French Capacity Mechanism « certification process · PDF fileSCHEDULING . Year 2 Year 1...
Transcript of French Capacity Mechanism « certification process · PDF fileSCHEDULING . Year 2 Year 1...
2
1. CONTEXT
2. MARKET PLAYERS
3. DUTIES COMING WITH CERTIFICATION
4. DEMAND SIDE MANAGEMENT
SOMMAIRE
Mechanism of Capacity
Background
4
A major risk to assess
To make Energy transition
succesfull, the electrical system
is faced with many
challenges
CONSUMPTION PEAKS CAN CREATE TENSION ON THE SYSTEM AND UNDERMINE THE SECURITY OF SUPPLY OF FRANCE.
New electricity usages
Development of renewable energy
Gap between the moments where electricity can be produced and those in which it is consumed
Security of Supply =
Ability to deal with winter peaks
5
Engagement of availability from Consumers or
Producers
Obligation of suppliers to acquire guarantees relative
to the consumption in pekas periods
MAIN ISSUE
Capacity market allows to sell the availability or to cover suppliers’ obligation when the electrical system needs it
Reduce Consumption
Buy Guarantees
PP1 PP2
7
Obliged entities
Capacity Operators
Players
Based on the consumption of the
portfolio
ELECTRICITY SUPPLIERS
Based on availability
PRODUCERS
Help consumers to reduce their consumption during
peak times
DEMAND SIDE MANAGEMENT
ACTORS OF THE MECHANISM
Producers Demand Side Operators Consommateurs
Suppliers Consumers Grid operators for the
Network losses
Capacity Operators Production / Demand response
Obliged Entities
RESPONSIBLE OF A PERIMETER OF CERTIFICATION Wheter it is the capacity opertor or any actor who signed a contract with RTE
8
HOW IT WORKS?
LIABILITY OF SUPPLIERS
PRICE OF CAPACITY
LIABILITY OF CAPACITY OPERATORS
Are available. Receive the same levels
of guarantees Obliged to cover thier portfolio
The price of capacity is linked to the security of supply.
Market for Guarantees Forecasted Production/Demand
Responses Forecasted consumption
1 Guarantee
• Renewables
1 Guarantee
• Thermal plants
1 Guarantee
• Demand response
9
GOVERNMENT, REGULATOR AND RTE WILL NOT ACT ON THE MARKET. THEY HAVE A SPECIFIC ROLE OF ORGANIZATION, MONITORING AND CONTROL.
Rôle of RTE Rôle of regulator
CREATE CERTIFICATES
NOTIFY OBLIGATIONS
CHECK THE LEVEL OF ENGAGEMENTS
UPDATE REGISTERS AND MAINTAIN THE
MECHANISM
MONITOR THE MARKET
PUBLISH DATA on transactions, obligations and
certificates
SURROUNDING ACTORS
3 Years at the same time
2015 2016 2017 2019 2018
2020
Certification of existing power plants Certification of coming plants or demand response Obligation (forecasts / real time)
New parameters for delivery year 4 : 2020
10
SCHEDULING
Year 2
Year 1
Year 3
Settlement
Settlement
THE MARKET OF CAPACITY IS NOT REPLACING EXISTING MECHANISMS SUCH AS : BALANCING DEMAND RESPONSE ENERGY SUPPLIES FEED IN TARIFF ANCILLARY SERVICES RESERVES (FRRA, FCR)
THE MECHANISM OF CAPACITY IS DESIGNED AS AN INSURANCE.
11
A NEW MECHANISM
13
1. CERTIFICATION IS A DECLARATIVE PROCESS 2. FIRST, OPERATORS WILL NEED TO LINK WITH A REPONSIBLE OF PORTFOLIO
3. CERTIFICATION ENTITIES (EDC) MAY BE GROUPED
MANDATORY FOR SITES STARTING AT 1 MW minimum of certification : 1 MW minimum of transaction : 0.1 MW (1 guarantee) VALUES WILL BE CHECKED DURING THE WINTER…
WHERE DOES IT START ?
No aggregation possible
Aggregation possible
Aggregation compulsory
Volume of capacity unit (MW)
1 MW
100 MW
CONNECTED TO ONE DSO GRID CONNECTED TO ONE TSO GRID VARIOUS DSO
CERTIFICATION PROCESS
CONTRACT WITH RTE
And
CONTRACTS DSO / Operators
Delivery of certicifaction Level
= NCC of production or
demand response
Registration of Certified capacities
14
? MW
DSO
Request Contract Delivery of Guarantees
Registration
DSO
GRD GRD GRD DSO
CERTIFICATION PROCESS
Historical Certification
Declarative Certification
Volume de garanties calculé par RTE sur l’historique
NCC = Prod [historical] x Cfilière
REQUEST
Declarative Certification
NCC = Pavail [PP2] x Kweek x Kday
REQUEST
15
Flexible Production
Fatal production
Any choice is defined for one year
TWO METHODS
NCC = Pavail [PP2] x Kweek x Kday
16
Real Availability
Imbalances
MARKET OF CAPACITY
Sells
Forecasts
REAL LEVEL OF CAPACITY
CERTIFIED LEVELS
OR Activated Energy
CONTROL OF CERTIFICATION
Operators Production / Demand
Any Guarantee detained by
the RESPONSIBLE Will not be accounted.
17
PP1 PP2
Periods in which the suppliers have to demonstrate their ability to cover the consumption of their portfolio of clients during winter
peaks
Operators are liable to a level of availabitilty for their capacities during periods of stress for the
system (PP2)
Days are scheduled from November to March (Excluding Christmas Periods) starting from 2017
Time frames : 7h – 15h and 18h – 20h
PP2 is longer than PP1 (between 10 to 25 days each year, with the same schedule starting on january to march and novembre to december in 2017)
Planned on day ahead for each day PP1, between 10 et 15 days per year (days of maximum consumption)
performs a posteriori controls on the basis of actual consumption to verify that the supplier has the necessary guarantees for the consumption of their customers
RTE : PP2 will adress also crucial situations for the system that are not linked to peak consumption periods.
« PP1 » AND « PP2 » STARTING FROM 2017
PP1 (MEASUREMENT OF CONSUMPTION) AND PP2 (MEASUREMENT OF AVAILABILITY) PEAK PERIOD PP2 Collection and control MEASUREMENT OF AVAILABILITY ET CONTROL OF CERTIFIED CAPACITIES NUMBER OF DAYS PP2 FOR EACH DELIVERY YEAR : [10 TO 25] EACH PP2 IS MANDATORY A DAY PP1 PP2 DAYS WICH ARE NOT PP1 DAYS WILL BE WARNED BASED ON A CRITERAI OF
TENSION FACED BY THE SYSTEM (DEMAND > OFFER)
18
X X X X X X X X X X X
Exemple (january) PP1 PP2
OPERATORS : PEAK PERIODS PP2
REBALANCING COSTS DEPENDS ON THE DATE OF REQUEST : Penalties will be invoiced with the settlement of imbalances (knowing the total number of PP2). EXCEPT FOR REBALANCING IN CASE OF INCIDENTS DURING DELIVERY YEAR REBALANCING will be « free » but limited to 2 times for each responsible and each year.
Only certification costs will be applied (due to change of certified volumes)
Year of delivery Y-1 Y-2 Y-3 Y-4 Y+2
Costs of (new) certification Costs of (new) certification
+ Penalties related to the number of PP2 already
scheduled and total PP2 numbers
Y+1
15/01
19
Certification
REBALANCING OF CAPACITY
1 : UPWARD
Transfer to RTE of the refunded volume
2 : DOWNWARD
Adding guarantees to the market
Removal of capacities from the market
20
New capacities will be delivered to operators
Register of
Certified capacities
OPERATOR
ISSUANCE
MW
RESPONSIBLE OF
PORTFOLIO
Refund
MW
MARCHÉ DE CAPACITÉ
TWO CASES OF REBALANCING
MARCHÉ DE CAPACITÉ
Global rebalancing in the portfolio is affordable. Controls will still be adressed by each site
…
Control on energy
3 TYPES OF CONTROL ARE POSSIBLE :
- BY THE ENERGY ACTIVATED : Check of produced energy during PP2
- BY AUDITS : on records or on the site, between the date of entry into force of the contract for certification and the end of the year of delivery
- BY TESTS D’ACTIVATION from 0 to 3 tests
Each Capacity Entity has to be activated at least one for each year.
Control and collection of DATA 21
AUDITS
Needed tests
COLLECTION ET CONTROL
DSO
Year of delivery Y-1 Y-2 Y-3 Y-4 Y+2
22
MANAGEMENT FEES
Certification Costs 10 €/MW (RTE) or DSO
Yearly fees for access to the register 1000 €/year
Transaction fees paid by the buyer
(rebalancing and first transfer to the RPC are excluded)
Audit and control costs on demand
Rebalancing costs free before delivery year
Yearly fees for access to the register 1000 €/year
Transaction fees 1 € / guarantee (with limitation)
Fees to calculate the level of consumption 4 €/MW (RTE) + DSO
Suppliers
Operators Production / Demand response
The price of settlement of imbalances is an incentive to favour the market.
The administered price cannot exceed 40 k€ / MW
23
Two separated Imbalances
• Obliged Actor : Notified volume of obligation – guarantees in the portfolio
• Certified responsible : Real level of capacity – certified level of capacity
Reference Price of Market
Administered price
- 2 GW 0
HOW ARE IMBALANCES CALCULATED ?
Global Imbalances
Two prices to be defined
25
Flexible Consumer
Reduce (the consumption)
The level of obligation
Certification of Load
capacity
Activated during peak period : PP1 Need to activate the energy to reduce directly the consumption
Available during peak period : PP2 Need to be available Not mandatory to be activated
1
2
OU
A CHOICE HAS TO BE MADE
Suppliers
Operators Production / Demand Reponse
EXEMPLE OF CERTIFICATION
26
18 MW
Consumer Available
Consumer Activated
x0,93
x0,93
20
20 18
MW 10 MW
10 MW
Or
In case of activation, energy will be compensated.
No demand response activated
Operators Production / Demand Reponse
Rules Contracts Practical guide Registers
HOTLINE CAPACITY MECHANISM phone : +33 1 41 66 71 03
mail : [email protected]
FURTHER DETAILS
28
http://clients.rte-france.com/lang/an/clients_traders_fournisseurs/services_clients/dispositif_mecapa.jsp