water Environment 4.9 4.3.4 Land pollution by handling of Hazardous/solid
waste 4.10
4.3.5 Socio-Economic Environment 4.11 4.3.6 Bio- Ecological Environment 4.11
CHAPTER 5: ENVIRONMENT MANAGEMENT PLAN 5.1 Air Environment 5.1 5.2 Water Environment 5.3
5.3 Noise Environment 5.3 5.4 Solid Waste 5.4 5.5 Fly Ash Management Plan 5.5 5.5.1 Action plan for fly ash disposal 5.6 5.6 Rain water harvesting scheme 5.6 5.7 Socio Economic Development 5.7 5.8 Green belt development 5.7 5.9 Environment Management Cell 5.8 5.10 Environmental Monitoring during operation
phase 5.10
5.10.1 Ambient Air monitoring 5.10 5.10.2 Stack Monitoring 5.10 5.10.3 Water quality Monitoring 5.10 5.10.4 Noise Monitoring 5.10 5.10.5 Do’s & Don’ts 5.12
CHAPTER 6 RISK ASSESSMENT 6.1 Executive summary 6.2 6.2 Introduction 6.3 6.3 Process Description 6.5 6.4 Risk Analysis due to storage/handling of coal 6.14 6.5 Risk analysis for the boiler 6.22 6.6 Risk analysis for steam turbine generator set 6.25 6.7 Risk analysis for Ash handling system 6.27 6.8 Risk analysis for Air pollution control
measures 6.28
6.9 Proposed fire fighting system. 6.30 CHAPTER 7 PROJECT BENEFITS
7.1 Improvement to full fill the sugar Deficit in Country
7.1
7.2 Improvement in Infrastructure 7.1 7.3 Employment Potential 7.2
CHAPTER 8 RAIN WATER HARVESTING PLAN 8.1 Introduction 8.1 8.2 Need for Artificial Recharge Project 8.2 8.3 Basic Requirement for Artificial Recharge
Project 8.3
8.4 Main Consideration for selection of Recharge Structure
8.4
8.4.1 Proposed Recharge structure in plant Area 8.5 8.4.1.1 Roof top Rain Water Harvesting 8.5 8.4.1.1.1 Raw Sugar Warehouse 8.6 8.4.1.1.2 General Store 8.15
8.4.1.1.3 White Sugar Warehouse 8.17 8.4.1.1.4 Future White sugar Warehouse 8.23 8.4.1.1.5 Contour Bunds in open Area 8.27 8.5 Total Rain Water Harvesting 8.29
LIST OF ANNEXURE Annexure Description Page no.
2.1 Process flow diagram 1 2.2 Process flow diagram of Coal handling System 2 2.3 Process flow diagram of Ash Handling system 3 6.1 Fire Water Network Diagram 4
6.2 Layout plan of Factory Premises Showing Unobstructed Open Path For Easy Movement Of Emergency Vehicle
5
A Copy of NOC A B Compliance of NOC B C Layout Plan of Company C Executive Summary (English) ESE.1 Executive Summary (Gujarati) ESG.1
LIST OF FIGURES
Figures Description Page No. 1.1 Location map 1.5 1.2 Satellite Imaginary Map 1.6 3.1 Base Map for 10 KM radius from project site. 3.3 3.2 Land use classification Area Ta. Gandhidham 3.5 3.3 Land use classification Area Village: Bharapar 3.6 3.4 Total population for village Bharapar 3.7 3.5 Total population for Ta: Gandhidham 3.7
3.6 & 3.7
Distribution of work Participation rate for Ta: Gandhidham
3.9
3.8 Windrose Diagram 3.18 3.9 Windrose Diagram 3.19 3.10 Isoplethe for SPM 3.28 3.11 Isoplethe For Sox 3.29 3.12 Isoplethe for Nox 3.30 8.1 Recharge System for Raw Warehouse Segment I 8.8 8.2 Recharge System for Raw Warehouse Segment II 8.10 8.3 Recharge System for Raw Warehouse Segment
III 8.12
8.4 Recharge System for Raw Warehouse Segment IV
8.14
8.5 Recharge System for General Store 8.16 8.6 Recharge System for White Sugar Warehouse
No. I 8.18
8.7 Recharge System for White Sugar Warehouse No. II
8.20
8.8 Recharge System for White Sugar Warehouse No. III
8.22
8.9 Recharge System for Future White Sugar Warehouse No. I
8.24
8.10 Recharge System for Future White Sugar Warehouse No. II
8.26
8.11 Contour Bund with Recharge Trench 8.29
LIST OF TABLES
Sr. No. Description Page No. 3.1 Land use Statistic of Renuka Sugar Industries (10
km radius) based on satellite imaginary 3.2
3.2 Land use classification Area of Ta. Gandhidham Based on Census 2001
3.5
3.3 Land Use classification Area of Village: Bharapar based on Cencus 2001
3.5
3.4 Distribution of work Participation Rate 3.9 3.5 Medical Facilities 3.11 3.6 Postal facilities 3.12 3.7 Salient Climatologically Features of Bhuj 3.14 3.8 Meteorological Data For March-10 3.15 3.9 Meteorological Data For April-10 3.16 3.10 Meteorological Data For May-10 3.17 3.11 Ambient Air monitoring Locations 3.21 3.12 Ambient Air quality Monitoring Results 3.22 3.13 NAAQ standard 3.25 3.14 Soil samples locations 3.32 3.15 Methodology for soil testing 3.33 3.16 Physical Characteristics of soil 3.34 3.17 List of villages covered under present baseline
study 3.36
3.18 Trees in the study area 3.38 3.19 Shrubs in the study area 3.40 3.20 List of Hebaceous species observed in study area 3.41 3.21 List of Climers observed in study area 3.42 3.22 Medicinal plants in study area and their medicinal
uses 3.43
3.23 Threatened and near Threatened birds of the study area
3.49
3.24 List of birds in the study area with its distribution and migratory status
3.50
3.25 Butterflies in the study area 3.54 3.26 Reptiles in the study area 3.54 3.27 Wild mammals in core zone 3.55 3.28 Mammals in the buffer zone 3.55 3.29 Migratory birds as winter visitors in the study
area 3.56
3.30 Recommended Plant species for green belt 3.58
development 3.31 Location of water samples 3.62 3.32 Analysis method and instrument used for water
testing 3.63
3.33 Physico chemical Characteristics 3.65 3.34 Noise monitoring Locations 3.67 3.35 Noise level 3.67 4.1 Identification of construction activities and
Probable impact 4.2
4.2 Identification of operation and maintenance activities and probable impact
4.4
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |1.1
CHAPTER 1
INTRODUCTION OF THE COMPANY
1.1 SHREE RENUKA SUGARS LIMITED (SRSL)
• The company was founded by Mr. Narendra Murkumbi and Mrs. Vidhya
Murkumbi in 1998, not just dreamers but doers in their own right.
• The combination of doers and dreamers produced enriching results: Over the
last decade, the company has emerged among the most exciting proxies of
conventional Indian Industry; the company is one of the largest and fastest
growing sugar industries in India.
• SRSL has its corporate office in Mumbai and headquarter in Belgaum
(Karnataka). Its crane crushing operations are located in Karnataka and in
Maharashtra (Munoli, Athani, Havalgah & Gokak sugars in Karnataka and
Ratnaprabha sugars in Maharashtra).
• It also operate three leased facilities at Arag (Maharashtra), Aland & Raibag
(Karnataka).
• The company posses India’s largest sugar refining capacity (4000 Tons per
day) across the two integrated refineries ( 1000 TPD each at Munoli and
Athani) and port based refinery in Haldia (2000 TPD).
• Acquisition of majority stack in KBK –Chem. Engineering Pvt. Ltd facilities
turnkey distillery, ethanol and bio-fuel plant solution. SRSL has acquired 100
KLPD distilleries from Petrochem (Khopli, Maharashtra) that converts rectify
spirit into ethanol and increased its production capacity to 300 TPD.
1.2 LOCATION OF THE PROJECT
The location of proposed project is at survey no.,
230/1,225/2,223/2,226/1,225/1,231/2,231/3,228/1,228/2,229/1,214, Village:
Bharapar, Ta. Gandhidham, Dist. Kutch (Refer Figure 1 and 2) Located At
Latitude 23° 0'51.70"N & On Longitude 70° 5'29.70"E in Eastern Gujarat.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |1.2
1.3 SCOPE OF THE STUDY
In order to identify the environmental impacts due to proposed 45 MW coal
based power plant & to draw a suitable environmental management plan to
mitigate adverse impacts, if any, an Environmental Impact Assessment study
has been undertaken.
The satellite picture of the location is shown in Figure – 1.
M/s. Shree Renuka Sugar Ltd. (SRSL) has retained M/s. Royal Environment
Auditing & Consultancy Services, Rajkot to carry out Environmental Impact
Assessment for 45 MW coal based power plant at village Bharapar, Ta.
Gandhidham, Dist. Kutch.
The EIA Study covers baseline data generation, predictions and evaluation of
impact on various environmental components and formulation of
Environmental Management Plan and Disaster Management Plan. The Scope
of the EIA Study is briefly described in the following sections.
1.3.1 PROJECT DESCRIPTION
This includes a concise description of Existing process which is likely to affect
environment. It includes Type of Project, Need for the Project (based on
demand supply position), Location Details, Magnitude of Operation, Proposed
Schedule for Approval and Implementation, Project Description (Layout,
Components etc.), Mitigation Measures to meet environmental standards,
environmental operating conditions etc., presented in Chapter 2.0.
1.3.2 DESCRIPTION OF THE ENVIRONMENT
The baseline environmental scenario has been established through primary
data generated in the study area and secondary data available at site/ published
in literature. The field monitoring started in first week of March, 2010 and
completed on last week of May-2010.
The EIA Report is based on primary data collected during March-2010 to
May-2010 for meteorology, air quality, and noise and secondary data (for the
relevant disciplines). The baseline environmental scenario has been presented
in Chapter 3.0 and methodologies adopted under various disciplines are briefly
described in following sections.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |1.3
1.3.3 METEOROLOGY
On site meteorological data was generated during the study period from
March-2010 to May-2010.
1.3.4 AIR QUALITY
Ambient Air Quality has been characterized with respect to PM2.5, PM10,
SO2, NOx by field monitoring at six locations within 10 KM radius.
At each location, 24 hour sampling was undertaken twice a week. The data
was analyzed for maximum, minimum and average and compared with
National Ambient Air Quality Standards.
1.3.5 WATER QUALITY
Water samples are taken from six locations within 10 KM radius. The water
quality has been characterized with respect to color, pH, TDS, turbidity,
conductivity, phosphate, oil & grease, total hardness, total alkanity, sulfate,
chloride, Dissolved oxygen.
1.3.6 SOIL QUALITY
Soils samples are taken from six locations within 10 KM radius. The soil
quality has been characterized with respect to pH, Bulk density, soil texture,
phosphorus, potassium, calcium, sulphate, organic matter, moisture content
etc.
1.3.7 NOISE
A noise survey was undertaken at 08 locations within the study area and inside
the plant to assess the background noise levels in different zones.
1.3.8 ENVIRONMENTAL MONITORING PROGRAMME
Based on the finding of impact assessment and recommendation in the EIA an
environmental monitoring programmer has been formulated for M/s Shree
Renuka Sugar Ltd.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |1.4
The monitoring programmer specifies the locations, parameters,
methodologies and frequency of monitoring for emissions and discharges as
well as ambient environment for the major disciplines. It is included in
Chapter 5.0, i.e. Environmental Monitoring Programme.
1.3.9 PROJECT BENEFITS
� The annual production of sugar in India in current year is expected to be only
around 14.7 – 15 Million tons which is very much below the annual
consumption of India of 22 Million tons.
� To meet this deficit , Govt. of India has allowed to import of Raw Sugar and to
capitalize on this scenario SRSL has decided to expand the sugar refining
capacity and choose this location of future refineries so as to be able to easily
import, process and export sugar.
� Others aspects are summarized in Chapter 6.0.
1.3.10 ENVIRONMENTAL MANAGEMENT PLAN
It includes Environmental Management Plans for Shree Renuka Sugar Ltd
summarized in Chapter no. 7. It includes the description of the institutional
set-up for ensuring that meditative measures are implemented and their
effectiveness monitored, after approval of the EIA.
1.3.10 RISK ASSESSMENT
Risk assessment is carried out with consideration of maximum inventory of
storage at site. It also includes the safety measures like fire detection and
control system & detail control plan showing hydrant pipeline network, fire
pumps, jockey pumps etc.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |1.5
Figure 1 Location map
fi
Figure 2
Satellite Imaginary Map
Project Site
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |1.6
Figure 1.2
Satellite Imaginary Picture
Royal Environment Auditing & Consultancy Service Page |2.1
CHAPTER 2
PROJECT DESCRIPTION 2.1 PURPOSE OF THE PROJECT
The annual production of sugar in India in current year is expected to be only
around 14.7 – 15 Million tons which is very much below the annual
consumption of India of 20 - 22 Million tons. In next two years also the
production is expected to be very much lower than the local demand for it .To
meet this deficit Govt. of India has allowed import of Raw Sugar and to
capitalize on this scenario SRSL has decided to expand the sugar refining
capacity and choose location of future refineries so as to be able to easily
import, process and export sugar.
To fulfill the process steam & power requirement for Sugar refinery, the
company has proposed to set up 45 MW power plant.
2.2 LOCATION & SILENT FEATURES OF THE PROJECT
Location of Project Survey no. 230/1,225/2,223/2,226/1,225/1,231/2,231/3,228/1,228/2,229/1,214 , Village: Bharapar, Ta. Gandhidham, Dist. Kutch
Capacity 45 MW Coal Based Power plant Capital Investment 160 Cr Total Land Area For Power plant 56340 m3
For Green Belt Development 55000 m2 Source of Water Company’s Own Desalination Plant (capacity: 5000 KLD) Nearest river None within 10 km radius Nearest Industries Sal steels Ltd & Shaifali Rolls Ltd National Park/ Sanctuary
Within 10 KM radius of proposed project there is no notified wildlife sanctuary/parks or any such ecologically sensitive area or reserved forest area.
Nearest Railway station
Gandhidham ~10 km
Nearest High Way National High way no. 8A ~10 km Nearest Port Mundra Port (~25 km)/ Kandla (~40km) Nearest Air port Gandhidham Air port ~ 10 km
Royal Environment Auditing & Consultancy Service Page |2.2
2.3 PROPOSED SCHEDULE FOR APPROVAL AND
IMPLEMENTATION
The zero date of the project is reckoned from the date of grant of “Consent to
Establish” (NOC) by the GPCB. The proposed expansion project will be
commissioned within 12 to 18 months from the date of grant of “Consent to
Establish” (NOC) from GPCB & Environmental Clearance from Department
of Environment and Forest, Gandhinagar.
The company has already got “Consent to Establish” (NOC) from GPCB for
sugar refinery vide up to NOC order no. GPCB/CCA/Kutch-736/id
25015/42596 dated 25th Jan-2010.
2.4 ANALYSIS OF ALTERNATIVE FOR SITE AND TECHNOLOGY
Shree Renuka Sugars Limit is proposed to set up 45 MW power plant at
village Bharapar, Ta. Gandhidham and Dist. Kutch.
Analysis of alternative based on site and technology is given below.
2.4.1 SITE ALTERNATIVE
To set up sugar refinery is a site specific project and it is not possible to
choose alternative site due to restriction of raw materials like raw sugar,
imported coal and port facilities.
Considering all the factors, the site has been identified as the preferred site
amongst the other port sites of Gujarat namely; Mundra, Veraval, Pipavav
Kandla Ports etc.
Factors which have weighed in favor of the site are briefly as follows: -
• Mundra Port/Kandla port is large enough to receive Panamax vessels
with adequate draft of 18 meters.
• Reliability and availability of utilities like water, fuel, electricity, etc.
• Possible to supply sea water and returning to sea.
• Excellent existing infrastructure.
• Sufficient conveyor space available from Jetty to loaders
• Transport convenience being on the existing Kandla-Ahmadabad
highway
Royal Environment Auditing & Consultancy Service Page |2.3
• Nearby container terminal at Mundra /Kandla provides competitive
edge for export of refined sugar
• Project Site is free from intense weather conditions, i.e. rain, snow,
hurricanes and allows year round shipping activity.
• The Site has been selected as the best site for the establishment of
Sugar Refinery.
• Availability of land for sugar refinery and 45 MW power plant.
• Absence of any irrigation canal or drainage channel within a selected
area.
• There is no displacement
• No Ecological sensitive placed within 10 KM radius
• Availability of Mundra port located at a distance of 25 km and kandla
port at distance of 40 km for finished product transportation and
receipt of raw material & fuel.
• Availability of workers in nearby areas.
2.4.2 TECHNOLOGY ALTERNATIVE
• Technical concept and equipment sizing has been finalized based on
determinates and industry norms for Coal based power plant.
Emphasis has been given on optimum layout, energy efficient and
environment friendly modern power plant considering all project
aspects.
• The laboratory is equipped for testing of raw materials, fuel and
sample preparation as well as chemical and physical testing.
2.4.3 BRIEF PROJECT DETAILS
Shree Renuka Sugars Ltd is proposed to established sugar refinery (3000
TPD) and to fulfill the requirement of Power and steam for this sugar refinery,
the company is proposed to set up 45 MW Coal based power plant at Village.
Bharapar, Ta. Gandhidham, Dist. Kutch.
Royal Environment Auditing & Consultancy Service Page |2.4
2.4.4 DETAILS OF PROJECT FACILITIES
Area for power plant : 56340 M2
Area of Green Belt : 55000 M2
Plant Capacity : 45 MW Coal Based Power Plant
2.4.5 DESCRIPTION OF PROPOSED POWER PLANT.
2.4.5.1 CAPACITY
The capacity of Power plant is 45 MW (1 no. 30 MW Extraction cum
Condensing TG set and 1 no. 15 MW Back pressures T G sets).
2.4.5.2 FUEL DETAILS FOR PROPOSED POWER PLANT.
Details of present and proposed raw materials consumption is given below;
Sr. No. Type of Fuel Quantity
(Tons/Hr.)
1. Imported Coal 21.822
Transportation:
It is expected that the coal supplied to the proposed power plant will be from
Indonesia Coal fields and will have properties equal to or superior to the India
coal. From the Port the coal will be transported in trucks to the site.
The coal used for the process will have the below mention quality
Sr. No. Parameter Imported Coal
Approximate Analysis 1 Total Moisture 33 2 Inherent Moisture 15% 3 Ash 6% 4 Volatile Matter 40% 5 Fixed Carbon 41% 6 Sulfur 0.7-1% 7 GCV 5400 Kcal/kg
Royal Environment Auditing & Consultancy Service Page |2.5
Sr. No. Parameter Imported Coal Ultimate Analysis
1. Carbon 53% 2 Hydrogen 3.97 3 Nitrogen 0.92 4 Oxygen 3.57
2.4.5.3 Process Details: (Refer Annexure-2.1)
i) Steam Boiler
Steam is generated in the two nos. of Atmospheric Fluidized Bed boiler of 70
TPH at a pressure of 86 Kg/cm2g by using Indian as well as imported coal as
fuel & water from RO plant where raw water will be treated in the water
treatment plant as per the flow sheet enclosed. Treated water require
parameter suitable for high pressure boiler for the generation of steam. Coal
from Coal yard conveyed to coal crusher plant to make it to size below 6mm
.Crushed coal conveyed to bunkers & from bunker feed to boiler through
spreaders uniformly on fluidized bed for combustion & subsequently
generation of steam. Flue gas generated will go through APCD that is ESP(2
Nos.) & finally escaped to air through 105 Mtr. Height common RCC
chimney with clear top diameter suitable for two number 70 TPH and one
number 110 TPH Boiler (Future) with permitted emission level up to 50
mg/nm3.
During operation 0.15 TPH bed ash & 0.5 TPH Fly ash from each boiler is
generated. The Coal Ash is highly demanding in cement factories and Ash
Brick making Industries.
The boiler completely control by DCS System for safe operation. The controls
envisaged in the boiler are three element drum level controls, Deaerator level
control, combustion control, safety valve etc.
ii) Fuel and Water Requirement
Two nos. boiler of 70 T/hr, 86 kg/cm2 g 520 +_5degreeC will use Imported
coal of 21822 kg/hr as fuel for both the boiler and raw water around 600 cu.
M per day.
Royal Environment Auditing & Consultancy Service Page |2.6
Required water for domestic and industrial purposes shall be obtained from
the Desalination plant.
Ground water or any other surface water will not be utilized for any
construction or industrial purposes. The company will get the permission of 2
MLD from Govt. of Gujarat water supply Dept. for construction of plant & in
future for plant operation.
The company will set up its own desalination plant with capacity of 5000
KLD sweet water.
In power plant; water will be used for steam generation and cooling purpose.
The details of water and wastewater generation are as follows in Water
Balance Diagram.
Waste Water Consumption
Details Water Consumption
(M3/day)
i) Industrial
Cycle Make Up 240
Cooling Tower Make Up 288
Misc. Purpose 72
ii) Domestic
20
Total 620 M3/day
Waste Water Generation
Details Water Consumption
(M3/day)
i) Industrial
Cooling Water blow down 100
RO reject 50
Boiler Blow down 350
ii) Domestic
10
Total 510 M3/day
Royal Environment Auditing & Consultancy Service Page |2.7
iii) Steam and Condensate
For feed water to the boilers, it is proposed to use straight condensate from
exhaust steam used in process ensure good quality of feed water. The
delivery line of the pump of condensate from refinery is to be provided with
conductivity meter to ensure that feed water is not mixed up with any sugar
& other harmful chemical and in case it is mixed, the condensate is
immediately stopped automatically on getting the alarm/signal. The make-
up water from RO plant and extracted condensate from the air cooled
condenser of TG set will be sent to feed water tank / de-aerator and this will
ensure almost no loss of condensate from the condensate pit of turbine
condenser.
The feed water will be pumped to de-aerator to be located near the boiler
area. One make up water storage tank and one feed water tank to be
provided to ensure that there is enough good quality water available and
boiler does not suffer due to starvation of water.
Make up water is required for shortages due to plant start up, brake down
and this will be meet through RO plant and sent to feed water system.
Raw water for cycle makeup 10 m3/hr,Raw water for cooling Tower makeup
12 m3/hr and Raw water for miscellaneous Purpose 3 m3/hr.
iv) Grid Inter Connection for Export
Power generation for the proposed TG set is planned at 11.0 KV and
exportable power has to be stepped up to 66 KV from 11.0 KV generator
transformer to be located in switchyard within the cogeneration complex and
then to be synchronized with the grid. The grid synchronization will be
done at GETCO Ltd 66KV Substation.
For operating cogen plant, a portion of power will be stepped down to
11.0 KV/415 Volts for running of sugar refinery and auxiliaries etc. For this
suitable transformers are to be installed at various convenient locations at
the cogen plant area.
Royal Environment Auditing & Consultancy Service Page |2.8
v) Coal Handling System (Refer Annexure-2.2)
It is expected that the coal supplied to the proposed power plant will be from
Indonesia Coal fields. From the Port the coal will be transported in trucks to
the site.
• Coal storage – Coal needs to be stored in proper procedure to avoid
it’s self combustion for the same purpose the coal heap height is to be
maintained as per the standard practices.
• Manual crushing – It is required for the maintain the required inlet
size of coal to crusher, for which is arrangement of gizzly hopper is
given. After maintaining the required size it is feed to coal conveying
system through the coal feeders.
• Primary coal screening – In this process the coal of required size is
get separated through screen & conveyed directly to boiler bunker, i.e.
bypassing the coal crusher & it saves the power.
• Coal crushing – The rejected size coal from primary screen is taken
into the impact type coal crusher for its further preparation to upto the
size ≤ 6 mm.
• Secondary coal screen –The crushed coal from the coal crusher is
feed to secondary screen from where the accepted size coal conveyed
to boiler bunker & the oversized coal send back to primary screen
inlet conveyor through the bucket elevator,to complete the cycle.
• Coal storage at boiler bunker –After size preparation the coal is get
conveyed to bunker by coal conveyor & stored for boiler operation.
The capacity of bunker is 220MT.
• All conveying system is provided with ZSS as well as emergency pull
cord switch.
vi) Ash Handling (Refer Annexure-2.3)
The ash handling system envisages wet extraction and disposal of bottom
ash & dry extraction for fly ash. The fly ash shall be extracted in Wet form
Royal Environment Auditing & Consultancy Service Page |2.9
from the electrostatic precipitator hoppers and transported to storage silo as a
measure for promoting fly ash utilization.
• Wet bottom ash handling system - The bottom headers of the
pulverized fuel fired boiler will be at 4m above ground level to
facilitate incorporation of the Wet bottom ash handling system. The
system shall include water immersed chain conveyor, clinker grinder
and suitable conveying system up to bottom ash silo. Ash in silo will
be unloaded to trucks for further disposal.
• Fly Ash Handling - Fly ash resulting from the combustion of coal in
the boiler gets collected in economizer hopper, air heater hopper, ESP
hoppers etc. The ash shall be evacuated to fly ash silo through dense
phase system. From fly ash silo, ash can be transported through trucks.
Fly ash silo will have provision for 30 days storage. Necessary
fluidizing arrangements, downward unloading chute, ash conditioning
arrangements shall be provided in ash silo.
2.4.5.4 LIST OF EQUIPMENTS AND ITS CAPACITY
Sr. No. NAME OF EQUIPMENT CAPACITY & OTHER DETAIL
1. Boiler & Auxiliaries 2 x 70 TPH, coal fired
1 x 110 TPH coal fired
2. TG and Auxiliaries
1 x 30 MW extraction cum condensing TG
set
1 x 15 MW back pressure TG set
3. Air cooled Condenser One no Air cooled condenser & auxiliaries
to condense 93.27 TPH steam.
4. EOT Crane 1 x 30/5 MT Electrically operated double
grinder crane
5. Aux. Cooling Tower FRP Counter flow with RCC basin with
Capacity 600 m3/hr
6. Water Treatment Plant 12 M3/hr membrane based water treatment
plant.
7. Fuel Handling system 110 TPH coal handling system with
necessary crusher, screens, conveyors etc.
Royal Environment Auditing & Consultancy Service Page |2.10
2.5 SOURCES OF POLLUTION AND CONTROL MEASURES
2.5.1 AIR POLLUTION
2.5.1.1 SOURCES OF AIR POLLUTION
Fugitive Emission
The fugitive dust emissions from the proposed coal handling system would be
significant and the sources will be as under:
1. Coal Crusher
2. Stock House
3. loading/Unloading of coal
4. Transportation of coal through vehicles
5. Transfer of product through belt conveyor
Sr.
No. Detail of Stack
Stack
Diameter(m)
Stack
Height(m)*
Air Pollution
Control
Measure
1 Coal Crusher/Screen
House
0.5 12.5 Bag Filter
2 Coal Injector Building 0.08 11 Bag filter
3 Stock House 0.35 12 Bag filter
4 Intermediate Bin 0.35 11 Bag filter
* Minimum Stack Height at least 2 m above nearest building.
Process Emission
Adequate and efficient measures shall be provided to keep the dust emission
at a bare minimum level. Efficient Collection of dust at sources, their de-
dusting with efficient filters and recycling the dust to process is the prime
objective. Primary dust source shall be the crusher house, screen house, raw
material and product handling in Power plant.
The particulars of most specific individual sources and their pollution control
measures are delineated as follows:
Royal Environment Auditing & Consultancy Service Page |2.11
Boiler Stack (Power Plant) Number of Stack 01
Stack attached to Boilers
Height of the Stack & die 105 m & top diameter 3 mtr
Type of fuel used Imported Coal
Air Pollution Control equipment Electrostatic Precipitator
Stack height from GL Adequate stack height provided as per GPCB
norms
Temperature 170-180 Deg C.
Expected Pollutants SPM, SOx, NOx
Electrostatic Precipitators
It is proposed to install high efficiency electrostatic precipitators to limit the
outlet emission to 50 mg/Nm³ while the boiler is operating at its MCR, firing
worst coal having maximum ash content. The electrostatic precipitators will
have four (4) parallel gas streams, isolated from each other on electrical as
well as gas side. Gas tight dampers will be provided at inlets and outlets of
each stream so as to allow Maintenance to be carried out safely on the faulty
stream, while the unit is working.
Electrostatic precipitators will be provided with microprocessor based
programmable type rapper control system and ESP management system to
ensure the safe and optimum operation. Opacity meters shall be provided at
the ESP outlet for performance optimization and for remote indication. ESP
Transformer rectifier sets will use silicon oil as the cooling medium. The dust
collection hoppers below ESP will have a minimum storage capacity of eight
(8) hours while firing worst coal. The hoppers will have heating arrangements
to prevent ash sticking to the sloping sides and down pipes. Level indicators
to indicate and trip the ESP in case of high ash levels in the ash hoppers while
will jeopardize the safety
Royal Environment Auditing & Consultancy Service Page |2.12
2.5.1.2 AIR POLLUTION CONTROL MEASURES
To control fugitive emissions, the following measures are proposed.
• Raw materials loading and unloading will be done in the covered area.
• Raw materials will be stored in the covered structure.
• The sprinkling of water will be done along the internal roads in the plant
in order to control the dust.
• All the workers and officers working inside the plant will be provided
with disposable dust masks.
• Green belt will be developed around the plant to arrest the fugitive
emissions.
• Bag filters & Dust Collectors will be cleaned regularly.
• Maintenance of bag filters will be done regularly.
• Closed belt conveyor will be used for transfer of raw material/product.
To control process dust emission the following measures are adopted.
• The vent is attached to the bag filters of adequate height to disperse the air
pollutants to the satisfactory levels.
• The vent will be regularly monitored for PM.
• Bag filters will be cleaned regularly.
2.5.2 WATER POLLUTION & CONTROL MEASURES
2.5.2.1 Source of Waste Water generation
The waste water generation pattern /source of waste water are described
below:
Cooling tower Blow down
In the condenser cooling water, residual chlorine of about 0.2 ppm is normally
maintained at the condenser outlet. This value would not result in any
chemical pollution of the environment since this is a re-circulating system and
the CW blow down is led to waste water treatment plant (WWTP) where due
to further dilution, the free available chlorine would be less than the limit of
0.5 mg / l set by the National Standard.
Royal Environment Auditing & Consultancy Service Page |2.13
pH 6.5 - 8.5
Temperature Not more than 5°C higher than the intake
water temp. When measured within 100m
radius from outfall.
iii. Free available chlorine 0.5 mg / liter Parameters.
Max. Limiting Concentration
Boiler Blow Down
The salient characteristics from the point of view of pollution are the pH and
temperature of water. Suspended solids are negligible. The pH will be in the
range of 9.5 to 10.3 and the temperature of water at the outlet of intermittent
blow down tank about 100°C. The boiler blow down is proposed to be led into
WWTP. The quantity of boiler blow down water of the unit is approximately
3%.
Boiler Blow down
Suspended solids 100 mg / liter
Oil and grease 20 mg / liter
Copper (Total) 1.0 mg / liter
Iron (Total) 1.0 mg / liter
Rejects From D.M. Plant/ R.O. plant
The effluent from the regeneration of cation resin units (DM plant) in the
water treatment plant will be generally acidic in nature and that from the
anion resin units alkaline in nature. The waste water from the water treatment
plant would therefore be normally neutral. However provision will be made
for addition of either alkali or acid to control the pH in a neutralizing pit
before disposal. Necessary analytical and control instruments will be provided
to ensure proper neutralization. The neutralized effluent is expected to have
suspended solids less than 5 ppm and pH in the range of 7.5 to 8 and will be
let into the plant waste water disposal system.
The effluent from the Desalination Plant i.e. R.O. plant will be sent to Water
treatment plant. The effluent having high TDS will send back to Sea.
Royal Environment Auditing & Consultancy Service Page |2.14
Oil/Water Mixture from Fuel Oil System
The oil/water mixture from the drain trench in the oil unloading area and from
the fuel oil tank farm/pump house are first led into a corrugated plate type
oil/water separator. The water separated from the oil in the separator will be
led into storm water drain. The oil from the oil water separator will be led
back to the fuel oil tank.
Sewage Disposal
Sewage from various buildings in power plant area will be conveyed through
separate drains to septic tanks. The effluent from septic tank will be disposed
in soil by providing dispersion trenches. There will be no ground pollution
because of leaching. Sludge will be removed occasionally and will be
disposed off as land fill at suitable places.
2.5.2.2 Water pollution Control Measures
Waste water is produced in a Power Plant during operation. The waste water
is to be treated suitably to make the properties of effluent suitable for
pumping into the normal drain canal. The waste water is generated from the
following areas Boiler Area Steam Turbine Area,
Floor Washings, DM Plant Area waste consists of regeneration waste, DM
plant drains, chemical unloading area washings etc.
The waste water generated in the plant area will be treated in the waste water
treatment plant to achieve the required parameter limits of effluent as per
stipulations in the Environmental Quality (Sewage & Industrial Effluents)
Regulation issued by Government of Gujarat, prior to discharge. Necessary
sampling and testing instruments are provided to monitor and control the
effluent parameters.
ETP is consists of following main equipments.
• Screen chamber
• Oil & Grease Trap
• Equalization Tank
Royal Environment Auditing & Consultancy Service Page |2.15
• pH- adjustment tank
• Settling Tank
• Sludge tank
• Treated Water Tank
• PROCESS DETAILS
The waste from the entire units is identified as mentioned in the technical
details. The streams are treated as per the
requirement with respect to the impurities specified in the parameters.
Stage I
The waste from process and washes estimated as 350 KLD considering
the flow rate 17.5 M3/hr is collected in the EQ-01 through BS
and OGT. This waste is mixed in EQ-01 (Equalization
Tank) through air grid. Further the effluent is pH adjusted in the
neutralization tank CT-01.
Stage II
The pH adjusted waste is pumped to UASB Reactor for the first stage
reduction of COD. The outlet from UASB is processed through ST-01
for settling of solids. The overflow from ST-01 is taken to second stage
of biodegradation.
Stage III
The over flow from ST-01 along with waste from EQ-02 is taken in the
second stage of biodegradation is by SAFF reactor where the BOD
along with COD will reduce due to advanced activated sludge process.
The air blower will supply the required air to the membrane diffusers for
the enhancement of biodegradation. SAFF reactor is designed in two
stages. Nutrients are added as required for the bacterial sustainability.
The outlet of SAFF reactor is passed through ST-02; where the biomass
over flow is settled down. The active biomass is re- circulated
Royal Environment Auditing & Consultancy Service Page |2.16
through air lift system.
Stage IV
The overflow from ST-02 is taken to FLOC-01 for chemical flocculation
treatment. The flocculants are added as required for the chemical
precipitation and mixed well through mixer and air grid as required.
The outlet from FLOC-01 is taken to ST-03 for the settlement of all
suspended impurities. The overflow is collected in the supernatant tank
SST-01.
Stage V (Final Treatment)
The bio-treated waste is pumped through pressure sand filter (PSF-01)
followed by ACF-01 for the tertiary treatment. Here the treated waste
water is filtered and polished for the final reuse. Disinfection through
sodium hypo chloride is done to reduce microbial contamination.
Stage VI
The end treated water is mixed with RO reject of 300 KLD (15
M3 / hr) and stored in treated water tank for necessary reuse. The entire
treated water shall be estimated as 3000 to 3500 TDS only; which is
almost same as inlet raw water TDS.
The same water can be recycled for the inlet of water treatment plant as
per requirement.
Stage VII (Sludge treatment)
Sludge treatment is done by withdrawing the entire sludge from ST-01;
ST-02; ST-02 and UASB by frequent valve operation to SLDT-01.
The sludge collected is pumped to FP-01 for solid and liquid
separation. The filtrate is returned to EQ-01 and dried sludge is
disposed of to suitable agency.
Royal Environment Auditing & Consultancy Service Page |2.17
Stage VIII
The gas generated from UASB is passed through pressure relief valve,
moisture trap and flame arrester to Gas dome tank. The gas collected in
gas dome is used as fuel or burned out.
2.5.3 Solid Waste Management
2.5.3.1 Solid waste Generation
The solid waste generated will be in the form of i) Bed Ash and the (iii) Fly
Ash from CPP. Following measures are proposed to minimize the impacts of
ash to the environment. Provision shall be made for 100% dry fly ash
utilization. Fly ash extracted in dry form shall be taken to buffer hoppers.
From the buffer hoppers, dry ash shall be transported to a storage silo. For this
suitable transportation vessel like air lock/air educator/pump tank shall be
used.
Storage Capacity
• Bed ash silo – 1x30cum capacity common for both boilers
• Fly ash silo – 1x400cum capacity common for both boilers
2.5.3.2 Solid waste Disposal
Fly Ash Utilization
Fly ash could be used after suitable processing, as necessary, as a construction
material. The following uses are possible for the fly ash:
• As admixture to cement
• As admixture to cement concrete for large construction
• As an aggregate in ‘aerated’ concrete or ‘foamed’ concrete for the
manufacture of pre-fabricated building blocks.
One of the uses identified is for manufacturing of light weight aggregate,
which in turn can be effectively used for manufacture of bricks and tiles.
These can be used in building industry (walls and floors) and pavement of
roads, etc. The calcium from lime reacts with silica and alumina in fly ash to
produce calcium/ aluminum minerals in a reaction similar to that of Portland
cement. These minerals bond the fly ash particles tightly so that hard, strong
Royal Environment Auditing & Consultancy Service Page |2.18
and practically unreachable pellets are formed. These pellets are heated at low
temperature to cure them.
Used/spent Oil
Negligible quantity of used oil shall be generated; which will be disposing off
to through registered recyclers.
2.5.4 Noise Pollution & Control Measures
Construction Phase
Main source of Noise pollution is vehicular movement during construction
phase. In order to reduce this following measures to be taken.
1. Speed limit of vehicle shall be restricted by 30 KMPH
2. Regular maintenance of vehicles shall be done
3. Ear plug or Ear muff to be used in high noise prone area.
Operation Phase
All equipment in the power plant will be designed / operated to have a total
noise level not exceeding 85 to 90 dbA. This will meet the requirement of
ISHA Standard (Occupational Safety and Health Administration). As per this
standard, protection from noise is required when sound levels exceed the
values prescribed by norms. In addition, since most of the noise generating
equipment will be in enclosed structures, the noise transmitted outside will be
still lower.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.1
CHAPTER 3
DESCRIPTION OF ENVIRONMENT 3.0 SITE AND SURROUNDING AREA
This chapter describes the existing environmental conditions of the study area,
which covers an area within 10 km radius around proposed 45 MW coal based
power plant of Shree Renuka Sugars limited. The methodology of establishing
baseline environmental scenario has been briefly described in Chapter 1.0 and
further details of data generation/ collection; analysis and interpretation are
presented in the respective sections in this chapter.
The entire study area falls in Kutch district Gujarat. The study area shows flat
topography in the vicinity of the project site. The field monitoring started at
site on first week of March 2010. Apart from primary data generated during
the field monitoring, additional data was also collected from secondary
sources like Indian Meteorological Department (IMD)- Bhuj.
3.1 LAND USE
Land is the most vital resource for sustenance of life and degradations of land
use to industrialization; urbanization and population growth is a matter of
concern. Therefore, it is necessary to establish the existing land use pattern to
optimize the land use as well as minimize degradation due to the
developmental activities.
The basic of land use classification for the purpose of EIA study report is to
define the distribution of the existing land according to its actual use. The land
use pattern indicates the manner in which different parts of land in the study
area is being utilized or un-utilized. It is an important indicator of
environmental health and human activity and a degree of inter-play between
these two.
Even though the soil quality, water availability and climatic conditions have
strong influence on agriculture and vegetation, the human activity may alter
the natural environment to a large extent to suit human needs. Unsuitable land
use often triggers rapid environmental deterioration and disturbs ecological
balance.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.2
The objectives of the present study are:
• To map the study area with respect to various land use/land cover
categories
• To identify the sensitive areas within 10 km radius around the project site.
The land use pattern has been established based on satellite imaginary and
based on Census Data of 2001 and truth verifications. Ground and ancillary
information have been used to identify the sensitive places within 10 km
radius of the proposed project.
3.1.1 Land Use classification Based on Satellite Imaginary
Land use statistic of Shree Renuka Sugar Ltd (10 Km radius) is as follow
Table 3.1
Sr. No. Description % Area Area in Ha
1. Built up residential 8.18 2569
2. Built up Industry 2.83 887.9
3. Salt Pan 19.6 6156.05
4. Reclaimed Land 0.19 58.88
5 Vacant Land 0.32 100.52
6. Transportation & Logistics 1.05 331.35
7. Agriculture Land 0.32 100.52
8. Dense Scrub 23.13 7267.95
9. Open Scrub 23.13 7267.95
10. Mudflat 11.86 3727.01
11. Mangrove 5.34 1677.65
12. Lake/Pond 0.21 67.15
13 Reservoir 0.52 163.35
14 River 0.42 131.6
15. Creek 3.35 1053.9
Total 100 31415.51
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.3
FIGURE 3.1
Base Map for 10 KM radius from project site
3.1.2 Land Use Classification Based on Census Data 2001
In traditional revenue records in India, major land use classifications are; (a)
Hills and rocky land, (b) Forests, (c) Pastures (d) Hebetated areas (e)
Cultivated areas (f) Cultural wasteland (g) Un-cultural wasteland. The land
use classification has varied somewhat from state to state and often overlaps.
Furthermore, combining of two or more categories into a single one could also
be found.
The above classification appears to be partly a land classification and partly a
land use classification. Only large-scale shifts in land use pattern, such as,
forests areas converted in to cultivated area can be observed from revenue
records. The shifting in cropping pattern, on the cultivated areas, is a slightly
better and more sensitive indicator of change in environmental quality but
even this reflects human manipulation due to environmental changes.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.4
As outlined earlier, the study area for this project encompasses areas falling
within a 10 km radius of the plant site. The entire study area falls in Kutch
district & in one Taluka namely Gandhidham in Gujarat. As per the census
records -2001, the area is predominantly rural in character.
The Census records, do not classify land as ‘Hilly and rocky’ or ‘Pastures’ or
‘Hebetated area.’ It appears that, ‘Hilly and rocky’ areas are included in
‘Uncultivable land,’ Pastures are included in ‘Cultivable waste land’ and
‘Hebetated area’ are included in ‘Area not available for cultivation’. In
revenue records total land of a village is classified in two categories (a)
Cultural land (b) Un-cultural land. Cultivable land is further sub-classified into
cultivated area and cultural wasteland. Un-Cultivable land includes hebetated
area, forest and pasture land covered by roads and buildings. Land use pattern
as per the census records of 2001, has been classified in the following
categories:
• Forest
• Cultivated Land
o Irrigated Land
o Un-irrigated Land
• Cultivable wasteland
• Area not available for cultivation
The following points are important to be mentioned regarding the land use
pattern described in this chapter:
i. Taluka has been used as a unit of civic administration as used in the
census records for the state of Gujarat.
ii. Land use classes have been computed on the basis of land use area of
industrial villages, falling totally or partly as the case may be, within
the study area.
iii. Land use area does not always tally with the geographical area, as
there are waterways etc. that may not be included in the land use
statistics of the villages. Summary of land use pattern data has been
presented in Table below.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.5
Table 3.2
Land Use Classification Area (Hectare %) of Ta. Gandhidham
Land Use Classification Area In Hectare
Irrigated 384.79
Un irrigated 5096.97
Cultivable Waste land 4286.8
Area Not Available for cultivation 4412.81
Figure no. 3.2
Land Use Classification Area of Ta. Gandhidham2.71%
35.94%
30.23%
31.12%Irrigated
Unirrigated
Culturable waste land
Area not available forcultivation
Table 3.3
Land Use Classification Area (ha) of Village. Bharapar
Land Use Classification Area in Hectare
Irrigated 34.43
Un irrigated 518.60
Cultivable waste land 63.64
Area not available for cultivation 369.55
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.6
Figure 3.3
Land Use Classifaction Area of Village Bharapar
3.49%
52.58%
6.45%
37.47%
Irrigated
Unirrigated
Culturable waste land
Area not available forcultivation
On perusal of the data compiled from the Census Records of 2001 following
facts can be delineated:
3.2 DEMOGRAPHY AND SOCIO-ECONOMIC
Demography and socio-economic features include population, number of
houses and households, literacy, population density etc. In order to assess the
demographic features of the study area, census data of Kutch District in
Gujarat for the year 2001 have been compiled and analyzed.
Proposed project is located at Taluka Gandhidham which covers 08 villages
namely, Antrarjal, Bharapar, Chudva, Galpadar, kidana, Mithi Rohar, Padana
& Shinay.
3.2.1 Demographic Profile of the Study Area
3.2.1.1 Households/Occupied Residential Houses and Total Population
The total 29,872 households in Taluka Gandhidham as well as residential
houses distributed over 08 villages as per census record of 2001.
The total 137 households in village Bharpar as per census record of 2001.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.7
Total Population:
The total population of the village bharapar stood at 659 out of which Total
population of males is 346 & Females is 313 as per the census record of 2001.
While total population of Gandhidham Taluka stood at 151693 out of which
males are 79,379 & female are 72,314 as per the census record of 2001.
Figure 3.4
Total Population For Village Bharapar
Male 52.50%
Female 47.50%
Male Female
Figure 3.5
Total Population For Taluka : Gandhidham
Female47.67% Male
52.33%
MaleFemale
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.8
3.2.1.2 Sex Ratio
In the village Bharapar area, there were 857 females for every thousand males,
where as in total Gandhidham Taluka, there were 911 females for every
thousand males, as per the census records of 2001.
3.2.1.3 Scheduled Castes and Scheduled Tribes
As per the census data of 2001, scheduled caste population observed is 10 and
scheduled Tribe population is 21 in the village Bharapar.
As per the census data of 2001, scheduled case population observed is 29,360
and scheduled Tribe population is 4354 in Taluka Gandhidham.
The proportion of SC was 19.35 % and ST was 2.87 % of total population in
Taluka Gandhidham as per census data of 2001.
3.2.1.4 Literacy
A person who can both read and write with understanding in any language is
taken as literate according to Indian Census.
As per Census of India 2001 total literate population of Taluka Gandhidham is
1,13,769 which is 75 % of the total population.
3.2.2 SOCIO-ECONOMIC PROFILE OF THE STUDY AREA
3.2.2.1 Distribution of Work Participation Rate
The work participation rate for total workers is defined as the percentage of
total workers to the total population. In a similar way it is defined for main and
marginal workers.
The work participation rate for total workers is defined as the percentage of
total workers to total population. In a similar way it is defined for main,
marginal and non-workers.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.9
Table 3.4
Distribution of Woke Participation Rate
Sr. No. Details Total % Of total population
Total population 151693
1. Total workers 47151 31
Total Main workers 44751 29.5
Total Marginal workers 2400 1.6
2. Total Non workers 104542 68.9
Figure 3.6
Distribution of Work Participation Rate for Gandhidham Taluka
31%
69%
Total WorkersTotal Non workers
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.10
Figure 3.7
Distribution of Total Workers for Gandhidham
94.91%
5.09%
Main Worker
MarginalWorker
3.2.3 Availability of Infrastructure Facilities and Amenities
I. Educational Facilities
Out of the 08 villages, falling within Gandhidham Taluka, there were
all villages with Primary Schools, 01 village has secondary school and
no village has senior secondary schools as per census record 2001.
Higher educational facilities are available in town only. There is no
medical and engineering college in the Taluka Gandhidham. Bhuj city
is a hub of educations, and has facility of polytechnic, Engineering,
medical, physiotherapy and other educational courses are available.
II. Medical Facilities
In the rural area, medical facilities are very poor. Detail of all the 62
villages of Taluka Gandhidham are as under.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.11
Table 3.5
Medical Facility
Sr.
No.
Details Total
No
Total no of villages have
facilities
Available Not available
1 Number of Medical facilities 0 0 08
2 Number of Allopathic Hospitals 01 01 07
3 Number of Family Welfare Centre 0 0 0
4 Number of Maternity Home 0 0 08
5 Number of Ayurvedic Hospitals 0 0 08
6 Number of Homeopathic Hospital 0 0 08
07 Number of registered private medical
practitioners 01 01 07
08 Number of community Health
Workers 08 08 0
Note: Details are taken from Census of India 2001.
III. Drinking Water Facilities
In the study area, drinking water facility is present in all the eight
villages. Wells, hand pumps and tube wells, Tap water are the major
sources of drinking water. In the rural part of the study area, almost all
the villages are enjoying tap water facility provided by Gram
Panchayat its community development programmer.
IV. Postal Facilities
In the study area, post and telegraph facility is available in the most of
villages. Details of postal Facilities as per Census of India 2001 are as
under in total 62 villages of Taluka Gandhidham.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.12
Table 3.6
Postal Facilities
Sr.
No. Details
Total
No.
Total No of villages have
facilities
Available
villages
Not available
villages
1 Number of post and telegraph
office 06 06 02
2 Number of telephone connections 474 07 01
3 Number of Telegram offices 0 0 8
4. Number of post and telegram
offices 0 0 8
V. Weekly Market Facility
Generally large villages have at least a few permanent kirana shops,
which cater to the daily necessities of the residents. In the rural part of
the study area not even a single village is having weekly market
facility.
VI. Transport and Communication
Communication facilities are available in most of the study area
villages. Out of 08 villages, 07 villages have Bus transport facility. No
villages have railway transport facilities as per census data 2001.
VII. Approach Road
Almost all the villages can be approached by pucca road while the
remaining can be approached by katcha road facility.
The National Highway No. 8A passes through the district along with a
number of State Highways. The district is provided with a well
managed transport system both private and public, connecting the
different parts of the district.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.13
VIII. Recreational and Cultural Facility
The infrastructural facilities in general meet the requirements of the
people. However, it requires to be further improved, especially with
respect to transport and communication and medical facilities.
Out of 08 villages no village has video hall, sports club, stadium or
auditorium as per Censes data 2001.
IX. Banking Facilities
Total 02 nos. of commercial bank facilities available in 02 villages as per census data 2001.
3.3 METEOROLOGY AND CLIMATOLOGY
Meteorology determines the general weather patterns and thus identifies the
probable pollution patterns. The climate of project area is arid. Hot and dry
summer from March to May, a monsoon or rainy season from June to
September and a cool pleasant winter from October to February characterize
it. However, climatologically, four seasons viz. summer (pre-monsoon),
monsoon, post-monsoon and winter could be deciphered comprising the
following months:
Summer (Pre-monsoon): March, April, May
Monsoon: June, July, August, September
Post-monsoon: October, November
Winter: December, January, February.
3.3.1 Past Records
3.3.1.1 Data Collected
Analysis of past records brings out the synoptic features of the area.
Climatologically data was collected from the nearest meteorological station
operated by Indian Meteorological Department (IMD) at Bhuj located about
40 km from the project site and the data recorded at this station has been used
to describe the climatology of the area.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.14
3.3.1.2 Analysis of Climatologically Data
Climatologically data for last 30 years collected from IMD, Bhuj is
incorporated and presented in Table 3.7.
TABLE: 3.7
SALIENT CLIMATOLOGICALLY FEATURES OF IMD BHUJ
(30 YEARS AVERAGE)
Month Temperature Rainfall
Max (deg c) Min (deg C) Mm
January 27.1 8.8 2
February 30.1 11.8 1.5
March 35.1 17.4 2.1
April 38.8 22 1.1
May 39.6 25.3 7.5
June 37.5 27.1 38
July 34 26.3 125.7
August 32.8 25.3 103.5
September 34.3 23.9 63.1
October 36.4 20.7 19.7
November 32.7 15.1 8.5
December 28.4 10.1 1.0
Average 33.9 19.48 31.14
3.3.1.3 RAINFALL
The average annual rainfall is about 31.14 mm. Rainfall peaks during July
(about 125.73 mm) followed by Aug (about 103.5 mm) with the four monsoon
months (June to September) contributing 88% of the total rainfall.
3.3.1.4 TEMPERATURE
The average annual minimum temperature is 19.48 deg C and average annual
maximum temperature is 33.9 deg C.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.15
3.3.2 ON –SITE METEOROLOGY
In order to corroborate and supplement the long-term meteorological data collected from IMD, Bhuj and to generate site-specific data, an Automatic Weather Station (WM 250) of M/s Envirotech Instrument Pvt. Ltd. make was installed at the project site of Shree Renuka Sugars Ltd, Village Bharapar, Ta. Gandhidham, Dist. Kutch.. In this report the on-site meteorological data collected from March-2010 to May- 2010 has been incorporated and analyzed. Monthly variation in on-site meteorological parameters at site has been given in Table 3.11; 3.12 & 3.13.
TABLE: 3.8 METEROLOGICAL DATA FOR MARCH-10
Date Direction Temp. Humidity Wind Speed
Avg. Max. Min. Max. Min. Max. Min. Max.
1/3/2010 230 24 30.5 38 87.2 2 20.8 2/3/2010 235 23 31.4 39 86.5 2 20.1 3/3/2010 230 21.4 33.2 31.2 91.5 2 29.5 4/3/2010 240 21.1 31.1 41.3 92.1 1 26 5/3/2010 230 22 31.3 41.1 90.3 0 19.6 6/3/2010 240 19 31.2 39.3 93 0 26.8 7/3/2010 305 22.2 32.1 31.1 66.4 3.7 23.9 8/3/2010 310 22.2 35.3 20.3 47.4 1.6 20.2 9/3/2010 330 21.1 37 14.2 57.3 0.4 34.4 10/3/2010 335 23.1 37.4 11.1 38 4.9 30.1 11/3/2010 310 24.1 38.5 11.1 27.1 1.9 28.1 12/3/2010 220 20 39 11.3 42.4 0.2 30.4 13/3/2010 245 19.1 36.5 19.2 78 0.8 18.3 14/3/2010 225 20 33.2 40.5 96 1.4 22.2 15/3/2010 220 21 36.1 34.6 96.3 1.4 20 16/3/2010 232 25.1 39.2 31.1 94.2 1.4 21.8 17/3/2010 235 26 38.5 33.3 92.3 6.3 28.1 18/3/2010 226 19 37.4 21.2 53 1.1 14.6 19/3/2010 198 19.2 39.4 14.2 80.2 0.5 14.8 20/3/2010 204 27 38.5 18.2 58.5 0.2 16.6 21/3/2010 225 28 39.5 19.1 60.1 0.5 18.2 22/3/2010 230 27.9 40.1 20.1 61.2 1.2 18.9 24/3/2010 235 28.1 42.1 21.2 65.3 1.5 19.2 25/3/2010 236 24.2 29.0 47.0 80.0 7.4 8.5 26/3/2010 226 23 33.2 46.1 78.2 8 19.9 27/3/2010 241 21 35.3 31 96.2 0.1 20.4 28/3/2010 225 21 38.1 16.1 90.2 0.2 19.8 29/3/2010 233 19.3 34.1 32 81.6 1.4 26.1 30/3/2010 222 23.3 33.4 51 93.6 1.6 31.6 31/3/2010 226 24.1 35 36.1 94.3 4.9 25.6
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.16
TABLE: 3.9
METEROLOGICAL DATA FOR APRIL-10
Date
Direction Temp. Humidity Wind Speed Avg. Max. Min. Max. Min. Max. Min. Max.
1/4/2010 218 24.6 35.2 47.6 88.1 4.1 26.9 2/4/2010 230 25.3 38.3 19 90.2 6.7 24.1 3/4/2010 218 22.1 35.3 41.1 96.4 2.8 23.4 4/4/2010 239 21.1 35.5 17 95.1 0.8 20.8 5/4/2010 226 19 37.4 21.2 53 1.1 14.6 6/4/2010 198 19.2 39.4 14.2 80.2 0.5 14.8 7/4/2010 243 22 39.4 15.5 63.4 0.5 20.6 8/4/2010 204 27 38.5 18.2 58.5 0.2 16.6 9/4/2010 238 24.1 40 14 49.6 0.9 16.4 10/4/2010 233 23 39.1 31.2 89.4 2 24.7 11/4/2010 211 25 38.3 37.4 87.3 3.5 24.7 12/4/2010 227 24.2 40.3 19.3 94.2 6.4 20.8 13/4/2010 219 25.3 38.1 36.1 82.4 2.4 18.1 14/4/2010 212 25.4 39.2 16.1 61.2 0.2 21.2 15/4/2010 201 25 38.3 25.5 64 1.3 14.2 16/4/2010 245 26 40.2 32.1 77.4 2.1 20.2 17/04/2010 232 25.1 39.2 31.1 94.2 1.4 21.8 18/04/2010 235 26 38.5 33.3 92.3 6.3 28.1 19/04/2010 233 26.1 39.1 40.1 91.4 9.8 24.1 20/04/2010 240 27 39.5 28.1 88.3 8.8 23.1 21/04/2010 236 27 36.6 45.2 87.6 10 28.7 22/04/2010 256 26.1 36.3 47.3 89.1 1.1 20.4 23/04/2010 236 23.3 38.3 27.1 91.3 0.4 20.6 24/04/2010 273 24 41.5 17.1 86 0.1 19.4 25/04/2010 236 25.2 37.5 34.1 88.5 1.8 23.9 26/04/2010 227 26 38.2 41.2 87.5 4.5 25.4 27/04/2010 255 26.2 42.1 19.1 89.4 2.7 16.8 28/04/2010 265 26.1 42.3 17.1 84.3 4.1 17.7 29/04/2010 238 27.2 39 29.2 88.4 2.2 25.4 30/04/2010 227 27.1 38.2 29 89.1 0.1 18.5
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.17
TABLE: 3.10
METEROLOGICAL DATA FOR MAY-10
Date
Direction Temp. Humidity Wind Speed Avg. Max. Min. Max. Min. Max. Min. Max.
1/5/2010 232 25.0 38.1 25.0 92.1 1.8 19.2 2/5/2010 258 27.1 37.5 36.1 83 0.5 17.7 3/5/2010 230 25.1 38.6 36 88.2 1.9 21.3 4/5/2010 241 27.1 38.1 43.1 86.3 3.7 21.3 5/5/2010 228 26 38.2 38.3 88.1 2.9 27.9 6/5/2010 242 28.1 40.2 28 85 4.6 21.2 7/5/2010 281 27.1 41.2 20 86.5 0.2 12.3 8/5/2010 262 28 41.4 24.3 83.1 4.4 20.9 9/5/2010 243 27 38.2 33 84.2 2.8 21.1 10/5/2010 238 25 40.2 30 86.3 2.2 20.1 11/5/2010 235 26.1 40.2 37.1 84.1 2 20.2 12/5/2010 227 26 37.5 32 79.2 1.5 26.6 13/5/2010 234 27 41.3 34 85.5 3.3 20.6 14/5/2010 231 27.2 39.5 26.3 90 6 22.8 15/5/2010 228 28.1 38 39.4 86.1 5.1 23.6 16/5/2010 225 25.2 37.3 30.1 88.1 1.9 20.5 17/5/2010 228 28.1 38.4 29.3 87.2 2.1 21.4 18/5/2010 230 26.2 37.3 29.7 86.5 2.4 22.4 19/5/2010 232 28.1 39.3 31.4 89.4 2.5 23.5 20/5/2010 235 25.4 36.8 32.5 78.1 2.2 24.7 21/5/2010 240 27.2 37.4 28.2 75.2 2.6 27.3 22/5/2010 254 28.1 39.4 29.2 74.3 3.2 21.2 23/5/2010 248 26.3 38.4 30.1 76.2 3.5 20.2 24/5/2010 239 25.8 37.4 27.4 77.3 3.4 22.1 25/5/2010 238 27.3 36.8 32.1 82.1 2.8 23.2 26/5/2010 240 25.8 38.6 33.2 83.5 3.1 25.6 27/5/2010 241 26.8 36.3 31.5 88.1 3.2 28.4 28/5/2010 242 28.5 37.7 30.4 81.3 3.3 29.3 29/5/2010 243 26.4 38.4 29.5 82.6 2.4 30.1 30/5/2010 244 25.8 39.8 30.3 81.7 2.9 29.1
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.18
Figure 3.8
Windrose Diagram
March 1st to March 31st, 2010
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.19
Figure – 3.9
Windrose Diagram
April 1 st to May 31st, 2010
3.3.2.1 Wind Speed and Direction
Wind rose diagram for study period has been prepared based on hourly
reading of wind speed and direction. Winds are moderate with minimum speed
of 0.1 km/hr on 5th, 6th March-10. Maximum wind speed 28.7 km/hr was
observed on 21st April-10. Wind Rose diagram is given in figure No. 3.8 & 3.9
3.3.2.2 Temperature
Minimum temperature was recorded as 19o C on 18th March-10 and 5th April-
10 & while the maximum temperature observed was 37.7o C on 28th May-10.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.20
3.3.2.3 Relative Humidity
Minimum relative humidity was observed as 11.1 % on 10th & 11th March-10
and Maximum relative humidity was observed as 93.6% on 30th March-10.
3.3.2.4 Rainfall
During study period no rainfall recorded.
3.4 AMBIENT AIR QUALITY
The prime objective of the baseline study with respect to ambient air quality is
to establish the present air quality and its conformity to ambient air quality
standards. This data has been further used during impact assessment to predict
the resultant ambient air quality during operation of proposed and its
associate’s facilities,
This section describes the identification of monitoring locations; methodology
adopted for monitoring, frequency of monitoring and results of monitoring
during the study period (March-10 to May-10).
3.4.1 METHODOLOGY ADOPTED FOR THE STUDY
The ambient air quality monitoring was carried out at 6 numbers of locations.
The guidelines of Central Pollution Control Board (CPCB) of Oct 1998 and
National Ambient Air Quality Standards (NAAQS) issued on 18th Nov-2009.
3.4.2 CRITERIA FOR SELECTION OF MONITORING LOCATION S
The baseline status of the ambient air quality has been established on the basis
of the following considerations:
• Meteorological conditions of the area • Topography of the study area; • Representatives of background air quality/pollution pockets for
obtaining baseline status; • Representatives of likely impact areas. • Representation of valid cross-sectional distribution in downwind
direction
Logistic considerations as easy accessibility, security, availability of reliable
power supply etc were also examined while finalizing the locations.
The Ambient Air Quality Monitoring locations are shown in below table.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.21
TABLE: 3.11
Ambient Air Quality Monitoring Locations
Station Code Location Distance from proposed site
(KM)
AAQ1 Village: Bharapar 0.37
AAQ2 Village: Shinai 5.32
AAQ3 Village: Kidana 2.83
AAQ4 Village: Tuna 2.95
AAQ5 Village: Mathak 7.52
AAQ6 Village: Adipur 7.23
3.4.3 FREQUENCY AND PARAMETERS FOR MONITORING
Ambient air quality monitoring has been carried out with a frequency of two
24 hourly sampling for consecutive two days in upwind & downwind direction
per week all the locations. The baseline data of ambient air has been generated
for the following parameters:
• Particulate Matter PM10;
• Particulate Matter PM2.5;
• Sulphur Dioxide (SO2); and
• Oxides of Nitrogen (NOx);
3.4.4 DETAILS OF THE MONITORING LOCATIONS
The monitoring locations represent the areas of maximum deposition,
reference ambient air quality and location characteristics.
3.4.5 INSTRUMENT USED FOR SAMPLING
Fin particulate matter dust Samplers APM-550 of Envirotech Instruments Pvt.
Ltd. make were installed for monitoring Suspended Particulate Matter
(PM10,PM2.5), & gaseous attachment APM 411 of Envirotech Instruments
Pvt Ltd for gaseous pollutants like SO2 and NOx.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.22
3.4.6 METHODS FOR SAMPLING AND ANALYTICAL TECHNIQUE
• For PM10, PM2.5
For PM2.5 Gravimetric method.
For PM10 measurement IS: 5182(Part 23) : 2006
• For Sulfur dioxide
Improved West and Geake Method Ultraviolet Fluorescence -IS-5182(part
2):2001
• For Nitrogen Oxide
Jacob & Hochheiser Modified (Na-Arsenite) Method IS-5182(part
vi):1975
3.4.7 PRESENTATION OF RESULTS
The summarized data for minimum, maximum and average of RPM, SPM,
SO2 and NOX during the study period are presented in Table: 3.12
TABLE: 3.12
AMBIENT AIR QUALITY MONITORING RESULTS
Parameter Observed
Observed Value
Sampling Locations
Limit as per
NAAQ std.
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6
100 PM10 (ug/Nm3)
Min 60 58 55 48 42 40 Max 85 82 73 72 69 65 Avg 72.5 70 64 60 55.5 52.5
PM2.5 (ug/Nm3)
Min 35 33 30 29 28 25 60 Max 45 42 40 38 32 30
Avg 40 37.5 35 33.5 30 27.5
Sox (ug/Nm3)
Min 3.4 3.2 4.4 2.1 2.5 2.9 80 Max 10.1 8.2 8.5 7.9 9.2 9.4
Avg 6.75 5.7 6.45 5 5.85 6.15
Nox (ug/Nm3)
Min 14.3 15.3 11.4 12.2 13.1 11.8 80 Max 19.2 18.4 17.4 18.4 19.3 20.1
Avg 16.75 16.85 14.4 15.3 16.2 15.9
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.23
3.4.8 OBSERVATION BASED ON MONITORING DATA
The observations based on the monitoring results presented in Table have been
summarized below.
3.4.8.1 SUSPENDED PARTICULATE MATTER (PM10)
The maximum value of PM10 is 85 ug/Nm3 observed at village Bharapar &
lowest concentration was observed at village Adipur which is 40 µg/m3 during
the study period.
The average concentration of PM10 varies from 52.5 µg/m3 to 72.4 µg/m3 at
all monitoring locations during the study period, which is well below the
permissible limit of 100 µg/m3 for residential/ rural area.
3.4.8.2 SUSPENDED PARTICULATE MATTER (PM2.5)
The maximum value of PM2.5 is 35 µg/m3 observed at village Bharpar &
lowest concentration was observed at village Adipur which is 25 µg/m3.
The average concentration of PM2.5 varied from 27.5-40 µg/m3 at all the
monitoring locations during the study period which is well below the
permissible limit of 60 µg/m3 for residential/rural area.
3.4.8.3 SULFUR DIOXIDIE (SO2)
The maximum value of SO2 was observed at location at village Bharapar
which is 10.1 µg/m3 and lowest 2.1 µg/m3 at village Tuna.
The average concentration of SO2 varied from 2.1 µg/m3 to 3.4 µg/m3. At all
the locations, the concentration of SO2 was observed within the permissible
limit of 80 µg/m3 for residential area.
3.4.8.4 OXIDE OF NITROGEN (NOx)
Highest concentration of NOx observed as 20.1 µg/m3 at village Adipur &
lowest concentration of 11.4 µg/m3 at village Kidana.
The average concentration of NOx varied from 14.4 µg/m3 to 16.85 µg/m3. At
all the locations, the concentrations of NOx were within the permissible limit
of 80.0 µg/m3 in residential/rural area as per National Ambient Air Quality
Standards.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.24
3.4.9 CONCLUSION
On perusal of the results presented in Table 3.16 it can be concluded that the
concentration of pollutants like PM10, PM2.5, SO2, and NOx in ambient air in
the study area are well within the permissible limit of NAAQS. The National
Ambient Air Quality Standard is presented.
ONSITE AMBIENT AIR MONITORING AT VILLAGE KIDANA
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.25
Table: 3.13
National Ambient Air quality standard: 16 th
November-2009
Sr.
No. Pollutant
Time
duration
Industrial/Residential/
Rural or others
Sensitive
area
(Notified by
Govt. Of
India)
1. Sulfur Dioxide
(SO2), ug/Nm3 24 hrs 80 80
2. Oxide of Nitrogen
(NOx) ug/Nm3 24 hrs 80 80
3.
Particulate Matter
(size less than 10ug)
or PM10 ug/Nm3
24 hrs 100 100
4.
Particulate Matter
(size less than 2.5
ug) or PM2.5
(ug/Nm3)
24 hrs 60 60
3.5 AIR MODELLING
3.5.1 Details of process stacks are as under.
Numbers of Stack 01
Stack Attached to Boilers
Type of fuel used Imported coal
Air pollution control equipments Electrostatic precipitator
Temperature 170-180 deg c
Expected pollutants SPM, SOx, NOx
3.5.2 Assessment of Impact based on ISCST3 model
The dispersion of pollutants in the atmosphere is a function of several
meteorological parameters viz. temperature, wind speed and direction, mixing
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.26
depths, inversion level, etc. A number of models have been developed for the
prediction of pollutant concentration at any point from an emitting source. The
Industrial Source Complex – Short Term (ISCST3) dispersion model is a
steadystate Gaussian plume model. It is most widely accepted for its
interpretability. It gives reasonably correct values because this obeys the
equation of continuity and it also takes care of diffusion, which is a random
process. For the present study, this model is used for the prediction of
maximum ground level concentration (GLC). Assessment of air pollution is
carried out for stacks attached to Boilers.
3.5.3 Model Input Data
The different air emissions at site of the M/s Shree Renuka Sugars Ltd are
SPM, SO2 and NOx from stack attached to Boilers in the plant. The site
specific and monitored details considered for input data for the software
“ISCST3” by Lakes Environmental for prediction of impact on air
environment are given in Table.
Model Input Data
Sr. No. Parameter Rate
1 Numbers of Stack 01
2 Temperature 170-180 deg c
3 Stack height 105 mtrs.
4 Stack diameter 03 mtrs.
5 Exit gas velocity 25 m/s
6 Concentration of SPM g/s 8.83 gm/sec
7 Concentration of Sox g/s 216 gm/sec
8 Concentration of Nox g/s 100 gm/sec
3.5.4 Presentation of results
The simulations were made to evaluate SPM, SO2 and NOx incremental short-
term concentrations due to proposed project. In the short-term simulations, the
incremental concentrations were estimated to obtain an optimum description
of variations in concentrations within study area of 10 km radius.
The air pollution caused by the gaseous emissions from a single or small
group of stacks is a local phenomenon. Its impacts will occur at a distance
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.27
ranging from within the immediate vicinity of the stack to 5 to 10 kilometers
away from the stack. Maximum ground level concentration will occur within
this range. All plumes at more downwind distances from the source by stack
emission become so diluted by diffusion in the ambient atmosphere, that
concentrations of pollutants become negligible. The maximum ground level
concentration for different parameters is given in below table.
CONCENTRATION OF POLLUTATNS
Pollutant
Maximum ground
level concentration
(ug/Nm3)
Distance
KM Direction w.r.t to site
SPM 6.11 1 NW
Sox 41.72 2.2 SW
NOx 19.31 2.1 SW
3.5.5 Meteorological Data
The site-specific hourly meteorological data measured at site. In order to
conduct a refined air dispersion modeling using ISCST3 short-term air quality
dispersion models, the site specific hourly meteorological data measured at
site is preprocessed using the U.S. EPA PCRAMMET and U.S. EPA
AERMET programs.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.28
Figure no. 3.10
ISOPLETH OF SPM
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.29
Figure no. 3.11
ISOPLETH of SOX
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.30
Figure no. 3.12
ISOPLETH of NOX
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.31
3.6 LAND ENVIRONMENT
3.6.1 TOPOGRAPHY OF THE STUDY AREA:
The area under study comes under Biogeographic zone 3 –The Indian desert
and in Biotic Province -3B 1 Kutch
plateau. Topography of the region
near the project site and its
surrounding was characterized by
plain area without much undulating
terrain, mainly barren land with
isolated agriculture fields. Terrain is
rocky with very less top soil layer,
hence not ideal for agriculture. Mathak,
Sangadh Joginar villages situated
towards South- west direction from the
project site are actively engaged in
agriculture activities.
Anjar village and Meghpar villages
situated towards the Northern boundary
of the study area, are characterized by
Undulating terrain and small hillocks, where many quarries are active in stone
mining. No natural forest area is observed within the 10 km radius from
Barapar village.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.32
3.6.2 Baseline Data
Soil may be defined as a thin layer of earth's crust which serves as a natural
medium for the growth of plants. It is the unconsolidated mineral matter that
has been subjected to and influenced by genetic and environmental factors,
such as, parent material, climate organism and physiochemical action of wind,
water and sum light an acting over a long period of time.
Table 3.14
Soil Sample Location
SAMPLE ID NAME DISTANCE FROM SITE(Kms)
S1 Bharapar 0.37
S2 Shinai 5.32
S3 Kidana 2.83
S4 Tuna 2.95
S5 Mathak 7.52
S6 Adipur 7.23
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.33
3.6.3 Methodology
Table 3.15
Methodology for Soil Testing
PHYSICAL AND
CHEMICAL PROPERTIES
UNIT DETAILS OF INSTRUMENT
USED FOR ANALYSIS
pH --- pH meter
Bulk Density Gm/cm3 Balance
Water Holding Capacity % ---
Soil Texture --- Sieve Shaker
Soil Colour --- ---
Nitrogen as N % Titrimetric
Phosphorus % UV-VIS spectrophotometer
Potassium % Flame Photometer
Calcium as Ca % Titrimetric
Nitrate as NO3-N %
Sulfate as SO4 % UV-VIS spectrophotometer
Conductivity Umho/cm Digital conductivity
Organic Matter % Titrimetric
Chloride % Titrimetric
Grain size distribution --- Sieve Shaker
Gravel --- --
Coarse --- --
Coarse Medium --- ---
Coarse- fine --- ---
Silt & clay --- ---
3.6.4 PHYCICAL CHARACTERISTICS
Physical characteristics of soil are delineated through specific parameters like
particle size distribution, bulk density, porosity. Particle size distribution is
analyzed in terms of percentage of sand, silt & clay. From Analysis result it is
observed that, Soil in the area is study is sandy.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.34
Table 3.16 Physical Characteristic of Soil
Sr. No.
Parameters Unit S1 S2 S3 S4 S5 S6
1 pH -- 8.3 8.5 7.9 7.8 8.6 8.1 2 Bulk
Density Gm/Cm3 1.45 1.23 1.21 1.23 1.36 1.42
3 Water Holding capacity
% 12 18 22 22 21 28
4 Soil Texture
-- Sandy Sandy Sandy Sandy Sandy Sandy
5 Soil Color
-- Earth Brown
Earth Brown
Dark Brown
Dark Brown
Earth Brown
Earth Brown
6 Nitrogen as N
% 0.12 0.18 0.36 0.35 0.70 0.75
7 Phosphorus g/kg 0.005 0.008 0.025 0.025 0.007 0.12 8 Potassium
as K g/kg 0.02 0.056 0.023 0.022 0.035 0.045
9 Calcium as Ca
g/kg 0.159 0.161 0.164 0.167 0.165 0.163
10 Nitrate as NO3-N
g/kg 0.065 0.070 0.086 0.087 0.055 0.060
11 Sulphate as SO4
g/kg 0.09 0.07 0.11 0.12 0.12 0.06
12 Electrcial Conductivity
Umho/cm 200 219 225 228 256 230
13 Organic Matter
g/kg 1.1 2.5 2.30 2.32 7.3 6.4
14 Chloride g/kg 0.148 0.150 0.145 O.144 0.150 0.151 15 Particle size distribution 16 Gravel % 3 5 12 16 15 17 C Sand % 12.5 16.1 14.3 13.8 16.4 11.5 18 C- M Sand % 32.33 55.3 40.3 39.3 49.2 52.1 19 C- F sand % 28.5 27.6 29.4 30.1 30.1 31.5 20 Silt & clay % 3.5 3.6 3.5 3.4 3.4 3.3 21 Moisture
Content % 0.4 1.2 0.8 0.9 0.9 0.8
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.35
3.6.5 Conclusion
Following text depicts the quality of soil in the study area
• pH is an important parameter indicative of the alkaline or acidic nature of
the soil. It greatly affects the microbial population as well as the solubility
of metal ions and regulates nutrient availability. The pH of the soil were in
the range of 7.9 to 8.6.
• Electrical conductivity, a measure of soluble salts in soil was in the range
of 200-256 mho/cm.
• The important captions present in soil are calcium and Phosphorus. It was
observed that both calcium and Phosphorus concentrations were in the
range of 0.159 to 0.165 g/kg and 0.005 - 0.12 g/Kg respectively.
• Potassium was in the range of 0.02-0.056 g/kg.
3.7 BIOLOGICAL ENVIRONMENT
3.7.1 TERRSTRIAL ENVIRONMENT
Environmental impact assessments have become an integral part of
development projects to formulate policies and guidelines for environmentally
sound economic development. Proper assessment of biological environment
and compilation of its taxonomical data is essential for the impact prediction.
3.7.2 PERIOD OF THE STUDY AND STUDY AREA
The baseline study, for the evaluation of the floral and faunal biodiversity of
the terrestrial environment with in 10 km from the project site, located near
Bharapar village in Kutch District was conducted during May-2010
3.7.3 METHODOLOGY
The sampling plots for this floral inventory were selected randomly in the
suitable habitats within the 10km radius from the project site.
3.7.4 TERRESTRIAL FLORAL AND FAUNAL COMPONENTS OF T HE
STUDY AREA:
The villages covered for the present baseline study are given in the table 3.17.
All together 20 villages were covered for the present biological baseline study.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.36
4 villages were selected in the core area (Project site and surrounding villages)
and 27 villages were selected in the buffer zone (with in10km radius).
Table 3.17
List of Villages covered under the present baseline study
# Village Name
Core zone ( closer to project site)
1 Barapar
2 Rampar
3 Tuna
4 Kiddana
Buffer zone- ( with in 10km radius)
5 Sangadh
6 Mathak
7 Jogninar
8 Shinai
9 Adipur
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.37
3.7.5 FLORAL DIVERSITY OF THE STUDY AREA:
The objective this floral inventory of the study area, is to provide necessary
information on floristic structure in the study area for formulating effective
management and conservation measures. The climatic, edaphic and biotic
variations with their complex interrelationship and composition of species,
which are adapted to these variations, have resulted in different vegetation
cover, characteristic of each region. The following account of floral inventory
has been, based on the field survey conducted for a short duration in the May,
2010, is not very comprehensive data and is aimed only to give a general
pattern of vegetation of this region during the study period as a baseline data
in absence of secondary data. Listing of the endangered, threatened and
endemic species of flora in a locality and drawing the attention to the
occurrence of such species, would aid in creating awareness amongst the local
people as a whole to protect such species from extinction, and to take
necessary measures for their conservation. These type of floristic study is an
inventory for such purpose and hence a necessity.
The dominant tree species, herbs, shrubs, climbers and major crops, were
documented during this base line study. The list of floral species documented
in the study area is enlisted in table# 3.18
The vegetation of the area investigated can be classified on the basis of
habitats as; Open barren/ fallow lands, areas under cultivations, hedge
vegetation, scrub forest, and vegetation in salt ingressed region
Open fallow lands is the most dominant landscape pattern of the study area.
These fallow lands were dominated by the herbaceous species; Cassia italica,
Cassia auriculata, Echinops echinatus, Crotalaria bruhia Leptadenia
pyrotechnica, Indigofera oblongifolia, and Boerhavia diffus .
Hedge vegetation mainly consisted of various climbers and stiff shrubs like
Balanites aegyptiaca, Aerva persica, Zizyphus nummularia, Capparis decidua,
Ipomoea obscura, and Prosopis juliflora. Scrub forest of this area was
dominated by species Prosopis juliflora, Salvadora persica, and Salvadora
oleoides. The salt ingressed region of this area was characterized by the salt
resistant species Suaeda fruticosa, Suaeda maritima, Salicornia brachiata and
Aeluropus lagopoides
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.38
The tree population was very less in this part of Kachchh district. The
dominant trees growing in this area are Phoenix sylvestris, Acacia nilotica,
Acacia leucophloea, Balanites aegyptiaca, Azadirachta indica,
Pithecellobium dulce, Prosopis cineraria, Salvadora persica and S. oleoides.
The tree species observed in the study area is enlisted in the table 3.18
Shrubs are the dominant perennials of this area, represented mainly by,
Leptadenia pyrotechnica, Prosopis juliflora, Aerva persica, Calotropis
procera, C. gigantea, Zizyphus nummularia, Tecoma stans, Cassia auriculata,
C.italica Ipomoea fistulosa, Euphorbia nivulia and Capparis decidua. The
shrub species observed in the study area are documented in Table 3.19
3.7.5.1 Trees
Tree species enlisted from the study area is given in the table #3.18. 43 tree
species belong to 20 families are enlisted from the study area.
Table 3.18
Trees in the study area
Family & Scientific name Vernacular name 1 Anacardiaceae 1/1 Mangifera indica L. Ambo 2 Annonaceae 2/1 Annona squamosa L. Saitafal 3/2 Polylathia longifolia (Conn.) Thw. Asopalav 3 Apocynaceae 4/1 Plumeria obtuse L Chambo 5/2 Nerium indicum Mill. Lalkaren 6/3 Thevitia peruviana (Pres.) Pilikaren 4 Arecaceae 7/1 Phoenix sylvestris (L.) Roxb Khajuri 8/2 Hyphaene dichotoma Bece Ravantad 9/3 Cocos nucifera L. Nariiel 5 Avicenniaceae 10/1 Avicennia marina var. acutissima
Stapf.&Mold Tivar
6 Balanitaceae 11/1 Balanites aegyptiaca (L.) Del. Ingorio 7 Caesalpiniaceae 12/1 Parkinsonia aculeata L Rambaval 13/2 Peltophorum pterocarpum (DC.)
Backer ex Heyne Sonmukhi
14/3 Tamarindus indicum L. Amali 15/4 Senna siamea Lam. Kasida 8 Casuarinaceae
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.39
16/1 Casuarina equisetifolia L. Sharu 9 Combretaceae 17/1 Terminalia catappa L. Badam 10 Ehretiaceae 18/1 Cordia dichotoma Forst. Mota Gunda 19/2 Cordia gharaf (Forsk.) E. & A. Nani Gundi 11 Malvaceae 20/1 Thespesia populnea (L.) Sol.ex Corr. Paras piplo 12 Meliaceae 21/1 Azadirachta indica A.Juss Limbado 13 Mimosaceae 22/1 Acacia auriculiformis L Austrialanbaval 23/2 Acacia nilotica (L.) Del.subsp.indica
(Bth.) Brenan Baval
24/3 Acacia senegal ( Willd.) Gobita) 25/4 Acacia chundra (Roxb.ex.Rottl. Kair 26/5 Acacia Jacquemontii Bth. Ratobaval 27/6 Acacia leucophloea (Roxb) Hermobhaval 28/7 Leucaena leucocephala (Lam.) De Pardesi Baval 29/8 Prosopis cineraria (L.) Druce Khyigdo 30/9 Dichrostachys cinerea Wt. & Arn. Mor Dhunadhiya 31/10 Pithecellobium dulce Benth. Goras-amli 32/11 Albizia lebbeck Benth. Siris 14 Moraceae 33/1 Ficus benghalensis L Vad 34/2 Ficus religiosa L Piplo 35/3 Ficus sp. Vad 15 Moringaceae 36/1 Moringa oleifera Lam Sargavo 16 Myrtaceae 37/1 Eucalyptus citriodora Hk. Nilgari 17 Salvadoraceae 38/1 Salvadora persica L. Piludo 39/2 Salvadora oleoides Decne Piludi 18 Sapotaceae 40/1 Achras zapota L. Chickoo 19 Simaroubaceae 41/1 Ailanthus excelsa Roxb. Aurdso 20 Rhamnaceae 42/1 Zizyphus glabrata Heyne ex Roth Bor 43/2 Zizyphus mauritiana Lam Bordi
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.40
3.7.5.2 Shrubs:
Shrubs encountered during the present survey are given in the Table#3. 19
shrubs belong to 13 families are enumerated from the study area, Most
dominant shrub among them were Prosopis juliflora, Leptadenia
pyrotechnica, Calotropis gigantea, C. procera, Capparis decidua and Cassia
auriculata
TABLE 3.19
LISTS OF SHRUBS IN THE STUDY AREA
Family & Scientific name Vernacular name
1 Apocynaceae 1/1 Thevetia peruviana Merr. Pili karan 2/1 Nerium indicum Mill Lalkaren 2 Asclepiadaceae 3/1 Leptadenia pyrotechnica (Forsk.) Decne. Khip 4/2 Calotropis gigantean (L.) R. Br Akado 5/3 Calotropis procera (Ait.) R.Br Akado 3 Bignoniaceae 6/1 Tecoma stans (L.) H.B.& K. Peilafol 4 Cactaceae 7/1 Opuntia elatior Mill. Fafdo Thor 5 1 Capparaceae 8/1 Capparis decidua (Forsk.) Edgew Kerdo 6 Caesalpiniaceae 9/1 Cassia auriculata L Aval 10/2 Cassia italica (Mill.) ex. Andrews Mithiaval 7 Chenopodiaceae 11/1 Suaeda maritima (L.) 8 Convolvulaceae 12/1 Ipomoea fistulosa Mart.ex Choisy Nasarmo 9 Euphorbiaceae 13/1 Euphorbia nivulia Buch. – Ham. Thor 10 Mimosaceae 14/2 Prosopis juliflora DC Gando baval 11 Nyctaginaceae 15/1 Bougainvillea spectabilis Willd. Bougainvel 12 Rhamnaceae 16/1 Zizyphus mauritiana Lam. - Boadi 17/2 Zizyphus nummularia (Burm.f.) W. &. Chanibor 13 Solanaceae 18/1 Solanum incanum L Ubhi ringan 19/2 Datura metel L Daturo
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.41
3.7.5.3 Herbs:
The herbaceous cover observed in this region is given in the table 3.20.Total
23 herbaceous species belongs to 13 families are recorded from the study area
Table 3.20
List of herbaceous species observed in the area
Family & Scientific name Vernacular name
1 Acanthaceae 1/1 Barleria sp. --- 2/2 Hygrophila ainguriculata (Schum.) Kanatashelio,Akaro 2 Asteraceae 3/1 Echinops echinatus Roxb Shulio 3 Cactaceae 41 Opuntia elatior Mill. Thor 4 Chenopodiaceae 5/1 Salicornia brachiata Roxb. 6/2 Suaeda nudiflora (willd) Moq. Moras 7/3 S. fruticosa L. 5 Cucurbitaceae 8/1 Cucumis callosus Cogn Kothimdu 9/2 Citrullus colocynthis L. Indravarna 6 Cyperaceae 10/1 Cyperus sps. - 11/2 Fimbristylis sps. - 7 Liliaceae - 12/1 Aloe barbadensis Mill. Kunvarpato 8 Nyctaginaceae 13/1 Boerhavia diffusa L. - 14/2 Boerhavia chinensis Druce Satodi 9 Papilionaceae 15/1 Crotalaria burhia Bach. – Ham. - 16/1 Indigofera oblongifolia Forks. - 10 Papaveraceae 17/1 Argemone mexicana L. Darudi 11 Poaceae (Gramineae) 18/1 Phragmites karaka Steud - 19/2 Aleuropus lagopoides Trin - 20/3 Cynodon dactylon Pers. - 12 Solanaceae 21/1 Solanum nigrum L. - 22/2 Solanum xanthocarpum Schrad. & Wendl. - 13 Typhaceae 23/1 Typha angustata Bory & Chaub -
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.42
3.7.5.4 Climbers and Twiners:
The climbers and twiners observed along the agricultural hedges and road side
hedges of the study area is given in the table#3.21.Total 3 climbers belongs to
2 families were recorded from the area
TABLE 3.21
LIST OF CLIMBERS OBSERVED IN THE STUDY AREA
Family & Scientific name Vernacular name
1 Convolvulaceae
1/1 Ipomea pes tigridis L Wagpadi
2/2 Ipomoea pes-capraeL. Dariani vel
2 Cucurbitaceae
3/1 Luffa cylindrica (L.) M.J.Roem Galku
3.7.6. CULTIVATED PLANTS IN THE STUDY AREA:
The agriculture fields are restricted to very few isolated pockets in the study
area. During the survey period of May 2010, most of the fields were without
any cultivation. Khedoi, Sinugrah, Nani Nagalpar and Moti Nagalpar are the
only villages observed with large scale agriculture practice. Cultivation of
Vegetables like Bhindi, Tindora, ground nut are observed at Nani Nagalpar
and Moti Nagaplar villages. The crop occupying the highest percentage of the
sown area of this region is taken as the major crop and all other possible
alternative crops which are sown in this region either as substitutes of the base
crop in the same season or as the crops which fit in the rotation in the
subsequent season, are considered as minor crop.
3.7.6.1 Major Crops
Major crops in the study area are Bajra (Pennisetum typhoides (Burm.f.), and
Jowar (Sorghum bicolor (L.) Moench),
3.7.6.2 Minor crops
Minor crops practiced in this region during winter are Makai (Zea mays L),
and Cotton (Gossypium herbaceum).
3.7.6.3 Pulses
The pulses cultivated in this region are Tuver (Cajanus cajan)
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.43
3.7.6.4 Vegetables
Bindi (Abelmoschus esculentus) is dominant vegetable crop of this area
especially at Moti and Nani Nagalpar villages
3.7.7 HORTICULTURAL PRACTICES AND FRUITS GROWN
Plantation of Phoenix sylvertris (Khajur or Dates) are observed at most of the
villages in the study area. Mango (Mangifera indica) orchards and Chikko
(Manilkara zapota) plantation and papaya (Carica papaya) cultivation were
observed in Nani Nagaplar village in the study area.
3.7.8 MEDICINAL PLANTS OF THE STUDY AREA: Plants are known for their therapeutic value and uses since ancient period. The
reference of curative properties of the some herbs in “Rigveda” (3500-1800
BC) though in brief, seems to be the earliest records of use of plants in
medicine. With the time more and more plants have been added to the native
medicine. Out of the 17000 known flowering plant species in India, about
7,500 wild plants species are reported to be used for medicinal purpose. Some
important work on Indian medicinal plants are from, Watt (1889-1893),
Ymoch et.al. (1890), Basu and Kirtikar (1918), Nandkarni (1954), Chopra
et.al. (1956) Jain and De Filipps (1991).
The medicinally important plants observed growing in the study area and their
usage is given in the table 3.22
Table 3.22
Medicinal plants in the study area and their medicinal uses
Scientific Name Vernacular
Name
Useful
parts
Medicinal uses
Acacia nilotica
Baval
Bark Astringent, biliousness, bronchitis,
cough, diarrhea, dysentery,
lecuoderma, piles, skin diseases
Flowers Astringent
Fruits Backache, eye complaints
Gum Sexual disorder
Leaves Diarrhea, gonorrhea
Seeds Diarrhea, dysentery, ulcers
Gum Cough, inflammations
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.44
Acacia senegal
Goradio Baval
Root
bark
Diabetes, urinary complaints
Seeds Demulcent, emollient
Stem
bark
Diabetes, urinary complaints
Scientific Name Vernacular
Name
Useful
parts
Medicinal uses
Ailanthus excelsa
Aurdso
Bark Asthma, astringent, bronchitis,
diarrhea, dysentery, fever, skin
disease
Leaves Tonic
Azadirachta
indica Juss.
Limdo
Bark Antiseptic, blood purifier, boils,
fever, tumors, ulcers, wounds.
Flowers Antiseptic, blood purifier, ulcers,
wounds
Fruits Anthelmintic, antipyretic ,coolant,
malaria, urinary diseases
Leaves Anthelmintic antipyretic, antiseptic
Balanites
aegyptiaca Del. -
Ingorio
Bark Anthelmintic, purgative, skin
diseases,
Fruits Anthelmintic , purgative,
Seeds Blood purifier, coolant, cough,
injury
Root
barks
boils
seeds Dysentery, fracture, liver disorder,
night blindness, piles, ulcers
Calotropis
gigantea
Akado
Flowers Analgesic, Anthelmintic,
astringent, expectorant
Leaves Malaria fever, wounds
Roots Dental problem, rheumatism,
stomach disorder
Root Asthma, diaphoretic, jaundice,
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.45
bark syphilis
Whole
plant
Anthelmintic, joint pain, leprosy,
lecuoderma, piles, purgative,
swelling, tooth ache, tumors, ulcers
Calotropis
procera
Akado
Flowers Analgesic, astringent,
Anthelmintic, digestive disorders,
expectorant,
Latex Analgesic, gout, rheumatism, skin
diseases
Leaves Sun stroke, wounds
Roots Boils, piles
Root
bark
Antidote, asthma, diaphoretic,
syphilis
Whole
plant
Anthelmintic, joint pain, leprosy,
lecuoderma, piles, purgative,
swelling, tooth ache, tumors, ulcers
Cassia auriculata
Aval
Leaves Asthma, fracture, swelling, leprosy,
Roots Asthma, fracture, swelling, leprosy,
urinary discharge
Root
bark
Digestive disorder, intestinal
diseases
Stem
bark
Asthma, astringent, leprosy
Cassia italica Sona mukhi leaves Digestive disorders, influenza,
purgative
Casuarina
equisetifolia
Sharu Bark Astringent, diarrhea, dysentery
Seeds Headache
Eucalyptus
citriodora
Nilgari Leaves Cold, fever, urinary complaints
Oil Asthma, bronchitis
Scientific Name Vernacular
Name
Useful
parts
Medicinal uses
Euphorbia
Thor
Leaves Ear ache, impotency, piles, tooth
ache
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.46
neriifolia Whole
plant
Anemia, asthma, bronchitis,
diabetes, lecuoderma, purgative,
rheumatism, schizophrenic
Ficus bengalensis
Vad
Aerial
roots
Aphrodisiac, appetizer
Bark Astringent, diarrhea, dysentery
Latex Coolant, sexual disorder
Leaves Abscesses
Roots Fracture, piles
Seeds Coolant
Ficus religiosa L.
Paipal
Bark Astringent, skin diseases
Flower Aphrodisiac, purgative, vomiting
Fruits Coolant and laxative
Leaves Purgative, antidote
Roots Jaundice
Root
bark
Aphrodisiac, lumbago
Ipomoea fistulosa Nasarmo Whole
plant
Anti fungal, antibiotic
Mangifera indica
Am
Bark Biliousness, coolant, diarrhea,
dysentery, leucorrhoea, ulcers.
Flowers
Leaves
Cancer
Gum Antidote
Opuntia eletior
Katar
Stem Analgesic, boils and wounds
Whole
plant
Asthma, cough, heart
inflammation, ophthalmia,
Salvadora
oleoides
Piludi
Fruits Ulcer in mouth
Leaves Purgative
Roots Dental problem
Whole
plant
cough, bronchitis, piles,
rheumatism
Roots Analgesic
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.47
Salvadora persica Pilu, Kharijal Whole
plant
Biliousness, inflammations,
lecuoderma, piles, skin diseases,
tonic to the liver
Solanum indicum
Ubhairingni
Fruits Dental problem, vermifuge
Roots Acidity, Anthelmintic, asthma,
bronchitis, carminative, cathartic,
cough, expectorant, fever
Stem Dental problem
Tamarindus
indica
Emli
Fruits Digestive disorder, inflammation,
laxative.
Leaves Analgesic, fever, skin diseases
Seeds Antidote, intestinal diseases
Source: C.N. Pandey, etal (2005) Medicinal Plants of Gujarat
3.7.9 ETHANOBOTANICLAL IMPORTANT PLANTS AND PRACTIC ES,
PREVAILING IN THE AREA
Man depended on plants since time immemorial. Our knowledge of the
intimate relationship between early man and plants is mainly due to the
surviving tradition. This relation ship now forms the base of the
interdisciplinary science known as Ethanobotany. The term “Ethanobotany“
was first coned by J.W. Harshberger in 1895. Plotkin (1995) defined
ethanobotany as the study of tribal people and their utilization of plants.
• Calotropis procera (Ait.) R. Br. (Asclepiadaceae)
Leaves are smeared with castor oil and the lukewarm castor smear is
applied on the abdomen of a child for relief against pain due to
constipation. Used extensively in the herbal medicine.
• Echinops echinatus Roxb. (Asteraceae)
Roots and seeds of this herb are used to cure stomach ache and to increase
the appetite. Roots are pounded and mixed with Acacia gum and applied
to destroy lice, powder applied to cattle to destroy maggots, used in
ayurvedic medicines.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.48
• Ficus religiosa L. (Moraceae)
Young buds and leaves are dried, powdered and given twice a day with
water as tonic. Leaves make fodder of choice for camels. Fruits are eaten
by birds
• Tamarindus indica L. (Caesalpiniaceae)
Pulp of the ripe fruits as well as a poultice of the leaves is applied
externally to inflammatory swelling to relive pain. Pulp is also very useful
for checking bilious vomiting; Poultice of flowers is useful in
inflammatory affection of conjunctivitis. Decoction of the leaves is used as
a wash for indolent ulcers. The bark is used for loss of sensation in
paralysis. The ash is given for urinary discharge and gonorrhea. The ripe
fruit is appetizing, laxative tonic to the heart, and heals wounds and
fractures. The seeds are useful in vaginal discharge and ulcers.
3.7.10 ENDEMIC PLANTS OF THE STUDY AREA
De Candolle (1855) first used the concept of “Endemic”, which is defined as
an area of a taxonomic unit, especially a species which has a restricted
distribution or habitat, isolated from its surrounding region through
geographical, ecological or temporal barriers.
Out of 17000 species of known flowering plants of India nearly 5000 species
are said to be endemic. Nearly 58 genera and 1932 taxa are found to be
endemic to peninsular India (Ahmedulla & Nayar, 1987). None of the
documented flora from the study area cab be assigned endemic status.
3.7.11 FAUNAL BIODIVERSITY OF THE STUDY AREA
For the documentation of the faunal biodiversity of the study area with respect
to birds, reptiles, amphibians, and butterfly species, a detailed survey had been
conducted among 20 villages in the study area, within 10 km radius from
proposed site near in Bharapar village, Gandhidham taluka in Kachchh
District. This report is based on a short duration study. The following lists are
obviously incomplete. It does not include many other species which might
occur in this part of Kachchh District, either as resident or as migrant in the
other seasons of the year. This data is based on the survey conducted during
May, 2010.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.49
3.7.12 Birds of the study area:
• Few Birds in the study area are categorized as near threatened by IUCN
red list 2010. Their distribution is given in the table # 3.23 Systematic
accounts of the birds in the study area with the status of occurrence is
given in the table 3.24.
TABLE 3.23
THREATENED AND NEAR THREATENED BIRDS OF THE STUDY A REA
Species Habitat Threat status
IUCN Location
Painted stork
(Mycteria leucocephala)
Shallow water
bodies
Near threatened
B-11
Tuna village
Kandla Village
Black headed ibis
(Threskiornis
melanocephalus)
Near water
bodies and
agriculture
fields
Near
Threatened
B10/8
Tuna village
Kandla village
Source: IUCN Red list of threatened species 2010 and Bird life international
2009
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.50
TABLE 3.24
SYSTEMATIC LISTS OF BIRDS IN THE STUDY AREA WITH IT S
DISTRIBUTION AND MIGRATORY STATUS
Old Common name New Common Name Scientific Name Status
I ORDER: ANSERIFORMES
Family: Anatidae (Ducks and teals)
Spotbill Spot-billed Duck Anas poecilorhyncha R
II ORDER: APODIFORMES
Family: Apodidae (swifts)
Common Swift Common Swift Apus apus R
House swift Little Swift Apus affinis R
III ORDER: CICONIIFORMES
Family: Accipitridae (vulture, Sparrow hawk, Eagle, Harrier, Kite and Vulture)
Shikra Shikra Accipiter badius R
Black-winged Kite Black-winged Kite Elanus caeruleus R
Family: Ardeidae (heron, Egret, Bittern)
Cattle Egret Cattle Egret Bubulcus ibis R
Median or Smaller Egret Intermediate Egret Mesophoyx intermedia
Egretta intermedia R
Little Egret Little Egret Egretta garzetta R
Indian Reef Heron Western Reef-Egret Egretta gularis
Note: R = Widespread Resident, r = Very Local Resident, W = Widespread Winter
Visitor, w = Sparse Winter Visitor, RW =Resident and winter visitor,
Family: Charadriidae (Plover, Stilt, Oystercatcher, Lapwing, Avocet )
Black-winged Stilt Black-winged Stilt Himantopus himantopus R
Red-wattled Lapwing Red-wattled Lapwing Vanellus indicus R
Yellow-wattled Lapwing Yellow-wattled
Lapwing
Vanellus malabaricus R
Avocet Pied Avocet Recurvirostra avosetta rW
Family: Ciconiidae (Open bill, stork, Adjutant)
Painted Stork Painted Stork Mycteria leucocephala R
Family: Phalacrocoracidae ( Cormorant
Little Cormorant Little Cormorant Phalacrocorax niger R
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.51
Family: Phoenicopteridae(Flamingo)
Flamingo Greater Flamingo Phoenicopterus rubber
P. roseus
Family: Podicipedidae (Grebe)
Little Grebe Little Grebe Tachybaptus ruficollis R
Family: Pteroclidae (Sandgrouse)
Indian Sandgrouse Chestnut-bellied
sandgrouse
Pterocles exustus
Family: Scolopacidae (Sandpiper, Turnstone, Stint, Snipe, Godwit, Curlew, shank,
Woodrock)
Curlew Eurasian Curlew Numenius arquata
Whimbrel Whimbrel Numenius phaeopus
Family: Threskiornithidae (Spoonbill and Ibis)
Black Ibis Red-naped Ibis Pseudibis papillosa R
Spoonbill Eurasian Spoonbill Platalea leucorodia RW
White Ibis Black-headed Ibis Threskiornis
melanocephalus R
Old Common name New Common Name Scientific Name Status
IV ORDER: COLUMBIFORMES
Family: Columbidae (Pigeon, Dove)
Blue Rock Pigeon Rock Pigeon Columba livia R
Ring Dove Eurasian Collared-Dove Streptopelia decaocto R
Rufous Turtle Dove Oriental Turtle-Dove Streptopelia orientalis R
V : ORDER: CORACIFORMES
Family: Alcedinidae (King fisher)
Small Blue King Fisher Common Kingfisher Alcedo atthis R
Family: Dacelonidae (King fishers)
White breasted
Kingfisher White-throated Kingfisher
Halcyon smyrnensis R
Family: Coraciidae (Roller)
BlueJay or Roller Indian Roller Coracias benghalensis
Family: Meropidae (Bee Eater)
Chestnut-headed Bee- Chestnut-headed Bee-eater Merops leschenaulti R
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.52
eater
Blue-cheeked Bee-eater Blue-cheeked Bee-eater Merops persicus
Merops superciliosus R
VI. ORDER: CUCULIFORMES
Family: Centropodidae (Cocucal)
Crow-Pheasant or Coucal Greater Coucal Centropus sinensis R
Note: R = Widespread Resident, r = Very Local Resident, W = Widespread Winter
Visitor, w = Sparse Winter Visitor, RW =Resident and winter visitor,
Family: Cuculidae (cuckoo, Koel)
Koel Asian Koel Eudynamys scolopacea R
Indian Drongo Cuckoo Drongo Cuckoo Surniculus lugubris R
Cuckoo Common Cuckoo Cuculus canorus R
VII. ORDER: GALLIFORMES
Family: Phasianidae (Peafowl , Partridge, Quail, francolin, spur fowl, jungle fowl,
Monal, )
Common Peafowl Indian Peafowl Pavo cristatus R
VIII ORDER: GRUIFORMES
Family: Rallidae ( Waterhen, coot, crake water cock, Moorhen, Rail,)
Coot Common Coot Fulica atra RW
IX ORDER: PASSERIFORMES
Family: Paridae (Tit )
Grey Tit Great Tit Parus major R
Family: Corvidae
Raven Common Raven Corvus corax R
House Crow House Crow Corvus splendens R
Old Common name New Common Name Scientific Name Status
Family: Laniidae (shrike)
Rufousbacked Shrike Long-tailed Shrike Lanius schach R
Grey Shrike Northern Shrike Lanius excubitor R
Family: Muscicapidae ( Short wing, Chat, Robin, Shama
Indian Robin Indian Robin Saxicoloides fulicata R
Pied Bushchat Pied Bushchat Saxicola caprata R
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.53
Family: Nectariniidae ( Sun Birds, Flower pecker, Spider hunter )
Purple Sunbird Purple Sunbird Nectarinia asiatica R
Maroon breasted Suinbird Long-billed Sunbird Nectarinia lotenia R
Small Sunbird Crimson-backed Sunbird Nectarinia minima R
Family: Passeridae ( Avadavat,Pipit, Wagtail, Munia, Snowfinch, sparrow, weaver
,Accentor)
House Sparrow House Sparrow Passer domesticus R
Family: Pycnonotidae (Bulbul, )
Red-whiskered Bulbul Red-whiskered Bulbul Pycnonotus jocosus R
Red-vented Bulbul Red-vented Bulbul Pycnonotus cafer R
Family: Sturnidae (Myna, Starling)
Bank Myna Bank Myna Acridotheres ginginianus R
Indian Myna Common Myna Acridotheres tristis R
Family: Sylviidae ( Warbler, Browning, Fulvetta ,Babbler, Laughing thrash,
Tailor birds,
Common Babbler Common Babbler Turdoides caudatus R
Jungle Babbler Jungle Babbler Turdoides striatus R
Tailorbird Common Tailorbird Orthotomus sutorius R
X. ORDER: PSITTACIFORMES
Family: Psittacidae (Parrot and Parakeet)
Rose-ringed Parakeet Rose-ringed Parakeet Psittacula krameri R
Note: R = Widespread Resident, r = Very Local Resident, W = Widespread
Winter Visitor, w = Sparse Winter Visitor, RW =Resident and winter
visitor,
• Butterflies from the study area:
Butterflies in the study area (Core zone and Buffer zone) are restricted to few
places where Lantana camara and Calotropis procera was growing.
Butterflies observed during the present study are documented in the Table
3.25.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.54
TABLE 3.25
BUTTERFLIES IN THE STUDY AREA
Scientific name & family Common name
Family Papilionidae
Papilio polytes Common Mormon
Family Pieridae
Eurema hecabe Common Grass yellow
Catopsilia Pomona Common Emigrant
Delias eucharis Common Jezebel
Ixias Marianne White orange tip
Family: Nymphalidae
Danaus chrysippus Plain Tiger
Danaus genutia Cramer Stripped Tiger
Hypolimanas misippus Danaid egg fly
Mycalesis perseus Common bush brown
• Herpetofauna :
Reptiles observed in the study area are given in the table 3.26
TABLE 3.26
REPTILES IN THE STUDY AREA
Sr. No. Common Name Scientific name
1 Common garden lizard Calotes versicolor (Daudin)
2 Indian Cobra � Naja naja (Linn.)
3 Common rat snake� Ptyas mucosus (Linn.)
4 Common Indian monitor Varanus bengalensis (Schneider)
5 Star Tortoise Geochelone elegans ( Schoepff.)
� Based on the information provided by the villagers (Secondary
information)
• Mammals:
o Core zone:
The wild mammals observed other than the domesticated ones in the
core zone is given in the table 3.27
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.55
Table 3.27
Wild mammals in the core zone
Sr. No. Common Name Scientific name
1. Three striped Palm squirrel Funambulus palmarum
2. Common Mongoose Herpestes edwardsi
3. Nilgai Boselaphus tragocamelus (Pallas)
o Buffer Zone
The wild mammals observed other than domesticated ones from buffer
zone of the study area is documented in the table 3.28
TABLE 3.28
MAMMALS IN THE BUFFER ZONE
Sr. No. Common Name Scientific name
1 Three striped Palm squirrel Funambulus palmarum ( Linnaeus)
2 Indian field mouse Mus booduga (Gray)
3 Indian Fox � Vulpes bengalensis (Shaw)
4 Common Mongoose Herpestes edwardsi
5 Hare Lepus sp.
6 Nilgai Boselaphus tragocamelus (Pallas)
7 Indian Hedgehog Paraechinus micropus (Blyth,)
8 Indian Wild Boar Sus scrofa Linaeus
�As per the information provided by the villagers consulted during the survey
(secondary information) None of them were sighted during the survey period
in the core zone and buffer zone).
3.7.13 ENDEMIC FAUNA OF THE STUDY AREA
None of the sighted animal species can be assigned endemic species category
of the study area.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.56
3.7.14 MIGRATORY BIRDS AS WINTER VISITORS IN THE ST UDY AREA
Table 3.29
Winter visitors in the study area
Zone Winter visitors Resident and Winter visitors
Core Zone -
Buffer zone - Eurasian Spoonbill, Common Coot,
Whole study area - Eurasian Spoonbill, Common Coot,
3.7.15 STATUS OF THE FOREST, THEIR CATEGORY IN THE STUDY
AREA
No natural forest area as such was observed within the 10 km radius from
project site.
3.7.16 RECOMMENDED PLANTS FOR GREEN BELT DEVELOPMEN T
Greenbelts are an effective mode of control of air pollution, where green
plants form a surface capable of absorbing air pollutants and forming a sink of
pollutants. Leaves with their vast area in a tree crown, sorbs pollutants on their
surface, thus effectively reduce pollutant concentration in the ambient air.
Often the adsorbed pollutants are incorporated in the metabolic pathway and
the air is purified. Plants grown to function as pollution sink are collectively
referred as greenbelts.
An important aspect of a greenbelt is that the plants are living organism with
their varied tolerance limit towards the air pollutants. A green belt is effective
as a pollutant sink only within the tolerance limit of constituent plants.
Planting few, known pollutant sensitive species along with the tolerant species
within a green belt however, do carry out an important function of indicator
species
Apart from function as pollution sink, greenbelt would provide other benefit
like aesthetic improvement of the area and providing suitable habitats for birds
and animals.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.57
3.7.16.1 Selection of plants for Green Belts:
The main limitation for plants to function as scavenger of pollutants are,
plant’s interaction to air pollutants, sensitivity to pollutants, climatic
conditions and soil characteristics. While making choice of plants species for
cultivation in green belts, due consideration has to be given to the natural
factor of bio- climate. Xerophytes plants are not necessarily good for
greenbelts; they with their sunken stomata can withstand pollution by
avoidance but are poor absorber of pollutants.
Character of plants mainly
considered for affecting absorption of pollutant gases and removal of dust
particle are as follows.
• For absorption of Gases:
1. Tolerance towards pollutants in question , at concentration , that are
not too high to be instantaneously lethal
2. Longer duration of foliage
3. Freely exposed foliage
4. Adequate height of crown
5. Openness of foliage in canopy
6. Big leaves( long and broad laminar surface)
7. Large number of stomatal apertures
• For Removal of Suspended Particular matter
1. Height and spread of crown.
2. Leaves supported on firm petiole
3. Abundance of surface on bark and foliage
4. Roughness of bark
5. Abundance of axillary hairs
6. Hairs or scales on laminar surface
7. Protected Stomata
3.7.16.2 Plantation along road sides:
Automobiles are the source of pollution of gaseous and particulate pollutants.
Component of green belt on road side hence should be with both absorbers of
gases as well as of dust particles. The choice of plants for road side should
include shrubs of height 1 to 1.5 meter and trees of 3-5 meter height. Medium
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.58
sized trees, alternating with shrubs are ideal for sorption of particulates and
gases.
TABLE 3.30
RECOMMENDED PLANT SPECIES FOR GREEN BELT DEVELOPMEN T
Plant species Habit Tolerance
limit
Stomatal
index
Mode of
Regeneration
Acacia auriculiformis Tree Tolerant 10.9 Seeds
Acacia catechu tree 8.24 seeds
Acacia leucocephala ( Hari
baval)
Shrub T 12.01 seeds
Ailanthus excelsa tree T 13.01 Seeds, shoot,
root cuttings
Azadirachta indica Tree T 29.2 Seeds
Bougainvillea spectabilis Shrub T 32.53 Cutting
Caesalpinia pulcherrima
(White gold mohur)
Tree T 29.09 Seeds and
Cuttings
Calotropis gigantean Shrub T 9.93 Seeds
Calotropis procera Shrub T 10.32 Seeds
Cassia siamea Tree T 21.2 Seeds
Cordia dichotoma (Gunda) Tree T N.A Seeds/ stem
cuttings
Delonix regia ( Gulmohur) Tree Sensitive 14.38 Seeds /stem
cutting
Euphorbia tirucalli Shrib T NA Cuttings
Hibiscus rosa-sinensis Small
tree
T 23.32 stem cutting
Ixora arborea Small
tree
T 17.3 stem cutting
Ixora rosea Small
tree
T 20.30 Stem cutting
Lawsonia inermis (Mendi) Shrub T 17.0 Seeds /stem
cutting
Mangifera indica ( Am) Tree T 30.77 Seeds/
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.59
grafting/
budding/
Manilkara zapota (Chikoo) Tree T 25.78 Grafting
Melia azadirachta Tree T Seeds /stem
cutting
Nerium indicum Shrub T 15.7 Cutting
Peltophorum pterocarpum Tree T 16.68 Seeds
Polylathia longifolia Tree T 22.27 Seeds
Sesbania sesban ( Shrub T 19.2 Seeds
Tamarindus indica Tree T 18.4 Seeds
Tectona grandis Tree T 23.48 Seeds
Terminalia alata Tree T NA Seeds /stem
cutting
Thespesia populnea Tree T 29.81 Seeds /stem
cutting
Thevetia peruviana Shrub T 27.8 Seeds /stem
cutting
Zizyphus mauritiana (Bordi) Tree T 12.4 Seeds /stem
cutting
T: Tolerant, NA =Not available
Highlighted species are most suitable for this locality, considering its terrain
and other existing vegetative cover in the study area
Sources: CPCB (March 2000) PROBES/75/1999-2000
3.7.17 Impact on flora and fauna in the region due to the project activity
Impact on flora and fauna in the region due to the project activities was
analyzed based on the following criteria
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.60
Criteria Significance Degree of impact envisaged and
management plan
Wild life
importance
No wild life was observed in
project site and immediate
surroundings. The wild life
observed in the buffer zone is far
away from the impact zone of
project activity. Any impact due
to the project activity on the wild
life in the study area will be
minimum and insignificant.
The major construction activities
from which air emission may
occur are; site preparation,
excavation, loading and unloading
of material, movement of
construction vehicles. To
minimize the air pollution during
the construction stage; Water will
be sprayed on road for dust
suppression.
During operation phase The
primary emissions shall be from
the Boilers of the Power Plant. The
industry will install Electrostatic
precipitators for reducing the dust
emission from different sources.
The flue gases will be discharged
through the stacks of adequate
height.
Full-proof air pollution control
system will be installed at
appropriate points of discharge.
Due care will be taken for the
concentrations remaining within
the prescribed norms.
The Turbine generator will
generate high noise. Noise from
TG will be controlled by providing
an acoustic enclosure or by
treating the room acoustically.
Dry pneumatic system is proposed
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.61
for handling of Ash. Steel Silo will
be constructed to store the ash.
Water will be regularly sprinkled
in the ash dykes and the approach
roads. Wall of adequate
height shall be constructed
to control the ash from dispersing
into Ambient air.
Floral diversity
and endemicity
From the data generated for the
floral diversity of this region, it is
clear that no rare and endemic
floral diversity existing in this
region.
No impact.
Faunal
endemicity
No endemic fauna was sighted No impact
State of
terrestrial
vegetation
Not much impact is envisaged on
the terrestrial vegetation due to the
proposed project.
No impact
Legal status
(National park,
Wild life
sanctuary,
Reserve forest)
No protected area within the study
area
No impact
3.8 WATER ENVIRONMENT
District Kutch, is facing water scarcity; in each village people have
constructed ponds to store the monsoon water. These impoundments provide
important sources of water for villages for their daily activity like bathing,
washing the cloth etc. Ground water sources are being used in some of the
villages for drinking and agricultural activities. A number of thick water
bearing sandstone occurs in Bhuj series at depths ranging from 10 –200 m
below the land surface. Ground water is available at depths of more than 15 m.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.62
Most of the rivers in Kutch district are non-perennial; water is available only
during monsoon. All the rivers and streams start from its central portion and
flow towards the sea in the south or Great Rann in north and Little Rann in
southeast.
3.8.1 Methodology for Water Quality Monitoring
To evaluate the physico-chemical characteristics of the water resources
existing in the study area, water samples from ground water source were
collected during the month of May-10 and analyzed for physico-chemical
parameters. Water samples from 06 ground water sources were characterized.
These sampling stations have been shown in table no 3.31.
Samples from ground water sources were collected by adopting grab sampling
method. The sample was filled into a sampling bottle. The physico-chemical
quality of water samples were characterized by adopting the relevant parts of
IS: 3025, “Standard Methods for Water Analysis” and the instruments used are
mentioned in Table 3.32 The details analytical result presented in Table No.
3.31
Table 3.31
Location of Water Samples
Station No. Name of location Distance from site(kms)
W1 Bharapar 0.37
W2 Shinai 5.32
W3 Kidana 2.83
W4 Tuna 2.95
W5 Mathak 7.52
W6 Adipur 7.23
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.63
3.8.2 DETAILS OF ANALYSIS METHOD AND INSTRUMENT USE D
Table 3.32
Analysis method and instrument used for water testing
NAME OF
PARAMETER
APPLICABLE STD
METHOD FOR
ANALYSIS
DETECTION
LIMIT
INSTRUMENT
DETAIL
Color appearance- pt-
co scale
Visual comparison
method
IS 3025(Part 4)-1983
1 Hazen Unit Color comparator
Turbidity NTU IS-3025(part 10)-
1984
0 NTU Turbidity meter
pH Electrometric Method
IS 3025(part 11)-1983
0.01 Name: pH meter
Total dissolved solids
mg/l
Gravemetric method
IS3025 (part 16)-1984
4 Hot air oven,
weighing balance
Total Alkanity as
CaC03 mg/l
Indicator method
IS-3025 (part 23)
1986
5 ---
Chlroide Cl- mg/l Argentometric
titration IS-
3025(part 32)-1988
1
Sulfate as SO4, mg/l Turbidity method IS-
3025(part24)-1986
2 Name: UV-vis
Spectrophotometer
Total Hardness as
CaCO3,
mg/l
EDTA-titrametric
method
2 ----
Suspended Solid, mg/l Gravimetric method
IS-
3025(part 17)-1984
4 Name: oven,
balance
DO, mg/l Iodometric method-
azide
modification. IS-
0.1
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.64
3025(part
38):1989
Total Kjeldhal
Nitrogen,
mg/l
Macro and semi
macro Kjeldahl
mehod
0.05
Total Ammonium
Nitrogen,
mg/l
Titrimetric method 0.05
Total Phosphate as
PO4,
mg/l
Stannous chloride
method
0.02 Name: UV-vis
spectrophotomete
Oil & Grease, mg/l Partition gravimetric
method
IS-3025(part 39)-
1991
1 Name: Oven,
weighing
balance
3.8.3 Physico-Chemical Characteristics
Parameters for analysis of water quality were selected based on the utility of
the particular source of water. Water samples were collected as grab water
sample in a 5-litre plastic jerry can and 250 ml sterilized clean glass/pet bottle
for complete physio-chemical tests.
The samples were analyzed as per standard procedure/method given in IS:
3025 (Revised Part) and Standard Method for Examination of Water and
Wastewater Edition 20, published jointly by APHA, AWWA and WPCF. The
groundwater quality analysis results are presented in Table 3.33
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.65
Table 3.33
Physcio Chemical Characteristic
Parameter W1 W2 W3 W4 W5 W6
Colour appearance-
pt-co scale
Colourless Colourless Colourless Colourless Colourless Colourless
Turbidity NTU Nil Nil Nil NIL NIL Nil
pH 7.20 8.1 7.5 7.5 7.9 7.6
Total dissolved solids
mg/l
3200 7400 1250 1160 1359 1360
Total Alkanity as
CaC03 mg/l
1200 2400 375 325 450 448
Chlroide Cl- mg/l 1450 2450 350 325 425 465
Sulfate as SO4, mg/l 310 630 95 92 140 147
Total Hardness as
CaCO3,
Mg/l
2400 5600 960 900 1050 1045
Suspended Solid, mg/l 45 55 35 30 32 36
DO, mg/l 5.5 6.1 6.2 5.3 5.8 5.9
Total Kjeldhal
Nitrogen,
Mg/l
0.35 0.40 0.50 0.40 0.50 0.48
Total Phosphate as
PO4,
Mg/l
NIL NIL NIL NIL NIL NIL
Oil & Grease, mg/l NIL NIL NIL NIL NIL NIL
3.8.4 CONCLUSION
• Hardness varies from 900-5600 mg/l.
• Total dissolved solid varies from 1160-7400 mg/l.
• pH varies from 7.2 to 8.1
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.66
ONSITE WELL WATER SAMPLEING AT VILLAGE SAINAI
3.9 NOISE ENVIRONMENT
The basic steps associated with impact assessment on the noise components of
the environment involve identification, prediction and evaluation of the
present exposure status of the workers (occupational) as well as general
population including sensitive receptors viz. School, hospital, post offices,
phone etc.
3.9.1 METHODOLOGY FOR NOISE MONITORING
Noise level standards have been designated for different type of land use, i.e.
residential, commercial, industrial area and silence zones, as per (The Principal
Rules were published by The Noise Pollution (Regulation And Control) Rules 2000
in the Gazette of India, vide S.O. 123(E), dated 14.2.2000 and subsequently
amended by the Noise Pollution (Regulation and Control) Amendment Rules,
2000 vide S.O. 1046(E), dated 22.11.2000, Noise Pollution (Regulation and
Control) Amendment Rules, 2002 vide S.O. 1088(E), dated 11.10.2002 and Noise
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.67
Pollution (Regulation and Control) Amendment Rules, 2006 vide S.O. 1569 (E),
dated 19.09.2006 under the Environment (Protection) Act, 1986)
The community noise sources including traffic and other activities were also
monitored to determine the general noise pollution status. While selecting the
Ambient Noise Monitoring Locations, the due consideration was given to
nature of the receptor i.e., commercial, residential, and sensitive as well as the
other landscape features of entire 10.0 km radius area from proposed project.
Table 3.34
Noise monitoring location
Station
No.
Name of location Distance from site(kms)
N1 Bharapar 0.37
N2 Shinai 5.32
N3 Kidana 2.83
N4 Tuna 2.95
N5 Mathak 7.52
N6 Adipur 7.23
3.9.2 NOISE LEVEL
The noise levels were observed in the study area for night and day basis. The
noise level is well within the stipulated norms specified by the statutory
authority. The summary of computed noise level for all the sampling locations
are presented in table 3.35
Table 3.35
Noise Level
Station Code Day time
Db(A)
Night time
Db(A)
N1 44.4 42.4
N2 45.6 43.4
N3 44.3 39.1
N4 43.2 41.2
N5 48.2 44.3
N6 54.1 44
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |3.68
3.9.3 CONCLUSION
As from the above table we can conclude that the existing noise levels in the
study area were well within the prescribed norms of CPCB.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.1
CHAPTER 4
ANTICIPATED ENVIRONMENTAL
IMPACTS & MITIGATION MEASURES
Prediction of impacts is the most important step of environmental impact assessment.
Superimposition of predicted impacts over baseline environmental scenario gives the
ultimate environmental scenario. In the present study, baseline environmental
scenario was established through environmental monitoring data for the period of
March-2010 to –May-2010.
4.1 IMPACTS & MEASURES
As a first step, the entire process has been divided into a number of smaller
sub activities for construction and operation phases. The probable impacts of
each of these activities on various sectors of environment (such as air, water,
noise, socio-economic environment etc.) have been identified and listed.
The lists various activities of construction phase and their probable impacts on
various sectors of environment. The impacts are classified as long term
impacts and short term impacts.
The impacts are envisaged to be short term impacts, confined to construction
period only (10 months). Further, the magnitude of the impacts is envisaged to
be low, as the site and infrastructural facilities are fully developed. Mitigation
measures for significant impacts are discussed in respective sections.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.2
TABLE: 4.1
Identification of Construction Activities and Probable Impacts
Construction Activities Sector Probable Impact
(A)Long Term Impact
Land Acquisition Socio–Economics • No displacement
Per capita Income Socio-Economics Local Labors will get extra source of income
Infrastructure
Development
Socio-Economics Basic infrastructure like road, hospital,
schools will be developed.
(B) Short Term Impact
Site clearing and
Leveling (cutting,
stripping, excavation, earth
movement,
compaction)
Air • Fugitive Emission
• Noise/ Air Emissions from
construction equipment & machinery
Water • Run-off from surface area
Ecology • Topographic Transformations
Transportation
and Storage of
Construction
Material/ Equipment
Air • Noise and Air Emissions from
Vehicles
• Fugitive Dust Emissions due to
Traffic Movement
• Spillage and fugitive emissions of
construction materials
Water • Spillage/ spread of debris material and
flow into streams
• Run-off from Disposal Areas
Soil • Spillage/ spread/ deposition of debris
• Conversion of land into waste land
Public Utilities • Increased flow of traffic
• Congestion on roads
Civil Construction
Activities
Air • Noise and Air Emissions from Construction Machinery
• Fugitive Dust Emissions due to Movement of Traffic
Water • Run-off from Construction Areas
containing Construction Material
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.3
Mechanical & Electronic
Erection Activities
Air • Noise & Air Emissions from
Machines/ activities
Water • Run-off from Erection Areas
containing Oils, Paints
Transportation & Disposal
of Construction Debris
Air • Noise and Air Emissions from
Transport Vehicles
• Fugitive Dust Emissions due to
Movement of Traffic
• Spillage and fugitive emissions of
debris materials
Water • Spillage/ spread of debris material and
flow into streams
• Run-off from Disposal Areas
Soil • Spillage/ spread/ deposition of debris
• Conversion of land into waste land
Below Table lists various activities of operation and maintenance phase and their
probable impacts on various sectors of environment. Most of these impacts are long
term impacts. However, the significance of most of these impacts is envisaged to be
low, as discussed in the following sections.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.4
TABLE: 4.2
Identification of Operation and Maintenance
Activities and Probable Impacts
Operation & Maintenance
Activities Sector Probable Impacts
1. Transportation of
Raw material
Air
• Noise and Air Emissions from
Vehicles
• Fugitive Dust Emissions due to
Traffic Movement
• Fugitive Dust Emission due to
coal, fly ash transportation.
• Spillage and fugitive emissions
of oil
Public
Utilities
• Increased flow of traffic
• Congestion on roads
2. Industrial Use of water Water Generation of Industrial Effluents
3. Domestic Use of Water Water Generation of sanitary effluents
4. Process Air Flue gas emission from boilers
Noise Noise from Boilers and its auxiliaries
5. Storage of Fly ash in
company premises
Soil Spill of material
Air Fugitive Emission
6. Coal Handling Air Fugitive Emission
Soil Spill of material
4.2 MITIGATION MEASURES DURING CONSTRUCTION PHASE 4.2.1 AIR ENVIRONMENT
The major construction activities from which air emission may occur are; site
preparation, excavation, loading and unloading of material, movement of
construction vehicles etc.
To minimize the air pollution during the construction stage; following
mitigation
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.5
Measures are proposed:
• Water will be sprayed on road for dust suppression.
• The sand and other such dispersible material will be stored at site for
Minimum working period.
• Tarpaulin or jute covering will be used wherever required to catch the dust
spreading into atmosphere.
• The equipment design shall be chosen for least suspension of dust/sand into
atmosphere.
These impacts on air environment will be negligible; short-term and localized.
4.2.2 NOISE ENVIRONMENT
The noise generated from construction machinery shall be kept low by
keeping the moving parts serviced and properly lubricated. Working hours
will be restricted.
The noise impacts will be local limited to the premises and short-term.
4.2.3 WATER ENVIRONMENT
The construction activities will be associated with mechanical fabrication,
assembly and erection. These activities do not consume large quantities of
water. Make-shift sanitation facility shall be provided by contractors for
disposal of sanitary sewage generated by the work force. There shall be no
disposal of construction waste outside the plant. The contractors will provide
cooking fuel to the workforce this will check cutting & felling of already
scanty shrubs, trees available in the nearby areas. The overall impact on water
environment during construction phase due to the proposed power plant is
considered as short term and not insignificant.
4.2.4 LAND ENVIRONMENT
Proposed construction of plant will take place in the 56340 sq. Mtr and area
has been identified for the same. The construction of the proposed plant will
disrupt the land and soil strata, but the disruption is for positive causes on the
industrial land and the impact will be permanent.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.6
The impacts on soil due to land disposal of solid wastes such as construction
rubble, campsite garbage and discarded topsoil may impact soil quality. No
quarry material will be required as the land is a gentle slope and mostly even
and will not involve major cutting and filling. During the site preparation
work, the excess soil generated will be utilized to level the areas with lower
gradient. The amount of cutting and filing is well balanced. The current
topography and usage of the area will be used as a basis for the development
of a reinstatement plan that will be implemented.
4.2.5 BIOLOGICAL ENVIRONMENT
There is no tree cover in the project site, The construction work will include
the activities like vegetation clearance, cutting, filling and leveling. All
construction material will be sourced from authorized mines by contractors.
Thus, no significant impact on ecological environment during the construction
phase is envisaged.
4.2.6 IMPACT ON HEALTH & SAFETY
Interaction of local labour with outside labour force during the construction
may lead to transference of communicable diseases if left uncontrolled and
unchecked. Also adequate facilities for the health of construction workers will
be provided at the campsite.
4.2.7 RISK & SAFETY
The movement of heavy earthmovers, excavators, transporting vehicles during
the construction phase may increase the risk of accidents and injuries. A road
safety awareness campaign will be undertaken to better inform the
communities about safer road habits. Also adequate safety facilities for
construction workers will be provided.
4.2.8 SOCIO-ECONOMIC ENVIRONMENT
During the construction phase, there shall be major positive impacts on the
socioeconomic environment of the region in the form of employment as direct
impact. The indirect impacts shall be brought about by way of establishment
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.7
of related service activities like petty commercial establishment, ancillary
establishment.
4.3 MITIGATION MEASURES DURING OPERATION &
MAINTENANCE
4.3.1 AIR ENVIRONMENT
Fugitive Emission
The fugitive dust emissions during operation & maintenance phase from the
proposed coal handling system would be significant and the sources will be as
under:
• Coal Crusher
• Stock House
• loading/Unloading of coal
• Transportation of coal through vehicles
• Transfer of product through belt conveyor
Mitigation Measures
• The company will do regular maintenance of the bag filters and ESP.
• High efficiency bag filters will be used to reduce the dust emission from
transverse points.
• Transportation of coal and fly ash will be done in closed trucks only.
• Storage of fly ash will be done in closed silo.
Process Emission
Main source of Process emission is boilers. Adequate and efficient measures
shall be provided to keep the dust emission at a bare minimum level. Efficient
Collection of dust at sources, their de-dusting with efficient filters and
recycling the dust to process is the prime objective. Primary dust source shall
be the coal crusher house, screen house, fly ash storage/handling in Power
plant.
The particulars of most specific individual sources and their pollution control
measures are as follows:
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.8
Mitigation Measures
• The vent is attached to the bag filters of adequate height to disperse the air
pollutants to the satisfactory levels.
The vent will be regularly monitored for PM.
• Bag filters will be cleaned regularly.
• Stack height of boilers will be kept more than design height calculation.
STACK HEIGHT CALCULATION
Sr. no. Parameter Unit
1. Fuel Fired (All the three boilers) 38967 Kg/hr
2. % Sulfur in Fuel 1%
3 Sulfur flow 389.67 Kg/hr
4 SO2 flow(Qs) 779.34 Kg/hr
4 Chimney Height(m) calculation 14 x (Qs) ^ 0.3
5 Chimney Height (m) 103.19 m
• As per calculation stack height is 103.19 m. The company will provide
stack height of 105 m.
• It is proposed to install high efficiency electrostatic precipitators to limit
the outlet emission to 50 mg/Nm³ while the boiler is operating at its MCR,
firing worst coal having maximum ash content. The electrostatic
precipitators will have four (4) parallel gas streams, isolated from each
other on electrical as well as gas side. Gas tight dampers will be provided
at inlets and outlets of each stream so as to allow maintenance to be carried
out safely on the faulty stream, while the unit is working.
• Electrostatic precipitators will be provided with microprocessor based
programmable type rapper control system and ESP management system to
ensure the safe and optimum operation. Opacity meters shall be provided
at the ESP outlet for performance optimization and for remote indication.
ESP Transformer rectifier sets will use silicon oil as the cooling medium.
The dust collection hoppers below ESP will have a minimum storage
capacity of eight (8) hours while firing worst coal. The hoppers will have
heating arrangements to prevent ash sticking to the sloping sides and down
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.9
pipes. Level indicators to indicate and trip the ESP in case of high ash
levels in the ash hoppers while will jeopardize the safety
4.3.2 NOISE ENVIRONEMNT
The upcoming projects will not result in any significant impact on noise
environment. The minor increase in vehicular transportation due to increase
material handling will not generate any significant excessive noise. Hence,
there shall not be any significant negative impact on noise environment of the
study area.
Mitigation Measures
• Ear muffs shall be provided to the concerned personnel during the
operation stage.
• Equipment design shall be kept to keep the noise below prescribed norms
• Enclosures shall be provided to moving parts
• Periodical lubrication is carried out
4.3.3 WATER ENVIRONMENT
Water is essential for human, agriculture, industry and commercial use. The
industrial activity shall have direct impact on the end users. The water
environment broadly covers the following points for consideration of impact.
a. Industrial operations, their effect on water quality and ground water potential
of study area.
b. Identifying potential sources of pollutants focusing specifically on discharge
of the wastewater.
Mitigation Measures
• The company will not use ground water for proposed project. The
company will set up its own desalination plant with capacity of 5000 KLD
sweet water.
• The main source of wastewater from proposed project will be from blow
down and backwash from RO and DM plant.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.10
• The major constituents in wastewater generated as Boiler blow down and
from cooling tower, are total dissolved solids (TDS) and that to be utilized
for dust suppression in raw material storage yard and sprinkling on the
road. Rejects from RO and filtration plant will be utilized either for
sprinkling or green belt development depending on characteristic of reject
water.
• The wastewater from the domestic activities shall be disposed off through
soak pit/Septic tank.
4.3.4 LAND POLLUTION BY HANDLING OF HAZARDOUS/SOLID
WASTE
The types of Solid wastes generated will be Bed Ash, Fly Ash, Coal Char and
Used / Spent oil. Management system for all such types of wastes is discussed
in this section.
a. Fly ash:
Ash which is generated at the various collection points shall be further
transferred into pneumatic ash conveying system. The ash shall be cooled
using air cooler so that it can be pneumatically conveyed. Fly ash which
escapes along with flue gases shall be collected using an electrostatic
precipitator shall be further conveyed to ash silo using pneumatic conveying
system. Fly ash thus collected in ash silo will be utilized in different activities.
These activities include cement plants; Brick Kilns; Construction activities.
Storage Capacity For fly ash
� Bed ash silo – 1x30cum capacity common for both boilers
� Fly ash silo – 1x400cum capacity common for both boilers
b. Used/spent Oil:
Negligible quantity of used oil shall be generated; which will be disposing off
to through registered recyclers.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |4.11
c. Coal Char:
Coal char will be used up as fuel along with coal in Captive power plant.
4.3.5 SOCIO-ECONOMIC ENVIRONMENT
There will be positive impact on the economic environment, Aesthetic
environment, character of community, employment centers and Commercial
facilities, community facilities and services. With commissioning of this
project, there shall be increase in employment generation. Along with the
direct employment in the industry; there shall also be indirect employment
opportunities; as the upcoming industrial activity may require many ancillary
products/services which are to be captured from the nearby available sources.
Further more, company is committed to do various social activities under
corporate social responsibility.
4.3.6 BIO-ECOLOGICAL ENVIRONMENT
A greenbelt development plan has been recommended. The company will
developed extensive greening of the area in the industrial premises using novel
technological agricultural methods/techniques using the recycled water. Base
on this experience, a further extensive high-density plantation is proposed to
be developed.
Dimension of green belt area is as under:
• Area proposed to be afforested : 55000 sq mtr
The impact shall be positive as the greenbelt will be developed on a barren
land in and around various units within the proposed site.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.1
CHAPTER 5
ENVIRONMENT MANAGEMENT PLAN From construction and operation activities of the process, environmental impact has
been identified, predicated an d evaluated to mitigate the standards specified by the
statutory authority and minimize the impact on eco system Environmental
Management Plan (EMP). Environmental Management Plan provided control
measures of potential environmental impacts. Environmental Management System for
different environmental
Types of Impact Mitigation Measures
5.1 AIR ENVIRONMENT
A) Construction Phase
a. Excavation
a) Excavation:
During excavation, care shall be taken that the
excavator shall not release the sand from higher
elevation. The piling of sand shall be done
uniformly and proper storage shall be maintained
to avoid dusting because of wind. If required
temporary windshield barrier shall be provided
with help of galvanized sheets and bamboos.
Water Sprinkling shall be done continuously on
the site and periodically on the roads where
vehicle movement is more.
b. Mechanical Erection
b) Mechanical erection:
Fume generation shall be there due to welding
and allied activities; this impact will be
negligible and restricted to project Site. The
workers would be trained to use welding shields
and use safer practices.
c. Vehicle Movement
c) Vehicular Movement:
The proper maintenance of construction
machines shall be ensured and the engine oils
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.2
and filter shall be replaced regularly. When the
machinery is not in use the engine shall be
switched off. All vehicles shall be properly
maintained and should have valid PUC
registration. This has to be checked periodically.
B) Operation Phase Flue Gas
Emission
a. Power plant Flue Gas Emissions from CPP
Adequate stack height as per GPCB norms is
proposed to emit the gases. Electrostatic
Precipitator (ESP) to be installed with boiler.
b. Crusher House Crusher House
Crusher house shall be equipped with bag house
to control particulate matter.
c. Fumes in Ash Storage Fumes in Ash Storage
Dry pneumatic system is proposed for handling
of Ash. Steel Silo is constructed to store the ash.
Water will be regularly sprinkled in the ash
dykes and the approach roads. Wall of adequate
height shall be constructed to control the ash
from dispersing into Ambient air.
d. Raw material & Fuel
Handling
Unloading of coal by truck or wagons shall be
carried out with proper care avoiding dropping
of the materials from height.
• Water sprinklers at the raw material
transfer for dust suppression at belt
conveyor discharge / transfer point
Crusher / screen discharge locations
• Tarpaulin sheet will be covered on the
material during the transportation.
• Cover Belt conveyor system is proposed
for internal transportation.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.3
v) Fugitive Emission
The Bag-house/dust collector will be installed at
appropriate transfer points like Raw material
handling area, Fuel storage area, Crusher house,
Screening plant, Stock bin area to minimize the
Fugitive emission.
Centralized de-dusting unit shall be provided to
control the fugitive Particulate matter
5.2 WATER ENVIRONMENT
A) Construction Phase
i) Sewage Waste Water i) Sewage wastewater:
It is the main pollution parameter during this
phase. Sewage wastewater shall be disposed
through soak pit and septic tank arrangement
B) Operation Phase
i) Industrial Waste water Industrial Wastewater:
During the operations phase the main source of
water pollution is from the blow-downs of Boiler
and reject streams of DM and RO Plants. Part of
this wastewater will be utilized for sprinkling
within premises for dust suppression after
treatment in ETP.
ii) Sewage Sewage wastewater:
Sewage wastewater generated shall be disposed
off through soak pit and septic tank arrangement.
5.3 NOISE ENVIRONMENT
A) Construction Phase During the construction phase the noise levels are expected to rise due to movement of vehicles, equipments and heavy machinery. The mitigation measures will include maintenance of the vehicles and heavy machinery and provision of personal protective equipment to the workers working in high noise level. This impact is supposed to be temporary and restricted within premises.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.4
B) Operation Phase The Turbine generator will generate high noise.
Noise from TG will be controlled by providing
an acoustic enclosure or by treating the room
acoustically. A proper routine and preventive
maintenance procedure for the boilers will be set
and followed.
Personal protective equipment like earplugs and
earmuffs shall be provided.
5.4 SOLID WASTE
A) Construction Phase i) During construction phase major solid
waste generated is construction and
domestic solid waste. The construction
waste will be utilized for leveling and
road construction in plant premises.
Generated domestic waste will be sent to
nearest municipal solid waste landfill
sites.
ii) The used welding rods will be disposed
off through registered metal recyclers.
iii) Used oil generated from construction
machinery will be collected, stored
separately and sold to authorized
recyclers.
B) Operation phase i) Fly ash: During operation phase major
solid waste generated is fly ash. Action
Plan is prepared as per the guidelines of
statutory authorities; which will be
strictly followed. Fly Ash will be utilized
in Paved Block / Brick Manufacturing
Plant.
ii) Used oil: Very small quantity of used oil
shall be generated from the plant. This
shall be sent to approved recycler.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.5
5.5 FLY ASH MANAGEMENT PLAN
Management system for ash is discussed in this section. The ash generated
will be handled as follows:
ASH HANDLING SYSTEM
The ash handling system envisages wet extraction and disposal of bottom ash
& wet extraction for fly ash. The fly ash shall be extracted in dry form from
the electrostatic precipitator hoppers and transported to storage silo as a
measure for promoting fly ash utilization.
Wet bottom ash handling system
The bottom headers of the pulverized fuel fired boiler will be at 4m above
ground level to facilitate incorporation of the wet bottom ash handling system.
The system shall include water immersed chain conveyor, clinker grinder and
suitable conveying system up to bottom ash silo. Ash in silo will be unloaded
to trucks for further disposal.
Fly Ash Handling
Fly ash resulting from the combustion of coal in the boiler gets collected in
economizer hopper, air heater hopper, ESP hoppers etc. The ash shall be
evacuated to fly ash silo through dense phase system. From fly ash silo, ash
can be transported through trucks. Fly ash silo will have provision for 3 days
storage. Necessary fluidizing arrangements, downward unloading chute, ash
conditioning arrangements shall be provided in ash silo.
TABLE 5.5
The estimated quality of the proposed ash generation is as follows:
Sr.no. Parameter %
1. Silica 13.5- 15.5 %
2. Ferric Oxide 12.4- 14.7%
3 Calcium Oxide 21.8-22.7%
4. Magnesium Oxide 4.02-4.34%
5 Alumina 17.3-20.2%
6 Alkalies(NA20) 4.9-5.04%
7 Alkalies( K20) 0.29-0.39%
8 S03 18.3- 20.1%
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.6
5.5.1 ACTION PLAN FOR FLY ASH DISPOSAL
• Proper disposal of fly ash is one of the most pressing environmental issues of
the power sector.
• Fly ash shall be disposed and utilized as per the guidelines issued by the
Ministry of Environment & Forest. Based on these guidelines and looking to
the quantity of the fly ash likely to be generated from the proposed project, the
Brick manufacturing plant is proposed to install.
• The results indicated that the fly ash generated is a viable raw material for
brick production at the nearby brick plant/captive brick manufacturing plant.
The amount of fly ash that can be consumed will depend on the brick plant’s
production rate and the amount of ash that can be successfully incorporated
into the brick body.
5.6 RAIN WATER HARVESTING SCHEME
As per Indian meteorological dept (IMD) data, the area experiences very low
rainfall. The water holding capacity of the soil is very less in the region. The
depth of ground water table in the region is about 10 to 15 m below ground
level. Therefore, recharging of the ground water will not be possible.
However, in the project rainwater harvesting structure will be constructed
along the storm water drains. These drains will collect the surface run-off
water and roof top water during rainy days. There will be generation of surface
run-off from the proposed plant facility during monsoon season. The run- off
will be of two types i.e. runoff from the previous area of the facility site and
run off from the built-up area of the complex.
• Run-off from the Built-up Areas
The run –off from the paved surfaces of proposed plant will be routed through
a carefully design storm water drainage network and collected in storm water
collection sump.
• Run-Off from the previous area
The run-off from the pervious area will be routed directly to the rainwater
harvesting structures constructed at suitable locations as per the contours. For
augmenting the ground water resources in the proposed plant, number of
rainwater harvesting pits will be constructed and the internal drains where
excess rainwater flowing in drain will be diverted to these pits. These
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.7
structures will facilitate percolation of water in to the ground and thus
augmenting the ground water sources. The roof top water will be routed to the
storm drains. This will result in increase in ground water tables and to some
extent the improvement of ground water quality. The size and the location of
rainwater harvesting pits will be decided during detailed engineering of
project.
5.7 SOCIO ECONOMIC DEVELOPMENT
Programs for environmental education and public participation may be
developed with the help of audio visual aids to create awareness about the
activities. Camps to apprise people of likely environmental hazards due to
existing and proposed faculties could be organized. Certain welfare measures
will be implemented for the benefit of local population. The operation of the
plant will generate direct/indirect employment for local population. Company
is committed to contribute funds for Socio-economic Development.
5.8 GREEN BELT DEVELOPMENT
Total Power plant area: 56340 sq. m
Green Belt to be Developed: 55000 sq. m
Type of Species:
• Jatropha curcas (Ratanjot)
• Peltophorum pterocarpum (Sonmukhi)
• Albizia lebbeck (siris)
• Ficus benghalensis (Vad)
• Salvadora persica (Piludo)
Green belt will be developed around the periphery of the proposed project; this
will help in reducing adverse effect of pollution in general. 400 trees per Acre
will be planted for the proposed project.
Budgetary allocation along with year wise development plan is shown below:
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.8
Table 5.8:- Budgetary allocation along with year wise development plant
Year Area Nos of trees Budget in Rs.
2011 12000 9000 9 Lacs
2012 18500 11000 12.5 Lacs
2013 24500 12000 15 Lacs
Total 55000 32000 36.5 lacs
5.9 ENVIRONMENT MANAGEMENT CELL
A separate Environment Management Cell will be earmarked for monitoring
of pollutants and development of greenbelt as per Environmental Management
Plan. Environmental Management Cell (EMC) will meet at least once a month
to assess the progress and analyze the data collected for the month. Any
deviation/variation noticed shall be immediately taken into consideration for
improvement of the same. Yearly action plan of EMP will be updated with
respect to results achieved and proposed activities for next year.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.9
ORGANOGRAM FOR PROPOSED ENVIRONMENT MANAGEMENT CELL
Lab-in Charge
Dy. Env. Mgr.
Manager-HSE
General Manager Works
Director
Lab Chemist
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.10
5.10 ENVIRONMENTAL MONITORING DURING OPERATION PHA SE
Regular monitoring of important parameters is of immense importance to
assess the status of environment during plant operation. With the knowledge
of baseline conditions, a properly planned monitoring program can serve as an
indicator for assessment of any deterioration in environmental conditions. This
will facilitate undertaking suitable measures to mitigate adverse impacts
during the operation of the plant and further help to protect the environment in
the area. The main attributes for which monitoring shall be carried out are:
1. Ambient air Quality
2. Stack Emission
3. Wastewater Quality
4. Noise Level
5. Hazardous Waste
5.10.1. Ambient Air Monitoring
Air quality monitoring for Sulfur Dioxide, Nitrogen Dioxide and Particulate
Matter (PM2.5, PM10) will be carried within plant & outside the plant
boundary.
5.10.2. Stack Monitoring
Stack emissions from boiler shall be monitored as per the given guidelines for
Suspended Particulate Matter, Sulphur Oxide and Nitrogen Oxides.
5.10.3. Water Quality Monitoring
The quality of the treated effluents shall be monitories as per the mentioned
parameters like pH, Temperature, Color, Oil & Grease, Suspended Solids,
Ammonical Nitrogen, Total Residual Chloride, Nickel, Hexavalent
Chromium, Total Chromium, and Total Metal content.
5.10.4. Noise Monitoring
Noise Monitoring will be carried our inside the plant, within the factory
premises and outside the premises as per the frequency and duration suggested
by the CPCB.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.11
TABLE 5.10
ENVIRONMENTAL MANAGEMENT PLAN
Sr. No. Activities Schedule
Meteorological Data
1 Wind velocity, Wind Direction,
Temperature, Relative Humidity
Daily or as required by statutory
Authority
Air pollution Monitoring
2 Stack Monitoring of flue gas
Stack
Once a month or as specified by
Gujarat Pollution Control Board
3 Ambient Air Quality within
Premises at 3 locations in upwind
and 3 location in downwind
direction.
Once every fortnight or as specified by
Gujarat Pollution Control Board
4 Ambient Air Monitoring at
locations outside premises at
Five locations 120o to each other
Once every Season or as specified by
Gujarat Pollution Control Board
Water Quality
5 Raw water Quality Once in Month
6 ETP outlet Once in Month
7 Cooling tower & boiler blow
down
Daily or as required by statutory
authority
Noise Monitoring
8 Work Zone Noise level Once every Quarter or as required by
statutory Authority
9 Ambient Noise Level Once in Month
Occupational Health
10 Employees Health Check up Once in Year
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |5.12
5.10.5 DO’s & DON’TS
Checklist in the form of DO’s and DO’NTS of preventive maintenance,
strengthening of HSE, Manufacturing utility staff for safety related measures
DO’s
• Always follow Safe work permit procedure.
• Always wear following mandatory PPE’s before entering the plant
• Ear plug/Ear muff
• Helmet
• Safety Shoes
• Hand Gloves
• Safety Goggles
• Cotton Cloths/suit
• Always follow Standard Maintenance Procedure(SMP) for maintenance of any
machinery
• In case of Chemical splash/Burn injury use Safety shower of nearby area.
• Report all the incident/accident/Nearmiss to top management
• Always follow the recommendation of incident/accident/Nearmiss
• Always use Assembly points for gathering during emergency.
• Always report unsafe condition/activities to seniors.
• Actively participant in Mock drill
• Do medical check up regularly
DON’TS
• Do not enter in plant without personal protective equipments
• Do not work without permit
• Do not use your own judgment/procedure for maintenance of equipment
• Do not open any container of chemicals which MSDS is not known
• Do not hide any accident/Incident/Nearmiss
• Do not take short cut always
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.1
CHAPTER 6 RISK ASSESSMENT
INDEX
Sr. No. Chapter Page No.
6.1 EXECUTIVE SUMMARY 6.2 6.2 INTRODUCTION 6.3 6.3 PROCESS DESCRIPTION 6.5 6.4 RISK ANALYSIS DUE TO STORAGE / HANDLING OF
COAL 6.14
6.5 RISK ANALYSIS FOR THE BOILER 6.22 6.6 RISK ANALYSIS FOR STEAM TURBINE GENERATOR
SET 6.25
6.7 RISK ANALYSIS FOR ASH HANDLING SYSTEM 6.27 6.8 RISK ANALYSIS FOR AIR POLLUTION CONTROL
SYSTEM 6.28
6.9 PROPOSED FIRE FIGHTING SYSTEM 6.30
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.2
CHAPTER 6.1
EXECUTIVE SUMMARY
Introduction
The enclosed Report on Risk Assessment for the proposed power plant of M/s Shree
Renuka Sugar Ltd., village: Bharapar, Taluka Gandhidham, Kutch (Gujarat) is based
on the study carried out in the month of May-2010
Main findings
The main hazards of a Coal Based Power Plant are:
1. Health hazards due to handling of Coal.
2. Fire hazard due to handling of Combustible Coal
3. Electrical hazards due to generation and transmission of power.
4. Other mechanical hazards in maintenance and operation.
5. Environment hazards due to air/water/soil pollution.
The present report addresses the risks posed by all the above hazards. Quantification
of risk was not possible due to the fact that no toxic chemicals are involved and the
radiative flux hazards due to any coal fire would be restricted primarily to the factory
premises.
As explained in the following chapters, the factory proposes to take adequate control
measures to ensure that the hazards do not result into any accident scenarios. The
necessary equipment / hardware would be provided at the design stage itself.
In addition the employees would be adequately trained to combat any emergency
arising out of fire in the coal yard.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.3
CHAPTER 6.2
INTRODUCTION 6.2.1 Legal Requirements
The organization has intention to install and operate 45 MW coal based power
plant at village. Bharapar, Ta. Gandhidham, Dist. Kutch to full fill the process
steam & power requirement for sugar refinery.
The General Duties of the “Occupier” specified at Section 7-A of the
Factories Act gives different obligations of the occupier. These will be
fulfilled to a great extent as can be seen from the information provided here
under. The factory is setting up a facility to generate power using thermal
energy from Coal. The factory is thus classified as an Industry involving
Hazardous Process as per the First Schedule of the Factories Act, under
Section 2(cb) - Sr. No. 5 (Power Generating Industries). As per G. F. Rule 68
– I, related to the Approval from Site Appraisal Committee, the organization
has to give information in Form 1 – B. At section 11.2 of the format, it is
indicated that a copy of the Report on Risk Assessment Study should be
submitted. The present report would serve the purpose.
6.2.2 Basic Document
Risk Assessment ensures that all the relevant hazards are addressed, with the
aim of identifying significant risks in the workplace. In the present case, Risk
Assessment is being carried out at a very initial stage with the Detailed Project
Report document as the reference. The risks identified are indicative in nature
only. Once the facility is set-up and ready for operation, this study should be
thoroughly reviewed.
6.2.3 Scope of Work
After detailed discussions with the plant personnel, the Scope of Work was
finalized as below:
i) To carry out a detailed Risk Assessment for the proposed 45 MW
Power plant at village Bharapar, Ta. Gandhidham, Dist. Kutch. The job
would consist of :
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.4
ii) Study of the documents / drawings made available.
iii) Identification of Hazards in the plant in general and in particular in the
following operations.
Fuel
• Receipt / handling and storage of coal in the yard.
• Transfer of coal by conveyor belts.
• Storage of coal in bunkers.
• Crushing of coal to the desired size.
• Pollution control measures to control coal dust.
Feed Water
• The basic source of water is from the sea.
• Storage / treating of raw water and feeding the same to the boilers.
• Operation of RO/DM plant.
Boiler
• Operation of the boiler including feed water pumps, coal spreaders, air
pre-heaters, air blowers etc.
• Heat recovery system, including condensers.
Turbine operation and Power Generation
• Operation and maintenance of Turbine.
• Power Transmission Grid.
Ash Handling System
• Collection of ash from various generation points.
• Transferring the same in silo with pneumatic conveying.
• Disposal of Ash.
Air pollution control system
• Operation of ESPs.
• Control over quality/ quantity of Flue gases.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.5
CHAPTER 6.3
PROCESS DESCRIPTION 6.3.1 PROCESS DESRIPTION
The company will set up 45 MW (1 No of 30 MW Extraction cum condensing
TG and 1 nos of 15 MW back pressure TG set) coal based power plant at
village Bharapar, Ta. Gandhidham, Dist. Kutch, by installing two nos of 70
TPH and one number of 110 TPH boilers.
Steam Boiler
Steam is generated in the two nos of Atmospheric Fluidized Bed boiler of 70
TPH at a pressure of 86 Kg/cm2 g by using Imported coal as fuel & water
from RO plant where Raw water will be treated in the water treatment plant as
per the flow sheet enclosed. The treated water with required parameter suitable
for high pressure boiler for the generation of steam. Coal from Coal yard
conveyed to coal crusher plant to make it to size below 6mm .Crushed coal
conveyed to bunkers & from bunker feed to boiler through spreaders
uniformly on fluidized bed for combustion & subsequently generation of
steam. Flue gas generated will go through APCD that is ESP(2 Nos) & finally
escaped to air through 105 Mtr. Height common RCC chimney with clear top
diameter suitable for two number 70 TPH and one number 110 TPH Boiler
(Future) with permitted emission level upto 50 mg/nm3.
The Coal Ash approx. 1300 kg/hr will be generated during the operation of
Imported coal. The Coal Ash is highly demanding in cement factories and Ash
Brick making Industries.
The boiler completely control by DCS System for safe operation. The controls
envisaged in the boiler are three element drum level controls, Deaerator level
control, combustion control, safety valve etc.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.6
Fuel and Water Requirement
The boilers shall be used Imported coal of 21822 kg/hr as fuel for both the
boiler and raw water around 600 cu. M per day.
Steam and Condensate
For feed water to the boilers, it is proposed to use straight condensate from
exhaust steam used in process ensure good quality of feed water. The
delivery line of the pump of condensate from refinery is to be provided with
conductivity meter to ensure that feed water is not mixed up with any sugar &
other harmful chemical and in case it is mixed, the condensate is immediately
stopped automatically on getting the alarm/signal. The make-up water from
RO plant and extracted condensate from the air cooled condenser of TG set
will be sent to feed water tank / de-aerator and this will ensure almost no loss
of condensate from the condensate pit of turbine condenser.
The feed water will be pumped to de-aerator to be located near the boiler area.
One make up water storage tank and one feed water tank to be provided to
ensure that there is enough good quality water available and boiler does not
suffer due to starvation of water.
Make up water is required for shortages due to plant start up, brake down and
this will be meet through RO plant and sent to feed water system.
Raw water for cycle makeup 10 m3/hr,Raw water for cooling Tower makeup
12 m3/hr and Raw water for miscellaneous Purpose 3 m3/hr.
Grid Inter Connection for Export
Power generation for the proposed TG set is planned at 11.0 KV and
exportable power has to be stepped up to 66 KV from 11.0 KV generator
transformer to be located in switchyard within the cogeneration complex and
then to be synchronized with the grid. The grid synchronization will be done
at GETCO 66KV Substation.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.7
For operating cogen plant, a portion of power will be stepped down to 11.0
KV/415 Volts for running of sugar refinery and auxiliaries etc. For this
suitable transformers are to be installed at various convenient locations at the
cogen plant area.
6.3.2 Equipments Details 6.3.2.1 15 MW Steam Turbine
15 MW TG- Shin Nippon Machinery Co. Ltd
Type -horizontal impulse, multistage, multi axial flow, back pressure, extraction, Gear(Down exhaust type)-B6-R7-ER(model) Output 1500KW(At Generator terminal)
Operating Condition:
Speed (Turbine/Generator) : 6515/1500 RPM Inlet Steam Pressure : 84Kg/cm2 A Inlet steam Temp : 5150C Exhaust Steam Pressure : 3 Kg/cm2 A Allowable Operation Range : 2.5-3.3 Kg/cm2 A Max. Ist Extraction Pressure(Un controlled extraction) : 8.9 Kg/cm2 A Max Inlet Flow 1st extraction flow : 0 & 3.9 to 13 t/hr Max. Exhaust Steam Flow : 85. 2 t/hr at 3 kg/cm2 A
Performance Table
Operation case Full Load Zero Bleed
Full Load 8 ATA x 13 TH
Partial Load 6 ATA x 13 TH
Inlet Steam Pressure(Kg/cm2) 84 84 84
Temperature( 0C) 515 515 515 Flow(Kg/hr) 85.2 88.45 65.9 Exraction Pressure (Kg/cm2) (Un controlled extraction at turbine nozzle)
8.9 8 6
Exraction Temperature (0C) 257 245 233
Exhaust Pressure (Kg/cm2) 0 13000 13000
Exhaust Temperature (0C) 155 154 171 Gland Leakage(Kg/hr) 300 300 300 Exhaust Flow (Kg/hr) 84900 75100 52600 Generator Power(KW) 15000 15000 10500
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.8
6.3.2.2 30 MW –Steam Turbine
30 MW TG- Model C8-R11-ERX
Type -horizontal impulse, multistage, multi valve axial flow, Condensing, extraction
&Gear(Axial exhaust type) Output 3000KW
Operating Condition:
Speed (Turbine/Generator) : 5500/1500 RPM
Inlet Steam Pressure : 84Kg/cm2 A
Inlet steam Temp : 5150C
Exhaust Steam Pressure : 0.18 Kg/cm2 A
Max. 1st Extraction Pressure(Un controlled extraction) : 8.11 Kg/cm2 A
Max. 2nd Extraction Pressure(Controlled extraction) : 3 Kg/cm2 A
Inlet Flow flow : 145000kg/hr
1st extraction flow : 0 & 6500 to 21630 kg/hr
2nd extraction flow : 0 & 36300 to 120940 kg/hr
Max. Exhaust Steam : 93370 kg/hr at 0.18 kg/cm2 A
Water condition 1st Expansion : 85 ata x 105 0C
Water condition 2nd Expansion : 8 ata x 45.45 0C
Performance Table
Operation case Full Load
Zero Bleed
Full Load
8 ATA x 13 TH
Partial Load 6
ATA x 13 TH
Inlet Steam Pressure(Kg/cm2) 84 84 84
Temperature( 0C) 515 515 515
Flow(Kg/hr) 85.2 88.45 65.9
1st Exraction Pressure (Kg/cm2)
(Un controlled extraction at
turbine nozzle)
8.11 6 7.7
Exraction Temperature (0C) 238 219 235
Flow at turbine nozzle kg/hr 9650 21630 12580
Flow spray water kg/hr 350 370 420
Pressure at termination
Point(Kg/cm2 A) 8.11 6 7.7
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.9
Temperature at termination
Point(0C) 200 200 200
Flow at termination Point(kg/hr) 10000 22000 13000
2nd Exraction Pressure (Kg/cm2)
(controlled extraction ) 3 3 3
Exraction Temperature (0C) 145 - 147
Exraction Flow (kg/hr) 120940 0 99000
Flow(spray water)kg/hr 1060 0 1000
Pressure at termination Port 3 3 3
Temperature at termination Port 135 - 135
Flow at termination Port kg/hr 122000 0 100000
Exhaust Pressure (Kg/cm2) 0.18 0.18 0.18
Exhaust Temperature (0C) 63.07 57.41 57.41
Gland Leakage(Kg/hr) 100 100 100
Exhaust Flow (Kg/hr) 14310 93270 28320
Generator Power(KW) 26700 28450 26500
The scope of each TG unit shall broadly cover the turbine and its integral
systems like Control Oil system, Lube oil System, Automatic Turbine Run-up
System, HP/LP Bypass system, Condensers, Condenser Air Evacuation
system, complete Regenerative Feed Heating system, Condensate Pumps with
drives, Boiler Feed Pumps with drives, LP Chemical Dosing system, Auxiliary
Equipment cooling water system, Instrumentation and Control devices,
equipment and systems such as Turbine Supervisory Instruments, Turbine
Protection and Interlock system, Automatic Turbine Testing system &
Hydrogen Generation Plant etc.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.10
6.3.2.3 Boilers (70 TPH x 86 Kg/cm2 (A) x 520 +/-50C )
Boiler x 2
Type -AFBC ( Atmoshperic fluidised bed boiler)
Parameters : 70 TPH x 86 Kg/cm2(A) x 520 +/- 50C
Fuel : Imported Coal
Performance Table
Air Pre heater IN : 320C
Air Pre heater OUT : 1400C
Bed Temp : 900-950 0C
Superheater IN : 830-850 0C
Econimiser IN : 410-430 0C
Temperature at chimney : 140 0C
Steam Temperature : 520 0C
Steam drum : 305 0C
Super heater(I) IN : 305 0C
De-Super heater IN : 421 0C
De-Super heater OUT : 3600C
Superheater 2 out : 4360C
IBSH OUT : 5200C
Econimiser IN : 1300C
Econimiser OUT : 215-2200C
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.11
6.3.2.4 Boilers (2 x 110 TPH, 86 kg/cm2(A) x 520 +- 10)
TYPE- AFBC (Atmoshperic Fluidised bed boiler)
PARAMETER : 2 x 110 TPH, 86 kg/cm2(A) x 520 +- 10
FUEL: Imported Coal
Steam Evaporation capacity 110 TPH
Steam outlet temp. 520°C± 10
Steam Pressure at outlet 88 Kg/cm^2(A)
Type of boiler CFBC
Make of Boiler M/s Thermax,Pune
Type of fuel used Imported Coal
Efficiency of boiler 89%±2%
6.3.3 Fuel feeding system
• Make - M/s AG Engineering, Pune .
• Capacity of plant - 80 TPH
• Inlet coal size - upto 6”
• Outlet coal size - ≤ 6 mm
• Type of screen - Two stage screen
• Type of Coal crusher - Impact hammer type with dust collector system.
• Coal storage – Coal needs to be stored in proper procedure to avoid
it’s self combustion for the same purpose the coal heap height is to be
maintained as per the standard practices.
• Manual crushing – It is required for the maintain the required inlet
size of coal to crusher, for which a arrangement of gizzly hopper is
given. After maintaining the required size it is feed to coal conveying
system through the coal feeders.
• Primary coal screening – In this process the coal of required size is
get separated through screen & conveyed directly to boiler bunker, i.e.
bypassing the coal crusher & it saves the power.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.12
• Coal crushing – The rejected size coal from primary screen is taken
into the impact type coal crusher for its further preparation to upto the
size ≤ 6 mm.
• Secondary coal screen –The crushed coal from the coal crusher is
feed to secondary screen from where the accepted size coal conveyed
to boiler bunker & the oversized coal send back to primary screen inlet
conveyor through the bucket elevator,to complete the cycle.
• Coal storage at boiler bunker –After size preparation the coal is get
conveyed to bunker by coal conveyor & stored for boiler operation.
The capacity of bunker is 220MT.
• All conveying system is provided with ZSS as well as emergency pull
cord switch.
6.3.4 Ash handling system
The ash handling system envisages wet extraction and disposal of bottom ash
& dry extraction for fly ash. The fly ash shall be extracted in Wet form from
the electrostatic precipitator hoppers and transported to storage silo as a
measure for promoting fly ash utilization.
Wet bottom ash handling system
The bottom headers of the pulverized fuel fired boiler will be at 4m above
ground level to facilitate incorporation of the Wet bottom ash handling system.
The system shall include water immersed chain conveyor, clinker grinder and
suitable conveying system up to bottom ash silo. Ash in silo will be unloaded
to trucks for further disposal.
Fly Ash Handling
Fly ash resulting from the combustion of coal in the boiler gets collected in
economizer hopper, air heater hopper, ESP hoppers etc. The ash shall be
evacuated to fly ash silo through dense phase system. From fly ash silo, ash
can be transported through trucks. Fly ash silo will have provision for 30 days
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.13
storage. Necessary fluidizing arrangements, downward unloading chute, ash
conditioning arrangements shall be provided in ash silo.
6.3.5 Air Pollution Control System
The pollution norms of the Gujarat state with outlet emission restriction to
50 mg/Nm3 calls for the selection of latest ESP technology. The ESP
technology has been well developed now. The state of art ESP function is
explained in the following steps:
• The unit is going to install one ESP for two no’s of 70 TPH and one no of
110 TPH boiler with three no’s of operating field.
• The supplier of ESP is M/s THERMAX LTD.
• The design of the ESP will be done in such a way which can give the
outlet dust concentration of 50 mg/Nm3 with full load capacity.
• The opacity meter will be installed at the stack for the online continuous
monitoring of particulate matter concentration in to gaseous emission and
the proposed power plant will be operated with DCS technology
• In any unfortunate case of emission more than desired emission from ESP,
the control logic will be built up in plant DCS so that the utilization of
boiler capacity will be reduced as per desired outlet concentration of
particulate matter from the ESP and it will be ensured that the
concentration of particulate matter in to gaseous emission will not exceed
the specified norms of GPCB.
• In any unfortunate case when ESP trip/fall and we can not meet the desired
emission norms, the emergency shutdown system will activated for shut
down of the boiler/power plant.
• The unit will take all necessary measures for the preventive maintenance
of ESP as well as boiler as suggested by their supplier in order to achieve
the design efficiency of the equipments
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.14
CHAPTER 6.4
RISK ANALYSIS DUE TO STORAGE
HANDLING OF COAL
6.4.1 Coal Requirement
The plant will consume imported coal only.
Assuming the worst possible of scenario, in which the plant would be forced
to use the Indian coal, the peak coal requirement would be around 572 MT
/day. Considering the fact that the bulk storage facilities for coal are available
in the proximity of the plant, the plant proposes to store about 30 days stock.
The plant have open yard storage capacity is 15000 MT and shed capacity is
10000 MT.
6.4.2 Receipt / handling /storage of coal
Coal will be stored in shed area having capacity of 10000 MT.
Bulldozer and pay loaders will be deployed for the purpose of stacking and
reclamation.
6.4.3 Hazards in Coal
Handling
1. Exposure to coal dust in handling coal.
2. Fall of object [Coal Pieces] while collecting spilled coal below running
conveyors.
3. Fire hazard.
6.4.4 Control Measures to be adopted
Following safe operating work procedure & precautionary measures will be
adopted.
1. Work permit system will be followed strictly.
2. The supervisor & the workers will be trained for the work to be carried
out. They will be made aware of the hazards involved in particular
work & remedial measures to be observed.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.15
3. Required P.P.E. as per job requirement be issued & their use be
ensured while working.
4. It would be ensured that the contractor would deploy well trained
physically fit workers for the work.
5. Authorized driver & cleaner only be assigned the work of driving the
vehicles.
6. Adequate lighting arrangement will be ensured in the coal yard & near
the equipment.
7. The workers will be using nose mask, safety shoes, gum boots &
helmet while working in coal handling plant to ensure their safety.
6.4.5 Hazards in Coal
Storage
Self heating of coal to its ignition temperature, resulting in what is called
spontaneous combustion, is a phenomenon identified with coal storage in
industries. Virtually all grades of coal (except high grade anthracite) are
vulnerable to spontaneous heating and ignition. Although the precise cause of
the spontaneous combustion of coal is not well defined, it is believed that
when coal is freshly mined, the fresh surface of coal pieces liberate absorbed
hydro-carbons, chiefly methane (in varying amounts), After the escape of the
absorbed gases, the exposed surface of coal particles get oxidized by the
oxygen in the ambient air.
1. The oxidation is very slow but heat is generated in the process. If the
heat is not allowed to dissipate, the temperature of the coal may rise
gradually but sufficiently enough to cause the mass to ignite. It is also
believed that this self heating of coal usually occurs in about 90 to 120
days after the coal is extracted in mining operations.
2. Oxidation in coal stacks takes place mainly from loosely packed coal
stacks and the consequent availability of oxygen in the voids of the
stacks. The rate of oxidation is high at the outer surface of the stacks
because of the availability of abundant oxygen there. The rise in
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.16
temperature, however, cannot be detected due to the dissipation of heat
by air movement.
This zone extends roughly up to a depth of 0.5m. The situation beyond
this zone, say up to a depth of 1.5m, is different. The coal in this zone
is also different. The coal in this zone also oxidizers fairly rapidly in
the presence of adequate quantity of air entering the stack, but the heat
generated in the course of this reaction is generally partially dissipated
through convection and conduction. The heat transfer from this zone
depends on factors like ambient temperature, rate of air movement
around that zone, free moisture available in the material and thermal
conductivity. The residual heat thus present in this zone further raises
the temperature of the coal mass until it attains the critical (threshold)
temperature i.e. the auto ignition temperature. Once it reaches critical
temperature, the coal in the zone starts burning and smoking and
eventually erupts in flames. Proneness to spontaneous combustion,
therefore, can be determined by ascertaining the critical oxidation
temperature or crossing point. The lower the crossing point, the more
is the proneness to self heating.
3. All types of coal, when exposed to the atmosphere, are liable to suffer
deterioration of quality through surface oxidation, but the extent of
deterioration differs from type to type. Under dry hot ambient
conditions, particularly in India where temperature in a shed could go
up to 45 deg C and humidity to less than 30%, the oxidation rate could
be high. It has also been observed that in large coal storage yards left
undisturbed for long periods, smouldering takes place at the surface
layers of the pile. In case of lignite, this phenomenon is more rapid.
Highly volatile coals are particularly liable to spontaneous combustion.
6.4.6 Control measures to be adopted during storage
Storage of large quantities of coal requires two conditions to be met viz. (i)
avoidance of deterioration in quality and (ii) avoidance of heating in the pile.
While neither of the conditions can be fulfilled completely, deterioration and
risk of fire can be reduced to a minimum by careful manipulation of the
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.17
conditions of storage. As basic necessary steps to avoid spontaneous heating in
coal storage, the following guidelines will be adopted:
1. The ground or floor where coal is to be stored will be thoroughly
cleaned of leaves, grass, weds, pieces of wood, cotton waste or other
organic waste and precautions taken to prevent such matter from
getting under, into or on the coal pile.
2. There will not be any steam or hot process pipelines or openings or
sewers under into through or adjacent to coal piles.
3. The floor and walls of coal storage bins will be of non-combustible
material.
4. The storage site will be provided with drainage facility to prevent
accumulation of water on the ground.
5. Special attention will be given to monitoring of the coal stack, floor or
wall temperature in excess of 420C.
6. The stack will be planned so as to facilitate dissipation of heat by wind
from the surface of the stack. Any barrier / obstruction to wind will be
removed.
7. Newly broken fines of coal are more susceptible to spontaneous
heating. Dropping coal from heights while piling will be avoided.
8. Conical piles will be avoided - this storage will be built up in layers by
roll packing – this helps to exclude oxygen and thus prevents fires by
discouraging spontaneous heating.
9. As far as possible coal piles from different sources will not be stored
together.
10. Coal stock should be limited in height. Low grade coal will not be
piled higher than 3 meters and best grade not higher than 4-5 meters.
Coal will be stored in mixed sizes as too many fines will be hazardous.
11. No standing timber or pipes, poles, etc. will be allowed in the piles.
These may give rise to formation of duct which allows sluggish air
flow which may be sufficient for heating the coal but not sufficient to
dissipate the heat.
12. It is recommended to locate coal yards at least 6-7 meters away from
any important buildings and other combustible storage areas.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.18
6.4.7 Control measures to be adopted for prevention of Coal Stock Fires
During the period of low off take, coal stock generally tends to build up to
alarming levels. Since most of the grades of coal are susceptible to
spontaneous ignition if it is undisturbed for a certain period of time, risk of fire
exists in coal stacks. Following precautions will be taken for preventing spread
of coal stock fire:
1. Consumption of coal will be done on first in first out basis.
2. Temperature of the coal pile will be checked regularly. Specific
attention will be given to the sloped sides of the piles where vulnerable
air pockets exist. If pile temperature exceeds 70 deg C, the pile will be
opened and placed the over heated material in a separate small pile or
use it promptly.
3. Inspection of stack will be done to detect smouldering and organize
removal /consumption of the smouldering coal on priority and to
extinguish the flames in time. Such inspections are vital after the rains
as water falling on the surface and penetrating the coal pile may
aggravate and accelerate spontaneous heating by assisting oxidation.
4. Coal having high moisture content will be stored separately, if
possible, and used promptly.
6.4.8 Transfer of coal from coal storage to Boiler
Pre-crushed (or sized and specified for feed) coal is fed to the vibratory screen
by dozing or shifting. The coal from this screen will be charged to the
conveyor. A suspension type magnet will be placed suitably at the end of the
conveyor belt to separate magnetic materials from coal stream.
1. Coal storage – Coal needs to be stored in proper procedure to avoid
it’s self combustion for the same purpose the coal heap height is to be
maintained as per the standard practices.
2. Manual crushing – It is required for the maintain the required inlet
size of coal to crusher, for which a arrangement of gizzly hopper is
given. After maintaining the required size it is feed to coal conveying
system through the coal feeders.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.19
3. Primary coal screening – In this process the coal of required size is
get separated through screen & conveyed directly to boiler bunker, i.e.
bypassing the coal crusher & it saves the power.
4. Coal crushing – The rejected size coal from primary screen is taken
into the impact type coal crusher for its further preparation to upto the
size ≤ 6 mm.
5. Secondary coal screen –The crushed coal from the coal crusher is
feed to secondary screen from where the accepted size coal conveyed
to boiler bunker & the oversized coal send back to primary screen inlet
conveyor through the bucket elevator to complete the cycle.
6. Coal storage at boiler bunker –After size preparation the coal is get
conveyed to bunker by coal conveyor & stored for boiler operation.
The capacity of bunker is 220MT.
7. The suspension type magnet will be placed suitably at the end of the
conveyor belt to separate magnetic materials from coal stream.
8. All conveying system is provided with ZSS as well as emergency pull
cord switch.
9. Transportation of coal from storage to boiler will be done through
closed belt conveyor belt system.
6.4.9 Hazards in Operations of Belt Conveyors
Like any other transmission machinery, belt conveyor’s present risk is injury.
Experience shows that conveyor accidents often involve fatal or very serious
injuries and severe damage to property.
1. As conveyor systems are vital links in the production chain, their stoppage
due to accidents or breakdowns can lead to serious business interruption
loss.
2. In bulk material transportation systems, excessive spillage represents
wastage of material, and emission of dust can present occupational safety
and health problems.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.20
3. Most personal injury accidents with belt conveyors occur when hands of
persons are trapped in inadequately guarded nip points and pinch points
near pulleys and idlers.
4. Mechanical failure of conveyor components due to deficiencies in design
and operational and maintenance procedures also render the conveyor
systems hazardous.
5. Spillage of materials, fires from friction, overheating, static charge and
other electrical sources are the other typical hazards encountered in belt
conveyor systems.
6.4.10 Emergency Procedure for Handling Coal Fire Description :
Coal stack of full height (eight meters) and a length of 10 m on fire or
smoldering below the surface on the entire length shall be considered as an
emergency. (The dimensions mentioned above are indicative only.
Uncontrolled fire in a portion of coal stack yard shall be treated an
emergency).
Resources:
a. Availability of fire hydrant and spray system around the stack yard.
b. Fire fighting tenders.
c. Portable diesel fire fighting pump.
d. Trained fire fighting personnel.
e. Earth moving equipment (2 nos. dozers & one pay loader).
f. 200 m of fire fighting hose along with different kinds of nozzles.
Procedure:
1. On observation of emergency fire situation in coal stack yard operation
engineer shall immediately report to Emergency control centre(ECC).
2. On receipt of communication from ECC all key personnel shall reach to
designated emergency control centre.
3. Work incident controller shall ensure containing of the fire affected stack
yard by cutting of coal on either side of coal stack by means of available
machinery such as dozers.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.21
4. The coal so removed shall be transported to the unaffected portion of the
stack yard or adjacent stack yard.
5. After ensuring complete isolation of the affected portion of stack yard,
press spray of water from water hydrant from all possible directions along
with tenders. Ensure quenching of flames and smoldering coal.
Spontaneous hibernation of steam from the quenched coal stack should not
be a cause of worry, however care to be exercised that persons involved in
tackling the emergency does not get hurt by the steam burst.
6. Excess fire fighting water going through the drain shall be contained in the
holding pond and shall be released only after complete settling of coal in
the holding pond.
7. After containing the fire completely, press dozers in service and compact
the coal further.
8. Reclaim the partially burnt coal at the earliest opportunity to bunker.
6.4.11 Crushing of Coal to the desired size
A non-reversible impactor (size 1200mm dia. X 1200mm width) would be
used for the purpose of crushing of coal from a size of 75 / 150 mm to 0 /
6mm.
The capacity of the machine would be around 90tons / hr, which is matching
with the peak requirement of about 700MT per day.
Following precautions related to safety would be taken while installing the
machine:
• It will be ensured that there is ready access to the Grease Nipple.
• Sufficient clearance will be kept between ground and discharge chutes
for fitting of discharge conveyor.
• It will be ensured that the side door is accessible and does not foul on
surrounding structure.
• V belts will be tightened as specified.
• A magnetic separator will be provided to avoid ingress of any non-
crushable material.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.22
CHAPTER 6.5
RISK ANALYSIS FOR THE BOILER
6.5.1 Equipment
The boiler will be manufactured in accordance with the requirements of latest
IBR rules and regulations and will have a valid registry with the Chief
Inspector of Boilers.
6.5.2 Description
Type -AFBC (Atmospheric fluidized bed boiler)
1 x 70 TPH
2 x 110 TPH
With Single – Drum, Natural Circulation, Balanced Draft, Top Supported,
Water Tube, Semi-Outdoor
Make: M/s THERMAX LTD which is IBR approved.
6.5.3 Controls
a. Three elements drum Level control.
b. De aerator level control
c. Pressure control valves with require ed manual isolation valves.
d. Combustion control
e. Instruments and fittings include :
i) Level switch for very low and high level.
ii) Local temperature Gauge.
iii) Temperature transmitter for DCS display.
iv) Level Gauge and Pressure Gauge.
v) Pressure transmitter.
vi) Level transmitter.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.23
Safety Margins
� To Generate 45 MW power total 234 TPH steam required.
� The unit will need to run the boilers at maximum of @ 92 % capacity.
� Pressure release valve(PSV) will be installed to release the pressure higher
than the set value.
6.5.4 Electrostatic Precipitator
Make: M/s THERMAX Ltd
The unit is going to install one ESP for two no’s of 70 TPH and one no of 110
TPH boiler with four no’s of operating field to limit the pollution level with
all fields in service to 50 mg/Nm3 (wet on actual O2 basis) with Imported coal
at the outlet with complete accessories including emitting and collecting
electrodes, transformer sets, Rapping mechanism, local control panel and
hoppers. ESP will be supported on steel structure starting from +300 mm
level.
Safety Margin
• The opacity meter will be installed at the stack for the online continuous
monitoring of particulate matter concentration in to gaseous emission and the
proposed power plant will be operated with DCS technology
• In any unfortunate case of emission more than desired emission from ESP, the
control logic will be built up in plant DCS so that the utilization of boiler
capacity will be reduced as per desired outlet concentration of particulate
matter from the ESP and it will be ensured that the concentration of particulate
matter in to gaseous emission will not exceed the specified norms of GPCB.
• In any unfortunate case when ESP trip/fall and we can not meet the desired
emission norms, the emergency shutdown system will activated for shut down
of the boiler/power plant.
• The unit will take all necessary measures for the preventive maintenance of
ESP as well as boiler as suggested by their supplier in order to achieve the
design efficiency of the equipments
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.24
6.5.5 Local Field Instruments
Thermocouples to measure the following:
• Bed temperature (Two in each compartment 1 Top + 1 Bottom).
• Furnace temperature.
• Main steam temperature.
• Steam temperature after attemperator.
Temp. gauges to measure the following :
• Flue gas temperature before economizer.
• Flue gas temperature before air heater.
• Flue gas temperature after air heater.
• Feed water temperature before economizer.
• Feed water temperature after economizer.
• Air temperature after air pre-heater.
• De-aerator steam / water temperature.
Pressure gauges to measure the following:
• Steam pressure at steam drum.
• Feed line pressure.
• Super heater steam outlet pressure.
• De-aerator steam pressure.
Draught gauges to measure the following:
• Air Box pressure.
• Flue gas at Economizer inlet pressure.
• Flue gas at Economizer outlet pressure.
• Flue gas at Air-heater outlet.
• Air at Air-heater inlet.
6.5.6 Noise level
85 dBA at 1.0 m distance for rotating equipment except Boiler Feed Pump
which will be 92 dBA at 1 m distance. For safety valves and start up vent with
silencers 110 dBA at 3.0 m distance. These values are within the acceptable
levels specified under Gujarat Factories Rules.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.25
CHAPTER 6.6
RISK ANALYSIS FOR STEAM TURBINE
GENERATOR SET
6.6.1 Design The turbine will be designed as per DIN standards.
Operating medium: Superheated Water Steam. The above consumption data
apply at steady state operating conditions, with the control valves fully open,
deposit-free balding and clean surfaces of the cooling equipment, in
accordance with the rules for "thermal acceptance tests of steam turbines (VDI
– Rules of Steam Turbines) DIN 1943, edition of February 1975.
6.6.2 Protection functions
Turbine protection for:
• Over speed protection
• Governor emergency trip
• Axial Vibration high
• Lube oil pressure low.
• Control oil pressure low.
• Manual trip
• Remote trip
• Bearing temperature high.
• Alarm on Live steam temperature low.
• Alarm on Live steam pressure low.
6.6.3 Machine noise
The machine noise level shall be determined according to DIN 45 635 and
evaluated according to ISO/TC43. The plant quoted will not exceed a noise
level of 90 dB(A) above the turbine table slab in any octave band without
noise hood.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.26
The noise level under floor will not exceed 90 dB(A) provided that the
influence of the ambient noise is less than 3 dB(A).
The measurements shall be taken at a distance of 1 m maximum from the
machine surface of the turbo set above the foundation table slab.
The influence of extraneous noises and acoustic reflections of the room shall
be taken into consideration when evaluating the measured values.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.27
CHAPTER 6.7
RISK ANALYSIS FOR ASH HANDLING
SYSTEM
Various ash discharge point in a FBC boiler are as below:
Convection bank / Economizer / Air heater / Electro static precipitator. Hopper will be
provided below all these discharge points. For controlling the dust emission in the
plant due to fly-ash discharge, dense phase ash handling is envisaged. In this system
ash will be mixed with pressurized air and ash will be discharged in a ash silo where
ash and air will be separated out. Then ash will be loaded in the transport vehicle and
will be disposed of for cement plant and land filling.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.28
CHAPTER 6.8
RISK ANALYSIS FOR AIR POLLUTION
CONTROL SYSTEM The pollution norms of the Gujarat state with outlet emission restriction to less than
50 mg/Nm3 calls for the selection of latest ESP technology. The ESP technology has
been well developed now. The state of art ESP function is explained in the following
steps:
The particles must be charged through exposure to a high voltage field. The charged
particles are collected on both the discharge and collecting electrodes. The electrodes
are rapped to remove the collected particulate. The particulate settles in the hopper
and is removed from the precipitator.
Particle charging occurs as a result of the development of a high negative DC voltage
between the negative discharge electrode and the grounded collecting electrodes. At
and above a critical voltage, the dielectric strength of the gas medium is exceeded,
and a corona discharge takes place in the region of the negatively charged discharge
electrode. The corona discharge is a visible manifestation of the ionization of the gas
between the discharge and collecting electrodes. The presence of this potential
difference accelerates naturally occurring free electrons in the vicinity of the
discharge electrode. These free electrons collide violently with gas molecules and
strip them of electrons.
A minority of the particles is collected as the positive ions collide with and carry ash
particles to the discharge electrodes. The majorities of the particles are collected as
the electrons moving toward the grounded collecting electrodes collide with and are
captured by electronegative gases to form negative ions that collide with and carry
dust particles to the collecting electrodes.
The dust particles accumulate on both the discharge and collecting electrodes over a
period of time. Both sets of electrodes must be cleaned to allow continuing ionization
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.29
at the discharge electrodes and to prevent back ionization, or back corona, at the
collecting electrodes. The electrodes are cleaned by rapping them sharply. This
imparts a vibration to the electrodes that has the effect of dislocating the dust through
a combination of the amplitude and frequency of the vibration. The two main goals of
rapping are to maximize the percentage of the dust that is dislocated from the
electrodes and to minimize the percentage of dust that is re-entrained into the gas
stream.
Particulate is removed from the precipitator after being rapped off of the electrodes
and settling into the dust hoppers (or wet bottom / drag bottom as the case may be).
Heaters are provided on hoppers to help keep the settled dust free flowing. The
specific features like higher surface area of collection electrodes, higher number of
fields, better rapping mechanism ensure the Gujarat Pollution Control Board norms of
particulate matter of less than 50 mg/Nm3.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.30
CHAPTER 6.9
PROPOSED FIRE FIGHTING SYSTEM
6.9.1 General Information
CODES AND STANDARD:
The Codes and Standard described below are applied to the designing and
manufacturing of the equipment/ material proposed:
SYSTEM DESIGN:
Tariff Advisory Committee Regulations.
EQUIPMENT DESIGN:
• I.S.I. Standards.
• TAC regulations.
6.9.2 Pressurized Hydrant System
The Hydrant is located around building to be protected and is connected by a
ring main of underground pipe to the delivery of pumping set. As per TAC
regulation the Pipeline is in form of a ring main, and the maximum number of
Hydrant points in a terminal do not exceed five. Risers have been provided in
the system to protect upper floors. In Power House and in storage yard Water
Monitors has been provided.
In this complex the number of Hydrant Points are 54 and 11 nos. of fire
monitor, hence the pump capacity is 273 m3/ hr. We have designed the system
hydraulically ensuring a minimum 3.50 Kg/Sq.cm water pressure is available
at the remotest hydrant point.
Necessary isolation i.e. sluice valves are provided at suitable location to
facilitate isolation of any particular pipeline for maintenance, or ensuring
water reaches by the shortest route to the area desired in case of fire.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.31
The system has been designed in Ordinary Hazard category and Hydrants
suitably spaced at 45m interval. Along with each landing valve two sets of
hoses, each of 15 m long one branch pipe are placed in a hose box. System
shall be designed to operate on Automatic Mode but stopping of the main
pump shall be done manually. For maintaining the pressure in the system a
Jockey pump has been included which shall start automatically on drop in
pressure and stop automatically when the pressure reaches the pressurized
level. The water supply to the system is from one electrically driven pumping
set of 273 m3/hr capacity operating at 88 MWC head & at 1450 rpm. Pump
proposed is suitable for 54 Hydrant points and 11 nos. of fire monitor. A Stand
by pump of the same capacity is also provided. The pumps draw water from a
water reservoir.
6.9.3 Main Fire Pump
Electrical driven pump, of capacity 273 cum/hr at 7 Kg/cm2, running at 1450
rpm. The Pump shall have Cast Iron casing, Bronze Impeller, Sleeves and SS
Shaft.
6.9.4 Diesel Engine Driven Fire Pump
273 M3/HR. 88 MWC pump suitable for Diesel Engine drive with coupling.
The Pump shall have Cast Iron Casing. Bronze Impeller and SS Shaft. Diesel
Engine complete with Flywheel housing. Exhaust manifold (day vibration
Damper. Air cleaner, Fuel Pump, Mechanical variable speed Governor, Heat
Exchanger, Fuel Filter, Lube oil filter, Fuel Oil Pump, 24 V.D.C. Starting and
battery charging system, Plant Engine Support, Instrumentation panel
consisting of starter switch - LO Pressure gauge, LO Temp Gauge, water
temperature gauge and Ammeter, Safety Control for alarming of low oil
Pressure and high water temperature, dry type silencer, flexible coupling/fuel
lines. Techno Motor (Mechanical), Fuel Houses water heater with Thermostat
switch, exhaust pipe, Batteries, Fuel Oil Tank, Cooling Water piping and
starter panel.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.32
6.9.5 Pressurization (Jockey Pump)
To keep the Hydrant system in a pressurized state a Jockey Pump is employed
of capacity 10.8 m33/hr with 88 MWC.
6.9.6 Others Accessories
Sr. No. Description Nos
1. Common MCC panel for main pump and jockey pump 01
2 Diesel engine control panel for diesel engine driven standby pump
with complete auto/manual switch, indication lamps, protective fuse
with battery chargers suitable for working on 230 V, AC, single
phase, enclosure being vermin & dust proof with interconnecting
cabling between battery, diesel engine instrument box and diesel
engine control panel.
01
3 0-200 PSI range, pressure gauge ½” NPT bottom entry 6” dial
weather proof with stainless steel internals with isolation cock.
04
4 Indicative type pressure switch having ½ “ NPT connection IP:32
encl. protection , bronze bellow as sensing element, SPDT contact
system, switch rating 6A inductive/10A resistive 380.02 A
inductive/10A resistive 250 V DC suitable for Max pressure range of
230 psi with isolation cock.
04
6.9.7 Functions Automatic Mode
This mode, as selected on the Pump set mode switch provides for complete
Un-attended operation. When the mode switch is put in "Auto" position, the
operation of the Diesel Engine Pumping set is as follows:
• While normal water pressure is above 3.00 Kg/Cm2 the Diesel Engine
Driven Pump shall be at rest.
• When the water pipe line pressure switch for Diesel Engine is actuated on
water pressure dropping to a pre set level, the control system shall actuate
the Pumping set.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.33
• When the Diesel Engine Driven Pump is to be switched off, this shall be
done manually. On shutting down the pump is ready for the next operation.
Off Mode
The Off-Mode, as selected on the unit mode switch, all functions from the
Panel are in Off condition. Battery Charging System however does not remain
effected.
Manual Mode
The Manual Mode of operation as selected on the unit mode switch is different
from the Automatic Mode that the Diesel Fire Pump has to be started
manually by the operator by pressing the "START" push button. To ensure
Engine stops, the "STOP" push button should remain in pressed position, till
the engine stops completely, otherwise the engine shall start again.
6.9.7 Unit protection
A three attempt starting facility is provided for the Engine and if it fails to start
in all the three attempts (from receiving the starting signal) the set is locked
out automatically and an Audible and Visual indication alarm is given.
6.9.8 Diesel Engine Protection
Low Lube Oil Pressure –
In case of engine lube oil pressure falling below a pre-set value the Diesel Fire
Pump shall be brought to rest.
Engine High Water Temperature –
In case the Engine Cooling Water Temperature goes above a pre-set value the
pumping set shall be brought to rest. On receiving the above faults and engine
being tripped, the engine mounted safety switch should be reset manually.
Engine comes back to normal and Diesel Engine Panel is ready for the next
operation.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.34
High Lube Oil Temperature –
On receiving the above faults and engine being tripped, the engine mounted
safety switch should be reset manually. Engine comes back to normal and
Diesel Engine Panel is ready for the next operation.
Over Speed Shut Down –
On receiving the above faults and engine being tripped, the engine mounted
safety switch should be reset manually. Engine comes back to normal and
Diesel Engine Panel is ready for the next operation.
6.9.9 Air Vessel
It is used for compensating slight losses in pressure, and is of size 300 mm
diameter and 1500 mm long, with dished ends. Each Air Vessel consists of :
Inlet Valve, Drain Valve, Vent Valve
This is mounted on the delivery side of common delivery header.
6.9.10 Strainer
Strainer is used on the suction side of the pumps to ensure filtered water is
available to the pumps. The body is of fabricated construction and the filter is
so designed to ensure cleaning by removing the cover plate. The strainer is
designed to ensure minimum pressure loss. Pressure gauges provided on
upstream and downstream side measure the pressure differential. Flanges are
drilled to make the counter flanges available.
6.9.11 Pressure Gauge
Pressure Gauge shall be of dial type with bourdon tube element of SS 316.
The Gauge shall be of reputed make. The dial size shall be ½” die and scale
division shall be in metric units marked clearly in black on a white dial. The
range of Pressure Gauge shall be 0 to 16 Kg/Cm2.
6.9.12 Pressure Switch
The pressure switches shall be employed for starting and shutting down
operation of the pumps automatically, dictated by line pressure.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.35
Indicative type pressure switch having ½ “ NPT connection IP:32 encl.
protection , bronze bellow as sensing element, SPDT contact system, switch
rating 6A inductive/10A resistive 380.02 A inductive/10A resistive 250 V DC
suitable for Max pressure range of 230 psi with isolation cock.
It shall be provided waterproof and weatherproof enclosure with IP 66 rating
in Aluminum. All other parts including pressure element and wetted parts shall
be Stainless Steel.
The pressure switches shall be Snap acting with 2 sets of NO + NC contacts.
6.9.13 Set of Pipelines
Consist of above ground and under ground pipelines. The underground
pipelines will be given anticorrosion treatment.
6.9.14 Set of valves
Consisting of sluice valve, non-return valves, landing valves etc.
6.9.15 RRL Hose
“FIRE CHIEF” brand, cotton/synthetic fiber , circular woven jacketted,
rubberised fabric reinforced rubberlined (RRL) fire hose, delivery, treated
against not with MYSTOX, bearing IS 636 type 2 mark, 35.7 Kg/cm2 burst
having T.A.C. and M.M.D. approval.
6.9.16 Branch Pipes
Branch pipe, short, SS 304, 63 MM male instantaneous inlet, male threaded
outlet, complete with 5/8” bore nozzle as per IS: 903 mark.
6.9.17 Hose Boxes
These are used for accommodating Fire Hose Pipes and Branch Pipes. These
shall be suitable for Wall Mounting fabricated from 16 SWG MS sheet double
coated with P.O. Red after single coat of Red oxide primer. Each Hose
Cabinet shall have front door, which is lockable, and glass is breakable in
emergency.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |6.36
6.9.18 Fire Hose Couplings
Delivery hose coupling, Stainless Steel SS 304, heavy duty inst. Pattern, pair
of male & female parts, 63mm x 63mm size, and bearing IS: 903
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |7.1
CHAPTER 7 PROJECT BENEFITS
7.1 IMPROVEMENT TO FULL FILL THE SUGAR DEFICIT IN
COUNTRY
• The annual production of sugar in India in current year is expected to
be only around 14.7 – 15 Million tons which is very much below the
annual consumption of India of 22 Million tons.
• To meet this deficit, Govt. of India has allowed to import of Raw
Sugar and to capitalize on this scenario SRSL has decided to expand
the sugar refining capacity and choose this location of future refineries
so as to be able to easily import, process and export sugar.
• To fulfill the process steam & power requirement for Sugar refinery,
the company has proposed to set up 45 MW power plant
7.2 IMPROVEMENT IN INFRASTRUCTURE
SRSL is planning to develop a good green belt in & around the complex. This
should be further enhanced and will be extended to the adjacent area. The
local community will be involved in the entire project development and can be
gainfully employed. Local work force will be recruited to the extent feasible.
The Management of SRSL is already actively involved in the community
development and local development. It also sponsors various programs,
educational facilities, development of infrastructure facilities like construction
of asphalted road of 20Km approx in & around the complex.
Apart from these the management also planning adopt the villages nearby and
provide more infrastructure like hospitals, Bus-shelters, transport facilities etc.
SRSL also encourage locals to set up ancillary units and self-employment
schemes. Under corporate social responsibility SRSL planned to invest Rs25 Lacs
approx. apart from ETP, RO etc.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |7.2
7.3 EMPLOYMENT POTENTIAL
The company shall provide employment potential under unskilled, semi-
skilled and skilled categories. The employment potential shall increase with
the start of construction activities, reach a peak during construction phase and
then reduce with completion of construction activities.
During operation phase also there will be employment opportunities, although
its magnitude will be much less. The direct employment opportunities with the
company are extremely limited and the opportunities exist mainly with the
contractors and sub-contractors. These agencies will be persuaded to provide
the jobs to local persons on a preferential basis wherever feasible.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.1
CHAPTER 8
RAIN WATER HARVESTING PLAN
8.1. INTRODUCTION
Shree Renuka Sugar Ltd. has developed India’s largest sugar
refining capacity having its corporate office in Mumbai and
headquarters at Belgaum (Karnataka) .The Company also produces
Power, Ethanol and bio-fertilizers besides Sugar.
Shree Renuka Sugar Industries, (Gujarat refinery) proposes to set up
a sugar refinery along with 45 MW coal based power plant at
Gandhidham, Kutch, Gujarat. This will be the captive power plant
for its sugar refinery in Bharapar, Gandhidham, district Kutch. An
area of 11.13 hectares has been earmarked for captive power plant
while the total area of the sugar refinery is 61 hectares. The water
requirement of thermal plant has been estimated as 1220 m3/day
(0.445 Mm3/year) which will be obtained by desalination of sea
water.
The present report recommends proposals for augmenting the ground
water storage of the plant area by harvesting roof top rain water of
different buildings and utilizing surface runoff. This will also help
in improving the quality of ground water which is at places brackish,
being close to the coast. All these proposals of rain water harvesting
will augment the ground water storage of the area and will reduce
the possibility of sea water ingress.
Climate of the area is moderate, during summer the maximum
temperature rises up to 40ºC and in winter season the minimum
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.2
temperature recorded as 8ºC. Average wind speed is 7m/s and
average annual rainfall is 452 mm.
8.2. NEED FOR ARTIFICIAL GROUNDWATER RECHARGE
Although, there will not be any additional ground water abstraction
from the plant area as the water requirement for the plant will be met
from sea water after due desalination , Renuka sugar industry is
proposing to undertake rain water harvesting measures to augment
the ground water storage as a national obligation. There is
availability of adequate roof top rain water from the different
buildings of the plant and there is unsaturated zone of around 9
metres during the post monsoon period of which 6 metres could be
recharged. So there is an ideal hydrogeological setting for rain water
harvesting measures to be undertaken in the national interest as well
as under social corporate responsibility to recharge loosely
consolidated sand of marine origin. It is therefore considered
necessary to take up rain water harvesting measures to augment the
ground water storage of Bharapar area of Gandhidham so that the
ground water basin has surplus exploitable ground water potential
even during the drought years and static ground water reserves of
the area are not depleted.
Rain water harvesting is necessary in this coastal area to improve the
quality of ground water which at places, particularly near the sea is
brackish to saline. Surface runoff generated in the area is relatively
better in quality, with total dissolved salts less than 500 mg/l as
compared to ground water. So any efforts for recharging the ground
water reservoir with surface runoff will improve the quality of
ground water.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.3
There are chances that wells close to coastal area might be
susceptible to sea water intrusion. Some wells have shown higher
salinity during summer, indicating the possibility of saline water
intrusion. Although, actual saline water intrusion might not have
taken place, its prospects can be reduced by recharging an area
between sea and the coast by forming a fresh water ridge.
8.3. BASIC REQUIREMENT FOR ARTIFICIAL RECHARGE
PROJECTS
The basic requirements for recharging ground water reservoir are
I. Availability of non-committed surplus monsoon runoff in space and time
II. Identification of suitable hydrogeological environment and sites
for creating sub-surface reservoir through cost effective recharge structures.
While considering the hydrological and hydrogeological scenario for
artificial ground water recharge in Bharapar of Gandhidham area, it
is observed that plant and green belt area, comprising 61 hectares
receives 0.275 mcm ( million cubic metres) of rain water from
average rainfall of 452 mm. So, the availability of water for artificial
recharge in the plant is not a problem and only the cost effective
recharge structures are to be constructed which can recharge a large
volume of available surface runoff. The available surface runoff in
the plant is not- committed for any purpose and is available every
year during the monsoon period.
Roof top rain water harvesting is most popular and convenient for
recharging ground water particularly for domestic use. Here in case
of SRSI plant, it is proposed to adopt roof top rainwater harvesting
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.4
in the plant area as an artificial recharge technique. In addition, there
is open land available where there is no plan of construction activity
which can be utilsed for capturing surface runoff. This will provide
significant water for ground water recharge. Under such situation,
when the objective is to recharge a large quantity of water, only cost
effective recharge structures, based on direct surface techniques are
beneficial.
Fortunately, in present case, there is loosely consolidated sand
under a thin alluvial cover and the sand is coarse grained, well sorted
,therefore will have adequate vertical and fast infiltration rate
allowing water to percolate down to the zone of saturation, which is
at the depth of around 9 metres during the post monsoon period.
There is therefore an unsaturated zone of at least 6 metres (the 3
metres of upper unsaturated zone is not to be recharged, as it may
cause adverse environmental impact like water logging and soil
salinity) which can be recharged. The total available water storage
capacity of the plant having an area of 61 hectares which could be
recharged amounts to 0.366 mcm taking 10 % as the specific yield of
the sand.
It is therefore proposed that roof top rain water from different
buildings and surface runoff may be recharged through contour
bunding in an open area available.
8.4. MAIN CONSIDERATIONS FOR SELECTION OF
RECHARGE STRUCTURES
Although, there are many recharge structures in practice for artificial
recharge of ground water, only those recharge structures are being
proposed which are cost effective and most suitable for
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.5
hydrogeological and hydrological setting of Gandhidham area. The
following considerations have been kept in mind while proposing the
recharge structures in the plant area.
1. Only those recharge structures are being proposed which are cost
effective and provide immediate ground water recharge as it is
most economical to recharge directly existing open
wells/tubewells.
2. Wherever, roof top rain water and surface runoff are available and
water levels are shallow, recharge trenches are most economical
recharge structure for ground water recharge.
3. The recharge structures should be easy to maintain and should not
have high recurring cost of annual maintenance.
4. Only such materials required for construction of filtration pits,
filter media, masonry structures which are available in the nearby
river beds, can be procured locally and easily.
Keeping these considerations in view, the following recharge
structures are being proposed for plant.
8.4.1. Proposed recharge structures in plant area
8.4.1.1. Roof top rainwater harvesting
The plant will have few buildings having concrete cement
roofs and AC sheet roof tops. The buildings will have open
area in front of each building having a provision of a
cemented drain which will be used as recharge trench by
leaving the bottom as unlined and filled with filter media.
Generally roof top rain water from each building is collected
by drains and put in the cemented drains which ultimately is
discharged to far off place either for reuse for gardening or
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.6
in ponds for ground water recharge. It is now proposed that
roof top rain water will be collected by drain pipes which
will be released to a recharge trench, just constructed in the
front of the building, half metre to two metres wide and one
metre in depth having filtration media. Surplus water will be
taken to another trench if necessary. Depending on the roof
top area of the building and sheds, the water will be fed to a
recharge trench; the length of the trench will depend on the
area of the roof top.
8.4.1.1.1. Raw sugar warehouse
There will be three raw sugar ware houses in this block
situated near the southern gate of the plant having the roof
top area of 22,800 m2 each making total roof top available
in this block to be 68,400 m2 . It is proposed to collect the
available roof top water in four segments .The roof is
supposed to be constructed from corrugated asbestos cement
sheets. The availability of rain water from roof top has been
estimated by taking 85 % of the 452.40 mm. average annual
rain fall. The intensity of rainfall, which is 60 mm. per hour
(15 mm. per 15 minutes) as peak rainfall for Gandhidham
area, has been taken for estimating water availability for
designing trenches.
The raw sugar warehouse block which is proposed to be
constructed near the southern gates of the plant will have
three warehouses I, II and III. For planning the rainwater
harvesting in this block, the roof of the three warehouses are
being considered in different combinations. As the roof of
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.7
the warehouses are inclined and ‘V’ shaped the half of the
roof of warehouse no. I and no. III is to be considered
separately and roof of the adjoining warehouses having roof
inclination towards each other have been considered
separately and collection of water is to be done accordingly.
The availability of rooftop rainwater from different rooftops
in raw sugar warehouse block has been estimated as under
(I) Half of rooftop of warehouse No. I Availability of roof top rain water 11400x 0.85 x 0.452 = 4380m3 Peak availability of water during 11400 x 0.85 x 0.015 = 145 m3 during 15 minutes
It is proposed that roof top rain water from the raw sugar
warehouse building may be collected through drain pipes
from the part of warehouse (I) and brought to recharge
trench of one metre width, one meter deep to be
constructed beside the wall of the roof.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.8
Figure 8.1
Recharge System for Raw Warehouse (Segment – I)
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
285 metres in length surrounding the building and will store
145 cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. A recharge trench of 285
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.9
metres in length will store 145cu.m. of water sufficient for
15 minutes of continuous rainfall and is calculated by taking
50 % porosity of the filter media.
285 x 1 x 1 x 0.5 = 143 cu.m
(Length x depth x width x porosity = storage)
Half of rooftop of warehouse No. I and half of adjoining warehouse No.II
Availability of roof top rain water 22800x 0.85 x 0.452 = 8759m3 Peak availability of water during 22800 x 0.85 x 0.015 = 290 m3 during 15 minutes It is proposed that roof top rain water from the raw sugar
warehouse building may be collected through drain pipes
of the part of warehouse (I)and (II) and brought to recharge
trench of two metre width, one metre deep to be
constructed beside the wall of the roof.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.10
Figure 8.2
Recharge System for Raw Warehouse (Segment – II)
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down through the drain and meet the
trench. The water will get accumulated in the trench which
will be 285 metres in length surrounding the front of the
building and will store 290 cu.m of water. This water will
gradually percolate through granular zone at depth and will
join water table which is around 9 metres below the land
surface during the monsoon and post monsoon period. A
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.11
recharge trench of 285 metres in length will store 290cu.m.
of water sufficient for 15 minutes of continuous rainfall and
is calculated by taking 50 % porosity of the filter media.
285 x 1 x 2 x 0.5 = 285 cu.m
(Length x depth x width x porosity = storage)
(II) Half of rooftop of warehouse No. II and half of adjoining
warehouse No.III Availability of roof top rain water 22800x 0.85 x 0.452 = 8759m3 Peak availability of water during 22800 x 0.85 x 0.015 = 290 m3 15 minutes
It is proposed that roof top rain water from the raw sugar
warehouse building may be collected through drain pipes
of the part of warehouse (I)and (II) and brought to recharge
trench of two metre width, one metre deep to be
constructed beside the wall of the roof.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.12
Figure 8.3
Recharge System for Raw Warehouse (Segment – III)
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
285 metres in length surrounding the building and will store
290 cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. A recharge trench of 285
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.13
metres in length will store 290cu.m. of water sufficient for
15 minutes of continuous rainfall and is calculated by taking
50 % porosity of the filter media.
285 x 1 x 2 x 0.5 = 285 cu.m
(Length x depth x width x porosity = storage)
(III) Half of rooftop of warehouse No.III Availability of roof top rain water 11400x 0.85 x 0.452 = 4380m3 Peak availability of water during 11400 x 0.85 x 0.015 = 145 m3 during 15 minutes It is proposed that roof top rain water from the raw sugar warehouse
building may be collected through drain pipes of the part of warehouse
(I) and brought to recharge trench of one metre width, one metre deep
to be constructed beside the wall of the roof.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.14
Figure 8.4
Recharge System for Raw Warehouse (Segment – IV)
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
285 metres in length surrounding the building and will store
145 cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. A recharge trench of 285
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.15
metres in length will store 145cu.m. of water sufficient for
15 minutes of continuous rainfall and is calculated by taking
50 % porosity of the filter media.
285 x 1 x 1 x 0.5 = 143 cu.m
(Length x depth x width x porosity = storage)
8.4.1.1.2. General Stores
A General Store is proposed to be constructed with cemented
roof top area of 2592 m2. The availability of rain water
from roof top has been estimated by taking 90 % of the
average 452 mm. of average annual rain fall. The intensity of
rainfall, which is 60 mm. per hour (15 mm. per 15 minutes)
as peak rainfall for Gandhidham area has been taken as
water availability for designing trenches.
Availability of roof top rain water 2592 x 0.90 x 0.452 = 1054 m3 Peak availability of water during 2592 x 0.90 x 0.015 = 35 m3 during 15 minutes
It is proposed that roof top rain water from the general stores
building may be collected through drain pipes and brought
to recharge trench of one metre width, one metre deep to
be constructed beside the wall of the roof.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.16
Figure 8.5
Recharge System for General Stores
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
72 metres in length surrounding the building and will store
33 cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. The storage capacity of
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.17
the recharge trench will be 36 cu.m. sufficient to store 15
minutes of heavy downpour as calculated as under taking
50% porosity of filter media :
72 x 1 x 1 x 0.5 = 36 cu.m
(Length x depth x width x porosity = storage)
8.4.1.1.3. White sugar warehouse
Currently, it is proposed to construct three white sugar ware
houses and two future warehouses with different roof top
areas. These warehouses are to be constructed in a row and
as such the roof top rain water which is supposed to be
collected can be recharged in the trenches. The availability
of rain water from each warehouse will be as under:
White sugar warehouse No.I
Availability of roof top rain water 17160 x 0.85 x 0.452 = 6593 m3 Taking the intensity of rainfall as 60 mm. per hour (15 mm. per 15
minutes) as peak rainfall for Gandhidham area, the water available will
be:
Peak availability of water during 17160 x 0.85 x 0.015 = 219m3 during 15 minutes
It is proposed that roof top rain water from the building may
be collected through drain pipes on the either sides of the
building and each drain pipe brought to recharge trench of
two metre width, one metre deep to be constructed in front
the building.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.18
Figure 8.6
Recharge System for White Sugar Warehouse No. I
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
264 metres in length in front of the building and will store
264cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. The storage capacity of
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.19
the recharge trench will be 264cu.m. sufficient to store water
for 15 minutes of continuous rainfall and is calculated as
under:
264 x 1 x 2 x 0.5 = 264 cu.m
(Length x depth x width x porosity = storage)
White sugar warehouse No. II
Availability of roof top rain water 17160 x 0.85 x 0.452 = 6593 m3 Taking the intensity of rainfall as 60 mm. per hour (15 mm. per 15
minutes) as peak rainfall for Gandhidham area, the water available will
be:
Peak availability of water during 17160 x 0.85 x 0.015 = 219m3 15 minutes
It is proposed that roof top rain water from the building may
be collected through four drain pipes, four each on the
either sides of the building and each drain pipe brought to
recharge trench of two metre width, one metre deep to be
constructed in front the building.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.20
Figure 8.7
Recharge System for White Sugar Warehouse No. II
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
264 metres in length in front of the building and will store
264cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. The storage capacity of
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.21
the recharge trench will be 264cu.m. sufficient to store water
for 15 minutes of continuous rainfall and is calculated as
under:
264 x 1 x 2 x 0.5 = 264 cu.m
(Length x depth x width x porosity = storage)
White sugar warehouse No.III
Availability of roof top rain water 17160 x 0.85 x 0.452 = 6593 m3 Taking the intensity of rainfall as 60 mm. per hour (15 mm. per 15
minutes) as peak rainfall for Gandhidham area, the water available will
be:
Peak availability of water during 17160 x 0.85 x 0.015 = 219m3 15 minutes
It is proposed that roof top rain water from the building may
be collected through four drain pipes, four each on the
either sides of the building and each drain pipe brought to
recharge trench of two metre width, one metre deep to be
constructed in front the building.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.22
Figure 8.8
Recharge System for White Sugar Warehouse No. III
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
264 metres in length in front of the building and will store
264 cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. The storage capacity of
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.23
the recharge trench will be 264cu.m. sufficient to store water
for 15 minutes of continuous rainfall and is calculated as
under:
264 x 1 x 2 x 0.5 = 264 cu.m
(Length x depth x width x porosity = storage)
8.4.1.1.4. Future white sugar warehouse
Provision for future white sugar warehouses includes two
warehouses having rooftop area of 14950m2 and 25990 m2
respectively. The rooftop rainwater available through these
ware houses are as under:
Warehouse-I Availability of roof top rain water 14950x 0.85 x 0.452 = 5744 m3 Taking the intensity of rainfall as 60 mm. per hour (15 mm. per 15 minutes) as peak rainfall for Gandhidham area, the water available is: Peak availability of water during 14950 x 0.85 x 0.015 = 191 m3 15 minutes
It is proposed that roof top rain water from the building may
be collected through four drain pipes, four each on the
sides of the building and each drain pipe brought to
recharge trench of 1.75metre width, one metre deep to be
constructed in front the building.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.24
Figure 8.9
Recharge System for Future White Sugar Warehouse No. I
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
230 metres in length in front of the building and will store
191cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.25
monsoon and post monsoon period. The storage capacity of
the recharge trench will be 201cu.m. sufficient to store water
for 15 minutes of continuous rainfall and is calculated as
under:
230 x 1 x 1.75 x 0.5 = 201cu.m
(Length x depth x width x porosity = storage)
Warehouse-II Availability of roof top rain water 25990x 0.85 x 0.452 = 9985m3 Taking the intensity of rainfall as 60 mm. per hour (15 mm. per 15 minutes) as peak rainfall for Gandhidham area, the water available is: Peak availability of water during 25990 x 0.85 x 0.015 = 331 m3 15 minutes
It is proposed that roof top rain water from the building may
be collected through drain pipes on either sides of the
building and each drain pipe brought to recharge trench of
1.5 metre width, one metre deep to be constructed around
the building.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.26
Figure 8.10
Recharge System for Future Sugar Warehouse No. II
The recharge trench will be unlined, filled at the bottom
with 30 cm. thick layer of pebbles, 30 cm. thick layer of
gravel, 30 cm. thick layer of coarse sand and 10 cm. thick
layer of pebbles or one layer of boulders. The water from
the roof top will come down the drain and meet the trench.
The water will get accumulated in the trench which will be
460 metres in length on either side of the building and will
store 331 cu.m of water. This water will gradually percolate
through granular zone at depth and will join water table
which is around 9 metres below the land surface during the
monsoon and post monsoon period. The storage capacity of
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.27
the recharge trench will be 345 cu.m. sufficient for 15
minutes of the continuous rainfall and is calculated as under:
460 x 1 x 1.5 x 0.5 = 345 cu.m
(Length x depth x width / porosity = storage)
Net recharge from trenches.
There will be total inflow of water in the different recharge
trenches of 66,840 m3. Except evaporation, there will be no
other loss and all the water entering the recharge trench will
percolate in the zone of saturation through coarse sand. It is
therefore safe to assume that 75 % (50,130 m3) of water
entering the recharge trench will join the ground water
storage.
8.4.1.1.5. Contour bunds in open area
Earthen bunds constructed along smoothened contours or
with small deviation from the contour are termed as contour
bund. Suitably sized contour bunds have been found very
effective especially on the land with gentle slope. The main
advantage is that long slopes are broken down into smaller
compartments with less slope, thus allowing rainwater more
time or opportunity to soak into the soil in each
compartment. This is suitable for permeable soils as that of
Bharapur area of Gandhidham.
Out of the total area of the plant, there is still 7.2 hectares of
open area which is lying unused and there is no immediate
program of any construction activity. This area will remain
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.28
unutilized and vacant land. It is proposed that surface runoff
of this open alluvial land may be utilized by constructing
contour bunds with a recharge trench. The contour bunds
may be constructed in the slope of the area with a recharge
trench of one metre width and one metre depth filled with
pebbles and gravel. The trench will be unlined and surface
water while on slope will be stopped by the contour bund
and water will enter the recharge trench. The contour bund
will be constructed out the material excavated from trench.
The contour bund will be about 1 metre in height and 1.5
metres in width. The length of contour bund will be decided
according the availability of vacant plot available at the site.
The idea is to get the entire runoff of the slope to come to the
contour bund. The catchment area of the contour bund
should be made dense by road roller and by providing thick
clay plaster so the catchment area develops runoff
coefficient of 50 % of the rainfall against the normal runoff
coefficient of 30 % of alluvial soil.
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.29
Figure 8.11
Contour Bund With Recharge Trench
11.
It is expected that 72000 m2 of catchment area will develop
surface runoff of 16272 m3. This water will be stored in
recharge trench and will percolate down to water table in due
course. It is expected that 75 % of water (12,204 m3) will be
recharged as the soils are sandy and will have high
infiltration rate.
8.5. TOTAL RAIN WATER HARVESTED
With all the rain water harvesting measures proposed to be carried
out in plant, ground water storage will be augmented by 69,109 m3
during a normal rainfall year. The details of water to be recharged
are indicated as under:
Draft EIA Report M/s Shree Renuka Sugar Ltd.
Royal Environment Auditing & Consultancy Service Page |8.30
Sr. No
Structure Recharge Quantity(m3)
A Rooftop rain water harvesting Raw Sugar Warehouse 1 Segment-I 4380
2 Segment-II 8759
3 Segment-III 8759
4 Segment-IV 4380
5 General Store 1054
White Sugar Warehouse 5 Warehouse No.-I 6593
6 Warehouse No.-II 6593
7 Warehouse No.-III 6593
Future White Sugar Warehouse 8 Warehouse No.-I 5744
9 Warehouse No.-II 9985
Total 75 % will be recharged
66,840 50,130
B Surface Runoff 10 Contour Bunds 12,204
Total 62,334
With the recharge of 62,334 m3of water, the water table in the plant area
will rise by 1.02 metres. This is in addition to normal natural ground
water recharge by rainfall in the plant area. The recharged water by
proposed rain water harvesting happens to be 23 % of the total rain
falling within the 61 hectares of the plant area and can be considered as
an efficient utilization for ground water recharge.