Fresh Energy's 2013 Power Breakfast | Betsy Engelking: Case Study

9
Geronimo’s Solar Development Process Betsy Engelking September 24, 2013 1

description

The first event of a three-part Solar Opportunities Series, Fresh Energy’s annual Power Breakfast outlined new and exciting solar opportunities for business and property owners. Learn more at fresh-energy.org/solarseries.

Transcript of Fresh Energy's 2013 Power Breakfast | Betsy Engelking: Case Study

Page 1: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Geronimo’s Solar Development Process

Betsy Engelking

September 24, 2013

1

Page 2: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Solar Price Trends

9/24/13 2GERONIMO ENERGY

Page 3: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Overview of Solar Development

• Identify Target Site

• Determine Site Suitability– Site Orientation

– Potential Shading

– Location relative to load/distribution system

• Site Owner Outreach– Self Generation/Lease/Own?

• Determine Interconnection Requirements

• Market Project– Net Meter

– PPA to Utility (or “Buy all/Sell all”)

– Community Solar

9/24/13 3GERONIMO ENERGY

Page 4: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Engineering & Environmental

• Field Work

– Phase I

– Fatal Flaw Analysis

– Wetland delineation

– ALTA survey

• Engineering

– Preliminary Site Plan

– Grading Analysis

– Geotech

• Borings or Pull-Test

9/24/13 4GERONIMO ENERGY

Page 5: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Resource AssessmentsData Sources

• Very different from wind projects!

• Smaller sites, production driven mostly by clouds and latitude.

• Public solar maps, datasets produced by NREL are sufficient.

– Some large projects use met towers, but they are smaller (~8 feet tall) and cheaper.

• Banks may begin to require on-site data as size of investment (and associated level of risk increases.

9/24/13 5GERONIMO ENERGY

Page 6: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Minnesota Solar Energy Standard

Utility Xcel Energy Minnesota Power

Otter Tail Power

Alliant/ Interstate*

2020 Retail Sales Forecast (kWh)

30,872,518,000 10,386,689,633 2,746,000,000 901,264,000

EstimatedExclusions (kWh)

477,943,000 6,664,068,038 91,642,461 12,272,000

Sales subject to Standard (kWh)

30,394,575,000 3,722,621,595 2,654,357,539 888,992,000

1.5% of Sales (kWh/MW**)

455,919,000/346 55,839,324/42.5 39,815,363/30.3 13,334,880/10.2

10% of 1.5% (small solar kWh/MW**)

45,592,000/34.7 5,583,932/4.25 3,981,536/3.0 1,333,488/1.0

9/24/13 6GERONIMO ENERGY

* Alliant/Interstate recently announced the sale of its Minnesota electric systems and customers to a consortium of Southern Minnesota

cooperatives. If the sale is approved, these customers may become exempt from the solar energy standard

** Assuming a 15% solar capacity factor

From Docket E-999/CI-13-542

Page 7: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Aurora Solar Project

• 100 MW Distributed Solar Project– 22 separate sites

– Each site between 2-10 MW

– Interconnected to Xcel Energy distribution substations

• Proposed in Xcel Energy’s Capacity Acquisition Process– Only renewable project in the process

– Competing with several natural gas generators

– PUC decision expected Feb-Mar 2014

• Will provide capacity resource and help meet Xcel Energy’s Solar Energy Standard

9/24/13 7GERONIMO ENERGY

Page 8: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

9/24/13 8GERONIMO ENERGY

Page 9: Fresh Energy's 2013 Power Breakfast |  Betsy Engelking: Case Study

Questions?

Betsy Engelking

[email protected]

(952) 988-9000

1