From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. ·...

46
SAFER, SMARTER, GREENER DNV GL © Graham Nott 18 October 2018 OIL & GAS From LNG Mega-trains to mid-sized modular units: 1 An exploration of the investment risks in today’s LNG export terminals Graham Nott

Transcript of From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. ·...

Page 1: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018 SAFER, SMARTER, GREENERDNV GL ©

Graham Nott

18 October 2018

OIL & GAS

From LNG Mega-trains to mid-sized modular units:

1

An exploration of the investment risks in today’s LNG export

terminals

Graham Nott

Page 2: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Introduction

2

Page 3: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Some rules of thumb

▪ 1 SCF LNG ~ 600 SCG Natural gas

▪ 1 MMTPA ~ 140 MMSCFD

▪ 1 MMTPA ~ 35 MW

▪ 1 TCF ~ 0.8 MMTPA for 20 years

▪ Liquefaction losses are typically ~ 8% for base load LNG plants

3

Page 4: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Historical background

4

Page 5: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Significant events in the history of natural gas liquefaction

▪ 1959 – First international LNG trade (Lake Charles, LA to Canvey Island, UK) – 5000 m3 LNGC

▪ 1964 – Compagnie Algerienne du Methane Ltd (CAMEL) GL4Z LNG plant at Arzew commissioned and ships

first gas.

– 3 trains of 17,000 BBL/day (3 x 415,000 Tonne/year ~ 2.2 MMTPA)

– Pritchard Cascade process (C3/C2=/C1), steam turbine compressor drivers

– Total investment cost $89 Million, delivered LNG cost $0.76/MMBTU

▪ 1969 – Atlantic Richfield Oil Company (ARCO) Kenai LNG plant commissioned

– 1 train of 1.23 MMTPA

– Predecessor of Conoco Phillips Optimised Cascade Process, built by Bechtel.

– First use of gas turbine compressor drivers (6 x Frame 5)

– Total investment cost $ 200 Million, delivered LNG cost $0.52/MMBTU

▪ 1971 – Exxon Marsa El Brega LNG plant commissioned:

– 4 trains each of 0.8 MMTPA

– First Air Products Single Mixed Refrigerant technology and use of Coil Wound Heat Exchanger

5

Page 6: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Significant events in the history of natural gas liquefaction

▪ 1972 – Brunei LNG (LUMUT) plant commissioned

– Initially 4 x 0.925 MMTPA (3.7 MMTPA) later expanded to 5 x 1.3 MMTPA

– First use of propane pre-cooled mixed refrigerant process (C3-MR)

▪ 1999 – Atlantic LNG Train 1 commissioned

– Strategic move by BG to reintroduce competition

▪ 2005 – SEGAS Damietta Commissioned

– First use of C3SplitMR to balance power between gas turbines and maximise LNG production at 5 MMTPA

– Compressor drivers using 2 x GE 7EA industrial gas turbines

▪ 2006 – Darwin LNG

– First use of Aeroderivative gas turbine technology with 6 x GE LM2500 to achieve 3.7 MMTPA

▪ 2009 – QatarGas II

– First AP-X project using 3 x GE Frame 9 gas turbines to achieve 7.8 MMTPA/train

▪ 2017 – Wheatstone LNG

– First use of LM6000 Aeroderivative gas turbine technology to achieve 4.5 MMTPA

6

Page 7: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Growth in LNG single train capacity

7

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00

Tra

in c

apacity (

MM

TPA)

Train capacity increased

as developers sough

economy of scale

The Qatari AP-X

plants marked the

end of the quest for

ever larger train

capacityMid scale isn’t new;

for a decade a 1 - 2

MMTPA train was

standard

Page 8: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Economy of scale

Advantages Disadvantages

8

▪ Single train, single equipment

▪ Avoids complexity and potential flow mal-distribution

▪ Low equipment count offers less lost time to

equipment failure and risk of loss of containment

▪ A single train can be optimised

▪ Larger equipment becomes increasingly difficult to

transport

▪ Foundations and ground works become increasingly

expensive

▪ Limited pool of suppliers

▪ Equipment becomes bespoke

▪ Time to market

Case 1 Case 2 Case 3 Case 4

Configuration 1 x 5 MMTPA 2 x 2.5 MMTPA 1 x 3 MMTPA 2 x 1.5 MMTPA

Drivers 2 x Frame 7+ 20 MW

4 x Frame 5 2 x Frame 7 3 x Frame 5

Relative LNG Cost 100% 117% 122% 142%

Source - Gastech 2008; LNG TECHNOLOGY FOR THE COMMERCIALLY MINDED – THE NEXT CHAPTER by Charles Durr, Christopher Caswell & Heinz Kotzsot

Page 9: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Construction cost pressures

9

Page 10: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

LNG Plant Cost

10

Source: Oxford Institute for Energy Studies, LNG Plant Cost Escalation by Brian Songhurst

Page 11: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

LNG Plant Costs (influence of infrastructure)

11

Source: Oxford Institute for Energy Studies, LNG Plant Cost Escalation by Brian Songhurst

Page 12: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Market forces

12

Page 13: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Increasing liquidity in LNG markets

13

Page 14: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Recent permitted and planned USA LNG projects

14

Page 15: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Recent approved or operational US LNG projects

15

FERC STATUS Project Name Location Gas flow Phase 1 Phase 2 Licensor Technology

Operation Sabine Pass Liquefaction Sabine Pass, LA 1.40 BCFD 4 x 4.5 MMTPA 1 x 4.5 MMTPA Conono Phillips Optimized Cascade

Operation Dominion Cove Point LNG Calvert County, MD Air Products C3-MR

Construction Southern LNG Elba Island, GA 0.35 BCFD 6 x 0.25 MMTPA 4 x 0.25 MMTPA Shell MMLS

Construction Cameron LNG Hackberry, LA 2.1 BCFD 3 x 5 MMTPA Air Products C3-MR

Construction Freeport LNG Freeport, TX 2.14 BCFD Air Products C3-MR

Construction Cheniere Corpus Christi LNG Stage 1 Corpus Christi, TX 2.14 BCFD 2 x 4.5 MMTPA Conono Phillips Optimized Cascade

Approved Southern Union Lake Charles LNG Lake Charles, LA 2.20 BCFD Air Products C3-MR

Approved Magnolia LNG Lake Charles, LA 1.08 BCFD 4 x 2 MMTPA LNG Limited OSMR

Approved Cameron LNG Hackberry, LA 1.41 BCFD Air Products C3-MR

Approved Exxon Mobil Golden Pass LNG Sabine Pass, LA 2.10 BCFD 3 x 5.5 MMTPA Air Products C3-MR

Source – FERC project list with additional data collated by author from FERC filing and developers websites

Page 16: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Pending and pre-filing US LNG projects

16

FERC STATUS Project Name Location Gas flow Phase 1 Phase 2 Licensor Technology

Pending Gulf LNG Liquefaction Pascagoula, MS 1.5 BCFD 1 x 5 MMTPA 1 x 5 MMTPA

Pending Venture Global Calcasieu Pass Cameron Parish, LA 1.41 BCFD 9 x 1.252 MMTPA GE SMR

Pending Texas LNG Brownsville, TX 0.55 BCFD 1 x 2 MMTPA 1 x 2 MMTPA Air Products

Pending Rio Grande LNG - NextDecade Brownsville, TX 3.6 BCFD 6 x 4.5 MMTPA Air Products C3-MR

Pending Annova LNG Brownsville, TX 0.9 BCFD 6 x 1 MMTPA Black & Veatch PRICO SMR

Pending Port Arthur LNG Port Arthur, TX 1.86 BCFD 2 x 6.75 Air Products C3-MR

Pending Eagle LNG Partners Jacksonville, FL 0.132 BCFD 3 x 0.33 MMTPA Chart IPSMR

Pending Venture Global Plaquemines Plaquemines, LA 3.4 BCFD 9 x 1.252 MMTPA9 x 1.252 MMTPA GE SMR

Pending Driftwood LNG (Tellurian) Calcascieu Parish, LA 4.0 BCFD 11 x 1.38 MMTPA 4 x 1.38 MMTPA Chart IPSMR

Pending Alaska Gasline Nikiski, AK 2.63 BCFD 3 x 6.5 MMTPA 3 x 6.5 MMTPA Air Products C3-MR

Pending Freeport LNg Dev. Freeport, TX 0.72 BCFD Air Products C3-MR

Pending Jordan Cove Coos Bay, OR 1.08 BCFD 5 x 1.56 MMTPA Black & Veatch PRICO SMR

Pending Cheniere Corpus Christi LNG Stage 2 Corpus Christi, TX 1.86 BCFD 1 x 4.5 MMTPA Conono Phillips Optimized Cascade

Pre-filing Commonwealth LNG Cameron Parish, LA 1.18 BCFD 8 x 1.1 MMTPA

Pre-filing Port Fourchon LNG La Fourche Parish, LA 0.65 BCFD

Development Cheniere Corpus Christi LNG Stage 3 Corpus Christi, TX 1.86 BCFD 7 x 1.4 MMTPA

Development Galveston Bay LNG Texas City, TX 3 x 5.5 MMTPA

Source – FERC project list with additional data collated by author from FERC filing and developers websites

Page 17: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Mid-scale LNG technology suppliers

17

Page 18: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Black & Veatch PRICO®

18

Source – Black & Veatch website

Page 19: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

LNG Limited OSMR®

19

Source – LNG Ltd website, 2015 OSMR® Conference Paper

Page 20: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Chart Energy and Chemicals IPSMR® process

20

Source – Gastech 2018. “Benefits of Mid-Scale LNG” by Scott Mossberg (Bechtel) and Douglas Ducote (Chart Energy & Chemicals)

Page 21: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

GE (SALOF)

21

Source – GE publicity materials.

Page 22: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Technical observations

▪ Mid-scale LNG LNG processes tend to:

– Use Brazed Aluminium Heat Exchangers (BAHX) over Coil Wound Heat Exchangers

– Use Aeroderivative over Industrial gas turbines

– Incorporate a higher element of modularisation and pre-assembly

– Use simpler processes with less refrigerant pressure stages

22

Page 23: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Process efficiency

23

Page 24: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Key factors influencing process efficiency

▪ Aeroderivative gas turbine drivers have a higher efficiency

compared to industrial G-T’s

▪ Compressor polytropic efficiency has increased significantly

over the past decades but generally larger compressors have

higher efficiency

▪ Mid scale processes are more simple and do not offer

multiple stages of refrigerant evaporation pressure and

therefore some irreversible work is lost

(i.e. Chart IPSMR 3 stages c.f. COP OCP 3/2/3)

▪ BAHX gives an order of magnitude increase in MCHE area

and therefore allows close temperature approaches

▪ Historically little of the heat in the G-T exhaust has been

captured

▪ Aeroderivative G-T’s are more adversely affected by ambient

temperature than industrial G-T’s

▪ End flash expander

▪ Air recirculation

24

33.3

36.3 36.537.7

41.1 41.243.0

44.1

28.8

36.0

29.4

33.3 33.034.6

Gas turbine efficiency in mechanical drive

Source – GE publicity materials.

Page 25: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Air recirculation and layout

25

Source – UNDERSTANDING OF HOT AIR RECIRCULATION PHENOMENA IN AIR-COOLED BASE LOAD LNG PLANT, Siti Farhana Bt M Shaari Malaysia LNG Sdn Bhd .

Page 26: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Compressor driver

26

Page 27: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Key factors influencing compressor driver selection

▪ Two shaft machines (i.e. Frame 5 and aero-derivatives) allow operating flexibility for compressor

re-start after settle out and allow more shaft power to be used in the process (or more

turndown).

▪ Electric drivers offer high availability but power must be produced somewhere and fuel gas might

be in surplus

– Industry confident that 95 – 100 MWe drivers are feasible (cf large generators)

– Freeport LNG in construction (3 x 5.1 MMTPA each with 3 x 75 MWe drivers)

▪ Aero-derivative G-T’s might be changed out in 2 days compared to 5 days for industrial gas

turbines.

▪ Aero-derivative G-T’s are more sensitive to loss of power at higher ambient temperatures.

27

Page 28: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

G-T inlet air cooling

28

Source: Gastech 2018: Debottlenecking; Getting the Most Out of Your LNG Plant Christopher Ott, Lead Process Engineer, Air Products and Chemicals, Inc.

Page 29: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Availability

29

Page 30: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Key factors influencing plant availability

▪ Gas turbine scheduled inspection and maintenance

▪ Effective heavy ends removal and MCHE tolerance

– Dilemma of lean gas

– Full scrub column v’s pre-cooling section with separator

▪ Common pre-treatment

▪ SIMOPS

▪ Gas nomination and supply

▪ Variable frequency drives and deNOX

30

Page 31: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Darwin LNG

31

Source: AERODERIVATIVE GAS TURBINE DRIVERS FOR THE CONOCOPHILLIPS OPTIMIZED CASCADESM LNG PROCESS— WORLD’S FIRST APPLICATION AND

FUTURE POTENTIAL

Cyrus B. Meher-Homji, PE. Bechtel Corporation

Page 32: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Venture Global Calcasieu Pass LNG

32

Source – NextDecade website

Page 33: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Modularisation

33

Page 34: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Modular LNG plant construction

▪ Example modular LNG plants

– Sakhalin

– North West Shelf Train 5

– Pluto

– Gorgon

– Snohvit

– Yamal

– Curtis Island (Australia)

34

Source – KBR website

Page 35: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Key factors affecting modularisation strategy

▪ Remoteness of site

▪ Competitiveness of local work force

– Costs of establishing camp

▪ Completeness of design

▪ Foundation loads / costs

▪ Seismic v’s transport loads

▪ Structural steel content

35

Source – NextDecade website

Page 36: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Module growth and congestion

On-Shore LNG Plant FLNG

36

▪ Footprint growth of onshore LNG plant reported by

JGC

– Project A – 20%

– Project B – 21%

– Project C – 14%

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

Co

nge

stio

n D

en

sity

(m

/m3)

Module ID

Feed Congestion

Initial Congestion

Final Congestion

Source – DNV GL collected data

Page 37: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

SIMOPS and Safety

37

Page 38: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Key safety considerations

▪ Smaller inventories but greater spill frequencies

▪ Smaller propane surge drum size

▪ Maintenance – lifting over live plant

▪ Construction of adjacent units

▪ Maintain safety gaps and separation (DDT), avoid

growth and congestion

▪ Flare sizing requirements (common failure)

▪ Possibility to reduce setback distance

38

Page 39: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Layout and plot size

39

Page 40: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Mid scale modular LNG claims to be competitive on plot size

40

Conoco Phillips ‘Two in one concept’

Sabine Pass – 78,000 m2 / 4.5 = 17,500 m2/MMTPA

= 6.4 m2/TPD

Air Products C3SplitMR

Damietta – 44,000 m2 / 5.0 = 8,800 m2/MMTPA

= 3.3 m2/TPD

Source – Conoco Phillips publicity materials

Page 41: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Driftwood LNG ‘Four in one’ concept

41

Source – Tellurian website

Page 42: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Economics

42

Page 43: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Key project cost implications

▪ First phase must bear infrastructure costs

– Jetty (>$50,000/m)

– Breakwater / dredging ($100 MM)

– LNG tanks (>$ 90 MM for 200K m3)

▪ Standard equipment and machinery

▪ But potentially faster to market

43

Page 44: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Summary

44

Page 45: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

Summary

▪ Modular mid sized LNG plant is not new

– But there are few reference plants for the ‘new’ technology licensors at this scale

– There are dangers in an over-reliance on modularisation and off-site construction

– The process cycles are not as optimised as ‘classical’ C3MR / Optimised Cascade processes,

however the use of aero-derivative gas turbines and inlet air cooling level the field

– ‘Other’ factors can drive plant availability in the real world

– SIMOPS should be central to the layout and development plan

45

Page 46: From LNG Mega-trains to mid-sized modular units LNG Mega-trains_tcm14... · 2021. 1. 29. · –Compressor drivers using 2 x GE 7EA industrial gas turbines 2006 –Darwin LNG –First

DNV GL © 18 October 2018

SAFER, SMARTER, GREENER

www.dnvgl.com

The trademarks DNV GL®, DNV®, the Horizon Graphic and Det Norske Veritas®

are the properties of companies in the Det Norske Veritas group. All rights reserved.

Thank you for your interest.

46

[email protected]

+44 7805 783889