FRENCH CAPACITY MARKET - RTE France · FRENCH CAPACITY MARKET ... the mechanism can be operational...
Transcript of FRENCH CAPACITY MARKET - RTE France · FRENCH CAPACITY MARKET ... the mechanism can be operational...
FRENCH CAPACITY MARKET Report accompanying the draft rules
RTE Réseau de transport d’électricité SA shall not be liable for damages of any nature, direct or indirect, arising from the use of data and information contained in this document, including any operational, financial or commercial losses.
APRIL 9 2014
FRENCH CAPACITY MARKET Report accompanying
the draft rules
4
SUMMARY
The principle: A mechanism to ensure security of supply
French law 2010-1488 of 7 December 2010 reforming the
organi sation of the electricity market (NOME Act), codified in arti-
cles L. 335-1 et seq. of the Energy Code, calls for the creation
of a capacity obligation scheme. It specifies that “each supplier
contributes, in accordance with the demand characteristics of its
customers, in terms of power and energy, to the security of elec-
tricity supply in continental France.”
Decree 2012-1405 of 14 December 2012 defines the general
organisational framework for the new scheme.
Obligations will be assigned to suppliers based on the actual
consumption of their customers during peak periods. To meet
its obligation, a supplier will have to secure capacity certifi-
cates, either by certifying the capacities it operates (generation
or demand-side capacities) or by purchasing certificates from
players that hold them. Individual obligations, defined based on
parameters established four years before the target delivery year,
will be updated to reflect the effective consumption data meas-
ured within the supplier's portfolio.
Capacity certificates will initially be issued by RTE to opera-
tors based on the projected contribution of their capacities to
reducing the shortfall risk during peak periods. Generators must
request certification for their capacities at least three years before
the target delivery year, while demand-side operators can submit
requests up until the start of the same delivery year. Availability
levels indicated in requests are compared with effective availabil-
ity and settlements are calculated to reflect imbalances.
The provisions proposed define a new market mechanism, regu-
lated by public authorities, through which holders of certificates
can trade them with obligated parties to enable the latter to meet
a legal obligation.
This mechanism is intended to provide a form of “insurance”:
operators are rewarded for the contributions their capacities
make to the power system by being available during periods of
tight supply. Starting four years before the delivery period, the
mechanism will generate economic signals complementing
those generated by the energy market.
The decree includes a detailed explanation of the principles to be
applied in certifying operators’ capacities, allocating obligations
to suppliers and organising capacity certificate trading along with
the related transparency mechanisms.
The principles outlined in the decree must be further refined so
the mechanism can be operational in time for the 2016-2017
winter period. This is the purpose of the rules, contracts and
agreements submitted by RTE on 9 April 2014, in accordance
with the responsibilities assigned to it in the decree, for approval
by the Minister and the opinion of the Energy Regulatory Com-
mission (Commission de régulation de l’énergie – CRE).
* * *
France will have to surmount major challenges to successfully man-
age its energy transition. Gone are the days when society could count
on abundant non-renewable sources: it must now find more efficient
and environmentally sound modes of production, transport and
consumption. This will require using less energy, optimising produc-
tion systems and making greater use of renewable energy sources.
As it stands, France boasts a competitive and low-carbon power
industry mainly because of energy choices made in the 1970s and
1980s (development of hydro- and nuclear power, increased use of
electricity through the promotion of electric heating, enhancement
of France’s energy independence). These choices helped make the
country more energy independent and competitive, and reduced
its carbon footprint, but they have also given rise to a particularly
intense peak demand phenomenon. In recent years, though growth
in average consumption (in energy terms) has slowed, peak power
demand has continued to trend sharply higher.
5
SUMMARY
The French capacity mechanism was designed to address this
issue by modifying consumption behaviour during peak peri-
ods (demand-based approach) while encouraging adequate
investment in generation and demand response capacities
(supply-based approach), at a time when energy markets’ abil-
ity to stimulate such investments was being questioned in
much of Europe.
Peak demand is not a problem in and of itself, if it is managed
in an economical and environmentally sound way without put-
ting security of supply at risk. And managing it efficiently is all the
more important since the decarbonisation policies implemented
to reach the climate targets set by the European Council in 2009
and adopted in the Commission's 2050 Energy Roadmap could
result in even greater use of electricity, for instance to power a
growing fleet of electric vehicles, meaning the peak demand phe-
nomenon could become permanent.
Against this backdrop, demand response can and must play
a central role. Though the capacity mechanism proposed is
technology-neutral and does not structurally favour any one
resource over another, it does make it possible to recognise the
capacities that actually serve security of supply needs, which load
curve management efforts clearly do. The specific procedures
proposed for demand response (flexible certification up until the
start of the delivery year, option to aggregate independently of
location or suppliers with which sites are affiliated) will facilitate its
integration. Generally speaking, the market design choices made
for France factor in demand response as a structural solution to
the capacity adequacy problem.
Introducing a capacity mechanism in France supports public
authorities’ objective of making the load curve more flexible, set
forth in Law 2013-415 of 15 April 2013 (“Brottes Act”). It is by no
means intended as an alternative to or substitute for the develop-
ment of demand response capacity: on the contrary, the capac-
ity obligation marks the final step in a four-year effort to open
all market mechanisms to demand response and allow it to par-
ticipate directly in energy markets. Over the coming months, RTE
will complete the process by removing the last technical barriers
to aggregation, consolidating France's position as the European
leader when it comes to leveraging demand response to the
extent permitted by the economic fundamentals of the sector.
A changing energy mix also is also creating greater need for flex-
ibility, notably on the demand side, due to the growing penetra-
tion of variable generation. The central risk factor for the French
power system could thus gradually evolve. Going forward, the
capacity mechanism will be able to shift from an exclusive
focus on national peak demand to an approach that ensures
adequate flexibility in a system characterised by increasing
intermittent energy penetration.
A new capacity mechanism cannot be implemented without
first carefully analysing the shortcomings of the existing market
model. In its Communication of 5 November 2013 on public
intervention in the electricity market, the European Commission
stressed that the first steps should be to analyse the causes of
generation inadequacy and to assess the impact of any measures
proposed.
Thanks in part to the introduction of coupling mechanisms that
help optimise and increase energy exchanges between countries
across Europe, the existing market model has definitely produced
results in terms of optimising electricity generation and flows
in the short term. That being said, market stakeholders, Mem-
ber States and academics are increasingly questioning whether
the model can ensure security of supply over the long term by
efficiently regulating investments in supply- and demand-side
capacity. Indeed, a theoretical analysis of how electricity markets
function highlights a certain number of shortcomings in the so-
called “energy-only” market when it comes to guaranteeing fair
remuneration of the capacities required to balance supply and
demand on the system during peak periods.
Security of supply is a public good. If it cannot be delivered – at
least over the medium term – through the individual gratifica-
tion of private preferences, then the desired level of security of
supply must be defined by public authorities. In the absence of
a specific mechanism, there is no reason why the energy market
alone, even one that functions perfectly, would be able to achieve
the target level, as positive externalities would not be internalised.
Concerns about the functioning of electricity markets have a
special resonance in France due to the specific characteristics
of its power sector and notably the peak demand phenomenon
observed. The Poignant-Sido report of 2010 on peak demand
* * *
* * *
6
management notably underscored the electricity market's inabil-
ity, in its current form, to generate the right economic signals to
stimulate the investments necessary to guarantee that adequate
levels of supply- or demand-side capacity will be installed and
available during peak periods. And concerns have increased since
the report was published, as evidenced by the recent study on the
crisis in European electricity markets conducted by the General
Commission for Strategy and Economic Foresight for the Prime
Minister. Similar doubts have been raised elsewhere in Europe
and brought to the attention of the European Commission.
Two examples illustrate the challenges at hand.
The first relates to generation capacity. The steep investments
made in combined-cycled gas turbine plants in Europe between
2004 and 2012 created a paradox: A combination of slower
demand growth and the massive development of renewable
sources resulted in a temporary situation of excess capacity that
market stakeholders failed to anticipate. It could be corrected by
taking a large number of unprofitable assets offline, but this could
suddenly put security of supply at risk, and there might not be
enough power immediately available if weather conditions were
particularly unfavourable for variable generation. An adjustment
involving the closure of new and efficient facilities with low green-
house gas emissions would in theory go against the objectives
set forth in European guidelines.
The second relates to demand response. Though load modu-
lation efforts appear vital to the power systems of the future,
analyses show that they can only continue if their contribution
to security of supply is adequately remunerated. The capacity
mechanism does not by any means seek to lock in generation
capacity’s share in the mix, but instead supports policies that pro-
mote the development of demand response.
Addressing these issues requires carefully reviewing the archi-
tecture of the French electricity market while preserving the
benefits of European energy integration. The adoption of the
capacity mechanism will not result in less attention being paid
to the other structural changes under way, such as the integra-
tion of energy markets across all borders and time horizons, the
development of cross-border interconnections, the inclusion of
demand in all market mechanisms and the overhaul of renewable
energy support mechanisms. It will merely complement these
developments.
A number of European countries have already taken similar
approaches (Sweden, Finland, Ireland, Spain and Italy), are in the
process of doing so (United Kingdom, Belgium) or are considering
capacity mechanisms (Germany). These national mechanisms may
differ in their intent and form, but share common characteristics.
French Decree 2012-1405 of 14 December 2012 established
three fundamental principles to be applied in defining the
architecture of the capacity mechanism. It must (i) be a market
mechanism (market-based) based on volumes (quantity-based),
(ii) applying to all capacity (market-wide), and (iii) involving the
assignment of individual obligations that can be met by acquir-
ing certificates from a third party. Lawmakers thus opted for a
decentralised mechanism as opposed to a single buyer system.
These principles lay the groundwork for a mechanism adapted
to the specific characteristics of and issues faced by the French
market.
A market mechanism can achieve economic efficiency by allow-
ing obligated parties to engage in trading to minimise the cost of
their capacity obligation. A market-wide mechanism was chosen
to provide effective guarantees in terms of security of supply and
ensure that the effects of the mechanism are proportionate to
the objective pursued.
Conversely, a targeted mechanism such as a strategic reserve
would, in France's case, have to be regulated in such a way as
to address low-probability, high-impact events, such as one-in-
ten-year cold spells, since demand in France is highly tempera-
ture sensitive (a 1°C drop in the temperature during peak winter
periods generates 2,400 MW of additional demand). This type of
mechanism would end up removing a large portion of market
capacities (several GWs) and result in significant distortion.
In a word, the French capacity mechanism preserves the struc-
ture of accountability energy market stakeholders are accus-
tomed to and avoids having public authorities make decisions on
their behalf.
* * *
* * *
7
SUMMARY
These principles were applied in the decree in such a way as to
create a mechanism that allows market stakeholders to trade
capacity certificates so the security of supply target can be met
at the least possible cost.
Electricity suppliers' capacity obligations reflect the contribution of
their customers to the shortfall risk, notably their consumption during
the so-called “PP1” peak period and their temperature sensitivity.
Capacity certificates are issued to capacity operators based on
their contribution to reducing the shortfall risk. The certificates
reflect the availability of their capacities during the “PP2” peak
period and the technical characteristics of their capacities (for
instance energy constraints).
An effort was made to ensure that the mechanism would gen-
erate precise signals (obligation and certification levels should
accurately translate contributions to increasing and reducing the
shortfall risk) while also providing stability over time. Three deci-
sions reflect how this balance is achieved:
(i) Capacity is considered to contribute to reducing the shortfall
risk when its availability is effective and attested;
(ii) Commitments to make capacity available are proportionate to
the benefits for the system, meaning they are targeted to short
periods when demand is highest;
(iii) Fulfilment of participants' commitments and obligations is
verified based on measured data and observed availability. Due to
the specific characteristics of variable energy sources, their effec-
tive capacity levels can be calculated using an alternative system
based on a normative approach.
The mechanism proposed for France will thus allow consum-
ers and suppliers to manage the risk represented by capacity
obligations by leveraging their demand response potential
during peak periods. This means the capacity mechanism will
have a very different impact on highly temperature sensitive
consumers that absolutely cannot adjust their consumption and
consumers that can shed load during peak periods.
For the mechanism to be economically efficient, the capacity
certificate “product” must be clearly defined, related transactions
costs must be low, and it must be possible to trade certificates
under good conditions.
To this end, the framework governing the market's functioning was
defined in such a way as to facilitate trading and to give stakehold-
ers confidence in the capacity certificate product. The mechanism
parameters will be published four years before the delivery year
and stabilised over the duration of each term, meaning trading can
be carried out within a stable framework with players knowing that
the value of the product will not be modified because of interven-
tion from outside the market. RTE will keep a register to ensure that
capacity certificates can be traced and therefore that the product
is credible.
Various measures will give capacity market stakeholders all infor-
mation available about the security of supply outlook. Not only
can they consult the Adequacy Forecast Reports prepared by
RTE, but the data contained in two registers kept by RTE (certified
capacities and peak demand-side management registers) will
also be made public.
The final pillar required for the capacity certificate market to func-
tion properly is competition, and this is undoubtedly the aspect
that has generated the most concerns about the mechanism,
both in France and at the European level. Special attention was
paid to this issue. Through control and market monitoring proce-
dures, the regulator will be able to detect any abuse or manipula-
tion by market stakeholders and track all trades. This transpar-
ency measure is similar to the ones applied in the energy market,
notably at the European level with the REMIT and Transparency
regulations.
It should be noted that an analysis taking into account the decen-
tralised structure of the market and based on the net positions
of stakeholders gives a different picture of the real competi-
tive landscape. The fact that alternative suppliers benefit from
the capacity certificates associated with ARENH rights goes a
long way toward reducing market concentration by creating
* * *
8
upstream-downstream integration effects. The results will also
depend on the terms set by CRE and the Minister for transfers of
certificates associated with the ARENH mechanism.
In response to market stakeholders’ requests to have a compre-
hensive view of the mechanism's impact, RTE provided estimates
in September 2013 of the financial consequences for some cat-
egories of consumer. Its simulations are included and expanded
upon in the present report and used to present analyses of the
“first-round effects” of the implementation:
> The transfer to alternative suppliers of the capacity value asso-
ciated with ARENH rights will significantly reduce implemen-
tation costs for consumers. Costs will notably be very low for
electro-intensive users;
> Taking into account consumers' flexibility substantially modi-
fies the results: a consumer that sheds load during peak
periods can generate direct financial gains through the
mechanism;
> The real impact on consumers will depend on the rates sup-
pliers offer in a competitive environment: they will be able to
move away from regulated tariffs in setting rates for small con-
sumers, and will take into account any capacity they operate,
their commercial strategies, etc.
The points discussed in this report must be further developed.
It will now be possible to conduct more comprehensive stud-
ies, based on accurate models directly taking into account the
rules, to show the dynamic impact of the capacity mechanism on
investment and security of supply. These studies will be carried
out within the framework outlined in the decree and serve as a
basis for subsequent revisions of the mechanism.
The rules and functioning of the capacity mechanism must be evalu-
ated from a European perspective. In theory, security of supply falls
within the purview of EU Member States' energy policies, but there
is in practice significant interplay between Member States’ policies
in the integrated market. This is why the European Commission has
expressed reservations about the introduction of capacity mecha-
nisms in numerous Member States, underscoring the risk this poses
to the functioning of the internal market. The framework for analys-
ing public interventions to safeguard security of supply was recently
expanded to include the recommendations in the European Com-
mission’s Communication “Delivering the internal electricity market
and making the most of public intervention”.
An analysis of the French capacity mechanism based on the
European Commission’s guidelines shows that it complies with
EU law, meets the criteria of necessity and proportionality and is
compatible with recommendations on public intervention in the
area of security of supply.
There is nonetheless one outstanding issue relating to the inclu-
sion in the mechanism of cross-border capacity, which under the
terms of Decree 2012-1405 of 14 December 2012 is initially to
be taken into account implicitly, through a reduction of suppliers'
obligations. Both the European Commission and the Agency for
the Cooperation of Energy Regulators support the explicit inclu-
sion of cross-border capacity in capacity mechanisms, but recog-
nise the difficulties this will entail.
To comply with European expectations, RTE proposes in this report
a roadmap showing the steps to be taken to enable the explicit
participation of foreign capacity in the mechanism. This two-phase
approach is compatible with the recommendations of the European
Commission, which considers that implicit recognition of the con-
tribution of foreign capacity can be a temporary solution. RTE also
provides initial insight into how it will be possible to enable foreign
capacity to participate explicitly in the French capacity mechanism:
> Without harmonising security of supply criteria across Mem-
ber States, but rather upholding the division of competences
defined in the Treaty of Lisbon;
> Without reserving interconnector capacity;
> Within volume limits reflecting the physical limitations of import
capacity during peak periods;
> Subject to the creation of a mechanism for cross-border certi-
fication or control;
> Subject to the signature of agreements to govern operational
management in crisis situations.
These conditions imply significant regional coordination, so it
makes sense to start with an interim phase. One idea would
be to allow the explicit participation of foreign capacities in the
capacity mechanism subject to their inclusion in France's balanc-
ing mechanism. The length and scope of the phase could vary,
depending in part on the work conducted under the aegis of
Member States, and a principle of reciprocity could be applied.
Based on the roadmap proposed and the measures provided for
* * *
* * *
9
SUMMARY
The rules: Choices proportional to objectives will limit the cost to consumers
Peak periods under the mechanism
The days constituting peak periods are not determined ahead
of time but rather indicated one day ahead by RTE. For each
peak day, the time slots considered are from 7am to 3pm and
from 6pm to 8pm, or ten hours per day. The fact that RTE will
notify participants of peak periods a day ahead of time gives
them the visibility they requested during the consultation and
ensures that they have a real incentive to keep peak demand
in check, since their obligations are reduced accordingly. Peak
days will in all cases fall within the [January-March; November-
December] period.
The rules provide for targeted and short peak periods:
> For obligations, the PP1 period corresponds to a period of between
ten and 15 days, encouraging flexibility on the demand side;
> For certification, between 10 and 25 PP2 days will be notified.
This solution makes operators accountable for the availability of
their capacities at times when security of supply is truly at risk.
It also ensures consistency between contributions to reduc-
ing the shortfall risk and the number of certificates allocated,
including for capacities that are only available for short periods
such as peak generation and demand response capacities.
Time periods defined for the mechanism
Delivery year
The delivery year will correspond to a calendar year effective
the second year the mechanism is in place. This will notably
create consistency between the capacity mechanism and the
existing calendar of the energy market and fit better with con-
tractual practices in Europe to facilitate integration going forward.
In accordance with the terms of the decree, the first delivery year
will begin on 1 November 2016 and end on 31 December 2017,
with the months of July and August 2017 excluded.
The rules include specific provisions applicable to the first two
delivery years:
> Specific dates for the first delivery year (from 1 November 2016
to 31 December 2017, excluding July and August);
> A shorter gap between the start of the mechanism term and
the delivery year. The rules define the mechanism parameters
for these two years. Deadlines for certification requests have
been modified accordingly.
in the decree, RTE is prepared to launch a ten-month consulta-
tion to find a concrete solution for allowing the explicit participa-
tion of capacity situated outside France in the mechanism, in line
with the terms of the decree. The principles to be applied to the
consultation and related deadlines are set forth in the rules.
Transposing such a change into regulations would require
an amendment of the decree of December 2012. RTE is thus
requesting that the Energy Minister specify the mandate for this
next consultation phase when the draft rules are examined by the
administration and Energy Regulatory Commission.
* * *
10
Principles applied in calculating obligationsSuppliers' obligations are calculated based on the contribution of their
customers to the shortfall risk, which, in the current market environ-
ment in France, only applies to peak periods. Peak demand is thus rep-
resentative of the risk generated, such that a consumer that does
not consume power during peak periods has no capacity obligation.
Calculation of the obligation
Capacity obligations are calculated as follows:
> Parameters published by RTE: securityF and extremeT
> Data measured and/or calculated:
ConsumpSupplier, Pcertifieddemandresponseactivated, GradientSupplier, ActualT
Calculation of reference power by type of consumer
The calculation of reference power is segmented by type of con-
sumer: profiled, remotely metered, and reference power for the
supply of losses.
Each is calculated based on underlying consumption observed,
adjusting for the temperature sensitivity of obligated parties and
the load reduction for certified demand response capacity acti-
vated during PP1 hours.
Estimation of the gradient
To reflect the effective contribution of consumers to the shortfall
risk, gradients are established for each category of consumption
to prevent transfers between participants (from temperature-
sensitive to non-temperature-sensitive users, or from profiled to
remotely read users). RTE proposes that gradients for each obli-
gated party and type of consumer be used1, based on approxi-
mations that already exist and are not specific to the capacity
mechanism:
ObligationSupplier = securityF x [ ]ConsumpSupplier + Pcertifieddemandresponseactivated
+ GradientSupplier x (extremeT - ActualT)
> The gradient applied to non-temperature sensitive consum-
ers is nil. This category includes users connected to the pub-
lic transmission grid and public distribution grid with average
annual power exceeding 175kW;
> The gradient for profiled consumers corresponds to their
profile, with a measure introduced to stabilise the evolution
of the overall gradient from one year to the next: the over-
all gradient for profiled consumers is extrapolated in a linear
manner from previous years, and a scaling factor is applied to
bring the sum of the individual gradients back to this overall
gradient;
> The gradient for remotely metered consumers is calcu-
lated for each supplier based on the sum of all consump-
tion observed. This approach allows each supplier to be held
responsible individually for the real needs of its customers.
Obligation parameters
The parameters for calculating the obligation are determined
four years ahead of time. This allows obligated parties to estimate
the amount of their obligation and take any necessary demand
management actions based on their forecasts.
Security factor
The security factor reflects the margins required to cover residual
contingencies, notably on the demand side (excluding tempera-
ture sensitivity), as well as the contribution of interconnections
to security of supply. For the first delivery year, RTE proposes a
security factor of 0.93.
Extreme temperature
Since the capacity mechanism is designed to be a sort of “insur-
ance policy”, the obligation is calculated as if one-in-ten-year
cold conditions occurred every year. When the mechanism is first
implemented, the extreme temperature will be a series speci-
fied in the rules, with an average value of close to -2.6°C.
Principles applied to certification
Calculation of the capacity level
Generic certification principles
The certification method proposed in the rules involves:
> Certifying capacity based on data provided by capacity
operators;
> Measuring effective capacity levels based on controls during
the deliver year;
> Addressing, through settlements, differences observed
between certified and effective capacity levels.
For controllable capacities, effective capacity levels are esta-
blished based on information gathered during the delivery year
in question and verified after the fact.
* * *
11
SUMMARY
This structure will, by its nature, give operators incentives to
rebalance as quickly as possible, once they observe any discrep-
ancy between effective capacity levels and the levels they have
certified.
A degree of flexibility has been introduced to limit the cost
of rebalancing in the case of unforeseeable events affecting
capacities (generation or demand response). The procedure
applied in such instances (two zero-cost rebalancing “tickets”
issued to each capacity portfolio manager) is designed to pre-
serve incentives to submit the best availability estimates ahead
of time.
Verification of capacities
Capacity is certified based on self-declared data submitted by
operators, so certification must necessarily be backed by effi-
cient data collection and verification measures.
Operators of intermittent capacities can choose between the
generic framework applicable to all capacities and one that
neutralises the risks associated solely with the primary energy
source, applying in this case the contribution factor calcu-
lated for each type of generation. This factor reflects the cor-
relation between contingencies associated with variability and
shortfall risk situations, in such a way that the certified capacity
level reflects the technologies1 average contribution to reducing
the shortfall risk2. The availability of this option makes it possi-
ble for operators that want to hedge the variability of their capa-
cities (notably by associating them with flexible capacities – for
instance storage or demand response) to reap the full benefits
of such hedging.
Certification procedures
Different certification procedures will apply to different types of
capacity:
> Existing generation capacities must request certification three
years before the start of the delivery year;
> Planned generation capacities that will be connected to the
grid can request certification once the first payment is made
under the connection agreement, up until two months before
the start of the delivery period;
> Demand response capacities can be certified up until two
months before the delivery period begins.
Setting the deadline for existing generation capac-
ities three years before the start of the delivery
year is crucial to give market stakeholders infor-
mation about the outlook for the system and for
the capacity market to generate economic signals
far enough ahead of time to allow enough capaci-
ties to be developed to meet the security of supply
criterion.
The fact that planned capacities can request cer-
tification closer to the start of the delivery period
makes it possible for all capacities to participate,
notably demand response and other capacities that
can be developed more quickly.
Capacity rebalancing
Rebalancing ensures consistency between the market and the
physical system up until the end of the delivery period. With
the rebalancing procedure proposed by RTE, an operator whose
capacity level is affected by a contingency can submit a rebalanc-
ing request:
> At no cost up until the start of the delivery period;
> The rebalancing cost will then increase gradually over the
course of the delivery period, based on the number of PP2 day
notifications, to incentivise operators to submit their best esti-
mates of the expected performance of their capacities.
The principle applied is that all certified capacity must be acti-
vated at least once a year. For verification to be efficient and pro-
portional, it must whenever possible be an extension of existing
measures, notably the balancing mechanism. Barriers to integra-
tion must be reduced: To this end, flexible aggregation rules will
be applied as soon as the mechanism is in place to allow for the
creation of certification entities, with coherent verification meas-
ures applied at the same level of aggregation, notably for demand
response capacity.
In more specific terms:
> Under the generic verification system, controls focus on quanti-
ties injected for generation capacities and actual activation for
demand response capacities, relying on the procedures for veri-
fying the activation of demand response capacities and on injec-
tion data for each capacity;
1 Concretely, the sum of the gradients of profiled consumers must correspond to the temperature sensitivity of profiled users taken as a whole, no more and no less. This segmentation makes it possible to envisage different approaches for each category of consumption. 2 The value of this factor will depend (i) on the capacity considered, (ii) on the volume of variable capacity already in the system, and, more generally, (iii) on the power system in which the capacity is considered.
* * *
12
> The audit-based verification procedure is used to confirm that
data declared by operators and gathered reflect the real perfor-
mance of the capacities;
> The activation test-based verification procedure complements
market-based activation and is designed to guarantee that all
capacities have been activated at least once. The idea is to con-
duct random tests for each capacity, with no prior notice to the
operator. Capacities cannot be tested more than three times
per delivery period.
Principles of the imbalance settlement
Unit price of the settlement
To limit arbitrage possibilities and generate the right incentives,
the settlements of obligated parties and capacity portfolio
managers are calculated using the same unit price.
RTE is proposing a two-part settlement system:
> When security of supply is not at risk, the settlement price will
be based exclusively on the market price. An incentive coef-
ficient will still be necessary to ensure that stakeholders have
incentives to operate through the market rather than wait for
a settlement;
> When security of supply is at risk, the imbalance settlement will
be based on an administered price. This price, which by defi-
nition defines the maximum value capacity can reach on the
market, plays a central role in encouraging investment in new
capacities. It is set based on the annualised cost of reference
peak capacity and published four years before the delivery year
by the Energy Regulatory Commission.
Indicator used to determine whether security
of supply is at risk
At the end of the peak period, RTE calculates the overall imbal-
ance observed, which corresponds to the algebraic difference
between total effective capacity and total effective obligations.
This overall imbalance reflects the physical tension between
effective obligation and capacity levels. The market is thus
informed of any uncertainty arising on either side and capacity
adjustment measures can be taken. Calculating the overall imbal-
ance also prevents a form of market manipulation wherein opera-
tors could certify too much (or too little) capacity to influence the
market price.
It is also necessary to define a threshold value for the overall
imbalance, above which security of supply is considered to be at
risk. This value corresponds to the so-called imbalance limit.
An imbalance limit of 2 GW ensures that a switch from the mar-
ket price to the administered price will only occur when secu-
rity of supply is at risk, and will not be based on the occurrence
of short-term risks.
Inclusion of cross-border capacity
The rules call for the contribution of interconnections to be
accounted for as a whole. The security factor takes into account
projected contributions during peak periods, reducing the obliga-
tion of each supplier accordingly.
To leave time to discuss the roadmap presented in this report and
propose concrete solutions for the explicit participation of cross-
border capacity, the rules stipulate that RTE will submit a report
on the explicit inclusion of cross-border capacity ten months
after the rules are published, potentially proposing at that time
changes to the regulatory framework. This provision complies
with the decree, article 20 of which calls for the system allow-
ing the participation of cross-border capacity to evolve based on
reports prepared by RTE and CRE. This consultation will be con-
ducted under the terms of a mandate issued by the Minister.
Analysis of the dynamic impact of the mechanism
The rules call for RTE to conduct studies on the dynamic impact
of the mechanism, in accordance with the principles set forth in
this report. The results of these studies will be included in a report
on how France's interconnection with other European markets is
to be taken into account going forward, and on ways to improve
the functioning of the capacity mechanism. RTE will submit the
results of its work to CRE and the Minister, and also share them
with market stakeholders.
13
SUMMARY
FOREWORD
French law 2010-1488 of 7 December 2010 reforming the
organisation of the electricity market calls for the creation
of a capacity mechanism in France. Decree 2012-1405 of 14
December 2012 stipulates that RTE is to propose rules for the
capacity mechanism, specifying exactly how it will function.
This was the subject of RTE's submission to the Energy Regula-
tory Commission and Energy Minister on 9 April 2014.
Originally referred to in the Poignant-Sido report of 2010, the
capacity mechanism is intended as a solution to the particu-
larly pronounced peak demand phenomenon observed in the
French power system. It is seen as a way to modify consump-
tion behaviours during peak periods (demand-based approach)
while also encouraging adequate investment in generation
and demand-side capacities (supply-based approach).
It is being designed during a period of energy transition in
France, a process that underscores the need for tools that
can allow new public policies to be implemented efficiently
so targets can be met at the lowest possible cost. The capac-
ity mechanism can act as a communication channel between
policy objectives and the market and allow the power system
to adapt to keep up with adequacy needs.
The present report accompanies the draft capacity mecha-
nism rules RTE submitted to the Energy Minister and Energy
Regulatory Commission, following the consultation organised
in 2013. It introduces proposals made by RTE and situates
them within the context of previous discussions on security of
supply and capacity mechanisms.
This report is divided into ten chapters. Chapter 1 outlines the
justifications for the implementation of a mechanism focusing
on security of supply, based on an analysis of the theoretical
economic framework and observation of the actual function-
ing of energy markets. Chapter 2 describes how key choices
were made about the capacity mechanism design, while chap-
ter 3 discusses the provisions set forth in Decree 2012-1405
and the main decisions made in the capacity mechanism
rules to ensure that the mechanism effectively contributes
to security of supply. Chapters 4 through 6 describe the fun-
damentals of the proposed mechanism including the main
procedures for calculating capacity obligations, capacity certi-
fications and settlements. The procedures proposed to ensure
that the capacity market is transparent and that competition
within it will be free and undistorted are presented in chapter
7. Chapter 8 includes an assessment of the impact the capac-
ity mechanism will have on different categories of consumer.
In chapter 9, readers will find an overview of the discussions
held at the European level about the participation of foreign
capacity in capacity mechanisms and a presentation of the
options selected in the rules, along with an outline of possi-
ble modifications. Chapter 10 provides data supporting the
French capacity mechanism's compatibility with the provisions
of European law.
14
1. WHYACAPACITYMECHANISMIS NECESSARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
1.1 Theoretical evidence of imperfections in energy markets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
1.1.1 Optimal functioning of energy markets within the theoretical framework of the “energy-only” market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181.1.2 Questioning the energy-only market’s ability to guarantee the optimal level of investment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 201.1.3 Failures of the energy-only market in the presence of externalities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 221.1.4 Imperfections of the energy market in terms of managing investment dynamics. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
1.2 Concrete consequences of energy market imperfections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
1.2.1 Assessment of security of supply risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 251.2.2 Impact on capacity remuneration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 281.2.3 Existence of investment cycles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
1.3 Projected trends in demand over the coming years . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
1.3.1 The growing role played by electricity in achieving energy policy objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 321.3.2 Growing need for flexibility in European power systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
1.4 Efforts to reform market structures in France . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
1.4.1 Ongoing integration of energy markets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341.4.2 Participation of demand response in energy markets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 361.4.3 Reform of renewable support mechanisms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 371.4.4 Implementation of the capacity mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
1.5 Capacity mechanisms in Europe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
1.6 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
2. CHOOSINGTHERIGHTCAPACITYMECHANISMFORFRANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
2.1 Why a quantity-based market mechanism .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
2.2 Why a market-wide capacity mechanism .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
2.2.1 Provide guarantees in terms of security of supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 462.2.2 Address market imperfections and avoid distortion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 472.2.3 Minimise the cost to consumers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 512.2.4 Economic efficiency in the presence of investment cycles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 532.2.5 Suitability to France’s situation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
2.3 Why a decentralised capacity mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
2.3.1 Compatibility with the philosophy of the European energy market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 562.3.2 Ability to address France’s specific challenges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 572.3.3 Timescales of the decentralised market and economic efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
2.4 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
3. GUIDELINESFORTHECAPACITYMECHANISMRULES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
3.1 Architectural principles set forth in laws and regulations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
3.1.1 Drafting of the capacity mechanism decree . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 623.1.2 Provisions laid down in the decree . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 643.1.3 Regulatory framework provided for in the decree . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
3.2 Purpose of the capacity mechanism rules: Guarantee real contributions to security of supply . . . . . . . . . . . . . . . . 69
3.2.1 Nature of commitments by capacity operators (installed or available capacity) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 693.2.2 Duration of capacity commitments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 703.2.3 Methods for calculating the obligation and certifying capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 713.2.4 Reference data used to calculate obligations and certifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 723.2.5 Methods of valuing demand response . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
3.3 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
SUMMARY
15
SOMMAIRE
4. CAPACITY OBLIGATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
4.1 General provisions regarding the obligation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
4.1.1 Obligated parties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 764.1.2 Reference power . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 764.1.3 Security factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 794.1.4 Summary of obligation principles. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
4.2 Period for measuring suppliers’ obligation: The PP1 peak period . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
4.2.1 Definition of PP1 and contribution to the shortfall risk . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 824.2.2 Definition of PP1 and peak demand management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 834.2.3 Notification of PP1 hours . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 844.2.4 Sensitivity of the obligation to the location in time of PP1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 874.2.5 Provisions adopted in the rules on PP1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
4.3 Delivery year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .90
4.3.1 Overlapping year centred on a winter or calendar year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 904.3.2 Impact of the choice of the delivery year on the functioning of the mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 914.3.3 Sensitivity of the capacity mechanism to the definition of the delivery year with regard to the security of supply objective . . . . . . . . 914.3.4 Sensitivity of suppliers’ obligation to the choice of delivery year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
4.4 Parameters of the capacity obligation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
4.4.1 Determination of the obligation parameters (extreme temperature and security factor) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 944.4.2 Extreme temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 964.4.3 Security factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
4.5 Determination of the obligation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
4.5.1 Perimeter of an obligated party . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1004.5.2 Observed consumption. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1014.5.3 Sensitivity of consumption to temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1024.5.4 Taking into account certified demand response measures activated . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1144.5.5 Specific provisions for the compensation of losses on public transmission and distribution systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
4.6 Timetable for suppliers’ obligation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
4.6.1 Before the delivery year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1174.6.2 During the delivery year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1174.6.3 After the delivery year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
5. CAPACITYCERTIFICATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
5.1 General provisions governing the certification of capacities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
5.1.1 Players involved in capacity certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1205.1.2 Capacity level. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1215.1.3 PP2 peak period . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1265.1.4 Calculation of the capacity level . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
5.2 Period covered by capacity certification (PP2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
5.2.1 Period during which the contribution in estimated . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1295.2.2 Consequences of the PP2 period defined on the distribution of certificates between technologies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1315.2.3 Consequences of the PP2 period defined on the variability of certificate volumes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1325.2.4 Approach adopted in the rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1335.2.5 Notification of PP2 hours . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1335.2.6 Sensitivity of effective capacity level to the location in time of PP2 hours . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1345.2.7 Provisions adopted in the rules on PP2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136
5.3 Calculation of the capacity level . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
5.3.1 Available power of capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
5.3.2 Determination of the coefficient to reflect the technical constraints of capacity (K) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
16
5.4 Certification requests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
5.4.1 Definition of capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1395.4.2 Certification deadlines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1415.4.3 Withdrawals of capacities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1435.4.4 Certification fees. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 144
5.5 Rebalancing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 144
5.5.1 The rebalancing process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1445.5.2 Financial consequences of rebalancing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145
5.6 Collection of data required to calculate effective capacity level . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 147
5.6.1 Linking of certification entities with BM and NEBEF entities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1485.6.2 Collection of activated power data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1485.6.3 Collection of activatable power data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1495.6.4 Collection of maximum energy data for PP2 days . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1495.6.5 Collection of weekly maximum energy data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 149
5.7 Capacity verification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 149
5.7.1 Initial consistency check at the time of certification. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1505.7.2 Verification of certified intermittent capacities under the normative approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1505.7.3 Verification of certified capacity under the generic approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 150
6. THE CAPACITY MECHANISM SETTLEMENT SYSTEM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 152
6.1 General principles of settlements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 152
6.1.1 Capacity rebalancing by suppliers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1526.1.2 Imbalance settlement at the capacity portfolio manager level . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1536.1.3 Overview of principles governing settlements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
6.2 Key aspects of capacity mechanism settlements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 154
6.2.1 Security of supply target . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1546.2.2 Unit price of the settlement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1546.2.3 Interplay between capacity rebalancing by suppliers and imbalance settlement at the capacity portfolio manager level . . . . . . . . . . . 154
6.3 Settlements provided for in the rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 154
6.3.1 Interplay between capacity rebalancing by suppliers and the imbalance settlement at the capacity portfolio manager level . . . . 1546.3.2 Unit price for the settlement and the security of supply target . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1556.3.3 Definition of indicators for assessing threats to security of supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
6.4 Assessment of the impact of the provisions on settlements for market stakeholders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 158
6.4.1 Framework for the assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1586.4.2 Principle of the study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1586.4.3 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 159
7. MARKETFUNCTIONING:TRADING,TRANSPARENCYANDCOMPETITION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162
7.1 Trading of capacity certificates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 163
7.1.1 Publication of mechanism parameters at the start of the term . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1637.1.2 Nature of the product and organisation of trading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1637.1.3 Trading procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 164
7.2 Transparency of the mechanism .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165
7.2.1 Publications relating to the registers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1657.2.2 Publications relating to the capacity obligation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1677.2.3 Publications relating to the functioning of the capacity market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168
7.3 Competition in a decentralised capacity market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 169
7.3.1 Competition and market power . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1697.3.2 Competition under the capacity mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1707.3.3 Monitoring of the market’s functioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 174
7.4 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176
17
8. CAPACITY MECHANISM IMPACT ASSESSMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 178
8.1 Challenges associated with detailed modelling of how capacity mechanisms function . . . . . . . . . . . . . . . . . . . . . . . . . . . . 178
8.1.1 Analysis of technical parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 178 8.1.2 Assessment of the aggregate effects of the mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179
8.2 Limitations of existing analyses of how the capacity mechanism functions in an interconnected market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 180
8.2.1 Analysis of the report accompanying the European Commission guidelines on public interventions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1808.2.2 Factors minimising the French mechanism’s impact on neighbouring countries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 183
8.3 Detailed analysis of short-term effects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184
8.3.1 Hypotheses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1858.3.2 Quantitative assessment of cost to consumers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 189 8.3.3 Impact on the CSPE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 195
8.4 Plans to strengthen the impact assessment system .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 196
8.4.1 A mechanism simulator made available to stakeholders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 196 8.4.2 Expand the “first-round” impact assessment by factoring in small consumers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 197 8.4.3 Include a study on the dynamic impact of the mechanism over the long term in the assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 197
9. EUROPEANINTEGRATIONOFTHE FRENCHCAPACITYMARKET . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 198
9.1 Interconnections’ contribution to security of supply in France . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 198
9.1.1 Integrating power systems improves security of supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1989.1.2 Recognition of the cross-border dimension in the French capacity market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199
9.2 Current status of cross-border participation in capacity mechanisms .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200
9.2.1 Cross-border participation in existing and planned capacity mechanisms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2009.2.2 Decision to implicitly recognise foreign capacity in the French capacity mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 201 9.2.3 Towards an explicit cross-border participation in capacity mechanisms in Europe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202
9.3 A practical way forward for explicit cross-border participation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .205
9.3.1 Key principles to design a solution for explicit cross-border participation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2079.3.2 Relevant event to be considered to allow effective cross-border exchanges of capacity products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2089.3.3 “No-go” solutions to implement explicit cross-border participation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2099.3.4 Target solution for explicit cross-border participation in the French capacity market . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2109.3.5 Shaping a transitory solution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211
10.COMPLIANCEWITHEUROPEANPROVISIONSANDPRINCIPLES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212
10.1 The European legal framework governing State intervention to ensure security of supply . . . . . . . . . . . . . . . . . . . 212
10.1.1 Competence of Member States with regard to security of supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21210.1.2 Regulation of Member States’ competence through the provisions of the Treaty and secondary legislation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21310.1.3 Legal forms of public intervention . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215
10.2 Compliance with the principles of necessity and proportionality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 216
10.2.1 Principle of necessity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21610.2.2 Principle of proportionality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 226
10.3 Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .229
BIBLIOGRAPHY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232
ANNEXE1:LISTOFPARTICIPANTSINMACCONSULTATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234
ANNEXE2:CONTRIBUTIONSTOTHESTAKEHOLDERCONSULTATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 236
SOMMAIRE
18
1.1.1 Optimal functioning of energy markets within the theoretical framework of the “energy-only” market
The European power market is being created by integrating
markets and networks. Since deregulation began with the first
electricity directive of 1996, individual Member States have
been organising their industry around common principles (libe-
ralised system more than the vertical integration of existing
markets) and including electricity in the free trade of goods
to encourage intra-European exchanges. Electricity prices are
determined by supply and demand in a competitive market and
will thus in theory optimise exchanges between countries and
allow consumers to choose the generators and suppliers that
have the most competitive prices.
Detailed regulations govern the functioning of the
market, applying to all exchanges and relationships
1. WHY A CAPACITY MECHANISM IS NECESSARYElectricity markets are undergoing major changes in many
European countries, including France. Market opening may have
helped optimise electricity flows in the short term, but there
are growing concerns about the ability of mechanisms imple-
mented in the early 2000s to efficiently regulate investments
in generation and demand response capacities and safeguard
security of supply over the long term.
Having a capacity mechanism in place will profoundly change
the architecture of the electricity market by correcting the
shortcomings observed with the current system. The goals are
to encourage investment in capacities that can be available
during peak demand periods and, in a broader sense, to lay the
foundations for the energy transition by rewarding investments
that are useful to the power system in proportion to their bene-
fits to the community.
RTE’s draft rules are part of a more comprehensive assessment
of the organisation of the deregulated power system. This chap-
ter outlines the justification for public intervention. It begins with
a description of why the market’s theoretical ability to safeguard
security of supply over the long term is increasingly being called
into question (§ 1.1). Next, it explains that an observation of the
market’s functioning tends to support these doubts, and sug-
gests that closer monitoring of security of supply will be required
from 2016-2017 taking into account the specific characteristics
of France’s current power system, i.e. its temperature sensitivity
and the occurrence of periods of peak demand (§ 1.2). This ana-
lysis is followed by a presentation of the public policies currently
being implemented in France and the European Union, and
shows how the specific issues facing France could become even
more pressing with the addition of a “flexibility” component
(§ 1.3). The chapter also outlines the programme for overhauling
the functioning of markets, of which the capacity obligation will
be one aspect (strengthening of cross-border interconnections,
operations in the day-ahead, intraday and real-time markets),
and discusses the reforms being made to renewable support
mechanisms (§ 1.4). The last section illustrates how the intro-
duction of a capacity mechanism in France will be in keeping
with a broader trend in Europe (§ 1.5).
1[European Council, 2011]
1.1 Theoretical evidence of imperfections in energy markets
between stakeholders and institutions: in other words, the Euro-
pean power market is a result of public intervention. These regu-
lations are constantly being better coordinated between Mem-
ber States. Electricity markets in Europe thus operate based on
standard market designs and are committed to gradually har-
monising structures until a “target model” is achieved:
Safe, secure, sustainable and affordable energy contributing
to European competitiveness remains a priority for Europe.
Action at the EU level can and must bring added value to that
objective… […]The EU needs a fully functioning, interconnec-
ted and integrated internal energy market1.
The European Union needs an internal energy market that is
competitive, integrated and fluid, providing a solid backbone
for electricity and gas flowing where it is needed. To tackle
Europe’s energy and climate challenges and to ensure
19
WHY A CAPACITY MECHANISM IS NECESSARY / 1
affordable and secure energy supplies to households and
businesses, the EU must ensure that the internal European
energy market is able to operate efficiently and flexibly2.
What are currently being harmonised are mechanisms for remu-
nerating energy generated (MWh) over different timeframes
(annual, day-ahead, intraday) and in different regions (recogni-
tion of interconnections). These mechanisms are considered
the cornerstone of the European energy market, though Mem-
ber States have their own specific instruments in place as well,
for instance in the area of reserves set aside by transmission
system operators to operate the power system3.
Most provisions in the framework governing the construction of
the European power market apply to energy trading between
firms in a competitive market, and correspond to the theoretical
model of the energy-only market. In an energy-only market, all
generation capacity dispatched is remunerated at the marginal
production cost of the mix. Free and undistorted competition
guarantees that generators’ prices reflect their real costs. The
energy price is the only economic signal needed: it ensures
the optimal use of generation assets in the short term (since all
capacities compete, only the most competitive are used to meet
demand), and also drives long-term investment (the prospects
for capacities to generate profits in the market lead rational
players to invest in the most competitive technologies and retire
units that are no longer profitable, meaning the mix adjusts to
demand in an optimal way):
The electricity market has two coordination functions. First,
in the short term, it ensures the efficient operation of com-
petitors’ equipment. Second, it indicates scarcity of capacity
in different technologies via a price signal to orient investors’
long-term decisions4.
In practice, the regulatory framework of the European energy
sector is designed to create the right conditions for an energy-
only market to function. Where day-ahead and intraday mar-
kets are concerned, the harmonisation of exchanges is based
on shared standards for products and timeframes structured
around power exchanges and system operators, with market
coupling allowing for ever greater integration of processes at
the European level. Financial products developed based on
these underlyings allow participants to manage price risks over
the long term and base their investment decisions on their own
forecasts and those of the market as a whole. The general sys-
tem governing the market’s functioning can be described as
follows:
Most energy markets in Europe only remune-
rate energy generated, since there is no specific
mechanism for assigning a value to capacities
that can be used to generate power when sup-
ply is tight (exceptions are Spain, Portugal, Italy,
Greece and Ireland, which apply a form of capa-
city remuneration). The underlying principle
is that electricity prices will increase if market
stakeholders see an imminent capacity shor-
tage, resulting in additional investment5.
The main characteristic of the energy-only model
is that it describes a balanced situation in which
a short-term approach to market functioning is
compatible with the long-term financing needs
of each power plant. In particular, generators’ pro-
fits exactly cover their fixed costs for each type of
generation capacity (base, semi-base and peak).
Indeed, in the energy-only model, each power
plant generates profits on the market when the
energy price is higher than its variable cost: the
difference between this price and the variable
cost is called the inframarginal rent6. Equilibrium
is achieved since market stakeholders base invest-
ment decisions on rents generated in the market:
generation capacity is invested in or retired in res-
ponse to this economic signal.
In this theoretical model, the market price climbs
above the variable cost of peak generation capa-
city7 only when supply is extremely tight, in other
words during periods of load curtailment8. In this
case, the inframarginal rent represents the diffe-
rence between the marginal production cost of
the mix (i.e. the variable costs of the most expen-
sive plant to run) and the energy price in load cur-
tailment situations. This price will in theory cor-
respond to consumers’ willingness to pay to avoid
service interruption9, or their marginal propensity
to pay, which is referred to as the cost of unserved
energy (or VoLL, Value of Lost Load).
The figure below illustrates the merit order of generation capa-
city and the price duration curve for peak load hours in a situa-
tion where long-term equilibrium is achieved10. The inframar-
ginal rent generated annually by peak generation plants (blue
area) perfectly covers their annualised fixed costs, along with a
portion of those of other capacities.
2[EC, 2012a]
3Consistent with the reserve requirements and levels defined in the Load Frequency Control and Reserves Network Code being adopted for Europe.
4[Finon, 2013]
5[General Commission for Strategy and Foresight, (CGSP),2014] Capacity mechanisms also exist in many other European countries, as discussed in section 1.5 of this report. Electricity markets in Europe are nonetheless still organised primarily around the energy market.
6 When the market price is higher than the marginal cost of the most expensive plant to run, the inframarginal rent is considered a scarcity rent.
7Peak load plants are dispatched last.
8Load shedding involves rationing supply to some consumers to restore/maintain the supply-demand balance.
9For the market to function perfectly, the price must accurately reflect consumers' marginal willingness to pay for electricity, which is not technically feasible in practice. What is given here is an approximation of a single value of the cost of unserved energy.
10The price duration curve is the curve obtained by arranging in decreasing order prices per MWh of electricity observed over all hours of a year.
20
If the energy price does indeed reach the cost of unserved
energy during periods when load curtailment is required, the
corresponding inframarginal rent will send a signal to the market
about the optimal level of investment for society. This optimal
level represents a perfect trade-off between the collective cost
of load curtailment for society and the cost of investing in new
capacities.
The key result of the energy-only model – that dimensioning
is optimised over the long term – is based on very signifi cant
assumptions, among others that the market will function per-
fectly even in shortage situations, when available capacity
cannot fully meet demand. During such periods, the energy
price should be able to rise to a very high level – that of the
cost of unserved energy – which some countries and market
Figure 1 – Illustration of the merit order and price duration curve for peak load hours in a perfect energy-only market
Base VC
VoLL
Peak VC
Semi-base VCPrice duration curve
8760
Peak capacity
Peak VC
VoLL
Peak VC
VoLL
Annual peak operation time
Load shedding
Optimal load shedding
Quantity (GW)
Quantity (GW)
Price (€/MWh)
Price (€/MWh)
Hours of operation
Price (€/MWh)
Price (€/MWh)
Hours of operation
stakeholders estimate at several tens of thousands of euros per
MWh. This central assumption seems fairly unrealistic, limiting
the scope and meaningfulness of the result.
1.1.2 Questioning the energy-only market’s ability to guarantee the optimal level of investment
1.1.2.1 Introducing a more realistic model of the energy
market
A number of academic studies analyse the dynamics of invest-
ments in power generation capacity in new energy markets.
Many of these studies focus on the failures of existing markets
and possible ways to fi x them.
21
WHY A CAPACITY MECHANISM IS NECESSARY / 1
The first limitation identified with the energy-only model has to
do with the assumption that markets can manage shortage situa-
tions in an optimal manner. What is being challenged, in more
specific terms, is (i) how the value of lost load is defined during
shortage situations, and (ii) whether prices are allowed to rise
to the value of lost load. In the model presented in the previous
section, the failure of prices to reach the value of lost load during
peak periods creates a deficit for economic agents who will not be
able to cover their fixed costs, at least in the short term.
In economic literature, the term missing money is used to des-
cribe this difference between fixed costs and the inframarginal
rent (see box below). Various factors can cause this phenome-
non to occur.
First, regulations or practices may limit the inframarginal rents
of electricity providers during shortage periods. This is notably
the case when electricity prices are capped, a situation that has
been covered in detail in economic literature due to the wides-
pread use of caps in electricity markets in the United States in
the 2000s, after the California crisis11. But similar effects can
occur even when no price cap is applied, if particularly high
prices are considered unacceptable. For instance, regulators are
in charge of protecting consumers from excessive price spikes
since electricity is an essential good. Public authorities’ reac-
tions to very high prices create an “implicit cap” above which
prices cannot rise.
The actual functioning of power systems is also
more complex than what the model presented
above assumes. If system operators reserve capa-
city ahead of time for the system, energy prices
can decline during peak periods. Indeed, some of
the capacity dispatched in these situations is remu-
nerated in advance, when it is reserved, and that
revenue is not reflected in the marginal prices offe-
red on markets or capacity mechanisms. This sim-
ply shows that no power system functions exactly
according to the principles of the energy-only mar-
ket. The academic literature also notes that in other
contexts, operational measures system operators
may take to limit the impact of load curtailment
can obstruct price spikes12. Lastly, it is technically
impossible today to distribute shortages based on
consumers’ willingness to pay. Security of supply
can thus be analysed within the framework of the
theory of public goods (see § 1.1.3).
The second limitation identified with the energy-
only model relates to the overly simple assumptions
adopted. Oversimplifications of the real situation
(e.g. convexity of costs13, optimality of the price set-
ting method14 or the failure to take into account the
discretionary nature of investments15) necessarily
limit the meaningfulness of the results.
11It should be noted that the rules governing the functioning of electricity markets in Europe also regulate price formation through a price floor/cap system (for instance: –€500/MWh – €3,000/MWh within the NWE region).
12See for example [Joskow, 2007]. This consideration seems to apply mainly to the context in the United States. In France, such measures would only be taken once markets had had the opportunity to function.
13It is assumed in the model that each time step is associated with an independent merit order; the model thus does not take into account the dynamic constraints associated with generation or demand response capacities.
14[Batlle, 2012]
15Most capacities have standard output, which restricts investment decisions.
16Ill-adapted generation mixes and even market imperfections can also translate into extra money for some capacities.
17For this reason, RTE opted not to focus its analyses on the missing money issue during the 2011 consultation on the capacity mechanism.
The missing money concept
The term “missing money” usually refers to a situation where capacity is insufficiently remunerated due to market
imperfections. When there is missing money, it implies that capacity would legitimately earn more revenue if the mar-
ket was functioning perfectly.
However, even in a market that operates perfectly, it is possible, and sometimes legitimate, for capacity remuneration
not to cover long-term costs. Indeed, once capacity exceeds the optimal level (surplus capacity), the energy market
acts as a stabilising feedback loop by undercompensating energy supply.
Symmetrically, situations of under-capacity can lead to capacity earning more revenue than it would at equilibrium,
resulting in additional revenue that is referred to as “extra money”16. It is normal for market stakeholders to be “subjec-
ted” to such revenue swings insofar as they had sufficient visibility when making their investment decisions.
The term missing money must therefore be used with caution. Missing money caused by market imperfections is
indeed undesirable, but when capacity remuneration is lower because there is too much capacity, then the market
is merely self-regulating, as it is expected to do. In other words, even if it is proven that capacity is earning insufficient
remuneration, corrective measures are not necessarily justified17.
Hereinafter, the term missing money is used only to refer to situations where capacity earns insufficient revenue due
to market imperfections.
22
When more realistic assumptions about actors’ behaviours
are applied (asymmetry of information, copycatting, etc.), the
conclusions about the energy-only market’s ability to regulate
investments efficiently are not the same. Taking the high varia-
bility of revenues in the energy-only market on the one hand
together with market stakeholders’ risk aversion and the limited
financial tools available for hedging risks on the other, it seems
that the price signals generated by the energy-only market can-
not efficiently drive investment.
These considerations lead to two conclusions, which are pres-
ented and discussed in sections 1.1.3 and 1.1.4, respectively:
> Security of supply is a public good that will not be sponta-
neously delivered through the energy-only market model;
> Energy-only markets are subject to specific investment cycles
that jeopardise the achievement of a stable equilibrium.
1.1.3 Failures of the energy-only market in the presence of externalities
1.1.3.1 Consequences of market failures for
investment
A true representation of energy markets shows that it would
be fairly unrealistic to assume that shortage situations will be
managed perfectly by the market. This creates doubts about
whether prices could rise to the levels required for fixed costs to
be exactly covered.
Nor would the impact be limited to peak capacities if a reve-
nue shortfall occurred during peak periods. All units operating
during these periods would be affected, including base-load and
semi base-load capacities, though the consequences would be
proportionately greater for peak power plants. In this case the
missing money problem could remove incentives to invest in
any type of capacity.
In concrete terms, it is doubtful that market stakeholders sub-
ject to economic performance requirements will agree to keep
unprofitable assets in operation indefinitely. If they observe a
revenue deficit on generation assets remunerated at the mar-
ginal price, stakeholders are likely to adjust their investment or
selling strategies to integrate this risk:
> By decommissioning assets or underinvesting:
when supply is reduced, inframarginal rents
are restored to levels that allow fixed costs to
be covered, which, in the model presented
above, translates into more frequent shortage
situations;
18[Léautier, 2012] “A wholesale price cap simplifies the analysis, while preserving the main economic insights.”
> By adding a margin to their selling prices, above and beyond
the variable cost of operating the assets.
In the first case, the profitability of generation assets is restored
at the expense of security of supply; in the second, the optimal
structure of the mix is modified. In both cases, consumers end
up paying for a market failure, and the structure of the gene-
ration mix moves away from the theoretical ideal.
Figure 2 below illustrates trends in the extremity of the merit
order and price duration curve for peak load hours when the
missing money issue is not addressed, resulting in a decrease
in capacity offered. The limitation of profits is illustrated by the
existence of a price cap: this is a simple and general represen-
tation of what happens when there is missing money18. The
situation is then compared to the theoretical framework of the
perfect energy-only market. In this situation, inframarginal rents
are restored for all capacities dispatched thanks to an increase
in the frequency of load curtailment.
1.1.3.2 Analysis from the standpoint of public goods
theory
In theory, a perfect energy-only market will create a level of
security of supply that corresponds to the value of lost load. This
value will vary depending on consumers, who are not all equally
sensitive to service interruption.
As discussed above, the idea that the market value of unserved
energy represents the real value of that energy is a very strong
assumption. There are in fact many technical and practical fac-
tors that prevent the market from fairly valuing unserved energy.
An instantaneous participation of demand in energy markets
during shortage situations is notably required for the market
value of unserved energy to be revealed. Efforts made in France
over the last three years to strengthen the regulatory framework
governing demand response, and the creation of a framework
for its participation in energy markets (NEBEF), are big steps in
the right direction (see § 1.4 and chapter 10). However, the mar-
ket’s handling of shortage situations can only be analysed from
a very long-term perspective.
Security of supply is thus a public good: when it is guaranteed,
everyone benefits, but when this is not the case all network
users are affected, regardless of the value they place on it.
The availability of peak capacities creates positive exter-
nalities for security of supply with no financial benefits for
operators of these capacities. This reduces investment
incentives: it is not in the interest of market stakeholders
23
WHYACAPACITYMECHANISMISNECESSARY / 1
to invest in certain capacities that would benefit security of
supply if the profit they generate is lower than the benefit
for society.
In economic theory, this justifi es public authorities regulating
the market’s operation by defi ning a collective preference –
since individual preferences regarding security of supply will not
emerge – and ensuring that the target is met through a mecha-
nism that aligns individual incentives and investments with this
preference for the common good.
Public authorities in France have set a security of supply
target corresponding to an annual loss of load expectation
of three hours. Since this target is not internalised by the
energy market, there is no reason for the level of security of
supply spontaneously created by the market to match the
energy policy objective. This means that, if a decision is made
to increase or decrease the security of supply target, energy
prices will not increase or decrease accordingly: there is no
communication channel between public policy targets and
market results.
Since the market on its own will fail to meet policy objectives, it
is necessary and justifi ed for public authorities to intervene to
ensure that the market meets public policy targets and does so
at the lowest possible cost.
1.1.4
Imperfections of the energy market in terms of managing investment dynamics
1.1.4.1 Theory of investment cycles in power systems
As discussed in § 1.1.2, a more accurate representation of mar-
ket stakeholders’ behaviours allows a more accurate representa-
tion of the dynamic functioning of deregulated power systems.
Generally speaking, this challenges the idea that the market
alone can optimise investments and shows that the long-term
equilibrium suggested by theoretical analysis is rarely found in a
more realistic, dynamic model.
In the real world, a number of factors must be incorporated
into any model of investment dynamics: market stakeholders’
strategies and decision-making processes, the time requi-
red to build new generation capacities, the irreversibility of
investments and their lifespan and uncertainty surrounding
exogenous variables. More specifically, capacity investments
and retirements are not spontaneous, but rather have their
own cyclical dynamics. These cycles are created by a sort of
viscosity when it comes to bringing new generation capacities
online or removing them from the market: investments are
“triggered” (usually by several stakeholders at once) beyond
a certain level of projected profitability, and retirement deci-
sions are made below a loss threshold, here again by various
stakeholders at once. Real-life power systems thus oscillate
Quantity (GW)
Price (€/MWh)
Hours of operation
Price (€/MWh)
Peak capacity
Peak VC
VoLL
Peak VC
VoLL
Load shedding
Price cap Price cap
Missing money, decline in inframarginal rent due to price decrease during load shedding
Inframarginal rent restored through increase in load shedding/decreasein installed peak capacity
Missing money problem: Price decrease during load shedding
Increase in load shedding/decrease in installed peak capacity
Merit order Price duration curve Optimal load shedding
Functioning, optimal case
Inframarginal rent, optimal case
Functioning, missing money problem not corrected
Inframarginal rent, missing money problem not corrected
Figure 2 – Eff ects of missing money problem caused by market imperfections on the merit order and price duration curve in the energy market
24
around the long-term equilibrium, which can also evolve
depending on demand, the costs associated with different
technologies, etc.
Similarly to other capital-intensive industries with highly
variable demand (e.g. aluminium), power systems are subject
to investment cycles19. This “boom and bust” phenomenon
is characterised by periodic waves of capacity investments
or retirements. Investment cycles result in an alternation
between phases of overcapacity and under-capacity on the
system, with the “first best case” equilibrium never being
achieved.
At first, the industry may be short of capacity and prices will be
high. This acts as a signal to investors, who start to add capa-
city. In the absence of a coordination device, however, they
are in danger of over-reacting – too many investors read the
high prices as a signal that their own investment will be profi-
table. Once the new capacity comes on stream, it will depress
prices. This will be sufficient to halt most new investments,
but the existing capacity is likely to stay in service. Scrapping
decisions are irreversible and will not be taken unless the
price falls sufficiently below the variable costs of staying in
operation20.
Investment cycles are intrinsic to power systems, owing to their
specific characteristics, to how related markets function, and to
the processes capacity investment and retirement decisions
entail. The economic literature offers two very general expla-
nations of why investments are cyclical: lead times for building
capacity (time lag between investment decisions and availabi-
lity of new capacity) and suboptimal levels of information and
coordination.
These two explanations are clearly verified in power
systems in energy-only markets since energy prices
are the main means of sending information and
coordinating decisions. Cycles are notably amplified
by the fact that energy prices alone do not seem
to accurately convey information to coordinate
investments, even when additional communication
channels are created, such as the Adequacy Fore-
cast Report, which provides aggregated information
about the supply-demand balance outlook (see
§ 1.2.1).
This reflects the difference between the time
constants of investments, which are particularly
long (typically several years for decisions to be implemented,
investment lifespan of several decades) and those of energy
markets, the liquidity of which is limited except for timescales
close to real time. The lifespans and capital intensity of gene-
ration assets also limit the ability to constantly re-optimise the
generation mix as fundamentals evolve. It is impossible for the
structure of the mix to readapt.
[E]xpectations need time to be updated to the new mar-
ket conditions, investments are delayed under uncertainty,
and power plants need usually a long time to be construc-
ted and to be brought online. Under these conditions, it
is to be expected that power markets experience business
cycles, i.e. periods of huge investment rates followed by
other periods with no investment activity. This might result
in severe fluctuations of the reserve margin, and therefore
of power prices21.
These representations suggest that when the market functions
naturally, decision-making will be amplified and concentrated22.
Investors will tend to overreact to price signals and may adopt
copycat behaviours that intensify investment waves23.
1.1.4.2 Consequences of the existence of investment
cycles
The existence of capacity investment and retirement cycles
in energy-only markets is not a problem in and of itself, if
the security of supply target set by public authorities is met.
However, a succession of cycles can result in wide swings
between overcapacity and under-capacity. This in turn has
adverse consequences for security of supply and economic
efficiency.
Phases of under-capacity can lead to excessive risk of load cur-
tailment, possibly driving security of supply down to particularly
low or even socially and politically unacceptable levels. Actual
under-capacity situations would also have harmful effects on
the economy, as the cost of unserved energy could rise to very
high levels.
Cycles increase the number of periods of investments and reti-
rements. All other things being equal, generation capacities
remain on the market for a shorter time than in an optimal situa-
tion and investment needs are greater, driving up costs to final
consumers. There can thus be an economic benefit to regula-
ting cycles.
19[Ford, 1999 and 2002], [De Vries, 2004], [Green, 2006], [Cepeda, 2011]
20[Green, 2006]
21[Olsina et al., 2006]
22The recent wave of investments in CCGT plants in Europe, described in section 1.2 of this report, illustrated this phenomenon.
23[Stoft, 2002], [Knittel & Robert, 2005]
25
WHY A CAPACITY MECHANISM IS NECESSARY / 1
24This mission is described in the decree of 20 September 2006.
The theoretical model on which power market deregulation in France and Europe has traditionally been based is that of the energy-only market. Initial analysis suggests that the model can optimise the functioning of generation assets and perfectly regulate the investments needed to ensure adequacy over the long term. However, this result is based on strong and unrealistic assumptions, chief among them that the market will efficiently manage shortage situations and that price spikes will occur. Wider spread use of demand response to increase demand-side flexibility could make the energy-only model more valid, but will not suffice, at least over the medium term, to resolve this difficulty:
1. Even in an energy-only market that functions perfectly, security of supply is a public good, meaning that public authorities should define a security of supply criterion;
2. There is no reason for the energy-only market to internalise this security of supply criterion: public authorities are therefore justified in implementing a mechanism to ensure that the criterion will be met by rewarding stakehol-ders for their contribution to reducing the shortfall risk.
In sum, the capacity mechanism is part of an effort to correct an identified market failure by internalising positive externalities affecting security of supply. It is totally legitimate from an economic theory standpoint.
If this market failure is not corrected, there is no reason why some capacities that are indispensable to the functio-ning of the power system will be made available during periods of peak demand. It is also possible that energy mar-ket prices will not efficiently coordinate market stakeholders’ decisions, leading to very intense investment cycles that reduce overall economic efficiency and can result in a rapid succession of phases of overcapacity and periods when security of supply is at risk.
instruments to efficiently regulate these cycles, enabling excess
capacity to be absorbed proportionately and then investments
to resume (§ 1.2.3).
1.2.1 Assessment of security of supply risks
1.2.1.1 Risks to security of supply
This is not the first time consistent and public efforts are being
made in France to monitor risks to security of supply. RTE was
among the first transmission system operators (TSOs) in Europe
to conduct such an analysis. This mission was entrusted to it by
the law of 10 February 2000, which marked the beginning of the
deregulation of the French energy sector24. Its work is backed by
a methodological approach and recognised expertise in supply-
demand balance simulations.
Adequacy forecasts are one of the crucial assessment tools that
must be made available to public authorities when it comes to
security of supply. The European Commission has placed heavy
emphasis on this necessity in recent months:
Member States should carry out a full analysis of
whether there is a lack of investment in gene-
ration, and why. They should seek cross-border
The analyses above show that, on a theoretical level, the ability
of energy-only markets to efficiently guarantee security of sup-
ply is doubtful. This conclusion would nonetheless be insuffi-
cient if not backed by a factual analysis of the situation.
France already has the instruments required to measure security
of supply and conduct assessments prior to introducing correc-
tive measures. These instruments meet the objectives set out
in the European Commission guidelines published in November
2013 and analysed in chapter 10 of this report. They can also be
used to illustrate how safety margins are gradually decreasing,
as peak demand continues to increase (§ 1.2.1).
Such considerations must be weighed against the difficulties
many generators and demand-side operators are having in
earning adequate remuneration. At a time when the econo-
mic fundamentals of the sector are changing profoundly, the
energy-only market can no longer drive investment efficiently.
Assumptions that new investments would follow the shutdown
of existing plants, or that consumption will start to trend higher
again, do not seem certain in the current context (§ 1.2.2).
Lastly, the existence of investment cycles has also been pro-
ven. The capacity mechanism will give public authorities new
1.2 Concrete consequences of energy market imperfections
26
is sourced. These factors vary widely from one country to the
next. In France, the main risk stems from the existence of a peak
demand phenomenon.
Power demand is very temperature-sensitive in France. The ade-
quacy studies conducted by RTE27 show that temperatures are
the dominant variable for the French power system. As a result,
peak demand periods are observed in winter during cold spells,
and the phenomenon has grown steadily more intense in the
past decades.
France concentrates almost half of the total temperature-
sensitive power demand in Europe, with some 2,400 MW of
additional consumption per degree Celsius.
[…]
Temperature sensitivity has been rising steadily over the
past ten years. The winter gradient increased by more than
30% between the winter of 2001-2002 and the winter of
2012-201328.
This phenomenon is all the more important in assessing supply-
demand balance risks in France as peak demand is growing fas-
ter than power demand in general. In other words, keeping peak
demand growth in check is a primary concern, especially while
the energy transition is under way and electricity continues to
substitute other energy uses.
solutions to any problems they find before planning to inter-
vene. Any capacity mechanism needs to take into account
any impact the intervention will have on neighbouring Mem-
ber States and on the internal energy market. Fragmentation
of the internal energy market must be avoided25.
The framework for preparing adequacy reports within Mem-
ber States was further strengthened with the European Com-
mission’s publication in November 2013 of guidelines on
public intervention in the electricity market26. These guidelines
included a checklist of criteria considered relevant in assessing
capacity adequacy.
The criteria and methodology RTE uses in its Adequacy Fore-
cast Reports are discussed in detail in chapter 10 of this report.
Analysis shows that the adequacy studies conducted in France
meet the criteria established by the European Commission. And
RTE goes beyond minimal compliance: its Adequacy Forecast
Reports are among the only reports that are made public and
based on a Europe-wide and probabilistic model of the supply-
demand balance. The conclusions of these reports can thus be
cited to justify public intervention.
1.2.1.2 Specific characteristics of peak demand in France
Factors that can put security of supply at risk include climate
conditions, the structure of power demand and where energy
25[EC, 2012]
26[EC, 2013a]
27[RTE, 2012]
28[RTE, 2013]
29[RTE, 2012]
Figure 3 – Growth in peak demand in France since 200129
70,000
80,000
90,000
100,000
110,000
102,
100
100,
655
96,7
10
94,6
00
93,0
80
92,4
00
91,8
20
90,3
00
88,9
60
86,2
80
86,0
20
84,7
10
83,5
40
83,4
90
82,1
40
79,7
30
79,7
10
79,5
90
78,6
60
77,4
40
77,0
30
76,1
30
74,9
00
MW
Day
11/1
5/20
01
12/1
0/20
01
12/1
1/20
01
12/1
2/20
01
12/1
3/20
01
12/1
7/20
01
12/0
9/20
02
12/1
0/20
02
01/0
7/20
03
01/0
8/20
03
01/0
9/20
03
01/2
6/20
05
02/2
8/20
05
01/2
7/20
06
12/1
7/20
07
01/0
5/20
09
01/0
6/20
09
01/0
7/20
09
02/1
1/20
10
12/1
4/20
10
12/1
5/20
10
02/0
7/20
12
02/0
8/20
12
27
WHYACAPACITYMECHANISMISNECESSARY / 1
1.2.1.3 Analysis of the conclusions of the 2013
Adequacy Forecast Report update
Adequacy assessments are conducted in France by simulating
the operations of the power system over 8,760 hours a year for
the next fi ve years, factoring in various technical parameters
such as the dynamic operating constraints of generation units.
These are stochastic simulations based on a large number of
supply and demand scenarios. They are used to identify the
confi gurations of the supply-demand balance during shortfall
periods, i.e. situations when the level of supply modelled does
not cover forecast demand. The shortfall volumes yielded by
these simulations are then compared to the secu-
rity of supply criterion set by public authorities,
which corresponds to an average annual loss of
load expectation of three hours30.
The Adequacy Forecast Reports published since 2009 have
highlighted many diff erent phenomena, including a wave of
investments in combined-cycle gas turbine plants, the eff ects
of the economic crisis and the upward trend in peak demand.
The most recent Adequacy Forecast Report update (2013) spe-
cifi cally emphasised the gradual but steady reduction of safety
30Decree of 20 September 2006.
31[RTE, 2013]
Excerptsfromthe2013AdequacyForecastReportupdate
Under the “Baseline” demand scenario, and based on the information currently available about generation capacity over the
period considered in the report, the shortfall criterion defi ned in decree 2006-1170 of 20 September 2006 (annual loss of load
expectation of up to three hours) is not exceeded before or during 2018.
The less favourable economic outlook factored into the “Low” scenario would strengthen this conclusion. Conversely, a sharper
economic rebound, as called for in the “High” scenario, could cause the shortfall criterion to be exceeded in 2016.
Though the situation forecast in the “Baseline” scenario may seem comfortable, given the power available through imports, the
risk should nonetheless increase, particularly after 2015. As such, capacity margins above and beyond the criterion […] should
decrease by almost 6 GW over the next three years. […]
This analysis of margins also allows for […] an assessment of the potential impact of the shutdown of other fossil-fi red facilities, for
instance combined-cycle gas turbine plants, which would result in an increase in the shortfall risk31.
Figure 4 – Margins and capacity shortfalls under diff erent scenarios in the 2013 Adequacy Forecast Report update
Mar
gin
Cap
acit
y sh
ortf
all
GW
-8
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
8
2014 2015 2016 2017 2018
5.8
4.8
-2
4.5
3.2
-3.4
0.4
-1.3
0
-1.9
0
1.8 1.92.2
3.23.6
4.2
-2.3
-6.5-7.2
-6.8
“Low” scenario with exchanges “Stronger DSM” scenario with exchanges “High” scenario with exchanges
“Baseline” scenario with exchanges “Baseline” scenario without exchanges
28
margins vis-à-vis the security of supply criterion, and suggested
that margins would be eliminated in 2017. One potential
consequence is that security of supply would not be gua-
ranteed in the event of an intense cold spell.
Security of supply must therefore be monitored in France.
This conclusion is all the more important considering that the
assessments conducted in 2013 already factored in a downward
revision of demand forecasts due to the ongoing effects of the
economic crisis in Europe and France. Sluggish demand eases
tension in the supply-demand balance, but will also overlap with
a significant reduction in generation capacity late in 2015, when
several fossil-fired plants will be decommissioned after new
environmental standards take effect. At the same time, some
generation capacities are facing economic difficulties, notably
combined-cycle gas turbine plants. The existence of risks thus
seems clear.
There are factors that could change this perception over the
medium term:
> Demand could prove even weaker than anticipated, which
would improve the outlook;
> Some generation units that will be affected by new environ-
mental regulations could make specific investments that
allow them to operate beyond 2015 under the new
standards: this would also make the situation less
worrisome;
> Existing units, notably combined-cycle gas turbine
plants, could be decommissioned for economic
reasons and definitively retired or mothballed,
which would darken the outlook.
The latter possibility is a crucial aspect of current
assessments. Indeed, adequacy forecasts are based
on information that is public, i.e. officially announced
by generators. The update prepared in July 2013
therefore did not take into account any shutdowns
not included in the baseline scenario, as it was based
on public information available at the time. Given
the unlikelihood that these units will become pro-
fitable, decommissioning cannot be ruled out. This
could create a negative margin vis-à-vis the criterion
if the shutdowns are not simultaneously offset by
the creation of new generation or demand response
capacities. Regulating the structural adjustment of
the mix going forward is one objective of the capa-
city mechanism.
1.2.2 Impact on capacity remuneration
Public intervention to ensure security of supply must be based
first and foremost on an assessment of the aggregate supply-
demand balance, as outlined in the section above, and not on
concerns about generators’ remuneration. There can be many
reasons for remuneration to be lower for some units, as dis-
cussed in the box in section 1.1.2, and it is not easy to identify
with certainty when the culprit is the theoretical missing money
problem and when other factors are responsible. Nonetheless,
the energy market’s ability to assign the proper value to genera-
tion, demand-side and storage capacities is a key consideration
when analysing failures in the energy market. Legitimate ques-
tions are now being raised about whether this market model,
developed in the 1980s and implemented in the 2000s, can
adapt to the changing cost structure of generation and demand
response32.
1.2.2.1 Stakeholders’ positions
More and more European energy firms are concerned about the
functioning of the market. Responses to the European Commis-
sion’s consultation on making the internal market work33 amply
demonstrated this34.
Their positions were further strengthened in May 2013 when
eight energy utilities (GDF Suez, E.ON, Eni, RWE, Enel, Gasterra,
Iberdrola and Gasnatural Fenosa) launched a “call to EU leaders
for a revitalised energy policy”, outlining the challenges firms in
The conclusions of the Adequacy Forecast Report are based on accurate analyses that meet the criteria set forth in Directive 2005/89/EC and expanded on by the European Commission in November 2013. These analyses are the tool used by RTE and public authorities in France to assess the security of supply outlook.
Though the regulatory warning threshold is not exceeded over the period under review, the 2013 Adequacy Forecast Report update points to a gradual and steady decline in margins over the period, and the disappearance thereof from 2017, meaning that security of supply risks will indeed increase in France and Europe.
If capacity retirements or demand growth exceed the levels factored into the Adequacy Forecast Report “Baseline” scenario, then security of sup-ply would decline to a level that is unacceptable with regard to the criterion defined by public authorities.
32Within [General Commission for Strategy and Foresight, (CGSP),2014], see the contribution of Fabien Roques, “European electricity markets in crisis: diagnosis and way forward”.
33[EC, 2012a]
34[GDF Suez, 2013] A general decrease in the load factor of thermal power plants […] is undoubtedly endangering the investments in new conventional plants which are urgently needed by the power system. Even more worrying is the reality that existing thermal power plants, built in an open market system without support schemes (as opposed to out-of-the-market RES) no longer reach the expected profitability and may have to be prematurely decommissioned due to profitability concerns.
29
WHY A CAPACITY MECHANISM IS NECESSARY / 1
the power sector are facing. This initiative, which other energy
companies with the same concerns have since joined, is now
called the “Magritte Group’’. It has called for a Europe-wide capa-
city mechanism that would recognise the value of capacity as a
safeguard.
In concrete terms, European energy companies are experien-
cing a perfect storm, which is endangering security of supply
and the transformation towards a low-carbon economy, as
well as undermining their capacity to attract capital35.
More recently, Union française de l’électricité, the French power
industry’s trade body, mentioned in its response to the public
consultation on energy and environmental State aid how diffi-
cult it had become for energy-only markets to internalise the
value associated with security of supply.
These concerns are shared by public authorities in many Mem-
ber States, including France:
Wholesale electricity prices alone do not provide sufficient
remuneration to ensure the long-term future of existing
peak generation capacities, or to trigger new investment in
generation or demand response capacities. Some plans to
build combined-cycle gas turbine plants in France have been
scrapped (notably in Hornaing), and others are running into
economic troubles36.
Delays and cancellations of new capacity projects are tangible
manifestations of these concerns, as are shutdowns and plan-
ned retirements of existing capacities for economic reasons:
Elsewhere in Europe, economic and market conditions for
combined-cycle gas turbine plants are similar to those obser-
ved in France. Some generators have already announced
plant shutdowns, and other facilities could be mothballed.
The Adequacy Forecast Report takes into account the shu-
tdowns announced and assumes that no new capacities will
be commissioned outside France over the period considered
in the report37.
1.2.2.2 Analysis of the situation
Current discussions about the failures of the energy-only mar-
ket often focus, in Europe, on the problem of the viability of
combined-cycle gas turbine plants (and, in France, on the eco-
nomic space created for demand response). Massive invest-
ments have been made in this type of facility in Europe in recent
years. Today, different studies show that prices on the wholesale
market do not allow operators to cover their total
fixed costs, and they are barely able to cover their
fixed operating costs38. Some thus see capacity
mechanisms as a means of ensuring that operators
can “cover their fixed costs”, since their results in the
market barely “cover variable costs”.
The problems currently seen with capacity remune-
ration are nonetheless probably of a different order,
and are largely due to shocks external to the electri-
city market or inconsistencies between regulatory
tools39:
> The economic crisis, combined with a failure to
anticipate the impact of new energy efficiency
standards and the introduction of shale gas into
the global energy equation, have caused demand
for all energy sources to contract and reversed
the merit order between gas- and coal-fired faci-
lities in Europe;
> The currently low price of CO2 emission certifi-
cates has not offset this evolution of economic
fundamentals;
> The development of renewable energies, driven by support
mechanisms outside the market, has driven energy market
prices down and blurred investors’ perception of prices. These
support mechanisms have led to a massive development of
generation capacities independently of the dynamics of the
electricity market. As a result, investments in generation capa-
cities are being shaped by two different dynamics: one that fol-
lows market signals, and one that follows regulatory incentives.
In a word, generation capacity remuneration problems cannot
all be blamed on energy market imperfections.
As regards demand response capacity, concerns about whether
there was sufficient economic space for it to develop underpin-
ned the proposals made in the Poignant-Sido report to address
the shortcomings of the energy-only market40.
1.2.2.3 Incentives to invest in peak generation
capacities
The current debate in Europe about the profitability of certain
generation assets has a special resonance in France, due to the
specific characteristics of its power sector, and notably the peak
demand phenomenon described earlier.
Peak demand periods are not necessarily a problem if they
reflect what the system needs physically to meet demand and
35Press release: “Call of eight leading energy companies to EU leaders for a revitalised energy policy”, 21 May 2013.
36[French Republic, 2013]
37[RTE, 2013]
38[General Commission for Strategy and Foresight, (CGSP),2014], IHS CERA estimated in a recent report that out of the 330 GW of thermal plants in operation in EU-27 countries, almost 113 GW (about 38%) are at risk of closure within the next three years in the absence of electricity market reforms.
39[Keppler et al., 2013]
40[Poignant-Sido, 2010]
30
if the resources used to meet that demand are eco-
nomically proportionate to the collective benefi ts to
consumers. The phenomenon does, however, pose
some diffi culties in terms of threats to the supply-
demand balance and security of supply, the costs
incurred to meet demand and how eff ectively mar-
ket signals respond to these consumption needs.
Indeed, satisfying peak demand requires having enough gene-
ration and/or demand response capacities available to balance
supply and demand in real time. The energy market must in fact
send the right economic signals to encourage suffi cient invest-
ment to ensure that these capacities will exist and be available.
In its current form, the electricity market has not been able to
create adequate incentives in such situations. This point was
notably made in the Poignant-Sido41 report of 1 April 2010,
which was based on the fi ndings of a workgroup that brought
together all power sector stakeholders under the aegis of two
parliamentarians. The workgroup specifi cally studied trends in
the structure of demand and peak demand in France, and the
report concluded that:
Eff orts to secure fi nancing [for demand response and peak
capacity] exclusively through the energy market are doomed
to fail since, though energy markets can in theory ensure that
peak capacity – and similarly demand response – is profi table,
they do not off er enough visibility. The timing and scale of price
spikes are too random and the risks are too high for investors.
Peak demand is not unpredictable. Adequacy assessments
illustrate the risk posed to the supply-demand balance by cold
spells. RTE’s most recent Adequacy Forecast Report shows that
by 2017, due to the erosion of margins, the French power sys-
tem would not be able to withstand a cold spell of the same
magnitude as that seen in 2012. Given these forecasts and the
fact that the peak demand phenomenon is predictable, it is cru-
cial to ensure that suffi cient generation or demand response
capacities are available to meet power demand when security
of supply is at risk. If security of supply is to be guaranteed, then
the required capacities must be eff ectively available during
these periods.
1.2.3 Existence of investment cycles
As discussed in § 1.1.4, the power sector has specifi c charac-
teristics that are conducive to investment cycles. Such cycles
have been observed in numerous countries:
[S]ome electricity markets running under competitive
rules have experienced periods of excess of investments,
and therefore over-capacity, such is the case of UK with a
large entry of private investors relying on gas-fired power
plants. Others have already experienced long periods with-
out new capacity additions that have ultimately led the
market to under-capacity conditions. Such was the case of
California during the electricity crisis in the summers 2000
and 200143.
Events in California convinced many that additional measures
were required to ensure that suffi cient investments were made
in deregulated electricity markets in the United States.
Investment cycles have also occurred in other contexts. Below
are examples of investment cycle phenomena observed in dere-
gulated energy markets.
41[Poignant-Sido, 2010]
42[Arango & Larsen, 2011]
43 [Olsina et al., 2006]
Figure 5 – Trends in power system reserve margins in Chile, Britain and Scandinavia (diff erent scales)42
0.7
0.6
0.5
0.4
0.3
0.21984
Res
erve
Mar
gin Reserve Margin
Smoothed Value
Chile
1988 1992 1996 2000 2004 2008
0.55
0.45
0.35
0.251988
Res
erve
Mar
gin
Reserve Margin
Smoothed Value
Nordpool
1992 1996 2000 2004 2008
0.35
0.30
0.25
0.20
0.151988
Res
erve
Mar
gin
Year
Reserve Margin
Smoothed Value
England and Wales
1992 1996 2000 2004 2008
31
WHY A CAPACITY MECHANISM IS NECESSARY / 1
The massive investments made in combined-cycle gas turbine
capacity in Europe between 2004 and 2012 can be conside-
red as characteristics of a phase of excess investment, though
subsequent developments moved things in a radically different
direction:
In the EU-27, some 12% of gas-fired capacity could be taken
off line within three years. These plants are nonetheless
crucial to the equilibrium of the system, which will have
to accommodate increasing penetration of intermittent
and unpredictable renewable energy sources. At the same
time, significant investments will have to be made to update
ageing infrastructure. Several large operators facing serious
financial trouble – who have seen their net debt double
in the past five years – will have a hard time meeting this
challenge45.
The phenomena described above have thus been observed in
France and elsewhere in Europe, particularly after the recent
wave of investments in combined-cycle gas turbine plants.
These massive investments have led to a paradoxical situation:
the combined effects of sluggish demand, generators’ failure
to anticipate the impact of new environmental standards and
renewable support mechanisms have created a temporary
situation of excess capacity, but the opposite could happen
suddenly if loss-making plants are retired simultaneously, in
spite of the steep investments made to maintain the supply-
demand balance.
In other words, the phenomenon of alternating phases of
overcapacity and under-capacity appears to be playing out,
creating a risk that many plants will be decommissioned well
before the end of their useful life, suddenly putting security of
supply at risk.
The French capacity mechanism will help regulate the
transition from a situation of overcapacity to one in which
security of supply could be at risk. The analysis above is not
based on a naïve approach to the market, postulating a perfect
functioning of the market where failures have been identified
in theory or in practice, or on a dogmatic challenge to the mar-
ket’s ability to drive investment. On the contrary, the analysis
RTE conducted and submitted to public authorities focuses on
the fact that security of supply risks are moderate for now, but
stresses the instability of this analysis and its significant sen-
sitivity to parameters outside the French power sector. It also
emphasises the peak demand phenomenon in France, this
being the biggest challenge to address and the
one on which public intervention should be based.
The capacity mechanism will need to look in detail
at the characteristics of this phenomenon and
offer solutions for managing it effectively.
44Source: Platts PowerVision
45[CGSP, 2014]
Figure 6 – New combined-cycle gas turbine capacity in Europe44
GW
0
5
10
15
20
25
30
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
France
Norway
Germany
Poland
Austria
Greece
Portugal
Belgium
Hungary
Romania
Bulgaria
Ireland
Slovakia
Croatia
Italy
Slovenia
Cyprus
Latvia
Spain
Czech Republic
Lithuania
Sweden
Denmark
Luxembourg
Switzerland
Finland
Netherlands
United Kingdom
32
1.3 Projected trends in demand over the coming years
Above and beyond the energy market failures described above,
the physical needs of power systems in France and Europe are
also changing dramatically, and these changes could result in
additional market failures.
To achieve the energy transition targets set by the European
Union, the power system must be adapted to accommodate a
huge and growing quantity of renewable energies. This makes
it even more necessary to have flexible technologies – either in
the form of generation or demand response capacities – to gua-
rantee that electricity supply and demand will balance.
An analysis of these trajectories leads to two observations: first,
significant investments will have to be made in the power sec-
tor, bearing in mind that the peak demand phenomenon could
continue due to the increasing role public authorities want
electricity to play to help meet their energy policy objectives
(§ 1.3.1), and second, increasing renewable penetration could
result in a need for more flexibility (§ 1.3.2).
1.3.1 The growing role played by electricity in achieving energy policy objectives
Europe is engaged in a far-reaching energy transi-
tion process. The European Council has set a target
of reducing greenhouse gas emissions by 80 to 95%
from the 1990 level by 2050. The European Com-
mission analysed the implications of this target in
its “roadmap for moving to a competitive low-car-
bon economy in 2050”47. Several industry-specific
roadmaps have followed, notably the “Energy Road-
map 2050”48, in which the Commission examines
the challenges of achieving the Union’s decarbonisation target
while also safeguarding security of energy supply.
The energy sector produces the lion’s share of man-made
greenhouse gas emissions. Therefore, reducing greenhouse
gas emissions by 2050 by over 80% will put particular pres-
sure on energy systems49.
The Energy Roadmap 2050 explores different ways to make the
energy transition happen and lists ten structural changes power
systems will have to undergo under any decarbonisation scenario.
Among these unavoidable structural changes, two are worthy of
particular note: the increasing role to be played by electricity
and the increasing role of renewables in the energy mix.
Electricity plays an increasing role.
All scenarios show electricity will have to play a much grea-
ter role than now (almost doubling its share in final energy
demand to 36-39% in 2050) and will have to contribute to the
decarbonisation of transport and heating/cooling.
[…]
Final electricity demand increases even in the High energy
efficiency scenario. To achieve this, the power generation sys-
tem would have to undergo structural change and achieve a
significant level of decarbonisation already in 2030 (57-65%
in 2030 and 96-99% in 2050).
Renewables rise substantially
The share of renewable energy rises substantially in all scena-
rios, achieving at least 55% in gross final energy consumption in
2050, up 45 percentage points from today’s level at around 10%.
46Given the time constants involved in developing new generation capacity and adapting the power system as a whole, 2017-2018 is the very near future.
47[EC, 2011a]
48[EC, 2011b]
49[EC, 2011b]
The imperfections of the energy market described in academic literature can also be observed in real markets:
> Forward analyses of the security of supply situation in France show that margins will decrease and then be elimi-nated in the near future46;
> It appears that energy markets alone are not guaranteeing the profitability of capacity;
> The existence of investment cycles in power markets has been demonstrated in many cases and countries.
In sum, the failures of energy markets have been characterised and supporting evidence has been gathered from actual operations. These failures raise questions about the ability of a market model first used in the 2000s to adapt to the changing cost structure of generation and demand response capacities. They support the idea that more must be done to guarantee security of supply and the proper economic functioning of electricity markets.
33
WHYACAPACITYMECHANISMISNECESSARY / 1
50[EC, 2011b]
51[EC, 2011b]
52The EU-ETS (EU Emissions Trading Scheme) is the European market for trading carbon emission permits.
53Directive 2009/28/EC.
[…]
In 2030, all the decarbonisation scenarios suggest growing
shares of renewables of around 30% in gross fi nal energy
consumption50.
Energy transition policies have direct consequences for the
functioning of energy markets and the security of supply tar-
get. However, these changes are not meant to be antithetical to
security of supply or economic effi ciency targets, as the Euro-
pean Commission points out in the Energy Roadmap 2050:
There will be no compromise on safety and security for either
traditional or new energy sources. The EU must continue to
strengthen the safety and security framework and lead inter-
national eff orts in this fi eld.
[…]
These create new challenges to power markets in the transi-
tion to a low-carbon system providing a high level of energy
security and aff ordable electricity supplies. More than ever
should the full scale of the internal market be used.
[…]
One challenge is the need for fl exible resources in the power
system (e.g. fl exible generation, storage, demand manage-
ment) as the contribution of intermittent renewable genera-
tion increases. The second is the impact on wholesale market
prices of this generation. Electricity from wind and solar has
low or zero marginal costs and as their penetra-
tion in the system increases, in the wholesale
market spot prices could decrease and remain
low for longer time periods51.
In other words, a tool is needed to effi ciently
guide the energy transition while safeguarding
security of supply and ensuring that electricity mar-
kets function properly.
Policy objectives aimed at reducing Europe’s carbon footprint
and diversifying its energy sources go beyond the integration
of the power sector into the EU-ETS52 mechanism, which in
theory must send the right signals for investing in technologies
with lower greenhouse gas emissions. In accordance with the
“20-20-20” objectives set by the European Council in 2007 and
translated into the “Renewable Energies” directive53 of 2009, all
Member States have identifi ed trajectories for the penetration of
renewable energies and implemented sector policies to support
them. These policies are very much a driving force in investment
dynamics within Member States today, as was discussed earlier.
Some eff orts to reshape the electricity mix have focused on
other technologies. The president of the French Republic has
committed to reducing the share of nuclear power in the mix to
50% by 2025, which should result in some existing plants being
Figure 7 – Trend in installed wind and solar power In France and targets for 2020 (Source: Data on grid connections taken from the Panorama des énergies renouvelables 2013 prepared by RTE, SER, ERDF and ADEEF).
MW
0
5,000
10,000
15,000
20,000
25,000
30,000
2001 2002 2003 2004 2005 2006 2007 2008 2009 20112010 2012 2013 … 2020*
* Estimated contribution of different technologies to the binding target for 2020 set in the National Renewable Energy Action Plan
Wind power connected (MW)
Photovoltaic power connected, cumulative (MW)
34
The implementation of a capacity mechanism in France is
not a standalone initiative. In an effort to correct the imper-
fections of the energy market and meet the requirements of
the energy transition and safeguard security of supply, the
existing model is gradually being strengthened and added
to in order to close all gaps identified. Some of the changes
being made aim to improve how existing electricity markets
function.
The various mechanisms in question were inspired by seve-
ral proposals contained in the Poignant-Sido report54 and the
architecture described in the “target model” for the
European energy market, which notably call for:
> The integration of electricity markets on all timescales and the
development of interconnections (§ 1.4.1);
> The integration of demand and demand response into mar-
kets (§1.4.2);
> The overhaul of renewable energy support mechanisms (§1.4.3);
> The capacity mechanism (§1.4.4).
1.4.1 Ongoing integration of energy markets
European energy market integration requires the continued
development of mechanisms for all timescales, and it must be
ensured that physical infrastructure does not impede the inte-
gration process.
shut down before then. Germany’s Energiewende policy and
decision to phase out nuclear power are another example.
With public authorities directly involved in expanding or reducing
the role of specific technologies, it seems the market will have
to regulate the adjustment of the rest of the electricity mix, or in
other words to drive a series of investments and retirements to
readapt the mix to reflect energy policy changes without jeopardi-
sing the government’s security of supply targets. The implemen-
tation of a capacity mechanism will address this need by crea-
ting more visibility and introducing a feedback loop with public
security of supply objectives into the market architecture.
1.3.2 Growing need for flexibility in European power systems
The penetration of renewable energy sources like wind and solar
power is increasing the level of intermittency in the generation
mix. This does not pose any particular problems while pene-
tration rates are low. Over the long term it will result in a need
for more flexible capacity to offset weather-driven variations in
renewable energy output. More flexibility will be required not
only of generation assets but also of demand response capaci-
ties and, more generally, all technologies that can modulate the
load curve, for instance storage.
What this is creating is a gradual shift from a need to have capa-
cities that are available to a need to have capacities that are both
available and flexible. Discussions held at the European level in
recent months have taken this shift into account, and the need
for greater flexibility is now recognised.
Wind and solar penetration rates in France are relatively low
compared with some European countries like Germany, such
that the balancing mechanism suffices, for now, to ensure ade-
quate flexibility. Capacity needs still focus specifically on peak
demand, which is the biggest unknown for the French power
system and should remain so in the years to come.
The Government has nonetheless set ambitious targets for the
penetration of intermittent energy sources and, over time, the resul-
ting change in the generation mix could create the need for more
flexibility. Bearing this in mind, the capacity mechanism rules must,
from the beginning, factor in the possibility that the fundamentals
of security of supply will evolve and ensure that adjustments can be
made to reflect a change in risk levels. This concern was taken into
account during the drafting of the rules, which acknowledge the
possibility that flexibility needs could change going forward.
54[Poignant-Sido, 2010]
The energy transition represents a major chal-lenge, and the energy market alone will not be able to meet all of the policy objectives set. Intro-ducing a mechanism that acts as a feedback channel with the security of supply target should help public policies efficiently drive investment while also safeguarding security of supply. The need for flexibility, which will only increase going forward, must be integrated into the mecha-nism’s design.
1.4 Efforts to reform market structures in France
35
WHY A CAPACITY MECHANISM IS NECESSARY / 1
1.4.1.1 Introduction of market mechanisms facilitating
internal energy market integration
To improve how electricity markets function, trading conditions
for all timescales must be improved by introducing the same
mechanisms and products across Europe.
Adopted in 2009, the Third Energy Package called for the fur-
ther construction of the internal market applying two comple-
mentary approaches: (i) the introduction of harmonised rules
for all of Europe, and (ii) further integration through pilot initia-
tives covering all timescales.
As a transmission system operator, RTE is particularly interested
in this work and is helping to build the internal electricity market
applying these two approaches.
RTE is notably involved in initiatives, many of them pilots, to
deploy the “target” model over all timescales at the regional
level. Two examples are CWE (Central-Western Europe) and NWE
(North-Western Europe), which have enabled day-ahead price
coupling on markets in these regions. Market participants can
now trade electricity from France to Finland and from Great Bri-
tain to Germany. Market coupling helps optimise energy trading
and the use of interconnections and is making markets more
liquid as it expands.
Where shorter timescales are concerned, the integration of
intraday markets in France, Germany, Austria and Switzerland
on 26 June 2013 was a first step towards the introduction of
implicit intraday cross-border capacity allocation. RTE is also
playing an active role in the NWE intraday project. The intro-
duction of cross-border intraday trading is a priority for the
European Commission, since it will boost the liquidity and effi-
ciency of the internal market.
To enable cross-border trading beyond the intraday period,
RTE is already participating in the creation of cross-border
balancing mechanisms. One example is BALIT (BALancing
Inter TSO), which allows transmission system operators RTE
and National Grid to exchange balancing energy (beyond
required margins). In this sense, BALIT creates more com-
petition within the balancing mechanism by bringing new
participants into national mechanisms, increasing economic
efficiency. An extension of BALIT to the South-West Europe
Regional Initiative (France-Spain-Portugal) is being finalised,
proof that interest in this type of mechanism is widespread.
The mechanism is a precursor for the development of cross-
border balancing energy trading at the European level, as
per the provisions of the Electricity Balancing
Network Code.
1.4.1.2 Integrating the internal market
through interconnection development
Grid infrastructure must keep pace with internal
market integration through market mechanisms. In its most
recent ten-year plan for grid development in continental France,
submitted for consultation in November 2013, RTE included
status reports on interconnection projects under consideration,
which could add 10 GW of exchange capacity between France
and neighbouring countries by 2025.
Of the projects being considered, five have been identified
as Projects of Common Interest, as defined in Regulation
347/201355: the three interconnection projects between
France and the British Isles, in the North Seas corridor: “IFA 2”,
the France-Alderney-Britain project and the planned intercon-
nection between France and Ireland; and two projects in the
North-South-West corridor of Europe: the Savoy-Piedmont
project and the France-Spain interconnection project in the
Gulf of Gascony. The fact that they have earned the Project of
Common Interest label underscores the key role these inter-
connections will play in achieving the objectives of Europe’s
energy policy, building the internal market, integrating
renewable energy and enhancing security of supply, as descri-
bed in Regulation 347/2013.
To meet all of the investment needs outlined in the ten-year
plan and the challenges raised by the energy transition in
France and Europe, annual transmission infrastructure invest-
ments of around 1.5 billion euros are planned over the next
ten years.
RTE is taking an active part in initiatives to conti-nue to build the internal market, improving how it operates and the quality of signals sent to mar-ket stakeholders.
These initiatives involve creating European market mechanisms covering all timescales, as required by target models, and developing new interconnection capacity.
Taken together, these efforts are contributing to the construction of the internal market, as recommended by the European Commission56.
55Regulation 347/2013 on guidelines for energy infrastructure.
56[EC, 2012a]
36
1.4.2 Participation of demand response in energy markets
To continue to build the internal market and meet the challenges
associated with the energy transition and security of supply,
demand response must be allowed to play a bigger role in energy
markets. Much progress has been made in this area in France,
which has taken a proactive approach to developing demand-
side management: as the result of a four-year programme, all
markets (energy, capacity, reserves and system services) will be
open to demand response with effect from 1 July 2014.
The Commission has voiced concerns that Member States are
not sufficiently tapping the potential of the demand side, which
it says could represent 60 GW of peak capacity (or 10% of total
peak demand in Europe).
The potential of the demand side in markets is currently
underutilised. Consumers have traditionally been considered
passive users, rather than an influential part of the energy
market. Changes in the supply side, particularly increases
in “variable” wind or photovoltaic power generation, require
more flexibility in energy networks. Changes to consump-
tion patterns, coming from energy efficiency, local energy
sources, and demand response solutions can provide such
flexibility and will be crucial for effectively matching supply
with demand in the future57.
The European Commission also expressed its attachment to the
participation of demand in energy markets, noting that Member
States are required by Directive 2012/27/EU on Energy Effi-
ciency58 to allow demand-side participation in markets.
In France, the Poignant-Sido report proposed a series of changes to
allow demand to participate in all markets, over all timescales. These
changes are being implemented in the French market to ensure
that demand response can participate and that the European Com-
mission’s recommendations are complied with to the letter.
The sections below describe briefly how the demand side can
participate in the French market. A more detailed presentation
can be found in chapter 10 of this report.
1.4.2.1 Participation of demand in the balancing
mechanism and the provision of reserves and
system services
Some types of demand response (industrial firms
connected to the public transmission system) have been
remunerated through the balancing mechanism since it was
first created in 2003.
RTE has been promoting different experiments since 2007,
under the aegis of CRE, to take better advantage of the demand
side potential:
> To encourage the aggregation of consumers’ potential to
modulate the load curve, RTE introduced the concept of the
demand aggregator in 2007, and has since then been working
to remove technical barriers to aggregation;
> An experiment launched in 2007 allows distributed demand
response to participate in the balancing mechanism, thanks
to the aggregation of residential demand (some representing
less than 1 kW).
A more recent experiment in Brittany aims to extend opportu-
nities to participate in the balancing mechanism to generation
or consumption sites that are not injection sites for the public
transmission system: they can submit balancing offers repre-
senting up to 1 MW instead of 10 MW. These offers can be acti-
vated to resolve certain grid congestion situations.
Since 2008, it has also been possible for demand response to
enter into rapid and complementary reserves contracts, as
per the provisions of article L.321-11 of the Energy Code. This
article stipulates that RTE may enter into rapid and complemen-
tary reserves contracts with generators and suppliers that can
be activated on the balancing mechanism. These contracts are
entered into based on procedures that are “competitive, non-
discriminatory and transparent”. RTE is also organising specific
tenders for demand response capacity that can be activated
through the balancing mechanism.
Lastly, specific mechanisms have been set up to allow the par-
ticipation of demand in short-term market mechanisms other
than the balancing mechanism (interruptibility contracts, speci-
fic tenders for demand response capacity).
As regards ancillary services, the new regulatory framework in
effect since 1 January 2014 calls for a gradual increase in eligible
volumes starting on 1 July 2014.
1.4.2.2 Participation of demand
in the energy market
Demand response can represent a new means of preserving
the supply-demand balance over the short and long terms. Its
integration into the energy market therefore requires specific
provisions to ensure that capacities can be effectively deployed
57[EC, 2013a]
58[EC, 2013a]
37
WHY A CAPACITY MECHANISM IS NECESSARY / 1
over different timescales (day-ahead or intraday basis) with no
discrimination vis-à-vis generation capacity.
Demand response capacities can be remunerated “implicitly”,
through private optimisation of supply portfolios. This approach
is widely used in Europe, to different extents. Explicit valuation
requires going through the energy market and is only possible
in a few countries (for instance the United States). This second
option is now available in France thanks to the NEBEF mecha-
nism (block exchange notification for demand response), ope-
rational since 1 January 2014, which allows demand response
capacities to compete with generation capacities in the energy
market.
The NEBEF mechanism implemented by RTE thus complements
the market architecture by introducing new ways to value
demand response. It allows demand-side operators to leverage
the flexibility of consumption sites to take full advantage of
short-term optimisation opportunities, since a site that reduces
its consumption can benefit directly or through a demand-side
operator from any differential between market prices and supply
prices over the same period. This makes the load curve more
flexible, including when sites are on regulated tariffs or have
entered into fixed-price supply contracts on the market.
By creating a level playing field for all stakeholders, these new
opportunities are also boosting competition within the energy
market.
In this regard, the introduction of the NEBEF mechanism by
RTE should help meet the public policy objectives set in France
and Europe for reducing energy use. For instance, the NEBEF
mechanism has made France a pioneer in implementing the
provisions of article 15.8 of the Energy Efficiency Directive of
25 October 2012.
1.4.3 Reform of renewable support mechanisms
Renewable power generation technologies have witnessed
significant growth over the past ten years thanks to support
mechanisms that offer substantial incentives. This was notably a
response to the binding renewable energy targets set by Europe,
where renewable energy sources are to represent 20% of gross
energy consumption by 2020. The EU’s objective is adapted to
each Member State: in France, renewable energy sources are
to make up 23% of gross domestic energy consumption by
2020. Member States are free to create support mechanisms to
ensure that objectives are met.
Different kinds of support mechanisms are found in Europe.
Spain has for instance opted for a premium on top of the
market price. However, a large majority of European countries
initially chose a price-based support mechanism – the feed-
in tariff – that locks in purchase prices for renewable power
over long periods (10 to 15 years on average). The incentives
created by these mechanisms are very substantial, as gene-
rators receiving subsidies are protected not only from market
price risks but also from quantity risks, since all of the elec-
tricity they generate must be purchased and they benefit
from priority dispatch to the grid, in compliance with current
regulations.
The architecture of feed-in tariffs has created economic distor-
tions in markets, as evidenced by the periods of negative prices
seen in France and Germany (when prices are negative, genera-
tors are paid to inject electricity and consumers are remunera-
ted for consuming it). The underlying causes of negative prices
are varied and concomitant. The markets in question have also
seen a structural decrease in electricity prices and base-load
prices that have in some cases risen above peak-load prices.
Low electricity prices have led some operators to temporarily
take generation units offline, since prices failed to cover their
costs. Though these problems cannot be blamed exclusively
on renewable support policies, there is no denying that support
mechanisms that are completely disconnected from power
market dynamics only exacerbate the failures already present in
a perfect energy-only market.
The European Commission reiterated recently that Mem-
ber States’ energy policies must be properly designed. It also
stressed that support mechanisms should be compatible with
electricity markets, and even suggested that feed-in tariffs could
be scrapped and replaced by instruments that are more like
market mechanisms:
France is taking a proactive approach to deve-loping demand response capacities: after four years of efforts, all markets (energy, capacity, reserves and ancillary services) will be open to demand response by 1 July 2014. RTE’s leading role in implementing these structural changes is widely recognised.
Taken together, these actions are helping address security of supply and energy transition chal-lenges by making the load curve more flexible to ensure that consumer needs will be met over all timescales.
38
Any support that is still necessary should there-
fore supplement market prices, not replace them,
and be limited to the minimum needed. In practice,
this means phasing out feed in tariff s which shield
renewable energy producers from market price
signals and move towards feed in premiums and
other support instruments, such as quota obligations,
which force producers to respond to market prices59.
While the European Commission was conducting its analysis,
France launched a broad consultation mid-December 2013 on
potential changes to support mechanisms, asking stakeholders
to respond to a series of questions about the effi cacy of the
various mechanisms possible and the target models to be deve-
loped going forward. The purpose of this consultation is indeed
to modify existing mechanisms to make them compatible with
the electricity market.
The President of the Republic also emphasised the need to
make changes to the forms of support available to renewable
energy sources (RES). The goal is to promote their integration
into the power system and favour their development over the
long term, while ensuring a more effi cient regulation of the
power system and optimising returns on collective invest-
ments in this area. Existing support mechanisms were crea-
ted at a time when RES were just getting started (except for
conventional hydropower). They were appropriate for the
industry’s debut. But the situation has changed since, and the
mechanisms must now be improved upon60.
The consultation closed at the end of February 2014.
1.4.4 Implementation of the capacity mechanism
Introducing a capacity mechanism is a major part of France’s
eff ort to correct the structural shortcomings of the energy mar-
ket and safeguard security of supply, bearing in mind the ambi-
tious policies the energy transition involves.
The mechanism was fi rst proposed in the Poignant-Sido report
of 2010 as a way to complement existing energy market ins-
truments. The report proposed that the mechanism design be
based on a capacity obligation for suppliers as well as a capacity
market61.
French law 2010-1488 of 7 December 2010 reforming the orga-
nisation of the electricity market (NOME Act) incorporated these
proposals from the Poignant-Sido report in article 6, creating a
capacity mechanism in continental metropolitan France.
1.4.4.1 A market mechanism designed to safeguard
security of supply
The term “capacity mechanism” usually refers to any com-
plementary mechanism used in energy markets to ensure
Assessing the economic impact of the capacity mechanism
In compliance with article 20 of Decree 2012-1405, RTE will conduct a series of economic assessments that it will submit to
CRE. The decree stipulates that these assessments are to focus notably on “the integration of the capacity mechanism within
the European market”, its “interaction with the mechanisms in place in these countries”, and “improving the functioning of the
capacity mechanism”.
RTE’s studies are to include an assessment of the economic impact of various market models, including the energy-only market
and the French capacity mechanism. Economic effi ciency will notably be measured based on each market model’s ability to
coordinate investors’ decisions, using a comparative approach. Simplifi ed models – particularly of investment cycles – are docu-
mented in the academic literature and can be useful in illustrating the phenomena at work and magnitude of the stakes, both in
terms of economic effi ciency and security of supply. Once the capacity mechanism rules have been published, the parameters
of the models can be aligned with those of the actual mechanism.
In addition to being submitted to CRE, these assessments will be made public to promote a broader understanding of the eco-
nomic role the capacity mechanism will play in the design of the French and European electricity markets62.
59[EC, 2013b]
60See chapter 4 of this report.
61Proposals 16 and 17.
62[French Department in charge of Energy and Climate (DGEC), 2013]
Guaranteed feed-in tariff s in France are currently being reformed at the initiative of the Energy Minister. The review of existing support mecha-nisms is still under way and should result in subs-tantial modifi cations to the law, favouring instru-ments that are compatible with the creation of the internal energy market.
39
WHY A CAPACITY MECHANISM IS NECESSARY / 1
remuneration not based directly on energy generated. Howe-
ver, this definition might be interpreted to mean that the ulti-
mate goal of the mechanism is to provide additional revenue
for generators, or even to compensate existing plants for some
stranded costs resulting from changes in market fundamentals
or renewable support policies.
A mechanism designed solely to ensure additional revenue for
generation plants, irrespective of the actual level of security of
supply, would be inefficient. Indeed, it could end up funding
excess capacity by artificially inflating investment incentives,
which would skew market fundamentals and incentivise players
to try to secure rents (speculative investments). Conversely, if
additional remuneration is improperly calculated, the mecha-
nism might not be able to safeguard security of supply. The
European Commission has expressed concerns about such
issues63:
In liberalised markets, investments are not guaranteed by
the State. Only where there is a real threat to generation ade-
quacy and security of supply as a result of closure or mothbal-
ling does the financial viability of existing plant become a mat-
ter of public concern. It is very important that there should
not be state support to compensate operators for lost income
or bad investment decisions.
[…]
One particular concern about market wide capacity mecha-
nisms is that they can over reward generation which was
already financially viable.
[…]
establishing the correct value for capacity payments is
difficult and open to accusations of political interference.
Neither can it be assured that required capacity will be
delivered (particularly given regulatory uncertainty asso-
ciated with the setting of the payment) or alternatively that
excess capacity will not result from the scheme resulting in
overcompensation.
[…]
the chosen mechanism [should] ensure that identi-
fied adequacy gap will be filled while avoiding risks of
overcompensation.
To avoid this twofold threat of economic inefficiency and the
absence of real security of supply guarantees, the mechanism’s
design must focus not on providing additional revenue to gene-
ration plants but on safeguarding security of supply. In other
words, rather than a capacity remuneration mechanism, what
is needed is a mechanism that rewards each contribution to
security of supply in proportion to its coverage of
system needs.
If this is achieved, then the mechanism will merely
internalise in full – without going beyond that – the
positive externality represented by an operator
making available capacity that can be effectively dispatched
when supply in the power system is tight. Such a mechanism
would be justified by economic theory and compatible with
market principles if properly designed.
In its report on the European power system of January 2014,
the General Commission for Strategy and Economic Forecasting
notably alludes to the need to complement the electricity mar-
ket and assign a value to security of supply through an additio-
nal, dedicated mechanism:
The most important point may be that many recent market
reforms involving the implementation of “capacity mecha-
nisms” suggest that most governments consider security of
supply to be essential to the economy, so much so that a spe-
cific mechanism is required to safeguard it.
[…]
The current debate about capacity mechanisms focuses on
the fundamental problem that energy-only markets do not
create the right incentives for long-term investments and
cannot guarantee that there will be sufficient reserve capa-
city to preserve the equilibrium of the system under all cir-
cumstances. More specifically, most governments have expli-
cit or implicit targets when it comes to the number of power
outages they estimate consumers would willingly accept […]
and today’s energy markets do not have a mechanism to gua-
rantee that the investments required to meet this dependabi-
lity objective will be made64.
1.4.4.2 A mechanism that encourages the investments
the energy transition will require
As discussed above, the energy-only market is designed first
and foremost to create an economically efficient system: it will
not contribute to the achievement of governments’ sustainable
development objectives. Consequently, the energy market
needs an additional instrument if it is to guide the energy transi-
tion and stimulate the investments required to meet this energy
policy goal.
In its submission to the European Commission’s public consulta-
tion on the draft guidelines on environmental and energy State
aid, Eurelectric emphasised the role capacity mechanisms can
63Excerpt from [EC, 2013]
64[General Commission for Strategy and Foresight, (CGSP), 2014]
40
play in meeting the challenges posed by the energy transition,
notably the need to accommodate a high level of renewable
generation on the power system:
The implicit assumption of the guidelines is that ensu-
ring a competitive, sustainable and secure energy system
can be achieved primarily through an energy-only market
model. EURELECTRIC considers that with moving towards
a low-carbon energy system with a high level of variable
renewables penetration, a fully-fledged investigation into
the need for developing a new market design will be crucial
to tackle the current challenges within the electricity sys-
tems related to generation adequacy and security of sup-
ply. The need for reviewing the market design has already
been recognised in some member states facing growing
generation adequacy problems in view of high level of RES
penetration and some cases, higher peak demand. There
is growing evidence that in some regions move towards
a market design based on markets for both energy and
capacity might be needed.
A capacity mechanism can thus be an efficient tool for driving
the energy transition in that it guarantees the same rewards for
the contributions of generation and demand response capaci-
ties, and for those of existing and new capacities.
The justifications for choosing a market-wide capacity mecha-
nism for France are outlined in chapter 2 of this report.
Suffice it to say here that this type of mechanism sends eco-
nomic signals to all market stakeholders and avoids locking in
economically inefficient generation plants that make no contri-
bution to security of supply.
In this sense, the proposed capacity mechanism should limit
unnecessary investments in new generation capacities and
guarantee the fair remuneration of existing assets.
1.4.4.3 Taking into account the physical needs of the
power system
For a mechanism to generate signals that are proportionate to
security of supply and energy transition objectives, it must cor-
respond exactly to what the energy system needs physically to
ensure security of supply. It must guarantee that sufficient quan-
tities of the different characteristics required in a given situation
are present in sufficient quantity: capacity, flexibility,
etc. ENTSO-E, the European Network of Transmis-
sion System Operators, also promotes this idea65:
PRINCIPLE 1: SHIFTING THE FOCUS TO THE PHYSICAL
NEEDS OF THE SYSTEM
For ENTSO-E, the decision to implement CRM in addition to
electricity markets should be preceded by a careful assess-
ment of the physical needs of the system. In particular, with
the advent of significant variable renewable generation, secu-
rity of supply consists of diverse challenges: long term ade-
quacy, flexibility, voltage control, transient stability, etc. Those
issues are much more complex and require thorough tech-
nical analysis. It is only on the basis of such a diagnosis that
possible solutions can be assessed.
Only TSOs, in-conjunction with national regulators, can pre-
cisely forecast the nature of those future security challenges.
European TSOs must therefore be part of all up coming
debates concerning CRMs and market design.
RTE applied these principles in all of its proposals and recom-
mendations throughout the consultation on the French capa-
city mechanism. Its positions on the capacity mechanism
are underpinned by a conviction that market design must be
shaped to serve consumers while reflecting the operational
constraints and physical needs of the system. This focus on
building a market based on the real value of products traded,
rather than the specific demands of some stakeholders,
extends beyond the capacity mechanism: it is a general prin-
ciple of market design.
The French capacity mechanism is designed to meet the security of supply targets set by public authorities. In France’s case, this means com-pensating all capacity and measures that help preserve the supply-demand balance during peak periods, without guaranteeing remuneration irres-pective of security of supply needs.
The mechanism must be strictly proportional to security of supply considerations. These consi-derations may evolve over time, for instance if the challenges raised by some renewable energy sources become more significant. The proposals made by RTE based on the consultation integrate the fundamental building blocks to enable such changes.
65[ENTSO-E, 2012]
41
WHY A CAPACITY MECHANISM IS NECESSARY / 1
Capacity market
Capacity market
Capacity payment (since 2007)
Capacity payment(since 1998)
Capacity payment (since 2011 –
currently suspended)
Strategic reserve
Strategic reserve
Strategic reserve(phase-out 2020)
Capacity payment(capacity marketplanned for 2014)
Capacity payment(since 2006)
Figure 8 – Map of capacity mechanisms in Europe (2013)(Source: ACER)
No capacity mechanism
Capacity mechanism proposed/under consideration
Capacity mechanism operational
1.5 Capacity mechanisms in Europe
France’s decision to create a capacity mechanism to ensure that
the security of supply criterion is met is not an isolated initiative.
The number of European countries that have introduced or are
planning capacity mechanisms is growing, reflecting the possi-
bilities offered by Directive 2005/89/EC66. In some countries,
the decision was taken long ago (Spain, Sweden, Finland, Ireland
and, to a lesser degree, Italy). Others (United Kingdom) have
already made considerable progress in their plans,
and should be organising their first capacity auc-
tions in 2014. The idea is still being considered in
some Member States, and decisions could be made
within the coming months. The map below, crea-
ted by ACER67, offers an overview of the capacity
mechanism situation across Europe.
The additional information RTE gathered for the purposes of
its own studies or collected via ENTSO-E shows that even more
countries have or plan to implement capacity mechanisms. For
instance, it appears that Bulgaria has a capacity remuneration
mechanism in place, and also uses one-off tenders68. There is
also evidence to suggest that capacity mechanisms are being
weighed in countries not included in this category on the ACER
map, Poland being a case in point69.
These examples show the degree to which capacity mecha-
nisms have become a reality in Europe. With this in mind, the
potential impact of the creation of a capacity mechanism in
France must be put into perspective, as two neighbouring
countries (Italy and Spain) have had mechanisms in place for
some time, and two others (the United Kingdom and Belgium)
are creating their own mechanisms.
Moreover, capacity is not remunerated under the exact same
terms in all countries, even in the absence of a clearly identi-
fied capacity mechanism. The reserves used by transmission
system operators in Europe vary greatly from one country to
the next, as do their remuneration procedures. For instance,
Germany does not have a capacity mechanism for now, though
one is under consideration70. However, the operating reserve
volumes German system operators have under contract are
almost twice as high as in France71. There are other forms of
reserves as well, such as Reserve Power Plants (ResKV), a type
of strategic reserve used to relieve congestion on the grid in
66Directive 2005/89/EC of 18/01/2006 concerning measures to safeguard security of electricity supply and infrastructure investment.
67[ACER, 2013]
68The prices of electric power sold by producers (…) may include the components: a capacity charge and a commodity charge. [SEWRC, 2004]. [BG, 2011]
69The work on introducing a law for a capacity mechanism, which guarantees producers a price for generating backup electricity, may start in the first quarter [of 2014], Marek Woszczyk, the head of Urzad Regulacji Energetyki, said in Warsaw. Bloomberg, 07/10/2013.
70See, for example, [BDEW, 2013]
71Discrepancies in reserve volumes between the countries reflect structural differences in market architectures and reserve usage.
42
exchange for capacity remuneration. The new government in
place in Germany since November 2013 is weighing the issue,
and many proposals have been submitted. One came from
BDEW (Bundesverband der Energie und Wasserwirtschaft72,
the German association of energy and water industries), which
is suggesting a decentralised and voluntary market-wide
capacity mechanism. BDEW’s proposal is one of a handful of
options the German government is considering implementing
at the federal level.
The bottom line is that capacity mechanisms have become a
reality in the European energy landscape. Chapter 9 of this
report discusses the interconnection of the French capacity
mechanism with the systems implemented in neighbouring
Member States.
1.6 Conclusions
The introduction of a capacity mechanism will profoundly
change the design of the electricity market and address the
shortcomings of its current organisation. The goal is to ensure
that investments are made in capacities that can be dispatched
during periods of peak demand and, more generally, in keeping
with energy transition objectives, to reward investments that
provide benefits to the power system proportionately to the
benefits provided to society.
In its current form, the European electricity market is based on
the theoretical model of the energy-only market with provisions
allowing stakeholders to trade energy in a market characterised
by free and undistorted competition. The energy-only market
ensures that generation capacity dispatched is remunerated at
the marginal production cost of the mix. Prices formed on this
basis generate only one economic signal, which is considered
sufficient to optimise generation schedules in the short term
and determine the optimal size of the mix for the long term,
including during shortage situations. Within this theoretical
framework, security of supply is supposed to be guaranteed by
the market, thanks to an economic signal that assigns a value
to capacity.
However, the academic literature identifies imper-
fections that can be empirically observed in today’s
energy markets.72[BDEW, 2013]
Many Member States already have or are introdu-cing capacity mechanisms to address existing or potential threats to security of supply. France's initiative is thus not unique: on the contrary, it is part of a broader trend to reform the architecture of electricity markets in Europe.
Because Member States have different reasons for implementing capacity mechanisms, the mecha-nisms they create reflect specific national charac-teristics and are not all alike. One challenge when such mechanisms are being introduced in Europe is to ensure that they are compatible with the internal electricity market nearing completion. Coordina-tion between neighbouring Member States should thus be sought. Just as it is taking an active part in preparing the ENTSO-E Network Code and regional initiatives overseen by regulators, RTE will make every effort to help find solutions that make capacity mechanisms compatible with the internal market.
First, the hypotheses used in the theoretical analysis of energy-
only markets are not realistic in terms of the expected behaviour
of participants or the operating constraints created by the gene-
ration and circulation properties of electricity.
Second, security of supply is a public good and is not automa-
tically guaranteed by the market due to externalities: it benefits
all once it has been produced, but when this is not the case all
network users are affected, regardless of the value they place on
it. This reduces investment incentives as it is not in the interest
of market stakeholders to invest in some capacities that would
benefit security of supply, since the profits they would generate
are lower than the benefit for society.
Lastly, a theoretical analysis of the energy-only market suggests
that a long-term equilibrium will be achieved based on a static
approach. This equilibrium is rarely achieved with a more realis-
tic dynamic approach. Cycles of investment in power capacity
are characterised by a sort of viscosity when it comes to adding
or retiring generation facilities. As these cycles alternate, succes-
sive waves of overcapacity and under-capacity are observed, at
the expense of security of supply and the system’s economic
efficiency. A detailed look at the theoretical framework of the
energy-only market raises questions about the market’s ability
to effectively guarantee security of supply. This conclusion is
also supported by a factual analysis of the situation.
43
WHY A CAPACITY MECHANISM IS NECESSARY / 1
If the imperfections of the energy market are to be addressed
and the requirements of the energy transition and security of
supply met, a tool must be available to effectively encourage
investment and complement the signals generated by existing
mechanisms. It is with this in mind that France is currently imple-
menting a series of market instruments. These instruments are
intended to improve how electricity markets function, without
being considered substitutes for one another. It is therefore
crucial that they be coordinated. Key undertakings include ena-
bling the integration of electricity markets over all timescales,
developing interconnections, allowing demand and demand
response to participate in markets, overhauling renewable sup-
port mechanisms and implementing a capacity mechanism.
Taken as a whole, these efforts aim to make the existing energy
market more efficient and add the dimensions that are lacking. In
this regard, a market mechanism focusing on security of supply
must reward the contributions of generation and demand res-
ponse capacities to security of supply, i.e. the contributions these
capacities make when the equilibrium of the power system is at
risk. The mechanism is not designed to provide additional reve-
nue to generators or demand-side operators irrespective of real
security of supply needs. In specifically seeking to address the
challenge posed by peak demand, the French mechanism will
have to make every effort to integrate demand response, which
can be an efficient way to ensure the system has all the capacity
it needs. The creation of a capacity mechanism is thus perfectly
compatible with the policy of encouraging demand response.
Many Member States have introduced this type of mechanism.
France’s initiative is in keeping with this trend. However, analysis
of these mechanisms reveals that they are very heterogeneous
and incorporate the full spectrum of possible solutions in terms
of market design.
The next chapter focuses on the different options available
when implementing capacity mechanisms and the specific
choices made by public authorities in France.
France already has the instruments required to measure secu-
rity of supply. They can be used to conduct assessments before
implementing public policies to correct shortcomings. These
include adequacy assessments like those found in RTE’s Ade-
quacy Forecast Reports. Such assessments have revealed the
existence of a peak demand phenomenon in the French power
system, and the fact that peak demand is growing faster than
electricity demand as a whole. They have also shown that safety
margins are gradually decreasing and will be eliminated in 2017.
Security of supply must therefore be carefully monitored in
France.
These considerations must be weighed against the difficulties
many generators and demand-side operators are having in
earning adequate remuneration. At a time when the econo-
mic fundamentals of the sector are changing considerably, the
energy-only market can no longer drive investment efficiently.
The existence of economic cycles is also corroborated by recent
trends in the generation mix.
Looking beyond the failures observed in energy markets, the
physical needs of the European and French power systems are
also changing dramatically, and this could exacerbate market
failures. If the ambitious objectives set by the European Union
for the energy transition are to be met, the power system will
have to play a greater role: it will need to adapt and accommo-
date a huge and growing quantity of renewable energies. This
makes it all the more necessary to have flexible capacities, whe-
ther supply- or demand-side resources, to guarantee that elec-
tricity supply and demand will be balanced.
An analysis of these trajectories leads to two observations: first,
significant investment will have to be made in the power sec-
tor, bearing in mind that the peak demand phenomenon could
continue due to the increasing role public authorities want elec-
tricity to play to help meet their energy policy objectives, and
second, increasing renewable penetration could result in a need
for even more flexibility.
44
When failures have been identified in a market
providing a public good, public authorities are jus-
tified in taking measures to correct them75. This
public intervention can take the form of regulatory
measures76 or economic instruments that lead
2.1 Why a quantity-based market mechanism
The architecture for the French capacity mechanism was defi-
ned in several stages: the general principles were laid out in the
NOME Act of December 2010, after which the overall organi-
sation of the mechanism was set forth in the implementation
decree of December 2012, drawing in part from
the recommendations in RTE’s report to the Energy
Minister of October of 201174.
2. CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE
In adopting a capacity mechanism to ensure security of sup-
ply, public authorities can choose between different market
designs, and their decisions are shaped in large part by the
country’s specific context. The Agency for the Cooperation
of Energy Regulators (ACER) proposed a classification of the
different types of public intervention possible in its report on
capacity mechanisms and the internal market73. The options
considered for the French capacity mechanism are repre-
sented in the taxonomy below:
73[ACER, 2013]
74[RTE, 2011]
75See Chapter 1 of this report.
76Pollution standards are an example.
77Intermediate forms also exist, for instance a quantity target with a price condition.
Figure 9 – Taxonomy of capacity mechanisms
The capacity mechanism that emerged from this process is
adapted to France’s situation and the specific challenges it is
intended to address. The design corresponds to a mechanism
that is market- and quantity-based, market-wide (applying to
all capacity) and decentralised. These three defining characte-
ristics are discussed in sections 2.1, 2.2 and 2.3 of this chapter,
respectively.
economic actors to change their behaviour. Other than in the
case of regulatory measures (the thermal regulation of 2012,
energy labelling, new energy standards), public intervention
involves introducing one of two types of economic instrument:
price-based regulations or quantity-based regulations77. Public
Price-basedQuantity-based
One-off tenders
Strategic reserve
Capacity obligation
Decentralised
Capacity auction
Centralised
Capacity mechanism
Capacity payment
Targeted mechanism Market-wide mechanism
45
CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE / 2
intervention is managed differently with these two options.
Price-based regulation involves using instruments to set a
price, but volumes then depend on private decisions. With
quantity-based regulations, instruments are used to define
quantities but prices are determined by the market (market-
based approach). Academic literature abounds with analyses
of this aspect of public intervention.
Many examples exist of choices that have been made between
price- and quantity-based regulation in the energy sector,
and more specifically within the context of the energy tran-
sition. Renewable support policies have been widely exami-
ned: some countries opted for price-based regulation in the
form of guaranteed purchase prices, while others introduced
quantity-based instruments such as RES quotas in the United
States [Renewable Portfolio Standard]. The CO2 emissions
trading scheme is another recent example of quantity-based
regulation.
This distinction between price- and quantity-based regulations
is equally important when it comes to security of supply. Price-
based regulation is already used through capacity payments78.
And capacity markets are a form of quantity-based regulation.
As such, the first choice that had to be made in designing the
French capacity mechanism was between price- and quan-
tity-based regulation.
During the consultation of 2011, several market stakeholders
expressed a preference for capacity payments, citing this
type of mechanism’s benefits in terms of simplicity and secu-
rity for investors. They also noted that capacity payments
were used in other European Union Member States (Spain,
Italy, Ireland, etc.).
Price-based mechanisms nonetheless present several draw-
backs that have been described in theoretical terms79, and the
practical consequences of which were beginning to become
visible in Europe at the time. Difficulties in determining an
appropriate guaranteed purchase price for some types of
renewable energy led to erratic development trends, inclu-
ding a surge of investments in photovoltaic power in France
late in 2010. Demand was also declining during this period,
underscoring the possibility that capacity payment mecha-
nisms could subsidise overcapacity providing no value to
consumers.
The fact is that price-based mechanisms offer few levers on
the service provided since everything depends on how well
authorities determine the purchase price, often
working with an asymmetry of information. As ACER
notes:
It is difficult to determine the right payment level
and to determine the effect of the payments;
the mechanism provides no guarantee against
extreme spikes. This is probably why Capacity
Payments are often combined with price caps in
the wholesale markets in order to avoid extreme
prices. An important drawback is that Capacity
Payments are not well targeted; it is not clear
what consumers pay for and what they get in
return80.
It was due to these considerations that the capa-
city payment solution was ruled out, and French
lawmakers opted to implement a mechanism
based on quantities and a market price. This deci-
sion was consistent with the recommendations of
the Poignant-Sido report:
Proposal 16: Plan the introduction of a capacity market in
France81.
This preference for a quantity-based mechanism over a capacity
payment scheme has since been supported in the European
Commission guidelines, which expressed serious concerns
about the use of capacity payments:
Establishing the correct value for capacity payments is
difficult and open to accusations of political interference.
Neither can it be assured that required capacity will be
delivered (particularly given regulatory uncertainty asso-
ciated with the setting of the payment) or alternatively that
excess capacity will not result from the scheme resulting in
overcompensation.
[…]
Mechanisms based on capacity payments do not ensure that
the identified adequacy gap is filled and create significant
risks of overcompensation.
Recent trends in Europe make the decision to implement a
market mechanism in France seem all the more relevant: for
instance, Italy and Spain are both moving away from capacity
payments and towards a quantity-based mechanism.
78A capacity payment is a fixed price paid to a class of economic agents for capacity that is available. ACER uses the following definition: “Capacity Payments represent a fixed price paid to generators/consumers for available capacity. The amount is determined by an independent body. The quantity supplied is then independently determined by the actions of market participants.”
79[Weitzman, 1974] “Quantities are better signals for situations demanding a high degree of coordination.”
80[ACER, 2013]
81[Poignant-Sido, 2010]
46
Once the decision in favour of quantity-based regulation was
confirmed, a choice had to be made about the scope of the
mechanism. Indeed, capacity mechanisms differ depending on
whether all or only part of generation and demand response
capacities are eligible to participate. This was one of the key
criteria ACER used to classify capacity mechanisms in its taxo-
nomy82: it drew a distinction between targeted mechanisms and
market-wide mechanisms (applying to all capacity).
Targeted mechanisms apply to a specific and limited amount
of generation capacity. The two main types of targeted mecha-
nisms are strategic reserves and one-off tenders. With strate-
gic reserves, capacities are “set aside” and dispatched only in
situations where load curtailment would otherwise be required
(§ 2.2.2.2). One-off tenders offer a solution for situations where
capacity shortages appear possible (§ 2.2.2.3). Market-wide
mechanisms apply to all supply- and demand-side capacities
that already exist or are planned (new capacities).
In the Staff Working Document on adequacy accompanying
its Communication of 5 November 2013 on State intervention
in electricity markets83, the European Commission seems to
lean in favour of targeted capacity mechanisms. It is therefore
important to consider this option, especially as, since markets
were deregulated, the legal framework in France has allowed
the State to react to perceived threats to security of supply by
organising targeted auctions, as part of the Multi-Year Invest-
ment Plan (programmation pluriannuelle des investissements)
instituted by the law of 10 February 2000.
The appropriate scope for the French capacity mechanism was
further discussed in 2011 based on the provisions of the NOME
Act, which anticipated a market-wide capacity mechanism. In
the conclusions of its report published in 2011, RTE supported
the inclusion of all capacities in the mechanism84:
For the mechanism to provide a real guarantee
in terms of security of supply, it is crucial that all
capacities participate in it and that suppliers make
availability commitments for all of their capacities.
If some capacities are excluded, then the scheme
would not deliver much more than is currently
possible, and this could create legitimate concerns
about the need for the mechanism. A mechanism
that only covered new capacities would have
82[ACER, 2013]
83[EC, 2013a]
84[RTE, 2011]
2.2 Why a market-wide capacity mechanism
much the same effect as the tenders already allowed
through the Multi-Year Investment Plan.
Public authorities took this recommendation into account and
adopted it in Decree 2012-1405 of 14 December 2012:
All capacity suppliers, or persons mandated by them, are to
present, for each delivery year, a certification request for their
capacities before a deadline set based on the technical cha-
racteristics of the capacities or, for new capacities, the status
of the project.
The choice to implement a market-wide mechanism was made
based on five key objectives: provide real guarantees in terms
of security of supply (§ 2.2.1), address market imperfections
and avoid distortion (§ 2.2.2), minimise the cost to consumers
(§ 2.2.3), ensure the mechanism’s economic efficiency in the
presence of investment cycles (§ 2.2.4) and adopt a mechanism
that reflects France’s specific situation (§ 2.2.5).
2.2.1 Provide guarantees in terms of security of supply
The main reason for adopting a market-wide mechanism is that
availability commitments must be secured for all capacities to
guarantee that security of supply is truly enhanced for consu-
mers. This is because security of supply is a public good that
cannot be ensured by specific capacities individually.
When electricity supply is tight, all capacities contribute to mee-
ting all demand, and there is no reason why only some should
be rewarded. On the contrary, because it is impossible to identify
the power plants that contribute specifically to security of sup-
ply, there is no technical justification for a mechanism that does
not reward all capacities.
The approach taken with the French capacity mechanism –
equal consideration is given to the contributions of all capa-
cities to security of supply, taking into account their specific
characteristics and availability commitments – thus provides
the best guarantee to consumers in terms of security of
supply.
47
CHOOSINGTHERIGHTCAPACITYMECHANISMFORFRANCE / 2
2.2.2 Address market imperfections and avoid distortion
To enhance security of supply, a capacity mechanism must
address the energy market imperfections discussed in chapter 1.
Not all mechanisms have the same economic impact, making it
important to identify those that can correct these imperfections
without creating distortions. Below is an analysis of market-wide
capacity mechanisms, strategic reserve schemes and one-off ten-
dering procedures.
2.2.2.1 Economic impact of market-wide capacity
mechanisms
Market-wide capacity mechanisms involve systematically rewar-
ding all contributions to security of supply, though the reward
may be equal to zero. The mechanisms function all the time,
and when demand representing total capacity needs is mat-
ched against supply representing all capacities, it creates a mar-
ket price that refl ects the scarcity of the resource. This type of
mechanism can be implemented within the diff erent types of
architecture discussed in § 2.3.
Market-wide capacity mechanisms create opportunities
to earn additional revenue for all capacities, based on their
contribution to security of supply. This revenue is added to
the inframarginal rent operators earn on the energy market
and makes up for the missing money resulting from imperfec-
tions in the energy market. The figure below shows how the
mechanism functions85 using the example from
chapter 1.
It can be noted that the capacity mechanism cre-
ates the same price duration curve as the perfect
energy-only market except during load curtailment.
A market-wide mechanism associated with a mar-
ket price can, if well designed, address the imperfections of the
energy market without distorting prices.
2.2.2.2 Economic impact of a strategic reserve
mechanism
2.2.2.2.1 Defi nition of a strategic reserve
Strategic reserve mechanisms involve pulling some capacities
out of the electricity market and “reserving” them to be dispat-
ched only in situations where load curtailment would otherwise
be required. In such extreme situations, the energy generated
by reserved capacities is sold on the energy market at a prede-
fi ned dispatch price, usually corresponding to the price cap on
the energy market.
ACER uses the following defi nition86:
Strategic Reserve
In a Strategic Reserve scheme, some generation capa-
city is set aside to ensure security of supply in exceptio-
nal circumstances, which can be signaled by prices in
85A price cap is applied to represent the market's imperfections (see section 2.2.2).
86[ACER, 2013]
Peak VC
VoLL
Peak VC
VoLL
Price cap Price cap
Missing money, decline in inframarginal rent due to price decrease during load shedding
No additional load shedding, price duration curve maintained. Insufficient rent on the energy market, offset by capacity price applied to all capacities
Missing money problem: Price decrease during load shedding
No additional load shedding, peak capacity maintained
Merit order Price duration curve
Quantity (GW)
Price (€/MWh)
Hours of operation
Price(€/MWh)Optimal load shedding
Peak capacity Optimal load shedding
Functioning, optimal case
Inframarginal rent, optimal case
Functioning with market mechanism applying to all capacities
Inframarginal rent with market mechanism applying to all capacities
Figure 10 – Illustration of the merit order and price duration curve for a market-wide capacity mechanism versus a perfect energy-only market
48
the day-ahead, intra-day or balancing markets
increasing above a certain threshold level. An
independent body, for example the Transmission
System Operator (“TSO”), determines the amount
of capacity to be set aside to achieve the desired
degree of adequacy and dispatches it whenever
due. The capacity to be set-aside is procured and
the payments to this capacity determined through
a (typically year-ahead) tender and the costs are
borne by the network users.
In other words, this is a targeted capacity remunera-
tion tool designed to guarantee adequacy in volume
terms, i.e. that load curtailment levels are optimal.
However, for a long-term equilibrium to be achie-
ved, the mechanism must not only restore the opti-
mal level of load curtailment by securing a certain
quantity of reserves, but also allow the capacity that
remains in the market to cover its fixed costs and thus make up
for the missing money.
A strategic reserve mechanism can thus only function pro-
perly under the strict condition that it has enough influence
over energy prices to correct the missing money problem. An
example of the effects a perfectly designed strategic reserve
mechanism would produce is presented in figure 11 below.
It should be noted that the price duration curve under the well-
designed strategic reserve mechanism is identical to the one in
the market at equilibrium with missing money in § 1.1.3.1. On
the other hand, the energy price is higher when reserves are dis-
patched than in the perfect energy-only market.
The missing money for capacities still in the market (not set
aside under the strategic reserve mechanism) is offset in theory
by prices being maintained at the price cap while reserved capa-
city is in use. Inframarginal rents thus cover fixed costs. Incen-
tives to invest or remain in the market are the same as in the
perfect energy-only market87.
For capacities included in the strategic reserve, revenue earned
on the energy market88 is complemented by a fixed component,
typically funded by a tariff surcharge paid by final consumers
(e.g. found on their bills, in addition to charges for energy). This
surcharge is usually fairly low in relation to MWh consumed,
since it is only intended to cover the share of fixed costs borne
by reserved capacity not covered by revenue earned in the
energy market.
2.2.2.2.2 Assessment of the impact of a strategic
reserve mechanism
Strategic reserve mechanisms, especially their parameters and
characteristics, must be perfectly defined to correct market
imperfections and resolve the missing money problem. In par-
ticular, the key parameters used for defining reserves and the
situations in which they are dispatched (reserve quantities, dis-
patch conditions, dispatch price or price offered for reserves on
the market) have a major influence on the mechanism’s ability
to restore balance.
The goal in setting these parameters must be to correct market
imperfections, not to minimise costs to consumers. For instance,
if the missing money problem is not resolved, capacity will conti-
nue to be withdrawn from the market and the strategic reserve
alone will not be able to guarantee security of supply over the
long term, except if it gradually absorbs all capacities in the mar-
ket. This would create what the academic literature refers to as
a slippery slope89.
This analysis suggests that three conditions must be met for a
strategic reserve mechanism to be able to resolve the missing
money problem for all capacities and keep load curtailment at
the optimal level:
> Required reserve volumes must be calculated based
on the optimal energy mix and desired level of load
shedding;
> Dispatching and remuneration procedures must ensure the
remuneration of strategic reserves while also preserving
investment incentives in the energy-only market;
> The mechanism and operator overseeing it must be cre-
dible for the mechanism to function properly and interact
with the energy-only market, which becomes all-impor-
tant when moving from a theoretical framework to the real
market.
Empirical observation shows that these mechanisms are often
implemented to avoid retiring old and polluting power plants90.
In addition to potentially jeopardising the environmental targets
of Europe’s energy policy, this underscores how tricky it can be to
find a virtuous system for selecting capacities for inclusion in the
strategic reserve. It also raises concerns about the terms under
which unprofitable, private assets are procured by public enti-
ties: Are they taken over temporarily, and allowed to return to the
market once economic conditions so permit (in which case the
mechanism would serve to protect operators from price risks)?
If they are taken over permanently, issues could arise when the
capacities are new and have a lifespan of several decades.
87In this case, price signals in the energy market with a strategic reserve mechanism in place are similar to those seen in an energy-only system when capacity is too low and shortfalls too high.
88Strategic reserves are remunerated in the energy market in a rather specific way, since the reserves are always dispatched at a predefined price, usually corresponding to the energy price cap. The remuneration thus always represents an inframarginal rent reflecting the differential between the variable cost of the strategic reserves and the price cap.
49
CHOOSINGTHERIGHTCAPACITYMECHANISMFORFRANCE / 2
The European Commission also lists a series of precautions to
be taken in designing strategic reserve mechanisms91:
[It] is important that [Strategic Reserves] be properly imple-
mented. Union rules on public procurement must be res-
pected and help ensure that there is no overcompensation.
Where strategic reserves are used to keep prices low, this
may result in high emissions from ineffi cient old plants and
discourage the development and deployment of new and
more effi cient technologies, including storage and demand
side response. With market coupling and the introduction of
cross-border intraday trading such a failure would happen
within a common price mechanism and spill over across
borders. It is therefore not only not cost-eff ective but risks
seriously distorting the internal market. This problem can
be avoided when strategic reserves are clearly used only in
the event of the failure of the (short run) wholesale market
to match supply and demand. This requires objective and
transparent criteria as to when strategic reserves can be
deployed.
A well-designed strategic reserve mechanism can correct mar-
ket imperfections. The functioning of this type of mechanism
nonetheless distorts energy prices, since off setting the mis-
sing money results in more frequent price spikes in the energy
market.
2.2.2.3 Economic impact of a capacity
auction mechanism
2.2.2.3.1 Defi nition of capacity auction
schemes
Capacity auctions are a class of capacity mecha-
nism under which total capacity needs are determi-
ned several years in advance and auctions are orga-
nised if additional capacity is needed. The European
Commission refers to this type of scheme as tende-
ring procedures92. The mechanism does not apply
to all capacities93 and tenders are only organised
occasionally94.
2.2.2.3.2 Assessment of a capacity auction
mechanism
One-off capacity auctions can off er public autho-
rities a practical way to intervene quickly to safe-
guard security of supply. In the European Commis-
sion’s words:
A tendering procedure has the advantage
of being relatively easy to organise and will
ensure that investors actually construct the
capacity tendered, and then participate in
the market as normal. New capacity which
89[Finon & Roques, 2013]. See [Stoft, 2002] and [De Vries, 2004] on the theoretical functioning of strategic reserves.
90“Old units can be purchased and kept available.” [De Vries, 2004]“[strategic reserve] provides for keeping old units operational, because they can be sold or leased to the system operator.” [De Vries, 2007]“The TSO can take over old units that the owners have decided to close.” [Finon & Pignon, 2008]
91[EC, 2013]
92[EC, 2013a]
93“Tendering procedure is normally less distortionary and easier to implement than market wide capacity mechanisms.” [EC, 2013a]
94“Properly implemented, tendering constitutes a one off intervention on the market.” [EC, 2013a]
Peak VC
VoLL
Peak VC
VoLL
Price cap Price cap
Missing money, decline in inframarginal rent due to price decrease during load shedding
Inframarginal rent restored through decrease in installed peak capacity/strategic reserve deployed at price cap
Missing money problem: Price decrease during load shedding
Decrease in installed peak capacity – strategic reserve deployed at price cap
Merit order Price duration curve
Reserves
Quantity (GW)
Price (€/MWh)
Price (€/MWh)
Hours of operation
Optimal load shedding
Peak capacity Optimal load shedding
Functioning, optimal case
Inframarginal rent, optimal case
Functioning with strategic reserve
Inframarginal rent with strategic reserve
Figure 11 – Illustration of the merit order and price duration curve under a perfectly designed strategic reserve mechanism versus a perfect energy-only market
50
benefits from the tender continues to participate on the
market. Consequently, it is important that the tender not
be designed in such a way as to distort normal market ope-
ration or production decisions or to distort future invest-
ment decisions95.
Special tendering procedures are thus fundamentally desig-
ned to resolve temporary and clearly identified physical issues.
France already has a similar instrument through its Multi-Year
Investment Plan. It allows public authorities to translate their
energy policy objectives through actions targeting the energy
mix. The existence of this instrument is not being called into
question with the implementation of the capacity mechanism.
Tendering procedures are fall-back measures and thus not
an appropriate solution to the structural imperfections of the
market.
Firstly, they do not structurally modify the economics of elec-
tricity markets, and do not place a specific value on security of
supply. And the missing money problem revealed by econo-
mic theory affects all capacities in the same way96. Therefore,
in an imperfect market where a missing money phenomenon
reduces investment incentives, the creation of new capacities
subsidised by a special tendering procedure would only add to
the profitability problem for all capacities.
Secondly, all capacities contribute to security of supply from a
technical standpoint. The only valid justification for a targeted
capacity mechanism would thus have to be economic, for ins-
tance a missing money problem that is particularly significant
for some plants. In this case the mechanism would be a sort of
specific subsidy granted to certain capacities simply because
they are not profitable. This would run totally counter to the
philosophy of an integrated energy market in which investors
assume the risk associated with their investments and make
decisions about investing in or retiring capacities based on their
revenue forecasts.
A mechanism that only targets some capacities necessarily
creates distortion. This is particularly visible with
selective mechanisms targeting new capacities. In
situations where there are facilities in the market
that are operational and have in some cases only
been in service for a few years but could be retired,
introducing a mechanism that subsidises new capa-
cities exclusively would not seem to make economic
sense and could cause considerable distortion.
The Commission addresses this concern about preventing
distortion when selecting capacities eligible to participate in
mechanisms in its recommendations on the neutrality of capa-
city mechanisms between existing and new capacities97:
In certain situations, it can be more cost-effective to retrofit
or retain existing generation capacity, which would other-
wise shut down, to keep it operational. This can also help
potentially to avoid the lock-in effects of constructing new
(fossil fuel) generation capacity.
Therefore, capacity mechanisms open to capacity retention
as well as new investments, without discrimination between
the two categories ensure cost-effectiveness and minimise
distortion.
The approach adopted by public authorities in France aims spe-
cifically to avoid distortion by giving equal consideration to all
capacities, be they new, older or refurbished.
Lastly, it should be noted that if special tenders are organised
too frequently, investors could begin to wait for the tenders,
which would be counterproductive:
[T]here is still a risk of distorting investment signals
by encouraging a ‘wait for the tender to be launched’
approach on the part of investors to secure additional
revenue. In the context of the current transition of the
electricity system, and in some Member States, the deci-
sion to shut down nuclear capacity, well designed and
one off tenders could have a role to play. However, only
if the connection between the tender requirements and
the system transition is clear, is it likely that investors
would consider a commitment not to repeatedly launch
more tenders, in order to be credible. Where a tender is
implemented to correct for regulatory failures it is likely to
undermine confidence in the willingness of public bodies
to correct such failures, thereby exacerbating the under-
lying problems98.
Because the tenders would be organised only occasionally and
closely administered, this scheme will automatically be less
effective in supporting the energy transition. Relying on this
type of mechanism to drive changes in the energy mix would
be tantamount to admitting the failure of the role of markets
for investments, and would transfer investment risk from private
companies to consumers.
95[EC, 2013a]
96See section 2.1.2 of this report
97[EC, 2013a]
98[EC, 2013a]
51
CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE / 2
2.2.3 Minimise the cost to consumers
Targeted capacity mechanisms are often presented as a way to
minimise the cost to consumers, since only a limited quantity
of capacity is rewarded99. The European Commission mentions
this characteristic100:
One particular concern about market wide capacity mecha-
nisms is that they can over reward generation which was
already financially viable.
However, an analysis of strategic reserves in operation shows
that they do not cost consumers less than market-wide capa-
city mechanisms. This issue of cost was a key consideration in
the design of the French capacity mechanism, which includes a
number of provisions to ensure that the cost of the mechanism
is strictly proportional to its objectives.
2.2.3.1 Comparison of costs entailed by strategic
reserves and market-wide capacity mechanisms
On first analysis, it may seem logical that a market-wide capacity
mechanism should cost final consumers more than a strate-
gic reserve, since it covers more capacity. With the former, the
cost of capacity for final consumers represents rewards for the
contributions of all capacities to security of supply, while with
the latter the tariff surcharge only aims to complement the infra-
marginal rent for the capacities reserved.
This logic is not borne out by a careful analysis of the mecha-
nisms’ financial impact on different market stakeholders. In fact,
this analysis shows that, with two perfectly designed mecha-
nisms that exactly offset the missing money resulting from
energy market imperfections, strategic reserves do not cost final
consumers less than market-wide capacity mechanisms.
A strategic reserve mechanism that is consistent with economic
theory is based on a system in which generators are compensa-
ted in two ways for missing money:
> For capacities included in the strategic reserve, fixed costs are
covered through two remuneration systems:
• In the energy market, capacities earn a specific rent every time
they are dispatched. This rent corresponds to the difference
between the dispatch price for reserves and their variable cost;
• This rent is then complemented by a fixed remuneration of
the capacities reserved, which is financed by final consumers;
> For capacity that remains in the market, revenue increases since
the price cap is reached more often on the energy market.
Electricity users are therefore called upon to offset the missing
money at two levels. They pay a tariff surcharge to complement
the revenue earned by reserved capacities. In the meantime,
prices in the energy market reach the price cap more often than
in the energy-only market, not only during load curtailment but
also when the reserves are dispatched. In other words, strate-
gic reserves result in direct costs, through the remuneration of
capacities reserved, as well as an indirect cost reflected in more
frequent price spikes in the energy market.
With a market-wide capacity mechanism, the mis-
sing money resulting from market imperfections
is offset exclusively through the capacity price paid
by final consumers. Unlike with strategic reserves,
consumers benefit from a lower and more stable
energy price, equal to the market price in a perfect
energy-only market101. They nonetheless participate
in a more direct way, through the capacity price,
which is supposed to offset the missing money in full,
whereas the strategic reserve only offsets part of it.
Figure 12 compares the economic results of capa-
city in three situations: the original situation, with
missing money that is not offset; and situations
where adjustments are made through a market-
wide mechanism or a well-designed strategic
99Targeted capacity mechanisms can nonetheless entail hidden costs, for instance in energy prices, making it difficult to evaluate them based solely on face value cost.
100[EC, 2013a]
101Except during load shedding, if we assume that the market imperfection that led to the implementation of the capacity obligation is representative of a price cap below the cost of unserved energy.
Assessments of the economic impact of different classes of capacity mechanism lead to the fol-lowing conclusions
> Market-wide capacity mechanisms address mar-ket imperfections without distorting energy prices;
> Targeted mechanisms such as strategic reserves address market imperfections but distort energy prices;
> Targeted mechanisms such as one-off tende-ring procedures do not address market imper-fections and result in discrimination for the capacities targeted.
This analysis suggests that targeted mecha-nisms such as capacity auction schemes can be considered fall-back solutions that do not address the structural challenges that have led France to introduce a capacity mechanism. This type of mechanism will therefore not be conside-red in the remainder of this report.
52
Revenue from energy market
Revenue from specific mechanisms
reserve mechanism. It is not possible to assess the impact of
capacity mechanisms on consumers solely by comparing the
direct financial effects of these mechanisms, i.e. the surcharge
on tariffs for strategic reserves and capacity prices, shown in
orange. The fact that energy price caps are reached more often
with the strategic reserve mechanism must also be taken into
account. A thorough comparison confirms that if both mecha-
nisms offset the missing money, they will have the same cost
impact on consumers.
2.2.3.2 Provisions to limit the cost of the French
capacity mechanism
Though it is market-wide, the French capacity mechanism also
includes specific provisions intended to limit its cost.
Firstly, though the French capacity mechanism applies to all
capacity, its application is market-based and not through a capa-
city payment. The decision to base the mechanism on a market
price ensures that contributions to security of supply are fairly
compensated. Though all capacities are rewarded, no value is
assigned to overcapacity, and the price corresponds to the bare
minimum required to safeguard security of supply.
Secondly, the fact that the specific economic situations of dif-
ferent types of capacities are taken into account – incumbent
nuclear and facilities benefiting from purchase obligations –
limits the mechanism’s total financial impact:
> Incumbent nuclear: The Regulated Access to Historical
Nuclear Electricity scheme (Accès Régulé à l’Électricité
Nucléaire Historique – ARENH) established by the NOME
Act102 allows all suppliers to set rates for their customers
under the same economic conditions as the incumbent
operator. The ARENH price “is representative of the econo-
mic conditions under which electricity is generated at the
power plants”103 in question, based on an addition of costs,
including capacity costs104. The capacity mechanism will not
modify the cost to suppliers of accessing incumbent nuclear
generation, and alternative suppliers will be able to cover a
A comparative theoretical analysis based on market-wide capacity mechanisms and strate-gic reserves shows that they are equivalent in terms of cost. Both mechanisms restore security of supply to the same level as the perfect energy-only market and offset the missing money resul-ting from market imperfections. In both cases, final consumers are called upon to ensure the coverage of fixed costs and the existence of investment incentives.
While the cost to final consumers is the same, finan-cing does not flow through the same channels:
> With market-wide capacity mechanisms, the value of security of supply is reflected exclusi-vely through the capacity market;
> With strategic reserves, some of this value is rewarded through capacity financing and some through higher energy prices.
Cov
erag
e of
fixe
d co
sts
Fixed costs(€/MWh)
Capacity in the market
Missing money
Capacity in the market SR
1. More frequent price spikes
2. SR surcharge
Capacity in the market
1. Capacity price
Figure 12 – Comparison of economic results of capacity in an energy-only market with missing money, a market-wide capacity mechanism and a strategic reserve mechanism
Energy-only marketwith missing money
System with market mechanism applying
to all capacities
System with strategicreserve
53
CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE / 2
large share of their capacity obligation without paying more
than in the current situation. In this regard, the capacity
mechanism will reveal the capacity price integrated into the
ARENH price;
> Facilities benefiting from purchase obligations (wind, photo-
voltaic and cogeneration): The capacity value of these facili-
ties is transferred to consumers through a reduction of their
contribution to public service charges105. The mandatory pur-
chase price thus already includes capacity remuneration for
the technologies in question.
Nuclear power plants and facilities benefiting from feed-in
tariffs (wind, photovoltaic and cogeneration) already include a
capacity component in their prices since their revenue is regu-
lated in order to promote competition in the French electricity
market and renewable development. The capacity mechanism
will reveal the value of this capacity component without crea-
ting additional costs for suppliers to meet their obligation, and
thus without adding to the cost to final consumers.
2.2.4 Economic efficiency in the presence of investment cycles
Economic theory suggests that investment cycles will occur in
industries characterised by leads time before new facilities are
commissioned and low degrees of information and decision-
making coordination (§ 1.2.3). These are characteristics of the
electricity sector. The long-term equilibrium predicted by static
analysis is rarely achieved: capacity investment and retirement
decisions do not produce immediate effects, but instead follow
their own dynamic, resulting in cycles. This dynamic component
has consequences both for security of supply and the economic
efficiency of the power system as a whole.
The economic literature examines how these cycles can be sha-
ped by market architectures and by mechanisms adopted to
ensure adequacy. Capacity mechanisms allow stakeholders to
coordinate their capacity investment and retirement decisions.
In particular, the investment cycle phenomenon that is intrinsic
to the energy-only market can be monitored and mitigated, at
least in part, when capacity mechanisms are in place106.
2.2.4.1 Impact of a market-wide capacity mechanism on
investment cycles
A market-wide capacity mechanism is a tool for quantity-
based regulation that creates the right incentives for capacity
investment and retirement decisions. Though the price signal
is the channel through which information is transmitted, at
102Law 2010-1488 of 7 December 2010 on the New Organisation of the Electricity Market
103Law 2010-1488, Article 1
104Decree 2011-466 of 28 April 2011 setting out the rules governing access to historical nuclear energy, Article 1, V: “The product transferred includes the generation capacity certificate, as defined in article 4-2 of the aforementioned law of 10 February 2000, corresponding to its profile.”
105Law 2013-312 of 15 April 2013 on preparing for the transition to a low-energy system and including a range of provisions for water pricing and wind power, Article 7 sexies: “Buyers of renewable or cogenerated electricity (subject to Purchase Obligations) generated in France assume the responsibilities of the producer of that electricity for delivering the corresponding capacity certificates.” “The value of the capacity certificates acquired within the framework of the contracts [Purchase Obligation] is deducted from the public service charges calculated for the buyer.”
106[De Vries, 2004] shows that a capacity obligation type mechanism is better able to dampen investment cycles. [Stoft, 2002] finds a similar result with a strategic reserve type mechanism.
a fundamental level, coordination is achieved
because market stakeholders can work with the
same volume forecasts.
With centralised mechanisms, quantitative forecasts
are generated administratively. Under decentralised
mechanisms like capacity obligations, total capacity
demand is calculated by aggregating the anticipa-
tions of market stakeholders, factoring smoothing
effects and the level of coverage required into the
method for calculating the obligation. Stakeholders’
decisions are therefore based on quantities, which
prevents overreactions to price signals and copycat
behaviours.
In phases of under-capacity, investments are limited
by total capacity demand. Even if the capacity price
is very high, it will only compensate the amount of
capacity that corresponds to total demand. New
capacity in excess of the amount needed to meet
real needs will not find a buyer. Cyclical effects are
lessened.
Market-wide capacity mechanisms thus send
signals about prices and quantities that help coordi-
nate capacity investment and retirement decisions.
Their stabilising role reduces the intensity of invest-
ment cycles.
2.2.4.2 Investment cycles under a strategic
reserve mechanism
Strategic reserve mechanisms help guarantee
capacity adequacy by influencing both the energy
market price and the amount of capacity available
when supply is tight, thanks to capacity reserves.
A strategic reserve mechanism will address the pro-
blems encountered in the energy-only market by
dynamically adjusting the size of strategic reserves. Any reduc-
tion or increase in reserve volumes will impact the outlook for
capacity remuneration, notably shaping decisions about pulling
older facilities out of the market, as they can earn complemen-
tary revenue by participating in the reserves and thus delay their
shutdown.
If security of supply is at risk, the mechanism operator will
increase the reserves. This impacts market stakeholders’ deci-
sions at two levels. First, the retirement of existing capacities can
54
be delayed if they become part of the reserve. Second, the with-
drawal of capacities from the market will drive up the energy
price, stimulating investment and causing the shutdown of
capacities in the market to be delayed. In the absence of a quan-
tity-based mechanism to prevent overinvestment, stakeholders
will continue to invest heavily and mimic others’ behaviour, as is
seen in the energy-only market.
In situations of overcapacity, the mechanism operator will scale
back the reserves and have no influence on the formation of
the energy price. The strategic reserve mechanism will not limit
copycat behaviours though.
In sum, a strategic reserve mechanism only partially addresses
the issue of the lack of coordination of capacity investment and
retirement decisions. It therefore has only a limited ability to
dampen the investment cycles found in the energy-only mar-
ket, and will not fully correct the structural failures of the market.
2.2.5 Suitability to France’s situation
A decision was made in favour of a market-wide
capacity mechanism because it addresses the speci-
fic challenges facing the French power system. Two
factors support this assertion: this type of mecha-
nism enables the participation of the demand side,
and the size of the strategic reserve required would
be problematic in France.
2.2.5.1 Enabling participation of the demand
side
One of the main reasons France is implementing a capa-
city mechanism is to address the problem posed by
peak demand in winter, when all supply- and demand-
side capacities contribute to security of supply.
A primary objective of the mechanism is to give consumers incen-
tives to make the structure of their consumption more virtuous,
notably to reduce peak demand in winter, as was discussed in
chapter 1. Such incentives only make sense if they apply to all
consumers, proportionately to their consumption. By the same
token, the capacities included must suffice to meet all demand.
This matching of obligations for all consumption with the parti-
cipation of all capacities in the mechanism makes the most eco-
nomic sense and creates the right incentives. It allows demand
response and targeted demand reduction actions to participate
in the mechanism in the same way, either implicitly or expli-
citly107, making the mechanism technology neutral108.
2.2.5.2 Strategic reserve planning with a key low-
probability, high-impact variable
Addressing France’s structural security of supply challenges
with a strategic reserve mechanism would require placing in the
reserve a disproportionate quantity of capacity relative to the
amount that would remain in the energy market.
Indeed, designing a strategic reserve requires establishing a
number of parameters, particularly rules for when reserves are
dispatched and the size of reserves needed to address speci-
fic security of supply considerations. If the strategic reserve is
designed to offset the missing money, then these parameters
are interlinked. Additional revenue earned by capacities outside
the reserve will depend on the likelihood that the reserves will
be dispatched, which in turn depends on the size of the reserve
and the dispatch price109.
However, little information can be found in the economic lite-
rature about the sizing of reserve volumes, with most studies
citing assessments by the bodies in charge of strategic reserves.
In practice, reserve volumes depend in large part on security of
supply needs. For instance, if security of supply would be threa-
tened by the shutdown of a certain number of plants, then the
size of the strategic reserve will be calculated in such a way as to
ensure that they remain in the system.
Bearing this in mind, a strategic reserve in France would have
to be large enough to guarantee security of supply during win-
ter cold spells. However, whereas with a conventional adequacy
assessment it would suffice to calculate the total capacity requi-
red to avert the risk, with a strategic reserve, a distinction must
also be made between the capacity that is “in” and “out of” the
market, i.e. the capacity that must be included in the reserve to
remain economically viable.
107With a market-wide capacity mechanism, a consumer that reduces its peak consumption by 10 MW also reduces its obligation by 10 MW, which is equivalent, for the consumer, to its 10 MW of load reduction being rewarded through certification. With a mechanism targeting only 10% of capacities, a 10 MW reduction in peak consumption reduces the consumer's obligation by 1 MW, which is no longer equivalent to having 10 MW of certified demand response participate in the capacity mechanism.
108The different ways in which demand response can participate in the French capacity mechanism are discussed in detail in part 3.
109“A planner first calculates the optimal volume of generation capacity, then decides the reserve volume and calculates the optimal dispatch price. The reverse is also possible: given a certain reserve dispatch price, the optimal reserve volume can be calculated.” [De Vries, 2004]
Any form of capacity mechanism will allow for a better coordination of capa-city investment and retirement deci-sions than the energy-only market, and will therefore dampen investment cycles. Market-wide capacity mecha-nisms appear more efficient than strategic reserves, particularly when it comes to preventing situations of overcapacity.
55
CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE / 2
The most critical risk in France – typically a one-in-ten-year cold
spell requiring around 30 hours of load shedding – is a low-proba-
bility, high-impact variable. The likelihood that the capacity needed
to cover this risk would be dispatched is low, meaning it would not
necessarily be economically viable if it earned revenue solely by
generating energy. It can therefore be considered that if a strategic
reserve was used in France, it would have to be large enough to
meet the additional demand recorded during cold spells.
An initial order-of-magnitude assessment of the required reserves
can be based on a brief analysis of winter demand peaks in past
years. In 2008, which is used here as the benchmark (no signifi-
cant cold spell), the highest level of demand recorded was just over
83 GW. In 2012, when a major cold spell occurred, peak demand
exceeded 101 GW. Without considering structural changes in
demand110, we see that 18 GW of capacity had to be available111 to
meet demand in 2012, capacity that was not used in 2008112.
Interconnections between the French power system and the
rest of Europe create opportunities for capacity in France to earn
revenue above and beyond its use to meet domestic demand. A
strategic reserve of 18 GW would therefore undoubtedly be dis-
proportionate. However, the capacity that it would be economi-
cally justifiable to use to meet peak and extreme peak demand
carries high variable costs. It is therefore unlikely that export
prices would be competitive.
To summarise, meeting peak demand in France
with a strategic reserve would require:
> Either a very large strategic reserve, far bigger
than the volume that would be required in other
contexts: Since the reserves would be dispatched
at the price cap on the energy market, the upper
portion of the price duration curve would be
significantly distorted;
> Or a structurally oversized generation mix to ensure
that it could meet peak demand while also produ-
cing energy at competitive prices for exports (peak
demand met with base-load generation).
It seems that both options could result in significant
distortions in energy markets, both in France and
Europe.
110This is an acceptable hypothesis for calculating orders of magnitude, especially as the two dates were relatively close and that the economic environment was not driving a significant increase in demand.
111Taking account of contingencies potentially affecting capacities and constraints that could decrease their availability would require adding a safety margin.
112With no cold spell in the winter of 2013-2014, peak demand did not climb above 85GW, illustrating how it is possible for peak demand to remain relatively low throughout the winter.
113[ACER, 2013]A strategic reserve mechanism would
not be adapted to France’s specific situation. The reserve size required to meet demand during cold spells would be problematic, and market-wide capacity mechanisms seem to offer a more efficient way to promote demand-side participation.
It is possible to adopt different types of models with market-
wide capacity mechanisms. The third key characteristic of the
French mechanism relates to its decentralised nature.
While the mechanism does indeed involve quantity-based regu-
lation, the law stipulates that each supplier will have to secure
enough capacity certificates to cover the consumption of its
own customers during peak periods. This is different from the
single buyer model, an alternative market model that ACER des-
cribes as follows:
A Capacity Auction scheme is a centralised scheme in which
the total required capacity is set (several years) in advance of
supply and procured through an auction by an independent
body. The price is set by the forward auction and paid to all
participants who are successful in the auction. The costs
are charged to the suppliers who charge end consumers.
2.3 Why a decentralised capacity mechanism
Contracted capacity should be available according to the
terms of the contract113.
The French capacity mechanism is a capacity obligation, which
is mainly a system for allocating costs, making market stakehol-
ders accountable and organising trading:
A Capacity Obligation scheme is a decentralised scheme
where obligations are imposed on large consumers and on
load serving entities (“LSE”, further referred to as “suppliers”),
to contract a certain level of capacity linked to their self-
assessed future (e.g. three years ahead) consumption or sup-
ply obligations, respectively. The capacity to be contracted is
typically higher, by a reserve margin determined by an inde-
pendent body, than the level of expected future consumption
or supply obligations. The obligated parties can fulfil their
obligation through ownership of plants, contracting with
56
generators/consumers and/or buying tradable capacity certi-
ficates (issued to capacity providers). Contracted generators/
consumers are required to make the contracted capacity
available to the market in periods of shortages, defined admi-
nistratively or by market prices rising above a threshold level.
Failure to do so may result in penalties. A (secondary) market
for capacity certificates may be established, to promote the
efficient exchange of these certificates between generators/
consumers providing capacity and the obligated parties or
between obligated parties114.
This decision to adopt a decentralised model for the capacity
obligation is a distinctive characteristic of the French mecha-
nism, allowing all suppliers and consumers to be held directly
accountable, above and beyond financing their capacity obliga-
tion. Parties subject to capacity obligations are responsible for
anticipating their capacity needs, securing enough capacity cer-
tificates to cover these needs, and making choices about redu-
cing consumption within their portfolios during peak periods.
They are also financially liable for any positive or negative imba-
lances between their level of coverage and actual needs.
There are three main justifications for adopting this model: it
is compatible with the internal electricity market, it is adapted
to France’s specific situation, notably in terms of the economic
virtues of the incentives created to reduce peak demand, and
lastly the timescales associated with decentralised markets
make them economically efficient.
2.3.1 Compatibility with the philosophy of the European energy market
The system proposed for France is a certificate market. It draws
from a classic economic theory model: to correct the market
failures described in chapter 1, property rights are created for
capacity as a “product”. Public authorities determine parameters
to ensure that their targets will be met. Market stakeholders are
then free to engage in trading within the framework of these
parameters. The assumption that the market will drive optimal
allocation is preserved and taken into account: public authori-
ties do not estimate needs in lieu of market stakeholders.
This choice is in keeping with the founding prin-
ciples of the internal European energy market and
intended solely to expand the range of market
products offered. The principle that market stake-
holders should be accountable for their respective
portfolios is upheld in that they assess their future
needs, decide how they will cover them, and are financially res-
ponsible for imbalances between their actual needs and cove-
rage. Because the architectures of energy and capacity markets
are similar, the roles and responsibilities of different participants
in the power system are consistent. At a time when the Euro-
pean Commission is expressing concerns about the adoption
of capacity mechanisms in Europe, this conceptual proximity to
the “target model” for Europe is a very important consideration.
The alternative to a mechanism with negotiable certificates is the
single buyer model. Models of this type can notably be found in
North America, in systems where the energy market is also cen-
tralised. The United Kingdom has also announced the creation
of a mechanism inspired by this philosophy115. With this type of
system, public authorities, not market stakeholders, evaluate
aggregate needs. This makes sense intellectually, since security
of supply is a public good and transaction costs are lower than
with a decentralised model. However, there are consequences
in terms of how responsibilities are distributed, and the system
explicitly involves capacity development planning.
The debate about the two approaches is informative but
inconclusive, the main criterion being whether the market or
a planner can estimate future needs more accurately. Without
claiming to settle a controversy that may continue amongst
researchers and practitioners for many years to come, some
conclusions can be drawn:
> The single buyer model reduces the risk incurred by inves-
tors by eliminating uncertainty associated with finding buyers
(the single buyer is responsible for acquiring all capacities and
then passing costs through), whereas no risk is transferred
from market stakeholders to the community with a bona fide
decentralised model;
> The single buyer model requires an ex-ante calculation of
the medium-term capacity target (the target is a parameter
exogenous to the functioning of the mechanism), whereas in
the decentralised model stakeholders are responsible for this
(the capacity target is an endogenous parameter that varies as
the mechanism functions);
> The single buyer model exposes the community to the risk
that demand forecasts will become self-fulfilling prophe-
cies, whereas the decentralised model exposes it to the risk
that the market will not function properly if stakeholders are
unable to accurately assess their capacity needs.
There is probably no definitive answer to these questions, as
they must also be considered in the light of how the system
functions as a whole. For this reason, RTE recommended in
114[ACER, 2013]
115[DECC, 2013]
57
CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE / 2
116[RTE, 2011]
117This would be even more feasible if several decentralised capacity mechanisms are in place; see for instance [BDEW, 2013]. Cross-border considerations are addressed in chapter 9 of this report.
118[EC, 2013a]
2011 that a simple adjustment be made, without completely
overhauling the structure of accountability, to avert the risk of
self-fulfilling prophecies:
In an architecture in which all capacity is contracted n years
ahead of time, the capacity obligation can be likened to a
number of MW the community of suppliers must “place”.
Once the total obligation is set, any measures suppliers could
take to reduce power consumption among their customers
will have no impact on the total capacity contracted116.
Two years later, it appears that the reserves that had been iden-
tified in 2011 when evaluating a centralised capacity mecha-
nism for France have increased. Based on trends in the structure
and level of demand, total capacity in the French power system
would more readily require an adjustment than a major structu-
ral increase.
Lastly, choosing a model for the capacity mechanism that is
in keeping with the founding principles of the internal energy
market will also create opportunities to envisage cross-border
functioning going forward117.
2.3.2 Ability to address France’s specific challenges
A decentralised system does not offer many benefits if obliga-
ted parties are passive with regard to their obligations. The main
advantage of a decentralised system – or a system without a
fixed capacity target – is that suppliers can cover (hedge) their
obligation by buying certificates or making physical adjustments
on the demand side. This creates a good feedback loop for the
capacity price and prevents it from rising above the capacity
value of demand response.
This incentive is logical given the role suppliers play in the current
market architecture: they are in direct contact with consumers
and therefore have exclusive insight into their behaviours and
consumption patterns. Suppliers can influence consumption
structures through their offers and rates. Their involvement in
this regard is a key aspect of the French mechanism’s efficiency.
The resulting model also enables the key to security of supply
in France – keeping peak demand in check – to be targeted.
In keeping with the objectives outlined in § 2.2.5.1, demand
response is given its rightful place in the mechanism, as it is
rewarded wherever there is economic space for it. In this sense,
the French capacity mechanism effectively promotes demand
response and lays the groundwork for the energy transition.
These different factors support the assertion that
the main virtue of the decentralised mechanism
relates to allocation, i.e. its ability to send the right
signals to different market stakeholders affected by
the peak demand phenomenon and to encourage
them to take action to hedge the resulting risks at
the least possible cost. Because demand trends do
not become an exogenous factor as would be the
case with a single buyer model, the system should
enable, once demand-side management actions
have been taken, a cost allocation that is fair, pro-
portionate, and reflective of the real responsibilities of each
obligated party when it comes to security of supply. This aspect
of the mechanism is in line with the European Commission’s
recommendations118:
Electricity consumers benefiting from the increased security
of supply should bear the associated cost
[…]
The most effective way of passing costs to the beneficiaries
of enhanced security of supply will normally be through their
electricity suppliers
[…]
In practice this will normally be a function of their consump-
tion at peak load, which requires that customer profiles are
accurate and detailed. This also allows suppliers to pass on
costs to the appropriate consumption groups. Consumers,
and in particular industry, who are able to manage their
demand flexibly should therefore end up paying less towards
the capacity mechanism.
2.3.3 Timescales of the decentralised market and economic efficiency
The economic crisis of 2008 caused demand growth to slow
considerably and showed that centralised capacity planning can
carry a cost for society. If an auction had been organised in 2008
for the years 2011 and 2012, capacity needs would have been
considerably overestimated and excess capacity would have
been subsidised.
A decentralised market model does not reduce this risk (as
explained in chapter 1, market stakeholders as a whole probably
failed to anticipate the effects the crisis would have on demand
or the impact renewable support mechanisms would have on
market prices), but it does not transfer the cost to society either.
In addition, it allows stakeholders with more accurate forecasts
to avoid assuming the related cost.
58
In sum, it is important for a mechanism designed to
regulate capacity levels to be able to adapt to changes
in the economic environment and demand. Decen-
tralised mechanisms appear to be more adaptable, since market
stakeholders trade continuously for several years before the deli-
very year and up until the last minute. Conversely, centralised capa-
city mechanisms function only briefly several years ahead of time.
This adaptability of decentralised capacity mechanisms is one
of the characteristics the European Commission has identified
as a potential way to minimise the cost to consumers, notably
by allowing trading on the secondary market:
Likewise obligations on suppliers relying on decentralised mar-
kets should limit the compensation to capacity to fill the iden-
tified gap to the minimum necessary. Capacity markets also
facilitate secondary trading, which helps to reduces costs119.
Some centralised capacity mechanisms, such as those in use in
North America, have introduced the possibility of subsequent reba-
lancing as a palliative measure. This does not change the fact that
most capacity is “contracted” three or four years ahead of time.
Allowing progressive rebalancing does not make sense if the time
constants associated with developing new capacities are incom-
patible. For instance, if the system is “short” several gigawatts of
capacity two years before delivery, there would not be time to
build enough generation capacities to fill the anticipated gap. The
decree also stipulates that safeguard measures can be taken in
such cases, but not if the projected imbalance is moderate, which
should be the situation in the French power system over the next
few years. The role demand response can play in balancing capa-
city must therefore be considered.
In general, it takes less time to develop demand response than
new generation capacities. With combined-cycle gas turbine
plants, for instance, about five years elapse between the invest-
ment decision and the start of industrial operations, whereas
demand response capacities can be developed more quickly
since less investment is required. This shorter lead time offers
real flexibility when it comes to meeting capacity needs.
The main benefit of this finer timescale is precisely that operators in
the capacity market can leverage all means of managing the sup-
ply-demand balance at their disposal up until the deliver year, par-
ticularly demand-side options. This choice is therefore in line with
the related objectives: give demand response its rightful place in
the mechanism and keep costs low by avoiding reserving too much
capacity ahead of time, regardless of how much is needed.
The choice is also consistent with the management of the
supply-demand balance through the cone of uncertainty. The
farther the date considered from the delivery year, the greater
the uncertainty about how the supply-demand balance will
evolve. Various risks appear over different timeframes, both on
the demand side (economic growth, temperatures) and on the
119[EC, 2013a]
Decentralised mechanism
Centralisedmechanism
Cone of uncertainty
Risk to be covered
A-3 A-1 A A-4
Best estimate of capacity need calculated in a given year
Capacity need estimated four years ahead with centralised mechanism
Capacities invested in each year with decentralised mechanism
Figure 13 – The finer timescales of decentralised market architectures reduce the margins required
59
CHOOSINGTHERIGHTCAPACITYMECHANISMFORFRANCE / 2
Illustration:Modeloftheeconomiceffi ciencymadepossiblebythetimescaleofadecentralisedcapacitymechanism
A simplifi ed model can be used to measure the impact of the timescales of centralised and decentralised markets.
Assumptions:Scenarios were generated for four consecutive years factoring in contingencies on the demand and supply sides. Modelled
with independent standard normal distributions, these unknowns are defi ned each year based on a standard deviation in GW.
New investments can potentially be planned based on these variables, to bring the overall system back to equilibrium, within a
maximum volume corresponding to the new capacity that can be added. Parameters were selected in such a way as to repre-
sent credible orders of magnitude for the situation in France. The goal is to not to calculate a specifi c value but rather a simple
estimate of the benefi ts of the fi ner timescale.
Figure 14 – Simplifi ed assumptions used to model variables
Using these scenarios with a Monte Carlo method enables a comparison of the margins required to ensure that the security of
supply criterion will be met with two approaches:
> A centralised mechanism is in place and the capacity needed to meet the security criterion is defi ned four years ahead of time;
> A decentralised mechanism is in place and participants in the capacity market can make use of all available resources, notably
shorter-term options.
This simplifi ed model is an imperfect representation of centralised and decentralised mechanisms, as the timescales of real
mechanisms – both centralised and decentralised – are often fi ner than what is represented here. Nonetheless, it does take into
account that timescales are more fl exible with decentralised mechanisms. Outcomes are not considered in terms of absolute
value but rather in terms of the diff erential between the two classes of mechanism, making the results more signifi cant.
Continuation l
1 1
Y-3 Y-2 Y-1 Y
Y-3 Y-2 Y-1 Y
Y-3 Y-2 Y-1 Y
1 1 1 0,5
1 1
Stan
dard
dev
iati
onca
paci
ty n
eed
Stan
dard
dev
iati
onca
paci
ty n
eed
New
cap
acit
yre
sou
rces
Structuraltrend in demand
Structuraltrend in demand
Structuraltrend in demand
Demandvariable
Demandresponse
Demandresponse
Demandresponse
2
Demandresponse
Changes ingeneration mix
Changes ingeneration mix
Changes ingeneration mix
Availability generation mix
2 2 2
1 1 1
Pea
k pe
riod
GW
GW
GW
60
supply side (trends in the generation mix, power plant availabi-
lity, water availability, etc.). Diff erent resources also become avai-
lable over diff erent timeframes to manage these risks.
The approaches listed above can be summarised as follows:
> One approach involves estimating, four years ahead of time,
the capacity needed to cover the entire cone of uncertainty.
Creating suffi cient margins four years in advance allows secu-
rity targets to be met. This is usually the approach taken with
so-called centralised capacity mechanisms.
> A second approach makes it possible for stakeholders to
estimate capacity needs over the entire four years preceding
the delivery year and to adjust their investments accordingly.
They can make use of all resources at their disposal, particu-
larly shorter-term solutions like demand response. This type of
dynamic approach, which off ers a degree of fl exibility in invest-
ment choices, is possible with decentralised market models.
This analysis confi rms that decentralised mechanisms can do
more than centralised ones to prevent overcapacity, and thus
reduce the cost to consumers. Participants in the capacity market
will do what is necessary to cover capacity needs for a
given year by adjusting their investments at the pace
that best suits them.
In practice, some centralised capacity mechanisms that have
finer timescales: in particular, when capacity needs are eva-
luated four years ahead of time, they can be divided into long-
term investments (generation capacities) and shorter-term
investments, for instance in demand response. However, this
results in more rigidity, with decisions about the respective
weighting of different timeframes made ahead of time at an
administrative level.
Lastly, the option value off ered by short-term measures reduces
excess capacity in the system and therefore the total cost to
participants, while also better dividing the cost of risks between
them. A perfectly predictable consumer will benefi t from signi-
fi cantly lower costs through the reduction in margins, and will
not pay the costs associated with short-term measures. This
allows for a better individualisation of costs and creates the
kind of accountability called for in the European Commission’s
recommendations120:
The costs of capacity mechanisms should be allocated to
consumers in proportion to their contribution to demand
during periods of scarcity or system stress.
Continuation j
ResultsThe study shows that the option to leverage short-term resources in the decentralised mechanism reduces the margins neces-
sary four years in advance by about 2 GW compared with the centralised mechanism. This outcome should be viewed in the light
of initial volume assumptions based on orders of magnitude for the French power system.
With a decentralised mechanism, when actual results correspond to the low capacity needs forecast for a given year, there will
be little (or no) reason to activate short-term resources. Conversely, under the centralised mechanism, additional margins will
have been created four years ahead of time to guarantee coverage in an extreme scenario, resulting in overcapacity. The study
thus shows that the centralised mechanism will create 2 GW of excess capacity every third year on average.
When conditions in the extreme scenario materialise, the margins created under the centralised mechanism will cover the
volumes required in these specifi c circumstances. Under the decentralised mechanism, short-term measures will be necessary
to achieve the same level of security, resulting in additional transaction costs. But in the end, the same amounts will be invested,
in one case because coverage is ensured through margins four years ahead of time, and in the other because shorter-term
measures are introduced over time.
When investments are indeed required for security of supply purposes, the amount of capacity available to the system is the
same under centralised and decentralised mechanisms. On the other hand, when the level of actual demand corresponds to the
lowest forecasts, the centralised capacity mechanism leads to excess capacity that is costly for consumers.
While the study shows that unneeded capacity is avoided by the decentralised mechanism in all scenarios on average, this model
is especially benefi cial in scenarios where margins created to guarantee coverage four years ahead of time prove unnecessary.
120[EC, 2013a]
61
CHOOSING THE RIGHT CAPACITY MECHANISM FOR FRANCE / 2
2.4 Conclusions
The French capacity mechanism is a capacity obligation under-
pinned by three key principles: it is a market mechanism (mar-
ket-based) that applies to all capacity (market-wide) and ope-
rates in a decentralised manner. These principles make the
mechanism adapted to the French system’s specific characte-
ristics and challenges.
A market mechanism was chosen because it creates economic
efficiency, allowing obligated parties to engage in trading to
minimise the cost of their capacity obligation. This choice was
supported by the observation that price-based regulations are
inefficient; the price-based mechanisms adopted in Europe are
currently being reformed, notably capacity payments in Spain,
Italy and Ireland and guaranteed purchase prices intended to
encourage the development of certain technologies in France.
The decision to adopt a market-wide capacity mechanism is
directly correlated to these objectives. For the mechanism to
truly guarantee security of supply, all capacities must partici-
pate. This matching of obligations for all consumption against
the participation of all capacities in the mechanism makes eco-
nomic sense and creates the right incentives for the demand
side to participate.
There are also economic justifications for this choice. The desire
to find structural solutions to the imperfections of the energy
market ruled out targeted “safety net” capacity mechanisms
like one-off tenders as an option. Strategic reserves are ano-
ther type of targeted mechanism that can indeed address the
failures of the energy market if the parameters of the mecha-
nism are perfectly defined, but analysis shows that, even in this
case, the mechanism does not cost less than a market-wide
capacity mechanism. Moreover, strategic reserves appear to be
less efficient than market-wide mechanisms in the presence of
investment cycles. Lastly, the size of the strategic reserve that
would be required in France, factoring in the low-probability,
high-impact variable represented by winter cold spells, would
mean taking a significant share of capacities out of the market,
creating distortions.
The French capacity mechanism will function in a decentralised
manner, applying market design principles similar to those of
the energy market. Obligated parties in the capacity market
must anticipate the needs of their customers and cover these
needs, and are financially liable in the event of imbalances. This
decentralised model preserves the structure of accountability
of energy markets in terms of investments and prevents having
public authorities make decisions in the place of market stake-
holders. On the other hand, transaction costs are higher with
this model.
The benefits of a decentralised model in terms of making par-
ticipants accountable is reflected in its economic efficiency
and cost allocation. A supplier that can accurately anticipate
the needs of its customers, and potentially influence their
consumption, will gain even more from the mechanism. In sum,
this market design is particularly suited to the challenge of redu-
cing peak demand, and also allows obligated parties to choose
between a variety of levers.
The model enables a dynamic approach to consumption trends,
leveraging the expertise of suppliers that interact most directly
with consumers. Not only does it avoid the introduction of a fixed
capacity target that could create incentives to consume more, it
also provides more flexibility since needs can be reassessed over
time. In a situation like 2008, a decentralised mechanism would
typically prevent about 2 GW of overinvestment.
Lastly, though a decentralised market model requires the crea-
tion of mechanisms to authorise transactions between stake-
holders, going forward, these mechanisms can also facilitate a
regional or even European approach, just as the standardisation
of negotiable products and trading conditions served as a basis
for the integration of European energy markets.
62
Article 6 of French Law 2010-1488 of 7 December 2010 on the
new organisation of the electricity market (NOME Act) calls for
the creation of a capacity mechanism in France:
Each supplier contributes, in accordance with the demand
characteristics of its customers, in terms of power and energy,
to the security of electricity supply in continental France.
Every electricity supplier must provide direct or indirect gua-
rantees of demand response or electricity generation capa-
city that can be called upon to balance supply and demand in
continental France, particularly during periods when demand
is highest among all consumers.
The law defines some key characteristics of the French capacity
mechanism. It is based on an obligation assigned to suppliers to hold
sufficient capacity certificates to satisfy the demand of
their customers, notably during peak periods, and on
the possibility for obligated parties to acquire certifi-
cates from third parties: therefore, from the outset, this
is a market in which certificates can be traded. The law
calls for this mechanism’s exact mode of functioning to
be defined in a Council of State decree121.
3.1.1 Drafting of the capacity mechanism decree
While preparing the decree on the capacity mechanism, the
Energy Minister entrusted RTE with the preparation of a report
suggesting principles for the mechanism’s organisation and
functioning, in accordance with the provisions of article 6 of the
NOME Act. This report was prepared on the basis of a consul-
tation with market stakeholders and submitted to the Energy
Minister on 1 October 2011. It notably proposed that all genera-
tion and demand response capacities participate in the mecha-
nism, that capacities be rewarded solely in exchange for effective
commitments, and that a decentralised market architecture be
implemented, based on principles similar to those of the energy
market, meaning market stakeholders would be accountable for
their contributions to security of supply. This is, in principle, the
model described in chapter 2 of the present document.
The report contained detailed proposals that were the subject of
a second consultation, conducted by the French administration
as part of the decree drafting process provided for in the law. This
consultation opened in November 2011 and closed in March
2012. Proposals contained in the initial report were debated,
3. GUIDELINES FOR THE CAPACITY MECHANISM RULES The market mechanisms implemented in Europe are showing
evidence of failure in several areas, as discussed in chapter 1 of
this report. These imperfections are raising questions about the
energy-only market’s ability to guarantee security of supply on
its own. Public intervention is justified, especially as the funda-
mentals of the power system are being turned on their head by
the ambitious energy transition policies introduced by Member
States in Europe and by peak demand growth in France.
Different types of capacity mechanism design are possible.
Chapter 2 of this report presented the justifications for the
model chosen for the French capacity mechanism: it is a mar-
ket mechanism (market-based) with quantity-based regulation,
applicable to all capacities (market-wide) and functioning in a
decentralised manner.
These principles were laid down in the decree of December
2012, and must now be put into practice. This is the purpose
of the draft rules published by RTE on 9 April 2014. The step at
hand is all-important since it involves defining the specific pro-
cedures that will determine in large part how the mechanism
functions.
This chapter begins with a review of the legislative and regula-
tory frameworks governing the capacity mechanism and from
which the architectural principles applied were drawn (§ 3.1). It
then describes the fundamental orientations RTE proposes in
the draft capacity mechanism rules to ensure that it will effecti-
vely reward capacities for their contribution to security of supply
(§ 3.2).
121 The provisions of article 6 of the NOME Act are codified in articles L. 335-1 to L.335-8 of the Energy Code. Article L. 335-6 establishes that the terms of application shall be defined in a
3.1 Architectural principles set forth in laws and regulations
63
GUIDELINES FOR THE CAPACITY MECHANISM RULES / 3
clarified or amended. For instance, a “safety net” mechanism
was introduced for situations of “exceptional risk” to security of
supply122. All issues discussed in the rest of this document (form
of the obligation, certification methods, nature of settlement,
mechanism transparency, regulation of dominant operator’s
market power, recognition of cross-border interconnections, etc.)
were addressed, often in great detail, during these discussions.
The Government sought the opinions of the Energy Regula-
tory Commission and Competition Authority while preparing
the decree. Their opinions, issued in the spring of 2012, led the
Government to make changes to the draft decree, the defini-
tive version of which was published in December 2012 (not all
changes are mentioned in this report). These opinions were also
taken into account while the mechanism rules were being draf-
ted in 2013.
3.1.1.1 Energy Regulatory Commission deliberation
In its deliberation of 29 March 2012123, the Energy Regulatory
Commission supported public authorities in terms of the market
design selected for the capacity mechanism, issuing a favourable
opinion on the draft decree, subject to certain modifications.
The Energy Regulatory Commission approved the choice of
a decentralised market mechanism the parameters of which
would reflect suppliers’ contributions to the shortfall risk, the
decision to reward the contributions of capacities to safeguar-
ding security of supply, and the option to hold market partici-
pants accountable.
Its observations were accompanied by proposed amendments
to improve how the mechanism would function, notably by
strengthening the provisions designed to make market stake-
holders accountable, but did not question the overall equilibrium
of the choices the Government proposed. Several amendments
made to the draft decree regarding the functioning of the capa-
city market reflected CRE’s recommendations:
CRE proposes to include in the draft decree a provision
allowing capacity rebalancing by suppliers, prior to verification
that they have met their obligation.
Imbalance settlement for capacity portfolio managers will be
key to the mechanism’s efficiency.
The concept of a reference capacity price should be intro-
duced in the draft decree: its method of calculation will be
determined by CRE124.
On the other hand, the Government did not adopt
the Energy Regulatory Commission’s proposal to
eliminate the transitional safety net mechanism
and the tendering mechanism for the delivery year
including the 2015-2016 winter. This has no impact
on the draft rules published on 9 April 2014: these
proposals did not relate to the general organisation
or functioning of the capacity mechanism that RTE
was to describe in the rules, but to provisions for
which RTE is not expected to make proposals.
The Energy Regulatory Commission also considers
that some features of the proposed mechanism can
“mitigate or manage the risk125“ that the mecha-
nism will have an unfavourable impact on competition. It notes
that, as part of its market monitoring activities, it will ensure that
the capacity mechanism does not restrict competition. The pro-
visions designed to prevent manipulation in the capacity market
are discussed in chapter 7 of this report.
Lastly, the Energy Regulatory Commission notes that the impli-
cit recognition of interconnections in the calculation of suppliers’
capacity obligation is an appropriate solution for the short term,
but that coordination should be organised at the European level,
or at least at the regional level, to allow for the explicit participation
of foreign capacity in reducing the shortfall risk. Chapter 9 of this
report discusses the participation of foreign capacity in detail.
3.1.1.2 Opinion of the Competition Authority
In its opinion published on 12 April 2012126, France’s Competi-
tion Authority expressed some concerns about the draft decree
based on its competitive assessment of the provisions submit-
ted to it by the Government.
The Competition Authority initially questioned whether it was
necessary to introduce a capacity mechanism in France and said
it regretted that the Government had not conducted an impact
assessment. On this point, chapters 1 and 8 of this report include
a discussion of the justifications for public intervention and consi-
derations for assessing the consequences and economic impact
of the mechanism described in the capacity mechanism rules.
Thus, in response to the Competition Authority’s concerns, the
justification for public intervention has been clarified.
The Competition Authority’s reservations do not call into
question the fundamental choices in favour of a market-wide
capacity mechanism and decentralised architecture. Instead,
they focus on the risks associated with the mechanism’s
decree of the Council of State.
122 System wherein the minister can organise a tender to secure enough capacity to face an exceptional risk.
123[CRE, 2012]
124[CRE, 2012]
125[CRE, 2012]
126[Competition Authority, 2012a]
64
transparency and complexity, and the concern that these could
distort competition and create barriers for new entrants to the
electricity market. These will be valuable considerations in terms
of defining specific rules for the mechanism’s functioning and
ensuring that market monitoring is efficient once the mecha-
nism is operational.
Having expressed its reservations and in the aim of making
the capacity mechanism more competitive, the Competi-
tion Authority stressed to the Government the importance
of taking into account competition-related risks and impacts
at every stage of the mechanism design process and during
implementation. It made several recommendations on the
proposals in the decree:
> Require that EDF inform CRE of all capacity transfer prices;
> Require accounting separation between EDF’s generation
and supply activities;
> Require that availability forecasts submitted for genera-
tors’ facilities be based on the historical availability of those
facilities;
> Factor in the contribution of interconnections to mitigating
the shortfall risk through a public auction of the correspon-
ding capacity certificates, allocating the proceeds to contri-
butions to public service charges;
> Envisage a legislative amendment applying to entities that
buy directly on wholesale markets to ensure that all rele-
vant participants are subject to the capacity obligation;
> Plan to avoid issuing certificates to facilities that benefit
from purchase obligations insofar as the feed-in tariffs at
which electricity is purchased from these facilities already
cover their costs in full;
> Do not have alternative suppliers assume the cost of the
transitional tendering mechanism.
The draft decree was amended to take some of the Compe-
tition Authority’s recommendations into account. Moreover,
in preparing the draft rules for the mechanism, RTE took the
competitive landscape described by the Authority into consi-
deration: the mechanism introduced in France is, in this regard,
a closely regulated and monitored market mechanism. Special
care was taken to ensure that stakeholders have access to all
relevant information and to facilitate monitoring and control
by the Energy Regulatory Commission. Along these lines, the
rules include provisions to ensure that the parameters of the
mechanism are visible and stable, transparency measures
relating to the physical underlyings of the mechanism and
the forecast security of supply situation, and transparency
measures relating to the functioning of the market, particularly
transaction volumes and prices.
Details of RTE’s proposals regarding the explicit participation
of foreign capacity in the capacity mechanism can be found in
chapter 9.
3.1.2 Provisions laid down in the decree
After consulting with power system stakeholders and inde-
pendent administrative authorities, the Government published
Decree 2012-1405 of 14 December 2012 relative to the contri-
bution of suppliers to security of electricity supply and to the crea-
tion of a capacity obligation mechanism in the electricity sector in
the Official Journal of the French Republic on 18 December 2012.
It establishes the general organisational structure of the French
capacity mechanism and is based on the principle, discussed in
chapter 2 of this report, of a decentralised, market-wide capacity
mechanism that makes all stakeholders accountable for their
contributions to security of supply. Suppliers must cover their
obligation based on effective consumption of their customers
and can acquire capacity certificates from operators. A decen-
tralised market model was chosen to hold stakeholders accoun-
table, and suppliers are thus induced to engage in trading to
cover their obligations as accurately as possible. Capacities are
certified in exchange for operators committing to make them
available. Lastly, all participants have financial incentives to meet
their commitments.
Chapters 1 and 2 of the decree stipulate that suppliers’ capacity
obligations and capacity operators’ certifications are calculated,
respectively, based on assessments of their contributions to
the shortfall risk or reducing it. These provisions are consistent
with the goal of implementing a capacity mechanism that truly
enhances security of supply.
This has significant consequences for the architecture of the
mechanism: suppliers’ obligations are calculated on the basis of
the contribution of their customers to the shortfall risk; it is the
structure of the shortfall risk that determines how certificates
are allocated to capacities, taking into account their technical
characteristics.
The decree notably defines how suppliers’ obligations are to be
determined (§ 3.1.2.1), the principles applied in certifying capa-
city (§ 3.1.2.2) and how the trading of capacity certificates will be
organised (§ 3.1.2.3).
65
GUIDELINESFORTHECAPACITYMECHANISMRULES / 3
3.1.2.1 Capacity obligation assigned to suppliers
For each delivery year, suppliers are required to hold capacity
certifi cates corresponding to the eff ective consumption of their
customers (including transmission and distribution system ope-
rators, for their losses) in order to meet the security of supply
objective mentioned in Article L.335-2 of the Energy Code.
The decree lays down the principles governing capacity certifi-
cate trading between obligated parties. It calls for the setting of
a deadline for trading capacity certificates (transfer deadline),
after which capacity certificates can no longer be traded, along
with a settlement deadline, by which time each supplier must
settle the amount corresponding to the imbalance between
its capacity obligation and the amount of capacity certificates
it holds.
3.1.2.2 Certifi cation of generation and demand
response capacities
Capacity operators commit to a certain level of capacity (certi-
fi ed capacity level) and are issued the corresponding amount of
capacity certifi cates. Capacity operators are affi liated with capa-
city portfolio managers.
At the end of the delivery year, RTE calculates, for each capacity
portfolio manager, the diff erence between the sum of certifi ed
capacity levels within its portfolio, refl ecting the self-assessment-
based commitments of capacity operators, and eff ective capa-
city levels. The capacity portfolio manager is fi nancially liable for
the amount of the settlement imbalance thus calculated.
During a capacity mechanism term, and prior to the delivery
year, capacity operators can make upward or downward reba-
lancings to refl ect changes in the projected availability of their
capacities.
3.1.2.3 Functioning of the capacity mechanism
The Energy Regulatory Commission monitors the functioning of
the capacity certifi cate market to ensure that the signals sent to
market stakeholders are meaningful and support the objective
of safeguarding security of supply.
To facilitate trading and the monitoring of the market, the
decree includes several provisions relating to the mechanism’s
transparency, and notably specifi es that RTE is to create and
maintain three registers for each delivery year:
Figure 15 – General organisation of the mechanism (timeline)
Phase 1Setting of parameters
Phase 2Y-4 à Y-1
Phase 3Delivery year
Phase 4Post-notification
Data collectionand capacity verification
by system operators
Calculationby systemoperators
of suppliers’reference
power
Capacity certificationand rebalancing
(Organised market sessions)
Certificate trading(self-supply, bilateral contracts)
4 years
Certification deadlines
Rebalancing
Publications by RTE(estimated capacity certificate requirements)
Certificate trading
Settlement,CPMs
Settlement,suppliers
…
Transferdeadline
Transparencyand publication
of parameters formechanism
term
Effectivecapacity
notification
Supplierobligation
notification
Start of term(opening ofregisters for
the yearin question)
SDB (supply-demandbalance) study
Peakperiods…
66
> The certified capacities register, a public document, lis-
ting all certified capacities connected to the transmission or
distribution systems. RTE describes all characteristics of the
capacities, the amount of power certified, and the capacities’
projected availability (updated);
> The capacity certificates register, not made public, which
records in a secure manner all transactions involving the
issuance, transfer or destruction of capacity certificates;
> The peak demand-side management register.
A capacity mechanism term is a multi-year scheme that starts
four years before the delivery year and ends two years after the
delivery year. The general timeline of the mechanism is pres-
ented in Figure 15.
The capacity mechanism term begins when the obligation and
certification parameters are published, which is also when the
certified capacities and capacity certificates registers are crea-
ted for the delivery year. RTE simultaneously publishes its initial
estimate of the capacity certificates required for all suppliers’
obligations to be met. This estimate factors in an evaluation of
the contribution of interconnections to reducing the shortfall
risk (see chapter 9).
Capacity operators can at this point request to have their capaci-
ties certified, in exchange for which they will receive capacity cer-
tificates. Capacities that can be developed very quickly, such as
demand response capacities, can be certified up until the start of
the delivery period. Operators can make adjustments to the data
submitted with capacity certification requests until the end of the
delivery period thanks to a flexible rebalancing process.
Approval Scheme
Approved by Minister on a proposal from RTE after consulting CRE
Approved by CRE
Approved by CRE on a proposal from RTE
Defined by CRE after consulting RTE
Decision made by Minister on a proposal from CRE (considered accepted if not contested within three months)
Approved by Minister on a proposal from CRE
Defined by CRE
Figure 16 – Regulatory framework provided for in the decree
RULES CONTRACTS OTHER TEXTS
Provisions defining delivery years and peak periods
Provisions relating to the obligation: > Calculation of reference
power; > Calculation of
obligation;> Unit power for capacity
certificate and capacity certificate recovery
Provisions relating to certification:> Certification method
and verifications;> Adaptation procedures
for capacity with reduced contributions to supply;
> Rebalancing of capacity operators and settlement for rebalancing.
Certification contract
DSO-Operator contract
CPM/RTE contract
DSO/TSO exchange agreements for
calculating reference power
DSO/TSO exchange agreements for
certification
DSO/TSO/operators on procedures
and deadlines for sending information
and organising information flows
Calculation method for actual demand within small and large consumer subcategory
Calculation method for actual demand within subcategory buying for losses
Procedures and amount of incurred expenses recovered by grid system operators for calculating
and sending obligation-related data
Calculation method for unit price of “supplier” settlement
Procedures for redistributing account balances
Amounts and recovery procedures for obligation-related expenses
Procedures for keeping registers
Calculation method and allocation schedule for ARENH certificates
Calculation method for certificates linked to transfer tariffs
Calculation method for reference price
Format and schedule for provisions relating to overall certificate levels
Procedures for gathering data on transactions
67
GUIDELINES FOR THE CAPACITY MECHANISM RULES / 3
Once the first capacity certificates have been issued, suppliers
can begin to cover their obligations, based on their own fore-
casts and risk hedging strategies, by acquiring capacity certifi-
cates from operators or securing capacity certificates for their
own capacities. Capacity certificates can be traded until the
transfer deadline, which is after the delivery year.
During the delivery year, data relating to the operation of capa-
cities is gathered and verified, particularly information about
actual availability during the peak period associated with
certification (PP2 period). Consumers’ actual demand is also
measured.
At the end of the delivery period, effective capacity levels are
calculated for all capacities, based on data collected during
the delivery year. Effective capacity levels are then aggrega-
ted for capacity portfolios. This aggregate is compared with
the sum of the certified capacity levels of capacity portfolio
managers. If an imbalance is found, the capacity portfolio
manager must pay an imbalance settlement corresponding
to that difference.
A supplier’s obligation is calculated based on observed
consumption and the obligation parameters defined before the
term begins. Each supplier is informed of its obligation before
the transfer deadline. Once this deadline has passed, the diffe-
rence between a supplier’s obligation and the amount of certi-
ficates held in its account in the capacity certificates register is
calculated, and the supplier is notified of any imbalance. It must
pay any resulting imbalance settlement.
3.1.3 Regulatory framework provided for in the decree
The next step in implementing the decree involves defining the
rules, contracts and conventions that will allow the capacity
mechanism to function properly. As with any market mecha-
nism, it should be possible for these aspects to be adapted more
quickly, since they do not call into question the general prin-
ciples of the mechanism.
The decree stipulates that the capacity mechanism rules are
to be approved by the Energy Minister, based on proposals
submitted by RTE, after the Energy Regulatory Commission
has issued an opinion. It also calls for the drafting of various
conventions and contracts that will complement the capacity
mechanism rules, subject to approval by the Energy Regula-
tory Commission.
To give an overall view of the mechanism and make it easier to
understand, in July 2013 RTE proposed a major simplification,
offering to analyse the mechanism as a whole, without taking
into account the numerous channels of approval mentioned
in the decree (see figure 16). This approach also means that
the proposals subject to approval by the Energy Minister and
those subject to approval by the Energy Regulatory Commis-
sion are being submitted together. By default, each article
of the RTE proposal is a proposal for a provision of the rules,
i.e. the text that must be approved by the Minister. [CRE] is
mentioned in the body of the title when articles are proposed
for inclusion in the provisions to be approved by CRE. No dis-
tinction is made between these provisions in the rest of this
report.
RTE drafted its proposal after a stakeholder consultation. It is not
proposed as a regulatory act: the provisions it contains can be
modified at the initiative of the Minister or CRE in the course of
the regulatory decision-making process, which will include ano-
ther stakeholder consultation. In this area, the process under
way in France is similar to what is being done at the European
scale between ENTSO-E, ACER and the European Commission
regarding the preparation of network codes.
3.1.3.1 Consultation of market stakeholders organised
by RTE
RTE organised a consultation through the Transmission System
Users’ Committee (Comité des clients Utilisateurs du Réseau de
Transport d’Électricité – CURTE), which brings together all stake-
holders in the French electricity market (generators, suppliers,
traders, demand-side operators and power exchanges), consu-
mer groups, and distribution system operators. The CURTE’s
work is open to representatives of the Energy Regulatory Com-
mission and the French administration, and to interested third
parties (academics for instance). A workgroup focusing speci-
fically on the capacity mechanism, hosted by the CURTE’s Mar-
ket Access Commission, consolidated all of the work carried out
during the consultation period.
Thanks to the diversity and commitment of the participants
involved, all aspects of the mechanism were analysed. Electri-
city market stakeholders took advantage of the consultation to
present their positions on the different building blocks of the
draft capacity mechanism rules. Participants worked together at
an intense pace (22 working meetings, 76 written contributions,
52 in-session presentations, one simulation tool made available
to participants).
68
The consultation was organised in two phases (see fi gure 17).
The fi rst (January to July 2013) was devoted to preparing a draft
of the capacity mechanism rules. These draft rules were the
subject of a public consultation that opened on 11 September
2013 and continued for six weeks. More than 500 comments
were received, detailed responses to which are included in an
appendix to the draft rules.
The second phase (September to December) provided an
opportunity for stakeholders to propose changes and for RTE
to propose amendments to the draft rules. The goal during this
phase was to strike the right balance between the desire to hold
market stakeholders accountable and create real and proportio-
nate incentives – which requires a clarifi cation and individualisa-
tion of the provisions suggested in the rules – and the benefi ts
to stakeholders in terms of forecasting if the relative stability of
the mechanism’s functioning was guaranteed, notably through
the introduction of normative provisions.
RTE considers that the amendments to the draft rules pro-
posed based on the consultation of September 2013 make the
mechanism more transparent and predictable, and strike a good
balance between constraints of diff erent types.
RTE would like to thank all participants for their quality contri-
butions, which made the consultation a forum for rich and
constructive debate and generated concrete proposals for the
implementation of the capacity mechanism, in keeping with the
provisions of the decree.
Figure 17: Consultation timeline
Q1 - 2013 Q2 - 2013 Q3 - 2013 Q4 - 2013 2014
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec …
Draftrules
Preparation of draft rules(parameters, general outline, specification) Submission
to CRE and Minister
Review by CRE
Finalisationof rules
Consultationon draft
rules
Approvalprocess
MAC mtg 10/04General progress
report andcoordination
of efforts
MAC mtg 11/07Overview ofconsultation
work
MAC mtg 18/12Progress reportpost feedback
Ministerialapproval
Rules
CREopinion
69
GUIDELINES FOR THE CAPACITY MECHANISM RULES / 3
Chapters 1 and 2 of this report discussed the central role the
mechanism must play in correcting how the energy market
functions and safeguarding security of supply.
The decree clarified the provisions of the NOME Act and suppor-
ted the principle of a decentralised, market-wide mechanism,
and the mechanism rules outline the key ideas and parameters
that will determine in large part how the mechanism functions.
For RTE, it was essential that these choices take into account the
importance of safeguarding security of supply and keeping the
mechanism proportionate to its purpose. Oftentimes the debate
centred on finding a balance between the need to individualise
the provisions of the rules on the one hand and the benefits of
stabilising some parameters, to reduce uncertainty for market
stakeholders, on the other.
Five key definitions are a particularly good reflection of these
objectives, and they are presented in the sections below: (1)
the nature of capacity commitments, (2) the periods during
which capacities are committed, (3) the parameters for cal-
culating capacity obligations and certifying capacities, (4) the
reference data used to calculate obligations and certify capa-
cities, and (5) the methods for assigning a value to demand
response.
3.2.1 Nature of commitments by capacity operators (installed or available capacity)
During the consultations of 2011 and 2013, the nature of the
commitments made by capacity operators was a key point of
discussions with market stakeholders. The two approaches that
emerged involved commitments based on installed capacities
and commitments based on the availability of generation or
demand response capacities.
Mechanisms based on installed capacities aim to ensure that
sufficient generation or demand response capacities exist to
cover the shortfall risk, without considering whether these capa-
cities will effectively be available when security of supply is at
risk. Conversely, mechanisms based on commitments to make
capacity available aim to guarantee that enough capacities will
effectively be available to cover the shortfall risk during peak
demand periods.
These approaches have very different consequences both for
the nature of the mechanism and the level of security of supply,
and the impact on market stakeholders will not be the same.
Capacity operators can be asked to make commitments for ins-
talled capacities to ensure the physical existence of the capa-
cities, in exchange for capacity remuneration. But there is no
guarantee that the capacities remunerated will be effectively
available when needed to safeguard security of supply, particu-
larly during peak demand periods. In theory, it can be assumed
that the energy market will naturally create incentives for ope-
rators to make their capacities available during peak periods.
However, insofar as the capacity obligation mechanism involves,
from the consumer’s perspective, taking out insurance that
power will be supplied even when supply is tight, it seems logical
that the cost incurred by the final consumer should bring with
it an extra guarantee that power will be supplied: the mecha-
nism must therefore make capacity remuneration conditional
upon operators effectively making capacities available, instead
of rewarding them merely because the capacities exist.
Mechanisms based on installed capacities can also make secu-
ring capacity remuneration a priority over contributing to secu-
rity of supply, since they are explicitly geared to creating a favou-
rable environment for investment and avoiding revenue deficit
situations.
Lastly, mechanisms based on installed capacities can create
entry barriers for demand response. Stakeholders will seek to
cover their needs by focusing on creating new capacities for the
long term, on the basis of forecasts in which demand may be
fixed at a set value. This approach to covering long-term needs
prevents the participation of capacities that can be developed
with shorter time constants, such as demand response.
In sum, a mechanism that rewards installed capacities is not
consistent with the end-goals of the capacity mechanism. In
particular, the commitments that result in capacity certifica-
tion do not reflect the real physical needs of the power system,
and in this sense such mechanisms do not serve the primary
purpose of contributing to security of supply.
On the other hand, a mechanism that rewards commitments to
make capacity available has several advantages.
3.2 Purpose of the capacity mechanism rules: Guarantee real contributions to security of supply
70
First, it is designed to guarantee that the capacities
needed to avert shortfalls are eff ectively available
when security of supply is at risk; it therefore applies
to all capacities that are available when needed by the system.
The mechanism provides a form of insurance when it comes to
security of supply: capacities are rewarded through the mecha-
nism for being available when security of supply is at risk, or in
other words as a direct result of their eff ective contribution to
security of supply. Commitments to make capacities available
are the trade-off for the remuneration of all capacities.
Second, this type of mechanism allows demand response to
participate in the exact same way as generation capacities: the
functioning of the mechanism thus allows competition between
the two types of capacities.
3.2.2 Duration of capacity commitments
Chapter 1 of this report described how temperature sensitivity
is the key characteristic of the French power system and how
peak demand has been growing steadily (§ 1.2). Bearing this in
mind, the adequacy assessments conducted by RTE show that
the impact of temperatures on demand is the main risk for the
French power system and that situations of exceptional demand
determine the contours of the shortfall landscape127.
The shortfall risk clearly corresponds to a risk of exceptionally
high demand, i.e. the risk of an intense cold spell.
During the consultation, two approaches were presented for
determining the period over which operators must commit their
capacities to cover the shortfall risk:
> The fi rst called for capacities to be committed for the entire
period during which shortfalls could occur (“winter period”,
from 1 November to 31 March). In this case, the commitment
period is defi ned based on a calendar variable. Each month is
weighted based on the shortfall probability associated with it.
> The second called for capacity commitments to target the
periods during which demand is highest. The commitment
period is in this case based on a demand variable.
The illustration below (fi gure 19) provides a graphical represen-
tation of the two approaches. The chart of the left represents the
month-by-month breakdown of the shortfall risk with a maxi-
mum in January (commitment period defi ned based on calen-
dar variable). The chart on the right represents the breakdown
of shortfall risks based on consumption levels. It illustrates the
approach wherein capacity commitment periods are based on
a demand variable.
To ensure that the capacity mechanism focuses on contribu-
tions to reducing the shortfall risk, RTE proposes the adoption
of the approach that bases capacity commitment periods on a
demand variable, given the direct and decisive impact demand
levels have on the shortfall risk.
Indeed, probabilistic adequacy studies show that the shortfall risk
increases with demand. In each shortfall scenario, shortfall hours
correspond systematically to hours when demand is highest.
127All shortfall situations considered, see fi gure 19.
RTE’s draft rules support a mechanism that rewards capacities based on eff ective availability, in line with the security of supply objective and the founding principles of the mechanism (par-ticipation of demand response, recognition of all capacities).
Figure 18 – Illustration of the shortfall landscape comparing supply and demand simulations
ShortfallSupplyDemand
30
50
70
90
GW
Shortfalllandscape
71
GUIDELINESFORTHECAPACITYMECHANISMRULES / 3
The following observations are worthy of note:
> The 50 hours during which demand is highest include 100%
of the shortfall hours in two thirds of the situations in which
shortfalls occur, and, in the most unfavourable scenario, just
under 40% of shortfall hours;
> Beyond the 150/200 hours when demand is highest, 100%
of the shortfall hours are included in 90% of the situations
with shortfalls, and these 150/200 hours of highest demand
include at least 80% of shortfalls in all cases.
In reality, the calendar variable is merely a realisation of the
demand variable: the shortfall probability is at its highest in
January simply because this is the month during which the pro-
bability of an intense cold spell is greatest.
Moreover, basing commitment periods on times when the
shortfall risk is greatest makes the periods more targeted, mea-
ning the capacity mechanism will not have any eff ects outside
the periods during which it is truly needed.
3.2.3 Methods for calculating the obligation and certifying capacity
Articles 3 and 10 of the decree stipulate, respectively, that
methods must be determined for calculating the obligation of
capacity suppliers and certifying and verifying capacities. The
decree states that these methods must focus on meeting the
security of supply objective in a proportionate manner.
3.2.3.1 Parameters for determining the method of
calculating the capacity obligation
With the architecture selected for the capacity mechanism, sup-
pliers’ contributions to the shortfall risk are translated into a spe-
cifi c capacity obligation for each supplier.
A suppliers’ capacity obligation is calculated based on its refe-
rence power – refl ecting its consumption during peak periods –
and on various parameters that are the same for all suppliers,
including a security factor that notably refl ects the margins
required to cover residual risks (excluding temperature risks).
These parameters are unrelated to the physical determinants of
suppliers’ contributions to the shortfall risk (temperature sensiti-
vity, fl exibility, etc.). To ensure that suppliers’ capacity obligations
are proportionate and allow the security of supply target to be
met, these parameters must be defi ned in the capacity mecha-
nism rules in such a way as to refl ect the physical contribution
of each supplier to the shortfall risk as accurately as possible.
Figure 19 – illustration des deux approches permettant d’apprécier le risque de défaillance(Source : RTE, GT du 02/04)
Non-shortfall situations
Shortfall situations
Time-based approach to describingshortfall landscape
Demand-based approach todescribing shortfall landscape
Shortfall landscape Probshortage
(t) Shortfall landscape : Probshortage
(C)
Shortfall landscape
25%
20%
15%
10%
5%
0%0%
20%
40%
60%
< 73 GWJuly
August
Septem
ber
October
Novem
ber
December
January
Febru
ary
MarchApril
May
73-75
75-77
77-79
79-81
81-83
83-85
85-87
87-89
89-91
91-93
93-95
95-97
97-99
99-101
101-103
> 103 GW
June
Proba(C) = t
Proba(t) = C
RTE’s draft capacity mechanism rules therefore recommend that capacity commitments be defi -ned based on a demand approach – targeting so-called PP2 periods – since this approach is rele-vant in evaluating the shortfall risk and prevents the capacity mechanism from producing eff ects when it is not needed.
72
3.2.3.2 Parameters for certifying capacity
Generation and demand response capacities effectively contri-
bute to reducing the shortfall risk by being available when secu-
rity of supply is at risk, and therefore during cold spells. Their
actual contribution to reducing the shortfall risk also depends
on the number of hours during which they can be dispatched
within these periods.
With the architecture selected for the capacity mechanism, a
capacity’s contribution to reducing the shortfall risk is translated
into an amount of capacity certificates specific to each capacity
and issued to the operator of that capacity.
The amount of capacity certificates issued is calculated based on
the available power declared for the capacity – or in other words
the capacity that can be dispatched during peak periods – and on
certification parameters that are the same for all capacity operators.
These parameters take the form of coefficients so as to reflect the
impact of a capacity’s technical constraints on its effective contri-
bution to reducing the shortfall risk, such as energy constraints
(daily and weekly) and controllability constraints. The certification
parameters defined in the rules must reflect the real impact of
technical constraints on a capacity’s contribution to reducing the
shortfall risk to ensure that the amount of certificates issued to the
capacity accurately reflects its impact on security of supply.
3.2.4 Reference data used to calculate obligations and certifications
The preceding sections stressed the amount of care taken in
defining the principles and methodologies to be applied in esti-
mating the effective contributions of all market stakeholders to
the shortfall risk for each mechanism parameter proposed in the
rules. One important principle relates to the type of data used to
determine the reference power of suppliers in order to calculate
their capacity obligation and to determine the available power
of capacities to calculate their amount of certificates.
Regarding suppliers’ obligations, the reference power used to
calculate the capacity obligation reflects their contribution to
the shortfall risk (§ 3.2.3.1). The decree stipulates that reference
power is calculated based on observed demand. The consump-
tion recorded for the delivery year should therefore be conside-
red the reference for calculating reference power.
Regarding capacity certification, it is easy to define the available
power of a capacity during shortfall hours for years when short-
falls occur: it suffices to measure the capacity’s active use during
those hours. However, shortfalls do not occur in most years. The
question thus relates to the most meaningful way to measure
a capacity’s effective contribution to security of supply during
years without shortfall situations.
Several means of measuring available power are possible, and
they are summarised within the two approaches below:
> The first considers that the level of availability obser-
ved during the delivery year must be used as the basis for
verifying an operator’s effective contribution to security of
supply. This approach involves individualising capacity levels;
it is consistent with the goal of holding market stakeholders
accountable and recognising capacities’ effective contribu-
tions to reducing the shortfall risk. For instance, two opera-
tors with the same type of capacity can have different rates
of effective availability, and this has a direct influence on their
contribution to reducing the shortfall risk. This approach is
also consistent with the choice made about the calculation of
reference power to determine the amount of suppliers’ capa-
city obligations;
> The second approach involves using normative values in the
certification process. By definition, these normative values
do not fit with actual results. With a normative approach,
the contribution of some capacities is set to values that do
not match observed reality. In this regard, it strays from the
objective of making market stakeholders accountable and
The parameters defined in the rules for calcu-lating capacity obligations must allow the real contribution of each supplier to the shortfall risk to be reflected. It was with this principle in mind that the capacity obligation parameters were set, to ensure that two consumers with the same contribution to the shortfall risk are assigned the same capacity obligation. The parameters for calculating capacity obligations are discussed in more detail in chapter 4 of this report.
Certification parameters must be defined in the rules in such a way as to reflect the real impact of a capacity’s constraints on its contribution to reducing the shortfall risk, and therefore its contribution to security of supply. It was with this principle in mind that the certification para-meters were set, to ensure that two capacities making the same contribution to reducing the shortfall risk are issued the same amount of cer-tificates. Certification parameters are discussed in more detail in chapter 5 of this report.
73
GUIDELINES FOR THE CAPACITY MECHANISM RULES / 3
ensuring that capacity levels defined do indeed correspond to
contributions to reducing the shortfall risk. However, certain
stakeholders consider that this approach must be used due to
the intermittent nature of some capacities, given the exoge-
nous nature of the risks to which those capacities are exposed
(availability of the primary resource).
3.2.5 Methods of valuing demand response
The French capacity mechanism was designed to address the
issue of peak demand growth, or in other words as a means
of modifying consumption behaviours during peak periods
(demand-based approach) and encouraging sufficient invest-
ment by complementing the price signals generated by energy
markets (supply-based approach). The capacity mechanism
must be able to stimulate investments that promote the eco-
nomic management of peak demand, meaning it must allow
demand response to play its rightful role in ensuring capacity
adequacy in the system. As such, the participation of demand
should not be seen as a mere feature of the capacity mecha-
nism’s design but rather as one of the main reasons for its
implementation.
The architecture of the mechanism encourages the partici-
pation of demand response by providing two ways for it to be
rewarded: it can be recognised “implicitly”, via a reduction in a
supplier’s capacity obligation, or “explicitly”, if demand response
capacity is certified and issued capacity certificates.
Demand response is rewarded implicitly when peak demand
management actions are taken directly by suppliers to reduce
their customers’ consumption during peak periods. Insofar
as the capacity obligation is calculated based on customers’
consumption during peak periods, these demand-side manage-
ment efforts immediately reduce the capacity obligation of the
supplier in question.
Demand response is explicitly rewarded when it participates
in the certification process. In this case the demand response
capacity is awarded an amount of certificates that reflects its
contribution to reducing the shortfall risk, based on methodolo-
gies and parameters similar to those used for generation capa-
cities. Demand response capacities that are activated either
directly by a consumer or through an aggregator can thus parti-
cipate directly in the capacity market in the same was as gene-
ration capacities.
The capacity mechanism rules call for adjustments to be
made for load reductions when certified demand response
capacity is activated, to prevent it from being counted twice,
both implicitly and explicitly, as this would result in the
amount of capacity physically available being insufficient to
cover the shortfall risk. The decree also lays down the prin-
ciple that there should be no discrimination between reduc-
tions in capacity obligations and the certification of demand
response capacity.
To comply with this non-discrimination principle and ensure
that demand response effectively contributes to security of sup-
ply, the methods used to estimate the contribution of demand
response and the related periods both for reductions in the obli-
gation and capacity certification must be consistent. RTE pro-
poses that the following principles be applied:
> Certification: Demand response capacities must commit to
be available during the period considered to calculate the
amount of capacity certificates (PP2) to be certified;
> Obligation: For demand response to result in a reduction of
a supplier’s capacity obligation, it must be activated during
the period considered to calculate the capacity obligation
(PP1).
RTE proposes that priority be given to methods and parameters that incorporate the values observed during the delivery year. This approach allows as much information as possible about the state of the system to be taken into account and to identify the real contribution of each market stakeholder to security of supply.
In the interest of finding a balance between the needs for individualisation and stability, RTE introduced an additional provision for the cer-tification of intermittent capacity: the overall scheme is similar to the one for controllable capacity, with the risk relating to the primary source accounted for on the basis of self-assess-ments with observed availability measured.
The rules include an optionality principle, leaving it up to capacity operators to choose between this scheme and one that includes normative values and neutralises the risks associated with the primary energy source. A coefficient is in this case applied to ensure that the certified capacity level reflects the technologies’ average contribu-tion to reducing the shortfall risk.
This approach addresses the expectations expressed during the consultation while allowing operators that are capable of hedging the varia-bility of their capacity (notably by backing it up with flexible capacity such as demand response) to fully benefit from this coverage.
74
The provisions proposed by RTE relative to the definition of methods of calculating capacity obligations and capa-city certifications ensure that there is no discrimination between the two ways of rewarding demand response capacities and therefore that these capacities effectively contribute to security of supply.
These proposals are discussed in detail in chapters 4 and 5 of this report.
Figure 20 – Valuing demand response through the capacity mechanism
3.3 Conclusions
Article 6 of the NOME Act calls for the creation of a capacity
obligation mechanism and for the principles underpinning the
functioning of this capacity obligation mechanism to be laid
down in a Council of State decree128.
The publication in the Official Journal of the decree relative to
the contribution of suppliers to security of electricity supply and
the creation of a capacity obligation mechanism in the electri-
city sector followed a consultation with power system stake-
holders organised by public authorities, taking into account
RTE’s proposals for the implementation of a capacity obligation
mechanism. France’s Energy Regulatory Commission and Com-
petition Authority were also consulted by the Government and
asked to issue opinions on the draft decree.
The decree is based on three pillars: the concept of
shortfall risk, the obligation for suppliers to hold capa-
city certificates, and the obligation for capacity opera-
tors to certify their capacities through contracts.
According to the provisions of the decree, suppliers
are obligated to hold, for each delivery year, an
amount of capacity certificates corresponding to the observed
consumption of each consumer, while transmission and distri-
bution system operators must hold an amount equivalent to
their estimated losses, to meet the security of supply objective;
operators of generation and demand response capacities are
required to enter into certification contracts with RTE for their
capacities, through which they commit to a specific capacity
level. The decree also specifies how the obligations assigned to
suppliers are to be determined, lists the principles to be applied
in certifying operators’ capacities, and describes how capacity
certificate trading is to be organised.
The decree stipulates that the capacity mechanism rules are to be
approved by the Energy Minister, based on proposals by RTE and
after the Energy Regulatory Commission has issued its opinion. In
preparing the draft rules, RTE organised a consultation with mar-
ket stakeholders in 2013, the goal of which was to draft capacity
mechanism rules that would (i) comply with the provisions of the
decree, (ii) translate into practice the priority of recognising real
contributions to security of supply, and (iii) balance the need to
individualise the provisions of the rules with the need to ensure a
degree of stability in the mechanism’s functioning.
Must be available during the period for which genera-tion capacity is committed to be available – PP2
Certified demand response
Must be activated during the reference period for calculating the obligation – PP1
Non-certified demand response
Ten-year results for extreme peak demand response activated one in ten years.
Demand response available during every PP2
period but activated only during one PP2 period
Demand response activated during every PP1 period,
i.e. during ten PP1 periods.
128The provisions of article 6 of the NOME Act are codified in articles L. 335-1 to L.335-8 of the Energy Code. Article L. 335-6 establishes that the terms of application shall be defined in a decree of the Council of State.
75
GUIDELINES FOR THE CAPACITY MECHANISM RULES / 3
Five key choices are particularly illustrative of how the three
principles were taken into account:
> A mechanism based on available capacity is consistent with
the proposal to adopt a market-wide capacity mechanism and
ensure that capacities are rewarded based on their real contri-
bution to security of supply;
> Using a demand-based approach to define the capacity com-
mitment period – i.e. securing commitments for the periods
when demand is highest – is a way to ensure that the capacity
mechanism’s effects target the needs of the power system
when security of supply is threatened;
> The parameters used for calculating suppliers’ capacity obliga-
tion – such as the security factor – and the amount of certifi-
cates issued for capacity – for instance technical constraints
impacting the capacity’s contribution to reducing the shortfall
risk – must be set in such a way as to reflect as accurately as
possible the real contribution of suppliers to the shortfall risk
and the real contribution of capacities to reducing the short-
fall risk;
> Taking into account realised values for consumption and
capacity availability during the delivery year allows the contri-
bution of each market stakeholder to security of supply to
be recognised. Small imbalances between the data submit-
ted and actual results lead to a mere adjustment. To ensure
a balance between this need for individualisation and market
stakeholders’ request for stability and predictability, a norma-
tive approach can also be taken in calculating capacity levels
for intermittent capacity;
> The methods used to calculate capacity obligations and certify
capacity must be defined in such a way as to guarantee non-dis-
crimination between the implicit and explicit valuation of demand
response. To ensure that demand response capacities effectively
contribute to security of supply, capacities that are certified must
be subjected to the same availability commitments as generation
capacities during the period considered (PP2), and demand-side
management measures factored into the reduction of suppliers’
obligations must be effectively activated during the period consi-
dered for the calculation of the obligation (PP1).
76
4. CAPACITY OBLIGATION
This chapter discusses the provisions concerning the calcula-
tion of the obligation for obligated parties. It begins with a review
of the general provisions governing the capacity obligation, i.e.
the identification of parties subject to the obligation, the defi-
nition of reference power and observed consumption, and the
time periods and methods applied in calculating the obligation
(§ 4.1). Details are then provided about the options selected in
RTE’s proposal regarding the definition of the PP1 period during
which the capacity obligation is calculated (§ 4.2), the definition
of the delivery year (§ 4.3) and the parameters for calculating
the capacity obligation (§ 4.4). The last sections of the chapter
present the exact formula used to determine the capacity obli-
gation (§ 4.5) and the obligation timetable for suppliers during a
capacity mechanism term (§ 4.6).
4.1 General provisions regarding the obligation
In accordance with article L. 335-1 of the Energy Code, capa-
city obligation refers to the obligation for any obligated party to
contribute to security of electricity supply by having valid capa-
city certificates for each delivery year.
The decree stipulates that the amount of a supplier’s obligation
“is calculated based on the reference power of its customers
and a security factor taking account of the shortfall risk.”
4.1.1 Obligated parties
The obligation capacity created by the NOME Act of 7 Decem-
ber 2010 applied to electricity suppliers. Taking into account the
recommendations made while the decree was being drafted, the
range of market stakeholders subject to the capacity obligation
was expanded by the Brottes Act of 15 April 2013 (article 15):
“End consumers and system operators, for their losses, that,
for all or part of their consumption, are not supplied by a
supplier, contribute, in accordance with the characteristics
of this consumption, in power and in energy, in mainland
France, to electricity supply security. For the application of
this chapter, they are subject to the provisions applicable to
suppliers.”
This change was intended to ensure that all consumers would
be subject to the capacity obligation, and that the obligations
calculated would be consistent with national consumption.
For the application of these provisions, the rules use the term
“obligated party” to refer to any market stakeholder subject to a
capacity obligation, not just suppliers. The following are defined
as obligated parties under the rules:
> Suppliers, as parties that purchase electricity for sale to end
consumers or system operators (for their losses) and have an
administrative permit;
> End consumers not supplied, for all or part of their consump-
tion, by a supplier;
> System operators, for their losses, when they are not supplied
by a supplier.
4.1.2 Reference power
The decree stipulates that the reference power of an electricity
consumer “reflects its contribution to the shortfall risk during
the delivery year in question.” System operators calculate and
communicate to RTE the reference power of the end consu-
mers connected to their systems, per supplier.
To reflect differences in the treatment of consumers depending
on whether they are remote-read, profiled or buying for losses,
reference power is broken down into three categories: profiled
reference power, remote read reference power and reference
power for the supply of losses.
For each type of consumer, the calculation method is based on
the following principles:
> Inclusion of consumption observed during the peak period
(PP1 period defined below);
> Adjustment for the temperature sensitivity of consumption;
> Adjustment for certified demand response capacities activa-
ted during the PP1 period.
77
CAPACITY OBLIGATION / 4
4.1.2.1 PP1 peak period
The PP1 peak period is the reference period for determining
the obligation of each obligated party. It comprises the hours
during which consumption is measured to calculate reference
power and, ultimately, to determine the amount of the capacity
obligation.
The PP1 period is defined in such a way as to meet the following
two objectives:
> PP1 hours must be the best metric for reflecting, in the obliga-
tion of an obligated party, the real contribution of the consu-
mers within its perimeter to the shortfall risk;
> It must be possible for peak demand management to be
rewarded through a reduction in the obligation, in accordance
with the objectives outlined in chapter 1 of this report and the
goal of fully integrating peak demand management into the
mechanism.
4.1.2.2 Observed consumption
The decree of December 2012 stipulates that “reference
power is calculated based on the observed consumption of
each consumer”129. The obligation is thus not determined on
the basis of predefined standards but rather on measured
data, in order to allocate to each consumer its real contribu-
tion to the shortfall risk. This would be incompatible with a
model in which a party’s obligation would represent a portion
of the total obligation determined separately. In the French
system, observed consumption during PP1 hours constitutes
the basis for calculating the capacity obligation of each obli-
gated party.
The basic data used to calculate the observed consumption
of a consumer are taken from the metering and information
systems of the operators of public systems to which the sites
are connected directly or indirectly. This principle is in keeping
with the regulatory framework governing the energy industry as
a whole, but could create difficulties when it comes to profiled
consumers since their load curve is not measured but rather
estimated based on normative profiles. Pending the deploy-
ment of new metering systems enabling more dynamic assign-
ment of energy flows, the provisions adopted in the rules are
based on the existing systems, particularly the profiling system
that enables a load curve to be reconstituted for each site equip-
ped with a meter indicating readings. The provisions authorising
the explicit valuation of demand response through the capacity
market (see chapter 5) allow this difficulty to be circumvented by
utilising demand-side operators’ facilities to certify their demand
response potential, provided that these facilities comply with
the regulatory framework governing the market
(NEBEF) or the balancing mechanism, i.e. that they
qualify under the rules in effect.
A reference base is used to calculate the observed consump-
tion associated with each obligated party for the calculation
of its reference power: the perimeter of the obligated party.
This perimeter makes it possible to identify a site’s affilia-
tion with a party for the calculation of the obligation, and
addresses cases where sites are associated with multiple
obligated parties.
4.1.2.3 Taking into account the temperature
sensitivity of consumption
The temperature sensitivity of consumption is defined as the
established link, below a certain temperature, between elec-
tricity consumption and temperature. It represents the rapid
response of consumption to a variation in temperature and is
therefore to be distinguished from the cyclical/seasonal com-
ponent of the consumption curve.
Consumption in France has been growing steadily more sensi-
tive to temperatures in the past ten years, and this is a defining
characteristic of the French power system. RTE estimates that
the winter gradient at 7pm increased by 35% between the win-
ter of 2001-2002 and the winter of 2011-2012. This increase
is largely responsible for the peak demand growth discussed in
section 1.2 of this report.
For the capacity mechanism to achieve its security of supply
objective, the sum of the temperature sensitivities considered in
the mechanism must correspond to the temperature sensitivity
observed in France as a whole during the delivery year.
4.1.2.3.1 Characterisation of temperature sensitivity
The link between power and temperature is considered to be
linear. This hypothesis is confirmed by the shape of the scatter
plot obtained when we represent a temperature on the X-axis
and the corresponding consumption of the group of sites stu-
died on the Y-axis.
We observe that below a threshold temperature, the variation
in demand is proportional to the variation in temperature. In
practice, the gradient is the slope of the scatter plot. Above the
threshold temperature, demand is not affected by the tempera-
ture variation.
129Decree 2012-1405, Article 1.
78
30
40
50
60
70
80
90
-5 0 5 10 15 20 25
Gradient
Actual national temperature [°C]
Threshold temperature =
15°CMea
sure
d E
RD
F po
wer
[GW
]
Figure 22 – Illustration of threshold temperature(Source: ERDF, WG of 09/07/13)
80
90
100
50
60
70
30
40
50
Dai
ly a
vera
ge p
ower
(GW
)
20
‐10 -5 0 5 10 15 20 25 30
Actual temperature (°C)
Heating gradient
Figure 21 – Illustration of the heating gradient in France(Source: ERDF, WG of 19/02/13)
2012
1996
7pm points in year of delivery RT8
ERDF data
79
CAPACITY OBLIGATION / 4
Little is seen of the “overheating” gradient for very cold tempe-
ratures; it is therefore not taken into account.
4.1.2.3.2 Determinants of temperature sensitivity
Temperature sensitivity is characterised by 48 half-hourly gra-
dients for a given year, smoothed temperatures and a thres-
hold temperature. The following concepts are used in the rules.
Smoothed temperature
The temperatures used in the capacity mechanism correspond to
variables derived from the raw temperature measured on various
weather stations. It is necessary to construct a temperature herei-
nafter referred to as the “smoothed temperature” – and not to
take raw temperatures – in order to constitute an effective expla-
natory variable of consumption. This temperature is in particular
smoothed to take into account the thermal inertia of buildings.
Threshold temperature
The threshold temperature corresponds to the temperature
below which a variation in temperature is considered to lead to
a variation in consumption. It basically refers to the temperature
below which heating is switched on.
Gradient
The link between power and smoothed temperature, conside-
red for a delivery year, is reflected by a temperature sensitivity
gradient (the slope of the curve) that is constant for a given year.
The link between power and temperature is not uniform over a
day. Forty-eight half-hourly gradients are therefore defined for
each half hour of the day.
4.1.2.3.3 Extreme temperature
In order to reflect the contribution of a consumer to the short-
fall risk due to its temperature sensitivity, the obligation must be
calculated based not on the consumption observed during the
delivery year but on an estimate of this consumption during a
severe cold spell corresponding to the risk against which the sys-
tem is trying to protect itself (one-in-ten-year cold conditions).
For this purpose, the use of an extreme temperature was pro-
posed during the consultation and is adopted in the rules, thus
enabling translation to a cold spell.
In concrete terms, consumption levels observed are translated to
those estimated at this extreme temperature. It is as if the cold spell
defined by this extreme temperature, corresponding to one-in-
ten-year cold conditions, actually occurred each year. The capacity
mechanism is thus similar to an insurance mechanism
providing coverage against an extreme situation with
the level of risk referred to in the security criterion defi-
ned by public authorities. The capacity mechanism
thus enables expected income from capacities to
be stabilised, by spreading out over each year reve-
nue that would otherwise be concentrated in a cold
spell with a probability of occurrence of once every ten years.
4.1.2.4 Adjustment for power reduced by activating
certified demand response capacity
Adjustments are made to reflect the load reduced through the
activation of certified capacity to prevent demand response
from being double counted. Indeed, as discussed in § 3.2.5,
demand response can be valued either through a reduction of
the capacity obligation or directly through the issue of capacity
certificates. It is important to ensure that the same load reduc-
tion is not counted twice, as this would distort competition
between stakeholders and result in a physical volume of capa-
city that is insufficient to meet the security of supply criterion.
The provision adopted in the rules for adjusting for load reduc-
tions through the activation of certified capacity involves adding
the load reductions in question to observed consumption.
4.1.3 Security factor
4.1.3.1 Provisions of the decree
The security factor is intended to meet the requirements set by the
law and decree whereby suppliers’ capacity obligation “encourages
compliance in the medium term with the required level of electri-
city supply security130”, in accordance with the general principle of
making stakeholders accountable for the risks they generate.
The decree stipulates that the security factor “[takes] account of
the shortfall risk” and that “the effect [of interconnections of the
French electricity market with other European markets] is incor-
porated in the determination of the security factor”.
The security factor applies to all obligated parties, making it a
“mutualising” parameter. It only integrates those determinants
of security of supply that are not taken into account through
other means. Roughly speaking, as regards obligations, refe-
rence power already reflects consumers’ contributions to the
shortfall risk, and similarly, on the certification side, certified
capacity131 reflects the contribution of capacity to reducing the
shortfall risk. The security factor included in the rules is thus
exclusively meant to reflect:
130Article L.335-2 of the Energy Code
131Concept discussed in detail in chapter 5 of this report.
80
> The contribution of interconnections to secu-
rity of supply;
> The margins necessary to cover residuals risks,
particularly on demand (other than tempera-
ture sensitivity risk).
The principles applied in determining the security factor, inclu-
ding methodology issues, are described in § 4.4.3. These prin-
ciples and the procedures for changing the security factor are
described in the capacity mechanism rules. The initial numerical
value of the security factor is indicated in the rules, which stipu-
late that any change in this value must be specifically approved
by the Minister.
4.1.3.2 Sensitivity of the security factor to the choice of
the extreme temperature
The determination of the extreme temperature and that of the
security factor are linked. It is thus possible to define several
pairs of values [extT;securityF] that produce the same overall
level of certificates necessary for compliance with the security
of supply criterion132, though the breakdowns between stake-
holders are not the same.
The simplified example below illustrates how the choice of the
extreme temperature influences the security factor. It is based
on the following hypotheses:
> The volume of certificates allocated to the reference mix is
1,000 MW;
> All French consumers are divided between two suppliers,
S1 and S2, the latter being temperature sensitive and the
former not;
> The customer portfolio of S1 is not temperature sensitive and
power demand among its customers on PP1 is 400 MW;
> The customer portfolio of S2 is temperature sensitive with a
gradient estimated at 100 MW/°C. Power demand among its
customers on PP1 is 400 MW.
Four cases are considered with different extreme temperatures:
0°C, -2°C, -3°C and -6°C. It is then possible to calculate for each
of these cases the reference power for S1 and S2 and the cor-
responding total for France.
Case 1 Case 2 Case 3 Case 4
extT (°C) 0 -2 -3 -6
RefP S1 (MW) 400 400 400 400
RefP S2 (MW) 300 500 600 900
RefP France (MW) 700 900 1,000 1,300
The total sum of the obligations must correspond to the volume
of certificates of the reference mix (1,000 MW) for the obligation
to provide an incentive for compliance with the security crite-
rion. It is therefore possible to determine the security factor that
enables compliance with this criterion, and thus the obligation
of suppliers S1 and S2.
Case 1 Case 2 Case 3 Case 4
securityF 1,43 1,11 1,00 0,77
Obligation S1 (MW) 571 444 400 308
Obligation S2 (MW) 429 556 600 692
Total obligation (MW) 1,000 1,000 1,000 1,000
It can therefore be seen that the choice of the two parameters
of the obligation, the extreme temperature and the security fac-
tor, has major redistributive effects between temperature sensi-
tive and non-temperature sensitive consumers.
4.1.4 Summary of obligation principles
4.1.4.1 Formulae
In compliance with the provisions of the decree and in the light
of the abovementioned considerations, it is proposed that the
formulae for calculating the obligation be expressed in the fol-
lowing form.
An obligated party’s obligation is calculated based on its refe-
rence power and the security factor.
Oblig,OP,DY = RefP,DY,OP x SF,DY
> Oblig,OP,DY is the obligation of the obligated party OP for
delivery year DY;
> RefP,DYL,OP is the reference power of the obligated party
OP for delivery year DY;
> SF,DY is the security factor for delivery year DY.
The option chosen in the rules is to make stake-holders accountable for the risks they generate. The temperature sensitivity risk is entirely taken into account by the “extreme temperature” para-meter. It would have been possible to increase the security factor to integrate a portion of the French power system’s temperature sensitivity, but this would have meant assigning a portion of the climate contingency to all obligated parties even though different consumers’ contributions to this risk vary greatly.
132The quantity of certificates needed to meet the security of supply criterion is determined based on the reference mix described in section 4.4.3.
81
CAPACITY OBLIGATION / 4
Reference power is calculated at the level of individual obligated
parties:
> Based on observed consumption, minus the load reduced by
activating certified demand response capacities within a peri-
meter during the PP1 peak period,
> Adjusting for the temperature sensitivity of consumption,
expressed through a gradient, in order to extrapolate obser-
ved consumption to consumption at the extreme tempera-
ture (close to -2.6°C, corresponding to one-in-ten-year cold
conditions).
If ∑tEPP1 ObservedConsumpOP,DY[t] = 0 then refP, DY, OP is set at 0.
> GradientOP,DY[t] is the gradient of the obligated party OP in
half-hourly step t in delivery year DY;
> AdjustedConsumpOP,DY[t] is the observed consumption
of the obligated party OP, in half-hourly step t in delivery
year DY, adjusted for certified demand response capacity
activated;
> ExtT[t] is the extreme temperature, in half-hourly step t, in
delivery year DY;
> SFT, AL[t] is the smoothed France temperature in half-hourly
step t, in delivery year DY;
> nbPP1Hours,DY is the number of PP1 peak period hours in
delivery year DY.
4.1.4.2 Chronological summary of the obligation process
For the first two delivery years, the rules adopt specific provi-
sions making it possible to take into account:
> A specific first delivery year (from 30 November 2016 to
31 December 2017 with July and August excluded) enabling
transition to a delivery year matching the calendar year;
> A shorter period between the start of the term and the deli-
very year. The rules directly incorporate the mechanism para-
meters for these two years.
Once the system is established, i.e. as of the third delivery year,
the chronology of the obligation process under the capacity
mechanism will be as follows:
01/01 DY-4
01/01 DY-2
01/01 DY-2
01/12 DY+201/01
31/1231/03
01/11
Publication of overall obligation
level
DELIVERY YEAR
DELIVERY
15/12 DY+2
15/02 DY+3
Obligationnotification
Transferdeadline
Collectiondeadline
Publication of parameters
–extT, Secu Fact
01/01 DY-3
Imbalancenotification
date
20/12 DY+2
DY
PERIOD
PP1 PP1
Publication of overall obligation
level
Publication of overall obligation
level
Publication of overall obligation
level
refP,DY OP =1
2 x nbPP1Hours,DYx ∑ [AdjustedConsumpOP,DY[t] + GradientOP,DY[t]
x (ExtT[t] – SFT,AL[t])]tEPP1
As explained above, the PP1 period is defined in such a way as to
meet the following two objectives:
> Create the best metric to reflect, through reference power, a
consumer’s contribution to the shortfall risk;
> Encourage the activation of peak demand management mea-
sures, rewarded by a reduction of the obligation, to contribute
to the reduction of peak demand.
4.2 Period for measuring suppliers’ obligation: The PP1 peak period
Consequently, the provision adopted in the rules corresponds to
a targeted PP1 period that is limited in volume and focuses on
the hours when actual consumption is highest. This PP1 period
is part of a delivery year corresponding, with the exception of
the first year, to a calendar year (01/01/YY to 31/12/YY). The
considerations underpinning the provision concerning the deli-
very year are described in § 4.3.
82
4.2.1 Defi nition of PP1 and contribution to the shortfall risk
Given the high level of temperature sensitivity in
France, the shortfall risk is currently concentrated
on the hours of highest demand. The synchrony
between an individual’s consumption and overall consump-
tion in France therefore heavily infl uences its contribution to
the shortfall risk. A consumer that does not consume during
hours of high consumption does not contribute to the short-
fall risk; its reference power should therefore be nil.
This principle was borne in mind when choosing between long
periods, which enable the obligation level to be stabilised but
result in the obligation being pooled among consumers, and
short periods, which target more precisely the periods during
which the shortfall risk is highest and thus enable diff erentiation
between consumers’ contributions to the shortfall risk.
4.2.1.1 Illustration of the impact of the defi nition of PP1
on the reference power of a consumer
The defi nition of the PP1 hours may heavily aff ect the reference
power of individual consumers, particularly non-temperature
sensitive ones. In the illustration in fi gure 23, consumer A (a
typical consumer contributing considerably to peak demand)
and consumer B (a typical consumer moderating its consump-
tion during demand peaks) see their reference power increase
or decrease by 50% depending on whether only hours of high
consumption or all hours are taken into account.
To uphold the provision of the decree concerning accountabi-
lity in proportion to the shortfall risk, the PP1 period must target
the hours of highest consumption for a volume representing
all hours during which shortfall has a signifi cant probability of
occurring.
With a “long” PP1 (potentially the whole weighted winter), hours
of low consumption would be used to estimate a consumer’s
contribution to the shortfall risk. Consequently, the obligation of
a consumer that does not consume during the hours of highest
consumption might not be nil, even though its contribution
to the shortfall risk is nil. The rules proposed by RTE make this
impossible.
4.2.1.2 Impact of the duration of PP1 on the value
allocated to a peak demand management measure
A consumer’s obligation must refl ect its consumption during
the hours when demand is highest. Moreover, in accordance
with the provision of the decree relating to non-discrimination
between certifi ed demand response and reductions in the obli-
gation through load reductions, all peak demand management
measures must be rewarded in proportion to their contribu-
tion to reducing the shortfall risk. Choosing a short PP1 period
is more in keeping with this principle since it avoids diluting
the value of peak demand management measures, which can
contribute substantially to reducing the shortfall risk.
To be accounted for through a reduction in the obligation, peak
demand management measures must be taken during PP1. The
PP1 volume thus determines the activation potential required.
For peak demand management measures to be valued propor-
tionately to the shortfall risk avoided, the scope of the activation
potential must refl ect the shortfall landscape133.
In fi gure 24, the red curve represents the obligation reduction
obtained for a peak demand management measure activated
for 50 hours as a function of the duration of PP1. The blue curve
represents the contribution to the reduction of the shortfall risk
as a function of the number of hours demand response capacity
is activated.
Thus, activation over a period of 50 hours contributes approxi-
mately 88% to reducing the shortfall risk compared with demand
response with no activation limit. If PP1 is very short, for example
less than 50 hours, the peak demand management measure’s
Figure 23 – Demand in France is at its highest between H4 and H6
Con
sum
ptio
n o
fa
few
cu
stom
ers
(MW
)
Fran
ce c
onsu
mpt
ion
(MW
)
600
400
500
100
200
300
0
H1 H2 H3 H4 H5 H6
120,000
80,000
100,000
20,000
40,000
60,000
0
Demandpeakpeak
Heures dans PP1H1 à 6 H4 à 6Puissance de référence A 200 300Puissance de référence B 200 100
Customer A Customer B France consumption
PP1 hours
H1 to 6 H4 to 6
Reference power A 200 300
Reference power B 200 100
133For certifi ed demand response capacity, this dimension is taken into account, in certifi cation terms, through the Kd and Kw coeffi cients (see section 5.3.2).
83
CAPACITY OBLIGATION / 4
134These studies and their results are presented in sections 4.2.4 (for France as a whole) and 4.3.4 (individual obligations) of this report.Heures dans PP1H1 à 6 H4 à 6Puissance de référence A 200 300Puissance de référence B 200 100
eff ect will be entirely taken into account in the reduction of the
obligation. If PP1 is long, a much smaller share of the measure’s
eff ect will be counted in the reduction of the obligation even
though its contribution to reducing the shortfall risk is the same.
The defi nition of the PP1 period must therefore be consistent
with the blue curve so that the impact of a peak demand mana-
gement measure on the reduction of the obligation refl ects
its contribution to reducing the shortfall risk, following two
principles:
> It must be based on the hours of highest consumption, indica-
tive of shortfall risk periods;
> It must be based on a volume of approximately 100 to
150 hours.
4.2.2 Defi nition of PP1 and peak demand management
Basing PP1 on the hours when observed consumption is
highest is also a means of encouraging active peak demand
management. It gives suppliers a real solution for managing the
Figure 24 – Peak demand management measure and contribution to reducing the shortfall risk
Contribution to reducing the shortfall risk
Reduction of obligation for peak demand-side management activated for 50h
Number of hours of activation / Duration of PP1
Red
uct
ion
of s
hor
tfal
l ris
k
51 101 151 201 251 301 351 40110%
20%
40%
60%
80%
100%
risk the obligation represents for them: activating
demand response capacity or other peak demand
management measures. The mechanism proposed
thus ensures that the economic incentives off ered
to market stakeholders correspond to the physical
needs associated with security of supply, the goal
being to approach the economic optimum.
This choice should be considered in the light of other valid
considerations for defi ning the PP1 period. During the consulta-
tion RTE organised in 2013, some suppliers supported the idea
of a long PP1 period, saying it would stabilise the obligation for
stakeholders by neutralising the uncertainty associated with the
location in time of PP1 hours. RTE conducted studies134 to esti-
mate the sensitivity of the obligation to the eff ective distribu-
tion of PP1 hours: these studies showed that the sensitivity was
non-signifi cant.
Most importantly, the alternative scenario involving a long PP1
period would make the signifi cation of the obligation and incen-
tives to reduce peak demand less representative. The less PP1
corresponds to real cold spells, the weaker the incentive to
reduce loads at the right time. With a long PP1 period (all winter,
weighted by shortfall probabilities), the economic incentive for
suppliers to initiate demand management measures with their
customers is greatly diluted. An action to reduce peak demand
would have to be repeated every day in winter to produce the
same reduction in the obligation: the eff ort required to reduce
the obligation by reducing loads during peak periods would be
disproportionate to the real needs of the system, and this would
As defi ned in the rules, the PP1 period:
> Targets periods of high consumption;
> Covers a time period that is consistent with the typical duration of shortfall episodes, enabling peak load reductions to be rewarded in propor-tion to their contribution to reducing the short-fall risk.
84
make no economic sense with regard to the chal-
lenges the French power system is currently facing.
There is also a chance that the timing of demand-
side management measures would not correspond
to peak load periods. For instance, consumers would
be incentivised to reduce consumption during
months with the highest shortfall probability –
notably January – and to consume during other
months. In February of 2012, such a system would
typically not have created any incentive for consu-
mers/suppliers to reduce consumption at the peak
time. The system might even have knock-on effects,
encouraging some consumers to stop in January
and then resume consumption early in February.
The benefits associated with a short PP1 period tar-
geting actual peaks in demand are not as great for
profiled consumers, due to the limitations intrinsic
to a profiling system that does not allow consu-
mers’ specific contributions to peak demand to
be identified with accuracy135. Ultimately, the only way for the
value created for the system to be accurately measured would
be either to replace the profiling scheme with one allowing
the individual treatment of each consumer (not planned as
of today, even after smart meters are rolled out) or to create
profiles for suppliers based on their offerings. In the meantime,
as indicated above, the direct valuation of the load reduction
potential of these consumers in calculating capacity sup-
ply (certification of demand response capacity) provides the
most benefits to the consumers in question. In this sense, the
explicit valuation of demand response on the capacity mar-
ket complements the new valuation opportunities created by
the NEBEF136 rules, which allow load reductions to be valued
at sites independently of the technological limitations of the
meters used there, based on information provided by demand-
side operators.
4.2.3 Notification of PP1 hours
4.2.3.1 Principles
On first analysis, targeting real peak periods on the power system
would require defining PP1 at the end of the delivery year, based
on the hours of highest demand observed during the winter.
This solution would nonetheless create two types of difficulty:
> “Peak shift”: Demand-side management measures taken by
obligated parties during the hours expected to be the hours
“of highest consumption” could have such a powerful impact
135Indeed, since demand reduction efforts are not factored into the load curve (no localised decrease in consumption), the possibility of efforts being rewarded is diluted in proportion to the consumer's share of profiled consumption (in the short term, through the alignment coefficient used in the BRE process which ensures consistency at each time step of the overall profile consumption result) or its share of consumers with this profile (longer term, through an updating of the profile).
136Block Exchange Notification of Demand Response. See report on the explicit valuation of demand response on the wholesale market on the RTE website.
on demand that these hours would no longer be included in
actual peak hours. This phenomenon could prevent demand-
side management measures from reducing the parties’ obli-
gation, in which case the mechanism’s impact would be dis-
proportionate to its objective;
> Predictability of PP1: A very large number of participants in
the consultation asked to have information about potential
peak periods in advance, in order to activate the measures at
their disposal with greater certainty. This point is of particular
concern to suppliers because the entire cost of the obligation
will be concentrated on PP1 hours.
4.2.3.2 Effect of notification on the selection of
the hours of highest consumption
The ideal signal should enable the selection solely of the hours
of highest consumption. However, it is by nature not possible
to predict the corresponding hours with any certainty: the issue
is exactly the same for market stakeholders as for the system
operator.
Given the link between consumption and temperature, pre-
dicting that demand on any particular day will be among the
highest of the winter comes down to predicting that that day
will be one of the coldest of the winter. It would require visibi-
lity on general temperature trends over a long period, whereas
short-term weather forecasts are not currently usable beyond
ten days. Climate scenarios, particularly those used in supply/
demand balance studies, do indeed provide visibility on the
temperature distribution at a given hour of the day and the year,
but it is not possible to deduce the temperature of a given hour
based on past values.
RTE conducted studies on a notification of PP1 hours based on
hour or day type criteria, to establish whether notification would
decrease the performance in terms of targeting the hours of
highest consumption. The studies confirm that targeting will
To address these difficulties, RTE proposes that the PP1 days that will be used to calculate suppliers’ obligations be notified one day ahead of time.
Notification of PP1 hours with a reduced volume requires managing the stock of hours to be noti-fied. Consequently, the hours notified might not correspond exclusively to the hours of highest consumption during the delivery year as observed after the fact.
85
CAPACITY OBLIGATION / 4
IllustrationoftheconsequencesofthechoiceofPP1foraconsumercapableofreducing
itsconsumptionby50%over15days
For purposes of simplifi cation, it is assumed that the consumer is non-temperature sensitive and that its consumption is constant
(equal to C) over the year in order to illustrate only the consequences of the choice of PP1. The consumer’s reference power thus
corresponds to its average consumption over PP1.
referenceP = Consumptionaverage on PP1 = C – Load reductionPP1
The impact of PP1 on the consumer’s reference power therefore corresponds to the taking into account of load reductions as
a function of PP1.
With a targeted PP1, the load reduction is considered in its entirety and consistently with its contribution to reducing the shortfall
risk:
Load reductiontargetedPP1 = NB activationload reduction x Volumeload reduction = 50%.C
referenceP, targetedPP1 = 50%.C
With a long PP1, to provide maximum benefi t to the consumer through a reduction of its obligation, the load reduction must be
positioned on the month corresponding to the highest weighting. In this illustration and in line with a weighting proposed in the
consultation, this month is January, with a weighting of 70%.
Load reduction long PP1 = Weightjanuary x NB activationload reduction x Volumeload reduction
= 70% x 15 x 50%.C = 21%.C
referenceP,long PP1 = 79%.C
This example illustrates the importance of the choice of the PP1 period for rewarding demand management actions through a
reduction of the obligation. The value assigned to demand response is reduced by more than half with a long PP1 period even
though its contribution to reducing the shortfall risk is virtually equivalent to that of a resource without constraints.
The example also illustrates the impact of a long PP1 period in terms of potential contradictions between incentives in the
energy market and the capacity mechanism. Thus for a delivery year such as 2012 with a cold spell in February, if the consumer
focuses demand response on the hours of the cold spell, this would only be refl ected in its capacity obligation in proportion to
the weighting of February (20% in the weighting presented in the consultation), resulting in an even lower benefi t (6%.C).
NB PP1 days
NB working days
25
86
Analysis of the performance of the signal
Table 1 – Days criterion – Performance in notifying the 100 hours of highest demand.
Nb of Days notifi ed* 10 15 20 25 30 35 40 45 50
Av. Nb Peak Days notifi ed 9.22 13.58 17.44 20.5 22.62 24.18 25.3 26.16 26.68
Min. Nb Peak Days notifi ed 6 9 12 14 16 19 20 20 20
Max. Nb Peak Days notifi ed 10 15 20 25 28 31 33 36 39
Average score 63.98% 79.20% 87.92% 91.34% 93.10% 95.38% 96.40% 97.64% 98.34%
Figure 25 – Distribution of the results of the table above
Table 1 shows that to expect to identify 90% of the
100 hours of highest consumption, it is necessary to
notify between 20 and 25 days (approximately 350
hours). It is important to underline that with a stock of
15 days, in 25% of cases, the signal only enables iden-
tifi cation of at most 70% of the 100 hours of highest
consumption (min. at 25%).
This volume is consistent with the distribution of the
100 hours of highest consumption for each winter – on
average over 20 days between November and March.
Figure 26 – Number of days containing the days of highest demand each winter (Source: Power consumption records – RTE Customer website)
If all the PP1 hours correspond exactly to the notifi ed hours, the period notifi ed must be reduced, in line with the defi nition of
PP1. In this sense, a period of 10 to 15 days (100 to 150 hours) is consistent with the volume necessary to estimate the contribu-
tion to the shortfall risk (see § 4.2.1).
The results of the above study on the signal, summarised in Table 1, show that a signal that covers such a period enables
identification of between 60% and 80% of the 100 hours of highest consumption. However, PP1 does not then solely con-
sist of the hours of highest demand. Of the days notified, on average one day out of 10 or two days out of 15 (for a signal
of 10 notified days or 15 notified days respectively) do not contain any of the 100 hours of highest demand in the winter.
The study showed it is possible that up to 40% of the notified days will contain none of the 100 hours of highest demand
(with 15 days notified).
0%10 15 20 25 30 35 40 45 50
25%
50%
75%
100%
Number of days notified in winter
% o
f th
e 10
0 h
ours
of h
igh
est d
eman
dam
ong
the
hou
rs n
otifi
ed
0
10
20
30
40
50
60
1996199719981999200020012002200320042005200620072008200920102011
1996199719981999200020012002200320042005200620072008200920102011
1996199719981999200020012002200320042005200620072008200920102011
1996199719981999200020012002200320042005200620072008200920102011
1996199719981999200020012002200320042005200620072008200920102011
1996199719981999200020012002200320042005200620072008200920102011
50 H
Ave = 12 d Ave = 20 d Ave = 26 d Ave = 32 d Ave = 38 d Ave = 42 d
100 H 150 H
Winter
Nu
mbe
r of d
ays
200 H 250 H 300 H
* “Peak Day”: Day containing at least one hour of the 100 hours of highest demand
87
CAPACITY OBLIGATION / 4
It is therefore necessary for the choice of PP1 to incorporate
elements allowing the variability of the obligation volume to be
smoothed, and in particular to:
> Remove periods of “interruption”, i.e. periods when demand is
not representative of normal behaviour (weekends, bank holi-
days and Christmas holidays);
> Include periods when temperatures are cold, limiting the
uncertainty linked to errors in the modelling of the climatic
correction;
> Include PP1 days (defi ned time slot) rather than independent
hours in order to stabilise intraday variations in consumption.
Lastly, notifi cation of PP1 days prevents a very high concentra-
tion of PP1 hours over a short period and thus tends to smooth
the distribution of the days notifi ed over the winter period. Using
a signal to designate PP1 days thus helps to stabilise reference
power.
4.2.4 Sensitivity of the obligation to the location in time of PP1
Variations in non-temperature sensitive consumption over the
winter result in a slight variation in reference power depending
on the “location” of the PP1 hours selected. During the consul-
tation, some suppliers cited this infl uence to request that the
PP1 period be extended, in order to stabilise the obligation. As
indicated above, RTE conducted specifi c studies on this issue to
quantify the uncertainty associated with the location in time of
PP1 days. These studies established that the location in time of
PP1 days has little infl uence on the amount of the obligation.
not be perfect, illustrate the impact of the number of days noti-
fi ed on the signal’s accuracy, and show that a PP1 period of
10-15 days will cover most of the hours of highest consumption.
4.2.3.3 Eff ect of PP1 notifi cation on the obligation level
“Transposing” actual consumption to an extreme temperature is
a way to translate the key critical risk facing the power system
and the level of tension against which it seeks to protect itself.
In fi gure 27, the climatic correction translates actual consump-
tion (yellow curve @realisedT) into consumption at the extreme
temperature, which serves as the reference for calculating the
obligation (blue curve @extT). In terms of temperature sensiti-
vity, the choice of the PP1 period, i.e. the choice of the points of
the blue curve, has no eff ect on the volume ultimately obtained.
However, though the extrapolation of temperature sensitive
consumption to the extreme temperature allows the wea-
ther contingency to be isolated, we also observe a variation
in non-temperature sensitive consumption during the winter
(see fi gure 28). Increased use of lighting when days get shorter
explains the bell-shaped variation centred on January (the dip is
due to the Christmas holidays).
This change in non-temperature sensitive consumption during
the winter leads to a variation in the reference power according
to the “location” of the hours of highest demand during the
winter. Thus, a winter in which the hours of highest demand are
in January will show a higher reference power than a winter in
which the hours of highest demand are at the end of February.
Figure 27 – Illustration of climatic correction on an ErDF profi led portfolio (Source: ERDF, WG of 09/07/13)
0
10
20
30
40
50
60
70
80
90
@TE
@TR
November December January February March
Pow
er [G
W]
Clim. Corr.TR TE
88
Figure 28 – Illustration of variations in temperature sensitive and non-temperature sensitive demand in the year 2011-2012 (data: RTE – 2012 Electrical Energy Statistics)
20
40
60
80
100
Sept
.
Oct
.
Nov
.
Dec
.
Jan.
Feb.
Mar
ch
April
May
June July
Aug.
Sept
.
Ave
rage
dai
ly p
ower
(GW
)
Month Average Standard deviation Min. Max.
November 2% 5% 0% 20%
December 22% 24% 0% 70%
January 52% 26% 0% 90%
February 21% 24% 0% 100%
March 2% 10% 0% 40%
Table 2 – Distribution of the ten days of highest consumption since 1996 (Data: RTE Customer website – Power consumption records since 1996)
Consumption excl. heating
Demand response
Heating
Air conditioning
It should be noted that the hours of highest consumption do
not occur in a random or uniform way over the winter period
as a whole. For instance, the ten days of highest consumption
have never all fallen in November or in March. The December
to February period contains on average 96% of the ten days
of highest consumption and at least 60% of these ten days.
The uncertainty resulting from the location in time of the PP1
days does not therefore correspond to the min-max variation
between the peak in January and the dip at the end of March.
The studies carried out seek to estimate (i) the level of variability
of the France obligation linked to the location in time of PP1,
and (ii) the benefi t of possible PP1 milestones in the last and fi rst
months, March and November.
4.2.4.1 Estimation of the sensitivity of reference power
based on actual consumption
The sensitivity of the France reference power to the selection of
PP1 days, factoring in the eff ect of PP1 day notifi cation, was eva-
luated over several years. For this purpose, consumption levels
transposed to the extreme temperature were calculated for
each eligible day, applying the methods described in the rules,
over the six years from 2006 to 2011.
For each delivery year, the 100 France consumption scenarios
for the year in question, drawn from the 100 Météo France
climate scenarios representative of the existing climate, were
divided into two sets of 50 scenarios: the first (the calibration
set) was used to determine the parameters of the signal and
89
CAPACITY OBLIGATION / 4
Figure 29 – Variability of reference power incorporating the eff ect of PP1 day notifi cation
Jan. – March & Nov. – Dec. with PP1 notifi cation (MW)
Jan. – March & Nov. – Dec. with PP1 notifi cation (%)
Stan
dard
dev
iati
on (M
W)
Stan
dard
dev
iati
on a
s %
of r
efP
0
200
400
600
800
1000
1200
1400
0
0.2%
0.4%
0.6%
0.8%
1.0%
1.2%
1.4%
2006 2011 Average2010200920082007
the second (the test set) to obtain a distribution of notified
days. This methodology using sets of calibration and test sce-
narios that are consistent yet different makes it possible to
obtain unbiased results (neither overestimated nor underes-
timated). The test set yields 50 distribution scenarios for PP1
days that are consistent with the provisions adopted in the
rules.
The distribution scenarios and consumptions at extreme tempe-
ratures for each delivery year enable 50 reference power values
to be obtained, thus giving a good estimator of the variability of
reference power incorporating the notifi cation.
Two lessons can be drawn from this study, based on the distribu-
tion of the selected PP1 days over the delivery period:
> The average variability over these six years is low, with a stan-
dard deviation of 500 MW, or a variability of less than 0.6% of
the France reference power;
> For each delivery year, the standard deviation is between
400 and 600 MW.
4.2.4.2 Estimation of the benefi ts of milestones in
March and November for the PP1 peak period
During the consultation, certain stakeholders proposed
methods of limiting the eff ect of the variation in non-tempera-
ture sensitive consumption by limiting the number of PP1 days
in the months of March and November or even using only the
months of January, February and December as the period for
selecting PP1 days.
RTE carried out a study based on actual consumption and
Météo France climate scenarios comparing the sensitivity of
reference power to the location in time of the PP1 hours with
(1) a milestone of fi ve days at most introduced in March and
November and (2) only the period [ January; February; Decem-
ber] taken into account. The sensitivity obtained in both cases
was then compared with that obtained with no milestone, which
served as a benchmark (basis 100).
This analysis shows that a limitation of the number of PP1 days
in March and November has no signifi cant eff ect on the variabi-
lity of reference power. Consequently, these methods were not
adopted in the mechanism rules.
Figure 30 – Impact of PP1 milestones on the variability of reference power
Rel
ativ
e se
nsi
tivi
ty o
f ref
P.(b
asis
100
: sta
ndar
d de
viat
ion
ofre
fP w
ithou
t mile
ston
e)
2006 2007 2008 2009 2010 2011 Average
0
20
40
60
80
100
120
140
160
Jan. to March & Nov. and Dec. with max. 5 d in March and Nov. Jan and Feb. & Dec.
90
To summarise, the two studies conducted confirm that the
methods adopted in the rules on the PP1 peak period lead to
a reference power, for France, with a low degree of sensitivity
to the actual climate in the delivery year: the average standard
deviation is 500 MW, a value well below the 2 GW threshold
adopted as the maximum imbalance for settlements. Additional
studies focusing on the supplier level support these results, and
can be found in § 4.3.4.
4.2.5 Provisions adopted in the rules on PP1
A series of major expectations regarding PP1 were expressed in
the course of the consultation:
> The hours notified must correspond to the hours when natio-
nal demand is actually highest;
> The hours notified are the PP1 hours (signal creating a
commitment);
> The volume of PP1 corresponds to a reduced number of hours
(50 to 200 hours).
Based on the results of the study on the signal discussed above,
these requirements are incompatible. It is therefore necessary
to ease certain constraints when defining the PP1 period:
> The volume of PP1 is not fixed but varies between a lower
and upper limit. The definition of these limits was conside-
red based on the performance of the signal obtained and
in compliance with the principle of non-discrimination
between reductions of the obligation and certified demand
response;
> The notification of PP1 is based on a consumption criterion.
PP1 hours will therefore be hours of high consumption. Howe-
ver, as the volume of PP1 is regulated and kept targeted, the
PP1 hours will not necessarily systematically be the hours of
highest consumption of the delivery year.
RTE proposes that PP1 days be notified on D-1 at 10:30am.
The need for a notification time prior to fixing on the spot mar-
ket became apparent during the consultation, as this allows
suppliers to activate peak demand management measures to
reduce their obligation and adjust their energy coverage accor-
dingly. Choosing the latest possible time makes it possible to
refine the demand forecast used for the notification and there-
fore to target days of high consumption more accurately.
The demand criterion used for activating a PP1 signal will be based on:
> Statistical distributions of possible consumptions at this
period of the year, produced by RTE on the basis of Météo
France temperature series and medium-term weather fore-
casts. These distributions are used to define consumption
thresholds beyond which a signal is sent;
> The day-ahead national demand forecast drawn up by RTE on
the basis of Météo France short-term temperature forecasts.
The PP1 peak period defined in the rules thus enables the natio-
nal demand peak to be targeted as closely as possible, with a pro-
vision included to provide greater stability for obligated parties.
1. The PP1 period corresponds to the time slots [07:00; 15:00[ and [18:00; 20:00[ (i.e. ten hours per day) on days notified by RTE.
2. The days notified are not selected before the delivery period. However, they will always be working days in the months between Novem-ber and March, minus the period correspon-ding to the Christmas school holidays.
3. PP1 days are notified on D-1 at 10:30am. Notification is based on a demand criterion.
4. The number of PP1 days notified varies between 10 and 15.
4.3.1 Overlapping year centred on a winter or calendar year
The decree stipulates that the delivery year is “a twelve-month
period, not necessarily coinciding with the calendar year, that
includes a PP1 peak period and a PP2 peak period”.
The decree indicates that the first delivery year is to include the
winter of 2016-2017 (“The first delivery year begins in 2016 and
4.3 Delivery year
covers the peak periods of the winter of 2016-2017”) but does
not specify anything for the following years.
The consultation highlighted two possible ways of defining the
delivery year: a delivery year centred on a winter (overlapping two
calendar years) or a delivery year corresponding to a calendar year.
The key arguments made to support either of the two options
were based on:
91
CAPACITY OBLIGATION / 4
> “Physical” factors associated with the actual management of the
power system, supporting a delivery year overlapping two years;
> “Contractual” factors relating to how the capacity mechanism
would fi t into the existing contractual system (energy market
and ARENH mechanism), supporting a delivery year corres-
ponding to a calendar year.
The issue of compliance with the European framework was also
addressed during the consultation: the defi nition of a “capa-
city certifi cate” product with identical periods would facilitate
exchanges of this product between countries.
All of the topics discussed during the consultation and pres-
ented in this section show that, in practice, provisions such as
the notifi cation of PP1 days reduce the impact on suppliers of
the defi nition of the delivery year. RTE therefore proposes that
the mechanism operate according to the calendar year, which
should facilitate its integration with existing contractual prac-
tices and then with Europe going forward.
4.3.2 Impact of the choice of the delivery year on the functioning of the mechanism
A delivery year that corresponds to the calendar year will make
the post-delivery year trading period longer than with a staggered
year; the transfer deadline is closely correlated to the deadline for
gathering defi nitive consumption data (fi nal consumption data
for December of year Y are not known until October Y+2).
The choice of a calendar year including two peak periods
(January to March and November-December) thus makes it
more diffi cult to send a signal on peak periods, as RTE only has
detailed information on the system at a seasonal scale.
4.3.3 Sensitivity of the capacity mechanism to the defi nition of the delivery year with regard to the security of supply objective
Aligning the delivery year with the calendar year leads to two dis-
tinct types of risks because of structural changes in consump-
tion and the capacity mix.
In terms of consumption, choosing a calendar year leads to
variability in the overall level of obligation due to the structural
growth in demand over a year (up to 2%). Nearly a year goes
by between the two winter segments of a calendar year. This
demand trend is structural and the climatic correction applied
does not compensate for the diff erence between the two refe-
rence power levels. Thus, depending on the location of the
PP1 hours, the reference power obtained will correspond to an
Figure 31 – Location of the 200 hours of highest demand of each delivery year with a calendar year and overlapping year
jan. 1996
jan. 1997
jan. 1998
jan. 1999
jan. 2000
jan. 2001
jan. 2002
jan. 2003
jan. 2004
jan. 2005
jan. 2006
jan. 2007
jan. 2008
jan. 2009
jan. 2010
jan. 2011
jan. 2012
jan. 2013
jan. 2014
jan. 1996
jan. 1997
jan. 1998
jan. 1999
jan. 2000
jan. 2001
jan. 2002
jan. 2003
jan. 2004
jan. 2005
jan. 2006
jan. 2007
jan. 2008
jan. 2009
jan. 2010
jan. 2011
jan. 2012
jan. 2013
jan. 2014
30
40
50
60
70
80
90
100
Con
sum
ptio
n (G
W)
Overlapping yearCalendar year
30
40
50
60
70
80
90
100
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
92
average of these two levels, weighted by the distribution of the
PP1 hours between the fi rst and second periods.
To illustrate this point, the consumption curves from 1996
to 2012 are shown with, in colour, the 200 hours of highest
consumption for a calendar year and for a staggered year.
Choosing a calendar year leads to the selection of 200 hours
corresponding to consumptions that underestimate the winter
peak. This eff ect is particularly visible in 2008 (consumption in
purple).
RTE conducted an analysis to evaluate the sensitivity of the
“France” reference power to the type of delivery year chosen.
One hundred PP1 hour distribution scenarios were considered,
obtained from 100 France consumption scenarios drawn from
the 100 Météo France climate scenarios representative of the
existing climate. For each scenario, PP1 hours were chosen
based on provisions of the draft rules (time slots and eligible
days, volume between ten and 15 days, notifi cation based on a
demand criterion).
The analysis shows fi rst of all that the “France” reference power
has a low degree of sensitivity to the distribution of the PP1
hours, whatever the option chosen for the delivery year: the
standard deviation is around 400 to 500 MW, or approximately
0.5% of the “France” reference power. This is in line with the
results presented above.
Secondly, it can be seen that the choice of a calendar year
slightly increases average uncertainty about the overall level of
obligation due to the location of the PP1 hours in time, for all the
years studied apart from 2008. The average standard deviation
is 490 MW (0.55% of the average “France” reference power) with
a calendar year compared with 450 MW (0.5% of the average
“France” reference power) with a staggered year.
4.3.4 Sensitivity of suppliers’ obligation to the choice of delivery year
Current commercial practices, at least in the large consumers
market, are organised around annual contractual periods begin-
ning on 1 January of each year of the contracts. This can result in
a signifi cant change in the customer portfolio of a given supplier
on 1 January. The actual distribution of the PP1 hours between
the periods before and after 1 January therefore plays a decisive
role as regards the amount of a supplier’s obligation.
To estimate the sensitivity of the reference power of the main
suppliers to the option chosen for the delivery year, RTE conduc-
ted a study using the same methodology as above but this time
at the supplier level.
Figure 33 summarises the results obtained for the main Balance
Responsible Parties (BRPs) (reference power of more than
800 MW). It represents, for the six years considered, the average
variability of the obligation of each BRP in proportion to its refe-
rence power, depending on whether the delivery year is centred
on a winter or corresponds to a calendar year.
The analysis shows that the standard deviation is less than 4%
for all the main suppliers, and even below 2% for all except one.
Comparing this with the initial simulation results presented in the
interim report of September 2013, we can note that the variabi-
lity of the reference power of the main suppliers is considerably
Figure 32 – Relative uncertainty linked to the choice of the delivery year on France reference power
Figure 33 – Relative uncertainty linked to the choice of the delivery year on the reference power of the main BRPs
Stan
dard
dev
iati
on (M
W)
Stan
dard
dev
iati
on a
s %
of r
efP
0
100
200
300
400
500
600
700
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
2006 2011 Average2010200920082007
Stan
dard
dev
iati
on a
s %
of r
efP
Main BRPs0%
1%
2%
3%
4%
5%
Winter year – Absolute deviation (MW) Calendar year – Absolute deviation (MW)
Winter year – Relative deviation (%) Calendar year – Relative deviation (%)
Winter year Calendar year
93
CAPACITY OBLIGATION / 4
lower. This refl ects the notifi cation of PP1 days, which results in
the days being distributed over the delivery period and, ultima-
tely, to a regulation of the weight of the early winter (November
and December)137. Consequently, the variability of reference
power due to the change in portfolios on 1 January is smoothed.
However, variability in the obligation is still greater for several sup-
pliers with a staggered year than with a calendar year (average dif-
ference in variability of more than 1 to 2 percentage points), espe-
cially as their contractual practice is centred on a calendar year.
Taking this observation as a starting point, several approaches
are possible.
The fi rst consists in introducing parameters in the capacity
mechanism rules to reduce the sensitivity of suppliers’ obliga-
tion to the location of the PP1 hours, either by:
> Stipulating a breakdown of PP1 hours between the periods
before and after 1 January: this option necessarily diminishes
the quality of the signal. Based on the same number of days,
hours with lower demand would be selected than with a sys-
tem with no predefi ned distribution. Insofar as peaks would
be less accurately targeted, issues relating to the valuation of
non-certifi ed demand response and the increase in the tem-
perature sensitivity modelling error would be exacerbated. To
address these problems, an increase in the number of PP1
days would enable the hours of highest consumption to be
better targeted, despite the predefi ned distribution, but would
also dilute the value of peak demand response;
> Aligning delivery years with calendar years: this
solution leads to a slightly higher variability of the
overall level of obligation but is very eff ective in
terms of stabilisation.
The second approach consists in transferring res-
ponsibility for managing this risk to suppliers, which
can if necessary cover it with initiatives outside the
capacity mechanism. Suppliers could implement
various solutions to manage and cover this risk:
> Contracts with consumers: one practical way would be to
make contract durations match the delivery years of the capa-
city mechanism;
> Hedging instruments: the risk stemming from the location
of PP1 hours essentially corresponds to the distribution of
reference power between suppliers, as the total reference
power is aff ected only to a small degree. In theory, suppliers
are therefore justifi ed in entering into hedging arrangements
amongst themselves to protect themselves against this. The
cost of hedging this risk should theoretically be low, apart
from interface costs, since the overall risk is low and one of
distribution. Such hedging products do not currently exist and
would therefore have to be created;
> Trading of certifi cates during the delivery period or beyond:
again, the choice of the delivery year essentially creates a risk
relating to the distribution of reference power between sup-
pliers. The decree allows for transfers of capacity certifi cates
during the delivery year and even after obligated parties have
been notifi ed of their obligation. Consequently, it is possible
137In the studies conducted by RTE on historical data, November and December account on average for 40% of PP1 days with a standard deviation of around 10%. These values are very stable from one delivery year to the next.
Figure 34 – Relative uncertainty associated with choice of delivery year on residual obligation of the main BRPs considering an allocation of ARENH rights in proportion to PP1 days
Main BRPs
Stan
dard
dev
iati
on a
s %
of r
efP
0
1
2
3
4
5
Winter year Calendar year
94
for suppliers to adjust their coverage based on the actual loca-
tion in time of PP1 hours by trading certificates.
During the consultation, many suppliers also stressed that the
methodology that will be used to allocate the capacity cer-
tificates associated with ARENH rights was not known when
the draft rules were submitted for consultation. The allocation
method chosen for ARENH certificates can have conside-
rable effects on the variability of suppliers’ reference power.
Basically, if the amount of ARENH certificates allocated to
suppliers changes symmetrically with their reference power
depending on the distribution of PP1 days, then suppliers are
exposed only on the residual consumption volume excluding
ARENH.
To estimate the possible effects of the allocation of ARENH certi-
ficates, the same sensitivity analysis was carried out considering
the residual obligation of suppliers once the ARENH certificates
have been allocated. In the model used, ARENH certificates are
allocated in proportion to the number of PP1 hours and ARENH
rights for the year N and N+1.
With the method of allocating ARENH certificates adopted for
this study, the variability of the residual obligation of all the main
suppliers apart from one is lower with a staggered year than with
a calendar year.
These results therefore show that the option chosen for allo-
cating the capacity certificates associated with ARENH rights
can limit the impact of the location of the PP1 hours linked to
the change in customer portfolios on 1 January. Thus, depen-
ding on the methods chosen for the ARENH, the option of an
overlapping year for the capacity mechanism could be adop-
ted without necessarily requiring a re-adaptation of current
commercial practices in the energy industry based on calen-
dar years.
Provision adopted in the rules for the delivery year
The studies conducted on the choice of the year do not identify one type of delivery year that stands out clearly intermsofstabilityalone. The sensitivity of the obligation to the choice of the delivery year is relatively low both for France and at supplier level, notably because notification distributes the days over the whole delivery period. These studies are all the less conclusive because the methods of allocating capacity certificates to ARENH rights are not known and can greatly affect the variability of suppliers’ obligations.
The debate about the type of delivery year to be selected is actually about a choice between two approaches: one based on the physical management of the system, which favours a staggered year centred on a winter, and one based on contracts, which favours a calendar year since this is usually the basis for contracts in the energy market.
Therulesproposeadeliveryyearmatchingthecalendaryear,startingwiththesecondyearthemechanismisinplace. This is the preferred choice of alternative suppliers and industrial consumers, since it will allow the capacity mechanism to align with existing contractual practices in the energy market.
At a time when the European Commission is asking Member States to align their approaches to capacity questions with the broader framework of the European energy market, the choice of a calendar year should also facilitate subsequent integration at the European level, based on existing contractual practices.
In keeping with the provisions of the decree and to facilitate the transition to the calendar year targeted, the first delivery year will begin on 1 November 2016 and end on 31 December 2017, with July and August 2017 excluded.
4.4.1 Determination of the obligation parameters (extreme temperature and security factor)
4.4.1.1 Timing of the publication of obligation parameters
Article 18 of the decree stipulates that “during the four-year
period preceding each delivery year, and at least once a year
for each delivery year, the public electricity transmission system
4.4 Parameters of the capacity obligation
operator publishes forecasts relating to the overall level of
capacity certificates enabling the capacity obligation of all sup-
pliers to be met.” This publication is based on a supply-demand
balance study conducted for the delivery year.
The rules include a provision that corresponds to the use of this
adequacy study to determine the possible need for an updating
95
CAPACITY OBLIGATION / 4
of the obligation parameters (extreme temperature and secu-
rity factor) and of the tables used for capacity certification (see
§ 5.3.2).
Any updates to these parameters must be approved by the
Energy Minister. Indeed, in the absence of specific references
in the decree to changes made to provisions in the rules, the
principle of parallel powers gives the authority responsible for
enacting an act the power to amend or abolish it. In this ins-
tance, insofar as the Minister approves “all provisions relating
to capacity certification” and “all provisions relating to capacity
obligation, and in particular to the method of calculating refe-
rence power and determining suppliers’ obligations”, it must
approve any modification of these parameters.
At the start of a capacity mechanism term, the mechanism para-
meters are published together with the first forecast of the overall
level of certificates. Forecasts of the overall level of certificates are
thus calculated with the same methods and parameters as those
ultimately used for calculating the obligations of obligated parties.
The provision adopted in the rules corresponds to the choice of
stable parameters throughout a term (intra-term stability). Para-
meters may vary from one term to another (inter-term change)
to reflect how the power system evolves and its dynamics over
several years.
Defining the mechanism parameters in advance gives suppliers the
visibility they need to incorporate the impact of the amount of their
obligation into their contracts with customers, meet their obligation
and possibly implement demand management measures.
This system allows compliance with the provisions of the Energy
Code138 stipulating that suppliers must act in advance:
“The obligations imposed on suppliers are determined in such
a way as to encourage compliance in the medium term with
the level of security of supply.”
“Capacity certificates are required sufficiently in advance.”
4.4.1.2 Determination of the reference mix taking the
supply security criterion into account
The obligation parameters are determined based on a supply-
demand balance study for the delivery year.
Through this study, a reference mix is determined that corres-
ponds to the anticipated mix to or from which capacities will be
added or subtracted to obtain a shortfall duration that exactly
matches the supply security criterion defined by
public authorities139, without exceeding it (this
would lead to overcapacity that would be costly
for consumers) or coming in below it (this would
reduce the level of security, at the expense of the
community).
This reference mix is used to estimate the overall
level of obligation corresponding to the volume of
certificates that must be held by the community of
suppliers for the security criterion to be met. The overall level
of obligation corresponds exactly to the volume of certificates
allocated to the reference mix.
3 h criterion met <=> CertificatesOverall Level = ∑ Certificates allocated
This approach ensures the necessary coherence between certi-
fication and obligation: when public authorities’ security of sup-
ply criterion is met, the overall level of certificates (and there-
fore the mix underlying it) exactly matches the sum of suppliers’
obligations.
The amount of certificates allocated to the reference mix is cal-
culated by certifying that mix in accordance with the capacity
mechanism rules for the term in question, i.e. taking into account
any updates to the certification parameters. Consequently, the
certification of the reference mix incorporates all changes in the
power system in its measurement of the contribution of capaci-
ties to reducing the shortfall risk.
138Article L-335.2
139The same method is used here as in the studies in the Adequacy Forecast Report. For further details, see page 35 of the 2013 Adequacy Forecast Report update and pages 82-83 of the 2012 Adequacy Forecast Report.
Figure 35 – Illustration of how the reference mix is determined
Forecast situation
(if E > criterion) (if E < criterion)
Referencemix
Existing capacities
Capacities under construction
Additionalpower Margin
Contribution of interconnections
Shortfall expectation
3h/year
Shortfallexpectation
Xh/year
Reference Mix
96
These two objectives are met thanks to supply-demand balance
studies conducted by RTE. The process involves two stages:
> First, determining the individual contribution to the shortfall risk
which leads to the determination of the extreme temperature;
> Second, ensuring via the security factor that the
mechanism is sufficiently complete to meet the
security of supply criterion.
4.4.2 Extreme temperature
4.4.2.1 Determination of the extreme
temperature
As indicated above, the extreme temperature must be
defined in such a way as to avoid assigning part of the
temperature sensitivity risk to non-temperature sen-
sitive consumers via the security factor. Making tem-
perature sensitive consumers responsible in this way,
without pooling, gives them a considerable incentive
to keep their consumption in check and supports the
peak demand management objective. This assign-
ment of responsibility must therefore be ensured.
Securityfactor
Extreme temp.(> France consumption
at extreme temp.)
Volume ofcertificatesrequired to
meet criterion
Probabilisticsupply-demandbalance study
Reference mix enabling security of
supply criterion to be met
Francesupply and
demandassumptions
Europesupply and
demand assumptions Capacity
certificationparameters
Update based on
changesin system
4.4.1.3 Determination of the obligation parameters
(extreme temperature and security factor)
Certifying the reference mix makes it possible to determine
the total amount of certificates necessary for the supply
security criterion to be met. The parameters of the obligation
(extreme temperature and security factor) are defined in such
a way as to:
> Ensure that the overall obligation volume corresponds exactly
to the volume of certificates of the reference mix, enabling
compliance with the supply security criterion;
> Determine the pair of values [extTsecurityF] that assigns the tem-
perature sensitivity risk to temperature sensitive consumers
without transferring it to non-temperature sensitive consu-
mers (see § 4.1.3.2).
140The power system is transposed to “3 hours” with the same methodology as that used to determine the reference mix (see figure 37).
141A “perfect resource” corresponds to a fictional capacity that is perfectly available with no technical constraint. It serves as a touchstone for the mechanism because each MW from a perfect resource is allocated 1 MW of capacity certificates.
142Considering this demand in France alone would naturally lead to a perfect resource need of 1 MW for 1 MW of consumption.
Figure 36 – Illustration of the relationship between the overall level of certificates and the obligation parameters
Simulations were carried out to determine the extreme tempe-
rature that meets these requirements. A marginal approach was
adopted to allow for the estimation of specific individual para-
meters without disrupting the system as a whole. This is impor-
tant because the phenomena studied intrinsically depend on
the system in which they play out: a consumer’s contribution to
the shortfall risk is directly linked to the form of the shortfall and
therefore to the underlying system as a whole. This approach
thus complies with the letter and spirit of the capacity mecha-
nism decree, which assigns to each consumer its contribution
to the shortfall risk.
The approach used can be described as follows:
> The initial situation corresponds to the projected state of the
interconnected French power system, with security of supply
set at the criterion defined by public authorities;
> Starting from this situation, various consumption profiles are
added marginally, causing security of supply to deviate from
the criterion defined by public authorities140;
> “Perfect resources”141 are then added until security of supply
is restored to the criterion defined by public authorities.
97
CAPACITY OBLIGATION / 4
This approach allows the following results to be obtained:
> The need in terms of perfect resources necessary with
consumption that is constant over the year and perfectly non-
temperature sensitive, taking account of the interconnection
of the French system142, is estimated;
> The addition of a purely temperature sensitive consumer
(perfect linearity of behaviour, no non-temperature sensitive
consumption and therefore no consumption at temperatures
above 15°C) then allows the calculation of the extreme tem-
perature taking account of interconnections. The addition of
such a consumer with a gradient of 100 MW/°C reveals a per-
fect resource need that corresponds to its consumption for a
temperature of -2.6°C in the interconnected French system.
The marginal approach is an eff ective way to separate the contri-
butions to the shortfall risk of non-temperature sensitive and
temperature sensitive users’ consumptions and to refl ect them,
without transfer, in the parameters of the capacity obligation.
4.4.2.2 Illustration of the extreme temperature with
regard to the weather contingency to which the system
is subject
To take into account temperature variations within a day, the
provisions adopted in the rules correspond to the choice of
a daily extreme temperature series in half-hourly steps. The
extreme temperature therefore takes the form of a vector with
20 values corresponding to the extreme temperatures of the
20 half-hourly steps of the PP1 range. The half-hourly transla-
tion of the extreme temperature adopted in the rules links the
extreme temperature, a result of supply-demand balance simu-
lations, with the climate data representative of all possible situa-
tions in the current climate.
A study was conducted on the basis of Météo France climate
data currently in force, consisting of 100 temperature series
representative of the current climate. Figure 38 corresponds to
temperatures constructed with the methodology described in
the rules.
Figure 37 – Illustration of the marginal approach to determining the contribution of a consumption profi le to the shortfall risk
Value of adequacycriterion = K
0 (3h)
Value of adequacycriterion = K
1
Addition of specificconsumption profile
Addition of X MW froma perfect resource
Value of adequacycriterion = K
2
By iteration, wedetermine X such that
K2 = K0 (back to 3h)
1
2
Figure 38 – Illustration of the extreme temperature with regard to the weather contingency
Smoo
thed
tem
pera
ture
(°C
)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-6
-5
-4
-3
-2
-1
0
08/02/12 1/20 1/10 1/5
98
Hourly extreme temperatures corresponding to a given level of
risk (1-in-20 chance, 1-in-10 chance and 1-in-5 chance) were
determined from these data. They correspond, for each hourly
step, to the quantile with the lowest temperatures of each series.
Thus the temperature with a 1-in-10 chance corresponds to
the 10th percentile of the minimum values of each series, and
the temperature with a 1-in-20 chance corresponds to the 5th
percentile of the minimum temperatures.
Figure 38 represents the extreme temperatures obtained with
the three abovementioned levels of risks and the coldest day of
the cold spell in February 2012.
Given the importance of temperature risk in the French power
system, its statistical distribution and its time constant of
approximately one week (see figure 39), the three hours of
expected shortfall in the French power system translate into a
shortfall that appears on average for 30 hours every ten years,
when an exceptional cold spell occurs. The mechanism there-
fore aims to act as if a severe cold spell occurred each year.
At supplier level, this comes down to making suppliers’ level of
obligation insensitive to the actual occurrence of the weather
contingency and transposing observed consumption to the
extreme temperature representative of the temperature sensi-
tivity risk.
4.4.3 Security factor
4.4.3.1 Taking interconnections into account in the
security factor
The law stipulates that the obligation takes into account the
interconnection of the French market with the other European
markets. The decree specifies that the security factor takes
account of the contribution of interconnections. Concretely,
“implicit” recognition of the contribution leads to a reduction of
suppliers’ obligation in proportion to the contribution of inter-
connections to security of supply.
The methodology applied to take the contribution of intercon-
nections to security of supply in France into account is drawn
from that used by RTE for adequacy studies (Adequacy Forecast
Reports): the role of interconnections is taken into account in
supply-demand balance studies through detailed modelling of
the whole of Western Europe.
The contribution of interconnections is thus accounted for
“implicitly”, through decisions about the size of the reference
Figure 39 – Cold spells in France – From 1947 to 2012(Source: Météo France)
The above studies show that the reference extreme temperature that is meaningful for determining the capacity obligation is represen-tative of one-in-ten-year cold conditions.
12 to 19 January1966
30 January to 7 February 1954
6 to 13 January2003
22 to 31 January1947
5 to 14 February1991
14 to 24 December1963
14 au 24 December2001
26 December 1996to 8 January 1997
8 to 23 January1987 1 to 27 February
1956
12 January to 6 February 1963
3 to 17 January1985
23 December 1970to 6 January 1971
1 to 13 February2012
7 to 13 February1986
23 to 28December 1962
19 to 24 February1948
7 to 11 January1967
16 to 21 January1957
10 to 17 January1960
4 to 8 March 1971
-12
-10
-8
-6
-4
-2
0
0 5 10 15 20 25 30 35
Min
imu
m v
alu
e of
tem
pera
ture
indi
cato
r (°C
)
Duration (number of days)The diameter of the spheres symbolises the overall intensity of cold spells, the biggest spheres corresponding to the most severe.
99
CAPACITY OBLIGATION / 4
Figure 40 – European modelling of supply-demand balance studies
Extensive modelling ofthe whole of Western Europe
Consumption
Availabilityof generation
Renewableenergies
Hydropower
Reference mix
Stochastic simulation(1,000 years simulated)
Stock managementInterconnections
Hourly optimisation
mix in France. Basically, if the contribution of interconnections
is nil, all of the power necessary to meet the supply security cri-
terion must be located in France; conversely, if interconnections
can contribute, less capacity is required in France.
The contribution of interconnections depends on two factors:
> The sizing of physical interconnection and its availability;
> The availability of margins in neighbouring countries, i.e.
capacity available beyond what is needed to meet demand in
neighbouring countries.
Indeed, if no margins are available in neighbouring countries,
physical interconnections may be available without any electri-
city being imported. The availability of foreign capacity depends
on factors external to France.
4.4.3.2 Determination of the security factor
The security factor is determined several years in advance and
ensures that the obligation level corresponds to the security of
supply criterion defined by public authorities.
It is set at the start of a capacity mechanism term on the basis of a
supply-demand balance study and is stable throughout the term.
To estimate the value of the security factor, an analysis was car-
ried out on the basis of the study of the year 2017 in the 2012
Adequacy Forecast Report. Figure 41 illustrates the principle for
determining the factor based on this study. This approach was
presented as part of the consultation in June 2013.
The reference generation mix, consisting of existing
capacities and projects under way, adding or remo-
ving “perfect” resources to allow the three-hour loss
of load expectation used as the adequacy criterion to
been met, was certified using the hypotheses for the
modelling of the mix and the outputs of the model:
> On the basis of availability during the 200 hours
of highest demand for thermal units and demand
response;
> On the basis of generation during shortfalls in the model out-
puts for hydropower units.
For 2017, the total volume of certificates enabling the criterion
obtained to be met is thus estimated at 93 GW. This represents
the overall level of certificates that covers the risk represented
via the reference extreme temperature. This volume of certifi-
cates already includes the contribution of interconnections
because foreign countries are explicitly modelled in the study143.
Based on the 100 demand series (1 series = 8,760 hourly ave-
rage power values) that serve as input for the model, and cor-
respond to the 100 climate series provided by Météo France,
an average reference power for France can be estimated. For
each series, the 100 hours of highest consumption are extra-
polated to the extreme temperature, and then the average of
these 100 extrapolated values is calculated. A reference power is
thus obtained for each series. The average of the 100 reference
powers calculated gives an estimate of the France reference
power. It is estimated at 99.7 GW in this study.
143If the study was conducted for France alone, the quantity of additional power required to meet the criterion would be much higher. This quantity represents the contribution of interconnections.
100
Interconnections
taken into account
Intermittence taken
into account
Overalllevel of
certificates
(enablescriterion
to be met)
93 GW
refP_France
(FRconsumptio
at ref T°)
99.7 GW
Overalllevel of
certificates
93 GW
Sum ofcapacity
obligations
93 GW
refP_France
99.7 GW
x secuF = 0.93
securityF
If the three-hour criterion is met, the total obligation must be
equal to the volume of certifi cates of the reference mix. The
security factor ensures consistency between the reference
power and the volume of certifi cates enabling the three-hour
criterion to be met, transferring to the obligation side the contri-
bution of interconnections taken into account in the certifi cation
of the reference mix. The security factor is thus deduced from
the over all level of certifi cates and the France reference power:
∑ Certifi cates = secuF x refP(extT)
=> secuF = 93/99,7 = 0,93
Figure 41 – The taking into account of interconnections and determination of the security factor
4.5 Determination of the obligation
As discussed above, a supplier’s obligation is given by the fol-
lowing formula:
Oblig,DY,OP = refP,DY,OP x SF,DY
> Oblig,DY,OP is the obligation of the obligated party OP for
delivery year DY
> refP,DY,OP is the reference power of the obligated party OP
for delivery year DY
> SF,DY is the security factor for delivery year DY
Si ∑tEPP1 ObservedConsump.OP,DY[t] = 0 alors refP, DY, OP est mise
à 0.
> GradientOP,DY[t] is the gradient of the obligated party OP in
half-hourly step t in delivery year DY;
> AdjustedConsumpOP,DY[t] is the observed consumption of the
obligated party OP, in half-hourly step t in delivery year DY,
adjusting for the demand response capacity activated;
> ExtT [t] is the extreme temperature, in half-hourly step t, for
delivery year DY;
> SFTt, DY[t] is the smoothed and thresholded France tempera-
ture in half-hourly step t in delivery year DY;
> nbHoursPP1,DY is the number of hours of the PP1 peak
period for delivery year DY.
The next section describes in detail how each of these terms,
which are used to determine the obligation, is evaluated, and
thus off ers a very specifi c reading guide for the rules.
4.5.1 Perimeter of an obligated party
4.5.1.1 Definition of the perimeter of an obligated
party
Determining the obligation of an obligated party requires iden-
tifying the consumption covered by this obligated party. For this
refP,DY,OP =1
2 x nbHoursPP1,DYx ∑ [AdjustedConsumpOP,DY[t] + GradientOP,DY[t]
x (ExtT [t] – SFTt,DY[t])]tEPP1
referencemix
101
CAPACITY OBLIGATION / 4
purpose, the concept of the perimeter of an obligated party has
been introduced in the rules.
The perimeter of an obligated party is the reference used to
calculate its reference power. In practice, this perimeter is divi-
ded into sub-perimeters per system operator, grouping the sites
connected to their systems. Procedures for exchanging infor-
mation about and tracking these sub-perimeters are defined in
agreements between distribution system operators and RTE.
The perimeter of an obligated party is not linked to a delivery
year. It has an initial form that evolves in accordance with
changes in the customer portfolio.
The perimeter of an obligated party (Perimeter OP(h, m, DY))
consists of all the sites for which the obligated party bears the
capacity obligation (in whole or in part) in hour h of month m in
delivery year DY.
Each system operator is responsible for monitoring the sub-
perimeter of the obligated parties for which it must calculate
the reference power.
4.5.1.2 Determination of the consumption site-
obligated party link
Consumption levels per obligated party are reconstituted by
allocating the observed consumption of a given consumer
between (a) the supplier(s) for the share they supply and (b) the
consumer itself for the share not sourced from a supplier.
For sites with only one contract, changes occur in the perimeter
with the effective dates of the single contract. The consumer that
holds only one contract and its supplier do not have to take any
special steps to be included in the perimeter of an obligated party.
For sites not bound by a single contract, a consumer is added
to the perimeter of an obligated party based on an attestation
filed jointly by the obligated party and the site. If no attestation
is filed to include a site within a supplier’s perimeter, it is consi-
dered that the site is not supplied by a supplier. In this case it
is directly subject to the capacity obligation and integrated into
the perimeter of the obligated consumer (or one is created, if
the consumer did not register as an obligated party).
The rules therefore adopt a declarative method for the monito-
ring of perimeters, to avoid complex and intrusive monitoring
of all the contractual links between a consumer and its sup-
plier or suppliers. This method enables intrinsic verification of
the attestation, the two parties to the system having opposing
interests: the supplier could seek to minimise its perimeter to
reduce its obligation; conversely, a consumer that does not have
an attestation would find itself bearing the financial burden of
the capacity obligation.
4.5.1.3 Role of public electricity distribution system
operators (DSOs)
DSOs communicate to RTE the reference power for each obliga-
ted party on their system, i.e.:
> The reference power of end consumers connected to their
system per obligated party (supplier and end consumer not
supplied for all or part of its consumption by a supplier) toge-
ther with the data and parameters used;
> The reference power, for their losses, per obligated party (sup-
plier or system operator for its losses not supplied for all or
part of its consumption by a supplier) together with the data
and parameters used.
The reference power per obligated party communicated by each
DSO is calculated in accordance with the provisions of the rules.
This information must be communicated within the deadlines
stipulated in the rules and the exchange agreement between
TSO and DSO for the calculation of the obligation.
4.5.2 Observed consumption
4.5.2.1 Data used
The basic data used to calculate the observed consumption of a
consumer are obtained from the metering and information sys-
tems of the operators of the public systems to which the sites
are connected directly or indirectly.
4.5.2.2 Observed consumption for profiled consumers
For profiled consumption, load curves are established in accor-
dance with the methods defined by the BRP/BM rules in force.
In this respect, the observed consumption data used in the capa-
city mechanism correspond to the Recotemp final consumption
data (aligned and standardised load curve adjusted for activa-
tion of NEBEF), i.e. to the load curve considered to have been
consumed on the basis of meter readings, adjusted for load
reductions.
This load curve, established according to the methods defined
in the BRP/BM rules and the experimental rules for rewarding
demand response on energy markets in force at the beginning
102
of the delivery year, is definitive, unlike the load curves estima-
ted to calculate imbalances, which are not based on actually
measured power levels.
4.5.2.3 Taking into account Site BRP NEBs
4.5.2.3.1 Affiliation with an obligated party
From a contractual standpoint, the NEB BRP-Site is similar to a
supply contract between the supplier affiliated with the BRP that
issued it and the consumer at the site to which it applies.
The NEB BRP-Site can also be seen as a self-supply vehicle for a
consumer, outside the “conventional” supply contract.
Given the ambiguous nature of the NEB BRP-Site, RTE has
included a flexible proposal in the rules:
> The NEB BRP-Site is affiliated, by default, with the supplier that
issued it;
> The NEB BRP-Site may be assigned to an obligated consumer
that so requests (the request form must be signed by the sup-
plier and consumer).
A request form is attached to the mechanism rules, and
the rules governing NEBs will evolve to ensure that sup-
pliers to all NEB BRP-Sites are identified when notice is
given to RTE.
4.5.2.3.2 Taking the NEB BRP-Site into account
in calculating the obligation
Once the NEB BRP-Site is affiliated with an obligated party, the
NEB is included in the obligated party’s adjusted consumption,
but not in the series used for the calculation of its gradient.
In other words, with this provision, NEB BRP-Sites are considered
to be non-temperature sensitive.
4.5.3 Sensitivity of consumption to temperature
4.5.3.1 Smoothed temperature
The process used to construct the smoothed temperature and
choose the threshold temperature adopted in the rules was the
same as that used to factor the weather contingency into the
profiling system.
This choice presents the advantage of using an existing process
that is known to market stakeholders and consistent with cur-
rent processes, particularly the profiling system.
The temperature considered corresponds to the national tem-
perature index calculated for France. It is calculated on the basis
of the Météo France “basket” of 32 weather stations.
The temperatures used correspond to variables derived from the
raw temperature measured at various weather stations. Indeed,
it is is necessary to take into account the inertia of consumption
with respect to temperature variations. This is accomplished by a
“smoothing” of temperatures aimed at delaying and attenuating
temperature variation ranges in order to constitute an effective
explanatory variable of consumption.
A list of the chosen weather stations, the associated weightings
and the smoothing parameters for calculation of the index are
indicated in part IV of Appendix F-M3 of chapter F of section 2
relating to the Balance Responsible Party system. Appendix 2 of
the rules describes the method of smoothing and constructing
the smoothed France temperature.
This smoothed temperature is not used by RTE in its work (Ade-
quacy Forecast Report – climatic corrections). However, the dif-
ferences associated with the temperature variable options used
are minimal.
4.5.3.2 Threshold temperature
The threshold temperature is that indicated in part III of Appen-
dix F-M3 of chapter F of section 2 relating to the Balance Res-
ponsible Party system, namely 15°C at present. The same logic
is applied as in the above section.
4.5.3.3 Gradient
4.5.3.3.1 Estimation of the France gradient and
gradient per major category of consumption
4.5.3.3.1.1 Method of estimating the gradient
This section presents the method of estimating the gradient adop-
ted on a national level and for each major category of consumption
(all profiled consumers and all remotely metered consumers).
4.5.3.3.1.1.1 General description of the method
An estimation of the gradient by a linear regression of the power
over the temperature cannot be satisfactory because of the sea-
sonal nature of consumption; this needs to be dispensed with
before evaluating the temperature sensitive share.
The methodology adopted in the rules leads to the determina-
tion of half-hourly gradients valid for a delivery year:
103
CAPACITY OBLIGATION / 4
> The gradient is calculated by the “difference regression”
method, i.e. a linear affine regression on the power deviation
with respect to the temperature deviation from one week to
the next. This method avoids the difficulty associated with
estimating the seasonal change in consumption that is not
representative of the temperature sensitivity of consumption;
> The data used pertain to consumption during the delivery
year with the exception of bank holidays and the period cor-
responding to the winter holidays together with the period
either side of them (basically from 01/01 to 12/01 and from
14/12 to 31/12 of the delivery year)144;
> The temperatures are aligned with a threshold temperature
beyond which consumption becomes temperature sensitive.
For this reason, power differences corresponding to nil tempe-
rature differences are omitted145. The gradient is therefore cal-
culated de facto on the cold part of the delivery year.
The singleness and additivity of the method are major assets
for the mechanism. Applied on a set of consistent data
with scaling to consumption in France, it ensures additivity
between the various estimated temperature sensitivities and
the equality of the sum obtained with the temperature sen-
sitivity for France.
Moreover, because consumption data from the delivery year is
used, the values obtained correspond exactly to real tempera-
ture sensitivity.
4.5.3.3.1.1.2 Calculation of the power difference
The power variation is calculated for the same half hour on two
days, one week apart. The weekly variation in seasonality due to
lighting in particular is negligible.
4.5.3.3.1.1.3 Calculation of the temperature difference
As for the power variation, the temperature variation is calculated
for the same half hour on the same two days one week apart.
In accordance with the description of the behaviour of demand
and the temperature sensitivity effect, each temperature is
compared with the threshold temperature in order to use only
the portion that genuinely explains the power difference in the
calculation of the difference. For example, the variation in power
between a half hour at 22°C and a half hour one week later at
17°C is not explained by this difference of 5°C (heating is not
switched on at such temperatures); each temperature is thus
aligned with the threshold temperature, in this case 15°C (min.
function(threshold temperature; actual temperature)), resulting
in a temperature difference of 0°C.
4.5.3.3.1.2 Performance of the method at
nationwide level in France
The method proposed in the draft rules and adop-
ted in the rules for determining load curves in
France, for profiled and remotely metered PDS
consumers, is simple and transparent; it is not based
on obscure black box modelling, and all data used
are public. In this sense, the method chosen for the
capacity mechanism puts all stakeholders on an
equal footing.
During the consultation, however, some stakeholders questio-
ned the performance of this method, notably with regard to two
aspects:
> The simplicity of the method was said to be liable to lead to
results not representative of physical reality;
> Consequently, the evolution of the gradients from one year to
the next was said to be unstable.
RTE carried out a series of studies on the basis of actual
consumption from 2006 to 2012. Based on these analyses,
questions about the method of determining the France gradient
were not taken into account.
4.5.3.3.1.2.1 Representativeness of the results obtained for France
The provisions adopted in the rules concerning the selection of
the pairs of values [consumption; temperature] used to calcu-
late the gradient lead, for each half-hourly step, to scatter plots
consisting of at least 180 points. From a statistical point of view,
the representativeness of the gradients obtained is real.
A study was conducted to estimate the sensitivity of the method
to the observed data used. For this purpose, 1,000 simulations
were carried out during which points used to determine the gra-
dients for a same year and same half-hourly step were randomly
removed. Two different quantities of removals were considered:
20 points and 100 points, or approximately 10% and 50% of the
total number of points used for the calculation.
The results of this study show that:
> The average of the gradients obtained is very stable: the devia-
tion of the average gradient from the initial gradient calcula-
ted with all the points is 0.05% with 20 points removed and
0.2% with 100 points removed;
> The variability of the gradients obtained is low: the standard
deviation is 20 MW, or 1% of the gradient, with 20 points remo-
ved, and 65 MW, or 3% of the gradient, with 100 points removed.
144A long period must be chosen – not just PP1 hours – to ensure that the gradient obtained is sufficiently statistically valid.
145A temperature delta calculated as follows is used:
104
7
9
11
13
15
17
00:0
0:00
01:0
0:00
02:0
0:00
03:0
0:00
04:0
0:00
05:0
0:00
06:0
0:00
07:0
0:00
08:0
0:00
09:0
0:00
10:0
0:00
11:0
0:00
12:0
0:00
13:0
0:00
14:0
0:00
15:0
0:00
16:0
0:00
17:0
0:00
18:0
0:00
19:0
0:00
20:0
0:00
21:0
0:00
22:0
0:00
23:0
0:00
28 March 2012
04 April 2012
21 March 2012
Threshold temp.
CASE 3CASE 2CASE 1
Smoo
thed
tem
pera
ture
[°C
]
min(dT
;
tT) =
dT
min(d-7
T ;
tT) =
tT
Δ3
(<0) = dT
–
tT
min(dT
;
tT) =
dT
min(d-7
T ;
tT) =
d-7T
Δ1 =
dT
–
d-7T
ΔΔ
Δ
Figure 43 – Illustration of the calculation of temperature diff erences (Source: ERDF, WG of 09/07/13)
Variations compared to previous week
Fran
ce s
ynch
ron
ous
seri
es [
GW
]
Pow
er differen
ce [GW
]
0
10
20
30
40
50
60
50
60
70
80
90
100
110
November December January February March
- + + + - + - + - + + - - + - + -+ +
∆ power > 0∆ power < 0
France synchronous seriesWinter of 2011-2012 - Wednesday at 7pm-{02/11 ; 9/11; … 08/02 ; 15/02; …}
--
Figure 42 – Illustration of the calculation of power diff erences(Source: ERDF, WG of 09/07/13)
105
CAPACITY OBLIGATION / 4
The chosen method therefore has a very low degree of sen-
sitivity to the observed data used and accurately refl ects the
France temperature sensitivity for the year considered.
Lastly, some stakeholders questioned the use of a single year
of history to determine the gradient as opposed to a multi-year
history said to guarantee greater stability.
The chosen option of determining the France gradient on the
basis of one year is consistent with the more complex modelling
used by RTE. While RTE uses a fi ve-year history to align its forecas-
ting models, this history is used to determine the threshold tem-
peratures and the smoothing coeffi cients (optimisation under
constraints); gradients are determined for each year independently
(the model requires such freedom). This approach is very similar to
that adopted for the capacity mechanism: the threshold tempera-
ture and smoothed temperature are determined beforehand; the
gradients are calculated on the basis of actual data for the year.
The option of calculating the gradient on the basis of a single
delivery year does not constitute a factor of instability for the
mechanism. On the contrary, it is in line with existing processes
and enables consistency in the terms used in the handling of
temperature sensitivity in general (threshold temperature,
smoothing and gradient, which must be taken as a whole).
Furthermore, this choice reinforces the dynamic aspect of the
mechanism with a gradient that refl ects the temperature sensi-
tivity of the year in question and makes it possible to take into
account actions implemented by stakeholders without being
bogged down by the inertia of past gradients.
4.5.3.3.1.2.2 Variability of the results obtained for France
In response to the feedback received on the method of deter-
mining the gradients, studies were conducted on historical data,
focusing this time on the evolution of the gradient from one
year to the next.
The illustration opposite shows the evolution of the average
gradient on the half-hourly time slots chosen for PP1 from the
winter of 2006-07 to the winter of 2011-12.
Several points can be drawn from this analysis:
> First, the average growth in France temperature sensitivity
obtained with the method in the rules is in line with that found
in documents published by RTE (Adequacy Forecast Report
and Electrical Energy Statistics);
> Second, a “rebound” can be observed between the gradients
for 2009, 2010 and 2011. Additional analyses were carried
out to identify the causes of this change, particularly whe-
ther it was a reflection of a physical change in consumption
or the method itself. These analyses identified as the expla-
natory factor the distribution of EJP (peak day demand res-
ponse) days over the winter, which introduces an unknown
factor in the evolution of the gradient if load reduction
volumes are not taken into account in calculating the gra-
dient. If EJP was certified, consumption would be adjusted to
reflect the EJP activated. In any event, the deformation of the
scatter plot due to EJP only affects the incumbent operator;
the evolution of the gradient excluding EJP, which affects all
suppliers, is stable.
The evolution in the France gradient obtained with the method
in the rules accurately refl ects physical demand trends.
4.5.3.3.2 Provisions adopted on the temperature
sensitivity of consumers
4.5.3.3.2.1 Guiding principles for choosing the method
of estimating temperature sensitivity
In parallel with the debate between precision and stability, many
stakeholders stressed the need to meet the following three
requirements:
(i) The calculation of the obligation must accurately refl ect the
contribution to the shortfall risk, no more and no less;
(ii) Non-temperature sensitive consumers must in no case be
penalised by possible uncertainties associated with the calcu-
lation of gradients;
(iii) Remotely metered consumers must not be penalised by
uncertainties associated with the profi ling system.
Fran
ce g
radi
ent (
MW
/°C
)
1,400
1,500
1,600
1,700
1,800
1,900
2,000
2,100
2,200
2007 2011201020092008
Figure 44 – Evolution of the average gradient on the PP time slots obtained with the method in the rules
106
These requirements aim to prevent full pooling, which would
completely dilute the objective of making market stakehol-
ders responsible for their temperature sensitivity. The rules
consequently incorporated a segmentation of the methods
adopted for each major category of consumption, taking
into account not only the process of determining consump-
tion (profiled or remotely metered) but also the physical para-
meters of this consumption (for example by distinguishing
between TSO losses, which are temperature sensitive, and
consumers connected to this network that are not tempera-
ture sensitive).
4.5.3.3.2.2 Method adopted for overall sizing of
temperature sensitivity per major category of
consumption
The studies based on past data presented above show that the
method of estimating the overall gradient by statistical regres-
sion on the basis of actually measured data enables the gra-
dients for France or per major category of consumption to be
estimated with satisfactory accuracy and stability.
RTE proposes to adopt this generic method to determine the
gradients corresponding to each major category of consump-
tion as a whole. The additivity of the method ensures that the
sum of the gradients of the various categories of consumption
corresponds exactly to the France gradient. Consequently, a
combination of this method with segmentation per major cate-
gory of consumption makes it possible (i) to target the real level
of temperature sensitivity in France and therefore to support
the mechanism’s security of supply objective, and (ii) to prevent
transfers of temperature sensitivity between major categories of
consumption, which would be contrary to the principles outli-
ned in the preceding section.
Also based on this proposal, it is considered in the rules that
the gradient is nil for certain categories of consumers owing
to a very low or statistically disputable temperature sensiti-
vity. This concerns all consumers connected to the public
transmission system and consumers connected to the public
distribution systems identified as non-temperature sensitive
by the distribution system operators.
Following strong requests from suppliers of profi-
led customers, smoothing was introduced in the
calculation of the overall gradient of profiled cus-
tomers: the rules adopt a linear extrapolation based
on the gradients obtained for the years DY-1, DY-2
and DY-3 via the generic method of estimating the
gradient. The total profiled customer gradient applied for year
DY therefore corresponds to the value of this linear extrapola-
tion. This provision presents the advantage of stabilising the
evolution of the profiled gradient from one year to the next146.
However, it causes a delay in taking into account changes in the
level and form of the temperature sensitivity trend among pro-
filed consumers, which could change radically with the deploy-
ment of smart meters and the switching of profiled consumers
to remote metering. This provision is not adopted for remotely
metered consumers.
4.5.3.3.2.3 Choice of method at the consumer level:
Redistributive issues
At an individual level, the gradient assigned to suppliers must in
theory reflect the real gradient of consumption in their custo-
mer portfolio in order to meet the objective of assigning obliga-
tions in proportion to suppliers’ contributions to the shortfall risk
and to enable them to benefit from any initiatives to manage
their temperature sensitivity.
With this in mind, it could seem preferable to adopt an indivi-
dualised approach across the perimeter of a supplier based on
the characteristics of its customers’ consumption. Indeed, a
normative approach would automatically lead to the pooling of
any temperature sensitivity management initiatives over all the
consumers in the class.
However, this approach presents some limitations:
> The flow reconciliation systems used on profiled sites are still
currently governed by a normative approach that cannot
be avoided with existing metering systems (ending profiling
would require the use of load curve data from sophisticated
meters);
> An individualised approach could raise fresh questions about
the assumed linearity of the power-temperature relationship.
The numerical result obtained with the raw method may not
have any statistical or physical reality, particularly for “small”
perimeters or for customers with “special” consumption
behaviours.
On the other hand, a normative approach intrinsically leads to
complexity, at several levels.
First, it involves defining a distribution key to assign to each
consumer a share of the temperature sensitivity of its class.
Defining this distribution key is a delicate matter (share of subs-
cribed power in relation to the sum of the subscribed power in
the class, the ratio for annual average power or during PP1, etc.).
146The basis on which the gradients chosen for the years DY and DY-1 are determined is 66% shared (the estimated gradients for years DY-1 and DY-2).
107
CAPACITY OBLIGATION / 4
In addition, when the distribution key is defined has an effect on
the precision and predictability of the gradients obtained:
> If the distribution key is determined before the delivery period,
the sum of gradients obtained will inevitably diverge from
the actual overall gradient. This approach must be ruled out
because it jeopardises the mechanism’s security of supply
objective;
> If the distribution key is determined at the end of the deli-
very period, the sum of the gradients can be normalised to
bring it into line with the real gradient. In this case, however,
a supplier’s gradient does not depend solely on consumption
within its perimeter but is also affected by the consumption
of other suppliers. A supplier that can accurately predict the
consumption of its customers will not be able to accurately
predict its obligation.
The method chosen to determine the sensitivity of consump-
tion to temperature on an individual level has effects only in
terms of redistribution of the gradient between stakeholders
(between individualisation and pooling) and not in terms
of sizing of the overall gradient. Thus, the choice between a
method based on individualised actual consumption and a
normative approach with a mutualising scaling factor147 comes
down to choosing how the overall gradient will be redistributed
between stakeholders (consumers and suppliers). This choice
considerably impacts the incentives for stakeholders to manage
their temperature sensitivity.
However, several market stakeholders (particularly suppliers of
profiled sites) expressed a desire to have more visibility on the
values of the gradients that will apply to their customers for a
given delivery year.
To meet the demands of various stakeholders, a compromise
must be found between the stability of the gradient (which
leads to pooling) and the principle of individualisation (which
provides incentives, exposing suppliers to the accuracy of
their forecasts).
When the mechanism is first introduced, RTE proposes to adopt
the following approaches:
> For profiled consumers, an approach based on the gradients
of the profiles used in the BRP/BM rules. This option was
requested by the suppliers of profiled sites, in order to have
better visibility;
> For remotely metered consumers, an individualised approach
per supplier perimeter. This option enables suppliers to esti-
mate the temperature sensitivity of their customer portfolio
solely on the basis of their forecast (no external
parameters) and thus to benefit from the actions
they take to manage the temperature sensitivity
of their customers.
4.5.3.3.3 Method adopted according to
the type of consumption
4.5.3.3.3.1 Scope of application and volume
of associated gradients
It is possible to identify four categories of consumption that dif-
fer in how their load curves are constructed and their underlying
physical nature:
> PTS remotely metered consumption;
> PDS remotely metered consumption;
> Profiled consumption;
> Losses (PDS and PTS).
In the consultation organised by RTE, information was communi-
cated concerning the orders of magnitude of the various tempe-
rature sensitivities per type of consumption, giving an indication
of the stakes for these categories in terms of gradient volumes.
This information makes it possible to identify the main catego-
ries showing temperature sensitivity in order to adopt a rational
and proportionate approach. 85% of the temperature sensitivity
of consumption on the ERDF grid is accounted for by profiled
consumers, 11% by losses from the ERDF grid and only 4% by
remotely metered consumers.
It also makes it possible to identify the scope of the redistribu-
tive effects that can result from the choice of an individualised
approach based on actual consumption as opposed to a pooling
normative approach for PDS remotely metered consumption; it
is therefore a matter of deciding how to distribute this tempera-
ture sensitivity, which for the winter of 2011/12 is estimated at
74 MW/°C for customers connected to the ERDF grid.
Applying the principle of non-transfer of temperature sen-
sitivity (from temperature sensitive consumers to non-tem-
perature sensitive consumers and from profiled consumers
to remotely metered consumers), the redistribution of the
gradients is partitioned per category of consumption. This
involves applying the principle of consistency of the sum of
the individual gradients with the France gradient but for each
category taken separately: concretely, the sum of the gradients
of profiled consumers must correspond to the temperature
sensitivity of profiled consumers as a whole, no more and no
147The scaling factor is applied to a larger base, for example all profiled consumers or all remotely metered consumers. Efforts by these consumers to reduce their temperature sensitivity are therefore pooled.
108
less. This segmentation makes it possible to envisage diff erent
approaches for each category of consumption.
4.5.3.3.3.2 PTS remotely metered consumption
To complement the numerical data indicated above, various
illustrations are presented below concerning the link between
power and temperatures for customers connected to the PTS.
Figures 46 and 47 do not show any link between powers and
temperatures and illustrate the hypothesis of non-temperature
sensitivity of customers connected to the PTS.
In addition, application of a linear regression of the power at 7pm
over the temperature gives a slope equal to -0.18 MW/°C. This
gradient has no statistical or physical validity. Application of the
ER
DF
tota
l
Profiledconsumers
Load curve
= 1,567 MW/°C
= 74 MW/°C
= 201 MW/°CLosses
- 10.0 - 5.0 0.0 5.0 10.0
ERDFtemperature sensitivity
= 1,
842
MW
/°C
Other networks = 169 MW/°C
Figure 45 – Orders of magnitude of temperature sensitivity per category of consumption(Source: ERDF, WG of 09/07/13)
Dai
ly e
ner
gy (M
Wh
)
Average daily temperature (°C)
-5 0 5 10 15 20 25 300
50,000
100,000
150,000
200,000
250,000
Figure 46 – Daily energy consumed by direct PTS customers according to average daily temperature, in 2012
109
CAPACITY OBLIGATION / 4
°CMW
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
-6
-4
-2
0
2
4
6
8
10
12/01/2012
12/02/2012
12/03/2012
12/04/2012
12/05/2012
12/06/2012
12/07/2012
12/08/2012
12/09/2012
12/10/2012
12/11/2012
12/12/2012
12/13/2012
Figure 47 –Trend in temperature at hourly time step from 1 to 13 December 2012
Power consumed (MW)
Temperature (°C)
400
-10 -5 0 5 10
Tem
p. d
iffer
ence
(°C
)
Tem
p. d
iffer
ence
(°C
)
Po
wer
diff
eren
ce (M
W)
Po
wer
diff
eren
ce (M
W)
Mostly agricultural or industrialtype activities (manufacturing,
automobile industry, etc.)
Mostly tertiary type activities(hotels and restaurants,
public administrations, etc.)
Non-temperature sensitive load curvesTemperature sensitive load curves
-10 -5 5 10
Figure 48 – Illustration of the temperature sensitivity of remotely metered consumers(Source: ERDF, WG of 09/07)
110
method in such a case (i.e. redistribution of the -0.18 MW/°C) is
of no benefi t in terms of accurately allocating the temperature
sensitivity of consumers.
The provision adopted in the rules therefore corresponds to
the choice of a nil gradient for PTS customers. Their reference
power will be equal to the average power consumed during PP1
hours at the actual temperature, adjusting for certifi ed demand
response activated.
4.5.3.3.3.3 PDS remotely metered consumption
The system to which consumers are connected is not an entirely
appropriate boundary in terms of temperature sensitivity: some
consumers connected to a distribution system are temperature
sensitive while others are not and in fact have a similar profi le to
certain sites connected to the PTS.
The main diffi culty here relates to the determination
of an appropriate classifi cation to distinguish tem-
perature sensitive from non-temperature sensitive
consumers.
An initial classification based on the “APE” code (main activity
code) in the NAF listing was proposed during the consulta-
tion. This classification was not adopted for different types of
reasons:
> Legal reasons: based on common practices, it could be consi-
dered discriminatory148;
> Technical reasons: this classifi cation appears disputable
because temperature sensitive and non-temperature sensi-
tive consumption may be covered by the same activity code.
Taking this analysis into account, ERDF proposed a new classifi ca-
tion based on a technical criterion: average annual power. Concre-
tely, PDS remotely metered consumers with average annual
power of 175 kW or less are considered temperature sensitive.
Figure 49 represents the average gradient in %/C over three past
years for sets of consumers grouped together by average power.
For each year we can see a relationship between the average
power of the group and the relative gradient of the class. The
groups of sites with lower power levels are more temperature
sensitive (gradient signifi cantly greater than 0) while the largest
sites are not temperature sensitive (gradient not signifi cantly
diff erent from 0).
The next step is to determine, for the capacity mechanism, a
threshold group beyond which consumers are no longer consi-
dered to be temperature sensitive; this comes down to determi-
ning a criterion corresponding to an average power, in this case
the average power of this threshold group.
When the mechanism starts functioning, it is proposed that the
average threshold power be set at 175 kW; this parameter will be
revisable, like the other parameters of the capacity mechanism.
Incorporating this criterion, RTE proposes to adopt the following
approach:
> For non-temperature sensitive remotely metered customers
connected to the PDS, the treatment is the same as for PTS
remotely metered consumers: the gradient is set at 0;
> For temperature sensitive remotely metered customers
connected to the PDS, the generic method is applied, per sup-
plier perimeter, on the load curve corresponding to the sum
of the load curves of remotely metered customers connected
to the PDS that are considered to be temperature sensitive.
This provision provides an answer to the intrinsic limitations of
the generic method (physical non-representativeness of the
148Council of State decision of 22 October 2012 on the tariff order of 13 August 2009.
# of group of averageP(503 load curves per group)
Rel
ativ
e gr
adie
nt i
n %
/°C
-1
0
0 10 20 30 40 50 60
1
2
3
4
Threshold groupcorresponding to an
averageP of 175 kW
Consumersconsidered
non-temperaturesensitive
(gradient not significantlydifferent from zero)
Consumersconsidered highly
temperaturesensitive
Figure 49 – Illustration of customers’ temperature sensitivity based on average power (Source: ERDF, contribution submitted to
the Concerte site on 22/01/2014)
RT7 RT8 RT9
111
CAPACITY OBLIGATION / 4
gradients obtained for small portfolios or atypical consumers)
by considering only temperature sensitive consumers.
Illustrations 50 and 51 represent the gradients obtained for
1,000 random samples with increasingly large populations (ran-
ging from 1 to 1,000 individuals) selected (1) among all remotely
metered customers and (2) only among customers considered
temperature sensitive.
We observe in case (1) that the average gradient obtained varies
greatly according to the selection sample. Thus, for a sample of
51 individuals, the gradient obtained is negative in more than 25%
of cases. Conversely, in case (2), for the same sample size, the gra-
dient is positive in more than 99% of cases and is even between
1.1 and 1.8% in 50% of cases. Setting the gradients of consumers
considered to be non-temperature sensitive to zero therefore
helps to stabilise the gradient obtained for small portfolios.
This provision adopted for customers considered to be non-tempe-
rature sensitive is in line with the system proposed in the consulta-
tion. It is a simplification measure, in view of the persisting difference
between the regulation framework applicable to top segments of
the customer portfolio (remote metering and contracts) and bot-
tom segments (profiling and regulated tariffs). By tending towards
standardisation of the gradient set at 0 for non-temperature sensi-
tive (industrial in practice) consumers, this provision ensures com-
pliance with the principle that a consumer that does not consume
on PP1 days has a zero obligation, in all cases.
Figure 50 – Random sampling among all remotely metered customers (Source: ERDF, contribution submitted to Concerte site on 22/01/2014)
Figure 51 – Random sampling among temperature sensitive customers (Source: ERDF, contribution submitted to Concerte site on 22/01/2014)
1
-4
-2
0
2
4
31 71
51
111 161 211 261 311 361 411 461 511 561 611 661 711 761 811 861 911 961
Number of aggregated load curves
Ave
rage
gra
dien
t per
load
cu
rve
in k
W/°
C
1
-4
-2
0
2
4
31 71
51
111 161 211 261 311 361 411 461 511 561 611 661 711 761 811 861 911 961
Number of aggregated load curves
Ave
rage
gra
dien
t per
load
cu
rve
in k
W/°
C
112
4.5.3.3.3.4 Profiled consumption
Two approaches were presented during the consultation to esti-
mate the temperature sensitivity of profiled consumers:
> The first approach corresponds to the application of the
method described in section 4.5.3.3.1 on the basis of defini-
tive profiled consumption. The method is therefore based on
(but does not duplicate) the existing profiling process, with
which stakeholders are familiar, and which enables a load
curve per consumer to be obtained. As it is perfectly addi-
tive, the calculation can be made on the profiled perimeter
of each obligated party, the hypothesis of linearity being
intrinsically validated for profiled consumption, by standar-
dised construction;
> The second approach corresponds to the creation of new
consumption profiles based on those described in the BRP/BM
rules with adjustment of the coefficients of the sub-profiles at
normal temperature which are extrapolated to extreme tempe-
rature. Temperature sensitivity is thus evaluated per sub-profile,
starting from the gradient calculated for all profiled customers,
based on series preceding the delivery year. This method requires
new alignment coefficients calculated for each half hour (Cprofi-
led). These alignment coefficients are determined at each time
step, using aligned profiled consumption as the reference, on the
delivery year, for all profiled sites extrapolated to the extreme tem-
perature determined by applying the method described in sec-
tion 4.5.3.3.1. This alignment covers both the energy alignment
necessary to ensure the consistency of profiled consumptions
with the total profiled consumption and an alignment correspon-
ding to an updating of the gradients previously determined, to
reflect changes in temperature sensitivity.
RTE and ERDF carried out joint and comparative analyses in
2013 of the results produced by these two methods. These ana-
lyses showed that the methods lead to similar results at the sup-
plier level and identical results for profiled customers.
Several stakeholders expressed their preference for the use
of gradients for sub-profiles defined in advance even if this
meant using new alignment coefficients, so that the sum of
the gradients would be in line with the gradient for profiled
consumers as a whole. The rules adopt a methodology of this
type, it being understood that the obligation calculated on all
profiled customers with this method is identical.
The rules therefore adopt a method that involves
estimating the gradient of a profiled consumer in
two stages:
Figure 52 (Source: EDF, WG of 07/06)
From 2009 to 2012, on the ten days of highest demand per winter (8am - 8pm time slot):> The alignment coefficient varies between 1.03 and 1.08
depending on the year> The coefficient is very volatile within the ten days of high-
est demand2009 2010 2011 2012
Average alignment coefficient 1.08 1.04 1.03 1.04
Daily volatility of coefficient
1.04 to 1.10
0.97 to 1.11
1.02 to 1.05
1.00 to 1.06
A 1% variation in the alignment coefficient at peak ≈ a devia-tion of 0.6 GW.
149The alignment coefficient as defined in Section 2, chapter C of the BRE-BM rules.
GradientsPS[h] = GProfil,S[h] x LCestim,S(M+14)[h] x PGADY[h]
> GradientsPS[h]: gradient of profiled site expressed in MW/°C;
> GProfil,S[h]: gradient corresponding to the sub-profile of the site
in the half-hourly step h of PP1 days expressed in %/°C. A list
of the applicable profiles is given in appendix F-M1 of the BRP/
BM rules in force at the beginning of the delivery year;
> LCestim,S(M+14): load curve of the site in the half-hourly step
h of PP1 days;
> PGADY[h]: profiled gradient alignment coefficient.
This alignment coefficient is determined after the delivery period
to ensure matching between the sum of the gradients of profi-
led sites and the total gradient for profiled consumers calculated
by applying the method described in section 4.5.3.3.1 on final
profiled consumption as a whole, adjusting for certified demand
response activated, and smoothed via a linear extrapolation over
the three years DY-1, DY-2 and DY-3 (see § 4.5.3.3.2.2).
4.5.3.3.3.5 Alignment coefficient and obligation
Concerns were raised during the consultation about the volati-
lity of the obligation level, especially for profiled consumption,
because of the alignment coefficient149.
The argument made directly projected the volatility of the align-
ment coefficient onto the volatility of the obligation. According to
this reasoning, if major discrepancies and volatility exist between
profiled and real consumption over peak periods, these discrepan-
cies and volatility should be reflected in the level of the obligation. It
was suggested that the figure could be as high as several GW.
113
CAPACITY OBLIGATION / 4
This link between the variability of the alignment coefficient and
the variability of the obligation does not seem to be borne out.
The alignment coefficient does not lead to any variability in France
consumption. On the contrary, for each half-hourly step, it ensures
consistency between the sum of the profiled consumption obtai-
ned from the modelling and actual profiled consumption.
RTE therefore conducted a study to test the hypothesis that a
correlation exists between the value of the alignment coefficient
and the value of reference power. For this purpose, the align-
ment coefficients for M+12 were retrieved for the delivery year.
In parallel with this, the reference power of profiled consump-
tion was calculated by applying the provisions adopted in the
rules and using the distributions of PP1 days corresponding to
the France consumption scenarios resulting from the Météo
France climate scenarios representative of the current climate.
Figure 53 shows that, for a same profiled reference power
value (56 GW), the average alignment coefficient on PP1 varies
between 1.00 and 1.03 (each column represents the alignment
coefficient associated with a distribution of PP1 hours).
The variability of the alignment coefficient is not therefore a
significant indicator of the variability of the capacity obligation.
4.5.3.3.3.6 Losses
The methods for determining the temperature sensitivity of
losses must be compatible with the provisions adopted for
the determination of the observed consumption
of losses. These provisions are being defined by
CRE and are unknown on the date of submission
of the rules.
However, as losses are proportional to withdrawal
and withdrawal is generally temperature sensitive,
the volume of losses is temperature sensitive. This
temperature sensitivity of losses also accounts for a significant
proportion of the France temperature sensitivity150 and cannot
therefore be overlooked. A method must thus be defined for esti-
mating this sensitivity. The generic method described in § 4.5.3.3
is suitable for estimating the temperature sensitivity of the losses
of each system operator.
In the same way as for the other categories of consumption,
questions arise concerning the redistribution of this tem-
perature sensitivity between the various stakeholders. This
is because covering the losses of each system operator can
involve several tens of suppliers and the system operator itself
for all or part of its losses.
This question is dealt with generically in the next section. Indeed,
the distribution of the gradient of losses between the various
suppliers and system operator is very similar to the situation of
a site where power comes from several suppliers and potentially
also from the consumer directly.
Figure 53 – Variability of the alignment coefficient for a same reference power
Alig
nm
ent c
oeffi
cien
t
Distribution of PP1 hours (56GW)
0,98
0,99
1,00
1,01
1,02
1,03
1,04
S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13 S14 S15 S16 S17 S18 S19 S20 S21 S22
150The orders of magnitude presented in section 4.5.3.3 indicate a temperature sensitivity for ERDF losses of around 200 MW/°C, or about 10% of the overall temperature sensitivity for France.
114
4.5.3.3.3.7 Distribution of the temperature sensitivity
of consumption between various suppliers
Defining the rules that will determine how the capacity
mechanism functions requires putting generic market design
concepts into practice, including in extremely complex situa-
tions. This is the case with consumption sites that get power
from several suppliers. The framework outlined in this section
can also be transposed to the compensation of system losses
or to the obligation of consumers that buy directly on markets.
How the temperature sensitivity of consumption is distributed
between various suppliers needs to be considered in the light of
the type of commitment made by a supplier vis-à-vis a consu-
mer. In general terms, a distinction can be made between two
types of supply:
> A supplier can commit to supply a block of energy. In this
case, it is committed to supplying a defined volume of energy
regardless of external conditions, particularly the actual
temperature;
> A supplier can commit to cover the actual consumption of the
site. In the context of the capacity mechanism, this supplier
has therefore made a commitment to cover the consumption
of the site at extreme temperature. This commitment may
also entail coverage of the differences between injection and
withdrawal at the site.
On this basis, we can consider that the supply of a block of
energy does not take away a share of the temperature sensi-
tivity of the site, unlike a commitment by a supplier to cover
actual consumption. Concretely, the rules therefore consider
site NEBs to be non-temperature sensitive.
There then arises the question of the existence for any site of
a supplier committed to covering actual consumption (residual
of energy blocks supplied by other means) and the singleness
of this supplier. The concept of a supplier undertaking to cover
a site’s actual consumption is incorporated in the rules via the
affiliation of sites with the perimeter of one or more obligated
parties151. The absence of such a supplier does not constitute
an obstacle in the final analysis: it corresponds de facto to the
consumer choosing to cover its own consumption, including
at extreme temperature. In this case the rules provide for the
recognition of obligated consumers’ affiliation either
based on the declaration of the consumer or on the
absence of affiliation with the perimeter of a sup-
plier. In this case, the consumer is responsible for the
temperature sensitivity of its consumption.
The last step involves defining the singleness of such a supplier
at each time step. The existence of several such suppliers does
not appear compatible with the fulfilment of this responsibility.
At the least, it would require explicit coordination, failing which
the actions of one supplier would thwart those of others. Howe-
ver, the legal analyses conducted by RTE and the feedback
gathered from participants in the consultation did not allow this
singleness to be decided upon. By default, the rules include a
specific procedure for cases where there are several such sup-
pliers for a given time step: it involves going through the BRP
(Balance Responsible Party) to distribute the consumption and
temperature sensitivity of a site between several suppliers.
4.5.4 Taking into account certified demand response measures activated
In keeping with the choices made in France about market archi-
tecture since the Poignant-Sido workgroup of 2010, the capa-
city mechanism calls for demand response to be able to parti-
cipate directly in the capacity market as supply, i.e. to directly
secure capacity certificates through the certification process.
Putting this principle into practices requires specific procedures
to ensure that demand response capacity is not rewarded twice,
once through a reduction of the obligation and once through
the certificates issued. On this point, the decree stipulates that
“the observed consumption of a customer that has contributed
to the constitution of a demand response certification entity is
adjusted to reflect load reductions, in accordance with the capa-
city mechanism rules”.
As a result, for each PP1 peak hour, the observed consump-
tion of a consumer that has committed to a demand response
capacity that is certified and activated must be revised upward
by the amount of certified demand response capacity activa-
ted to calculate the obligation. This requires assigning an acti-
vated demand response amount to each consumer, based on
individual measurements (ideally) or by applying distribution
keys over a volume of attested load reduction attributed to the
demand response capacity certified as a whole. The capacity
mechanism rules proposed by RTE describe the methodology
for calculating a supplier’s obligation taking into account the
certified demand response activated. They do not, however,
address financial flows between stakeholders (supplier, consu-
mer and any demand-side operator involved).
4.5.4.1 Non-temperature sensitive consumers
The principle discussed above does not imply that a sup-
plier must know which certified demand response capacity is
151The rules therefore distinguish between the concepts of a “portfolio obligated party” and an “obligated party for declared supply”.
115
CAPACITY OBLIGATION / 4
activated within its perimeter. It needs only to know the sum of
the certified demand response capacity activated, or simply the
amount of observed consumption adjusted for certified demand
response activated, to determine its obligation. This is compa-
tible with the changes made to the regulatory framework for
demand response, i.e. the introduction into the technical rules
for rewarding demand response a segregation between inde-
pendent demand-side operators and the suppliers of sites that
activate demand response. This new regulation model, based on
the Competition Authority opinions of 26 July 2012 and 20 July
2013 and validated by the Energy Regulatory Commission in
its deliberations of 31 January 2013 and 28 November 2013,
is described in detail in RTE’s report on the NEBEF rules152. If
demand response is accurately evaluated, then the supplier will
be in the exact same situation (in terms of its obligation) as if its
customers had not reduced load. The supplier’s obligation the-
refore does not depend on the amount of certified demand
response capacity activated.
On the other hand, putting these regulatory principles into
practice becomes challenging when it comes to passing on the
cost of the obligation to the supplier’s customers. To invoice to
its customers the obligation amount resulting from the certi-
fied demand response activated, the supplier must either have
access to the sites concerned and corresponding demand res-
ponse volumes or have available from the system operator not
the measured consumption but the measured consumption
adjusted for load reductions. Otherwise, the supplier has no
other choice than to distribute the obligation resulting from
demand response among all its customers. This can create a
windfall effect for the consumer that reduces its consumption:
its obligation corresponds to its actual consumption (since the
amount of the obligation corresponding to demand response
is distributed between all consumers) but its load reduction is
also rewarded. For example, if its consumption is nil following
the demand reduction, it is not subject to any obligation and
it also receives remuneration corresponding to the amount of
the load reduction (through capacity certificates). However, the
same consumer reducing demand simply in order to reduce the
amount of its obligation will not benefit from this remuneration:
it will merely have a nil obligation. Thus, the decree’s principle of
non-discrimination between a reduction in the amount of the
capacity obligation due to load reduction and the certification
of demand response capacity is not upheld.
For the supplier to be able to pass through the cost of the obli-
gation accurately, it would have to have access to consump-
tion data per site adjusted for the demand response capacity
activated. This could create competition problems
that have been addressed in recent years, resulting
in the introduction of a regulated model between
demand-side operators and suppliers. These issues
do not relate specifically to the capacity market but
more generally to the relationship between inde-
pendent demand-side operators and suppliers; they
are also being addressed in the work being done on the imple-
mentation of the provisions stipulated by article L. 271-1 of the
Energy Code.
The alternative to having the financial impact of the explicit
valuation of demand response being addressed bilaterally and
through contracts would be to impose a regulated payment
on the sites in question, which could be incorporated into
the payment currently being defined in application of article
L. 271-1 of the Energy Code. In this case, the supplier would
not need to know the exact consumption per site adjusted for
load reductions. It would invoice customers on the basis of
consumption measured (without taking into account demand
response). The “surplus” obligation resulting from the activa-
tion of certified demand response is covered by the demand-
side operator. A change corresponding to an extension of
article L. 271-1 of the Energy Code to capacity would enable
energy and capacity to be treated in the same way and could
therefore be promoted.
In any event, by the time the capacity mechanism is in effect,
answers will have to have been found to the legal ques-
tions currently being examined to ensure that the supplier
is able to assign to consumers their share of the obligation
or to obtain the corresponding payment from the consumer
with in a regulated system.
4.5.4.2 Temperature sensitive consumers
For temperature sensitive consumers, the supplier’s gradient
is evaluated based on observed consumption adjusted for
certified demand response activated (it is on this scatter plot
that the linear regression is applied). As a result, the fact that
demand response capacity is activated within its perimeter will
have no impact on the analysis of the supplier’s temperature
sensitivity.
On the other hand, it is very difficult to comply with the prin-
ciple of non-discrimination between reductions in the obliga-
tion and certified demand response activated, since the linear
regression is applied to the entire delivery period, not just the
peak period.
152Block Exchange Notification of Demand Response. See report on the explicit valuation of demand response on the wholesale market on the RTE website.
116
Illustrationofpossibletreatmentsofdemandresponse
The following textbook case illustrates this phenomenon.
The hypotheses are as follows:
> We consider a temperature sensitive portfolio with a perfectly linear temperature dependency at temperatures below 15°C
with a gradient of 1 MW/°C;
> The PP1 hours correspond to hours at a temperature of 0°C;
> The extreme temperature is set at -5°C.
Case 1: Below 5°C, 5 MW of demand response
(non-temperature sensitive) is systematically
triggered.
The temperature/consumption chart used to estimate
the gradient is as follows.
The estimated gradient using the proposed method is
0.75 MW/°C (dotted orange line).
Observed consumption during PP1 is equal to 15 MW
(green dot). The application of the gradient yields a refe-
rence power of 18.75 MW (purple diamond) whereas the
consumer consumes 20 MW when the temperature is -5°C
(pink diamond).
Case 2: Below 5°C, temperature sensitive demand
response with a gradient of 0.5 MW/°C is systemati-
cally triggered.
The temperature/consumption chart used to estimate
the gradient is as follows.
The estimated gradient using the proposed method is
0.75 MW (dotted orange line).
Observed consumption during PP1 is equal to 17.5 MW
(green dot). The application of the gradient yields a refe-
rence power of 21.25 MW (purple diamond) whereas the
consumers consumes 20 MW when the temperature is -5°C
(pink diamond).
Pow
er (M
W)
Temperature (°C) Temperature (°C)
Pow
er (M
W)
-15 -10 -5 0 5 10 15 20 25-10
-5
0
5
10
15
20
25
30
-10 -5 0 5 10 15 20 25-10
-5
0
5
10
15
20
25
30
Power with no demand response Estimated gradient
Power with demand response activated
Reference power applied
Non temperature-sensitive demand response activated
Power with no demand response Estimated gradient
Power with demand response activated
Reference power applied
Non temperature-sensitive demand response activated
117
CAPACITY OBLIGATION / 4
It is easier to visualise this difference in treatment with a compari-
son of demand response capacity that is activated during all PP1
hours, but is not certified, and the same demand response capa-
city that is certified and activated in the same way. In one case, it
is possible to calculate a difference in obligation generated by the
“implicit” demand response, and in the other, it is possible (accor-
ding to precise methods to be described) to calculate the volume
of certified demand response factoring in the temperature sensiti-
vity of the demand response (by carrying out a linear regression on
the load reductions possible during PP2 peak hours). Two different
values are obtained: for highly temperature sensitive demand res-
ponse, certification is preferable; for demand response that is not
temperature sensitive (but applicable to temperature sensitive cus-
tomers), implicit demand response may be preferable (see illustra-
tion of how demand response can be treated below).
A regulated approach (extension of article 14 of the Brottes
Act to the capacity aspect) may raise a difficulty in identifying
the volume to which the regulated payment should be applied.
Addressing this difficulty would, strictly speaking, require
knowing how the supplier invoices the capacity. It can be assu-
med that the supplier invoices its customers applying the linear
regression formula on the consumptions actually measured (a
simplifying hypothesis which comes down to saying that the
supplier passes on to customers the exact portion of the capa-
city obligation generated by their consumption). In this case,
the supplier recovers a certain obligation volume from its cus-
tomers. The overall volume notified to it by RTE results from
the application of linear regression on the observed consump-
tions adjusted for load reductions. The resulting difference in
obligation could be assigned to the demand-side operator.
Ultimately, this comes down to assigning to demand response
a temperature sensitivity corresponding to the difference in gra-
dient between the two situations presented above. However, if
we carry out a linear regression on the demand response, the
demand response volume obtained does not match the diffe-
rence in obligation.
Before this approach was implemented, a decision would have
to be made about the method of determining the volume on
the basis of which the demand-side operator must compensate
the supplier.
4.5.5 Specific provisions for the compensation of losses on public transmission and distribution systems
The methodology for calculating the obligation corresponding
to compensation for losses on public transmission and distri-
bution systems must be consistent with the methods used to
determine the observed consumption associated with the com-
pensation for losses, which are to be proposed by CRE.
The approach proposed in the rules corresponds to a near-exact
transposition of the methods and systems used for other types
of consumption.
It involves a treatment of energy blocks supplied to compensate
losses on the PTS and PDS similar to that of declared supply (Site
NEB) on the one hand, and on the other an affiliation with a peri-
meter of the residual obligation created by differences between
the volume of losses observed during PP1 and the sum of the
energy blocks supplied. This obligation may be borne either by a
supplier or by the system operator.
4.6 Timetable for suppliers’ obligation
4.6.1 Before the delivery year
In the course of a capacity mechanism term, two events occur in
the period preceding the delivery year:
> Publication of the obligation parameters. They are published
no later than 1 January, four years before the delivery year;
> Publication of RTE’s forecast for the total capacity certificates
required for all suppliers to meet their capacity obligation, in
keeping with the provisions of paragraph I of article 18 of the
decree. The first forecast for a delivery year will be published
simultaneously with the capacity obligation parameters. They
will subsequently be published annually, no later than the first
of January of each year.
4.6.2 During the delivery year
As indicated above, the delivery year DY adopted in the rules
begins on 1 January of year DY and ends of 31 December of year
DY.
118
Within this delivery year, there is a delivery period
that corresponds to a formalisation of the “winter”
period, this being the period during which the shortfall risk
is concentrated and the PP1 days can be selected. The peak
period corresponds to the periods from 1 January to 31 March
and from 1 November to 31 December of year DY.
4.6.3 After the delivery year
4.6.3.1 Provisions included in the decree
Several provisions of the decree specify the organisation of the
different steps to be taken after the delivery year. They can be
applied directly.
Notification of the obligation: “At least fifteen days before the
deadline for transferring capacity certificates, the public electri-
city transmission system operator informs each supplier of the
amount of its capacity obligation.”
Transfer deadline: “The deadline for transferring capacity cer-
tificates, beyond which transfers of capacity certificates are no
longer possible.”
Collection deadline: “The deadline for the collection of capacity
certificates, or the date by which each supplier must hold the
amount of capacity certificates corresponding to its obligation;
it is set no later than two months after the transfer deadline.”
Notification of imbalances to obligated parties and of the
amount of settlements relating to capacity rebalancing by
obligated parties: “No later than fifteen days after the transfer
deadline, it [RTE] informs each supplier of its imbalance and the
settlement corresponding to its capacity rebalancing.”
4.6.3.2 Methods adopted in the rules
The first milestone after the end of the delivery year is the noti-
fication of the obligation. The provision adopted in the rules
corresponds to a notification of the obligation no later than
1 December of year DY+2. This milestone is set based on the
time required for the recovery of the observed consumption
data, particularly for profiled consumption.
Starting from the date by which RTE is to have informed obligated
parties of the amount of their obligation, the transfer deadline
for a given delivery year is set at 15 December of year DY+2,
in compliance with the provisions of the decree. Consequently,
the provision of the decree imposes a collection deadline of
15 February DY+3 at the latest.
It is then proposed that the deadline for notification of the sett-
lement relating to capacity rebalancing by obligated parties be
set at 20 December of year DY+2.
Collecting and distributing the settlement is a two-stage pro-
cess, beginning with the collection of the settlement owed by
obligated parties followed by the payment of amounts owed
to obligated parties within the limit of the amounts collected.
Consequently, a deadline has been added for the collection
of the settlement owed by obligated parties, and it is set at
15 January of year DY+3, after which RTE pays any amounts due
to obligated parties.
4.6.3.3 Incorporation of the public offering
The Energy Code includes an obligation for suppliers to orga-
nise public offerings to sell any certificates held in excess of their
obligation153.
In response to requests made by several stakeholders, the rules
adopt a set of provisions to facilitate the implementation of this
obligation for suppliers:
> The concept of suppliers’ surplus certificates is directly
incorporated in the rules, and corresponds to the diffe-
rence between an amount of certificates and an obligation
amount;
> Suppliers will be notified of surpluses when they are informed
of their level of obligation. The volume of certificates held on
the date of notification of the level of their obligation will be
considered for this purpose. The surplus amount will be upda-
ted following each change in the number of certificates held;
suppliers can find information regarding their surplus directly
in the register;
> Suppliers will thus be able to organise public offerings to meet
their obligation between the time they are notified of their
obligation and the transfer deadline;
> The procedures adopted for the capacity certificates register
will allow interfacing with any organised trading platforms. It
will thus be simpler to organise public offerings working from
the register and through trading platforms.
153Article L-321-16.
119
CAPACITY OBLIGATION / 4
120
The certification process involves allocating to each capacity
the amount of certificates that corresponds to its contribution
to reducing the shortfall risk.
A capacity’s contribution to reducing the shortfall risk depends
on its specific characteristics, the power system in which it ope-
rates and the security of supply criterion set by public authori-
ties. Certification parameters must therefore be chosen in such
a way as to reflect a capacity’s contribution to reducing the
shortfall risk as accurately as possible. The general provisions are
the framework within which the certification process unfolds.
5.1.1 Players involved in capacity certification
Operators of generation and demand response capacity are affec-
ted by the certification aspect of the capacity mechanism. They can
either act as their own capacity portfolio manager, a role created by
the decree, or designate a capacity portfolio manager that will bear
the financial responsibility for imbalances within their portfolios.
5.1.1.1 Operator
Under article 321-16 of the Energy Code, opera-
tors must file a certification request with the public
transmission system operator for any generation or
demand response capacity connected to the public
transmission system or public distribution system154.
Participation is thus mandatory for all capacity.
The rules provide detailed definitions of capacity operators and
categorise them according to the nature of their capacities
(generation or demand response).
5.1.1.1.1 Operator of generation capacity
A generation capacity operator can be:
> Either the holder of the Transmission Network Access
Contract (CART), the Distribution System Access Contract
(CARD) or the calculation service contract for an injection
site;
> Or a legal entity with a mandate from the holder of the Trans-
mission Network Access Contract (CART), the Distribution
System Access Contract (CARD) or the calculation service
contract for an injection site.
5.1.1.1.2 Operator of demand response capacity
The operator of demand response capacity, whether operated
directly by a consumer or indirectly through an aggregator, can be:
> Either the holder of a Network Access Contract, a calculation
service contract, a single contract or a regulated tariff contract
for extraction sites;
> Or a legal entity with a mandate from the holder of the
Network Access Contract, calculation service contract, the
single contract or regulated tariff contract for the extraction
site or for each extraction site constituting the demand res-
ponse capacity.
5. CAPACITY CERTIFICATION
Supply in the capacity market is constituted by capacity certi-
ficates issued by RTE and allocated to operators of generation
and demand response capacity that contribute to security of
supply. This chapter discusses capacity certification, i.e. the pro-
cess by which each operator is allocated an amount of certifi-
cates proportionate to the benefits provided to the power sys-
tem in terms of reducing the shortfall risk.
The chapter begins with a review of the general provisions
governing certification, particularly the identification of stakhol-
ders affected, how their capacity level is determined, and the
time periods and methods applied in calculating this capacity
level (§ 5.1). Details are then provided about the options selec-
ted in RTE’s proposal: definition of the PP2 period during which
the capacity level is determined (§ 5.2), the methods used to cal-
culate availability factoring in the technical constraints of capa-
cities (§ 5.3), practical implementation of certification, particu-
larly timetables (§ 5.4), and the principles of rebalancing (§ 5.5).
In the interest of transparency for all involved, the certification
process is based on extensive data collection (§ 5.6). To comply
with regulations, the certification process also includes consis-
tency checks, some aspects of which are described at the end
of the chapter.
154The decree also stipulates (II, article 8) that certification request documentation is to be presented to the operator of the system to which the unit is connected.
5.1 General provisions governing the certification of capacities
121
CAPACITY CERTIFICATION / 5
5.1.1.2 Capacity portfolio manager
Similarly to the balance responsible entity system in place in
the energy market, the decree introduced the role of the capa-
city portfolio manager to spread capacity availability risks when
determining the effective capacity level.
The capacity portfolio manager is the legal entity financially
responsible for the imbalances of the capacity operators in its
portfolio. It pays the penalty charged to operators as laid out in
article L. 335-3 of the Energy Code. Operators can act as their
own capacity portfolio manager or enter into contracts with
capacity portfolio managers. Capacity portfolio manager status
is acquired by signing a contract with RTE.
5.1.2 Capacity level
5.1.2.1 Certified capacity level and effective capacity level
5.1.2.1.1 Overview of the provisions of the decree
The decree establishes a certification process based on a certified
capacity level followed by verification of the effective capacity level.
The certified capacity level […] reflects the contribution of the
capacity to reducing the shortfall risk during the delivery year.
The effective capacity level reflects, for a given delivery year,
the real contribution of the capacity to reducing the shortfall risk
for a given delivery year155.
These two concepts are inseparable.
5.1.2.1.2 Two approaches: actual capacity or
normative basis
The real level of security of supply depends on the effective avai-
lability of capacity when supply is tight. As capacity is certified in
advance (from three to four years before the deli-
very period for existing generation capacity) and
the effective capacity level is measured after the
delivery period, imbalances may be observed. Two
approaches can be taken to measuring imbalances:
> The approach based on actual capacity involves an indivi-
dualisation of the imbalance between the certified capacity
level (on the basis of which capacity certificates were issued)
and the effective capacity level: the initial certification may be
based on self-assessed data (operators have the most infor-
mation about expected availability);
> The normative approach involves pooling imbalances
between certified capacity levels and effective capacity levels:
in this case initial certifications may be based on normative
values (typically per technology) associated with real-time
minimum commitments.
However, the decree specifies that operators are to indicate
in their certification requests “the forecast availability of their
capacity during the PP2 period”. Hence the regulations explicitly
provide for a mechanism that will hold capacity portfolio mana-
gers responsible for imbalances between their commitment to
a level of certified capacity and their effective capacity level. This
provision is compatible with the philosophy of the approach
based on actual capacity. A generic approach based on the indi-
vidualisation of imbalances has therefore been adopted.
This approach presents several advantages.
Firstly, with an approach based on self-assessed rather than nor-
mative data, the certified capacity level of an operator is not
limited by the performances of other operators. A normative
approach would penalise the most efficient operators in a given
sector and benefit the least efficient ones. With an individua-
lised approach, each operator can reap the full benefits of any
155Decree 2012-1405, Article 1.
Figure 53 – Relationship between certified capacity level and effective capacity level(Source: RTE, Market Access Committee meeting of 11/07/2013)
Effective capacity levelCalculated based on effectively available power
Starting 3-4 years before delivery year
Certified capacity levelCalculated based on forecasts
Année de livraison Delivery year
122
improvement in its own performances. It creates a powerful sys-
tem of accountability. Operators decide on the projected avai-
lability of their capacity. To avoid distortion and strategic beha-
viour, they must be held accountable for differences between
actual and forecast availability.
Secondly, the approach should lead to virtuous behaviour,
notably by creating a closer link between the physical state
of the system and the information conveyed by the capacity
mechanism. And maintaining this link through to the last reba-
lancing gate should pave the way for a dynamic management
of capacity adequacy. For instance, is operators anticipate that
they will make a lesser contribution to reducing the shortfall
risk (technical problem, exceptional maintenance or decision
to close a unit), they have an incentive to rebalance, and the
resulting decline in the level of capacity certified can trigger the
creation of new capacity and peak demand management mea-
sures. This feedback loop appears to be an important factor
in the stability of the mechanism, creating a restoring force
that binds the two sides of the supply-demand balance. It
is particularly important for capacity that can be
deployed rapidly, especially demand response
and other peak demand management actions.
Not taking into account short-term resources would
mutualise capacity risks with the cost being borne
by the whole community (in practice, it would mean
increasing the security factor for all consumers).
A third advantage of this approach is its simplicity:
the number of capacity certificates allocated to a
resource depends directly on the attested availa-
bility and technical characteristics of the resource
during the PP2 peak period. This “self-assessment
+ verification” system circumvents the problem of
defining normative coefficients that are often chal-
lenged by the operators that claim to do be more
efficient. Indeed, a normative approach requires
determining capacity certificate allocation values
ahead of time and generates significant distortion,
particularly in terms of the bases for calculating refe-
rences for allocation values.
Lastly, this approach reduces the risk of “phantom
capacity” appearing because real availability is taken
into account. It ensures that capacity that is not avai-
lable during the peak period will not be rewarded
through the capacity mechanism. Of course this
system would not be appropriate if the objective
was merely to remunerate existing assets by offsetting some
stranded costs, but, as indicated in chapter 1 of this report, such
is not the purpose of the mechanism introduced in France.
5.1.2.1.3 Intermittent capacities
The applicability of the generic approach described above (cer-
tification based on self-assessments, restatement post verifica-
tion) to intermittent or non-controllable capacities was discussed
extensively during the consultation. Some participants noted
that the intermittent nature of some capacities would necessarily
require the application of a normative approach, since the availa-
bility of these capacities depends exclusively on external parame-
ters156. They also stressed the impact this volatility would have on
all stakeholders and on the quality of the signal conveyed by the
mechanism. Since a large share of intermittent capacity benefits
from purchase obligations, the law already provides for a specific
system to be created for these capacities (to be proposed by CRE).
Based on these considerations, the possibility was included in
the rules for an operator of intermittent capacities to opt for an
alternative certification system. Under this alternative system,
certificates are allocated to operators based on normative coef-
ficients, rather than on their self-assessments with subsequent
adjustments following the verification of effective capacity
levels. This gives operators options with regard to the treatment
of the risk associated with the primary source.
Two concerns should nonetheless be mentioned in considering
this system:
> Technical studies conducted by RTE (presented in this chapter)
did not support the assertion that the application of the generic
system to intermittent capacities would jeopardise the quality
of the capacity mechanism signal: as of today, the main risks
for the level of certified capacity, and thus for signals relating to
capacity, are those that could affect nuclear capacity;
> This approach could prevent the full use of all resources through
the capacity mechanism, notably demand response resources.
5.1.2.1.3.1 Structure and volume of intermittent risks
To assess the impact of the certification of intermittent capa-
cities using an approach based on accurate availability data,
The generic approach adopted involves certifying capacity based on availability forecasts submitted by operators and calculating a settlement after the fact to reflect the level of effective capacity meas-ured based on availability during the PP2 period.
156A parallel can be drawn with climatic correction used on the obligation side to ensure that obligated parties’ obligations are not affected by weather contingencies. If weather contingencies are neutralised in calculating the obligation, they should also be neutralised in the certification process. However, the restatement carried out to calculate the obligation does not include all external risks, but specifically weather contingencies. The aim is to compare the actual situation to a situation representative of the risk against which the system is seeking to protect itself, i.e. a cold spell. This is why it is proposed in the draft rules that a correction be made for temperature sensitive capacities (not intermittent sources, but some demand response for example) so that the capacity level allocated to them is consistent with their contribution in a “one-in-ten-year cold conditions” type situation.
123
CAPACITYCERTIFICATION / 5
Figure 54 –Standard deviation of eff ective capacity level for wind and run-of-river power
Wind (standard deviation in MW and %) Run-of-river (standard deviation in MW and %)
Stan
dard
dev
iati
on (%
)
Stan
dard
dev
iati
on (M
W)
Stan
dard
dev
iati
on (%
)
Stan
dard
dev
iati
on (M
W)
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
0
50
100
150
200
250
300
350
400
450
0
50
100
150
200
250
300
350
400
450
2008 2009 2010 2011 2008 2009 2010 2011
Without milestones (MW)
Milestones 5 days (MW)
Without milestones (%)
Milestones 5 days (%)
RTE conducted technical studies on the structure and volume
of the risks to which intermittent capacities are subject. The
goal was to estimate the impact the certifi cation method used
for intermittent capacities has on the “stability” of the capacity
mechanism.
These studies are based on actual production between 2008
and 2011 and the results quantify the variability of wind and
run-of-river power generation risks. The charts below show the
results in terms of the variability of capacity levels with days
selected over the entire delivery period or with milestones limi-
ting the number of days in March and November to fi ve.
Two conclusions can be drawn from these studies:
> Variability is limited within a given year (approximately 300 MW
for wind power and 200 MW for run-of-river power);
> The risk may however be more signifi cant for one technology:
the standard deviation can represent up to 17% of the eff ective
capacity level for wind power and 7% for run-of-river power.
These results show that the variability of wind and run-of-river
power in past years was low in relation to the power sector,
especially compared with nuclear capacity (standard deviation
of about 1,000 MW). The volatility of capacity supply mainly
corresponds to risks relating to nuclear power generation.
Looking ahead, forecasts were drawn up for 2016-17 to estimate
the variability of wind and photovoltaic power generation. The
variability of intermittent renewable energy sources remains
limited in 2016-17 with a standard deviation of approximately
150 MW for PV and 500 MW for onshore wind. Variability is thus
still lower than for nuclear power.
Figure 55 – Comparison of the breakdown of annual wind and run-of-river power production
An
nu
al g
ener
atio
n (T
Wh
)
Wind (distribution of annual generation in TWh) Run-of-river (distribution of annual generation in TWh)
32
34
36
38
40
42
44
46
16
18
20
22
24
26
28
30
124
Another study was conducted based on probabilistic simula-
tions to complement the analysis of the structure of intermittent
risks, focusing notably on the breakdown between intra-annual
risks, which are sensitive to the location in time of PP2 days, and
inter-annual risks, which are sensitive to risk realisation during
the delivery year. Within this context, the variability of annual
production in these segments was studied for a large number of
scenarios assuming no changes in the fleet.
Two observations can be made:
> Inter-annual variability in wind power generation is low: the
main risk is intra-annual;
> Inter-annual variability of hydropower generation is high: this
is due to differences in water conditions between years. The
intra-year risk, however, is lower. Based on projections for
2016-17, the total variability of run-of-river hydropower is
estimated at around 600 MW.
Differences between the characterisation of the intermittence
of run-of-river hydro and wind power generation have distinct
consequences for the signal conveyed to the market and the
system:
> A wind capacity operator has no new information about the fore-
cast production of its capacity when the delivery period begins;
> A run-of-river capacity operator has more reliable information
about its forecast production when the delivery period begins.
Choosing whether to treat the risk associated with water
conditions for run-of-river hydro generation, which can be
predicted before the start of the delivery period, through an
approach based on actual results or a normative approach,
means choosing whether the real state of security of supply
in the delivery year in question is targeted or not.
5.1.2.1.3.2 Impact of a normative approach
Making a separate treatment of intermittent capacities possible
is not without consequences for the mechanism.
The first question it raises is whether normative cer-
tification should be an option for all capacities. With
no adjustments made to reflect observed availability,
a purely normative approach results in certificates
being allocated to capacities irrespective of their
actual contribution to reducing the shortfall risk.
A normative approach leading to a total absence of
imbalances, regardless of the actual availability of the
capacity, could induce undesirable windfall effects157.
This approach heavily penalises demand response.
Secondly, the normative approach does not allow all
resources available to the capacity mechanism to be utilised,
particularly the addition of new capacity as the delivery year
approaches. Risks relating to water conditions can typically be
detected between year Y-3 and the delivery period. In this case,
the procedures stipulated in the decree and implemented in the
rules (rebalancing by the operators in question) must allow this
information to be communicated to the market (for example a
rise in prices following a reduction of the expected actual avai-
lability of certain resources) to create economic space for new
capacity (typically demand response on dates close to the deli-
very year). These resources cannot be utilised with a normative
approach.
Thirdly, the option of applying a normative approach to inter-
mittent capacities raises the issue of the equal treatment
of all capacity. This is an especially important consideration
because stakeholders have underlined the fact that all types of
capacity, controllable or not, is subject to external risks.
The rules make it possible for the operator of non-controllable capacity (wind, photovoltaic, run-of-river hydro power) to choose between one of the two following systems when certifying capacity:
> The generic system (certification based on self-assessed data with subsequent restatement based on verified availability) applicable to con-trollable capacity;
> An alternative system (certification based on normative coefficients calculated for each technology, neutralising the risk associated with the primary source).
This option addresses the expectations expressed during the consultation and incentivises opera-tors to forge strategies to hedge variability risks (particularly by adding flexible capacity such as demand response). It thus allows a distinction to be made between external risks associated with the primary source and those that are within the operator’s “control”.
The coefficients used with the normative system are based on adequacy studies and reflect the average contributions of these technologies to reducing the shortfall risk.
This ability to choose between the two approaches is modelled after the renewable energy support schemes adopted in some European countries, which give operators an option between partici-pating in the market or a de-risked system (Ger-many and Spain are examples).
157If capacity level is determined over a relatively long period (around ten years), without no specific treatment, a capacity that is closed could be assigned a capacity level for ten years, though it would admittedly diminish each year over the period.
125
CAPACITY CERTIFICATION / 5
5.1.2.1.4 Unforeseeable risks
Some generators indicated during the consultation that they did
not want the evaluation of their effective capacity level measu-
red after the availability verification to take into account unfore-
seeable risks that affect availability in real time. These include all
events that are beyond the control of the operator and result in
temporary unavailability (equipment failures, etc.).
Accounting for unforeseeable risks presents the same type of
difficulties as those outlined above. It is indeed not easy to esta-
blish a rule ahead of time for distinguishing between risks that
are unforeseeable (and thus acceptable) and foreseeable (consi-
dered “abnormal”). An incentive system similar to that used for
imbalance settlements in energy markets, assigning to each
stakeholder the cost of the rebalancing the system requires,
should provide an adequate response to these issues and avoid
introducing a rule for identifying the nature of risks that would
inevitably be complex.
Because they can rebalance before the delivery period (see
chapter 6), operators are able to adjust their certified capa-
city levels to take the realisation of unforeseeable risks into
account: they can revise their capacity levels downward during
periods or years when numerous unforeseeable risks occur, or
upward if few unforeseeable risks materialise. The rules also
include various provisions to attenuate the effect of such
occurrences:
> The difference between certified and effective capacity levels
is evaluated at the capacity portfolio manager level, making it
possible to spread risks;
> Availability commitments are made for the whole PP2 period,
so risks can be spread over time.
Some stakeholders said that while such measures may be
necessary, they are not sufficient to ensure fair competition
in the capacity market, particularly with respect to stakehol-
ders with large perimeters. A specific provision was therefore
included in the rules to limit the application of rebalancing costs
if unforeseeable risks affect generation or demand response
capacity.
The system adopted in this provision (two zero-cost rebalancing
“tickets”) is designed to maintain the incentive for stakeholders
to submit their best availability forecasts ahead of time (tickets
valid only for two days after the unforeseeable event is repor-
ted and for a volume proportional to the impact of the event
on certified capacity). Operators will therefore have to report all
unforeseeable risks affecting their resources, including capacity
of less than 100 MW158, to be issued rebalancing tic-
kets. This new system will make operations in the
power system even more transparent.
5.1.2.2 Certification based on self-assessed
data with verification of availability
Under the generic approach, the principles outlined above
involve basing the number of capacity certificates allocated to a
resource to the self-assessed data provided by the operator. All
capacity is certified based on its specific characteristics. Certified
capacity levels are based in part on the estimated availability of
the capacity during the PP2 period, per the terms of the decree:
“The certified capacity level […] takes into account in particular
the estimated availability of the capacity during the PP2 peak
period of the delivery year” (article 1).
All self-assessed data submitted is then compared with the
effective capacity level measured during PP2 in the delivery
year. The effective capacity level is calculated using the same
method as the certified capacity level. The difference between
the two is the basis for the imbalance settlement subsequently
calculated.
Consistency between certified and effective capacity levels is
thus guaranteed. Because the same method is applied in cal-
culating certified capacity levels and effective capacity levels,
certification parameters are set at the start of the mechanism
term and maintained throughout. Only data that can cause the
capacity level to change are reported by operators. They have
the information necessary to anticipate the amount of certifi-
cates they will receive to match their effective capacity level.
The certified capacity level is thus based on the operator’s fore-
cast of its effective capacity level. The proposed method thus
mirrors the system in place in the energy market: operators
submit data based on their own calculations and imbalances are
determined based on actual results.
The deadline for initial certification is at least three years before
the delivery year for existing generation capacity (the decree of
158In this regard, the provision goes beyond the principles of EU Regulation 543/2013.
Rebalancing plays a central role in the mecha-nism: operators can rebalance at any time, including during the delivery year, to adjust their certified capacity level as they obtain more spe-cific information about the availability of their resources during the mechanism term.
126
December 2012 specifi es that a deadline must be set for opera-
tors to submit certifi cation requests). They are not expected to
submit fi rm and fi nal assessments of the projected availability
of their capacity, since rebalancing is possible. Rebalancing cor-
responds in a way to a “re-certifi cation” of capacity, refl ecting
adjustments to operators’ forecasts based on new information
about their capacity. The cost of the rebalancing, which is added
to the cost of the certifi cates required for rebalancing by the
capacity portfolio manager, refl ects the cost to the community
of disclosing the new information. The cost is zero before the
delivery year starts and rises progressively thereafter, with the
cost of imbalances, during the delivery year.
5.1.3 PP2 peak period
The decree specifi es that the “peak period” refers to “the hours
of a delivery year during which the shortfall risk is greatest, par-
ticularly those during which national demand is highest”. The
peak period used in the capacity certifi cation and verifi cation
methods is called the PP2 period.
At the time of certifi cation, the certifi ed capacity level must refl ect
the capacity’s contribution to reducing the shortfall risk, meaning
it must take into account projected availability during the PP2
peak period. The real-time measurement of eff ective capacity
availability must therefore focus on this same PP2 period.
In a year with shortfall situations, the best way to assess each
capacity’s contribution to reducing the shortfall risk is to
measure its availability during the actual shortfall hours. PP2
must therefore include these hours. However, the capacity
mechanism is intended to provide insurance by rewarding capa-
city that contributes to security of supply even in years with no
shortfall situations. As a result, the PP2 period must be defi ned in
such a way as to provide the best estimate of a capacity’s contri-
bution to reducing the shortfall risk when no shortfall occurs.
5.1.4 Calculation of the capacity level
Diff erent methods of calculating the capacity level were pro-
posed during the consultation, notably focusing on the algo-
rithm used. These proposals were combined into a formula cen-
tred around:
> Available power during PP2
> A coeffi cient enabling technical constraints to be taken into
account (defi nition and calculation presented in § 5.1.4.2).
5.1.4.1 Available power
The principle applied in calculating available power must be that
a capacity that is not available during the peak period does not
contribute to reducing the shortfall risk and will therefore not be
allocated any capacity certifi cates.
In the rules, available power is defi ned as the power that can be
made available during PP2. Generation capacity that does not
produce energy but could do so, or demand response capacity
that is not activated but could be, is considered to be available
during the period in question.
Figure 56 – Organisation of the certifi cation process
Initialcertified
capacity level
(Initialavailability)
Difference
Rebalancing
PP2
Rebalancing is flexible and possible even during delivery year
Effectivecapacity level
(Actualavailability)
Certifiedcapacity
level afterrebalancing
(Availabilityafter
rebalancing)
127
CAPACITYCERTIFICATION / 5
5.1.4.2 Technical constraints
Capacity can be subject to technical constraints (other than
availability) that aff ects its contribution to reducing the shortfall
risk. Examples include:
> Energy constraints;
> Constraints linked to controllability/intermittence;
> Dynamic constraints.
How these constraints are factored in when calculating certi-
fication levels depends on the weighting assigned to them in
determining the capacity’s contribution to reducing the short-
fall risk. They must therefore be measured and verified.
5.1.4.2.1 Energy constraints
The key risk the capacity mechanism must address is a cold spell
with a particular time structure that could range from several
hours to several days in a row.
On a theoretical level, the certifi cation process must take into
account technical constraints such as daily energy constraints
(number of hours per day during which the capacity can be being
activated at maximum power), weekly energy constraints (num-
ber of consecutive days of a week during which the capacity can
run) and seasonal energy constraints (number of days per year
during which the capacity can operate).
Seasonal constraints are less of a concern if the capacity can be
activated for two weeks in a row. On the other hand, capacity that
can only be activated one day a week makes a real contribution
to reducing the shortfall risk but it is limited, regardless of its sea-
sonal availability. In the interest of simplicity, the seasonal energy
constraint is not taken into account in the rules for the fi rst
year of the mechanism but can be integrated into a later version.
Following the publication in September 2013 of the report
accompanying the draft rules, which included a chart illustrating
how daily constraints were taken into account, some stakehol-
ders questioned whether it was necessary to only have capacity
that could be activated ten hours per day to contribute to security
of supply and the mechanism’s effi ciency.
This “activatable capacity” factor neutralises diff erences
between generation and demand response capacity by basing
the issuance of certifi cates on contributions to security of sup-
ply. The entire shortfall landscape is taken into account in
estimating each capacity’s contribution. This provision is in
keeping with the decree, which requires that only one “capacity
certifi cate product” be adopted. It will thus facilitate trading, at
least when the mechanism is fi rst implemented. All other pro-
visions considered would inevitably have led to the creation of
diff erent products, adding another layer of complexity.
5.1.4.2.2 Controllability / intermittence
5.1.4.2.2.1 Methods based on certifi cation procedure
adopted
A capacity’s controllability or intermittence is fi rst taken into
account through the approach adopted for certifi cation.
If certifi cation is based on actual results, then the operator will spe-
cify the variability of its capacity in its certifi ed capacity level decla-
ration and ultimately receive the amount of certifi cates correspon-
ding to its real contribution (producible energy during PP2).
With a normative approach to certifi cation, this principle does not
apply. According to regulations, the normative approach must refl ect
the average contribution of capacities to reducing the shortfall risk.
5.1.4.2.2.2 Normative certifi cation and contribution to
reducing the shortfall risk (capacity credit)
Adding intermittent generation capacity to a power system
does not reduce the shortfall risk in proportion to past average
producible power values. To estimate this contribution to secu-
rity of supply, a contribution coeffi cient (CC) must be applied to
translate these technologies’ average contribution to reducing
the shortfall risk.
Figure 57 – Illustration of capacity credit based on installed wind power in Great Britain (Source: IEEE Power Energy Society)
Peak
Installed wind capacity
Cap
acit
y cr
edit
0 10 20 300%
5%
10%
15%
20%
25%
30%
ELCC / LOLE
ELCC / LOLP (90%)
ELCC / LOLP (95%)
ELCC / LOLP (97%)
128
The value of this coefficient depends (i) on the capacity consi-
dered, (ii) on the amount of intermittent capacity already in the
system, and (iii) more generally, on the broader power system
(structure of demand, structure of the fleet excluding intermittent
capacity, interconnection capacity). The goal is to determine the
correlation between the intermittent risk and shortfall situations.
The method adopted to determine the contribution coefficients
for eligible technologies (wind, solar, must-run hydro) is similar
to that used to estimate contributions to the shortfall risk of
different consumption profiles: it is based on equivalence with
a perfect resource, with no constraints, that receives 1 MW of
certificates per MW installed.
The value of the contribution coefficient can then be estimated
based on the value of the certificates issued to the technologies
and past records of their producible energy at peak.
Values adopted in the rules for the contribution coefficient per
technology
For the first delivery years of the capacity mechanism, the rules
adopt the following CC values for the technologies in question:
> CChydro = 85%
> CCwind = 70%
> CCsolar = 25%
5.1.4.2.2.3 Length of historical data required
Certification calculations based on the normative approach
incorporate past producible energy values for the capacity. The
length of historical data used varies depending on the techno-
logy. These lengths are determined in such a way as to be:
> Sufficiently long for the average producible energy value to
be close to producible energy value certified. This allows risks
associated with the primary source to be smoothed.
> Sufficiently short for structural changes in the capacity to be
taken into account within a relatively short period of time and
consistently with the timeframes of the mechanism.
5.1.4.2.3 Dynamic constraints
The dynamic constraints of generation facilities are not explicitly
factored into the rules. They are taken into account indirectly
through the definition of PP2 and the certification process with
verification of availability. Dynamic constraints that would pre-
vent generation capacities from being available on days notified
by RTE are factored into the calculation of the effective capacity
level.
5.1.4.2.4 Accounting for system constraints
In their current form, the rules do not include any specific provi-
sions about accounting for network availability constraints. The
introduction of such a provision, which would entail introducing
a localised incentive into the certification process, has not been
ruled out. However, the complexity of system constraints is such
that the timetable for preparing the rules for the first delivery
year was not compatible with the inclusion of a provision on this
subject.
This issue was nonetheless raised during the consultation.
Two options for taking system constraints into account were
presented:
> The first was based on a pooling of system constraints at the
level of the security factor, with related constraints (unavaila-
bility of networks) being neutralised in the calculation of the
effective capacity level;
> The second was based on the terms of connection contracts
regarding temporary limitations with ex-post verification if
network availability does not meet an operator’s expecta-
tion. RTE favours this second option, as it avoids having the
Value of adequacycriterion = K0 (3h)
Value of adequacycriterion = K1
Value of adequacycriterion = K2
Addition of 100 MWof a specific resource
Addition of X MWof a perfect resource
By iteration, we determine X such that K1 =K2 The specific resource is allocated X certificates for 100 MW
1 2
129
CAPACITY CERTIFICATION / 5
community bear a cost stemming from an inability to remove
power from certain facilities. The guiding principle in the rules
proposed is that obligated parties should have resources to
manage their obligation and not be exposed to costs that are
completely beyond their control.
5.1.4.3 Provision adopted on the calculation of
the capacity level
In compliance with the provisions of the decree and in the light of
the considerations above, the formula for calculating the capacity
level (certified or effective) adopted in the rules takes the form:
CapacityLevel = PP2AvailablePower x K
The K coefficient adopted in the rules applies only to the energy
constraints discussed in § 5.1.4.2.1 and breaks down as follows:
K = Kd x Kw
The Kd coefficient reflects the influence of daily energy constraints
on a capacity’s contribution to reducing the shortfall risk
The Kw coefficient reflects the influence of weekly energy
constraints on a capacity’s contribution to reducing the short-
fall risk
Normative approach
CapacityLevel = HistoricPeakProducibleEnergy x CCtechnology
Chronological summary of the certification process:
For the first two delivery years, the rules adopt specific provi-
sions making it possible to take into account:
> A specific first delivery year (from 30 November 2016 to
31 December 2017 with July and August excluded) enabling
transition to a delivery year matching the calendar year;
> A shorter period between the start of the term and the deli-
very year. The rules directly incorporate the mechanism para-
meters for these two years and certification request deadlines
have been modified accordingly.
Once the mechanism is established, i.e. as of the third delivery
year, the chronology of the certification process will be as follows:
15/01 DY+131/12
A+3 mois
Operationalgenerationcapacities
01/12 DY+2
Transferdeadline
Publication of certification
parameters
15/12 DY+2
Planned generation capacities
Demand response capacities
REBALANCING period
Certificationperiod
01/11 DY-4
01/11 DY-1
01/11 DY-301/01
31/0301/11
DELIVERY YEAR
DY
PERIOD
PP2 PP2
15/02 DY+3
Collectiondeadline
Notificationof effective
capacity level
Imbalancenotification
date
DELIVERY
by month on the basis of a shortfall landscape evaluated seve-
ral years before the delivery year. In this case the PP2 periods
consists of approximately 1,200 hours;
> A “demand-based” approach with PP2 targeting the actual
hours of highest demand during the delivery year. Each hour
of the PP2 peak period is equivalent. This definition results in a
lower number of PP2 hours (between 100 and 300).
5.2 Period covered by capacity certification (PP2)
5.2.1 Period during which the contribution in estimated
Two main approaches were given consideration during the
consultation:
> A “time-based” approach with PP2 being a non-targeted
period defined in advance made up of working days between
November and March. The hours included in PP2 are weighted
130
Figure 58 shows a comparison of the shortfall periods
identifi ed in RTE’s probabilistic supply-demand balance
studies and demand levels during shortfall hours.
Two key conclusions can be drawn from it:
> The hours of highest demand are a good indicator of short-
fall situations. 99% of shortfall hours are contained in the
300 hours of highest demand;
> The 100 hours of highest demand include 94% of the hours
with shortfalls.
The adoption of a targeted period and demand-based approach,
resulting in a PP2 of between 100 and 300 hours during the
delivery year, is thus an appropriate way to estimate capacity’s
contribution to reducing the shortfall risk.
Given the link between contributions to reducing the shortfall risk
and the hours of highest demand, a capacity that is available all win-
ter will make the same contribution to reducing the shortfall risk as
one that is only available during periods of high demand. Both must
therefore receive the same number of capacity certifi cates.
However, their capacity level depends on availability during PP2.
To illustrate the infl uence of PP2 on the volume of certifi cates
allocated to a capacity, the chart below considers two capacities,
one available over 100 hours and one over 500 hours.
The blue curve shows the link discussed above between short-
fall hours and the hours of highest demand. A resource available
in the 200 hours of highest demand has a contribution almost
equivalent to that of a “perfect” resource159 (98% of the shortfall
hours are within the 200 hours of highest demand). The green
and purple curves illustrate the impact of the scope of PP2 on
the volume of certifi cates allocated with regard to the availa-
bility constraint. Since capacity availability is measured over
PP2, capacity that is available during the 200 hours of highest
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 100 200 300 400 500 600
Shar
e of
hou
rs w
ith
sh
ortf
all
Rank of hours of highest consumption
Figure 58 – Link between shortfall and hours of highest consumption
Hours of highest consumption/Duration of PP2
Red
uct
ion
of s
hor
tfal
l ris
k
1101
201301
401501
601701
801901
1,0011,101
1,2011,301
1,4011,501
1,6011,701
1,8011,901
2,001
0%
20%
40%
60%
80%
100%
Figure 59 – Impact of the duration of PP2 on the contribution calculated for capacity(Source: RTE, WG of 07/02/2013)
Contribution to reduction of shortfall risk according to number of hours of availability
Contribution allocated to a capacity available for 100 hours according to duration of PP2
Contribution allocated to a capacity available for 500 hours according to duration of PP2
159A “perfect” resource is a capacity with no technical constraints and that is available at full power all the time.
131
CAPACITYCERTIFICATION / 5
demand, and thus has a high contribution, will receive fewer
capacity certifi cates if availability is measured over a longer
period (the allocation would only be about 50% with a PP2 of
1,000 hours for example). As such, the certifi cates allocated to
this capacity would not refl ect its contribution to reducing the
shortfall risk.
The bottom line is that the application of a non-targeted (and
therefore long) PP2 period underestimates the certifi cates that
should be allocated to capacity that is available less but may
make a considerable contribution to reducing the shortfall risk.
5.2.2 Consequences of the PP2 period defi ned on the distribution of certifi cates between technologies
As discussed above, the defi nition of the PP2 period can have
major redistributive eff ects between the diff erent types of
capacity, particularly demand response. Indeed, it appears that
demand response capacities are often available during targe-
ted periods: all other things being equal, a longer PP2 period
will reduce the number of certifi cates allocated to a demand
0
2,000
4,000
6,000
0
50
100
150
200
250
0
500
1,000
1,500
2,000
2,500
3,000
0
20,000
40,000
60,000
CCGT
WIND
BM DEMAND RESPONSE
NUCLEAR
Trend in effective availability according to method of defining PP2
2011 2011
2011 2011
Eff
ecti
ve p
ower
(MW
)
Delivery year (Winter)
Figure 60 – Winter 2011/2012 – Comparison of time- and demand-based approaches
100h of highest demand 200h of highest demand 300h of highest demand
Winter with weighting [1,8,70,20,1]% Winter with weighting [2.5,30,55,10,2.5]% Winter with weighting [5,20,40,30,5]%
response capacity even through its eff ective contribution can
be signifi cant.
A comparison of the demand-based approach targeting the
200 hours of highest demand and a time-based approach
covering the whole winter with monthly weightings linked to
the shortfall probability highlights the impact PP2 has on the
number of capacity certifi cates allocated to each technology.
This impact is illustrated in fi gure 60, which was taken from a
study presented during the consultation on four technologies
characteristic of the French fl eet: nuclear, combined-cycle gas,
wind and demand response.
Choosing a PP2 period not targeted to the hours of highest
demand and weighting availability over the whole winter results
in much less certifi cation of demand response and similar capa-
cities. The eff ective capacity level thus does not refl ect the real
contribution of demand response to reducing the shortfall risk
during the delivery year, regardless of weightings. Conversely,
with a targeted PP2 period, the amount of certifi cates allocated
to demand response refl ects its contribution to security of sup-
ply, without prejudice to generation capacity.
132
Table 3 – Trend in total eff ective availability level
5.2.3 Consequences of the PP2 period defi ned on the variability of certifi cate volumes
Some generators questioned the choice of a targeted PP2
period, citing the underlying risk of instability and saying they
consequently did not have enough visibility to make commit-
ments with regard to availability.
To test this argument, RTE conducted a study that quantifi es the
impact of the choice of the PP2 period on the eff ective capacity
level. This study was based on past availability data and compared
the eff ects of the two approaches (targeted vs. non-targeted) on
the same perimeter, using the same hypotheses. Results are pres-
ented for the fl eet as a whole and for each technology. The eff ective
availability of the generation fl eet was calculated for the years from
2006 to 2011. The fi gure below and accompanying table show the
aggregated results of availability calculations for the period from
2006 to 2011 depending on the PP2 period chosen.
The fi rst conclusion to be drawn from this study is that levels
are consistent with time- and demand-based approaches and
stable over time.
Similar results are obtained with all methods each year and none
can be considered divergent or more volatile than the others:
> Trends are the same, since a drop in the eff ective level of avai-
lability is observed only in the winters of 2008 and 2009, and
the level increases for the other years with both approaches;
Figure 61 – Trend in total eff ective availability level
Delivery year (winter)
80,000
85,000
90,000
95,000
100,000
80,000
85,000
90,000
95,000
100,000
2006 2007 2008 2009 2010 2011
Hou
rs of high
est deman
dW
eighted w
inter
Max DIFFERENCE between methods adopting the same approach 2006 2007 2008 2009 2010 2011
Demand-based 371 105 1,156 713 221 402
Time-based 845 1,326 1,314 1,523 1,751 2,593
Type # PP2 method 2006 2007 2008 2009 2010 2011
Demand 1 100 hours of highest demand 85,124 88,301 94,204 91,841 96,763 98,059
Demand 2 200 hours of highest demand 84,865 88,291 93,574 91,372 96,580 97,667
Demand 3 300 hours of highest demand 84,753 88,197 93,048 91,128 96,542 67,657
Time 4 Winter with weighting [5,20,40,30,5]% 83,228 87,494 91,406 89,217 95,915 96,118
Time 5 Winter with weighting [1,8,70,20,1]% 84,073 88,820 92,720 90,740 97,665 98,711
Time 6 Winter with weighting [2.5,30,55,10,2.5]% 84,029 87,572 91,693 89,600 96,975 97,932
100h of highest demand
200h of highest demand
300h of highest demand
Winter with weighting [5,20,40,30,5]%
Winter with weighting [1,8,70,20,1]%
Winter with weighting [2.5,30,55,10,2.5]%
133
CAPACITY CERTIFICATION / 5
> Orders of magnitude are similar in terms of raw results with
a difference of less than 3%. The maximum difference of 3%
corresponds to the winter of 2008, between methods 1 and 4;
> The standard deviation over the five delivery years is compa-
rable (4 GW effective) whatever the method.
Time- and demand-based approaches can then be compared
based on the choice of parameters:
> With a time-based approach, monthly weightings heavily
affect the effective availability of the fleet. The maximum dif-
ference between the methods {4, 5 and 6} varies between
845 MW (winter of 2006) and 2,593 MW in effective value (win-
ter of 2011). The weighting applied thus has a major impact
on the capacity level. This weighting depends on modelling
choices that can have an arbitrary component. For instance,
during the consultation in the first half of 2013, significant dif-
ferences were observed between evaluations conducted by
RTE and EDF using monthly weightings.
> With a demand-based approach, the choice of the number
of hours in the PP2 period has little impact on the effective
availability of the fleet. The maximum difference between
the methods {1, 2 and 3} ranges between 105 MW (winter of
2007) and 1,156 MW in effective value (winter of 2008). This
low level of sensitivity to the number of hours taken into
account is an advantage of this approach and a major fac-
tor of stability.
5.2.4 Approach adopted in the rules
The rules adopt the “demand-based” approach since it presents
the following advantages:
> It ensures consistency between the contribution to reducing
the shortfall risk and the amount of certificates allocated,
notably for capacity available for shorter periods. If a capacity
is available during peak hours, it will receive all the capacity
certificates to which it is entitled. Peak capacity, and particu-
larly peak demand response, is not penalised and given the
same treatment as base/semi-base load capacity;
> It avoids diluting operators’ responsibilities with regard to the
availability of their capacity: in particular, it guarantees that if
load shedding is required due to the unavailability of genera-
tion capacity during the peak period, some capacity portfolio
managers will necessarily show imbalances;
> It is in keeping with the provision of the decree regarding the
principle of non-discrimination between a reduction in the
amount of the capacity obligation due to load reduction and
the certification of demand response capacity;
> It prevents a potential windfall effect for demand response
capacity that could be certified but then declare
itself unavailable (with regard to the certifica-
tion) during PP1 hours while being activated
during these hours. With a period PP2 spanning
the whole winter and a targeted PP1 period, this
capacity would be double remunerated: it will be
rewarded implicitly for being activated during PP1
hours (leading to a reduction in the capacity obli-
gation) and then recognised as certified capacity
(relating to availability). Even if was not available
during PP1 hours, these hours could carry a very
low weighting with a “time-based” approach160,
meaning it could receive almost the full remune-
ration possible as certified capacity;
> It makes capacity and energy signals consistent.
With a time-based approach, capacity subject
to availability constraints could give priority to
months with a very high weighting rather periods
when supply is actually tight.
The studies conducted also provided some insight into the
comparison of the two approaches (see below). The results sup-
port the choice of a demand-based approach.
5.2.5 Notification of PP2 hours
The decree stipulates that there is to be no discrimination
between a reduction of the obligation and certified demand res-
ponse capacity, implying that the PP1 period must be included
in the PP2 period. This is notably necessary to take into consi-
deration the activation of demand response capacity, either in
the certification or the obligation. The notification system adop-
ted for PP1 days is therefore also for the notification of PP2 days.
A large share of PP2 days (at least 40% and potentially as much
as 100%) will consequently be notified on D-1 at 10:30am.
During the consultation, many stakeholders stressed the need
for the capacity mechanism to address periods of tension
beyond those of high demand to comply with the provision
of the decree relating to peak periods: “the hours of a delivery
year during which the shortfall risk is highest, particularly those
during which national demand is highest.”
Consequently, the notification of PP2 days not included in
the PP1 period will be based on a criterion incorporating
data related to demand and tension on the system. This pro-
vision adds flexibility because the projected shortfall landscape
is not set in stone. To factor in tightness of supply, information
160Note: the “time-based” approach involves defining the winter period as the PP2 peak period. Winter hours are weighted with a probability coefficient reflecting the associated level of risk. With this approach, January alone contains between 50% and 70% of the shortfall risk depending on the models used. PP2 hours are thus determined several years in advance, initially as peak hours (morning and evening peaks) on working days in the winter period. The amount of capacity certificates allocated to a capacity is calculated by multiplying its availability in each winter month by the risk coefficient associated with each month.
134
Stan
dard
dev
iati
on (M
W)
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
2,000
2006 2007 2008 2009 2010 2011 Average
Stan
dard
dev
iati
on (M
W)
France BM demandresponse
Wind RoR Hydro Nuclear PV Thermal
0
500
1 000
1 500
2 000
Figure 62 – Variability of eff ective capacity level for France depending on location in time of PP2 days
Figure 63 – Variability of eff ective capacity level for France and per technology depending on location in time of PP2 days (average, minimum and maximum between 2006 and 2012)
Jan. to March & Nov. and Dec.
Jan. to March & Nov. and Dec. with max. 5 d in March and Nov.
Jan and Feb. & Dec.
Jan. to March & Nov. and Dec.
Jan. to March & Nov. and Dec. with max. 5 d in March and Nov.
Jan and Feb. & Dec.
system, RTE will be able to notify PP2 hours as soon as situa-
tions of tight supply are anticipated, i.e. after the network access
deadline time.
5.2.6 Sensitivity of eff ective capacity level to the location in time of PP2 hours
The issue of operators’ visibility on the eff ective capacity level of
their capacities was addressed during the consultation, just as
debates were held about the sensitivity of the obligation to the
will have to be gathered about forecast demand, exchanges
between France and neighbouring countries and capacity avai-
lability. For this purpose, RTE will rely on information gathered
through the programming system. Taking this dimension into
account necessarily puts notifi cation after the economic optimi-
sation of stakeholders’ customer portfolios, which is done after
spot market fi xing. Consequently, PP2 days outside PP1 will be
notifi ed at the latest at 7pm for the following day, leaving at
least 12 hours before the fi rst PP2 hour of the following day. By
using the information made available through the programming
135
CAPACITYCERTIFICATION / 5
location in time of PP1 hours (see chapter 4). Some stakehol-
ders noted that their eff ective capacity level depended in part
on the location in time of PP2, and therefore on eff ective climate
conditions. This could create uncertainty about the amount of
capacity certifi cates operators will receive.
A study was conducted, applying the provisions adopted in the
rules, to test the sensitivity of the eff ective capacity level to cli-
mate scenarios using data from the 2006-2011 period. For each
year, 100 scenarios were considered with diff erent distributions
of PP2 hours, applying 100 consumption scenarios for France
based on the 100 Météo France climate scenarios.
It should be noted that the study overstates the sensitivity we
are seeking to establish. The distribution of PP2 days and the
availability of certifi ed capacities are not independent variables.
Capacity availability depends on demand forecasts and the pro-
jected state of the system, particularly for nuclear power at the
beginning and end of the period. Consequently, if risk realisation
plays out diff erently, generators will adjust the availability of their
capacity accordingly, for instance by postponing scheduled main-
tenance shutdowns. As such, implicitly assuming that the availa-
bility of the capacity certifi ed in 2010 would have been the same
even if weather conditions had been diff erent is an approximation.
The number of PP2 days was set at 25. PP2 days were notifi ed
using two approaches:
> Setting a maximum number of days that could be selected in
March and November;
> Selecting days exclusively in January, February and December.
Figures 62 and 63 show the standard deviation of available
power in France and per technology applying the diff erent
approaches to PP2.
The fi rst conclusion that can be drawn from the study is that the
variability of the capacity level in France is indeed accounted
for primarily by nuclear capacity: the standard deviation of the
capacity level in the nuclear segment corresponds on average
to 90% of the total standard deviation of the total capacity level.
Standard deviations for the hydro and thermal power segments
are nearly three times lower than for the nuclear segment.
Secondly, volatility in the capacity level ranges between 500 and
1,800 MW (between 0.5 and 1.9% of the total capacity level for
France) depending on the provisions adopted for PP2 and the
related signal. By way of comparison, this level of uncertainty is
of the same order of magnitude as the error in demand fore-
casts for the following day during winter peaks.
This study also illustrates the stabilising eff ect of the signal. The
standard deviation decreases by about 20% with a milestone
limiting the number of days in November and March. This stabili-
sing eff ect only has a noticeable impact on the nuclear segment
Nuclear
Max
imu
m a
vaila
ble
pow
er (G
W)
Month
Thermal
November December January February February
60
55
50
45
Nov. Dec. Janv. Feb. March Apr. Nov. Dec. Janv. Feb. March Apr.
25
20
15
10
5
Figure 64 – Trend in average maximum power available on eligible PP2 days
136
and is not constant for all delivery years. Milestones might be
able to attenuate extreme situations but they cannot eliminate
them. The highest variability was seen in the system in 2009,
refl ecting the variability of the actual availability of nuclear capa-
city (standard deviation between 1,100 and 1,500 MW).
These results refl ect the strong seasonality of the availability of
nuclear capacities based on the timing of scheduled shutdowns.
Figure 64 illustrates the change in available power in the nuclear
and conventional thermal segments for the winter of 2010/11;
each dot represents the average over a day, in line with the
methods adopted in the rules (eligible time slot and days).
The availability curve of nuclear capacity is “bell-shaped” and moves
considerably between early November and mid-January (diff erence
of more than 10 GW), whereas the availability of conventional ther-
mal is “fl atter”. The eff ective capacity level of nuclear capacity is
thus much more sensitive than conventional thermal to the num-
ber of PP2 days positioned in November and March.
Some participants in the consultation spoke of the need to sta-
bilise the capacity level via the selection of PP2 days. The idea
was to reduce the weighting of November and March by adding
milestones; some even suggested that no PP2 days should be
selected in these months.
The fi rst point to bear in mind is that the studies cited showed
that these provisions only aff ect the nuclear segment because
of the highly seasonal nature of its availability. And the avai-
lability curve for nuclear capacity must not be considered an
exogenous factor. Operators can adapt the availability of their
capacities on the basis of their consumption forecasts and the
state of the system, particularly at the beginning and end of the
period (for instance by rescheduling shutdowns). Studies based
on actual results therefore overestimate the volatility of capaci-
ties, including nuclear capacities.
Secondly, it is essential that the period during which PP2 days
are selected cover all shortfall risk periods. Diff erent assess-
ments of the shortfall landscape were presented during the
consultation, and all showed a shortfall risk in November and
March. Depending on the estimate used, these months contain
between 2 and 10% of shortfall situations in probabilistic supply-
demand balance studies; the fi gure can rise to almost 50% loo-
king at the records of degraded modes for the supply-demand
balance on the balancing mechanism. The proposal to exclude
March and November from the period during which PP2 days
are selected was therefore not adopted in the rules.
For illustration purposes, the historical distribution of EJP days,
decided by EDF, was analysed from 2004-05 to 2011-12.
The analysis shows that on average, 30% of EJP days were acti-
vated in November and March, with highs of more than 40% in
certain years and a minimum of 10% for all years. A signal sub-
ject to energy constraints (22 days for EJP) requires a conside-
rable volume in November and March for the management of a
portfolio that is preponderant in the French power system.
5.2.7 Provisions adopted in the rules on PP2
The rules defi ne the PP2 peak period as a targeted period corres-
ponding to a limited number of days (between 10 and 25) and a
time slot defi ned applying the “demand-based” approach adopted.
Consistency between PP1 and PP2 is ensured by the fact that
PP1 is included in PP2 (all PP1 hours are PP2 hours). Because PP1
Figure 65 –Distribution of EJP days between 2004-2005 and 2011-2012
0%
10%
20%
30%
40%
50%
Nov. Dec. Jan. Feb. March
Maximum Minimum Average
The rules proposed include a provision limiting the number of PP2 days that can be activated in November and March (maximum 25% of total). This regulates the variability of the capacity level inthe nuclear segment and therefore in the system while ensuring that there are still enough PP2 days to cover most potential shortfall and tight supply situations in these months. The studies pre-sented above give an estimate of the eff ects of this provision (20% attenuation of the variability associ-ated with the location in time of PP2 days).
137
CAPACITYCERTIFICATION / 5
and PP2 volumes are comparable, there is no signifi cant devia-
tion from the principle of non-discrimination between certifi ed
demand response capacity and a reduction of the obligation.
Notifi cation of peak days on D-1 gives stakeholders more visibi-
lity while also allowing information about anticipated situations
of tight supply to be taken into account, which will make it easier
for the mechanism to be adapted going forward (notably to the
changes resulting from the integration of renewable capacities).
Lastly, milestones were introduced in response to requests
by several stakeholders, the goal being to stabilise the capa-
city level for France, and particularly for the nuclear segment,
through the PP2 days selected.
1. The PP2 period corresponds to the time slots [07:00; 15:00[ and [18:00; 20:00[ (i.e. 10 hours per day) of the days notified by RTE.
2. All days notified for PP1 are days notified for PP2 (inclusion of PP1 in PP2).
3. PP2 days are notified on D-1: the PP2 days that are also PP1 days will be notified before 10:30am; PP2 days outside PP1 will be noti-fied at 7pm at the latest.
4. The signal is based mainly on a demand cri-terion (days when demand is expected to be highest) and factors in information about anticipated tension in the system.
5. Between 10 and 25 PP2 days are notifi ed with no more than 25% of them in March and November.
5.3.2.1.1 Kd chart
The Kd chart for a delivery year is based on supply-demand
balance simulations for the delivery year focused on evaluating
the contribution to reducing the shortfall risk of a resource with
a daily energy constraint on a time slot of a PP2 day.
The Kd chart for a delivery year is established by RTE and speci-
fi ed in the rules. This chart is known to operators from the start
of a capacity mechanism term and remains stable throughout.
The Kd chart for the fi rst delivery year is shown below:
5.3 Calculation of the capacity level
5.3.1 Available power of capacity
Available power corresponds to the power that can be activated
during PP2. Data can be gathered about available power either:
> Through a separate system for collecting capacity availability
data that is not directly linked to the capacity mechanism rules;
> Or through a system developed by RTE to fulfi l its role and
responsibilities with regard to implementing the rules.
5.3.2 Determination of the coeffi cient to refl ect the technical constraints of capacity (K)
The formula used to calculate the parameter K is as follows:
K = Kd x Kw
5.3.2.1 Determination of Kd modelling daily energy
constraints
The Kd parameter refl ects the infl uence of the energy constraints
associated with a capacity on its contribution to reducing the
shortfall risk.
The value of Kd is determined from a chart (Kd chart) in force for
the delivery year and from the parameters declared by the ope-
rator (for the calculation of its certifi ed capacity level) or measu-
red (to calculate its eff ective capacity level).
Figure 66 – Illustration of the Kd chart
0%
20%
40%
60%
80%
100%
0 1 2 975 643 8 10
Valu
e of
Kd
(%)
Value of Nd (hours in the PP2 time slot)
138
5.3.2.1.2 Parameters used in the calculation of Kd
The parameters used in the calculation of Kd are as follows:
> EPP2d: Maximum energy activatable on the PP2 time slot
> MaxP: Maximum available power of the capacity
An Nd coeffi cient is calculated from this data as follows:
Nd = min ( EPP2dMaxP
; 10 )The Nd coeffi cient corresponds to the number of hours capacity
can be activated at MaxP per day on the PP2 time slot.
Based on these data and the Kd chart, an operator can estimate
the value of the Kd coeffi cient associated with its capacity.
5.3.2.1.3 Daily constraint and available power
As indicated above, the available power of a capacity corres-
ponds to the power that can be activated on the PP2 time slot.
The daily constraint refl ects the maximum energy that can be
activated on the PP2 time slot.
On a PP2 day, if an operator has activated the capacity and the
energy generated corresponds to the maximum energy decla-
red, it has fulfi lled the commitment in its certifi cation contract.
It is therefore necessary to ensure that the energy constraint is
not counted twice.
In this specifi c case, the formula PP2Available-Power x Kd is replaced by PP2Activation.
5.3.2.2 Determination of Kw modelling the weekly
energy constraint
The value of the Kw coeffi cient is also determined using a chart
(Kw chart) applicable to the delivery year and parameters decla-
red by the operator (for the calculation of its certifi ed capacity
level) or measured (to calculate its eff ective capacity level).
5.3.2.2.1 Kw chart
The Kw chart for a delivery year is based on supply-demand
balance simulations for the delivery year focused on evaluating
the contribution to reducing the shortfall risk of a resource with
an energy constraint over several consecutive days of the deli-
very period.
This chart is known to operators from the start of a capacity
mechanism term and remains stable throughout.
The Kw chart adopted in the rules for the fi rst delivery year is
shown below:
5.3.2.2.2 Parameters used in the calculation of Kw
The parameters used in the calculation of Kw are as follows:
> EPP2d mentioned for the calculation of Kw
> wE: energy that can be activated over fi ve consecutive wor-
king days on the time slots [07:00-15:00[ and [18:00; 20:00[
The approach diff ers however from the one used for Kd in the
sense that data is not measured over PP2 days but monitored
more broadly over the delivery period.
An Nw parameter is calculated from this data as follows:
Nw = min ( wEEPP2d
; 5 )Nw corresponds to the number of working days during which the
capacity can be activated taking into account its daily constraint.
Based on these data and the Kw chart, an operator can estimate
the value of the Kw coeffi cient associated with its capacity.
5.3.2.3 Illustration of how the Kd coeffi cient is
determined for capacity
The information below is provided purely for illustration
purposes.
For capacity with available maxP of 100 MW, maxE,d of 400 MWh
and no energy constraint (meaning it can be activated every day
of the delivery period):
Nd = 400100
hours per day at maxP during hours of the PP2 time slot
The value of the Kd associated with a capacity is calculated as:
Kd (4) = 70%
Figure 67 – Illustration of the Kw chart
0%
20%
40%
60%
80%
100%
0 1 32 4 5
Valu
e of
Kw
(%)
Value of Nw (number of consecutive days)
139
CAPACITYCERTIFICATION / 5
0%
20%
40%
60%
80%
100%
0 1 2 975 643 8 10
Valu
e of
Kd
(%)
Value of Nd (hours in the PP2 time slot)
Figure 68 – Determination of the Kd coeffi cient for a capacity
5.4 Certifi cation requests
Certifi cation requests can be fi led for capacity once the capa-
city mechanism term starts, i.e. when the register is opened for
the delivery year in question following the publication of the
mechanism parameters (possibly including updated certifi ca-
tion charts); requests can be fi led for planned capacity based on
a predefi ned specifi c technical milestone.
5.4.1 Defi nition of capacity
5.4.1.1 Capacity status
Under the terms of the decree, deadlines are set for certifi cation
requests “based on the technical characteristics of the capacity
and, for new capacity, based on the status of the project” (para-
graph I of article 8 of the decree). The rules must therefore make
it possible to defi ne the technical characteristics to be taken into
account for setting certifi cation request deadlines.
The status of capacities (existing or new) also has an impact on
the security deposits required. The decree specifi es that “the
certifi cation contract includes […], where appropriate, especially
for new capacities, the amount of the security deposit to be pro-
vided by the operator” (paragraph III of article 9 of the decree).
The rules factor in this requirement that security deposits be
provided for planned capacity for each delivery year for which
certifi cation is requested. Security deposits are only returned
when the capacity is brought into service.
5.4.1.1.1 Existing capacity / new capacity
Under the terms of the decree, existing capacity is capacity that
is included within a certifi cation entity for a future, present or
past delivery year. New capacity is capacity that has never been
part of a certifi cation entity.
5.4.1.1.2 Operational capacity/planned capacity
Capacity can be certifi ed several years before the delivery year.
It is possible for capacity to be considered existing capacity, as
defi ned in the decree, but still in the project phase. The terms
above (existing capacity/new capacity) are applied to the certi-
fi cation process, and particularly to the certifi cation entity. They
do not specify whether the capacity exists or not. For instance,
a capacity may be certifi ed for the fi rst time three years before
becoming operational; it is in this case considered existing capa-
city for the following delivery year, but is still planned capacity
until industrial operations begin.
A distinction must therefore be made between capacities that
are operational and those still in the project phase. All capacity
that is operational for a delivery year must have a certifi cation
contract for that delivery year.
5.4.1.2 Nature of capacities
It is essential that the addition (new capacity) and removal
(decommissioning) of capacities be properly accounted for in
140
the mechanism. The mechanism is intended to achieve the level
security of supply desired by public authorities, but it must not
create an entry barrier for new capacity or reward “phantom”
capacity.
Two risks relating to planned capacities have been identified:
> Projects might not be completed: the risk is that projects
may be postponed or cancelled even though the capacity is
necessary to guarantee security of supply. This creates a risk
of default by an operator that has sold certified capacity;
> If planned capacities are not taken into account, then the
investment signal will be meaningless.
Essentially, there are two possible approaches to this issue: one
involves certifying all planned capacity declared, with significant
financial guarantees required in exchange; the second involves
physical verifications of capacity, in which case the financial gua-
rantees demanded can be lower since the risk is lower.
5.4.1.2.1 Generation capacity
5.4.1.2.1.1 Operational generation capacity
Using the definitions given at the beginning of this section, any
generation site covered by a network access contract or calcula-
tion service contract is considered operational generation capa-
city. For the first delivery year, any generation site with either
type of contract in force as of 1 November 2014 is also counted
as existing generation capacity.
Existing generation capacities will be certified once the mecha-
nism term starts, and this will provide additional information
about the state of the fleet, above and beyond what is included
in adequacy studies based on the declarations made by genera-
tors (a certification request indicates that the generator plans to
be present during the delivery year).
5.4.1.2.1.2 Planned generation capacity
As discussed above, there is often uncertainty about when plan-
ned capacities will become operational. With this in mind, the
rules adopt a proposal that sets the certification deadline as
close as possible to the delivery year, to ensure a high probability
that the underlying capacity project will be completed.
5.4.1.2.2 Demand response capacity
The Energy Code stipulates that “certification requests must be
submitted by operators for all demand response capacity” (Art.
L321-16). As written, this provision is difficult to put into prac-
tice. Technically, any consumption site with a circuit breaker can
reduce its load, but all consumers cannot be obliged to request
certification.
A proper definition of “demand response capacity” must there-
fore be used for the specific purposes of certification: demand
response capacity is a demand response capability (flexibility)
that has been certified as such. Applying this principle, it is pos-
sible to accurately define operational demand response capa-
city and planned demand response capacity.
5.4.1.2.2.1 Operational demand response capacity
Operational demand response capacity is an existing extraction
site or group of extraction sites constituting a certification entity
for a given delivery year.
The operator of operational demand response capacity can only
declare certification parameters (available power and data used
for the calculation of K) on the basis of the extraction sites that
are affiliated with it when the certification request is made.
5.4.1.2.2.2 Planned demand response capacity
Planned demand response capacity refers to the planned peri-
meter of extraction sites declared by the capacity operator and
constituting a certification entity for a given delivery year.
The operator of planned demand response capacity can declare
certification parameters (available power and data used for the
calculation of K) on the basis of the extraction sites affiliated with
it when the certification request is made and its forecasts regar-
ding future changes in the perimeter.
Certification of planned demand response capacity requires a
security deposit.
5.4.1.3 Aggregation methods
5.4.1.3.1 Aggregation thresholds
The rules specify how different capacities can be aggregated
within a certification entity. For aggregated capacities, only
one certification request is filed and one certification contract
issued.
This is in keeping with the provision of the decree stating that
“The methods of certifying and verifying capacities making a
limited contribution to security of supply be adapted accor-
dingly” (paragraph 1 of Art. 10). The decree specifies that
“requests for certification of such capacities can only be made
in aggregated form” (paragraph II of Art. 10). In the rules, the
141
CAPACITY CERTIFICATION / 5
individual volume of capacities is adopted as the technical
characteristic used to determine to which capacities these
provisions apply.
Capacities with a power rating of less than 1 MW must be aggre-
gated with one or more capacities of the same type (generation
or demand response) to constitute a certification entity with
total power of at least 1 MW.
Some stakeholders indicated during the consultation that they
needed to be able to aggregate capacities beyond the sprea-
ding of imbalances ensured by capacity portfolio manager peri-
meters. The idea is to take into account technical characteristics
such as rotating activations of individual capacities for demand
response or mutual influence for hydro capacities.
A threshold was therefore introduced in the rules. Aggregation is
possible for capacities with individual power of at least 1 MW and
no more than 100 MW.
Capacities with power ratings of 100 MW or more must be certi-
fied individually: every capacity with a power rating of 100 MW or
more must form its own certification entity. The same 100 MW
threshold is applied in EU regulation 543/2013 of 14 June 2013,
the “transparency regulation”.
The minimum threshold of 1 MW is consistent with the target
level of detail of offers on the balancing mechanism for 2016
(the threshold is in the process of being lowered from 10 MW
to 1 MW).
5.4.1.3.2 Capacity aggregation perimeter
The Energy Code stipulates that certification requests must be
filed for all generation and demand response capacities. Under
the rules, aggregated sites forming part of the same certifica-
tion entity can be connected to different networks, in keeping
with the work being done to update the balancing mechanism
and eliminate technical barriers to aggregation. This provision
means that RTE must centralise the certification data for these
sites. It avoids segmenting capacities based on the system
operators with which they are affiliated, and thus an external
constraint serving no economic purpose for operators.
The certification of certification entities comprising sites
connected to different networks, together with a mandatory
aggregation threshold of 1 MW, ensures that capacities partici-
pate. It reduces the risk of overcapacity that could arise if some
capacities were not taken into account.
5.4.2 Certification deadlines
The certification deadlines set represent a compromise between
two contradictory goals:
> One was to give stakeholders as much visibility as possible on
the future state of the system. This would imply setting the
certification request deadline well ahead of the delivery year;
> The other was to factor in the maximum amount of capacity
that can be activated, including in the short term, to avoid the
extra cost of building new capacities that are not needed to
achieve the desired level of security of supply.
5.4.2.1 Existing generation capacity
The deadline for requesting certification of existing generation
capacity depends on whether it is already operational or in the
project phase:
> Existing generation capacities that are operational must ask
to be certified by 1 November of DY-3 (i.e. three years before
the delivery year);
> Existing generation capacities in the project phase must ask
to be certified by 1 November of DY-1 (i.e. one year before the
delivery year)
For existing generation capacities that are operational, setting the
deadline three years before the start of the delivery year may seem
like a constraint in that operators must submit availability forecasts
for their capacity. But the rebalancing system adopted eases this
constraint. Players must also have sufficient visibility on projected
capacity levels for the market to function properly (see chapter 7).
Figure 69 - Illustration summarising the aggregation thresholds adopted in the rules
Aggregation possible
Aggregation compulsory
1 MW threshold
100 MW threshold
No aggregation possible
Volume of capacity unit (MW)
142
For this reason, three years before the delivery year, system capaci-
ties will either be certified and recorded in the capacity register or
considered absent and ineligible to participate in the mechanism at
a later date (they will have been required to submit an irrevocable
closure notice). These procedures are a powerful tool for monito-
ring market manipulation and can be compared to some measures
applied in North American capacity markets, where the behaviours
of existing capacity during capacity auctions are closely monitored.
Specific procedures are nonetheless being planned for capacities
that are in the process of being mothballed (see § 5.4.3.2).
The difference between the amount of capacities in the register
and the forecasts published by RTE relating to the total certificates
required for all stakeholders to meet their obligation will give opera-
tors valuable insight for their forecasts on situations of tight supply.
5.4.2.2 Demand response capacity
The deadline to request certification for demand response capa-
city is set at the beginning of the delivery period.
Demand response capacities are given more flexibility to take
into account i) the fact that they can be developed or removed
shortly before the start of the delivery period, and ii) the fact that
extraction sites have less visibility on their order books and thus
their ability to adjust their consumption. This flexibility also helps
put into practical application the provision in article 13 of the
Brottes Act of 15 April 2013 stating that, if costs are the same,
priority should be given to demand response capacities.
5.4.2.3 New capacity
5.4.2.3.1 Planned capacity
An operator of a capacity in the project phase can request to
have it certified up to two months before the beginning of the
delivery period, i.e. up to 1 November of DY-1. For generation
capacities, the connection agreement must also be signed.
5.4.2.3.2 Operational capacity
Requests to certify new operational capacity must be submitted
within two months following the commissioning date and two
months before the beginning of the delivery period.
5.4.2.4 Overview of provisions adopted for certification
request deadlines
Once the system is established, i.e. as of the third delivery year,
the certification request deadlines will be as follows:
Summary of certification request deadlines
Generation Demand response
Operational capacity 2 months before the start of the delivery period in DY-3, i.e. 1 November DY-3
2 months before the start of the delivery period, i.e. 1 November DY-1Planned capacity 2 months before the start of the delivery
period, i.e. 1 November DY-1
The rules include specific certification request deadlines for the first two delivery years:
> For the first delivery year
> For the second delivery year
Generation Demand response
Operational capacity 1 November 201531 August 2016
Planned capacity 31 August 2016
Generation Demand response
Operational capacity 31 December 201531 October 2017
Planned capacity 31 October 2017
143
CAPACITY CERTIFICATION / 5
5.4.3 Withdrawals of capacities
The way a mechanism accounts for “withdrawals” of capacities is
key to its performance. This is especially important for France, given
the situation described in section 1.2.3 of this report: the introduc-
tion of a capacity mechanism in France is seen as a means of regu-
lating the shift from the historical situation characterised by excess
capacity to a new configuration characterised by risks that the
security of supply criteria defined by public authorities may not be
met. The capacity mechanism will be implemented at a time when
some operators are considering shutting down or mothballing cer-
tain facilities, but could reconsider in the light of the value of certi-
ficates on the capacity market. The way in which units that could
otherwise be shut down temporarily or for good are integrated into
the capacity mechanism is therefore all-important.
The specific question of the fate of capacities that have already
been mothballed was also addressed during the consultation.
These capacities could indeed be fired up again if a system need
was identified, and it could cost less to bring them back into ser-
vice than to develop new ones. In the meantime, temporary shu-
tdowns could be appropriate if market prices are low (operators
save on some operating costs when capacities are mothballed).
Improper management of the provisions applicable to these capa-
cities could disrupt the functioning of the market, or even lead to
behaviours constituting manipulation. If it was possible for any ope-
rator to decline to participate in the mechanism initially because
it might mothball its capacities, the system could be vulnerable to
“capacity retention” behaviours - with some operators voluntarily
drying up supply to artificially inflate the price. Even though capa-
city certificate trading will be closely monitored when the mecha-
nism is in place (see chapter 7), the rules governing the mecha-
nism’s functioning must protect the community from these types
of behaviours by making them visible and inefficient.
5.4.3.1 Closure notices
The first rule governing “withdrawals” involves requiring closure
notices for capacity to not participate in the mechanism. Prepa-
red by operators, these notices specify the duration of the clo-
sure, which must cover at least the delivery year considered and
at least three years total for generation capacities and at least
one year for demand response capacities.
This provision is in keeping with the decree, which stipulates that
all existing capacities, whether generation or demand response,
must either request certification or submit a closure notice by
the certification deadline. Capacity for which a closure notice
has been filed for a delivery year is no longer eligible to be issued
capacity certificates: it is definitively excluded from the mecha-
nism for the current year and at least the next two years. The pro-
vision thus incentivises capacity operators to establish forecasts
for their capacity and convey this information to the market; it
makes strategies involving holding back supply citing potential
closures less efficient since, for the capacity in question, opera-
tors cannot take advantage of the price increase their retention
strategy could cause. Moreover, the transparency and monitoring
measures discussed in chapter 7 of this report ensure that any
capacity retention strategy implemented by an operator with
several capacities will be detected and sanctioned.
5.4.3.2 Mothballed capacities
Given the specific characteristics of the French security of sup-
ply landscape, a special system has been introduced for moth-
balled capacities. Under this system, an operator can participate
in the mechanism by using the rebalancing procedure to buy
or sell the corresponding capacity certificates if it provides the
Energy Regulatory Commission with prior notice and specific
documentation, in the format specified in the rules. In concrete
terms, mothballed capacity can participate in the mechanism
by being reactivated between the certification deadline and
the delivery year (in a sense, it has an option to participate in
the mechanism). Likewise, a decision can be made to mothball
capacity between the certification date and the delivery year.
To participate in the capacity mechanism, the operator of capa-
city that has been mothballed must request certification by the
certification deadline, declaring a certified capacity level equal
to 0. If, based on market conditions, the operator subsequently
decides to reactivate the capacity, it must rebalance upward.
There are no costs associated with rebalancing before the
start of the delivery period (except the cost of the certification
request), as explained in the next chapter.
Basically, an operator can decide to mothball a facility after the
certification deadline by rebalancing back to zero. It will in this
case have to return the amount of capacity certificates corres-
ponding to the capacity initially certified through the procedure
outlined in the next section.
In both cases described above - if certification is requested or
the capacity level is rebalanced back to zero - operators must
submit documentation explaining the technical and economic
reasons and specifying how long it would take for the capacity to
be reactivated. This documentation is sent to the Energy Regu-
latory Commission, which is charged with overseeing markets
144
The certification procedures adopted make operators res-
ponsible for imbalances between the level of availability they
indicate when certifying their capacity and the effective availa-
bility of their facilities verified during the delivery period. Such
an accountability system only makes sense if operators have
options to manage the risk. Rebalancing is one tool at their dis-
posal: as the delivery year approaches, operators will have more
accurate information about the future availability of their facili-
ties, and by rebalancing they can modify the reference used to
calculate their imbalance.
The procedures involved in rebalancing are thus a core aspect
of the mechanism’s functioning: the more onerous rebalan-
cing is, the more committed operators will be to the availability
forecasts provided on the certification deadline (three years
before the start of the delivery year for generation capacity);
conversely, if there was no cost involved in reba-
lancing, then operators would not be bound by
the availability forecasts submitted ahead of time,
and the information originally recorded in the
register may be of less value, which is why appro-
priate transparency and oversight measures are
necessary.
by article L. 131-2 of the Energy Code. In sum, the procedures
for entering and exiting the mechanism are tightly regulated.
In practice, the capacity mechanism can significantly influence
operators’ decisions about mothballing or reactivating certain
facilities. And these decisions impact all stakeholders, given the
key role they play in shaping the market price for all capacity (this
effect is notably visible in North American markets). As a result,
maximum transparency is required about the amount of capacity
mothballed. This is why the rules stipulate that specific informa-
tion will be included in the certified capacity register about the
number of facilities mothballed and their historical capacity levels.
All operators should be able to use this information to determine
how many capacity certificates might be returned into the system.
5.4.4 Certification fees
Several options are possible for invoicing certification fees: they
can be calculated per MW certified, per certification entity, based
on the number of sites, etc. With the industrialisation of the cer-
tification process, most costs will correspond to operational
maintenance costs for IT systems. The number of sites or certifi-
cation entities is thus not a discriminating factor: the number of
certificates is what counts.
The rules therefore stipulate that the scale will be defined
in euros per MW certified. A different approach to invoicing
(for instance indexation to the number of sites) would have
been unfavourable for aggregation, and this would have gone
against the objective of giving priority to demand response
defined by publication authorities in the Brottes Act161. It
would also have been detrimental to new entrants with smal-
ler capacities.
Certification fees are also set in the rules. The values proposed
are 6 euros per MW certified for RTE and 57 euros/MW for distri-
bution system operators.
161Article 13 of this act, now article L. 335-2 of the Energy Code, affirms that “At equal cost, [the capacity mechanism] gives priority to demand response capacity over generation capacity.”
5.5 Rebalancing
5.5.1 The rebalancing process
Rebalancing is the mechanism that ensures consistency
between the market and the physical reality. The rebalancing
mechanism proposed allows an operator to submit a rebalan-
cing request as soon as a contingency occurs that impacts its
effective capacity level. The price of rebalancing must incenti-
vise operators to take action as soon as they observe a discre-
pancy between their expected effective capacity level and their
certified capacity level. The mechanism thereby guarantees that
capacity supply in the market corresponds at all times to the
best estimate of the effective capacity level.
The rules define rebalancing as the process by which a capacity
operator modifies the capacity certification parameters it decla-
red, resulting in a fresh certification of the capacities in question
(in other words a new certification contract is established) which is
recorded in the certified capacity register for transparency’s sake.
There are two types of rebalancing:
> Upward rebalancing, resulting in the issue of new capacity
certificates;
> Downward rebalancing, after which capacity certificates are
returned.
145
CAPACITY CERTIFICATION / 5
Rebalancing requests are accepted between 1 January of year
DY-4 and 15 January of year DY+1. The capacity portfolio manager
submits a rebalancing request to the transmission system ope-
rator for a capacity within its perimeter. Rebalancing requests
generally include:
> A new certification application with updated technical
parameters;
> The signed consent of the holder of the certification contract
for the capacity;
> Documentation of technical justifications;
> For capacities with certified capacity levels exceeding 100 MW,
a declaration of change in parameters.
Rebalancing requests may also be submitted for modifications
resulting from the constitution of demand response capacity
(change in the perimeter of the extraction sites covered).
5.5.2 Financial consequences of rebalancing
It is proposed in the rules that rebalancing be free of cost
between the start of the mechanism term (four years before the
start of the delivery period) and the start of the delivery period
and then rise incrementally after that. This choice is all-impor-
tant in determining how the mechanism will function: in sum,
the projected capacity level declared by an operator with its ini-
tial certification request is not binding and may be modified over
the following three years with no penalty. If its availability fore-
casts change during these three years, an operator will only pay
the transaction costs associated with rebalancing to modify its
declaration, which is what makes the procedure efficient. Many
generators and demand response operators requested this type
of flexibility during the consultation.
5.5.2.1 Absence of rebalancing costs before the delivery
period starts
As indicated above, the absence of rebalancing costs before
the delivery period begins has a major advantage: the certified
capacity register is not “set in stone” several years in advance,
nor is the certificate price that will be calculated on this basis.
This ties back in with the general debate discussed in chapter
3 about the compromise between the stability and accuracy
of the mechanism signals: while “closing” the register several
years ahead of time would certainly afford more visibility on
the capacity price, the economic value of the signal would
be reduced since it would not factor in information about the
projected supply-demand balance that becomes available
between the start of the term and the start of the delivery
period.
This choices makes it essential to guarantee a high level of
transparency with regard to the registers and systematic
monitoring of the market by the competent authorities. The
measures adopted, which are discussed in more detail in
chapter 7, appear sufficient to prevent operators from sub-
mitting frivolous initial declarations that could impact the tru-
thfulness of the market and interfere with price formation: any
strategy involving the deliberate declaration of projected avai-
lability that does not match up with historical levels or com-
parable capacities will easily be spotted by other stakeholders
and CRE. And with the procedures for submitting rebalancing
requests adopted in the rules, operators must systematically
justify their requests, which provides an additional verification
tool for relevant authorities to use.
PP2
Start of term(01/01/DY-4)
Rebalancingcost
Zero rebalancing cost Progressive rebalancing costaccording to numberof PP2 days elapsed
Start of deliveryperiod
(01/01/DY)
End of deliveryperiod
(31/12/DY)
PP2
Figure 70 – Cost of rebalancing depending on timing
146
5.5.2.2 Progressively increasing imbalance
settlement prices after the delivery period starts
Rebalancing guarantees that market signals are
consistent with the physical situation. It must be
possible for information about contingencies, inclu-
ding those that arise during the delivery period, to
be conveyed to the market through rebalancing.
This is why rebalancing is authorised until the end of
the delivery period.
However, it does not make sense for the cost of
rebalancing to be nil as the delivery period begins.
In order to give stakeholders incentive to commu-
nicate any new information they have about their effective
capacity level to the market as quickly as possible, rebalancing
must take into account the value associated with the timing of
rebalancing requests. It is therefore proposed that the rebalan-
cing price will increase progressively over the delivery period,
as PP2 days elapse. For a same contingency, an operator that
rebalances earlier will be subject to a lower settlement than one
that rebalances later.
To encourage stakeholders to accurately disclose their imba-
lance situations, the rebalancing price must be defined in such a
way as to provide an incentive to opt for rebalancing rather than
a settlement and to rebalance as soon as a contingency arises
affecting a capacity level.
The desired incentive structure can be visualised using a simple
example. The situation of a capacity portfolio manager with a
negative imbalance of ΔV<0 that waits for a settlement is com-
pared with that of a stakeholder that rebalances.
When the capacity portfolio manager waits for the settlement,
the cost associated with its imbalance is:
CostImbalance settlement
= – ∆V x (1 + K) x MarP
If the stakeholder rebalances, it must buy back the missing
certificates on the market at the MarP price (or, if it has not
yet sold them, this will represent its cost of opportunity) and
then rebalance the amount ∆V. The total cost for this stake-
holder is:
CostRebalancing
= – ∆V x MarP + I∆VI x Crebal
To ensure that rebalancing is more advantageous regardless of
the market price during a given delivery year, the rebalancing
cost must be structured in the same way as the imbalance sett-
lement price for capacity portfolio managers, i.e. around the
market price. It is therefore proposed that:
Crebal
= krebal
x MarP
To guarantee that the CostImbalance settlement is always
higher than the CostRebalancing, it is therefore necessary that:
krebal
< K
This result is illustrated below:
Initial situation
Certifiedcapacity
levelEffectivecapacity
level
∆V∆V x (1+K) x marP
-∆V x (1+K) x marP -∆V x (1+krebal.
) x marP
x marP x krebal.
x marP∆V ∆V
Imbalance settlement Rebalancing
RebalancingPurchase ofcertificates
on the market
+
Figure 71 – Illustration of relationship between rebalancing and imbalance settlement
162These principles are without prejudice to changes made subsequently to the balancing mechanism in application of the Network Code currently being drafted in application of EU Regulation 714/2009 of 13 July 2009.
163This is a legal requirement for generators connected to the public transmission system and optional for others.
147
CAPACITYCERTIFICATION / 5
Formulaefordeterminingthesettlementforrebalancingbyacapacityportfoliomanager
The amount of the settlement associated with rebalancing by a capacity portfolio manager is calculated with the following
formula:
SettlementRebalancing,CPM = ∑ Volume
Rebalancing,request x UnitPrice
request
The amount of a rebalancing request is the diff erence, in absolute value, between the certifi ed capacity level as of the rebalan-
cing request date (datereauest
) and the capacity level shown in the rebalancing request. It is calculated as follows:
VolumeRebalancing,request
=
I Certifi edLevelcapacity
(daterequest
) – CapacityLevelrequest I
The unit price of a settlement for a rebalancing request depends on when it is submitted. It is calculated as follows:
UnitPricerequest
(daterequest
) = rmP x KDY
x NbPP2daysnotifi edDY(daterequest)
NbPP2daysnotifi edDY(FPL)
> rmP: reference market price used to determine the unit price for the imbalance settlement (see chapter 6);
> KDY: The incentive coeffi cient K for the delivery year used for settlements (see chapter 6);
> NbPP2daysnotifi edDY
(d): Number of PP2 days notifi ed for the delivery year between the start of the delivery period and the
request date d.
A unit price of zero is thus applied to settlements for rebalancing requests submitted before the date the delivery year begins.
compliant rebalancing
requests,CPM
5.6 Collection of data required to calculate effective capacity level
Since declarations are the cornerstone of the certifi cation pro-
cess under the approach adopted, the eff ective availability of
capacities must be systematically verifi ed (along with the other
parameters used). This verifi cation process necessarily requires
going through appropriate channels to systematically collect
data that can attest to the availability of capacities. This is one of
the reasons why mechanisms that remunerate available capa-
city (rather than installed capacity), which are economically pre-
ferable, are sometimes considered costlier to implement.
It is easy to calculate the availability of generation and demand
response capacity on power systems organised according to a
mandatory pool scheme: North American capacity mechanisms
(PJM, New England, New York) are for instance organised around
a pool structure in which all transactions must be either centra-
lised or reported to the system operator. This type of scheme is
not generally not used in Europe when a separation has been
created between the functions of the network operator and the
day-ahead market operator: specifi c procedures for verifying
availability must in this case be implemented.
However, through the balancing mechanism, France already has
a means of gathering much data that can attest to the availabi-
lity of facilities, whether they are connected to the transmission
or distribution networks. In other words, the French balancing
mechanism is not just a venue for activating energy and making
the adjustments necessary to guarantee equilibrium in real time;
it is also used to verify the availability of each facility connected
to the public transmission system and of many units connec-
ted to the public distribution systems to evaluate the operating
margins of the system162. This unusual organisation is centred
round a programming process under which generators163 report
148
their technical constraints and dispatching schedules to RTE
one day ahead at 4pm and declarations are regularly updated
after that through a series of rebalancing gates. The advantage
of this system is that available reserves can be better evaluated,
allowing the system operator to fine-tune its efforts.
Relying on the balancing mechanism to collect data about
availability and carry out verifications would thus be an obvious
option in France, since the mechanism exists and has proved
its worth. This organisational structure would save on costs
that would otherwise be generated by the implementation of
new verification measures. The data collection and verification
mechanism RTE proposes would thus rely whenever possible
on the balancing mechanism, in the interest of technical and
economic efficiency.
As regards the explicit certification of demand response capacity,
extensive discussions were held about how to gather information
about capacity availability. Here again, it would be possible to leve-
rage existing systems, notably the NEBEF mechanism, through
which activated demand response capacity can already be eva-
luated a day ahead, and it could be expanded to allow information
to be gathered about the availability of non-activated NEBEFs.
Other data will also have to be gathered through ad hoc mecha-
nisms (maximum daily energy that can be activated during PP2
peak hours, maximum weekly energy) that will cost less to create
if they are designed as extensions of the balancing mechanism.
5.6.1 Linking of certification entities with BM and NEBEF entities
With the chosen option of using existing systems to collect and
verify data about capacities, the links between the aggregates
used for certification purposes in the capacity mechanism (cer-
tification entities) and existing procedures for identifying facili-
ties and sites on the balancing mechanism (balancing entities)
or the participation of demand response in the market (NEBEF)
(demand response entities) must be properly defined.
The rules must also seek to reduce any potential
entry barriers and plan a specific regime for demand
response from the outset.
The capacity mechanism rules do not impose equiva-
lence between certification entities and these entities
(balancing and demand response entities), as this could
make these mechanisms more rigid and less efficient.
However, to ensure that the data necessary to calculate the effec-
tive capacity level and accurately verify capacity164 is collected effi-
ciently, the rules define the combinations that are possible between
certification entities and balancing and demand response entities,
applying a simple principle: all sites that are part of the same balan-
cing entity or demand response entity must either belong to the
same certification entity or belong to certification entities that are
affiliated with the same capacity portfolio manager.
The rules include a specific treatment demand response:
1. A demand response certification entity is strictly equivalent to
one or more entities (balancing entity or demand response entity).
2. A demand response certification entity can modify its consti-
tution (i.e. the sites it comprises).
This flexibility afforded to demand response in creating certifi-
cation entities (2) offsets the strict equivalence constraint (1).
It is justified by the fact that the composition of balancing enti-
ties and demand response entities changes very frequently, and
their contractual ties with extraction sites must be able to evolve
with them. For generation capacity, the flexibility afforded by the
absence of the strict equivalence requirement makes it possible
to address situations where relevant data for certain facilities
(hydro capacities for instance) are only available on a broader
scale than the certification entity (entire hydropower valley).
The method adopted for linking certification entities and balan-
cing/demand response entities (or the absence of linking)
affects the procedures used to collect and verify capacity data.
The way the activatable power of demand response capacity
is collected will typically differ depending on whether it parti-
cipates in the balancing mechanism. At the same time, capa-
city that does not participate in any of these mechanisms can
only be rewarded for the power activated, in keeping with the
mechanism objectives.
5.6.2 Collection of activated power data
The collection of activated power data is based:
> For generation capacities, on metering data for injections to
the public transmission and distribution systems;
> For demand response capacities, on the results of the load
reduction verification methods put into place on the NEBEF
and balancing mechanisms.
Records, in MW, of the participation of capacities in primary and
secondary system regulation are incorporated into the calcula-
tion of activated power.
164In filing a certification request, the capacity operator just indicate specific combinations for its capacity, which must be active during the verification. If a capacity does not comply with the configuration requirements, the data collected and verified shall be considered null.
149
CAPACITY CERTIFICATION / 5
5.6.3 Collection of activatable power data
The collection of activatable power data is based on:
> Upward offers made on the balancing mechanism for capaci-
ties participating in it;
> A specific system incorporating the methods of rewarding
demand response on energy markets for demand response
capacity not participating in the balancing mechanism. This
system relies on declarations by demand-side operators,
notably containing:
• The sheddable load record that will be taken into
account as activatable power for the share not effectively
activated;
• The technical and economic conditions for activation,
particularly the price above which the capacity will be
activated;
• The demand response entities concerned.
The first declaration submitted through this system must be
received by 11am.
5.6.4 Collection of maximum energy data for PP2 days
The collection of maximum energy data for PP2 days is based
on existing systems, notably the balancing mechanism, but
additional information is required from operators
to account separately for the hours during which
shortfall risks are the greatest. Indeed, “maxE” decla-
rations made on the balancing mechanism may
cover a whole day, whereas the capacity mecha-
nism targets a specific time slot. Basically, capaci-
ties that are available and activatable outside these
hours do not contribute to reducing the shortfall
risk, and this must be reflected in their effective
capacity level.
5.6.5 Collection of weekly maximum energy data
New systems will have to be implemented to collect weekly
maximum energy data. The existing systems cover a one-day
window and weekly maximum energy does not correspond to
the sum of daily maximum energies of the days making up the
week165.
To this end, operators will have to submit new declarations on
their energy stocks. The type of information required is similar
to that provided with certification requests to justify declared
values (one example would be upstream reservoir levels repor-
ted for hydro capacity).
165The value of the daily maximum energy depends on the activations of previous days. Concretely, a capacity that can only be activated one day a week can declare, each day of the week, a daily maximum energy corresponding to a stock covering one day if it is never activated. If the weekly maximum energy was calculated as the sum of the daily maximum energies, it would then correspond to a possible activation for five days in a row.
5.7 Capacity verification
The importance of verifications in a system relying on declara-
tions with controls after the fact was discussed at the beginning
of § 5.6. In drafting the rules, RTE focused on proposing control
procedures that (i) allow for an efficient verification of the effec-
tive availability of capacities and their contributions to reducing
the shortfall risk, (ii) are extensions of existing systems, as this
minimises costs, and (iii) create possibilities for new entrants
to effectively compete with existing capacities, notably in the
demand response sector, in keeping with the objectives outli-
ned in § 1.4.
The first criterion for evaluating verification procedures is their
efficiency in safeguarding security of supply and ensuring that
each capacity is rewarded in proportion to its contribution to
security of supply:
> Verifications must prevent the appearance of “phantom” capa-
cities (capacities that exist only on paper and cannot contribute
to security of supply): therefore, all capacities must have been
activated at least once by the end of the delivery period;
> It must also be possible to use verifications to establish whe-
ther operators have met their availability commitments: verifi-
cations of capacity must therefore be systematic.
The second criterion is that verification procedures must be
extensions of existing mechanisms for gathering data. This ties
in directly with the choices discussed in § 5.6, i.e. the priority
given to using the balancing and NEBEF mechanisms as the
main channels for gathering and checking data. Introducing
new verification mechanisms that are not extensions of existing
ones would inevitably drive up the costs associated with the
mechanism’s implementation.
Thirdly, verification procedures must not, generally speaking,
create entry barriers. In the particular case of demand response,
150
which public authorities have opted to promote as a structu-
ral response to the need to ensure long-term equilibrium in
the power system, barriers to aggregation must be abolished.
Any inconsistent or redundant verification measures applied
to demand response entities would be a step backward with
regard to the progress made in France since 2010. This is why
RTE is proposing that verification not be fragmented beyond the
certification entity level:
> If a capacity (certification entity in this context) is connected
to only one public system (for instance one PDS), verification
will be ensured by the corresponding system operator, as part
of the responsibilities entrusted to it in the decree;
> If a capacity (certification entity) comprises facilities or sites
connected to several public systems, verification will be ensu-
red by RTE, though the data relating to each capacity will be
conveyed through the relevant system operators.
The role assigned to distribution system operators in terms of
verification must be considered in the light of the Competition
Authority opinion of 20 December 2013, which, on the related
subject of the “demand response” decree provided for in the
Brottes Act of 15 April 2013, suggested that distribution system
operators should not take part in verifications of demand res-
ponse. The rules proposed by RTE comply with the decree of
December 2012, which specifically gives these operators an ope-
rational responsibility in verification, and take the Competition
Authority’s opinion into account whenever possible.
The sections below outline the verifications the rules provide for
in accordance with these principles, from the certification request
stage all the way through to the delivery period concerned.
5.7.1 Initial consistency check at the time of certification
When a capacity certification request is received, a series of
consistency checks is carried out to verify the information
declared by operators, notably focusing on:
> Compliance of the data used to identify existing capacities
(e.g. CARD or CART contract);
> Compliance of the estimated available power of the capacity,
which cannot be greater than (i) the sum of the Net Continuous
Power values of the production sites of a generation capacity or
(ii) the sum of the subscribed power values of extraction sites for
existing demand response capacities.
5.7.2 Verification of certified intermittent capacities under the normative approach
The verification procedure applied to operators that have opted
for the normative approach described in § 5.1.2.1.3 (neutrali-
sation of the risk affecting the primary source of intermittent
capacities) has been adapted. Verification is intended to ensure
that the capacities effectively contribute to security of supply
during the PP2 peak period. For instance, an intermittent capa-
city that undergoes extended maintenance during the delivery
year should not be issued certificates. With this adaptation, the
normative approach to availability is compatible with the stated
goal of not issuing certificates to capacities that do not effecti-
vely contribute to security of supply in a given year.
5.7.3 Verification of certified capacity under the generic approach
The procedure for verifying certified capacity under the generic
approach involves two separate levels of controls:
> Most capacities are regularly dispatched on the energy market or
balancing mechanism: in this case verification simply involves chec-
king that declared data matches up with collected data (availability);
> Some capacities are never dispatched on markets or the
balancing mechanism (unless a shortfall situation actually
occurs): they are verified by being regularly activated outside
the merit order to confirm that they are in working order;
> For capacities subject to specific technical or energy constraints,
additional verifications are required, either through desk or on-
site audits.
These verification procedures are based on generic processes
and can be applied with the same standards to generation and
demand response capacities.
5.7.3.1 Verification of injected quantities
These verification procedures involve analysing data relating to
the activation of capacities to calculate their effective availability.
Actual results are taken into account in order to verify a capacity’s maxi-
mum available power (factoring in the sensitivity of available power to
weather conditions) and its ability to be activated at the power level
required (success of upward offers for the balancing mechanism,
compliance of demand response programmes for NEBEF).
5.7.3.2 Activation tests
During the consultation, it became apparent that capacity
availability could not be confirmed solely on the basis of these
151
CAPACITY CERTIFICATION / 5
verification procedures and that “physical” activations could be
required. Since verification methods evolve rapidly, RTE opted
to outline the guiding principles for activation tests rather than
setting precise procedures in stone.
Though no stakeholders opposed the idea of activation tests,
there was some discussion about who should bear the related
costs. The rules put into practical application the provision of the
decree calling for operators to be billed for the “costs incurred
by [the system operator to which the capacity is connected] for
the certification and verification of their capacity” (article 9). To
limit the extra costs to the community of too large a number of
tests, a capacity cannot be tested more than three times within
a given delivery year. The rules also stipulate that the tests must
be decided on and carried out by system operators in a propor-
tionate manner and under the supervision of CRE.
Activation tests may cover all of the technical parameters decla-
red by the operator; however, their main aim will be to verify the
activatable power of capacities. Any capacity that has a non-
zero activatable power (i.e. that is not fully activated) can be sub-
jected to one or more activation tests. The scope of activation
tests is limited and regulated: for instance, if an activation test
focuses on verifying activatable power and the capacity fails, the
consequences will relate only to the activatable power level on
record.
Two approaches to activation have been adopted:
> Within the market. The technical and economic data declared
for demand response capacity not participating in the balan-
cing mechanism must be verified through activation (if the
spot price is higher than the price indicated by the operator, a
NEBEF has to be declared, or else the capacity is considered to
fail the activation test within the market);
> Outside the market. Random tests are carried out without
prior notice to operators. At each time step of the PP2 period,
a random sample is taken for each activatable but non-acti-
vated capacity. A sample is taken for each capacity (not for
one out of all the non-activated capacities). There is therefore
no systematic activation on each time step. Activation pro-
babilities are determined in such a way that a capacity that
is not activated once within the market over the entire PP2
period has a high probability of being activated through tests.
Conversely, a capacity that is activated over a significant part
of the PP2 period has a very low probability of being activated
during the time steps when it is not in use. A capacity’s proba-
bility of being activated also incorporates the results of audits
where applicable.
At the end of the delivery period, all capacities will have been
activated at least once through the verification system (activa-
tion test) or another system.
There is also a question about responsibility for verifications,
particularly after the Competition Authority’s recent opinion on
demand response. Under the rules, tests conducted on an entity
comprising sites connected to only one system will be decided
by the operator of that system and carried out by RTE through
the balancing mechanism, thus providing an aggregated view
of all capacities. Where demand response is concerned, these
provisions might not comply with the recommendations in the
opinion issued by the Competition Authority on 20 December
2013: RTE would like to point out that total compliance with
this recently issued opinion would require an amendment
of the decree of 14 December 2012 instituting the capacity
mechanism.
5.7.3.3 Audits
Verifying some technical parameters or energy constraints
declared for capacities necessarily require audits.
The rules distinguish between and describe two types of audit:
> Desk audits: according to the rules, an operator must provide
to RTE, through a distribution system operator if its capacity is
only connected to that operator’s network, all information that
can be used to validate the technical parameters declared for
its capacity. For instance, an audit of the data declared with
the certification request about weekly maxE may be ordered,
and the operator will then have to submit data that can be
objectively validated (measurements, updated file, etc.);
> On-site audits: once a certification contract has been signed,
RTE, a third party mandated by it or a distribution system ope-
rator (if all capacities within a certification entity are connec-
ted to its network) can at any time go to a capacity site or any
other site where it is possible to measure, monitor and acti-
vate capacities, and can ask the operator to produce any proof
of the technical characteristics declared and its ability to start
and monitor activations.
The comments above about the role of system operators in
verifying capacities also apply to audits, the Competition Autho-
rity having considered in its opinion of 20 December 2013 that
distribution system operators should not take part in the verifi-
cation of demand response. The rules proposed by RTE comply
with the decree of December 2012 on the capacity obligation.
152
The capacity mechanism is designed to function in a works
within a decentralised market architecture; this structure deci-
sion is in keeping with the founding principles of the internal
European energy market166 and particularly the core principle
of holding market stakeholders accountable. Under this struc-
ture, suppliers and capacity operators are active with regard to
their obligations and commitments, and have incentives to take
the actions required to help maintain security of supply strictly
within their respective perimeters.
This principle of accountability applies when it comes to fore-
casting demand or generation plant availability needs167, and
also to the capacity mechanism rules regarding settlements,
as provided for in the decree. Similarly to the imbalance settle-
ment system in place in the energy sector (the imbalance set-
tlement price must reflect the cost of the imbalances observed
within the perimeter of a balance responsible party), the rebal-
ancing price for suppliers and the imbalance settlement for
capacity portfolio managers hold stakeholders responsible for
the cost associated with their imbalances. The market mecha-
nism implemented thus encourages suppliers to cover their
obligations as accurately as possible and incentivises capacity
operators to submit their best power availability estimates for
their facilities.
The provisions relating to governing settlements in the capacity
mechanism rules will thus play a central role in incentivising mar-
ket stakeholders to adopt behaviours and make economic deci-
sions that help meet the security of supply target. For the capacity
mechanism to function efficiently, market stakeholders must: (i)
have incentives to base their actions on their best forecasts, (ii)
not be able to make arbitrages that are suboptimal collectively,
and (iii) have incentives to disclose information and transfer it to
the market so it can be efficiently integrated into the price.
The present This chapter presents the provisions in the capacity
mechanism rules that relate to how these incentives translate
into settlements. It begins with an overview of the general prin-
ciples applicable to the settlement for capacity rebalancing by
suppliers and the imbalance settlement for capacity portfolio
managers (§ 6.1). The factors to be taken into account in the
capacity mechanism rules for the calculation of settlements are
then discussed (§ 6.2). A third section reviews the options rela-
tive to settlements included in RTE's proposal (§ 6.3).
6.1 General principles of settlements
Article 1 of the decree describes the settlement relating to rebal-
ancing by suppliers and that relating to imbalances of capacity
portfolio managers.
The settlement for supplier rebalancing is the financial trans-
action conducted between that supplier and the transmis-
sion system operator when rebalancing occurs for a given
delivery year.
The capacity portfolio manager imbalance settle-
ment is the financial transaction conducted by that
manager when the total effective capacity within
its portfolio differs from the total capacity certi-
fied, or when a capacity operator in its portfolio
rebalances.
6. THE CAPACITY MECHANISM SETTLEMENT SYSTEM
166See chapter 2 of this report.
167See chapters 4 and 5 of this report.
168See chapter 3 of this report.
The sections below discuss the provisions in the decree that
relate to these definitions and within the framework of which
RTE has made its proposal related to settlements.
6.1.1 Capacity rebalancing by suppliers
The provisions concerning relating to the settlement for capacity
rebalancing by suppliers are found in article 6 of the decree. An integral
part of the model chosen by public authorities, these provisions were
introduced while the decree was being prepared, after being approved
by the Energy Regulatory Commission168, to ensure that efficient eco-
nomic incentives are in place to make suppliers accountable.
A settlement for capacity rebalancing by a supplier is proportion-
ate to the supplier's imbalance – i.e. the difference between the
153
THE CAPACITY MECHANISM SETTLEMENT SYSTEM / 6
amount of its capacity obligation and the amount of capacity
certificates held in its account – and to a unit price that depends
on the sign of the imbalance.
The decree also stipulates that the method of calculating the
unit price for capacity rebalancing must be defined in such a
way as to (i) ensure, over the medium term, that suppliers have
an economic incentive to meet their capacity obligation, (ii)
encourage suppliers to evaluate their capacity certificate needs,
with an eye to meeting their capacity obligation, based on a
good faith estimate of their customers' reference power, and
to (iii) limit arbitrage possibilities between an imbalance settle-
ment at the capacity portfolio manager level and a settlement
for rebalancing at the supplier level.
This calculation method is approved by the Energy Regulatory
Commission, on the basis of a proposal by the public electricity
transmission system operator.
6.1.2 Imbalance settlement at the capacity portfolio manager level
The provisions relating to concerning the settlement for imbal-
ances at the capacity portfolio manager level are found in article
14 of the decree.
Under the terms of the decree, the imbalance settlement
of a capacity portfolio manager is calculated based on the
capacity portfolio manager's imbalance – i.e. the difference
between total effective capacity and total certified capacity
within its portfolio – and the sum of the amounts rebalanced
within its capacity portfolio. If rebalancing has occurred several
times, the settlement also takes into account the number and
direction of these adjustments. Thus, for a given imbalance,
recourse to rebalancing will increase the algebraic value of the
settlement compared with a situation where rebalancing did
not occur.
The decree also stipulates that the method of calculating the
imbalance settlement of a capacity portfolio manager must be
determined in such a way as to (i) ensure, over the medium term,
that operators have an economic incentive to meet their com-
mitments, (ii) encourage capacity operators to submit truthful
information with certification and rebalancing requests, particu-
larly regarding the projected availability of their capacity, and
to (iii) limit arbitrage possibilities between an imbalance settle-
ment at the capacity portfolio manager level and a settlement
for rebalancing at the supplier level.
6.1.3 Overview of principles governing settlements
The formula applied in calculating the settlement can be written
as follows:
Capacity rebalancing by suppliers
Settlement = – imbalance
Volume x unit
Price
A supplier with a negative imbalance pays the amount corre-
sponding to its imbalance, multiplied by the settlement price
for negative imbalances, into the settlement fund for capacity
rebalancing by suppliers.
A supplier with a positive imbalance receives the amount cor-
responding to its imbalance, multiplied by the settlement price
for positive imbalances, from the settlement fund for capacity
rebalancing by suppliers. It may receive less if the balance in the
account is too low to compensate all stakeholders with positive
imbalances. In this case, they will receive a settlement propor-
tionate to their imbalance.
Imbalance settlement for capacity portfolio manager
Settlement = – imbalance
Volume x unit
Price + rebalancing
Cost
Capacity portfolio managers with negative imbalances pay into
the settlement fund for capacity portfolio manager imbalances
the amount corresponding to their imbalances, multiplied by
the negative imbalance settlement price, plus the cost associ-
ated with rebalancing.
Capacity portfolio managers with positive imbalances receive
from the settlement fund for capacity portfolio manager imbal-
ances the amount corresponding to their imbalances, multiplied
by the positive imbalance settlement price, plus the cost associ-
ated with rebalancing. They may receive less if the balance in the
account is too low to compensate all stakeholders with positive
imbalances. In this case, they will receive settlements proportion-
ate to their imbalances.
154
6.3 Settlements provided for in the rules
To ensure that the settlement gives stakeholders the right eco-
nomic incentives, RTE drafted the capacity mechanism rules
with three key parameters in mind, the goal being to ensure that
the settlement will give stakeholders the right economic incen-
tives: the security of supply criterion set by public authorities
(§ 6.2.1), the reference unit price of the settlement used to cal-
culate the imbalance price (§ 6.2.2) and the interplay between
capacity rebalancing by suppliers and the imbalance settlement
for capacity portfolio managers (§ 6.2.3).
6.2.1 Security of supply target
The decree stipulates that the settlement system can be
adapted when “there is no significant threat to security of sup-
ply”. Moreover, article L.335-2 of the Energy Code states that
“obligations assigned to suppliers are calculated in such a way
as to incentivise them to work, over the medium term, towards
the security of electricity supply target used to prepare the Ade-
quacy Forecast Report”.
These provisions show that In other words, the calculation of the
settlement system must support the objective of safeguarding
security of supply and be proportionate to this objective. The
settlement definition adopted in the capacity mechanism rules
must therefore take into account both the security of supply cri-
terion and the imbalance amount (in absolute terms) beyond
which the threat to security of supply is considered significant.
6.2.2 Unit price of the settlement
The provisions of the decree explicitly state that a settlement amount,
be it for an imbalance at the capacity portfolio manager level or for
capacity rebalancing by a supplier, is based on a unit price.
6.2 Key aspects of capacity mechanism settlements
6.2.3 Interplay between capacity rebalancing by suppliers and imbalance settlement at the capacity portfolio manager level
The efficiency of the provisions governing the settlement can-
not be measured solely by analysing the impact of each compo-
nent separately: a broad assessment of stakeholders' economic
results is required. The settlement creates incentives through
the gains to which stakeholders can aspire and the risks to
which they are exposed.
Market stakeholders' economic results may overlap with incen-
tives for capacity rebalancing by suppliers and the imbalance
settlement at the capacity portfolio manager level for integrated
companies.
The challenge in drafting the rules was to manage the interplay
between the systems applicable to capacity rebalancing by sup-
pliers and imbalance settlements for capacity portfolio manag-
ers while upholding the provisions of the decree that seek to
limit the possibility for stakeholders to arbitrage between the
two types of settlement.
6.3.1 Interplay between capacity rebalancing by suppliers and the imbalance settlement at the capacity portfolio manager level
To ensure that the settlement creates the right incentives, and
that integrated stakeholders cannot engage in arbitrage, the
systems governing rebalancing by suppliers and the imbalance
settlement for capacity portfolio managers must be aligned.
Indeed, an imbalance between the number of capacity certifi-
cates held by an integrated stakeholder and its obligation could
alternatively be considered a certification or obligation compo-
nent, depending on the number of certificates transferred by
the part of the company that acts as an “operator” to its “sup-
plier” arm.
The challenge in drafting the rules was to deter-mine the reference or references to be that should be used to calculate this unit price. Two options emerged during the consultation:
> A unit price based on prices applied in different mechanism-related transactions (market price);
> A unit price set at the administrative level.
155
THE CAPACITY MECHANISM SETTLEMENT SYSTEM / 6
∆V
Capacitylevel
Obligationlevel
Capacitycertified
level
Imbalancesettlement
at CPM level
Player certifiesat obligation level
Pays ΔV * CPM settlement price
Capacitycertified
level
Imbalancesettlementat supplier
level
Real situation Player certifies at capacity level
Pays ΔV * Supplier settlement price
Figure 72 – Interplay between obligation- and certification-related settlements
The chart below illustrates how an integrated stakeholder could
arbitrage between its imbalance as a supplier and its imbalance
as a capacity portfolio manager when it shows an imbalance
(ΔV) between its obligation and capacity.
If the stakeholder opts for the capacity portfolio manager set-
tlement, its imbalance ΔV will be valued based on the capacity
portfolio manager settlement price. In the other case, the set-
tlement will be equal to the product of ΔV and the supplier set-
tlement price. To make arbitrages impossible, the capacity port-
folio manager settlement price and supplier settlement price
must be equal.
Having a “supplier” settlement and a “capacity portfolio man-
ager” settlement comes down to defining a settlement unit
price that represents the same variable for capacity rebalancing
by suppliers and the imbalance settlement for capacity portfolio
managers. This approach is also in keeping with the idea that
all contributions to the shortfall risk should be treated equally,
whether generated by an imbalance at the level of a supplier
or capacity portfolio manager.
Arbitrages between an imbalance settlement at the capacity portfolio manager and supplier levels are effectively prevented when the unit price for rebalancing by suppliers is the same as the unit price for rebalancing by capacity portfolio managers.
6.3.2 Unit price for the settlement and the security of supply target
The decree specifies that the unit price for the settlement can
be adapted when there is no significant threat to security of sup-
ply. Bearing this in mind, RTE is proposing a two-part settlement
scheme:
> When security of supply is not at risk, the settlement price will
be based exclusively on the market price. In this case, stake-
holders are not penalised for imbalances, which are simply
restated based on their market value. An incentive coefficient
K is nonetheless still necessary to incentivise stakeholders to
go through the market rather than wait for a settlement;
> When security of supply is at risk, the settlement price must
switch over to an administered price. This price, which by
definition sets the maximum value capacity can reach on the
market, plays a key role in creating incentives to invest in new
capacitiesy. It is therefore set based on the annualised cost of
the reference peak-load capacity and made public four years
before the delivery year.
By structuring the settlement around the market price in this
way, the mechanism introduces an important self-regulation
function that makes the signals generated by the capacity mar-
ket more consistent with forecast levels of security of supply lev-
els. This ensures that if overcapacity becomes an issue, the ref-
erence market price can be low or even zero, reflecting the state
of the system, and thus avoid unnecessary extra costs for con-
sumers. Conversely, if capacity is tight in terms of safeguarding
156
security of supply, the reference market price will rise, in line with
anticipated tension in the system.
Settlements are thus shaped by two reference prices: a refer-
ence market price (MarP) and an administered price (AdminP).
RTE proposes that the “reference capacity price for the deliv-
ery year” and the “maximum price determined with reference
to the cost of building new capacity”, defined by CRE169, be
used as the reference market price and the administered price,
respectively, for settlements within the framework of the capac-
ity mechanism.
6.3.3 Definition of indicators for assessing threats to security of supply
With a settlement scheme based on the actual level of secu-
rity of supply, a meaningful indicator must be determined
to estimate if security of supply is effectively threatened
(§ 6.3.3.1) and a threshold value must be defined for this indi-
cator (§ 6.3.3.2).
6.3.3.1 Determining the overall imbalance
The decree stipulates that the settlement scheme can be calcu-
lated based on “the sum of the imbalances of capacity portfolio
managers and the difference between the sum of the capacity
obligations of suppliers and the total capacity certificates they
hold as of the capacity certificate transfer date”. In other words,
the decree stipulates that the difference between effective
capacity levels and the aggregated obligations of all obligated
parties in France (assuming that all certificates effectively par-
ticipate in the market) is the indicator to be used to determine
whether security of supply is at risk. This difference corresponds
to the overall imbalance.
This choice of the Using the overall imbalance
observed as the indicator for measuring the threat
169Decree 2012-1405, Article 23
Table 4 – Matrix of the imbalance settlement depending on the state of the system
Security of supply at risk Security of supply not at risk
Negative imbalance settlement price AdminP (1+K) MarP
Positive imbalance settlement price (1-K) MarP (1-K) MarP
to security of supply creates incentives that are consistent with
the actual state of the system and enhances the mechanism's
efficiency. The signal generated by the market closely reflects
physical tension between effective obligations levels and effec-
tive capacity levels. Any risks that emerge on either side are
communicated to the market and can be addressed with capac-
ity adjustment measures. In particular, demand response and
load reduction capacity, suitable responses to short-term capac-
ity concerns, can be fully leveraged.
Using the overall imbalance observed as the indicator also pre-
vents stakeholders from manipulating the market by certifying
an excessively high (or low) level of capacity to artificially modify
the market price.
In such situations, if the imbalance price was based on the fore-
cast overall imbalance, measures with an activation cost that is
higher than the imbalance price based on the reference market
price will not be activated, even though the state of the system
would justify their use.
The actual level of security of supply would be lower, as
would the rewards offered for such measures, particularly on
the demand side, than if the actual imbalance was taken into
account.
Conversely, the actual state of the system might not be as
unfavourable as anticipated. In this case, capacity could be
dispatched even when the level of security of supply did does
not require it, thus generating extra costs for suppliers and, ulti-
mately, for consumers.
6.3.3.2 Determining the maximum imbalance
If the overall imbalance observed is considered the best indica-
tor to assess the threat to security of supply, then a threshold
value must be defined to establish the level beyond which the
157
THE CAPACITY MECHANISM SETTLEMENT SYSTEM / 6
overall imbalance observed is considered to pose a threat to
security of supply. This threshold value is referred to as the maxi-
mum imbalance.
Above and beyond the objective of keeping the settlement
proportionate, the challenge for RTE in determining the maxi-
mum imbalance is to ensure that market stakeholders have
sufficient visibility on the settlement scheme to which they
will be subject.
The sensitivity analyses conducted on the obligation, presented
in chapters 4 and 5 of this report, provide preliminary informa-
tion about the variability of the capacity mechanism, applying
the provisions of the capacity mechanism rules to the six years
between 2006 and 2011.
Figure 73 – Illustration of the impact taking the actual imbalance in the system into account has on measures activated during the delivery year
Figure 74 – Imbalance settlement scheme applicable depending on the overall imbalance observed
Overall imbalance0 Maximum imbalance
Security of supply not at risk
Reference market price
Security of supply at risk
Administered price
Overall imbalance
Negative imbalance price
oI est.
oI (overall imbalance) actual
oI actual
Price gap not factored in,preventing activationof resources, notablyon demand side
AdmP
MarP
oIlimit
Overall imbalance
Negative imbalance price
oI est.
OI (overall imbalance) with resources activated
Imbalance price withoutresources activated
Imbalance price withresources activated
1
2
RTE proposes that the maximum imbalance be defined in such a way as to ensure that the set-tlement scheme does not depend on the occur-rence of short-term risks, and that the maximum imbalance be published before the start of the delivery year.
The maximum imbalance could be set factor-ing in a quantity of uncontrollable risks – i.e. the amount of risks that stakeholders would not have sufficient resources to cover.
Setting the maximum imbalance at 2 GW ensures that a switch from the market price to the admin-istered price will occur only when there is a sig-nificant threat to security of supply, without depending on the materialisation of short-term risks.
158
6.4 Assessment of the impact of the provisions on settlements for market stakeholders
6.4.1 Framework for the assessment
The previous sections outlined the defining choices made in the
rules to ensure that the settlement scheme incentivises stake-
holders to balance through the market rather than wait for a
settlement. With the way settlements are calculated, the settle-
ment price for rebalancing by suppliers or imbalance settlement
by capacity portfolio managers is lower than the market price
when they show positive imbalances and higher when they
show negative imbalances. Relying on the settlement thus has
a cost for stakeholders.
Moreover, if security of supply is at risk (i.e. if the overall imbal-
ance observed exceeds the value of the maximum imbalance
set by RTE before the start of the delivery year), a settlement
for supplier rebalancing or an imbalance at the capacity portfo-
lio manager level will be based on the administered price. The
switchover to the administered price entails additional costs for
stakeholders showing imbalances.
Lastly, articles 7 and 14 of the decree stipulate that the settle-
ment fund for capacity rebalancing by suppliers and the settle-
ment fund for capacity portfolio manager imbalances cannot
have a negative balance170 and that settlements paid out from
them is reduced proportionately to ensure that the sum of the
settlements paid is equal to the amount available in the account.
This provision creates an additional incentive for stakeholders
with positive imbalances to rebalance through the market, but
can generate additional costs (particularly for stakeholders with
a zero imbalance expectation and thus only showing a small
imbalance).
The financial risk to which market stakeholders are
exposed – , suppliers through the rebalancing set-
tlement and capacity portfolio managers through
the imbalance settlement, – can be analysed. Inso-
far as stakeholders can turn to the market if risks
materialise before the start of the deliver year, sup-
pliers by buying or selling certificates and capac-
ity portfolio managers by rebalancing one or more
times, the study focuses only on the residual risks
that can impact stakeholders during the delivery
year, i.e. the real-time risks that cannot be offset
through the market.
6.4.2 Principle of the study
The model comprises ten market stakeholders each with a sup-
plier perimeter and a capacity portfolio manager. We begin at
the start of the delivery year, in the following situation:
> The reference market price has been set;
> Each stakeholder positions itself based on its best estimate
(anticipated value).
We then model the residual uncertainty stakeholders face
with regard to availability and obligation levels, with a variable
centred on 0. The variables are independent standard normal
distributions. Each simulation represents a delivery year for
the mechanism, and yields the settlement to which each par-
ticipant is subject. The same climate scenario is used on the
obligation and certification sides. The simulation is repeated
a large number of times to obtain the average settlement per
participant.
Structure of the settlement
The structure of the settlement modelled is the one proposed
by RTE in the draft capacity mechanism rules. The parameters
were defined as follows:
Parameter Value applied
Administered price (€k/MW) 60
Maximum imbalance (GW) -2
K 0.1
Two assumptions are used for the reference market price: €10k/
MW and €30k/MW (see chapter 8 as well).
Risks incurred by stakeholders
The risks incurred by stakeholders are defined by a standard
deviation based on their size. Two distributions of risks between
stakeholders are simulated: in the first case, standard deviations
for risks are proportionate to stakeholders' capacity/obligation
levels, and in the second the standard deviations are lowered to
factor in risk -spreading.
170Article 7 of the decree: The sum of the amounts paid out of the fund cannot exceed the sum of the amounts effectively paid in by suppliers with positive settlement for that delivery year.Article 14 of the decree: The sum of these settlements cannot exceed, for a given delivery year, the sum of amounts effectively paid in for positive settlement.
159
THE CAPACITY MECHANISM SETTLEMENT SYSTEM / 6
Case 1: Risks proportionate to stakeholders' capacity or obligation
Risks are aligned as follows:
> For the supplier share: the standard deviation represents 1.5% of the obligation;
> For the capacity portfolio manager share: the standard deviation represents 2% of certified capacity.
The resulting breakdown between stakeholders is as follows:
171Obligation – Capacity level
Stake-holder 1
Stake-holder 2
Stake-holder 3
Stake-holder 4
Stake-holder 5
Stake-holder 6
Stake-holder 7
Stake-holder 8
Stake-holder 9
Stake-holder 10 TOTAL
Capacity level/Obligation (GW) 60 15 10 5 3 2 2 1 1 1 100
Standard deviation for obligation risk (GW) 0.90 0.23 0.15 0.08 0.05 0.03 0.03 0.02 0.02 0.02 0.95
Standard deviation for capacity risk (GW) 1.2 0.3 0.2 0.1 0.06 0.04 0.04 0.02 0.02 0.02 1.25
The total variability for the system171 is close to 1.6 GW, consistent with the results obtained using historical data, which showed a maxi-
mum overall variability of 1.6 GW.
Case 2: Risks taking into account risk spreading
The alignment of risks per stakeholder is shown in the table below, taking into account whether stakeholders they have the ability to
smooth their imbalances. Risk spreading reduces the standard deviations for the three largest stakeholders:
Stake-holder 1
Stake-holder 2
Stake-holder 3
Stake-holder 4
Stake-holder 5
Stake-holder 6
Stake-holder 7
Stake-holder 8
Stake-holder 9
Stake-holder 10 TOTAL
Capacity level/Obligation (GW) 60 15 10 5 3 2 2 1 1 1 100
Standard deviation for obligation risk (GW) 0.68 0.21 0.14 0.08 0.05 0.03 0.03 0.02 0.02 0.02 0.73
Standard deviation for capacity risk (GW) 0.90 0.29 0.19 0.10 0.06 0.04 0.04 0.02 0.02 0.02 0.97
6.4.3 Results
The first observation is that the average settlement cost in
relation to stakeholders’ capacity or obligation levels is small.
For a stakeholder with an obligation of 10 GW, the amount is
€0.27k/MW, broken down as follows:
Average settlement cost
Negative imbalance settlement (€k/MW) 0.51
Positive imbalance settlement (€k/MW)
-0.23
Total (€k/MW) 0.27
Average settlement cost for stakeholder 3
(Reference market price = €30k/MW)
Average settlement cost
Negative imbalance settlement (€k/MW) 0.25
Positive imbalance settlement (€k/MW) -0.07
Total (€k/MW) 0.18
Average settlement cost for stakeholder 3
(Reference market price = €10k/MW)
The simulation results are presented in the chart below. The red
curve represents the results obtained for stakeholders' imbal-
ance settlement costs in the simulation with risks distributed
proportionately to their capacity or obligation levels. The green
curve shows the results obtained for stakeholders' imbalance
160
settlement costs in the simulation that takes into account their
ability to smooth their imbalances.
With risks distributed in portion to stakeholders' capacity or obli-
gation levels, the settlement cost is proportionately higher as
the stakeholder’s' size increases. For a stakeholder with 60 GW
of capacity, the settlement cost is €0.48k/MW, compared with
€0.24k/MW for one with 1 GW (assuming a reference market
price of €30k/MW).
This result depends on the stakeholder's quantity of risks in rela-
tion to the overall imbalance defi ned as the maximum imbal-
ance. A larger stakeholder (with potentially high risks) can by
itself, if it has a negative imbalance, trigger a shift in the overall
imbalance on the system and thus a switch to the administered
price. A larger stakeholder will therefore settle negative imbal-
ances at the administered price more often than a smaller one,
given the correlation between the imbalance settlement regime
determined and the sign of its imbalance.
Taking into account the ability to spread risks reduces the imbal-
ance settlement cost for larger stakeholders, from €0.48k/MW to
€0.28k/MW172. It can also be observed that all stake-
holders benefi t from the spreading of risks through a
lower average imbalance settlement cost, including
smaller stakeholders for which risk levels have not
changed. This is explained by the decline in the overall
variability of the system173 from 1.6 to 1.2 GW.
0
10
20
30
40
50
60
70
80
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
GW
€k/M
W
Player 1
Player 2
Player 3
Player 4
Player 5
Player 6
Player 7
Player 8
Player 9
Player 10
Figure 75 – Settlement cost based on size of stakeholder (reference market price assumed = €30k/MW)
Total capacity
Imbalance settlement cost, 1st case
Imbalance settlement cost with smoothing
The impact assessment conducted on the provi-sions relating to settlements in the draft capacity mechanism rules produced three key results:
> A larger stakeholder will face a higher set-tlement cost than smaller stakeholders as a whole. Due to its size and the potential signifi -cance of its risks, there is indeed a correlation between its imbalance and the overall imbal-ance on the system: all other things being equal, a larger stakeholder will therefore settle negative imbalances at the administered price more often;
> A stakeholder facing fewer a smaller quantity of risks does not have to contend with the same issue and its settlement cost will thus be lower;
> All stakeholders benefi t from the spreading of risks, including smaller ones that cannot spread risks at their individual level; this is because the decrease in the system's overall variability results in a lower settlement cost for all stakeholders.
172Assuming a reference market price of €30k/MW.
173Obligation – Capacity level.
161
THE CAPACITY MECHANISM SETTLEMENT SYSTEM / 6
162
7. MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION The French capacity mechanism is based on suppliers being
required to have capacity coverage equivalent to the consump-
tion of their customers. This obligation allows all energy market
stakeholders to contribute to security of supply in proportion to
their contribution to the shortfall risk, and creates incentives to
keep peak demand growth in check, this being a key criterion for
evaluating the shortfall risk in France.
It would not be economically efficient to require that all obli-
gated parties ensure the physical coverage of their own obli-
gation if other operators can do it for them at a lower cost.
This is why obligated parties have the option to go through
the market and meet their obligation indirectly by buying from
a third party securities representing an operator’s unit contri-
bution to reducing the shortfall risk. These securities, called
capacity guarantees in the rules and capacity certificates in
this report, must therefore be carefully defined and they must
be negotiable.
This kind of market mechanism, designed to deliver a collec-
tive result, is in keeping with an existing body of theory deve-
loped in the economic literature based on the work of Ronald
Coase174. Creating standardised products called capacity certi-
ficates is a matter of creating property rights to reductions in
the risk of shortfalls on the power system and allowing market
stakeholders to trade them to meet the objective set by public
authorities at the lowest cost. A capacity market is thus crea-
ted through the trading of capacity certificates between market
stakeholders.
For such a system to be economically efficient, the property rights
need to be sufficiently well defined and related transaction costs
low enough, especially with regard to the gains stemming from
the optimisation of the provision of the good.
The first condition is considered to have been met if the number
of capacity certificates allocated to each resource through the
capacity certification process accurately reflects its contribution
to security of supply, and if those that buy capacity certificates on
the market are not held responsible for a potential failure of the
capacity to which the certificates were originally allocated. This
objective is met through the certification principles outlined in
chapter 5 of this report and the method of calculating whether an
obligated party has met its obligation found in chapter 4.
The second condition can only be met in relative terms, insofar
as there will necessarily be transaction costs involved in creating
a new negotiable good from scratch. For transaction costs to be
considered sufficiently low to be economically optimal for the
capacity mechanism, specific conditions must be met:
1. It must be possible for stakeholders to trade capacity certifi-
cates freely, based on their needs, and at prices that effectively
correspond to underlying costs;
2. Stakeholders must have access to relevant information to
understand the market fundamentals and act accordingly;
3. Competition in the market must be free and undistorted.
Some consultation participants voiced reservations about the third
condition, and to a lesser degree the second, as did the Competition
Authority175. Concerns about whether a market mechanism can
efficiently reveal the value of security of supply and ensure optimal
coordination of stakeholders’ decisions are legitimate, as these issues
are what will determine the mechanism’s economic efficiency. This
chapter outlines the measures intended to address them, notably
particularly those proposed in the capacity mechanism rules. The
provisions that would govern capacity certificate trading are pres-
ented in § 7.1, those relating to the transparency of the market and its
fundamentals in § 7.2, and those designed to ensure free and undis-
torted competition in the capacity market in § 7.3.
174[Coase, 1960]
175[Competition Authority, 2012a]
163
MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION / 7
7.1 Trading of capacity certificates
For the capacity market to be efficient, transactions must
involve goods that are clearly defined, and the framework must
give stakeholders confidence in a system that allows them to
meet their obligation through the market rather than holding
physical capacity. Transactions should generate a signal-price
that reflects the state of the power system.
This “market-driven” approach requires that the mechanism’s
parameters be stable throughout each term. Otherwise, regu-
latory uncertainty could discourage stakeholders from trading,
especially several years before the delivery year, since the value
of a capacity certificate could change due to the intervention
of forces outside the market during a term. For instance, a
decrease in the security factor during a mechanism term would
reduce the value of a capacity certificate. The publication of the
mechanism parameters at the start of the term, i.e. four years
before the delivery year, provides the regulatory stability indis-
pensable to the smooth flow of trading. By reducing uncertainty
relating to the mechanism’s time horizons, it plays an important
role in shaping stakeholders’ forecasts.
The capacity mechanism rules are the foundation for capacity
certificate trading. They include all of the building blocks required,
from precise definitions (nature of the product, eligible stakehol-
ders, transfer system, etc.) to the tools to be implemented (crea-
tion of the register, traceability, etc.). Though the mechanism rules
do not institute an organised market for certificate trading, they
do lay the groundwork for its future creation by leaving enough
leeway for an exchange platform to be created.
The section below discusses the effects of the publication of the
parameters before the delivery year and the provisions intended
to make exchanges more fluid.
7.1.1 Publication of mechanism parameters at the start of the term
The publication of the definitive parameters at the start of the
capacity mechanism term gives suppliers sufficient visibility
to integrate their obligation into their customer contracts, to
cover their certificate needs ahead of time, to organise any
demand management actions necessary and, ultimately, to
meet their obligation. Operators can also anticipate their own
certified capacity level and thus the amount of certificates
that will be allocated to their capacities. This is especially
important when it comes to planned capacity and investment
decisions.
However, the fact that the mechanism parameters are defined
several years ahead of time and do not change after they are
published could create some uncertainty when they are being
set. It is impossible to reassess them later if the fundamentals
of security of supply change significantly and unexpectedly, and
this could make them less representative of security of supply.
This is another illustration of the compromise that must be
found between the accuracy and stability of the mechanism
(see section 3.2). The disadvantages in terms of accuracy are
nonetheless lessened by the fact that the mechanism does
not set a capacity target: as such, even if the mechanism para-
meters are not perfect, market stakeholders will reassess their
capacity needs and this will bring the value back into line with
the fundamentals.
A stable regulatory framework is thus crucial for trading to func-
tion smoothly, and its drawbacks in terms of when the parame-
ters are defined are offset by the absence of a fixed capacity
target. In this case, the benefits of stability far outweigh the
disadvantages in terms of accuracy.
The rules stipulate that all capacity mechanism parameters are
to be published together at the start of the term, i.e. four years
before the start of the delivery year:
> For the obligation: extreme temperature value and security factor;
> For certification: charts used for capacity certification, contri-
bution coefficients for each technology subject to the certifi-
cation approach that neutralises the risk affecting the primary
source of intermittent capacities;
> For settlements: the administered price representing the price
applied to negative imbalances when security of supply is
seriously threatened.
7.1.2 Nature of the product and organisation of trading
7.1.2.1 Nature of the “capacity certificate” product
Decree 2012-1405 of 14 December 2012 provides a definition
of the “capacity certificate” product:
A capacity certificate is intangible personal property, fungible,
negotiable and transferable, corresponding to a normative
164
unit power value, created by the public transmission system
operator and issued to a capacity operator after a capacity
has been certified and valid for a given delivery year.
Capacity certificates are all recorded in the capacity certificate
register kept by RTE. This register lists, in a secure and confiden-
tial manner, all transactions involving the issuance, exchange
or destruction of capacity certificates. The capacity certificate
register is opened once the first capacity certificates are issued.
Ownership of a capacity certificate is established once it is
recorded by RTE in the holder’s account in the capacity certi-
ficate register. Because capacity certificates are paperless, their
recording in the capacity certificate register constitutes suffi-
cient proof of ownership. The negotiable product exists separa-
tely once it is issued: a that holds a certificate bears no risk with
regard to the underlying capacity to which the certificate was
originally issued.
Each capacity certificate is valid only for a given delivery year.
This means that a capacity certificate issued for a delivery year
and recorded in an account in the register for that year cannot be
transferred to an account in a register for a different delivery year.
Capacity certificates are issued in units of 0.1 MW. They are
numbered to facilitate their management and the tracking of
exchanges.
7.1.2.2 Holder of an account in the capacity certificate
register
An account holder is a legal entity with at least one account in
the register. It may be an obligated party, a capacity portfolio
manager, an operator or any other participant in the market.
An account holder may have several accounts, depending on its
own capacity mechanism-related needs. However, an account
holder can only have one account as an obligated party. It is the
number of certificates held in this account that will be used to
calculate the supplier’s imbalance for capacity rebalancing, and
then to calculate its final imbalance.
7.1.2.3 Issuance and cancellation of capacity
certificates
As the body that maintains the register, RTE alone can issue or
cancel capacity certificates.
Certificates are issued when a capacity contract comes into
effect for a capacity that was not previously the subject of a
certification contract for the same delivery year, or in the event
of upward rebalancing by an operator. When certificates are
issued, RTE places an amount of certificates corresponding to
the amount certified in the contract in the holder’s account in
the capacity certificate register.
Capacity certificates can only be cancelled in the event of
downward rebalancing by an operator. RTE cancels the certifi-
cates once they have been returned to it by capacity portfolio
manager that rebalanced.
7.1.2.4 Transfers of capacity certificates
A capacity certificate changes ownership when it is transferred
between two legal entities each holding an account in the capa-
city certificate register.
To avoid factoring transactions conducted at prices that have
no economic relevance for the market as a whole into the refe-
rence price, the rules distinguish between two types of capacity
certificate transfers:
> Certificate transactions: certificates are transferred based on a
price agreed upon between the parties;
> Certificate transfers: the exchange is agreed upon between
the parties but with no payment involved.
All transaction prices must be notified to CRE in keeping with
paragraph I of article 17 of the decree.
7.1.3 Trading procedures
Capacity certificates can be traded bilaterally or through orga-
nised markets. A platform to concentrate liquidity would offer
real advantages in terms of forming and revealing a public refe-
rence price to guide stakeholders’ forecasts. This is why the
capacity mechanism rules proposed by RTE include provisions
that will facilitate the creation of such a platform.
7.1.3.1 Bilateral trades
The capacity mechanism rules suffice to allow bilateral trading
between mechanism stakeholders. Two stakeholders must sim-
ply agree on a trade and a price, and then carry out the transac-
tion and notify RTE, which will modify both parties’ positions in
the capacity certificate register accordingly.
In sum, the procedures involved in bilateral trades are similar to
those that exist in the energy market with the block exchange
notification (NEB) mechanism.
165
MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION / 7
7.1.3.2 Development of an exchange platform
Examples observed in energy markets show that bilateral tra-
ding of long-term products is relatively illiquid. This can be a
major obstacle to the formation of a credible signal-price and
even make it difficult for stakeholders to find counterparties. It
seems necessary to have an organised market in place that will
concentrate liquidity through trading sessions in the capacity
market, thereby enhancing the quality of the signal-price.
The decree recognises the importance of having an exchange
platform for the capacity mechanism. It stipulates that if no such
platform is developed through private initiatives, and the Energy
Regulatory Commission recommends that one be created, the
Energy Minister can organise a call for tenders for this purpose.
During the consultation, EPEX Spot expressed an interest in set-
ting up an exchange platform for capacity certificates.
7.1.3.3 Interfacing with an exchange platform
Setting up an exchange platform will require determining how it
will interface with the capacity certificate register, which records
ownership of capacity certificates. To facilitate the development
of an exchange platform, the capacity mechanism
rules explicitly make this interface possible, but sti-
pulate that the exact scope and functioning of this
interfacing will be defined at a later date based on
work to be conducted jointly by RTE and the compa-
nies organising the exchange platform. This solution
avoids the potential problem of creating preliminary
constraints that could hinder or turn into obstacles to the deve-
lopment of an exchange platform.
The capacity mechanism rules create a robust framework for the trading of capacity certificates between market stakeholders. This framework is based on existing provisions for energy, with a central register maintained by RTE allowing transactions to be tracked. The future develop-ment of an exchange platform is factored into the capacity mechanism rules. Taken together, these provisions lay a solid foundation for the develop-ment of certificate trading.
7.2 Transparency of the mechanism
The capacity certificate market must be an efficient tool for
coordinating the efforts of mechanism participants. This will
be accomplished if the price at which certificates are traded
reveals relevant information. For this price to be meaningful,
stakeholders must have enough information about the state of
the system and market fundamentals at the start. This is why in
designing the rules, particular attention was paid to provisions
that could ensure that the mechanism functions in a transpa-
rent manner.
Transparency is needed with regard to the fundamentals of the
power system (i.e. the projected supply-demand balance for the
delivery year) and the actual functioning of the market (transac-
tion volumes and prices). The rules therefore include transpa-
rency measures focusing on:
> The physical underlyings of the mechanism, via the publica-
tion of an aggregate of the registers (§ 7.2.1) and forecasts
of obligation volumes at the aggregate and individual levels
(§ 7.2.2);
> The functioning of the market, notably to provide visibility on
transaction volumes and prices (§ 7.2.3).
7.2.1 Publications relating to the registers
Since markets were opened to competition, the aggregated data
about the supply-demand balance outlook provided through
RTE’s Adequacy Forecast Reports have been indispensable to
the functioning of the deregulated power system. The need
for adequacy reports of this kind has since been recognised at
the European level and included in the European Commission’s
guidelines as a prerequisite to the implementation of a capacity
mechanism.
RTE’s annually updated Adequacy Forecast Reports already
provide a good deal of information about the supply-demand
balance outlook. They inform market stakeholders about the
fundamentals of the power system by providing an aggregate
view of forecast electricity supply and demand. These reports
are also a forward-planning tool in that they allow longer-term
scenarios of changes in the electricity mix and demand struc-
ture to be examined in the light of the targets set by French and
European authorities176.
176Additional information is made available every year through medium-term studies looking at the following winter or summer and the Electrical Energy Statistics.
166
The capacity mechanism rules call for the existing arrangement
to be strengthened through the regular publication of aggre-
gates of certified capacity levels and peak demand management
measures. For each delivery year, RTE will create and maintain
two registers, in addition to the confidential capacity certificate
register in which are recorded, in a secure manner, all transactions
involving the issuance, trading or destruction of certificates:
> The certified capacity register, listing all capacity certified;
> The peak demand management measure register, listing all
peak demand management measures reported by consu-
mers and suppliers, particularly any peak demand flexibilities
recognised through other mechanisms but not certified as
demand response capacity. RTE takes the data in this register
into account in calculating the overall obligation and makes
it public in a way that protects the confidentiality of commer-
cially sensitive data.
The publication of the aggregate data recorded in the regis-
ters will be key to the mechanism’s transparency and convey
information of a different nature than what is included in RTE’s
Adequacy Forecast Reports. Indeed, the latter are based on non-
binding data gathered from generators, whereas the certified
capacity registers will include data that is declared by genera-
tors to certify their capacity and can only be modified through
rebalancing. This should for instance facilitate the collection of
information about operators’ real prospects with regard to the
definitive closure or mothballing of certain facilities.
7.2.1.1 Publications relating to the certified capacity
register
The rules stipulate that the data in the certified capacity register
is to be made public. In concrete terms, this means that detailed
information will be made available about individual capacities --
volumes certified, technical characteristics, projected availability
and effective levels in previous years. Under the rules, the certi-
fied capacity register is to provide stakeholders with information
for the next four delivery years, as well as the last two, regarding:
> The total level of capacity certified for each technology;
> Details about individual certification levels for capacities of
more than 100 MW;
> Details about aggregated certification levels for capacities of
less than 100 MW.
The rules also stipulate that effective capacity levels must be
made available at these same scales for past years. Once the
mechanism is established, all market stakeholders will thus be
able to compare the certified capacity level of a capacity or tech-
nology with the effective level for previous years.
This publication will, in and of itself, be a powerful market moni-
toring tool since it will make it possible to gauge the credibility
of the information on record. With such measures in place, it
will be easy to detect any false information that is intentionally
conveyed (unrealistic data provided for initial certification with
subsequent rebalancing). If market manipulation is involved
and behaviours violate sector regulations on market abuse or
competition, punishments can be decided by the authorities in
charge of verification.
The information the capacity mechanism rules say must be
included in the certified capacity register are also required
under the provisions of Commission regulation 543/2013 of
14 June 2013 on submission and publication of data in elec-
tricity markets. Known as the “transparency” regulation, it aims
to make electricity markets more transparent by giving mar-
ket stakeholders access to a common set of data relating to
generation, transmission and consumption of electricity on
a European platform developed and managed by ENTSO-E.
The regulation provisions notably define this common set of
data and specify that data gathering is to begin late in 2014.
Market stakeholders (generators, consumers, etc.) must pro-
vide transmission system operators with different types of data
that is made public within the framework of the transparency
regulation. For instance, article 14 stipulates that transmission
system operators are to convey to the platform the sum of
generation capacity installed for all existing production units
with a power rating of at least 1 MW per production type, based
on information provided by generators. For capacity (existing
or planned) with a power rating of 100 MW or more, the trans-
mission system operator must also provide individual informa-
tion such as the name of the unit, installed capacity, voltage
connection level, etc.
Some provisions of the transparency mechanism require that
market stakeholders make public data that are also required
under the capacity mechanism rules. RTE is thus proposing that
the mechanism allow a pooling of procedures relating to data
provided for capacity certification and publication in the certi-
fied capacity register on the one hand and for publication within
the framework of the transparency regulation on the other.
This pooling ability offers advantages at different levels:
> It limits the number of declarations stakeholders have to make
and thus reduces the transaction costs the mechanism will
entail;
> It enhances the quality of consistency of the data published
by RTE.
167
MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION / 7
7.2.1.2 Reporting changes in the parameters of capacity
certification
Capacity rebalancing does more than offer flexibility to capacity
operators. Only if rebalancing procedures are followed and reba-
lancing corresponds to the physical reality will the number of
capacity certificates available on the market accurately reflect
security of supply.
The decree stipulates that “an operator of certified capacity, or
a person mandated by it, informs the public transmission or dis-
tribution system operator to which the capacity is connected
of any changes in or additional information available about the
characteristics or operating conditions of that capacity suscep-
tible of impacting its projected availability during the PP2 peak
period.” (paragraph I of article 11).
Operators have two days to file a declaration if they become
aware of any such major change in operating conditions. Decla-
rations are required for capacities with certified capacity levels
exceeding 100 MW. Changes are considered to be major when
they cause the level of certified capacity to vary by 10%.
The capacity register take into account modifications in the fore-
cast availability of units, and new declarations are made public.
All mechanism stakeholders will thus be informed of changes in
the amount of certificates in issue.
7.2.1.3 Publications relating to peak demand
management measures
The capacity register referred to in the preceding paragraph
lists the capacity certificates available, including those offered
by demand-side operators that opt for explicit valuation through
the market (certification). Other publications focus on demand.
RTE will prepare forecasts of the overall level of certificates each
year (see paragraph below), but suppliers may also organise
measures with their customers, notably to reduce the obliga-
tion to which they are subject, and these measures may impact
national demand. These measures must also be reported to give
stakeholders more comprehensive information about the sup-
ply-demand balance.
Indeed, article 18 of the decree stipulates that RTE is to create
a “register, with information provided by suppliers and consu-
mers, listing measures intended to manage demand during
peak periods”. It goes on to say that the “information contai-
ned in the register that is necessary for the market to function
properly is made public and updated in a timely manner when
changes occur”.
Consequently, the rules stipulate that measures taken by sup-
pliers and consumers to reduce their consumption during peak
periods must be recorded in this register, particularly demand
flexibility at peak that is recognised through other mechanisms
but not certified as demand response capacity. Like the data in
the certified capacity register, this information is made public,
taking into account its commercially sensitive nature.
7.2.2 Publications relating to the capacity obligation
7.2.2.1 Publication of forecasts of overall certificate
levels
To help suppliers estimate their capacity obligation level, RTE
will publish its own forecasts of the overall obligation level, i.e. of
total demand in France.
A first forecast of the total number of certificates required for
the security of supply criterion to be met will be published at
the same time as the mechanism parameters, four year before
the start of the delivery year. The overall level of certificates will
be estimated applying the same methods and parameters and
those used to calculate the obligations of obligated parties.
This forecast will then be updated annually taking into account
the data in the certified capacity and peak demand manage-
ment measure registers, along with the most recent electricity
demand forecasts. Together with the information continuously
available through the certified capacity register, this forecast will
allow give mechanism stakeholders insight into the state of the
system and allow them to act accordingly. Suppliers will notably
be able to define and adjust their strategies for covering their
obligations.
7.2.2.2 Estimation of suppliers’ obligation
The efficiency of the market model proposed is based on the
assumption that suppliers are best placed to estimate the capa-
city obligation to which they will be subject. If this was not the
case, then the single buyer (capacity auction) model described
in § 2.3, under which public authorities estimate future capa-
city needs, could be justified. During the consultation, some
suppliers expressed doubts about their ability to estimate their
capacity need and concerns that this uncertainty could interfere
with the formation of the capacity certificate price. This debate,
a recurring theme throughout the consultation, boils down to
whether the economic optimum can be achieved with a decen-
tralised market structure.
168
Without seeking to provide a definitive answer to a ques-
tion that is central to economic and political theory, it is
important to determine whether, within the guidelines
adopted, there are mechanisms that can enable sup-
pliers to evaluate their capacity need. They have all the
information required to calculate their obligation: they
are in charge of the commercial policies that shape their
customer portfolios, and the parameters for calculating
the obligation (security factor, reference temperature
and gradient) are set before the delivery year. The one unknown is
the effective consumption of their customers, but this too can be
forecast. The situation is exactly the same for them as in the energy
market (suppliers anticipate extraction levels within their perimeter
to choose their procurement strategy and thus their transactions on
the forward, day-ahead and intraday markets), and they have tools at
their disposal: the incentive created by the mechanism to manage
demand during peak periods depends on it.
When the mechanism is first implemented, RTE will help obligated
parties understand how it functions by offering to calculate what
their capacity obligation would have been in past years based
on historical consumption data provided by them, applying the
parameters and rules published. This type of exercise requires
determining, ex post, peak periods that might not match those
that would actually have been defined. The approximation can
nonetheless help stakeholders better understand how their phy-
sical data translates into a specific number of capacity certificates.
RTE is also proposing to provide each obligated party with an
estimate of its obligation after the end of the delivery period,
based on available consumption data, and of the overall imba-
lance. These estimates will be provided after the end of the deli-
very period but before the transfer deadline for a term177, ena-
bling stakeholders to trade certificates on this basis to balance
their perimeters as obligated parties and thus limit any settle-
ment to which they may be subject for imbalances.
7.2.3 Publications relating to the functioning of the capacity market
The market monitoring measures implemented will allow CRE
to enhance the transparency of the mechanism by publishing
detailed data about the functioning of the mechanism and
exchanges. Indeed, the decree stipulates that:
II. – At least once a year, the Energy Regulatory Commission
publishes, through all appropriate channels, statistical data rela-
ting to all transactions and public offers regarding capacity certifi-
cates and related products, including the volumes exchanged or
offered and prices178.
This data complements the physical data published by RTE to
provide stakeholders with a clear vision of the market and its
underlyings.
177The rules call for notification of the estimated obligation within 12 months of the end of the delivery period.
178Decree 2012-1405 of 14 December 2012, Article 17.
The purpose of the capacity certificate market is to reveal the value of contributions to security of supply. For mar-ket stakeholders to be able to assign a price to capacity certificates, they must have access to information about the general state of the system and the security of supply outlook. To this end, additional provisions have been introduced to make the market more transparent, beyond the existing mechanisms (Adequacy Forecast Reports), and correspond to best practices in terms of market transparency:
> The registers that include information about the physical state of the system will be made public (data provided at an individual level for units with power ratings of more than 100 MW, and aggregated otherwise);
> Each year, RTE will publish a forecast of the obligation level corresponding to total consumption in France, apply-ing the methods in the rules;
> RTE will assist obligated parties when the mechanism is first implemented by calculating, based on historical data, what their capacity obligation would have been in previous years;
> RTE will provide stakeholders with estimates of their obligations before the transfer deadline, based on available data;
> CRE will publish statistics on exchanges so that estimates can be made of the volumes traded or offered and prices.
169
MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION / 7
7.3 Competition in a decentralised capacity market
Creating a market that allows stakeholders to meet their capa-
city obligation will not suffice to make the mechanism economi-
cally efficient. How the market actually functions will also be key:
if some stakeholders have market power and abuse it to distort
prices, the market process will stray from the overall optimum.
Given the highly concentrated structure of the French electricity
market, particular attention was paid to competition issues in the
future capacity certificate market during the preparation of the
decree and the consultation of 2013. The decree was drafted
and the rules designed with these issues in mind (§ 7.3.1). None-
theless, it seems that the combination of a decentralised market
architecture and the ARENH scheme implemented in 2011 to
support the deregulation of the supply market in France require
a re-examination of the competitive structure of the capacity
certificate market (§ 7.3.2). The decree also introduced special
market monitoring procedures that will be that much easier to
put into practice thanks to the transparency of the registers,
proof that these considerations were taken into account from
the beginning of the mechanism design process (§ 7.3.3).
7.3.1 Competition and market power
Energy markets can only be efficient if there is free and undis-
torted competition between market participants. Various mea-
sures have helped to reduce the market power of incumbent
operators: the development of cross-border interconnections,
the harmonisation of methods for allocating rights to use inter-
connections, the development of implicit allocation methods
for exchange capacity (market coupling) and the harmonisation
of rules governing exchanges in different Member States. Ope-
rators’ positions and ability to influence markets are increasingly
being measured at the regional, and even European level.
Capacity mechanisms are being created in Europe under the
aegis of Member States that are responsible for their own security
of supply. This domestic focus has been a source of concern for
the European Commission, which expressed its reservations and
expectations in the guidelines published in November 2013179:
> Lack of competition in national energy markets could lead to
market manipulations that threaten security of supply:
Appropriate structural solutions to address problems of mar-
ket concentration leading to underinvestment should be
identified and implemented180.
> Public interventions to ensure security of supply could distort
competition at the national and transnational levels:
In concentrated markets, interventions to ensure generation
adequacy risk rewarding dominant incumbents for withhol-
ding strategies. In particular capacity mechanisms risk repli-
cating, or even embedding, problems of market concentra-
tion which exist in some Member States181.
There is a high degree of concentration in the French electri-
city market: incumbent operator EDF has a dominant position in
electricity generation and supply.
101. In 2011, EDF claims to have had 79.4% of electricity gene-
ration capacity in France. This includes 92% of nuclear capa-
city (EDF operates all nuclear power stations in France though
competitors hold drawing rights on some of them based on
industrial contracts), 66% of fossil-fired capacity (coal, fuel oil
and gas), 81% of hydropower capacity and 32% of renewable
energy capacities. Even excluding the capacity certificates
associated with ARENH rights, as provided for in the NOME Act,
it seems that EDF will still have a majority of capacity certificates.
102. At the same time, CRE’s market observatory showed that
in 2011, EDF and public local distribution companies supplied
94% of residential consumption and 78% of consumption at
non-residential sites (EDF accounts for a very large share of
this total). EDF will consequently by far need the most capa-
city certificates182.
This situation is mainly a reflection of the energy policy choices
France made in the past, which gave the incumbent operator a
nuclear power generation fleet that is competitive at the natio-
nal and European levels. However, this does not means that its
dominant position is abused:
> Market concentration is measured by the number of stake-
holders in a market and their respective market shares. This
measurement can be taken on the supply or the demand side;
> A stakeholder’s market power refers to its ability
to cause market prices to move away from the
level that would be achieved in a market charac-
terised by pure and perfect competition, for its
own benefit;
> The exercise of market power refers to a situation
where a stakeholder takes advantage its market
power. This usually detracts from the collective
179[EC, 2013a]
180[EC, 2013a]
181[EC, 2013a]
182[Competition Authority, 2012a]
170
well-being and enhances the profits of the stakeholder in
question. Competition law only punishes the abuse of domi-
nant position183.
The two do not always go hand in hand. A market can be
concentrated without the company or companies with signifi-
cant market share necessarily having market power, especially
if regulations are in place to keep the market competitive. Simi-
larly, market manipulation can be seen in markets with relatively
low concentration levels, as evidenced in studies focusing on
the “pivotal” role played by some firms in specific instances, such
as the California crisis of 2000-2001184. Lastly, market power is
only a potentiality, and will not necessarily be exercised: just
because a stakeholder’s position would allow it to distort com-
petition does not mean it will do so.
While it seems clear that greater vigilance is required with regard
to the design of mechanisms that could reinforce dominant
positions, this should not be considered sufficient reason to
avoid implementing such mechanisms. First, there are already
specialised authorities in place to evaluate market functioning
and deal with abuses of dominant position. Second, the regula-
tory framework in France already includes provisions intended
to promote competition: the Regulated Access to Incumbent
Nuclear Electricity (ARENH) scheme offers a structural and
appropriate solution to market concentration in France185.
Lastly, the assessment by public authorities, for instance in the
Poignant-Sido report, did not focus on the possibility that the high
level of concentration in the French market could lead to strate-
gic underinvestment. On the contrary, the workgroup focused on
how to fairly divide responsibility for investments in peak gene-
ration facilities that are not profitable in the energy market des-
pite the positive externalities they create, a responsibility that has
hitherto been implicitly borne by the incumbent operator.
The purpose [of a capacity obligation] is to distribute
responsibility for insurance against the risk of a gene-
ration shortfall186.
On the other hand, the European Commission’s
concerns suggest that a close look must be taken
at how the provisions proposed could, once imple-
mented, allow strategic behaviours, particularly capa-
city withholding. It should be recalled that a portion of
the Competition Authority’s review of this question in
April 2012 focused on the robustness of the mecha-
nism with regard to capacity withholding strategies.
It found that the introduction of a safety net mechanism created
capacity withholding risks by permitting opportunistic behaviours
by generators (artificially minimising the availability of their gene-
ration capacity to activate the mechanism), and suggested that
operators not be allowed to commit to availability levels below
their historical average to prevent strategic behaviours.
These concerns have been taken into account. The safety net
mechanism is indeed reserved for exceptional circumstances,
and the procedures in place will make it easy to see if opera-
tors are significantly underestimating the future availability of
their capacity. Indeed, the transparency of the certified capacity
register will allow all parties to identify any capacity withholding
strategies, including preventively by comparing the amount of
capacity certified for a given year to levels from previous years.
Another concern is whether the capacity obligation could create
entry barriers in an already complex regulatory environment. The
certification methods proposed in the rules (neutrality between
all technologies) ensure equal treatment for all capacity operators
(generation, demand response or storage) and prevent forms of
selection that could exclude new entrants. In the supply market,
the capacity obligation adds another layer of complexity that
could be seen as an obstacle for new entrants, or as an oppor-
tunity: it applies to all stakeholders, but each supplier can forge
its own strategy for covering the obligation. This new facet of the
supply business creates opportunities for stakeholders to dif-
ferentiate their offerings and stimulate competition. Lastly, the
verification procedures proposed ensure that stakeholders are
not subject to excessively onerous declaration requirements and
take special care to avoid imposing a segmentation of demand
response entities, as discussed in sections 5.6 and 5.7.
7.3.2 Competition under the capacity mechanism
Market power is hard to quantify as many factors must be taken
into account, and some of them might not be measurable. It is
nonetheless possible to select an indicator of the competitive
situation, a simplified one necessarily, and to consider the effects
of the market architecture adopted with regard to this indicator.
183Article 102 of the TFEU and article L. 421-2 of the French Commercial Code.
184[Wolak, 2003]
185Appropriate structural solutions to address problems of market concentration leading to underinvestment should be identified and implemented [EC, 2013a].
186[Poignant-Sido, 2010]
The French electricity market is highly concen-trated and this would be problematic if it resulted in market manipulation. However, it has not led to underinvestment and thereby not created any security of supply risk. Special attention was nonetheless paid to this situation in designing the capacity mechanism rules.
171
MARKETFUNCTIONING:TRADING,TRANSPARENCYANDCOMPETITION / 7
For instance, market concentration is a traditional measurement
for assessing competition. This type of analysis can be conduc-
ted on the capacity certifi cate market, though the specifi cs of
the market architecture must be taken into account. In the sec-
tions below, the eff ects of two aspects of the market architec-
ture on the structure of the market - its decentralised nature
and the ARENH scheme - are analysed.
7.3.2.1 Eff ects of a decentralised architecture on the
market’s structure
In a centralised market, a stakeholder’s market power depends in
large part on its market share, or in other words its share of the
total capacity certifi cates issued for a given delivery year. With a
capacity auction scheme modelled after the mechanisms in place
in the Eastern United States, market concentration would thus be
largely determined by the market shares held by generation and
demand response capacity operators. In a decentralised market,
a vertically integrated company must also cover its own needs: as
such, its potential market infl uence is primarily determined not by
its absolute position but rather by its net position.
The signifi cance of net positions is one eff ect often cited when
vertical integration is a factor:
In evaluating proposed horizontal mergers in vertically sepa-
rated markets, antitrust agencies (and courts) focus primarily
on […] the concentration levels in the industry prior to the
merger and the predicted change in concentration levels
due to the merger, where concentration is measured using
the HHI. […] [Generalizing] the analysis to vertically integrated
markets suggests that analysts use the fi rms’
net positions to measure the eff ects of market
power. As noted above, zero net demand causes
no ineffi ciency187.
This eff ect is particularly pronounced in France,
given the incumbent operator’s share of the gene-
ration and supply markets. Estimated on the sole
basis of certifi ed capacity, the concentration level is
very high. However, if the incumbent’s net position
is considered, then its weight in the market is relative since it
also has a signifi cant share of the supply market. In this regard,
the decentralised market architecture is particularly suited to
conditions in the French market, as some academic studies
have noted:
Considering the specifi c characteristics of the French electricity
market, with a high degree of vertical integration, and the way
competition was organised by the NOME scheme, […] the criti-
cism directed against [the decentralised obligation] is not valid188.
The decentralised architecture and vertical integration also
impact diff erent stakeholders’ incentives. A stakeholder that has
capacities will not necessary want to see the capacity certifi cate
price increase: it can actually have more to lose than to gain if it
is a net buyer.
Vertically integrated wholesalers, or those with long-term
contracts, have less incentive to raise wholesale prices […].
Findings suggest that vertical arrangements dramatically
aff ect estimated market outcomes. Had regulators impeded
vertical arrangements (as in California), simulations imply
vastly higher prices than observed and production ineffi cien-
cies costing over 45 percent of those production costs with
vertical arrangements. We conclude that horizontal market
structure accurately predicts market performance only when
accounting for vertical structure189.
These considerations support the use of a market concentra-
tion indicator that takes the eff ects of vertical integration into
account.
7.3.2.2 Measures to stimulate competition
The NOME Act190 provided a structural response to competi-
tion issues in the French electricity market by introducing, from
2012, the ARENH mechanism (Regulated Access to Incumbent
Nuclear Electricity). Developed in cooperation with the European
Commission, this scheme is designed to promote competition
187[Hendricks & McAfee, 2010]
188[Finon, 2011]
189[Bushnell et al., 2008]
190Law 2010-1488 of 7 December 2010 on the New Organisation of the Electricity Market.
Awordaboutthisdiscussionofmarketpower
The reasons why market power exists can be nume-
rous and complex, and they cannot be covered solely
by analysing market concentration in terms of absolute
or net positions. Other factors can include the pivotal
role played by certain fi rms in the market, the elasti-
city of supply and demand curves and the existence
or absence of entry barriers. The indicators calculated
in the sections below do not take these consideration
into account, and thus only off er a partial picture of the
competitive situation. They are not meant to be subs-
tituted for a real analysis of competition in the French
electricity market, but rather to illustrate, through
simple orders of magnitude, the consequences of the
architecture choices made for the capacity market.
172
in the supply market by giving alternative suppliers direct and
regulated access to electricity generated by the incumbent’s
historical nuclear fleet on economic terms equivalent to those
of the incumbent operator:
To ensure that consumers are free to choose their
electricity supplier, and that pricing across the
country and all consumers benefit from the compe-
titive pricing of power generated with the historical
nuclear fleet, it will be possible, during a transitional
period defined in article L. 336-8, for all operators
supplying final consumers in continental France, or
system operators for their losses, to have regulated
and limited access to nuclear power generated by the
incumbent at the nuclear power plants mentioned in
article L. 336-2.
This regulated access is granted on economic terms
equivalent to those resulting for Électricité de France
from the use of the nuclear power plants mentioned
in the same article L. 336-2191.
The ARENH scheme shapes how the French elec-
tricity market functions if the ARENH price is com-
petitive relative to the wholesale market price, i.e.
if nuclear power generated with the incumbent
fleet is competitive relative to electricity generated
in Europe: in this case the market functions as if all
suppliers had a form of vertical integration between
upstream and downstream operations through the
property rights they hold to a portion of incumbent
nuclear electricity.
A similar effect can be seen with the capacity
mechanism: the decree of 2011 specifying how
the ARENH scheme functions indicates that an
alternative supplier that exercises its ARENH rights
will also have access to the corresponding capacity
certificates192:
The [ARENH] product includes the generation capa-
city certificate, as defined in article 4-2 of the afore-
mentioned law of 10 February 2000, corresponding
to its profile.
This is a particularly important point with regard to
competition, since it means that all suppliers, inclu-
ding those that do not operate any capacity, benefit
from a vertical integration effect through ARENH without bea-
ring any more costs than they did before the capacity mecha-
nism was implemented.
In concrete terms, there is no guarantee that the incumbent
operator will be a net seller of capacity certificates, whereas
some alternative suppliers with capacity will be “long” on cer-
tificates when the mechanism first takes effect. Over the longer
term and provided that the ARENH price remains competitive,
suppliers’ net positions will be determined by the temperature
sensitivity of their customer portfolios with regard to the ARENH
capacity rights held.
The capacity value associated with the ARENH can be made
available in two ways:
> The first involves the transfer of “physical” capacity certificates
from EDF to alternative suppliers, which could then use these
certificates to meet all or part of their obligation;
> The second involves financial transactions: EDF would hold all
capacity certificates allocated to the nuclear plants and sell
them on the capacity market, with the proceeds passed on to
alternative suppliers in proportion to their ARENH rights.
The decree instituting the capacity mechanism tasks the Energy
Regulatory Commission with proposing specific procedures to
the Minister. When this report went to press, CRE’s intentions in
this area were not known. If it opted for a financial treatment
of ARENH rights, the market would be more concentrated, but
probably more liquid as well. Measuring these conflicting effects
from a competition standpoint is complex and would require an
in-depth analysis that RTE did not conduct. In the rest of this
report, only a system involving the “physical” transfer of capacity
certificates is considered, as the simplified indicators used are
meaningful with this assumption.
7.3.2.3 Simulations of concentration in the capacity
market
The decentralised organisation of the capacity mechanism and
initial allocation of capacity certificates to alternative suppliers
provided for under ARENH have combined effects on market
concentration. These effects were studied through a simulation
wherein the certification and obligation levels of all capacity mar-
ket stakeholders, suppliers and capacity operators, were calcula-
ted for the years 2006 to 2011193. Market concentration is measu-
red using the Herfindhal-Hirschmann Index (HHI)194.
The study focused first on the effect of the decentralised mar-
ket architecture with vertical integration. The HHI is calculated
191L. 336-1 of the Energy Code.
192Decree 2011-466 of 28 April 2011 setting out the rules for access to historical nuclear energy, Article 1, V.
193Calculations have been simplified and do not correspond exactly to the final capacity mechanism rules. However, the results suggest orders of magnitude, since the simplifications are not unidirectional. Simulations were carried out a time when all rules and parameters of the French capacity mechanism were not known with certainty. The most significant approximations calculated for the purposes of this study are: the peak periods considered are placed within the calendar year on the winter days when demand is highest, with a maximum of five days in March and November; accounts are separated for capacities subject to purchase obligations; hydro capacities are overestimated (technical limitations not factored into the study), some capacities connected to the distribution grid are not allocated. The orders of magnitude shown in the results are thus significant, but must be considered as estimates rather than exact values.
194The Herfindhal-Hirschmann Index, or HHI, is a measurement of market concentration that indicates the degree to which a market shows one characteristic of pure and perfect competition: market atomicity. The HHI is calculated as the sum of the squares of the market shares of each participant (expressed as a percentage).
173
MARKETFUNCTIONING:TRADING,TRANSPARENCYANDCOMPETITION / 7
based on stakeholders’ net positions, or in other words the dif-
ference between the capacity certifi cates allocated to their cer-
tifi ed capacity and their capacity obligations. Integrated compa-
nies are therefore considered net buyers or sellers, depending
on the respective weightings of their generation and supply
activities.
Two slightly diff erent market concentration indicators are com-
pared: an HHI calculated using absolute positions and an HHI
based on net positions. Neither measures the competitive situa-
tion perfectly, but the comparison does illustrate how taking
into account the eff ects of vertical integration in a decentra-
lised market makes it necessary to reconsider how competition
actually works.
The second eff ect studied is that of the ARENH, which reba-
lances stakeholders’ positions by enhancing the vertical integra-
tion of new entrants. Its impact is estimated by comparing two
HHIs, one with and one without ARENH, taking net positions into
account.
Net sellers of capacity certifi cates are considered separately
from net buyers. This gives a better indication of market power,
which is mainly the result of a stakeholder’s net position in the
market once its own needs have been covered. A stakeholder
that has exactly enough capacities to meet its own needs will in
theory not be able to infl uence the market price since it will not
be buying or selling.
With this approach, it is possible to compare the respec-
tive eff ects of the decentralised architecture and the
ARENH scheme on market concentration in France’s
situation. Looking at the market concentration of sellers
of capacity, we can see that, on average195:
> A decentralised market reduces HHI market
concentration by 3,000 points compared with a
centralised market;
> The existence of the ARENH scheme reduces the
HHI of the capacity market by 2,400 points.
These eff ects are cumulative. The combination of a decentra-
lised market with the ARENH regulation to increase competition
yields a picture of market concentration that is diff erent from
the initial perception.
Having a decentralised architecture and the ARENH scheme in
place to strengthen competition yields market concentration
levels that are generally considered acceptable. In the chart
above, the black line corresponds to a HHI of 2,500, conside-
red the limit between high and moderate concentration levels
under the defi nition applied in the United States196. The HHI of
net sellers of capacity certifi cates dips in one year below 2,000,
this being the level below which the European Commission says
it is unlikely to identify competition concerns197.
As mentioned above, the indicators presented here do not allow
conclusions to be drawn about the real state of competition in
195Based on aforementioned hypotheses and averaged results from data for 2006-2011.
196[DOJ, 2010]
197Guidelines on the assessment of horizontal mergers under the Council Regulation on the control of concentrations between undertakings, paragraphs 16, 19 & 20.
HH
I
High concentration
Moderate concentration
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
2006 2007 2008 2009 2010 2011
ARENH effect
Decentralised marketand vertical integration
Figure 77 – Illustration of the eff ects of market architecture and the ARENH on concentration in the capacity market based on past data
HHI Capacity operators
HHI Net sellers w/o ARENH
HHI Net sellers
HHI Net buyers w/o ARENH
HHI Net buyers
174
the French electricity market. On the other hand, they do show
that the market architecture chosen has an impact on effective
competitive conditions.
7.3.2.4 Anticipated trends in market concentration with
the development of demand response
The market concentration estimates presented above are based
on past data. Anticipating future trends requires taking into
account the development of new resources, notably demand
response, and other measures that have a dynamic impact on
demand, particularly during peak periods in winter.
This is an important point since a highly concentrated market
will be less susceptible to the exercise of market power if it can
be easily challenged in the absence of entry barriers. The speci-
fic characteristics of certain types of demand response (notably
industrial), some of which may have lower fixed costs than gene-
ration capacities, place them in a good position to challenge
dominance in the capacity market. This is in keeping with the
objectives of the mechanism outlined in chapters 1 and 2: the
French capacity mechanism must allow demand response to
play its rightful role in ensuring that there is adequate capacity
for supply and demand to balance.
The architecture of the French electricity market has evolved
recently to allow the explicit participation of demand response
in energy markets, including demand response aggregators198.
Consumers and aggregators thus have access to all electricity
markets (balancing mechanism since 2003, “rapid and comple-
mentary reserves” since 2010, wholesale electricity
market since 2013 and system services as of 1 July
2014). There are no restrictions on this participa-
tion since the agreement of site suppliers is not
required199.
The goal in creating this framework for rewarding
demand response is to encourage the development
of its potential and the role of demand-side opera-
tors in France. Their participation in electricity mar-
kets should help reduce concentration in the energy
market and the capacity market, in which demand
response capacities can also participate explicitly200.
The introduction of the capacity mechanism can
in turn boost competition in other markets, inclu-
ding the energy market. Encouraging the develop-
ment of capacities other than energy production by
rewarding their contribution to security of supply
can help diversify the energy mix and the structure of the mar-
ket. The high capacity value of demand response, the potential
of which reaches its height during peak periods, will stimulate
the development of capacities that will also participate in the
energy market.
7.3.3 Monitoring of the market’s functioning
7.3.3.1 The need for monitoring
The preceding sections outlined competition issues in the capa-
city market and provided evidence that in the final analysis, a
decentralised mechanism, taken together with ARENH, a struc-
tural measure that strengthens competition in the supply mar-
ket, creates a much more complex competitive situation than
what is often described.
In practice, assuming that ARENH-related transfers will be “phy-
sical”, all suppliers will be allocated enough capacity certificates
initially to meet all or part of their obligation. In other words, the
capacity market could function with all stakeholders starting out
with more or less balanced positions: none would have to buy all
of the certificates needed to cover its needs, a factor that drasti-
cally reduces the opportunities for exercising market power.
However, in this scenario, trading volumes are likely to be low,
and this will make the capacity certificate market less liquid. In
this sense, the physical transfer of capacity certificates associa-
ted with ARENH rights will reduce certificate trading volumes,
whereas a financial treatment would increase it. Under these
conditions, it seem necessary to set up an exchange platform, as
mentioned earlier, to concentrate liquidity and make it easier for
a credible reference price to be formed. A geographic extension
of the market would also enhance liquidity, which is why efforts
198These changes are discussed in chapters 1 and 10 of this report.
199The demand-side operator's regulated access to the consumer is based on Competition Authority recommendations and the implementation by RTE, under the supervision of CRE, of the new organisation of the regulatory framework for demand response called for in the Brottes Act [Competition Authority, 2012b], [Competition Authority, 2013]
200The participation of demand response in energy markets is discussed in detail in chapters 1 and 10 of this report.
Taking into account the decentralised architec-ture of the mechanism and the vertical integra-tion effects resulting from the ARENH scheme gives a more accurate picture of the capacity market. The competitive situation in the capac-ity market thus appears more favourable than initially thought.
Moreover, competition in the energy and capacity markets will be mutually strengthened, notably through the development of demand response. The French capacity mechanism could thus allow demand response to play a key role in “rounding out the capacity equation”, making it harder for stakeholders to exercise market power while also reducing costs.
175
MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION / 7
undertaken with other Member States to promote common
approaches are so important.
Nonetheless, capacity certificate trading will have to be closely
monitored in the beginning to ensure that the mechanism is
functioning properly.
With this in mind, the regulatory authority decided from the out-
set to give the regulator the resources to efficiently monitor the
functioning the capacity certificate market. It notably stipulated
that all transactions involving capacity certificates were to be
notified to CRE, a requirement that will cost almost nothing if
the notification procedure is coupled with the capacity certifi-
cate register recording all exchanges of certificate:
The procedures for collecting this data are defined by the
Energy Regulatory Commission after prior consultation with
the public transmission system operator201.
7.3.3.2 Efficiency in detecting market manipulation
How efficiently the capacity certificate market is monitored
should be considered in the light of market manipulation oppor-
tunities. As indicated earlier, the concerns voiced by the Com-
petition Authority in April 2012 and reiterated in the European
Commission’s recent Communication focus specifically on the
exercise of market power by the incumbent operator and pos-
sible capacity withholding strategies.
Where the incumbent operator is concerned, specific pro-
visions allow CRE to get information about the exchanges it
makes, including the cost of internal transfers. Decree 2012-
1405 of 14 December 2012 provides for two different entities
for capacity operators (capacity portfolio manager) and the
obligation (supplier). This provision, which applies to all stake-
holders, enables monitoring of vertically integrated companies.
As specified in article 17 of the decree, CRE must be notified of
exchanges conducted between these entities:
Any person that transfers a capacity certificate or related pro-
duct, or makes a public offer to buy or sell capacity certificates
or related products, informs the Energy Regulatory Commis-
sion, directly or through a third party, of the characteristics of
the transfer or offer, particularly the price202.
As for the mechanism’s vulnerability to capacity withholding
strategies, the transparency measures adopted in the rules for
the registers should make it easy for market stakeholders or
monitoring authorities to detect any abusive practices. In this
regard, the transparency of the registers will be key to resolving
the issue discussed in chapter 5 about stakeholders’ ability to
rebalance at zero cost. During the consultation, some stake-
holders suggested that while the ability to rebalance at zero
cost before the delivery year gives virtuous operators the flexi-
bility needed to manage their capacity commitments, it could
also create inexpensive market manipulation opportunities for
others. RTE took this point very seriously: the solution it adop-
ted in the capacity mechanism rules was to insist on maximum
transparency (declarations for capacities of more than 100 MW
recorded including names and made public, regulation of “signi-
ficant” rebalancing volumes representing more than 10% of cer-
tified capacity) rather than introduce more complexity, for ins-
tance by making an operator’s ability to rebalance conditional
upon its market power.
Likewise, there is no plan to require that capacity operators’
commitments be based on availability levels from previous
years, as the Competition Authority suggested in 2012, since
this could distort the incentives created by the mechanism,
which are currently based exclusively on commitments. There
is no need for such regulation mechanism in the energy
market, for instance, to ensure that supply commitments are
coherent. However, past availability data will be made public
for each capacity, and CRE will be able to use them in monito-
ring the market.
Taking into account these measures, which are stipulated in the
decree and put into practice in the rules, CRE estimated in its
opinion of April 2012 that it was in a position to ensure that the
capacity market functions properly:
CRE estimates that its market monitoring tasks, both upstream –
where it can track and monitor all transactions, including those
relating to self-supply – and downstream – where it can ensure
that suppliers’ commitments are consistent with
their purchasing costs – will allow it to ensure that
the capacity mechanism does not interfere with
competition in the downstream market.
If a dysfunction is observed, CRE will propose
to the Minister any measures necessary to gua-
rantee that competition is effective, both in the
upstream and downstream markets203.
The Energy Regulatory Commission will regularly
submit reports on its monitoring activities to the
Energy Minister:
201Decree 2012-1405 of 14 December 2012 relative to the contribution of suppliers to security of electricity supply and to the creation of a capacity obligation mechanism in the electricity sector, article 17.
202Decree 2012-1405 of 14 December 2012, Article 17, paragraph 1.
203[CRE, 2012]
176
7.4 Conclusions
The capacity obligation is designed to safeguard security of
supply, and the capacity market associated with it is intended
to minimise the cost. This will be an economically efficient archi-
tecture for delivering a public good (security of supply) provided
that transaction costs are sufficiently low. The trading of capa-
city certificates and the functioning of the market are thus extre-
mely important, and their efficacy depends on three factors: the
existence of a robust framework to govern exchanges, a high
degree of transparency, and effective competition.
First, the market is designed to function in such a way as to
facilitate exchanges and give stakeholders confidence in the
“capacity certificate” product. Since the mechanism parameters
are published ahead of time and remain stable throughout the
mechanism term, trading can take place in a stable regulatory fra-
mework and the value of the product cannot be modified by the
intervention of forces external to the market. Though it creates
greater uncertainty when the parameters are being set, this pro-
vision appears indispensable for the market to function properly.
Moreover, the fact that the movements of capacity certificates are
recorded in a register kept by RTE makes the product credible. In
this regard, the architecture adopted is similar to that
of the energy market: it enables bilateral trades and
leaves room for the creation of an exchange platform
on which supply and demand can be matched. This
organisation of exchanges appears necessary given that the mar-
ket is unlikely to be very liquid.
As regards transparency, various provisions allow stakeholders
to participate in the capacity market with full knowledge of the
security of supply outlook. In addition to the Adequacy Forecast
Reports RTE already publishes, they will have access to data
from two registers maintained by RTE:
> The certified capacity register, listing all certified capacities
individually;
> The peak demand management register, listing all demand-
side measures that impact the mechanism.
In addition, RTE will help obligated parties become familiar with
the mechanism and send them estimates of their obligation.
Lastly, CRE will publish data on the market’s functioning and
transactions, helping stakeholders to assess the prices observed
in the market.
The last requirement for the market to function properly –
effective competition – was undoubtedly the biggest source
of concern about the mechanism both in France and Europe.
Given the high level of concentration around the incumbent
operator in the French electricity market, some feared that there
would be no real competition in the capacity market, and that it
could even have harmful consequences for the supply market.
I. No later than one year after the capacity mechanism rules
are published, and at least once a year after that, the Energy
Regulatory Commission submits to the Energy Minis-
ter a report on the functioning of the capacity certificate
market204.
7.3.3.3 Public offerings
Lastly, to prevent potential capacity withholding strategies,
article 6 of the NOME Act stipulates that:
All certified capacity certificates must be made available to
suppliers, either directly or indirectly, to allow the obligation
mentioned in the same article to be met. Capacity certificates
held by a supplier beyond what is needed for it to meet its
obligation must be offered for sale publicly.
To put this provision into practice, the capacity mechanism rules
call for public offerings to be organised once obligated parties
have received the final notification of their capacity obligation.
204Decree 2012-1405 of 14 December 2012, article 19.
Measures included in the market architecture to strengthen competition play a preventative role, but the functioning of the market must also be closely monitored by CRE. Market monitoring will be that much more important since the market is not expected to be very liquid. The monitoring and transparency measures set out in the decree and the rules complement one another to form what is considered a sufficient framework, based on current needs, as the publication of the infor-mation in the registers should allow any suspi-cious behaviours to be easily detected.
177
MARKET FUNCTIONING: TRADING, TRANSPARENCY AND COMPETITION / 7
A more careful analysis of the market structure nonetheless
paints a different picture of the risk that market power will be
exercised. Factoring in the decentralised nature of the market,
and the vertical integration effects created by the measure-
ment of stakeholders’ net positions, market concentration will
be lower than initially thought. The benefits alternative suppliers
will derive from the capacity certificates associated with ARENH
rights will also significantly reduce market concentration. In this
regard, the risk of market power being exercised seems limited.
Thanks to the verification and monitoring procedures that are
integrated into the mechanism through the certified capacity
register, the regulator will be able to detect any abusive prac-
tices and track all exchanges.
Lastly, it would be limiting to view the capacity mechanism solely
as a threat to competition in the electricity market. By encou-
raging the development of demand response, it will allow new
capacities to compete with existing ones, including in energy
markets. Moreover, by adding another dimension to the supply
business and creating new activities, it will favour a diversifica-
tion and differentiation of offerings, depending on the strategies
stakeholders adopt to meet their obligation (a similar philoso-
phy is applied in the mechanism proposed by the BDEW in Ger-
many). In a word, this new market mechanism will be a source of
many opportunities for the most efficient stakeholders.
178
8. CAPACITY MECHANISM IMPACT ASSESSMENTS
There has been a gradual paradigm shift in public decision-
making in recent years, both in France and Europe. Preliminary
assessments are now required to ensure that planned measures
are necessary and proportionate, and once in effect, these mea-
sures are subject to regular evaluations in case modifications are
required.
The capacity mechanism is being introduced against this backdrop.
Where the initial impact assessment is concerned, RTE’s pro-
posed capacity mechanism rules include an analysis of the
cost to consumers. Provisions are also in place to allow the
mechanism’s functioning to be gradually adapted as feed-
back is received, as the decree of December 2012 calls for the
Energy Regulatory Commission to regularly prepare reports on
the functioning and integration of the capacity mechanism.
Based on these reports and the assessments RTE will conduct in
accordance with the rules, it will be possible to adjust, adapt or
even reform the mechanism. In a word, the existing regulatory
framework and proposals for putting it into practical application
are intended to achieve compliance with best practices in the
area of public policymaking.
Many studies cited in the previous chapters aim to quantify the
effects of decisions made about different mechanism parame-
ters. While they provide useful information, it is also necessary
to evaluate the aggregate effects the provisions proposed will
have on the functioning of the energy market and investments.
This evaluation allows the cost of the mechanism to be mea-
sured against its security of supply benefits for the consumers
that finance it. A specific difficulty arises with this type of analy-
sis: to be accurate, it must take into account all of the capacity
mechanism parameters, but these are still being determined
through a consultation with stakeholders and are thus changing
frequently. Moreover, experience has shown that when models
of the functioning of capacity mechanisms are produced hastily,
the results are unusable since the situations modelled do not
correspond to reality.
This chapter takes account of this dichotomy. It begins by pres-
enting the challenges posed by detailed modelling of the func-
tioning of capacity mechanisms (§ 8.1) and then outlines the
difficulties associated with dynamic aspects, underscoring how
the analyses currently being considered at the European level to
model the French mechanism need to be expanded (§ 8.2). The
next section presents aspects of the initial impact assessment
focusing on the financial consequences for consumers of the
mechanism’s implementation, on an all other things being equal
basis (§ 8.3). The last section is devoted to putting into context
the results of the research efforts under way, which will serve
as a basis for the different steps in the implementation process
provided for in the decree (§ 8.4).
8.1 Challenges associated with detailed modelling of how capacity mechanisms function
8.1.1 Analysis of technical parameters
During the consultation on the rules, special attention was paid
to quantifying the effects of the technical provisions RTE was
proposing. Numerous studies discussed in chapters 4, 5 and 6
allow the impact of the different aspects of the mechanism to
be quantified. All in all, some 30 studies and simulations were
carried out, and the results were presented during the consulta-
tion to inform the discussions.
Some of the most significant results of these studies were:
> Taking temperature sensitivity into account in the parame-
ters for calculating the capacity obligation ensures that the
obligation is borne by temperature sensitive consumers,
which indeed represent the biggest risk to the power system.
Large consumers that can reduce load during peak periods
consequently have a zero obligation;
> A targeted PP1 period provides an incentive to reduce load
during peak periods, when security of supply is at risk. This
179
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
increases competition between capacity suppliers that can
respond to the needs of the power system, and thus helps
lower costs;
> Similarly, the value of demand response capacity is maximised
by defining a short PP2 period.
8.1.1.1 Use of a simulator during the consultation
In addition to being a forum for sharing technical results, the
consultation was enhanced from the outset by an original fea-
ture: market stakeholders were given access to a free, calibra-
ted and open source supply-demand balance simulator205. RTE
developed this simulator206 specifically for the consultation, to
allow each stakeholder to assess the impacts of the key choices
made regarding the certification method and the impact of
parameter choices.
RTE issued nine free user licences to market stake-
holders and administrations. The tool illustrated the
benefits of measuring a capacity’s contribution to
reducing the shortfall risk based on availability rather
than solely on installed power. It also supported the
choices made with regard to the parameters used in
the certification method, especially the considera-
tion of technical and management constraints that
affect capacities’ contribution to reducing the shortfall risk.
As a follow-up, a new simulator, in the form of a serious game,
will be made available to consultation participants, authorities
and other interested parties so they can see how the market
will function, from the certification process through to the post-
delivery year period (§ 8.4.1).
205The simulator was made available on request by RTE with free licences for the purpose of the consultation.
206The simulator is called CLAC (Capacity Lab – Aide à la Certification).
BASIC MODULEOptimisation
in period T
ADVANCED MODULE
Optimisationover T1
Optimisationover Ti
Optimisationover TN
LT > STDivision into sub-scenarios
T > T1 … Ti … TN
LT analysis
Model 1
Model 2
ST analysis
Results processed
Model parametersST
Simplified, fictional mix
N contingency scenarios
Setting of LT parameters
Figure 78 – Functional diagram of the simplified open source supply-demand balance simulator
8.1.2 Assessment of the aggregate effects of the mechanism
Analysing the economic impacts of the mechanism requires
taking a step back from the technical discussions relating to
the obligation, certification and settlement processes and
evaluating the consequences of the mechanism’s aggregate
effect on different categories of stakeholders to inform the
public authorities charged with making decisions about the
proposals.
To be thorough, this impact assessment must compare (i) the
charges specifically associated with the capacity obligation
borne by consumers (costs) and (ii) the effects of the security
of supply protection provisions (benefits) in two alternative
scenarios:
> A scenario with no capacity mechanism in place: consumers
are exposed to the market price in the same was as today (fac-
toring in the complexity of the regulatory framework). Capa-
cities do not generally receive any specific remuneration for
contributing to security of supply. The energy price is the
economic signal relied upon to optimise both the short-term
functioning of generation resources and long-term invest-
ment decisions;
> A scenario with a capacity mechanism introduced in accor-
dance with the rules proposed by RTE.
180
There is nothing simple about this type of analysis.
First (1), for the “no capacity mechanism” scenario to be a cre-
dible reference, it has to model in detail how the existing market
functions. This poses several problems.
With the way power systems are currently organised in Member
States, some capacities already benefit from a form of capacity
remuneration through different means (particularly by being
included in the reserves system operators use for real-time
balancing) while others receive subsidies that disconnect them
from price signals: a model of the existing market’s functioning
cannot disregard these realities or their impact on the market.
Moreover, the market’s functioning in periods of tight supply
does not follow the theoretical principles (real, albeit infrequent,
extreme price spikes during which time supply to consumers
depends on their marginal willingness to have power supply
interrupted) supporting the energy-only model’s ability to gua-
rantee the optimal remuneration of generation and demand
response capacity. In practice, this form of market organisation
has consequences for investment structures (underinvestment
in peak versus base-load capacity) and security of supply (load
shedding), and these consequences are borne by consumers,
either through what they pay for supply or through a level of
security of supply that fails to meet the objective set by public
authorities.
Second (2), it is difficult to quantify the effects the proposed mar-
ket models could have over the medium or long terms, as dyna-
mic analyses of the functioning of complex markets subject to
multiple regulations over a long period are particularly challen-
ging. To obtain meaningful results, the specific characteristics of
the different capacity mechanisms adopted must be accurately
modelled. For the French mechanism, this would notably require
factoring in the impact of the active capacity need management
promoted through the mechanism’s decentralised architecture,
as this could reduce the overall cost of covering the shortfall risk
compared with a situation where capacity adequacy is managed
passively. Transaction costs would also have to be evaluated.
Different descriptions of the functioning of capacity mecha-
nisms have been presented since European authorities began
to express concerns about the development of national mecha-
nisms. Some of these descriptions do not seem compelling:
either the mechanisms are described in summary form, in which
case the results reflect the crude nature of the initial assump-
tions, or they are modelled in detail but using simulations that
only show costs in a static manner, without considering how
these costs will influence the behaviour of those that bear them.
The sections below illustrate this dichotomy:
> Careful analysis of reports, such as the one appended to the
summary of the public consultation organised by the Euro-
pean Commission on the internal market and published in
June 2013, shows that trying to simulate the impact of the
introduction of mechanisms in France and Germany can result
in an oversimplified description of the capacity mechanism,
such that the mechanism simulated bears no resemblance to
the one adopted, making the results incorrect (§ 8.2);
> Simulations aiming to evaluate the financial impact of a capa-
city mechanism for consumers, with “all other things being
equal”, are then presented (§ 8.3): however, the results only
represent the “first-round” impacts, and do not include a dyna-
mic analysis of the longer-term effects on the power system
(location of investments, trends in market prices, etc.).
8.2 Limitations of existing analyses of how the capacity mechanism functions in an interconnected market
numerous Member States. Along with this Communication, it
launched a public consultation on the internal energy market,
generation adequacy and capacity mechanisms.
The European Commission took the 132 consultation res-
ponses submitted into account in preparing its Communication
on making the most of public intervention. It published the res-
ponses to the public consultation along with a report entitled
8.2.1 Analysis of the report accompanying the European Commission guidelines on public interventions
8.2.1.1 The report and its conclusions
In its Communication of 15 November 2012 on making
the internal market work, the European Commission voiced
concerns about the introduction of capacity mechanisms in
181
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
207[EC, 2012a]
208The report was prepared by Thema Consulting Group, E3M-Lab and COWI.
209Executive summary of the report: The empirical analysis shows that there is generally no urgent need for capacity mechanisms in Europe. Individual (asymmetric) capacity mechanisms of all designs are prone to distort cross-border trade in two main ways:- By causing over-capacity: Regulators are likely to overestimate the necessary domestic capacity reserve margin and to underestimate the contribution from cross-border trade.- By distorting allocation of investments: Investments are likely to shift to markets with CRM, thereby increasing total costs and distorting cross-border trade.
210Section 7.6 of the Thema report, “Capacity Mechanisms in Individual Markets within the IEM”: Asymmetric capacity mechanisms in the IEM imply that capacity remuneration in addition to energy-only market revenues are only applied in some system control areas and only remunerate plants located in this area. It is assumed that other (usually adjacent) system control areas operate as energy-only markets. Assuming that the asymmetry is taken into account by investors, generation capacity investments by country differ from symmetric energy-only market cases.
211OPTIMATE is a market architecture simulator designed as part of a European R&D programme.
“Capacity Mechanisms in Individual Markets within the IEM”207,
a document also used in drafting the Communication on public
intervention. This report208 analyses the consequences of the
introduction of capacity mechanisms in Europe.
On the whole, the findings of the report209 are unfavourable to
the adoption of capacity mechanisms in Europe. They notably
warn of the risk of market distortion if there is no coordination
on mechanism implementation.
However, the report does not conclude that the energy-only
market alone can stimulate investments in electricity:
It is difficult on an empirical basis to determine whether the
energy-only market design of the target model will yield
adequate investment signals. Moreover, the academic lite-
rature is inconclusive too. Whereas some hold that energy-
only markets are fundamentally flawed and that there is a
need for permanent capacity remuneration mechanisms
(CRM), others argue that the need for such mechanisms
is mainly linked to temporary market interventions and
uncertainties as [Climate policy, Market development, Mar-
ket regulations and Market design, Technology and costs &
Economic environment].
[…]
Still, it cannot be ruled out that capacity mechanisms may
be necessary to ensure sufficient peak and back-up capacity
in the future low carbon European electricity system, or as a
transitory precaution in some individual member states in the
shorter term.
The main conclusion of the qualitative analysis is that there is
no immediate and general underlying need for capacity mecha-
nisms in Europe. The two key conclusions of the accompanying
quantitative analysis are:
> The architecture of the energy-only market may not suffice to
ensure the economic viability of at least a portion of capacities:
The model based analysis reveals that the economics of new
capacity, in particular in gas-fired open cycle and CCGT plants,
may be challenging.
> Non-coordinated introduction of capacity mechanisms could
have negative consequences for Europe as a whole:
Model simulations of individual CRM in France and Germany,
respectively, confirm that unilateral mechanisms distort
investments and trade and lead to higher sys-
tem costs. The impacts on investments differ
in the two cases due to differences in capa-
city mix and interconnectivity. Impacts are felt
throughout Europe and total costs increase in
both cases. Compared to the reference sce-
nario (which also exhibits adequate capacity),
EU generation costs are found to increase by
1.3-1.5%.
The latter conclusion is important: if it is valid, then it
could call into question the justification for a capa-
city mechanism in France. The first task must the-
refore be to examine the robustness and validity of
the approach presented in section 7.6 of the Com-
mission’s report, “Impact of asymmetric capacity
mechanisms”.
8.2.1.2 General analysis of methodology
The methodology underpinning the assessment
is based on a comparison of a reference situation,
with energy-only markets in place in all countries,
and an “asymmetric” situation where one only
country adopts a capacity mechanism210.
This methodology is useful for studying market
architectures, and is notably used for the OPTIMATE
project211. However, the consequences of each
choice must be properly evaluated for the compa-
rison to be meaningful. This was not done for the
study included in the “Capacity Mechanisms in Indi-
vidual Markets within the IEM” report:
The approach in this section is that the asymme-
tric capacity mechanism represents a distortion
of the optimal market configuration presented in
previous sections. This simulation assumes that
reserve and reliability criteria are met in all sys-
tem control areas, taking interconnections into
account. In other words, the LOLPs are below
the maximum accepted thresholds and there is
no reason for an individual control area to adopt
a unilateral capacity mechanism. The question
posed in this section is then what would be the
impacts if a distorting regulation which remunerates capaci-
ties unilaterally was adopted in one control area. The mode-
ling does not account for any direct benefits in terms of loss
of load probabilities.
182
In other words, it is assumed that the energy-only market archi-
tecture is perfect and ensures optimal investment develop-
ment212. The security of supply benefits a capacity mechanism
could provide are not taken into account, even though these
benefits are the raison d’être for the mechanisms213.
The methodology used in the study presented in the “Capacity
Mechanisms in Individual Markets within the IEM” report there-
fore introduces non-negligible bias in that:
> The reference situation is a perfect energy-only mar-
ket that guarantees adequacy. As the authors explain,
“there is no reason [in this simulation] to adopt a
capacity mechanism”. In sum, it is considered from
the outset that the introduction of a mechanism
purportedly serving no purpose can only detract
from an initial situation that is theoretically optimal;
> The potential benefits of capacity mechanisms
in terms of security of supply are not taken into
account. This is tantamount to conducting a cost-
benefit analysis without taking benefits into account.
Both of these biases are highly questionable: many
academic studies have shown that the energy-only
market does not produce optimal results (these stu-
dies are summarised in chapter 1), and that the exis-
tence of externalities makes it necessary to adopt
specific mechanisms to ensure security of supply.
Empirical observations also support the theory that
market failures and investment cycles do exist.
8.2.1.3 Analysis of simulation assumptions
and data
It is suggested that the study allows the adoption of
a capacity mechanism in France to be simulated.
However, the assumptions and data inputted to the
model describe a mechanism that is in fact radically
different from the French mechanism:
We assume that the capacity remuneration fee allows
open cycle gas plants to recover capital costs. We also
assume that the same fee applies to CCGT plants as well.
The level of this fee is 40k€/MW-year in both cases.
The study thus considers a capacity payment mecha-
nism that specifically rewards certain technologies at
a particularly high fee. In other words, the study simu-
lates the adoption of a mechanism that is diametrically
opposed to the one being introduced in France. The French mecha-
nism is based on a capacity market that covers all capacity (market-
wide) and is technologically neutral. The price is not set ahead of time
but rather by the market, at the point where the supply and demand
curves for certificates meet. These are fundamental differences and
they profoundly impact the effects of the capacity mechanism.
In sum, the results of the study the European Commission
published as a complement to the consultation on the internal
market do not apply to the French mechanism. At best, they
show, based on an extremely simplified model, that a selective
capacity payment mechanism planned without taking the secu-
rity of supply situation into consideration can result in massive
and subsidised excess capacity214. This is precisely the concern
that led public authorities in France to opt for a decentralised,
quantity-based mechanism (chapter 2). Moreover, in designing
the rules submitted for approval by the Minister and CRE (chap-
ter 3), RTE sought to prevent the mechanism from keeping
excess capacity in the market when more competitive resources
were still available to safeguard security of supply. As such, there
should be no bias in favour of overcapacity in the French system
since, with the capacity mechanism in place, the capacity price
should tend toward zero in situations of excess capacity215.
Lastly, the mechanism simulated in the study the European Commis-
sion financed only focuses on some technologies (combined-and
open-cycle gas turbines). It therefore introduces a distortion and
promotes the development of these technologies exclusively. The
French mechanism will treat all capacities equally through a techno-
logy-neutral certification process216, and will also take demand res-
ponse capacities into account, as illustrated in chapter 3.
The bottom line is that the mechanism simulated in the study,
based on hypotheses, includes biases that public authorities
expressly sought to avoid in France. This raises two problems:
> The fact that the simulations are presented as representations of
the French capacity mechanism could mislead readers, since the
mechanism simulated bears no resemblance whatsoever to the
French capacity market. The results can therefore not be used to
evaluate the efficiency of the French capacity mechanism;
> The results are of limited validity in practice since only one type
of mechanism is simulated with only one capacity remuneration
fee. The fact that they are presented in a very general form217
automatically biases the reading and interpretation of the results.
8.2.1.4 Analysis of study results
The study results are analysed qualitatively, which allows the ori-
gin of the additional costs identified to be undertsood:
212Section 7.6 of the Thema report, “Capacity Mechanisms in Individual Markets within the IEM”: We assume that investment develops in an optimal way under reference conditions (cf. 7.1.4) so as to ensure capacity adequacy (captured through system reserve margin thresholds and the ramping constraints). This development of investment constitutes the benchmark case or, as referred to in the text that follows, the energy-only markets case.
213Section 7.6 of the Thema report, “Capacity Mechanisms in Individual Markets within the IEM”: We do not model capacity adequacy failure cases. […] The possible benefits of [a capacity mechanism] in terms of avoiding damages from unforeseen power supply failures are not accounted for in our modelling.
214The European Commission explicitly recommends against this specific characteristic in its guidance for state intervention in electricity: “Does the chosen mechanism ensure that identified adequacy gap will be filled while avoiding risks of overcompensation (unlikely with payments payments)?”
215In accordance with the recommendations in the European Commission guidance on state intervention: “Capacity mechanisms should be designed to deliver a price of zero when there is sufficient capacity available.”
183
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
As expected, the increased incentives to invest in peak load
devices in France leads to an increase in the overall invest-
ments in France, while the opposite effect is observed in
neighbouring, interconnected countries. More specifically,
up to 2030, the model suggests that, relative to when France
operates an energy-only market, investment in France will
increase by 21.7 GW, while investments decrease by 15.9 GW
in Germany, 3.6 GW in Belgium and 2.1 GW in the Nether-
lands. The changes mainly concern open cycle gas plants
and to some extent CCGT plants (Table 20). The generation
mix in France is considerably altered, as capacity remunera-
tion attracts much more investments in open cycle plants
than projected in the reference case. The share of open-cycle
plants in the overall non-RES projected investments is 40%,
more than double than in the reference case. The correspon-
ding share of the base-load investments falls to 50% from
70% in the reference case.
The additional costs identified stem directly from the errors and
approximations mentioned in the previous section:
> The total quantity of capacity is distorted: the simulations point to
overcapacity in France and under-capacity in the other countries.
This is a direct result of the “blindness” of the mechanism simula-
ted, which involves unconditional capacity payments;
> The generation mix is distorted: the simulations point to ove-
rinvestment in peak generation capacities and an underre-
presentation of base-load capacities. These effects are direct
results of the fact that the mechanism simulated targets only
specific technologies (gas-fired power plants).
8.2.2 Factors minimising the French mechanism’s impact on neighbouring countries
It is all the more important to carefully examine the
reality of the market architecture adopted when
modelling its impact on neighbouring countries
given that the interaction between energy markets
was a constant concern while the French mecha-
nism was being designed.
At the very outset of the mechanism design process,
it was perfectly clear that the principles applied to
the management of cross-border interconnections
in Europe made it impossible to duplicate the sys-
tems adopted in the United States, and the progres-
sive coupling of European markets made this issue
all the more pressing218. With this in mind, priority
was given to ensuring that the capacity mechanism
would not interfere with the organisation of the
internal energy market:
The introduction of a capacity mechanism
should not jeopardise the benefits of efficient
market functioning […]. This is why it is important
that the mechanism does not interfere with the
operation of market rules219.
Under the mechanism, operators’ commitments
to make capacity available during peak periods do
not limit their generation output (which will still be
determined by the functioning of energy markets)
or the destination of that output (still determined
by the rules in effect, and notably by market cou-
pling220). In other words, participation in the French
capacity mechanism does not involve any obliga-
tion in terms of generation supply on energy mar-
kets or equivalent restrictions on exports: a capacity
that is dispatched within the framework of the mar-
ket, even if an export contract is in effect, is consi-
dered to be available. Nor does the supplier that
holds the certificates associated with the capacity
have rights to the energy produced: energy cannot
be reserved in this system. Lastly, the adoption of
the capacity mechanism has no consequences in
terms of regulating energy prices, for instance on
the setting of price caps/floors.
216In accordance with the recommendations in the European Commission guidance on state intervention, under the heading “technological neutrality”: “Base restrictions on participation in a mechanism to ensure generation adequacy on the technical performance required to fill the identified adequacy gap and not on predefined technology types.”
217Taken from the Executive Summary of the “Capacity Mechanisms in Individual Markets within the IEM” report: “Model simulations of individual CRM in France and Germany, respectively, confirm that unilateral mechanisms distort investments and trade and lead to higher system costs. The impacts on investments differ in the two cases due to differences in capacity mix and interconnectivity. Impacts are felt throughout Europe and total costs increase in both cases. Compared to the reference scenario (which also exhibits adequate capacity), EU generation costs are found to increase by 1.3-1.5%.”
218[Veyrenc & Bhavaraju, 2008]
219[EC, 2013a]
220As was shown during the 2011 consultation, energy market coupling eliminates the concept of energy destination.
The “Capacity Mechanisms in Individual Markets within the IEM” report published with the results of the public consultation of 15 November 2012 on the internal energy market includes quantita-tive analyses of the effects of the implementa-tion of the French capacity mechanism.
An analysis of the methodology, assumptions and data used in the study and its results shows that the mechanism simulated bears no resem-blance to the one adopted in France. The conclu-sions of this report must be viewed with caution. It should also be noted that some principles laid down by the European Commission in its Com-munication on making the most of public inter-vention, and the Staff Working Document this report accompanies, are not upheld with the mechanism simulated. It would have been use-ful to have a thorough study of these aspects, despite the complexity involved.
184
the scope of validity of the results presented in the pages that
follow.
The impact assessments presented analyse how the cost of the
capacity obligation is distributed between different consumer
categories. They combine the different hypotheses in a number
of scenarios to identify the configurations that are the most or
least favourable to individual stakeholder categories (§ 8.3.2).
A numerical estimate is also provided of the indirect effect on
final consumers through the contribution to the public service
of electricity (CSPE) they pay. Indeed, facilities benefiting from
purchase obligations effectively participate in the capacity mar-
ket since they are awarded capacity certificates; in accordance
In response to stakeholders’ request to have a comprehensive
view of the mechanism’s effects, in September 2013, RTE pro-
vided some data on the financial impact the mechanism would
have on certain categories of consumers. These data have since
been expanded and are presented below. They show the first-
round effects of the implementation, on an all other things being
equal basis, and illustrate the immediate impact the mechanism
will have, not taking into account any effects implementation
will have on stakeholders’ behaviours or strategies, something a
dynamic analysis can show.
The methodological framework and hypotheses
used in the impact assessments are outlined below
(§ 8.3.1). This information is crucial to establishing
These principles imply that the energy market will be com-
pletely decoupled from the capacity mechanism in the short
term. They will prevent the mechanism from having any direct
short-term effects on energy prices, since the full separation of
capacity and energy as products is guaranteed, meaning Euro-
pean energy markets will continue to play the same role. These
options make the system very different from that in effect in the
United States, where the revenue earned by a generation unit in
the energy and capacity markets can in some cases be offset.
Once the mechanism is in place, it will be necessary to verify that
decoupling is truly a source of economic efficiency and that is
does not translate into undue rents during peak periods.
On the other hand, over the long term, the mechanism could
indirectly influence prices. As the Agency for the Cooperation of
Energy Regulators notes in its report on capacity mechanisms,
direct effects are not the only impact to consider:
Secondly, [Capacity Mechanisms] may influence investment
decisions (investment in plants and their locations), with
potential impacts in the long term […]221.
It would not be desirable for the capacity mechanism to have no
influence whatsoever on investment decisions, except if there was
no capacity need at all. The idea, rather, is to ensure that the mecha-
nism’s long-term impacts are strictly proportionate to its objectives,
in which case there is no distortion since the different mecha-
nisms allow the objectives set for them to be met. The architecture
adopted for the French mechanism ensures that the market price
of capacity certificates will tend toward zero if no capacity is needed.
ACER’s recommendations nonetheless stress the incomplete-
ness of the studies currently available in terms of the long-term
impact the coexistence of different national regulations will have
on security of supply. More thorough studies would be complex
and cannot be conducted before the parameters of the mecha-
nism are defined. It is proposed that such studies be conducted
as part of the effort to support the mechanism’s rollout, applying
the provisions proposed in the rules in application of the decree.
8.3 Detailed analysis of short-term effects
221[ACER, 2013]
The French capacity mechanism was designed in such a way as to minimise its impact on energy markets:
> In the short term, energy and capacity “products” will be completely independent and there will be no interference;
> In the long term, the capacity mechanism will influence investment decisions proportionately to security of supply targets: the resulting impact on energy prices should be indirect and small.
Additional studies are required to quantify this effect. To be conclusive, they must factor in all parameters set by public authorities. These stud-ies will be conducted within the framework of the existing provisions of the decree and those adopted in the rules when the capacity mecha-nism is in place.
185
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
with the provisions of the law, the value of these certificates is
returned to final consumers via a reduction in public service
charges through the CSPE (§ 8.3.3).
8.3.1 Hypotheses
Various factors must be taken into account in analysing the eco-
nomic impact of the mechanism. Six explanatory parameters
were identified and tested in the simulations described below:
> The value of the security factor, which notably changes depen-
ding on the recognition of the contribution of foreign capacity
(see chapter 9 for more details);
> The capacity price, which allows different configurations to be
tested with regard to the security of supply outlook;
> The temperature sensitivity of consumers, which varies widely
between consumers and results in a very uneven distribution
of the national obligation, meaning that economic impacts are
highly segmented;
> The consumer’s ability to reduce load during peak periods,
which is a means for consumers to directly manage the “capa-
city risk” and influences the impact of the mechanism depen-
ding on consumers’ flexibility;
> The regulatory framework in the wholesale market, which
affects the initial distribution of capacity certificates between
market players. The procedure adopted for the transfer of
capacity certificates associated with ARENH generation (see
chapter 7) will thus be all-important, since it will have a deci-
sive influence on the competitive structure of the future
capacity market (and, in practice, it will also do a great deal to
balance players’ positions);
> The regulatory framework in the retail market, which affects
how costs are passed on to consumers, notably depending on
the rates suppliers offer them. A distinction must therefore be
drawn between large consumers whose rates depend on mar-
ket prices and smaller consumers that can remain on regula-
ted tariffs between now and when the capacity mechanism
takes effect.
8.3.1.1 Security factor
The value of the security factor depends on two parameters:
> How the contribution to security of supply in France of capa-
cities located in other countries is modelled: this contribution
is accounted for implicitly, through a reduction in the security
factor; the higher the contribution of foreign capacities, the
greater the reduction in the security factor;
> The technical choices made in the rules, are notably between
(i) making the reference extreme temperature the main contin-
gency considered or on the contrary pooling all contingencies
within the security factor, or (ii) stabilising the parameters for
calculating the obligation or normalising the amount of certi-
ficates allocated to certain capacities and pooling the related
“imperfections” through the security factor.
As discussed in § 4.4, RTE proposes that the security factor be
set at 0.93 for the first two delivery years.
A different approach could have been taken in accounting for
the contribution of interconnections. If public authorities decide
not to take the contribution of interconnections into account, or
to account for it while also increasing the three-hour coverage
threshold (considering the three-hour criterion without taking
interconnections into account would result in a higher level of
effective coverage), the value of the security factor could be 1.
The two hypotheses tested below thus correspond to a security
factor of 0.93 or 1.
8.3.1.2 Capacity price
Assessing the economic impacts of the mechanism requires
using a hypothesis of the average capacity price that will result
from transactions in the market. Of course this price depends on
the projected state of the power system, but also on the para-
meters set in the rules, such as the value of the security factor
and the reference extreme temperature. Insofar as the “security
factor” variable is tested separately, testing the “capacity price”
variable means examining the impact of the “reference extreme
temperature” parameter.
The capacity certificate price could in theory move between 0
and the administered price used for the imbalance settlement,
which RTE proposes to define as the annualised cost of develo-
ping a peak generation plant (combustion turbine), of €60k/MW
for a given delivery year. The simulation could therefore test the
range [0; €60k/MW]
However, given the supply-demand balance outlook presented
in chapter 1, which predicts a situation that requires vigilance
but does not imply a definite shortage, it is proposed that a nar-
rower price range be considered. A capacity price of €30k/MW/
year for all capacities corresponds in all likelihood to a high value
for the first delivery years.
The two hypotheses tested below thus correspond to prices of
€10k/MW/year and €30k/MW/year. A reference situation with
a capacity price of zero will also be considered.
186
8.3.1.3 Temperature sensitivity
The data presented in chapter 4 allow a qualitative assessment
of the impact of the formula used to determine the obligation.
Because the formula selected is based on the consumption gra-
dient, the lion’s share of the national obligation will be allocated
to temperature sensitive consumers. This is logical since they
are responsible for peak power demand and thus the need for
peak generation capacity. On the other hand, non-temperature
sensitive consumers should not be affected by the capacity
mechanism; the gradient is even set at 0 for some of them.
In the simulations presented here, differences in consumers’
temperature sensitivity are considered through “idealised”
hypothetical cases (100% base-line consumption) and concrete
examples based on actual load curves.
The configurations tested thus correspond to a gradation
between the consumer that is not temperature sensitive at all
(industrial user for instance) and a residential consu-
mer with electric heating.
8.3.1.4 Consumer’s ability to reduce load at
peak times
The principle underlying the mechanism adopted in
France is that any consumer or supplier should be
able to manage the risk the obligation represents
for it by leveraging its demand response potential
during peak periods.
This means that the capacity mechanism will have a
very different impact on a highly temperature sen-
sitive consumer that absolutely cannot adjust its
consumption and a consumer that can reduce load
during peak times. A consumer with a very low obli-
gation (industrial user for instance) can take advan-
tage of this flexibility to generate a net gain with the
mechanism.
The simulations illustrate this by considering two
hypotheses: a consumer that never reduces load
and one that reduces its peak consumption by half
on all PP1 days.
8.3.1.5 Specific mechanism regulating the
wholesale market: transfers of ARENH-related
capacity certificates
Another significant variable is how capacity cer-
tificates associated with the ARENH mechanism
discussed in § 7.3 affect the analysis of competitive conditions
in the capacity certificate market.
ARENH is a regulatory mechanism that was instituted by the
NOME Act in 2010 to facilitate the deregulation of the French
supply market while also allowing consumers to benefit directly
from the competitiveness of historical nuclear electricity. The
law provides that each supplier shall have Regulated Access to
Historical Nuclear Electricity (ARENH) under the same econo-
mic conditions as the incumbent operator222.
As a result, alternative suppliers:
> Pay a price that factors in the costs associated with histori-
cal nuclear generation capacity: the ARENH purchase price is
representative of the economic conditions under which histo-
rical nuclear electricity is generated;
> Benefit from all advantages associated with historical nuclear
electricity in terms of energy but also capacity certificates.
In application of this second principle, current regulations sti-
pulate that alternative suppliers will receive the capacity cer-
tificates associated with energy sourced through the ARENH
mechanism223. This is a crucial factor in evaluating how the
mechanism will function; the consequences in terms of com-
petition were discussed in chapter 7. In practice, alternative sup-
pliers with ARENH rights will not be “net buyers” on the market,
but rather will be in a situation comparable (at least in part) to
that of players with upstream-downstream integration.
The capacity value associated with ARENH is an important com-
ponent of the impact assessment. However, whereas RTE is res-
ponsible for proposing a security factor value, CRE is charged
with proposing a method for calculating the amount of capacity
certificates to be delivered with ARENH rights224, and it has orga-
nised a consultation in recent months to consult market stake-
holders on this subject. The fact that the results of this process
are not yet known makes it necessary to formulate hypotheses
about the coefficient that will be applied to convert 1 MW of
ARENH electricity delivered into a number of capacity certifi-
cates. Needless to say, these hypotheses are without prejudice
to the choice that will ultimately be made by CRE.
In conducting the evaluations below, RTE considered two
hypotheses, corresponding to the two lines of reasoning
promoted by stakeholders during the consultation. These
hypotheses were presented in September 2013, and were not
challenged in the responses to the public consultation orga-
nised by RTE:
222As stated in L. 336-1 of the Energy Code: “To ensure that consumers are free to choose their electricity supplier, while also promoting the attractiveness of the country and allowing all consumers to benefit from the competitive pricing of nuclear power generated in France, it will be possible, during a transitional period defined in article L. 336-2, for all operators supplying final consumers in continental metropolitan France, or system operators for their losses, to have regulated and limited access to historical nuclear electricity from the nuclear plants mentioned in article L. 336-2 on economic terms equivalent to the conditions for Electricité de France resulting from the use of the nuclear plants mentioned in the same article L. 336-2.”
223Decree 2011-466 of 28 April 2011 setting out the rules governing access to historical nuclear electricity stipulates that “the product transferred includes the generation capacity certificate, as defined in article 4-2 of the aforementioned law of 10 February 2000”.
187
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
> The first involves allocating one MW of capacity guarantee for
each MW of ARENH electricity delivered;
> The second involves using a different conversion key to try
to create a level playing field for alternative suppliers and EDF.
First hypothesis
ARENH is defined as a “flat” product and alternative suppliers’
allocation rights are based on their customers’ consumption
during the reference periods defined in the regulations. By this
same logic, the transfer involves allocating one capacity certifi-
cate for each MW of ARENH electricity delivered.
Second hypothesis
Transfers based on a conversion rate of more than 1 suggested
during the consultation apply a different logic to the allocation
of capacity certificates. It involves calculating the distribution of
certificates in such a way as to ensure that each supplier is in an
“equivalent economic position” to EDF with regard to historical
nuclear generation capacity. This calculation can be based on
an estimation of the number of capacity certificates “contained”
in each MWh of nuclear electricity produced:
> It is assumed that the certification of the historical nuclear
power plants will result in the issuance of 55 GW of capacity
certificates (estimated applying the certification methods pro-
posed225 to historical availability data in recent winters, based
on RTE’s assessments);
> This amount is then compared to annual nuclear electri-
city generation (416 TWh on average in the past ten years):
each MWh of nuclear electricity thus “contains” an average
0.132 kW of certificates;
> The conversion key thus works out to 1.16 (1 MW of ARENH
generated produces 8760 x 0.132 kW = 1.16 MW of capacity
certificates in a year).
It may seem surprising that the ratio between certificates in
MW and ARENH generation in MW is greater than 1. This result
actually reflects the fact that the nuclear power plants are
more available in the winter, and thus during the PP2 periods:
the amount of certificates allocated to nuclear power plants is
higher than the average power delivered in a year (55 GW in
winter, compared with average output of 48 GW over the year).
In other words, the second hypothesis involves transferring to
suppliers, through ARENH, the value associated with the modu-
lation of generation. To be thorough, this hypothesis should
be qualified: the cost of imbalance settlements resulting from
the certification of nuclear capacity should also be passed on
to suppliers if they are to be on equal economic footing with
EDF. It is assumed that this cost will be minimal: nonetheless, the
value has been rounded down from 1.16 to 1.15 by
default for the purposes of the assessments.
As such, the conversion key values applied in the
simulation to translate MW of ARENH capacity into
capacity certificates are 1 and 1.15, respectively.
8.3.1.6 Regulatory framework in retail
market
The regulatory framework governing the retail mar-
ket affects how costs are passed through to consu-
mers, notably depending on the type of rates sup-
pliers are likely to offer them.
Under current legislation, regulated tariffs, to
which large consumers226 can still subscribe, will
be phased out on 1 January 2016, before the first
capacity mechanism delivery year begins. From the
first delivery year on, large consumers will only have
access to market rates, which will factor in the bene-
fits of ARENH generation if it is more competitive
than the market price.
On the other hand, small consumers (subscribed
power of no more than 36 kVA) will be able, as of the
first deliver year, to choose between the regulated
tariffs offered by the incumbent operator and local
distribution companies or the market rates offered
by alternative suppliers. The continued availabi-
lity of regulated tariffs will impact how the market
functions. Indeed, the law establishes a principle
of reversibility allowing small consumers to switch
from regulated tariffs to market rates and vice versa.
From a competition standpoint, regulated tariffs act
as an automatic price cap on the rates offered by all
suppliers in the French electricity market: it can be
considered, in this segment, that the regulated tariff
is the reference price for the retail market.
In other words, the capacity mechanism will not
have the same impact on different categories of
consumers:
> For large consumers, it is the impact on market rates (deter-
mined based on the ARENH price plus a market supplement)
that must be analysed;
> For small consumers, the goal is to assess the impact on cur-
rent supply prices in the segment, assuming that they will be
aligned with the regulated tariff at this timescale227.
224Decree 2012-1405 of 14 December 2012 relative to the contribution of suppliers to security of electricity supply and to the creation of a capacity obligation mechanism in the electricity sector states that it is CRE’s responsibility to propose the method for calculating the amount of capacity certificates to be delivered with ARENH electricity (the method used to calculate this amount of capacity certificates, along with the transfer terms and timeframe, are defined in an order by the Energy Minister based on a proposal by the Energy Regulatory Commission”). Article 337-14 affirms: “To ensure fair remuneration for Electricité de France, the price, which will be reassessed every year, shall be representative of the economic conditions under which the nuclear power plants mentioned in Article L. 336-2 generate electricity over the duration of the mechanism defined in Article L. 336-8.”
225See section 5.1.2 of this report.
226Large consumers are defined in accordance with the terminology used in decree 2011-466 of 28 April 2011 setting forth the rules for regulated access to historical nuclear electricity, i.e. sites subscribing to power of more than 36 kVA, by contrast to small consumers.
227This is a simulation hypotheses that obviously does not imply that all rates will be effectively aligned.
188
The simulations presented below therefore draw a distinction
between the impact for large (industrial) consumers and small (resi-
dential and tertiary) consumers. Insofar as the tariff framework appli-
cable to the latter after 1 January 2016 will be adjusted by the Govern-
ment and Energy Regulatory Commission between now and then,
the simulations involving large consumers are more detailed.
8.3.1.7 Results
To be thorough, the impact assessment must vary these six
explanatory factors. It is not easy to provide an aggregate result
for something this complex: the method applied involves com-
bining certain hypotheses to produce different scenarios.
This scenario-based approach notably allows correlations
between different coefficients to be taken into account. For ins-
tance, selecting a low security factor will, all other things being
equal, result in a lower market price. The studies below therefore
do not simultaneously test a hypothesis involving a low security
factor together with a high capacity price.
Figure 79 – Overview of explanatory factors to be taken into account in the impact assessment
Explanatory factor Hypotheses applied in the scenario-based approach Determination
Security factor
0.93 Value proposed by RTE in the rules
Set in the RTE rules
1Higher level of security of supply chosen for France
(No taking account of the contribution of interconnections or increase in the criterion)
Capacity price
€0k/MW/year Floor price scenario
Dependent on functioning of capacity market €10k/MW/year Median scenario tested
€30k/MW/year High scenario tested
Temperature sensitivity
Industrial consumer
Non-temperature sensitive Consumer
Set in the RTE rules
Residential consumer
Consumer using electric heating
Consumer's ability to reduce load
Consumer that never reduces load
Dependent on consumers
Consumer that reduces peak power demand by half throughout PP1
Transfers of ARENH-related certificates
1 MW of ARENH = 1 MW of certificates
Same approach as for allocation of rights to alternative suppliers
Set by Minister and CRE
1 MW of ARENH = 1.15 MW of certificates
Alternative approach that involves estimating the number of capacity certificates “contained” in each MWh of nuclear electricity produced
Regulatory framework in retail market
Large consumerImpact on market rates
(based on ARENH price plus a market supplement)
Set by Minister and CRE
Small consumerImpact on market rates linked to regulated tariffs (it is assumed
they will align with regulated tariffs in effect at this timescale)
189
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
8.3.2 Quantitative assessment of cost to consumers
The outcomes of the simulations presented here depend on the
hypotheses above. They exclude taxes and network costs.
As with the discussion of competition-related factors in chap-
ter 7, the ARENH effects are central to the assessment. Cal-
culated based on the methodology that will apply in 2015 to
a virtual consumer with a consumption profile similar to the
national load curve, ARENH rights will represent, by RTE’s esti-
mates, about 78% of its energy needs228. In power terms, his-
torical nuclear electricity should account for just over half of
its capacity certificate needs. Assuming a total capacity certifi-
cate requirement of 92 GW (estimated applying the proposed
methods for certifying the total capacity needed in 2016-
2017), and that certification of historical nuclear generation
capacity totals 55 GW (estimated applying the proposed cer-
tification methods to availability data for recent winters), then
historical nuclear electricity will represent 60% of the overall
capacity need.
This ratio varies considerably depending on the type of
consumption. For a small consumer with subscribing to a peak/
off-peak tariff (which most consumers with electric heating do),
ARENH electricity could cover about two-thirds of its energy
consumption229, but less than half of its capacity obligation.
Conversely, for an industrial consumer with a consumption
profile that is not very seasonal, ARENH electricity could cover
almost all of its energy and capacity certificate needs. Impacts
thus vary depending on the consumer category.
8.3.2.1 Large consumers
By the time the capacity mechanism is in effect, all large
consumers will be paying market rates, as the regulated tariffs
still available to consumers that never exercised their right to
switch since the market was deregulated will be phased out on
31 December 2015.
Suppliers base their market rates on wholesale market prices.
If ARENH electricity is still a competitive source for alternative
suppliers when the mechanism comes into effect, market rates
should align with ARENH supply costs, tacking on a “market sup-
plement”. Otherwise, the rates offered to large suppliers will be
based entirely on the wholesale market price.
Bearing this in mind, the capacity mechanism’s impact on each
consumer in this segment should be a direct reflection of the
capacity obligation it creates for its supplier. This
amount can nonetheless be adjusted to reflect
the capacity certificates transferred to alternative
suppliers through the ARENH and priced through
the capacity market. Assessing the mechanism’s
impact on these consumers therefore involves
weighing the capacity obligation they create for
their supplier against the certificates these same
suppliers receive in relation to the ARENH, assu-
ming that suppliers will indeed pass on to their
customers the capacity value included in ARENH
rights thanks to effective competition in the elec-
tricity supply market.
Three cases are analysed below: (1) a virtual consu-
mer consuming base-load electricity exclusively,
(2) a very large consumer with the “average” pro-
file typifying all consumers connected to the public
transmission system, and (3) a typical remotely read
large consumer connected to the public transmis-
sion system.
All three analyses were conducted bearing in mind that the
mechanism parameters were subject to further modifications. In
all three cases, the delivery year is staggered with a winter period
in the middle in order to obtain, within the time allotted for the
consultation and the drafting of the rules, an initial estimate of
the capacity mechanism’s consequences. The fact that a calen-
dar year is adopted in the rules only has a marginal impact on
outcomes, as explained in chapter 4.
8.3.2.1.1 Virtual consumer consuming base-load
generation exclusively
The ideal configuration for this consumer (excluding demand
response) is a low capacity price, the security factor proposed
by RTE and a conversion key greater than 1 (i.e. the second
hypothesis for this parameter).
Pursuant to the order of 17 May 2011 relative to the calculation of
rights to regulated access to historical nuclear electricity, a consu-
mer with steady power consumption creates, for its supplier, an
ARENH right corresponding to 96.4% of the energy consumed.
If 1.15 MW of capacity certificates are transferred for every
MW of ARENH electricity delivered, then the certificates obtai-
ned through ARENH represent 110.6% of power consumed
(calculated by multiplying the ARENH right by the capacity
certificate).
228Throughout the assessment, it is assumed that the maximum total ARENH electricity that can be delivered, which the law caps at 100 TWh, is not reached. If the cap is reached, then regulations stipulate that the ARENH rights allocated to each supplier shall be reduced in such a way that the amount is divided between suppliers requesting ARENH.
229CRE’s 2011-2012 report on the functioning of retail electricity and natural gas markets in France, published in January 2013, mentions (p. 56) that the ARENH rights calculated for the off-peak/peak hour profile is 64.1%.
190
In terms of the obligation, assuming a security factor of 0.93, the
obligation represents 93% of power consumption. In this case, it
appears that ARENH electricity goes beyond covering the consu-
mer’s need and results in a surplus of certifi cates, with ARENH
covering 119% of the obligation. Assuming a capacity price of
€10k/MW, the net gain for the consumer will be €0.2/MWh.
A site with a “fl at” consumption profi le and capable of reducing
its consumption by half during peak periods can also transfer
the corresponding certifi cates through the market, for a gain of
€0.6/MWh (assumed capacity price of €10k/MW). Added to the
€0.2/MWh mentioned above, this consumer’s net gain will be
€0.8/MWh.
The tables below show outcomes using diff erent hypotheses about
the capacity price, the security factor and ARENH certifi cates.
Now, if it is assumed that the security factor is determined with-
out taking into account the contribution of interconnections
and thus set at 1 (instead of 0.93), that each MW of ARENH
Figure 80 – Case of virtual consumer consuming base-load generation exclusively
0.8
0.85
0.9
0.95
1
1.05
1.1
1.15
01/0701/08
01/0901/10
01/1101/12
01/0101/02
01/0301/04
01/0501/06
* Peak consumption reduced by half
WITHOUT DEMAND RESPONSE
€/MWh1 MW of ARENH >1 MW of certifi cate
1 MW of ARENH >1.15 MW of certifi cate
C = 0.93 0.0 -0.2
C = 1 0.0 -0.1
WITH DEMAND RESPONSE*
€/MWh1 MW of ARENH >1 MW of certifi cate
1 MW of ARENH >1.15 MW of certifi cate
C = 0.93 -0.6 -0.8
C = 1 -0.6 -0.7
Capacityprice:€10k
WITHOUT DEMAND RESPONSE
€/MWh1 MW of ARENH >1 MW of certifi cate
1 MW of ARENH >1.15 MW of certifi cate
C = 0.93 -0.1 -0.6
C = 1 0.1 -0.4
WITH DEMAND RESPONSE*
€/MWh1 MW of ARENH >1 MW of certifi cate
1 MW of ARENH >1.15 MW of certifi cate
C = 0.93 -1.8 -2.3
C = 1 -1.6 -2.1
Capacityprice:€30k
Outcome with an alternative set of hypotheses
Constant profi le
Obligation with security factor of 0.93
Obligation with security factor of 1
Related capacity certifi cates transferred under ARENH (hypothesis: 1/1)
Related capacity certifi cates transferred under ARENH (hypothesis: 1/1.15)
The tables below show outcomes using diff erent hypotheses about the capacity price, the security factor and ARENH certifi cates.
191
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
electricity produced translates into 1 MW of capacity certificates
(instead of 1.15), and that the market capacity price is €30k/MW,
the impact on the consumer’s bill becomes very slightly posi-
tive230 (+€0.1/MWh).
Taking flexibility into account has a substantial impact on the
outcome: if the consumer can reduce its consumption by half at
peak times, its gain will be €1.7/MWh (assumed capacity price of
€30k/MW). The net balance is positive for the consumer, which
will save €1.6/MWh.
8.3.2.1.2 Very large consumer with the “average”
profile typifying consumers connected to the public
transmission system
The results above can be refined a first time by inputting the ave-
rage consumption profile of customers connected to the public
transmission system in the winter of 2011-2012231 rather than
assuming base-load consumption exclusively. This
configuration is a fair description of the consump-
tion profiles of most electro-intensive industrial users
connected to the transmission system.
The capacity obligation is calculated for the
100 hours of highest consumption, included in the
PP1 eligibility time slot [07:00; 15:00[ then [18:00;
20:00[, defined in accordance with the rules, norma-
lising the temperature gradient to 0 for the reasons explained in
chapter 4. ARENH rights are calculated applying the rules appli-
cable in 2015, based on a series that combines the first half of
2012 and the second half of 2011.
ARENH covers 105% of the obligation (conversion coefficient:
1.15). Assuming a capacity price of €10k/MW, the consumers in
question will see a net gain of €0.1/MWh.
Figure 81 – Case of large consumer with an “average” profile
0
0.2
0.4
0.6
0.8
1
1.2
1.4
01/07
01/08
01/09
01/10
01/11
01/12
01/01
01/02
01/03
01/04
01/05
01/06
Profile extraction PTS
Obligation with security factor of 0.93
Obligation with security factor of 1
Related capacity certificates transferred under ARENH (hypothesis: 1/1)
Related capacity certificates transferred under ARENH (hypothesis: 1/1,15)
A site with this kind of consumption profile and capable of redu-
cing its consumption by half at peak times can also transfer the
corresponding certificates through the market. This results in a
gain of €0.7/MWh (assumed capacity price of €10k/MW). Added
to the €0.1/MWh mentioned above, this consumer’s net gain
will be €0.8/MWh.
230In this case, ARENH covers 96.4% of the obligation.
231The data considered have not been adjusted for NEBs.
232ARENH covers in this case 85% of the obligation.
Now, if it is assumed that the security factor is determined without
taking into account the contribution of interconnections and thus
set at 1 (instead of 0.93), that each MW of ARENH electricity pro-
duced translates into 1 MW of capacity certificates (instead of
1.15), and that the market capacity price is €30k/MW, the impact
on the consumer’s bill will be an additional cost of €0.6/MWh232.
192
Here again, taking flexibility into account has a substantial impact
on the outcome: if the consumer can reduce its consumption
by half at peak times, its gain will be €2/MWh (assumed capacity
price of €30k/MW). The net balance is positive for the consumer,
which will save €1.4/MWh.
8.3.2.1.3 Typical large consumer (TSO or DSO)
A third variant can be introduced to estimate the impact on the
energy bills of standard industrial consumers representative of
alternative suppliers’ portfolios. The simulation is conducted by
aggregating the remotely-read load curves of the balance res-
ponsible entities of these suppliers. The capacity obligation is
calculated for the 100 hours of highest consumption, included
in the PP1 eligibility time slot [07:00; 15:00[ then [18:00; 20:00[,
defined in accordance with the rules, normalising the tempera-
ture gradient to 0 for the reasons explained in chapter 4. ARENH
rights correspond to average rights for the calendar years 2011
and 2012 calculated applying the method applicable in 2015.
ARENH covers 86% of the capacity obligation for
these customers as a whole.
Assuming a capacity price of €10k/MW, the net cost to these
consumers is €0.2/MWh.
A site with this kind of consumption profile and capable of
reducing its consumption by half at peak times can also
transfer the corresponding certificates through the mar-
ket. This results in a gain of €0.8/MWh (assumed capacity
price of €10k/MW), which more than offsets the €0.2/MWh
cost mentioned above, putting this consumer’s net gain at
€0.6/MWh.
Here again, assuming that the security factor is determined with-
out taking into account the contribution of interconnections and
thus set at 1 (instead of 0.93), that each MW of ARENH electricity
produced translates into 1 MW of capacity certificates (instead of
1.15), and that the market capacity price is €30k/MW, the impact
on the consumer’s bill would correspond to an additional cost of
€1.4/MWh233.
Taking flexibility into account again has a substantial impact on
the outcome: if the consumer can reduce its consumption by half
The tables below show outcomes using different hypotheses about the capacity price, the security factor and ARENH certificates.
* Peak consumption reduced by half
WITHOUT DEMAND RESPONSE
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 0.1 -0.1
C = 1 0.2 0.0
WITH DEMAND RESPONSE*
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 -0.6 -0.8
C = 1 -0.5 -0.7
WITHOUT DEMAND RESPONSE
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 0.3 -0.2
C = 1 0.6 0.1
WITH DEMAND RESPONSE*
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 -1.7 -2.2
C = 1 -1.4 -1.9
Outcome with an alternative set of hypotheses
Capacityprice:€10k
Capacityprice:€30k
233ARENH covers 70% of the capacity obligation (instead of 86%).
193
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
The tables below show outcomes using different hypotheses about the capacity price, the security factor and ARENH certificates.
* Peak consumption reduced by half
WITHOUT DEMAND RESPONSE
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 0.4 0.2
C = 1 0.5 0.3
WITH DEMAND RESPONSE*
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 -0.5 -0.6
C = 1 -0.3 -0.5
WITHOUT DEMAND RESPONSE
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 1.0 0.6
C = 1 1.4 0.9
WITH DEMAND RESPONSE*
€/MWh1 MW of ARENH >1 MW of certificate
1 MW of ARENH >1.15 MW of certificate
C = 0.93 -1.3 -1.7
C = 1 -0.9 -1.4
Outcome with an alternative set of hypotheses
Capacityprice:€10k
Capacityprice:€30k
at peak times, its gain will be €2.3/MWh (assumed capacity price
of €30k/MW). The net balance is positive for the consumer, which
will save €0.9/MWh
For large consumers, ARENH-related certificates cover a large share of the obligation generated for their suppliers. The most favourable configu-ration for these consumers (excluding demand response) is a low capacity price, a security fac-tor matching that proposed by RTE and a con-version key above 1 for ARENH rights (i.e. the second hypothesis for this parameter). If large consumers’ flexibility is taken into account, the results are substantially different, as the quantity of certificates will largely exceed the level required to cover the obligation. In sum, the mechanism’s “first-found” impact is very limited for large consumers, and can even be “positive” (n the sense that gains are possible) if consumers leverage their flexibility through the mechanism.
8.3.2.2 Small consumers
The regulations governing the functioning of the retail market are
an important consideration in assessing the mechanism’s impact
on smaller consumers. It is possible to conduct simulations consi-
dering that consumers in this segment will buy electricity at
market rates, though the impact of regulated tariffs remaining in
effect after 1 January 2016 should not be overlooked.
Moreover, residential customers subscribing to the regulated
tariff already pay a capacity-type fee since tariffs have histori-
cally been calculated based on the long-term adaptation of the
mix including a reference to the cost of capacity. A comparison
of the current situation with that resulting from the capacity
mechanism would require comparing these two values. The
issue is more complex for residential consumers buying elec-
tricity from alternative suppliers based on market rates since,
even though the availability of regulated tariffs should result in
an alignment of rates on offer, alternative suppliers source elec-
tricity through ARENH and the market, and must therefore set
their rates by adding various cost components without taking
into account any type of capacity cost. The difference between
194
the two approaches and the price squeeze risks they create are
amply discussed elsewhere and are not addressed in this sec-
tion, but they must be borne in mind to establish the scope of
validity of the orders of magnitude presented below.
By the time the capacity mechanism is in place and consumers
first begin to feel its effects (2016), the applicable tariff system will
have evolved. Article L. 337-6 of the Energy Code stipulates that,
between now and 1 January 2016, tariffs will “gradually be calcu-
lated taking into account the addition of the regulated access to
historical nuclear electricity price, the supplemental electricity
supply cost which includes the capacity certificate, electricity
transmission and marketing costs as well as normal remunera-
tion”. However, the contours of this future tariff system have not
been finalised. It will be the responsibility of CRE (from 2016) to lay
down the applicable principles, within the regulatory framework
defined by the Government.
In the analysis below, it is assumed that the new tariff system is
based on a “market” approach. Rates offered to small consumers
are thus calculated by adding together the different cost compo-
nents: ARENH, a market supplement for energy, the
capacity certificate price, etc. The elements below are
not applicable if regulated tariffs continue to be set on
the basis of costs.
With a “market” approach, the capacity cost com-
ponent, which public authorities currently factor
into regulated tariffs234, will have to be replaced by a
component that refers to capacity certificate prices
set by the market. To provide an order of magnitude
of the sensitivity of the impact on consumers, it is
necessary to formulate a hypothesis about the dif-
ference between the two references for the capacity
cost235. For the purposes of the simulations below,
this difference is set at ± €10k/MW.
Three situations are possible:
> If the difference between the current capacity
price component and the market price is nega-
tive, then the implementation of the capacity
mechanism will, all other things being equal, put
downward pressure on tariffs;
> If there is no difference, the effect on tariffs will be
nonexistent;
> If the difference is positive, the implementation of
the capacity mechanism will result in an increase
in this component within regulated tariffs.
More detailed simulations would have to (i) be based on an
accurate analysis of the capacity component included in regula-
ted tariffs, (ii) factor in the final decisions made by public autho-
rities about the future tariff system, and (iii) use load curves that
are representative of each category or subcategories of consu-
mer (for instance customers on the off-peak/peak tariff.). These
results can thus only be presented once public authorities’ deci-
sions about the future tariff system are known.
In the meantime, broad assumptions can help provide an order
of magnitude of the sensitivity of the impact for small consu-
mers. Considering an overall capacity need in France of 92 GW,
in keeping with the simulations presented in the previous sec-
tion, and that small consumers represent about 165 TWh of
annual energy consumption and thus account for half of this
need, or 46 GW, the value of the capacity certificate for each
MWh consumed works out to 0.28 kW. If ARENH covers half of
this need, then the balance to be covered is 0.14 kW. Based on
a difference of €10k/MW between the average cost of capacity
operated by EDF (excluding historical nuclear) and the market
capacity price, the result is €1.4/MWh.
In other words, if the average cost of the capacity operated by EDF
excluding historical nuclear is €10k/MW below (above) the market
price, then the sensitivity of the impact on the average price paid by a
small consumer, provided that the new tariff setting system is based
on a “market” approach, should be +€1.4/MWh (-€1.4/MWh).
This corresponds to the average between the most temperature sen-
sitive consumers (for instance those that have opted for the peak/
off-peak tariff) and others. In reality, there are likely to be large gaps
between results depending on the consumers considered, for ins-
tance a non temperature-sensitive customer versus one that relies
exclusively on electric heating. As was the case with large consu-
mers, the potential impact can be partly or totally mitigated if a peak
demand management or demand response mechanism is in effect.
234Regulated tariffs must be calculated in such a way as to cover costs. They therefore include a capacity component corresponding to the share of fixed costs associated with generation assets developed and maintained by EDF that cannot be recovered through the energy market. Their structure is based on the theoretical updated generation mix, and takes into account, in this case, a normative capacity cost (which may be different from the real capacity costs) associated with the shortfall risk. See, for example, the CRE report of 4 June 2013 (analysis of EDF's generation and marketing costs relating to regulated electricity tariffs), page 40.
235This method builds on the qualitative analysis included in the impact assessments carried out on the draft NOME Act and presented by the Government in April 2010. See [French Department in charge of Energy and Climate (DGEC), 2013]
The simulations carried out for different con-sumer categories give an idea of the “first-round” effects of the capacity mechanism implemen-tation and the impact the change in approach to setting regulated tariffs will have on small consumers. The mechanism’s financial impact on large con-sumers should be limited. For small consumers, the impact could be positive or negative depend-ing on the difference between the capacity certif-icate price and the capacity component currently
195
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
8.3.3 Impact on the CSPE
Like all capacities situated within the interconnected French
market, generation facilities that receive public support through
purchase obligations will participate in the capacity mechanism.
These capacities will thus be awarded capacity certificates that
obligated parties can buy. The proceeds will be deducted from
the charges for the public service of electricity financed through
the CSPE, and this deduction will ultimately benefit the consu-
mers subject to this contribution.
To assess the impact of the capacity mechanism’s
implementation compared with the existing situa-
tion, hypotheses must be formulated about the
quantity of certificates that could potentially be allo-
cated to the facilities in question, the capacity price
and the CSPE financing base.
Determining the quantity of certificates that could be allo-
cated to facilities subject to a purchase obligation requires
making an assumption about the subsidised technologies’
penetration when the mechanism is implemented. The figures
below correspond to the installed power estimates for these
technologies in 2017 adopted in RTE’s 2013 Adequacy Fore-
cast Report update:
> Installed wind power: 11.4 GW;
> Installed photovoltaic power: 7.5 GW;
> Cogeneration subject to feed-in tariff: 1.2 GW;
> Renewable embedded thermal: 1.9 GW.
The next step is to determine a quantity of capacity certificates for
each technology applying the provisions in the rules, and notably
the contribution coefficient for intermittent energy sources
based on the values presented in § 5.1. This quantity is multiplied
by a reference capacity price: in keeping with the analytical fra-
mework used until now, this calculation is done considering two
hypotheses (€10k/MW/year and €30k/MW/an).
The results of the impact assessment are summarised in table
5 below.
included in regulated tariffs. In all cases, the cost of the capacity obligation is borne by tempera-ture sensitive consumers alone.In addition to the values presented here, which obviously vary depending on the parameters selected, three observations can be made:> The transfer to alternative suppliers, and
through them to consumers, of the certificates associated with ARENH capacity significantly reduces the cost of implementing the mecha-nism for consumers;> Results are substantially modified when con-
sumers’ flexibility is taken into account, and the mechanism even creates opportunities for gains for the most flexible consumers;> The real impact on consumers will depend on
how suppliers set their rates in a competitive environment: the pricing policies applied to small consumers may differ from the approach to calculating regulated tariffs, and should take into account any capacity they operate them-selves, their commercial strategies, etc.
Table 5 – Assessment of the impact on the CSPE of the pricing of capacity certificates allocated to technologies subject to a purchase obligation
Installed capacity (GW)
Certificates(GW certified)
Value in €m with price of €10k/MW
Value in €m with price of €30k/MW
Wind power 11.4 2.3 22.8 68.4
PV 7.5 0.4 3.8 11.3
Cogeneration (<12MW) 1.2 1.0 10.2 30.6
Embedded thermal 1.9 1.6 16.2 48.5
Total 22.0 5.3 53.0 158.8
The amounts calculated should be considered in relation to the financing base of the CSPE (forecast domestic consumption (excluding
losses) net of around 380 TWh of energy exempt from the CSPE236).
236Energy Regulatory Commission deliberation of 9 October 2012 on a proposal relative to public electricity service charges and the unit contribution for 2013.
196
The considerations discussed in § 8.3 confirm that the pro-
visions adopted will initially carry a moderate cost for consu-
mers. The studies presented will be useful during the first two
delivery years of the mechanism, when there is unlikely to be
a significant capacity shortage. However, it is important to
stress that this information is indicative only and was collec-
ted during the limited time allotted to the consultation and the
drafting of the rules, while the mechanism parameters were
still subject to modification. These elements must therefore
be viewed only as a first analysis of the consequences of the
capacity mechanism.
When the time comes to implement the rules, it is proposed that
additional tools be used to complement these analyses.
8.4.1 A mechanism simulator made available to stakeholders
For educational purposes, RTE is developing a capacity mecha-
nism simulator called “CLéM”. It is a multiplayer web application
allowing users to “play the part” of a capacity operator, a capacity
portfolio manager, a supplier or a trader. The former estimate the
availability of their capacities, request to have them certified and
seek to maximise the value of the capacity certificates received
over the different phases of the mechanism; the latter estimate
the obligation their customers’ consumption will represent and
buy electricity at the best price on the market or, depending on
costs, initiate peak demand management measures.
8.4 Plans to strengthen the impact assessment system
Depending on the market price, the certification of capacities subject to a feed-in tariff could reduce the charges covered by the CSPE by between €50m and €160m a year, translating into savings of between €0.13 and €0.42/MWh.
Figure 82 – Presentation of CLéM
197
CAPACITY MECHANISM IMPACT ASSESSMENTS / 8
The goal is thus to illustrate the roles of the different players and
the timescales of the mechanism, and to make the microeco-
nomic determinants of the capacity price sensitive by leading
players to a collective trade-off between different options to
ensure that capacity supply and demand are balanced. The first
external session is planned for June 2014.
8.4.2 Expand the “first-round” impact assessment by factoring in small consumers
As discussed in § 8.3, it will be possible to further refine the
impact assessment for small consumers once the new metho-
dology for setting regulated tariffs is known. In its present wor-
ding, the Energy Code leaves several options open, the main two
being a historical vision of accounting cost coverage or a vision
based on the principles of contestability, in which case tariffs will
be determined by adding together independent components
(ARENH, price of wholesale market supplement, price on capa-
city certificate market).
More should be known about these choices within the coming
months (CRE’s remit has been expanded to include tariff sys-
tems). It is possible that the capacity mechanism rules and the
functioning of the capacity market itself could be factored into
the tariff setting formula. In this case, RTE is ready to contribute to
the analyses based on which the tariff formula will be modelled or
to assist with monitoring, within a framework determined by CRE.
8.4.3 Include a study on the dynamic impact of the mechanism over the long term in the assessment
As discussed in § 8.1.2, it is particularly challenging to conduct a
meaningful study of mechanism’s dynamic impact over the long
term due to the difficult choice that must be made between
the accuracy and feasibility of the model. The process involves
evaluating the long-term performances of various market archi-
tectures, taking into account the costs and benefits of each237,
along with factors ranging from the asymmetry of information
between agents or regulatory authorities, factors that can cause
the mechanism to be less efficient than hoped.
It was due to this complexity that a “second-round”
impact study could not be carried out during the
consultation, since the rules must necessarily be
stabilised before such a study can produce meaningful results.
However, it is not because the task is difficult that it must be
skipped, since the results could provide valuable insight to
inform future adjustments to the mechanism.
As mentioned in chapter 1 of this report, RTE is planning to carry
out economic studies on the functioning and impact of the
capacity mechanism within the framework of the role assigned
to it in article 20 of decree 2012-1405 of 14 December 2012.
The results of these studies will be sent to CRE so improvements
can be made to the capacity mechanism and shared with stake-
holders to continue the consultation approach adopted for desi-
gning the mechanism.
These studies will look beyond national borders and take a broa-
der view of security of supply to reflect the integration of Euro-
pean electricity markets. RTE’s models already include several
European countries, for instance for the studies in its adequacy
reports. It could also be possible for these studies to be conduc-
ted in cooperation with other countries, for instance through
a France-German partnership. Collaboration with academics
could also be useful depending on the objectives sought and
methods applied.
The main purpose of these models will be to represent the
impact of the market architecture adopted on investment and
security of supply in European countries. They thus require
a clear picture of the security of supply policies that will be
implemented by European countries. Observation of the capa-
city’s mechanism’s initial functioning will also provide relevant
information for studies and simulations of how it could evolve.
Indeed, the first years will be a learning period for all power sys-
tem stakeholders, and it will be possible to analyse their beha-
viours to improve the mechanism and anticipate the impact it
will have toward 2018-2020.
237[Cepeda & Finon, 2011]
198
9. EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET
9.1 Interconnections’ contribution to security of supply in France
9.1.1 Integrating power systems improves security of supply
By enabling the exchanges of energy between countries, inter-
connections have always contributed to enhance security of
supply in Europe. Indeed, interconnections mitigate the risks on
security of supply at a larger scale than the national one. Impor-
ting energy can therefore be one of the most effi cient solutions
to balance the system, including during periods of system-stress.
This mitigation of risks is all the more important that the
structure of electricity supply is different between European
countries as the risks on security of supply originate from
structurally different issues and can be country-specific. This
leads to a reduction of the correlation of contingencies and
to a greater degree of complementarity or mutual assistance
between countries.
A contingency can be simply defi ned through three characte-
ristics: its probability, intensity and duration. The following taxo-
nomy describes the main contingencies aff ecting security of
supply and proposes an indicative evaluation of their key-cha-
racteristics. This evaluation can diff er between countries.
Figure 83 – Main contingencies aff ecting security of supply
AVAILABILITY OF THERMAL PLANTS
lcpx0 h†xt0 o ctu cxt0 o ck lwkp lwkn0 cq¯ v ugr v0 qev0 pqx0 f †e0
> Probability: HIGH> Intensity: LOW> Duration: VARIABLE
AVAILABILITY OF HYDRO CAPACITY
lcpx0 h†xt0 o ctu cxt0 o ck lwkp lwkn0 cq¯ v ugr v0 qev0 pqx0 f †e0
RES GENERATION
Eolien PV
COLD SPELL/HEAT WAVE
CORRELATIONS
> Probability: LOW> Intensity: MODERATE> Duration: LONG
> Probability: LOW> Intensity: MODERATE> Duration: LONG
> Probability: VERY HIGH> Intensity: LOW> Duration: - PV: LOW - Wind: MODERATE
105 000
99 000
102 000
96 000
93 000
90 000
87 000
84 000
81 000
78 000
75 000
72 000
7:00
14:00
21:0001/12/11
15/12/1129/12/11
12/01/1226/01/12
09/02/1223/02/12
MW
Heure
Jour
102 000 - 105 000
99 000 - 102 000
96 000 - 99 000
93 000 - 96 000
90 000 - 93 000
87 000 - 90 000
84 000 - 87 000
81 000 - 84 000
78 000 - 81 000
75 000 - 78 000
72 000 - 75 000
105 000
99 000
102 000
96 000
93 000
90 000
87 000
84 000
81 000
78 000
75 000
72 000
7:00
14:00
21:0001/12/11
15/12/1129/12/11
12/01/1226/01/12
09/02/1223/02/12
MW
Heure
Jour
199
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
The exposure to a given contingency differs from one country to
another. This report has already described the peak-load issue in
France (chapter 1). The thermo-sensitivity of the French demand
and its impact on the peak-load during cold spells represent the
main risk on security of supply in France. Contingencies affec-
ting demand are also a concern for other European countries,
such as Sweden, Finland or Hungary.
The level of penetration of renewable energy sources (chiefly
wind and solar) in the energy mix of a given country has a direct
impact on the intensity of the contingency linked to their inter-
mittency, which is considered as low in France. However, in other
countries such as Denmark or Germany, where there is a high
penetration of renewable energy sources, intermittency has
become the main risk on security of supply. As the production
from renewable energy sources depends on weather conditions,
intermittency is by definition a highly probable contingency.
This enhances the need for back-up capacities (be it generation,
demand-response or storage capacities).
Some countries have a large share of hydro generation in their
energy mix – such as Norway, Switzerland or Portugal. There-
fore, drought years constitute a structural risk on their secu-
rity of supply, especially in case of long and severe drought
periods. Drought years can affect security of supply in other
countries. For example, in the Netherlands, where river water is
used to cool thermal power plants, drought years also threaten
security of supply because temperatures of rivers are growing.
Contingencies affecting the availability of thermal plants can
affect security of supply in every single European country. At the
European level, the power system is highly interconnected and
the failure of a plant has a low impact. Nonetheless, at the natio-
nal level, the failure of a plant can have a major impact, espe-
cially in countries where plant sizes are significant compared to
their electricity consumption.
The integration of European power systems mitigates the
risks on security of supply between European countries and
reduces the impact of main contingencies and enables mutual
assistance between countries. This integration is two-fold. On
the one hand, it relies on the “hardware”: the development of
interconnections. On the other hand, it relies on the “software”
in order to enable the efficient use of infrastructure: the mar-
ket design. The European electricity market is a major asset
to ensure security of supply in France and other European
countries.
9.1.2 Recognition of the cross-border dimension in the French capacity market
9.1.2.1 Economic efficiency of the French
capacity market
The efficiency of a market mechanism largely depends on its abi-
lity to accurately reflect the physical state of the system in which
it is implemented. Regarding the energy market, the accuracy of
market coupling mechanisms is directly linked to their ability to
reflect as truthfully as possible the impact of cross-border energy
exchanges on physical energy flows and on the power system. By
the same token, the French capacity market needs to reflect the
contribution of capacities to security of supply, including the inter-
connected system between France and neighbouring countries.
On the one hand, a market-design focusing on the sole contribu-
tion of French capacities or underestimating the contribution of
cross-border capacities to security of supply would result in over-
capacity in France. This overcapacity is costly for the French sys-
tem and therefore sub-optimal from an economic point of view.
On the other hand, a market-design overestimating the contribution
of cross-border capacities to security of supply in France could cause
a capacity shortfall, which means that the adequacy criterion defined
by the government would not be met. This situation leads to a very
high cost of shortfalls and therefore to economic inefficiencies.
RTE is particularly aware of the important contribution of cross-
border capacities to security of supply in France. Indeed, RTE is
legally in charge of the establishment and publication of ade-
quacy forecasts in France and is strongly involded in ENTSO-E’s
work on adequacy report at the regional or pan-European levels.
Therefore, the methodology of its Adequacy Forecast Reports
is based on a detailed model of the Western European power
system238 in order to reflect as accurately as possible the contri-
bution of interconnections to security of supply in France.
9.1.2.2 French and European frameworks
The “loi NOME/NOME law” has recognized the importance of
the cross-border dimension in the French capacity market:
Le mécanisme d’obligation de capacité prend en compte
l’interconnexion du marché français avec les autres marchés
européens.
This provision clearly reflects the willingness to recognise the
European dimension of security of supply in the design of the
capacity market.
238Details of the model used can be found in chapter 10 of this report.
200
The French approach is consistent with European Commis-
sion’s guidelines on generation adequacy in the internal
electricity market. Indeed, the Commission stresses the need
to properly include the cross-border dimension in adequacy
assessments:
Given this increasing integration of electricity markets
and systems across borders it is now increasingly dif-
ficult to address the issue of generation adequacy on a
purely national basis. Member States’ generation ade-
quacy assessments need to take account of existing and
forecast interconnector capacity as well as the genera-
tion adequacy situation in neighbouring Member States.
Surplus generation in neighbouring Member States may
alleviate adequacy concerns; shortages may exacerbate
them239.
The Commission has also included requirements on the need to
recognize the cross-border dimension in capacity mechanisms’
market designs:
[Capacity] mechanisms should be open to any capacity, inclu-
ding capacity located in other Member States, which can
effectively contribute to meeting the required generation
adequacy standard and security of supply240.
9.2.1 Cross-border participation in existing and planned capacity mechanisms
Many European countries have introduced capacity mecha-
nisms (chapter 1) based on different market designs. However,
ACER has underlined in its report on “Capacity remuneration
mechanisms and the internal energy market” that, most of the
time, these mechanisms are purely national schemes:
The existing CRMs are to a large extent tailored to a specific
market situation. As a result there is a large variation in the
existing CRMs’ design features. The experience with cross-
border participation is virtually non-existing241.
For instance, the Spanish and Italian capacity payments
do not provide for a remuneration of cross-border
capacities. Some countries have attempted to address
the issue of the impact of their capacity mechanism
on the energy market (e.g. Ireland’s capacity payment
scheme242) but it can also lead to distortions:
The [Capacity Mechanism] in the SEM takes account
of non-domestic generation by providing that impor-
ters into the SEM receive a capacity payment based
on their volume of imports; exporters from the SEM
9.2 Current status of cross-border participation in capacity mechanisms
pay a capacity payment to the SEM system based on their
volume of exports.
[…]
An example of how specific design choices may lead to a CRM
having a distortive effect on energy market is provided by the
capacity payment scheme operating in Ireland and Northern
Ireland. In this case, the distortions extend to the energy mar-
ket in Great Britain.
[…]
The way the SEM CRM has been designed may raise two chal-
lenges. First, its compatibility with the day-ahead target model for
cross-border trade (market coupling) to be implemented on the
Ireland - Great Britain interconnector. Once market coupling is
implemented it is no longer possible to distinguish which market
participant exports and/or imports and therefore to distinguish
who should receive or reimburse the capacity payment.
Second, and maybe of lesser importance, the ex-post ele-
ment of the capacity remuneration payment induces a risk
for traders and therefore requires a higher price difference
between the SEM and the Great Britain market to trigger
exports, which can impact utilisation of the interconnectors
and affect generation dispatch decisions243.
Swedish and Finnish strategic reserves do not provide for the
participation of cross-border capacities either. For example, in
239[EC, 2013a]
240[EC, 2013a]
241[ACER, 2013]
242[ACER, 2013]
243The electricity markets of Ireland and Northern Ireland are unified through what is called the “Single Electricity Market”, or SEM.
The French capacity market has a cross-border dimension because it makes sense economically and because it is necessary in order to meet legal requirements (both French and European). This prin-ciple should now be declined in the market design and different design solutions can be considered.
201
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
Sweden, cross-border participation has not been considered
as a possible option because the capacity mechanism was ori-
ginally designed to avoid the decommissioning of domestic
plants, which were considered as necessary to maintain an ade-
quate level of security of supply.
These examples highlight that the explicit participation of cross-
border capacities is not considered as a priority option in the
design of capacity mechanisms through Europe, regardless of the
type of capacity mechanisms chosen (strategic reserves, capacity
payments...). The participation of cross-border capacities is rather
defined implicitly, most of the time when dimensioning the needs.
For instance, the volume of strategic reserves needed in isolated
systems might be higher than in interconnected ones.
However, in the context of an integrated European electricity
market, the absence of cross-border participation can’t be
considered as a long-term target. Many countries will adapt their
mechanisms. For example, such adaptations are currently being
considered in Spain, Italy and Ireland.
Cross-border participation is an open-issue for capacity mecha-
nisms which are currently under consideration or being imple-
mented in other Member States. No “one-fits-all” solution has
emerged so far. Some explanations on the complexity of this
issue can be found in the United Kingdom’s consultation paper
on “Proposals for the implementation of a capacity mechanism
in the context of the Electricity Market Reform”.
The Government is keen to find a way for interconnected
capacity to be able to participate in the Capacity Market. Parti-
cipation of interconnected capacity would increase efficiency
by increasing competition in the auction, and provide appro-
priate incentives for additional investment in interconnection.
[…]
This is a complex area and we have worked closely with expert
stakeholders, other EU Member States and the European
Commission to explore possible solutions. However despite
this work we have been unable to find a solution that the
Government believes offers a practical solution for the first
capacity auction in November 2014. We continue to work
on this issue however and aspire to finding a solution that is
capable of being implemented at the earliest in time to com-
pete in the 2015 capacity auction244.
While reforming its capacity mechanism, Italy has not directly
addressed the question of cross-border participation. This issue
if left open:
la partecipazione di capacità localizzata all’es-
tero non è prevista dallo Schema di Disciplina.
Tuttavia, in coerenza con le future linee guida
della Commissione Europea, laddove operatori
localizzati sulla rete di un altro gestore di rete
europeo esprimessero, tramite il predetto ges-
tore, l’interesse a partecipare al mercato della
capacità italiano, Terna potrebbe esplorare col
medesimo gestore le eventuali modalità di par-
tecipazione di capacità localizzata sulla sua rete
al fine di delineare una proposta di modifica dello
Schema di Disciplina245.
Lastly, the transposition of mechanisms implemented in other
parts of the world, especially in the United States, can’t be consi-
dered as a proper option (chapter 8). Indeed, major differences
exist between the European and US electricity markets especially
regarding the regulatory framework, the governance framework
and the division of responsibilities between markets parties.
To sum up, there is no practical example of capacity mechanism
targeted on security of supply which allows for the participation
of cross-border capacities in Europe246.
9.2.2 Decision to implicitly recognise foreign capacity in the French capacity mechanism
During the process of designing the future capacity market
in France, the participation of capacities located outside the
French borders has been discussed many times and will be
implicitly recognized as a first step.
Indeed, this question was raised in 2011 during a public consul-
tation led by RTE in the framework of the report on the proposi-
tions for the design of the capacity mechanism commissioned
by the Energy Minister. The report issued in October 2011 advo-
cated that cross-border interconnection could be taken into
account implicitly at a first step, and explicitly in a second step.
Notably prerequisite to allow the explicit participation of
cross-border capacities are not currently fulfilled and an
additional implementation time is required. Consequently,
the explicit participation of cross-border capacities is not
foreseeable in a short-term vision, though RTE would like to
keep it as an “open-option” for the future. Notably if some
neighbouring countries adopt capacity mechanisms similar
to the French scheme, the operational implementation of this
explicit option would be much simpler247.
244[DECC, 2013]
245[AEEG, 2013]
246Germany’s reserve power plant mechanism, ResKV, enables the participation of capacities from other European countries. However, it is designed to secure reserves for the system (congestion management), not to guarantee security of supply.
247[RTE, 2011]
202
The perspective of explicit cross-border participation
was not a minor argument in favor of a decentralized
capacity market, based on tradable certificates. The
report detailed how a market design based on the
exchange of certificates that could be traded as a
commodity, regardless of Members States choices
on the level of security of supply, could offer a bet-
ter prospect for further European integration than
a system based on national auctions. The target is
therefore an explicit participation of cross-border
capacities through cross-border exchanges of capa-
city certificates.
The 2011 consultation listed several potential obs-
tacles to explicit cross border participation and led
to the recommendation of an implicit participation
of cross-border capacities as a first step. These obs-
tacles need to be carefully addressed in order to
consider the explicit participation of cross-border
capacities in the French capacity market:
> Certification and control of foreign capacities;
> Participation of demand-side capacities from
countries where their integration in the market is
not as developed as in France;
> Equivalence of the commitments of foreign and
French capacities;
> Settlement of imbalances for foreign capacities;
> Selection of foreign capacities participating in the
French capacity market;
> Guarantees on the individual contribution of cross
border capacities participating in the French capa-
city market to security of supply in France;
> Limited interconnection capacities require dedica-
ted cross border capacity calculation and alloca-
tion processes;
> Scope of cross border participation, from selected
countries to any interconnected country;
> Involvement of relevant foreign TSOs;
> Involvement of relevant foreign public authorities
in charge of security of supply;
> Consistency in Capacity Mechanisms participa-
tions and avoidance of double counting.
The French National Regulatory Authority, Commis-
sion de régulation de l’énergie, also acknowledged
that the complexity of these issues and that the
implicit participation of cross-border capacities was
an appropriate solution as a first step248.
Based on these considerations and on the relatively short imple-
mentation timeframe of the capacity market, explicit cross-bor-
der participation is ruled out in the first stages of the capacity
market. The 2012 decree provides that:
Interconnections between the French electricity market
and other European markets are taken into account in cal-
culating the capacity obligation; their effect is reflected in
the determination of the security factor, taking into account
the shortfall risk.
The scope of the consultation led by RTE in 2013 was legally
framed by the decree of December 2012. Consequently, the
implicit participation was not questioned as a principle, and only
the different possibilities to implement it were discussed.
This implicit solution already delivers important gains in terms
of economic efficiency, by lowering domestic capacity require-
ments and thus avoiding overcapacities. As such, the participa-
tion of cross-border capacities to the capacity market is model-
led as a positive externality.
This approach does not negatively impact the development of
interconnections as security of supply is also modelled as an
externality in RTE’s network development studies249 (incl. cost/
benefit analysis).
9.2.3 Towards an explicit cross-border participation in capacity mechanisms in Europe
In its Communication “Making the internal energy market
work”250, the European Commission has expressed concerns
about the implementation of national capacity mechanisms
and especially on the potential risk of fragmentation of the inter-
nal market.
Since then, capacity mechanisms are one of the most debated
topics regarding the electricity market design in Europe. The
European Commission along with ACER and industry represen-
tatives have highlighted the need to properly design capacity
mechanisms. This means that their impact on the internal mar-
ket needs to be considered and that the participation of cross-
border capacities needs to be addressed in a near future.
This section of the report gathers the positions of the European
Commission, ACER and Eurelectric regarding the cross-border
participation in order to identify common principles.
248[CRE, 2012]
249The examples cited in chapters 1 and 10 of this report are evidence that interconnection capacity between France and other European countries is being proactively developed.
250[EC, 2012]
251All quotations in this section are taken from the document [EC, 2013a]
252[EC, 2013a] It should be possible to allow capacity equal to the maximum import capacity of the Member State to participate in a national mechanism. This would create a demand for the use of the interconnection which could be marketed by TSOs separately from the normal allocation of cross border capacity.
253[EC, 2013a] Alternatively, long term allocation capacity on interconnectors could allow for cross-border participation in capacity mechanisms by allowing generators to demonstrate their ability to deliver electricity to the Member State in question.
254[EC, 2013a] Long term allocation capacity on interconnectors could allow for cross-border participation in capacity mechanisms by allowing generators to demonstrate their ability to deliver electricity to the Member State in question. […] With reliability options the incentive effect of the option should ensure that generators located in other Member States would anyway ensure they had sufficient interconnection capacity rights.
203
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
9.2.3.1 European Commission
The European Commission has recommended the explicit parti-
cipation of cross-border capacities in capacity mechanisms in its
Staff Working Document “Generation Adequacy in the internal
electricity market - guidance on public interventions”, accom-
panying the Communication “Delivering the internal electricity
market and making the most of public intervention”251:
[Capacity] mechanisms should be open to any capacity, inclu-
ding capacity located in other Member States, which can
effectively contribute to meeting the required generation
adequacy standard and security of supply.
However, the Commission has recognized that the implicit par-
ticipation of cross-border capacities could be considered, as a
temporary solution:
[I]t may be necessary, as an interim step, for Member States to
calculate the contribution of imports to meeting the genera-
tion adequacy standards.
The Commission has proposed two possible solutions for the
explicit participation of cross-border capacities in capacity
mechanisms. Both solutions are based on the hypothesis that
the cross-border participation of capacities should be limited to
the physical import capacity of a given country.
It should be possible to allow capacity equal to the maximum
import capacity of the Member State to participate in a national
mechanism. This would create a demand for the use of the inter-
connection which could be marketed by TSOs separately from
the normal allocation of cross border capacity252. Alternatively,
long term allocation capacity on interconnectors could allow for
cross-border participation in capacity mechanisms by allowing
generators to demonstrate their ability to deliver electricity to
the Member State in question253.
Both options are designed in order to manage scarcity situations
while taking into account realistic physical imports. However,
they can lead to very different results, since the volume of long-
term physical transmission rights allocated to market parties is
significantly below the maximum import capacity. Indeed, long-
term capacity calculation is subject to a high-degree of uncer-
tainty and therefore, the effective import capacity can only be
known as real-time approaches.
The management of scarcity situations is one of the main
challenges raised by the design of a cross-border capacity
mechanism. However, it is not the only issue that
needs to be addressed by the market design.
Indeed, it is crucial to design a solution in which
the contribution of cross-border capacities parti-
cipating to a given mechanism is guaranteed with
regard to security of supply in this country. The
European Commission has also stressed this issue
and defined it as the “effective contribution” of
cross-border capacities to security of supply. Such a
definition can also be found in the NOME law.
The Commission suggests two ways to address this
issue of “effective contribution”: a system based on the
allocation of interconnection capacity rights (financial
or physical) or a system involving “reliability options”254.
Both proposals are worth exploring, but could create
ties between capacity and energy markets.
The European Commission has recognised that the
explicit participation of cross-border capacities is a
complex issue and that it requires further and careful
attention from Member States and stakeholders255.
Notably, the Commission has highlighted the need
to avoid double-counting if a given capacity partici-
pates in several mechanisms simultaneously256.
Based on this diagnosis, the Commission has recom-
mended the establishment of a regional cooperation in
order to properly address those questions and issues257.
9.2.3.2 ACER
In its report on “Capacity remuneration mecha-
nisms and the internal market for electricity”258, the
Agency for the Cooperation of Energy Regulators
(ACER) has supported the participation of cross-
border capacities in capacity mechanisms, while
recognising the difficulties linked to its implementa-
tio259. ACER has defined these practical difficulties and proposed
potential solutions in point 45 of its report:
Cross-border participation to CRMs does not necessarily require
that cross-border capacity is set aside. However, it requires a
strong coordination of national security of supply policies and
the fulfilment of additional conditions, namely that:
a) the TSO, in whose jurisdiction the CRM is implemented,
is able, directly or through the adjacent TSO, to monitor the
actual availability of the (capacity) resources committed by
foreign provider over the contracted period and that the
255[EC, 2013a] The Commission Services recognise there may be practical difficulties of implementing a framework for cross border certification of capacity and accounting for “capacity” import and export. […] The Commission Services will continue to work with Member States, ACER and National Regulatory Authorities, and ENTSO-E and TSOs to examine how cross border trading can be facilitated in capacity mechanisms.
256[EC, 2013a] Obviously generation abroad or interconnector capacity should not be double-counted or double remunerated.
257[EC, 2013a] Regional cooperation would facilitate addressing this problem and should be pursued where possible.
258All quotations in this section are taken from the document [ACER, 2013]
259[ACER, 2013] In the case of national [Capacity Mechanisms], greater efficiency could be achieved and the distortion of the IEM minimised by assuring participation – to the extent possible – of adequacy and system flexibility resources provided by generators and load in other jurisdictions. The challenges to this are however significant.
204
foreign provider is able to provide the same level
of commitment with respect to security of supply
than a local provider;
b) efficient cross-border allocation mechanisms are
implemented on all timeframes, in particular in the
day-ahead, intra-day and balancing timeframes;
c) MSs accept that their national resources (e.g.
generation plants) are partly contracted to ensure
the security of supply of a neighbouring MS and
guarantee that providers will not be hindered in
exporting at any moment in time, i.e. TSOs do not
deviate from their routine in offering cross-border
capacity in particular in stressed situation on both
sides of the border.
According to ACER, in order to enable the explicit
participation of cross-border capacities, Member
States must recognise that part of their national
resources are contracted to ensure security of
supply of a neighbouring Member States and
guarantee that there will be no export restriction
including during stress events260.
To that extent, ACER has underlined a lack of
coordination between Member States on secu-
rity of supply issues261 and made the following
recommendations:
I. the harmonisation of generation adequacy
criteria and security of supply levels should be
undertaken where possible;
II. a common (at least regional) and coordina-
ted approach for a thorough security of supply
assessment should be implemented.
9.2.3.3 Eurelectric
Numerous stakeholders have contributed to the
debate on cross-border participation in capa-
city mechanisms. Eurelectric has notably pres-
ented a possible solution during its conference
of December 2013: “Future electricity markets
with or without capacity mechanisms: What
does Europe say?”262
Like the European Commission and ACER,
Eurelectric has advocated for cross-border
participation in capacity mechanisms263 and
acknowledged the complexity of the issue264.
Eurelectric has made a detailed proposition of market design in
order to enable cross-border participation in capacity mechanisms.
This proposition aims at defining key principles for such a design
but needs to be further assessed, especially regarding operational
aspects. The key elements of this proposition are as follows:
> All participants (national or foreign) in a CRM must fulfil the
same requirements and market rules in relation to e.g. cer-
tification, penalty regime, availability requirements, energy
producing requirements, etc.
> It should not be possible to participate with the same capa-
city in more than one CRM at a time. Each MW in the CRM
cannot be committed twice and receive double earnings.
Therefore it should also be possible for capacity providers
to “opt out” of their national scheme in order to instead par-
ticipate in a mechanism established elsewhere.
> TSOs should bear the responsibility of proposing the
amount of cross-border interconnection capacity volume
that can be offered for CRM cross-border participation. This
amount should be approved by the relevant regulators. The
higher the amount, the more competition from foreign par-
ticipants will be possible in the national CRM.
> There would be a separate congestion rent for the CRM
cross-border capacity allocation. This congestion rent
should be used in the same way as the energy congestion
rent from forward and day-ahead allocation. This means
that the benefit from cross-border capacity and energy tra-
ding will be considered when calculating the benefit of new
transmission investments.
> There should be no cross-border capacity reservation for
CRM: cross-border participation in a CRM should have no
influence on the cross-border allocation for forward, day-
ahead, intra-day and balancing markets.
Eurelectric has also explored options in terms of market design
to allow cross-border exchanges of capacity products including
the allocation of cross-border interconnection capacity. This
proposed model is based on the same principles as the day-
ahead market coupling ones265.
The paper presents examples of implementation of such
models, including a schematic vision of cross-border trades in
different market situations.
Lastly, Eurelectric has recommended greater coordination
on security of supply in Europe to allow cross-border capacity
mechanisms to work efficiently266.
260[ACER, 2013] Without such a guarantee, the foreign provider would not be able to deliver the same level of commitment with respect to security of supply than a local provider.
261[ACER, 2013] The Agency observes […] that MSs currently have national and diverging approaches to security of supply with a lack of coordination among them.
262The quotations in this section are taken from the accompanying note to this presentation [Eurelectric, 2013]
263[Eurelectric, 2013] EURELECTRIC agrees with the European Commission that national capacity remuneration mechanisms (CRM) should be open to cross-border participation.
264[Eurelectric, 2013] We believe that it is possible to let capacity providers from other bidding zones participate in capacity mechanisms using market-based procedures. […] EURELECTRIC recognises the complexity of the [Capacity Mechanism] cross-border participation concept.
265[Eurelectric, 2013] A possible design for CRM cross-border participation could be based on the same principles as Day-Ahead market coupling. Two situations are possible:- CRM is based on central auctions to set the value of the CRM: The cross-border capacity for participation in CRM could be allocated implicitly during a common auction to determine the CRM price in different bidding zones.- CRM is not based on auctions, but on other mechanisms: The cross-border capacity for participation in CRM could be auctioned separately (explicit auction). In both situations, cross-border capacity will be allocated by TSOs several times for two purposes:1) to use resources (generation, demand response, storage) from two or more bidding zones to ensure adequacy […]2) to ship energy […]Congestion rent accumulated during these two auctions should be essentially used for building cross-border interconnection capacity.
205
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
To ensure consistency between the French legal framework and
recent guidelines from the European Commission, RTE proposes
a roadmap on cross-border participation. Based on a three-step
approach, this roadmap enables the implementation of the
French capacity market on schedule with an implicit participa-
tion of cross-border capacities while investigating on practical
evolutions in order to reach the target of explicit cross-border
participation.
> Step 1: Implicit cross-border participation
In accordance with the provisions of Decree 2012-1405 of
14 December 2012 creating a capacity obligation mechanism ,
the rules of the French capacity market provide for the implicit
participation of cross-border capacities. This cross-border partici-
pation is based on the representation of the positive impact of
interconnections on security of supply and leads to a reduction of
the obligation of suppliers in the capacity market.
> Step 2: Public consultation on cross-border participation
In accordance with the provisions of Decree 2012-1405 of
14 December 2012 , the rules of the French capacity market267
entrust RTE with the responsibility of proposing potential evo-
lutions of the market design regarding cross-border participa-
tion. To that extent, RTE will launch a public consultation regar-
ding cross-border participation in the French capacity market.
Following this consultation process and its outcomes, RTE will
9.3 A practical way forward for explicit cross-border participation
report to the French National Regulatory Authority and the
Energy Minister on potential evolutions of the French capa-
city market design regarding cross-border participation no
later than ten months after the entry into force of the French
capacity market rules. These propositions should include the
design of a target towards explicit cross-border participation
and can be based on a step-by-step approach to implement
this target.
This roadmap paves the way towards explicit cross-border partici-
pation in the French capacity market (incl. a timeline to conduct
this work).
Prior to the consultation process and in order to foster concrete
propositions on cross-border participation, RTE is conducting
internal studies on this topic and shares forward-
looking principles on explicit cross-border parti-
cipation in this report.
> Step 3: Evolutions of the French capacity
market design
In order to implement evolutions of the French
capacity market design regarding cross-border
participation, amendments to the decree of
December 2012 might be required.
266[Eurelectric, 2013] [Capacity Mechanisms] should be […] underpinned by close coordination between Member States and respective transmission system operators (TSOs). […] EURELECTRIC […] pleads for harmonisation/coordination of national CRMs to facilitate participation of foreign generation, demand response and storage.
267Article 5.2.3.4.
The European debate on capacity mechanisms has grown in 2013, especially regarding the design of cross-border participation. Common principles have been elaborated by different stakeholders in order to tackle the issue of explicit cross-border participation:
> Capacities participating in a given capacity mechanism need to have an effective contribution to security of sup-ply of the dedicated country;
> The participation of cross-border capacities to different capacity mechanisms needs to be properly designed in order to be consistent and effective ;
> Cross-border participation should be limited to the effective physical import capacity;
> A regional cooperation framework on security of supply needs to be agreed upon by Member States and TSOs.
Currently, no capacity mechanism has implemented a solution for the explicit participation of cross-border capaci-ties. This underlines the complexity and the numerous challenges raised by this issue.
This European debate on capacity mechanisms has arisen during the last consultation process on the French capacity market, which was framed by the 2012 decree’s provision on the implicit participation of cross-border par-ticipation. Taking into account both the European and the French context, RTE proposes to pave the way towards explicit cross-border participation in the French capacity market through a dedicated roadmap.
206
Therefore, and as proposed by RTE, a step-by-step approach
seems to be an efficient way forward as it enables the relatively
quick implementation of transitory solutions. A transitory solu-
tion can be defined as the phase between the current implicit
cross-border participation and the target (the so-called “full”
explicit cross-border participation).
As all prerequisites for a go-live of the target might not be fulfil-
led simultaneously on all borders and, especially, depend on the
implementation of a cooperation framework between Member
States at a regional level, there is a chance of overlapping between
explicit and implicit cross-border participation solutions. In such a
case, it will be important to avoid double counting.
Any form of explicit cross-border participation requires an effec-
tive contribution of foreign capacities to security of supply of
the country in which the capacity mechanism is implemented.
However, the definition of effective contribution may differ in
the target (“full” explicit cross-border participation) or in a tran-
sitory solution. In this regard, during the implemen-
tation of a transitory solution, explicit participation
of cross-border capacities to the French capacity
market should be limited to capacities which are also
participating to the French balancing mechanism268.
The integration of the energy market has shown the
efficiency of the “regional” approach for cross-border
projects. This approach is based on the cooperation
of a set of countries within an electricity regional ini-
tiative and the progress reports of those initiatives in
terms of market coupling are of crucial importance for
the completion of the target model at the EU level.
268This will nonetheless require a change to the method of accounting for foreign bids currently applied in the French balancing mechanism. Changes made to the balancing mechanism following the implementation of the Electricity Balancing Code will also have to be taken into account.
269Bundesverband der Energie- und Wasserwirtschaft.
Figure 84 – Roadmap on cross-border participation in the French capacity market
Step 1 Implicit
Step 2 Consultation
Step 3 Modifications
Transition Intermediate model Target model
Publication of capacity
mechanism rules +10 months
The French and German governments, along with stakehol-
ders from both countries, have recently called for greater
Franco-German cooperation in the area of electricity. To that
extent, the Union française de l’électricité and its German
counterpart – BDEW269 – have elaborated, along with their
members, a work program in order to identify common sub-
jects of interest and cooperation. Their goal is notably to pro-
mote mutual understanding on security of supply issues and
to foster electricity market reforms in order to tackle those
issues.
RTE has included forward-looking principles on explicit cross-
border participation in this report. These principles are the
outcomes of early discussions on explicit cross-border parti-
cipation in the French capacity market. They constitute a raw
material elaborated in order to prepare the public consultation
process provided for in article 5.2.3.4 of the French capacity
market rules.
Contrary to the French capacity market rules, these principles
have not yet been shared and discussed with stakeholders. It will
be the scope of discussion of the public consultation on cross-
border participation. Such a discussion will necessary have to be
challenged at a regional level.
The points discussed in this section should be considered as RTE’s prospective contribution to the European debate on cross-border partici-pation in capacity mechanisms, and go beyond the current legal framework implementing the French capacity market.
207
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
degree of uncertainty regarding the implementa-
tion timeframe of explicit cross-border participation
or even question the ability to implement it at all.
Moreover, harmonising security of supply criteria in
Europe would not necessarily make sense from an
economic point of view. Defining a common value of
lost load that could be agreed upon by all countries
despite their differences seems very unlikely. Indeed,
European countries have structural differences: their
economy, their energy mix, their structure of energy supply and
their exposure to risks on security of supply. Therefore, a constrained
harmonisation of security of supply criteria could lead to economic
inefficiencies. Moreover, it is worth underlining that a regional har-
monisation does not solve the issue as the interface between these
regional security of supply still needs to be addressed.
9.3.1.3 Economic efficiency and real value for security
of supply in concerned countries
The design of an explicit cross-border participation solution
should be seen as an opportunity to improve the economic
efficiency of capacity mechanisms. To that extent, it is worth
acknowledging that implicit cross-border participation already
is an efficient solution as the positive impact of interconnections
is valued through a reduction of the obligation of suppliers and
therefore avoid a situation of overcapacity in France. This effi-
ciency will be further enhanced by:
> The completion of the energy market;
French stakeholders have been strongly involved in electricity
regional initiatives, including for innovative projects272. This has
led to an early and significant level of integration of the French
market with its neighbours.
> Improved adequacy assessments;
European TSOs, within ENTSO-E, are currently working on the
improvement of their adequacy assessments at the European
level. This work is a step in the right direction to reach this objec-
tive. At the French level, RTE’s adequacy assessments comply
with the guidelines from the European Commission273.
9.3.1 Key principles to design a solution for explicit cross-border participation
Cross-border participation in capacity mechanisms is a complex
subject that needs to be tackled while considering the target
model for the European electricity market. Therefore, in order to
design and implement a solution for cross-border participation,
it is important to have a common understanding on high-level
design principles and on the challenges that need to be tackled.
9.3.1.1 Preservation of the internal energy market
The progressive integration of the internal energy market is a
major success for Europe. Security of supply in Europe is also
enhanced by the optimisation of cross-border trades through
market coupling mechanisms. The European Commission has
outlined the benefits of the internal energy market in its Com-
munication “Making the internal energy market work”270.
These breakthroughs towards the integration of the internal
energy market have required several years of intensive work and
are not yet completed. To that extent, any market design evo-
lutions driven by the implementation of capacity mechanisms
needs to be done while preserving the internal energy market
and its benefits271. This applies both for the implementation of
capacity mechanisms at the national level or for the design of
explicit cross-border participation solutions.
9.3.1.2 Compatibility of Member States’ competences
and choices
The Lisbon Treaty provide for the division of competences
between the European Union and Member States and energy is
defined as a shared competence. Moreover, the Treaty specifies
that Union energy policy measures shall not affect a Member
State’s right to determine the general structure of its energy sup-
ply. This means that the final responsibility with regard to security
of supply issues remains national (incl. security of supply targets).
A review of this division of competences would require major legal
amendments, possibly up to the European treaties.
Therefore, explicit cross-border participation in capacity mecha-
nisms should not be conditioned to a pan-European harmonisa-
tion of security of supply criteria. Indeed, it would create a high
270[EC, 2012]
271See section 10.2 of this report for a discussion of the absence of provisions in the French capacity mechanism that would disrupt energy markets.
272See chapter 10 of this report.
A solution for explicit cross-border participation in capacity mechanisms must be compatible with Member States’ competences as provided for in the Lisbon Treaty. Therefore, it should also be respectful of their (different) choices in terms of security of supply.
Preserving the internal energy market and its benefits is a crucial principle to take into account while designing solutions for explicit participation in capacity mechanisms.
208
Explicit cross-border participation to the French
capacity market could increase its economic effi-
ciency as it will enlarge the choices of investors
regarding the location of capacities.
However, explicit cross-border participation only makes sense if the
effective contribution of a capacity to security of supply in a country
is not impacted by the geographical location of this capacity. It is
not enough to enable capacities to participate in a capacity mecha-
nism: the underlying physical reality must be similar, regardless
of the location of these capacities (domestic or cross-border). In
other words, a capacity should be able to choose the geographical
zone in which it will effectively contribute to security of supply. This
choice should be consistent with the geographical scope of the
capacity mechanism in which this capacity participates.
ACER has made a similar observation274:
Cross-border participation to [Capacity Mechanisms requires
that] […] MSs accept that their national resources (e.g. genera-
tion plants) are partly contracted to ensure the security of sup-
ply of a neighbouring MS and guarantee that providers will not
be hindered in exporting at any moment in time, i.e. TSOs do
not deviate from their routine in offering cross-border capacity
in particular in stressed situation on both sides of the border.
[…]
Without such a guarantee, the foreign provider would not be
able to deliver the same level of commitment with respect to
security of supply than a local provider.
Explicit cross-border participation in the French capacity market
will only lead to an increased economic efficiency if cross-bor-
der capacities can effectively and physically contribute to secu-
rity of supply in France. This means that:
> A certified cross-border capacity should be available during periods
of system stress. This availability should be subject to a control;
> The level of certified cross-border capacities should be com-
patible with the import capacity of interconnections;
> Certified cross-border capacities for a given capacity mechanism
should be committed to contribute to security of supply in this
country even in cases of simultaneous shortage in several countries.
9.3.2 Relevant event to be considered to allow effective cross-border exchanges of capacity products
The expected outcome of explicit cross-border participation in a
capacity mechanism is to be able to rely on imports when security
of supply is threatened. This implies that the definition of a capa-
city product tradable cross-border and the associated market
design cannot be separated from a broader discussion over secu-
rity of supply and the way it is ensured in a market environment
at the European level.
In most cases, the way cross-border capacities could contribute
to security of supply of a given country – like France – is straight-
forward: power flows indicated by the market coupling algorithm
would most certainly be directed towards the country facing the
risk of shortage. This means that current markets already provide
for the participation of cross-border capacities to security of sup-
ply – albeit in an aggregate form and without any kind of guarantee.
This explains why the implicit solution considered so far is in itself
already a fair way to consider the interconnection of countries.
However, capacity mechanisms are precisely implemented to ensure
the effective contribution of capacities to security of supply. In a way,
the capacity mechanism works like an insurance policy. As the consu-
mer pays for insurance, he needs to be granted an insurance cover.
The effective contribution is the cover granted to consumers as they
pay for security of supply. Explicit cross-border participation solutions
need to provide this “insurance” cover to the system or will be ineffi-
cient. To properly assess this issue, it is necessary to consider events
during which the current markets do not spontaneously direct energy
flows towards countries that have chosen to cover their consumers
towards risks on security of supply through a capacity mechanism.
Indeed, in some specific situations, it is not sure that the natural out-
come of energy markets will lead to optimal flows between areas.
This is notably the case when there is a shortage in two countries
simultaneously: what should happen to the capacity contracted
through a capacity mechanism and the energy it generates? The
market coupling algorithm might not be able to clear in those situa-
tions. Indeed, in case of simultaneous shortages, the market situa-
tion will probably result in a lack of offers of energy bids (included “at
any price”) to meet the demand. In those cases where the market
does not clear, the allocation of bids might not be accurate despite
their key role regarding the energy flows between countries.
In those situations, specific provisions could be required to handle
power flows properly and ensure that they benefit to consumers
on the basis of what they have paid for security of supply. Such
273See chapter 10 of this report.
274[ACER, 2013]
As for domestic generation or demand-side capac-ities, the effective contribution of cross-border capacities to security of supply in the country in which the capacity mechanism is implemented is a crucial point to be addressed.
209
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
provisions would constitute a clear basis for cross-border partici-
pation in capacity mechanisms, and would be impacted by cross
border exchanges of capacity.
In order to be efficient and credible, these provisions need to be
embedded in a broader cooperation framework on security of sup-
ply and especially on the management of shortage situations. Such
a cooperation framework could be negotiated and implemented by
transmission system operators with the approval of national regu-
latory authorities and under the control of Member States. Along
with market arrangements, it needs to include provisions on opera-
tional issues and could be completed by cooperation agreements
at Member State level, especially bilateral agreements to ensure a
faster implementation (for example between France and Germany).
These cooperation frameworks need to be consistent with Mem-
ber States’ competences regarding the structure of their electricity
supply as defined by article 194 of the Lisbon Treaty, and especially
without considering harmonisation of security of supply criteria as
a prerequisite. The Commission de régulation de l’énergie has also
stressed the importance of European coordination regarding expli-
cit cross-border participation in the French capacity market275.
9.3.3 “No-go” solutions to implement explicit cross-border participation
Cross-border capacities contribute to security of supply in France
through interconnections, of which transfer capacity is limited.
The potential of their contribution is therefore constrained, and
there are situations in which an additional cross-border capacity
will not bring any improvement to security of supply in France
because interconnections are already fully used. This physical
limitation needs to be properly addressed in the design of a solu-
tion to ensure explicit cross-border participation in the French
capacity market.
Various solutions can be considered as able to ensure the effec-
tive contribution of cross-border to security of supply. Although
intuitive, two options must be ruled out: the use of physical trans-
mission rights and the reservation of interconnection capacity.
9.3.3.1 Use of physical transmission rights (PTR)
Intuitively, one could consider that holding, or even nominating,
PTRs is a sufficient solution to ensure the effective contribution of
cross-border capacities to security of supply in France276.
However, while PTRs provide for an entitlement to use part of
the available cross-border transmission capacity at a point in
the future to flow energy between countries, they are not a
necessary prerequisite for cross-border trading.
Indeed, the European target model for electricity
provide for two different types of auctions. In the
day-ahead timeframe, transmission capacity and
electricity are traded together through implicit auc-
tions. It completes the explicit auctions where capa-
city (PTR) and electricity are traded separately in the
long-term timeframe.
Moreover, nominating PTRs is not a sufficient condi-
tion to guarantee the direction of a power flow.
Indeed, as capacity is allocated in different time-
frames (long-term, day-ahead, intraday), the aggre-
gated balance of flows provide for the direction and
volume of power flows. To that extent, an individual
stakeholder nominating a PTR can’t guarantee the
physical flow linked to this commercial exchange.
This particular point has been detailed in RTE’s 2011 report to the
Energy Minister on the main design principles of the French capa-
city market277.
Holding PTRs is a neither necessary nor sufficient condition to
ensure the effective contribution of cross-border capacities to
security of supply in a given country. This design solution for
cross-border trades of a capacity product must be ruled out.
9.3.3.2 Reservation of interconnection capacity
Reservation of interconnection capacity could also be considered
as a potential design solution for explicit cross-border participa-
tion. However, this solution has an obvious negative impact on
energy trades and might not be compatible with the existing legal
provisions on the allocation of interconnection capacity278.
Though this solution could guarantee the effective contribution
of cross-border capacities to security of supply, it does not pres-
erve the European energy market. Reservations of interconnec-
tion capacity would limit the possibility for cross-border energy
trades, disturb the optimisation process of trades and therefore
lead to economic inefficiencies.
Considering this solution would nonetheless be justified if capa-
city and energy trades were exclusive goods, i.e. if capacity trades
automatically precluded energy trades.
However, at the national level, generation plants can trade capa-
city certificates through the capacity mechanism without lowe-
ring their energy outputs or restraining their ability to participate
275[CRE, 2012] Stronger cooperation between Member States, system operators and regulators appears crucial to guarantee that the tools implemented are similar and coordinated or, failing that, to ensure that different mechanisms can interact effectively.
276PTRs are “physical transmission rights with a use-it-or-sell-it condition”.
277[RTE, 2011]
278See, among others, the provisions of the Network Code for Capacity Allocation and Congestion Management.
210
in the energy market. This means that a “security of supply” pro-
duct and an energy one are not exclusive goods.
By the same token, cross-border trades of “security of supply” pro-
ducts – in other words capacity products – do not compete with cross-
border energy trades. To that extent, to ensure the effective contribu-
tion of a capacity to security of supply in a given country, reservation of
interconnection capacity appears to be an excessive solution.
To sum up, reservation of interconnection capacity is a sufficient
but not necessary condition to ensure the effective contribu-
tion of cross-border capacities to security of supply. Moreover, it
would probably a distortive solution with regards to the European
energy market outcomes. As this solution is not a necessary one
and leads to economic inefficiencies, it should be ruled out.
9.3.4 Target solution for explicit cross-border participation in the French capacity market
The design of a market solution to allow explicit participation
and effective contribution of cross-border capacities in capacity
mechanisms need to respect ground principles. Based on inter-
nal studies, RTE has defined 5 main design conditions and shares
them in the following section
RTE considers that it is possible to allow explicit cross-border par-
ticipation in the French capacity market:
> Without harmonising security of supply criteria between
Member States (condition 1).
A solution for the explicit cross-border participation in capacity
mechanisms must be compatible with Member States’ competences
as provided for in the Lisbon Treaty. A review of this division of com-
petences would require major legal amendments, possibly up to the
European treaties, and should therefore not be questioned, especially
to allow a fast implementation of explicit solutions. Moreover, from an
economic point of view, national security of supply criteria accurately
reflect a Member State’s specific situation and might therefore be
more efficient than a European harmonised criterion
> Without reserving interconnection capacity (condition 2).
This point was discussed in paragraph 9.3.3.2. Reserving intercon-
nection capacity would go against the principles of the internal
market and reduce the economic optimisation enabled through
energy trades. Indeed, capacity and energy are not exclusive pro-
ducts. This means that participation in the capacity mechanism
does not preclude participation in energy markets. Likewise,
cross-border capacity trades and cross-border energy trades are
not exclusive. This solution therefore seems sufficient to ensure
the effective contribution of cross-border capacities to security of
supply in France but is disproportionate.
> Limited to the effective physical import capacity and based
on market rules (condition 3).
Cross-border capacities can contribute to security of supply in France
through interconnections. Their contribution therefore cannot
exceed the import capacity of interconnections between France and
its neighbours. This physical limitation needs to be address through
a market-based allocation process of the interconnection capacity.
Moreover, to ensure the effective contribution of cross-border
capacities to security of supply in France, these capacities need to
be available during system stress events in France.
RTE also considers that the target model for explicit cross-border
participation in the capacity market should allow trades of capa-
city products and be consistent with cross-border energy trading
mechanisms. The implementation of this target model is possible:
> If a cross-border certification or control process is in place
(condition 4).
Explicit cross-border participation in the French capacity mar-
ket will require a dedicated and robust market architecture that
reflects the specific characteristics of “capacity” as a product
along with the various aspects of security of supply.
Cross-border capacity trades can only be efficient if there is a
cross-certification process between Member States or if conver-
sion keys different “capacity” products are defined. This is a prere-
quisite to ensure the effective contribution of cross-border capa-
cities to security of supply in a given country.
If cross-border trades does not include such arrangements, there will
be no certainty towards cannot the effective contribution of capaci-
ties to security of supply and thus these types of solutions should not
be considered as a way-forward for the future market design.
> If cooperation frameworks are in place to manage shortage
situations (condition 5).
As discussed in § 9.3.2, widespread shortage situations should be
considered as reference events to assess the effective contribu-
tion of cross-border capacities to security of supply in another
country. These specific events can be defined as a situation when
a shortage situation in one country creates a shortage situation in
other countries (a sort of snowball effects) or in case of simulta-
neous shortages in two countries.
211
EUROPEAN INTEGRATION OF THE FRENCH CAPACITY MARKET / 9
In such situations, a cooperation framework on security of sup-
ply and especially on the management of shortage situations is
required. Such a cooperation framework could be negotiated and
implemented by transmission system operators with the approval
of national regulatory authorities and under the control of Mem-
ber States. This cooperation framework would allow the proper
management of widespread shortage situations and the effective
contribution of cross-border capacities to security of supply.
The fulfilment of these conditions requires a major regional coordi-
nation. The agreement of cooperation frameworks on security of
supply will notably require an intense work between Member States,
national regulatory authorities and transmission operators. To that
extent, it makes sense to consider a transitory solution for the explicit
cross-border participation with a shorter implementation timeframe.
9.3.5 Shaping a transitory solution
Whereas the target solution will require significant preliminary work,
it could be possible to introduce a transitory solution in the rela-
tively near future. Though it would be imperfect and designed to
be ultimately replaced by the target solution, a transitory solution
could truly improve the design of the capacity market, provided
that it offers real benefits in terms of security of supply. As discussed
above, in the absence of a cooperation framework ensuring that
conditions 4 and especially 5 are met, it will be necessary to define
another process to ensure the effective contribution of cross-bor-
der capacities to security of supply. This control process could be
based on existing market mechanisms and could entail:
> The mandatory participation of cross-border capacities in
the French balancing mechanism (condition 6, which can be
substituted for conditions 4 and 5)
Explicit cross-border participation needs to rely on the effective
contribution of cross-border capacities to security of supply. If it
does not, the credibility of the entire process will be called into
question. As in France, cross-border capacities need to have avai-
lability commitments. In the absence of such a commitment, it will
not be possible to check their effective contribution to security
of supply. Moreover, an availability commitment limited to a few
GW of capacities located in a foreign country has no added-value
on security of supply in France. Indeed, this size of this capacity is
insufficient to cover the needs in its own country in case of shor-
tages. Therefore, the method of participation and the definition
of commitment need to be adapted for cross-border capacities.
In this regard, the direct or indirect participation of cross-border
capacities in the French balancing mechanism could ensure,
albeit imperfectly, their effective contribution to security of sup-
ply and to the reduction of the shortfall risk in France (substitute
for condition 5). The participation of cross-border capacities in
the French balancing mechanism would also allow cross-border
capacities to have similar verifications and controls as the French
ones (substitute for condition 4).
This option could even be pushed further based on a reciprocity
principle applied to Member States that have introduced a capa-
city market with availability commitments. Through a mutual
recognition of capacity mechanisms and ensuring the absence of
double counting, this system could allow cross-border capacities
to participate in the French capacity market and to French capaci-
ties to participate in other capacity mechanisms.
If a transitory solution is adopted and conditions 4 and 5 are removed,
provisions would still be required to ensure that condition 3 is met.
This means that the physical limit of interconnection import capacity
needs to be taken into account. Such provisions could be designed
as transmission rights dedicated to capacity markets. Some stakehol-
ders have recently suggested a solution along these lines. The idea is
for suppliers to hedge part of their obligations with interconnection
transmission rights, which would be based on the average contri-
bution of interconnections to security of supply during a peak load
event. This proposition assumes that the transmission rights would
be allocated free of charge, on a pro-rata basis. This solution would
have to be considered during the public consultation that RTE is pro-
posing to organise on explicit cross-border participation.
Other propositions were made. For instance, the French Com-
petition Authority has proposed in 2012 a solution involving the
allocation of cross-border capacity rights. This would be based
on market rules through an auction process. This type of system
could also be considered.
Lastly, implementing transitory solutions could lead to the imple-
mentation of a different approach at each border, as it might
take a lot of time to define a unique harmonised approach. This
also means that implicit and explicit participation of cross-border
capacities will coexist for a time. Implicit participation will remain
for market zones which are not covered by the explicit solution.
Implementing such a transitory solution would go beyond the
current legal framework of the French capacity market. RTE is
thus requesting a mandate of the Energy Minister on the possible
implementation of a transitory solution regarding explicit cross-
border participation in the French capacity market and on the
scope of the proposed public consultation.
212
10.1.1 Competence of Member States with regard to security of supply
Article 4 of the Treaty on the Functioning of the
European Union (TFEU) includes energy in the
list of areas of shared competence between the
Union and Member States. Article 194 of the TFEU
specifies how this competence is shared between
the Union and Member States when it comes to
10. COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES The creation of a capacity mechanism in France is provided for
in law 2010-1488 of 7 December 2010 reforming the organisa-
tion of the electricity market (NOME Law) and is a major evolu-
tion of the market design in France. This provision is embedded
in a broader review of the functioning of the regulated power
system and, especially, of market mechanisms. The main goal of
this revision program is to integrate demand-side response in all
market mechanisms, all timeframes279.
Imperfections observed in the energy market, together with
a substantial change in the physical needs of the French and
European power system, have raised questions about whether
the energy-only market alone can guarantee security of supply,
notably at a time when the energy transition is under way and
peak demand in France is increasing. Therefore, public interven-
tion to complement the existing market signals is justified.
Three fundamental choices about the capacity mechanism’s
market design were made in decree 2012-1405: (1) it would
be a market mechanism, (2) involving all capacities, and (3) all
market stakeholders would be held accountable for their contri-
butions to security of supply thanks to a decentralised archi-
tecture280. The capacity mechanism rules proposed by RTE put
these principles into practice. Moreover, while drafting its pro-
position of rules, RTE paid a special attention to the definition
of the required parameters to calculate suppliers’ obligation,
capacities’ certification or imbalance settlements. These
choices were made in order to design a capacity mechanism
that targets security of supply, is proportionate to this objective
and guarantees equal treatment for all stakeholders281. To this
end, RTE has prepared a roadmap and common principles for
allowing the explicit participation of cross-border capacities in
the mechanism along including a timetable to conduct a public
consultation on this issue before submitting concrete proposals
to the French Energy Minister and Regulatory Authority282.
All provisions included in French laws and in the rules proposed
by RTE regarding the capacity mechanism must be considered
within a European context. Indeed, though security of supply
is a component of Member States’ energy policies, there is, on
the one hand, significant interplay between Member States’
energy policies in an integrated market, and on the other hand,
a competence of the European Union in the area of energy .
In this report, RTE has sought to assess the French capacity
mechanism’s compatibility with the provisions of European
law. This chapter reviews the European legal framework within
which the capacity mechanism falls (§ 10.1) and demonstrates
that the market design adopted for the capacity mechanism
and developed in the rules proposed by RTE complies with the
general principles of necessity and proportionality set out in the
EU acquis and the European Commission’s recommendations
(§ 10.2).
10.1 The European legal framework governing State intervention to ensure security of supply
279See chapter 1 of this report
280See chapter 2 of this report
281See chapters 3 to 7 of this report
282See chapter 9 of this report
energy policies. This article indicates that Union policy on
energy shall aim to:
(a) Ensure the functioning of the energy market;
(b) Ensure security of energy supply in the Union;
(c) Promote energy efficiency and energy saving and the
development of new and renewable forms of energy; and
(d) Promote the interconnection of energy networks.
213
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
283Article 3 of Directive 2005/89/EC
284[EC, 2013]
285Recital 10
286Considering different rulings in European case law, notably ECJ, 27 April. 1994, Case C-393/92, Municipality of Almelo ECR I, p. 1477, according to which electricity constitutes a good, it seems difficult to challenge that capacity can be considered a good, despite its potentially strategic characteristics (ECJ, 4 Oct. 1991, Case C-367/89, Richardt: ECR 1991, p. I-4621, point 16).
287[EC, 2013], [ACER, 2013]
288[EC, 2013]
This article also emphasises that measures taken by the Union
shall not affect a Member State’s right to determine its own
energy mix and the “general structure of its energy supply”. In
other words, security of supply is a matter of national compe-
tence and this competence must be exercised with due regard
to the principles and provisions of European law.
Secondary legislation takes this competence sharing into account
when defining the role of Member States in security of supply mat-
ters. Article 4 of Directive 2009/72/EC of 13 July 2009 concerning
common rules for the internal electricity market notably affirms that
“Member States shall ensure the monitoring of security of supply
issues”, and particularly “measures to cover peak demand and deal
with shortfalls of one or more suppliers”. Member States thus define
their own security of supply criterion and arrange to meet it by taking
the measures necessary to ensure a “stable investment climate”283.
The EU acquis thus does not prohibit state intervention to
ensure security of supply. The European Commission confirms
this in its Communication “Delivering the internal electricity
market and making the most of public intervention”:
Public intervention can be useful and effective to attain policy
objectives set at Union, regional, national or local level, but it must
be well designed and should be adapted to changes in market
functioning, technology and society that occur over time284.
Capacity mechanisms are explicitly named within the secondary
legislation among the tools for guaranteeing security of supply.
The possibility for Member States to introduce capacity mecha-
nisms is notably included in the measures provided for in Direc-
tive 2005/89/EC of the European Parliament and of the Council
of 18 January 2006 concerning measures to safeguard security
of electricity supply and infrastructure investment:
Measures which may be used to ensure that appropriate
levels of generation reserve capacity are maintained should
be market-based and non-discriminatory and could include
measures such as contractual guarantees and arrangements,
capacity options or capacity obligations. These measures
could also be supplemented by other non-discriminatory ins-
truments such as capacity payments285.
It was against this backdrop that the French Energy Code, in
articles L.335-1 et seq., called for an obligation to be imposed on
suppliers to contribute to security of electricity supply. The goal
was to supplement existing measures with a market mechanism
targeting security of supply.
10.1.2 Regulation of Member States’ competence through the provisions of the Treaty and secondary legislation
Though the EU acquis does not prohibit public inter-
vention to ensure security of supply, Member States’
competence is regulated by the provisions of the Treaty
and by secondary legislation, notably the provisions of
the Third Energy Package and Directive 2005/89/EC.
10.1.2.1 Provisions of the Treaty
The provisions relating to the free movement of goods –
articles 34 and 35 of the TFEU – impact the design of
the French capacity mechanism insofar as, in European
Court of Justice case law, electricity is considered a
good286. These articles respectively prohibit restrictions
on imports and exports along with any quantitative res-
trictions and measures having equivalent effect.
These provisions have a direct link with the capa-
city mechanism’s provisions on the participation of
cross-border capacities to security of supply in France. As dis-
cussed in chapter 9 of this report, the issue was raised during
the consultation of 2011, when the decree was being drafted,
and the various problematic points and difficulties identified led
to the decision that the contribution of cross-border capacities
to security of supply in France would be implicitly accounted for
the implementation of the capacity mechanism. The European
Commission and the Agency for the Cooperation of Energy
Regulators have also noted the difficulties related to the explicit
cross-border participation in capacity mechanisms287.
Implicit participation of cross-border capacities to security of
supply in France already ensures a high degree of economic
efficiency since it reduces capacity needs and prevents overca-
pacity. Chapter 9 also outlines the key principles to allow explicit
cross-border participation to the French capacity market, and
therefore to security of supply in France, along with milestones
RTE has proposed in the rules to pave the way towards this expli-
cit cross-border participation.
The European Commission considers this step-by-step approach as a
possible solution in its Staff Working Document “Generation Adequacy
in the internal electricity market - guidance on public interventions”:
[I]t may be necessary, as an interim step, for Member States to
calculate the contribution of imports to meeting the genera-
tion adequacy standards288.
214
10.1.2.2 Provisions of secondary legislation regarding
the energy sector
The provisions included in the Third Energy Package and Direc-
tive 2005/89/EC define the competence of Member States in
assessing their national level of security of supply and taking
safeguard measures in case of emergency situations.
Along these lines, article 7 of Directive 2005/89/EC289 provides
that Member States must prepare reports to:
Describe the overall adequacy of the electricity sys-
tem to supply current and projected demands for
electricity, comprising:
a) Operational network security;
b) The projected balance of supply and demand for
the next five-year period;
c) The prospects for security of electricity supply for
the period between year five and 15 years from the
date of the report; and
d) The investment intentions, for the next five or
more calendar years, of transmission system opera-
tors and those of any other party of which they are
aware, as regards the provision of cross-border inter-
connection capacity.
The law of 10 February 2000 had already tasked RTE
with the publication of adequacy reports in France290,
well before such adequacy assessments became
mandatory in Europe. These reports, called Adequacy
Forecast Reports, are prepared under the control of
public authorities291. The decree of 20 September
2006292 specified the framework, scope and study horizons for
these reports, in compliance with the provisions of Directive
2005/89/EC.
Article 11 of the decree of 20 September 2006 provides for an
adequacy criterion to be applied in France, which is an average
3 hours annual loss of load expectation:
The Multi-year Adequacy Forecast Report required by Article
1 of the present decree […] takes into account the annual
loss of load expectation used in previous adequacy forecast
reports, i.e. an average annual loss of load expectation due to
imbalances between electricity supply and demand of three
hours293.
Safeguard measures implemented by Member States in emer-
gency situations shall be taken respectfully of other EU provi-
sions. Notably article 3 Directive 2009/72/EC provides that
measures introduced by Member States must be “clearly defi-
ned, transparent, non-discriminatory and verifiable”. These
conditions are also provided for in article 2 of decree 2012-
1405, which specifies that the capacity mechanism rules must
be transparent and non-discriminatory.
The key provisions of the rules proposed by RTE were deve-
loped in chapters 3 to 6 of this report and have been designed
to implement a mechanism that is clearly defined and unders-
tandable by all market stakeholders.
The non-discrimination requirement relates not only to the dis-
tinction between French and cross-border capacities but also to
the application of non-discriminatory provisions to all capacity
mechanism participants. The participation of cross-border capa-
cities has been addressed both in the previous section of this
chapter and in chapter 9 of this report. As regards the second
point, all provisions proposed by RTE in the capacity mechanism
rules are respectful of the principle of non-discrimination, as it
was demonstrated in chapters 3 to 7 of this report. Two signi-
ficant examples are the non-discrimination between demand-
response, renewables and conventional generation capacities
289Directive 2005/89/EC of 18 January 2006 concerning measures to safeguard security of electricity supply and infrastructure investment.
290Article L.141-1 of the Energy Code.
291Several of these provisions were also included in the Energy Code, following amendments and repeals to the law of 10 February 2000, notably the NOME Act.
292Decree 2006-1170 of 20 September 2006 relating to multi-year adequacy forecast reports.
293Decree of 20 September 2006.
RTE considers that implicit participation of cross-border capacities already fairly recognises their contribution to security of supply in France. In a first step, it is thus a way to include the partici-pation of cross-border exchanges to security of supply in the French capacity market provisions, in compliance with the European Commission’s recent recommendations.
In order to allow the implementation of the target solution – explicit participation of cross-border capacities – a second step is required. To that extent, the proposed capacity mechanism rules provide for the organisation of a public consulta-tion in order to submit propositions regarding explicit participation of cross-border capacities in the capacity mechanism ten months after the publication of the rules.
The provisions of Directive 2005/89/EC concern-ing adequacy assessments are taken into account by RTE in its Adequacy Forecast Reports, which examine the electricity supply and demand bal-ance outlook for France over the medium and long terms.
215
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
whether this measure constitutes an aid, and if so, if it is compa-
tible with the internal market, given its exclusive jurisdiction over
competition matters.
The framework for the energy sector is currently changing since
the European Commission is revising its guidelines on environ-
mental State aids – the guidelines that serve as an analytical
framework for assessing whether State aids are compatible with
the internal market – and organised a public consultation on the
issue between 18 December 2013 and 14 February 2014. The
new draft guidelines include, for the first time, a section devoted
to energy State aids296.
The draft guidelines notably include a list of conditions under
which an exemption can be granted if a State adopts a capacity
mechanism that qualifies as State aid, i.e. if the five conditions
outlined above are met.
The European Commission has indicated that the final draft of
the guidelines on environmental and energy State aids should
be adopted in the first half of 2014.
10.1.3.2 Public service obligations provided
for in the Third Energy Package
The provisions of Directive 2009/72/EC authorise
Member States to impose public service obligations
on private undertakings in the energy sector.
Member States may impose on undertakings
operating in the electricity sector, in the gene-
ral economic interest, public service obligations
which may relate to security, including security
of supply, regularity, quality and price of supplies
and environmental protection, including energy
efficiency, energy from renewable sources and
climate protection297.
Supplementing the conditions laid down in article 3
of Directive 2009/72/EC, European Court of Justice
case law has specified the framework for evaluating
the compatibility of public service obligations with
the EU acquis, particularly in its Federutility298 and
Enel Produzione299 decisions, and has affirmed that
the legality of measures undertaken by Member
States should be evaluated based on necessity and
proportionality tests.
294[EC, 2013]
295See e.g., the definition adopted by the ECJ in Case C-280/00 Altmark Trans GmBH [2003] ECR I-7747 (ECJ, 24 July 2003).
296In their previous version, the guidelines only addressed the issue of State aid in the environmental sector.
297Article 3, paragraph 2 of Directive 2009/72/EC.
298Case C-265/08 Federutility and Others v Autorità per l’energia elettrica e il gas [2010] ECR I-3377 (ECJ Grand Chamber, 20 April 2010.
299Case C-242/10 ENEL Produzione SpA v Autorità per l’energia e il gas [2011] ECR I-0000 (ECJ, 21 December 2011).
in the certification process described in chapter 5 and the non-
discrimination between suppliers in the parameters defined
to calculate their capacity obligation, which are described in
chapter 4.
The consultation process on the capacity mechanism design
was transparent, as described in chapter 3. Stakeholders (incl.
the transmission system operator) are subject to transparency
obligations in the capacity mechanism and those provisions
have been described in chapter 7.
10.1.3 Legal forms of public intervention
Public interventions in the electricity market can take different
forms, the two most common of which are State aid and public
service obligations provided for in the Third Energy Package, as
the European Commission notes:
Public intervention at regional, national or local level can take
different forms. Examples include state aid to certain sectors
or companies in the form of grants or exemptions from taxes
and charges, the imposition of public service obligations, and
regulation through general measures294.
10.1.3.1 Environmental and energy State aid
State aids in the energy sector are governed by the general pro-
visions of article 107 of the TFEU relative to State aids and their
interpretation by the European Court of Justice. Paragraph 1 of
article 107 of the TFEU provides that forms of aid granted by
Member States that threaten to distort competition are incom-
patible with the internal market. Paragraphs 2 and 3 of that
article define the forms of aids that can be considered compa-
tible with the internal market.
State aid exists when all of the following five conditions are met:
there must be (i) a transfer of State resources (ii) conferring an
advantage (iii) on certain undertakings (iv) which distorts com-
petition and (v) which affects trade between Member States295.
When a State considers that these conditions are met, it must
notify the European Commission of the measure, in accordance
with article 108 of the TFEU, so the Commission can evaluate
RTE considers that all legal and regulatory pro-visions, and the regulatory framework govern-ing the implementation of the capacity mecha-nism, meet the conditions laid down in Directive 2009/72/EC.
216
France and Europe are changing significantly, and this could
increase the occurrence of market failures. The power system
will have to do more to help meet the ambitious energy transi-
tion objectives set by the European Union; it must therefore be
adapted to accommodate growing and massive penetration of
renewables. This makes it all the more important to have flexible
capacities, be they generation or demand-response resources,
to protect the electricity supply and demand balance.
Additional information must also be provided in response to the
specific framework proposed in the “Generation Adequacy in the
internal electricity market - guidance on public interventions”
Staff Working Document. According to European Commission
recommendations, the necessity of a capacity mechanism is
determined by whether a risk to security of supply has been
identified on the basis of generation adequacy assessments
that are “objective, facts based and comprehensive”301 and whe-
ther this risk persists after other measures positively impacting
the supply-demand balance have been introduced.
10.2.1.1 Assessment of generation adequacy in France
The time horizons considered for the capacity mechanism
are such that the methodology and conclusions of the sec-
tion of RTE’s Adequacy Forecast Reports devoted to the five-
year medium term must be considered. A description of RTE’s
methodology can be found in the 2012 Adequacy Forecast
Report or the 2013 Adequacy Forecast Report update.
10.2.1.1.1 Transparency and stakeholder consultation
The Adequacy Forecast Report is based on hypotheses about
future trends in electricity supply and demand that RTE
10.2 Compliance with the principles of necessity and proportionality
It is not RTE’s role to determine the legal qualification of the capacity mechanism. It could be noted, however, that the design adopted for the capacity mechanism can be assessed with regard to the framework for public service obli-gations. The obligation is imposed upon suppliers to help meet the security of supply target set by public authorities by having sufficient capacity to ensure electricity supply to their final customers. Generators and demand-response operators are required to participate in the mechanism and ensure that it functions properly by certifying all of their generation capacities. The commitments undertaken during the certification process to make their capacities avail-able ensure that they will effectively contribute to security of supply during peak demand periods.
Regardless of how the capacity mechanism is legally qualified, the legality of the public intervention is notably eval-uated based on necessity and proportionality tests. These principles therefore need to be respected when imple-menting the capacity mechanism.
Compliance with the principles of necessity and proportionality
should be assessed in the light of the adequacy between the
given public intervention and the objective of public interest it
pursues. In this instance, ensuring security of supply is the aim of
public interest pursued by French public authorities300.
It is important to emphasise that the European Commission
recently expanded its analytical framework for examining public
intervention to ensure security of supply through the Staff Wor-
king Document “Generation Adequacy in the internal electricity
market - guidance on public interventions” accompanying its
Communication “Delivering the internal electricity market and
making the most of public intervention”. This Staff Working
Document features a checklist regarding (1) the
assessment of needs, (2) the adoption of structu-
ral measures to improve the functioning of energy
markets, and (3) design choices compatible with the
internal market.
The facts presented by RTE regarding the necessity
and proportionality of the mechanism thus refer pri-
marily to the framework proposed by the European
Commission in November 2013.
10.2.1 Principle of necessity
Chapter 1 of this report discusses various points
that justify public intervention to ensure security
of supply. Indeed, empirical observation points to a
number of imperfections in current energy markets.
In addition, the physical needs of power systems in
300Because the principle of subsidiarity applies, national authorities have, under EU case-law, discretionary power to define what they consider to be services of general economic interest and “to provide, to commission and to fund such services”, “in compliance with the Treaties”, as specified in article 14 of the TFEU. It is thus within the remit of Member States, under the aegis of national judges, to determine what is in the general interest, in compliance with the qualifications specified in EU law.
301[EC, 2013a]
302[EC, 2013a]
217
COMPLIANCEWITHEUROPEANPROVISIONSANDPRINCIPLES / 10
European Commission recommendations on the introduction of capacity mechanisms302
Continuation l
JUSTIFICATION OF INTERVENTION
Assessment of generation gap
(1) Is the capacity gap clearly identifi ed and does this distin-
guish between need for fl exible capacity at all times of year
and requirements at seasonal peaks? Has a clearly justifi ed
value of lost load been used to estimate the cost of supply
interruptions?
(2) Has the assessment appropriately included the expected
impact of EU energy and climate policies on electricity infra-
structure, supply and demand?
(3) Does the security of supply and generation adequacy
assessment take the internal electricity market into
account; is it consistent with the ENTSO-E methodology
and the existing and forecasted interconnector capacity?
(4) Does the assessment explain interactions with assess-
ments in neighbouring Member States and has it been
coordinated with them?
(5) Does the assessment include reliable data on wind and
solar, including in neighbouring systems, and analyse the
amount as well as the quality of generation capacity needed
to back up those variable sources of generation in the system?
(6) Is the potential for demand side management and a realistic
time horizon for it to materialize integrated into the analysis?
(7) Does the assessment base the assessment of gene-
ration plant retirements on projected economic conditions,
electricity market outcomes and the operating costs of that
generation plant?
(8) Has the assessment been consulted on widely with all
stakeholders, including system users?
Causes of generation adequacy concerns
(9) Has retail price regulation (with the exception of social
prices for vulnerable customers) been removed?
(10) Have wholesale price regulation and bidding restric-
tions been removed?
(11) Have renewable support mechanisms been reviewed in
line with the Guidance on renewable support before inter-
vening on generation adequacy grounds.
(12) Has the impact of existing support schemes for fossil
and nuclear generation on incentives for investments in
additional generation capacity or maintenance/refurbish-
ment of existing generation capacity been assessed?
(13) Are eff ective intraday, balancing and ancillary service’s
markets put in place and are any remaining obstacles, in
those markets removed? Have any implicit price caps from
the operation of balancing markets been removed?
(14) Have structural solutions been undertaken to address
problems of market concentration?
Options other than support for capacity
(15) Have the necessary steps been taken to unlock the
potential of demand side response, in particular has Article
15(8) of Directive 2012/27/EU on Energy Effi ciency been
implemented and do smart meter roll out plans include the
full benefi t of demand side participation in terms of genera-
tion adequacy?
(16) Have the benefi ts of expanded interconnection capac-
ity been expanded, in particular towards neighbouring
countries with surplus electricity generation or a comple-
mentary energy mix been fully taken into account.
(17) Have the impacts of the intervention on the achieve-
ment of adopted climate and energy targets been assessed
holistically, and is lock-in of high carbon generation capacity
and stranded investments avoided?
218
Continuation j
CHOICE OF MECHANISM
Choice and design of intervention
(1) Has the eff ectiveness of a strategic reserve been examined?
(2) Has the potential for a credibly one-off tendering proce-
dure to address the identifi ed capacity gap been examined?
(3) Does the chosen mechanism ensure that identifi ed ade-
quacy gap will be fi lled while avoiding risks of overcompen-
sation (unlikely with payments payments)?
Recommendations to avoid distortion of internal
electricity market
(4) Is the chosen mechanism open to demand side participation?
(5) Is the mechanism to ensure generation adequacy consist-
ent with the long term decarbonisation of the power sector?
(6) Is the chosen mechanism (other than a tendering
scheme) open to existing and new generation?
(7) Are conditions for participation in the mechanism based
on technical performance and not technology type?
(8) Does the chosen mechanism deliver a price of zero
when there is already suffi cient capacity available?
(9) Has a framework for the phase out of the mechanism in
line with a roadmap for addressing underlying market and
regulatory failures been developed
(10) Does the lead time for a capacity mechanism correspond to
the time needed to realise new investments, that is 2-4 years?
(11) Is the mechanism open to all capacity which can
eff ectively contribute to meeting the required generation
adequacy standard, including from other Member States?
Insofar as imports are accounted only on an implicit basis, is
a mechanism established to calculate this benefi t and allo-
cate funds to this value for the development of additional
interconnection capacity?
(12) Is it ensured that there are no export charges or proce-
dures to reserve electricity for the domestic market?
(13) Have all barriers to the equal treatment of national and
cross border contracts been removed?
(14) Are there no price caps or bidding restrictions as a
result of the chosen mechanisms?
(15) Is it ensured that the operation of the chosen mecha-
nism does not lead to ineffi cient production by operators?
(16) Is it ensured that the capacity mechanism does not
adversely aff ect the operation of market coupling or cross
border intraday trading?
(17) Does the chosen mechanism allocate the costs to con-
sumers on a non-discriminatory basis, taking into account
their consumption patterns and without reductions for par-
ticular customer segments?
calculates as realistically as possible. RTE consults power sys-
tem stakeholders on the hypotheses used in the Adequacy
Forecast Report.
In line with RTE’s commitment to transparency,
the hypotheses adopted in the 2012 Adequacy
Forecast Report were submitted to a collegiate
consultation process with the “Network Outlook
Committee” (Commission Perspectives du Réseau)
of the Transmission System Users’ Committee
(Comité des utilisateurs du Réseau de Transport de
l’Electricité – CURTE)303.
The assumptions incorporated into models of the Western Euro-
pean power system are based on information provided to RTE
by diff erent power system actors during bilateral exchanges304;
on work done by ENTSO-E; on information made public by
stakeholders in the European power market (generators, sup-
pliers, system operators, electricity exchanges); and on research
conducted by various energy market research consultancies or
government agencies. RTE also met with diff erent stakeholders
in the European power system (transmission system operators,
regulators, etc.), through working groups (ENTSO-E) and bilate-
ral meetings, to exchange ideas about changes in the methodo-
logies used in its Adequacy Forecast Reports.
303[RTE, 2012a]
304RTE guarantees the confi dentiality of all information of a commercially sensitive nature to which it is given access.
219
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
10.2.1.1.2 Demand forecasts
Demand forecasts are constructed in two phases: 1) forecasts
established for annual energy demand for each year of the study
horizon, and (2) forecasts established for power demand on an
hourly basis. Each of these phases includes a retrospective analy-
sis of past years, making adjustments to years used as reference
periods for simulations, as well as a forward-looking study.
Four demand scenarios were created for the medium term to
represent the spectrum of possible outcomes: “Baseline”, “High”,
“Low” and “Stronger DSM”. The main assumptions differentiating
these scenarios are outlined below.
The “Baseline” scenario integrates the central assumptions
for each driver of demand.
The “High” scenario incorporates all assumptions implying an
increase in demand. […]
The “Stronger DSM” scenario assumes the same economic envi-
ronment as the “Baseline” scenario but calls for an acceleration
of demand-side energy management efforts in general. […]
The “Low” scenario incorporates assumptions leading to
a decrease in demand, including a relatively unfavourable
economic situation and a weak demographic
variant305.
The key factors differentiating the scenarios are shown in the
table below.
Economic growth also has a significant impact on electricity
demand in other European countries. To be able to build projec-
tions of European demand while maintaining a consistent fra-
mework, GDP assumptions have also been established for these
countries using a similar approach as the French one.
All scenarios assume that energy efficiency will steadily improme,
helping to keep electricity demand growth in check, notably
through the diffusion of technological progress and the imple-
mentation of laws or regulations favouring the development of
energy efficiency, including Directive 2009/125/EC of 21 Octo-
ber 2009 creating a framework for defining eco-design require-
ments applicable to energy-related products.
The Adequacy Forecast Report is prepared using demand data
series for France as well as for European countries (at a Western
European scale).
305[RTE, 2012a]RTE’s Adequacy Forecast Reports fully comply
with the European Commission’s recommenda-tions regarding transparency and stakeholder consultation.
Table 6 – Main assumptions used in demand scenarios
Demand scenario “Baseline” “High” “Stronger DSM” “Low”
Key assumptions Central Higher overall demand
Increased energy efficiency
Lower overall demand
GDP Central High Central Low
Energy efficiency Central Lesser effect Greater effect Central
Demographic Central Haute Central Low
Electricity price CentralFavourable to rollout of new electricity-based
solutionsCentral
Unfavourable to rollout of new electricity-based
solutions
The demand forecasts produced by RTE for the Adequacy Forecast Report comply with the Euro-pean Commission’s recommendations regarding their consideration of the impact of EU energy and climate policy, particularly energy efficiency tar-gets. A steady improvement in energy efficiency is highlighted in all scenarios.
220
10.2.1.1.3 Supply forecasts
Medium-term supply trends are presented by technology in the
Adequacy Forecast Report: (1) centralised fossil-fired capacity, (2)
nuclear power, (3) embedded thermal generation, (4) renewable
energy sources and (5) generation capacity outside France.
For centralised fossil-fired generation, and particularly combined-
cycle gas plants, the Adequacy Forecast Report takes into account
official announcements by generators, notably the mothballing of
one unit (between 2014 and 2016) and the shutdown of several
others in the summer of 2013, with these same units taken offline
every summer in all the years considered in the report through
2018. It is assumed that no new capacity will be commissioned
outside France over the period considered in the report.
As regards nuclear power in France, it is assumed that the two
reactors Fessenheim will be out of service at the end of 2016,
reducing installed capacity by 1,760 MW, per the announce-
ments made by public authorities.
Onshore wind capacity development should resume in 2014,
thanks to several policy signals306, and expansion in the coming
years is expected to at least match that observed in the past two
years, implying the addition of around 800 MW a year, which
would take wind power capacity to more than 12 GW in 2018.
The Adequacy Forecast Report assumes that photovoltaic capa-
city will increase by 800 MW a year, to factor in uncertainty about
the industry’s development (particularly the effects of the mea-
sures introduced by the French government in 2013 to encou-
rage its expansion). Based on this growth estimate, photovoltaic
capacity should reach 8.3 GW in 2018.
As regards demand response, it is assumed in the Adequacy
Forecast Report that capacity will be flat over the medium term,
stabilising at a level slightly above that observed
today, with a decrease in tariff-based demand res-
ponse being offset by the increased participation
of demand response in market mechanisms. The
forecast could be revised upward depending on the
effects the framework laid down in law 2013-312
(Brottes Act) on preparing for the transition to a low-
energy system will have on the demand response
potential, and on the reintroduction of demand res-
ponse tariffs announced by the Government.
Regarding generation capacity outside France,
assumptions for all 11 countries modelled (Spain,
Portugal, United Kingdom, Ireland, Belgium, Luxembourg,
Netherlands, Germany, Switzerland, Austria and Italy) are taken
into account.
The development of the electricity transmission system is also
factored into the assumptions307.
10.2.1.1.4 Probabilistic approach
Future supply and demand forecasts thus produced are com-
pared by simulating the operations of the Western European
power market on an hourly basis over a full year.
For both Europe and France, around a hundred demand
series have been produced based on temperature datasets
produced in cooperation with Météo France for Europe, to
assess the impact of cold spells and heat waves on the Euro-
pean power system.
[…]
With regard to generation capacity, the methodology applied
to foreign countries for the medium term is similar to that
used for France.
[…]
Generally speaking, to ensure the balance between supply
and demand, generation facilities are used in ascending order
of their marginal cost of production (the merit order), until
demand is met. Since the late 1990s, when instruments were
306Examples: Adoption of Regional Climate, Air and Energy Plans, changes in the law to facilitate wind turbine installation.
307Over the medium term, two noteworthy changes will affect interconnections to France, both of which are scheduled for 2015: the strengthening of exchange capacity with Spain […] and the strengthening of the French network in the Alps.
The supply forecasts produced by RTE within the framework of the Adequacy Forecast Report comply with the European Commission’s recom-mendations on taking into account EU energy and climate policy, particularly the greenhouse gas emissions reduction target, by factoring in the effects the EU directives designed to help achieve this target will have over the period under review and the renewable energy development target.
Regarding renewable energy development, the trend still points to a more robust expansion of these resources than other technologies over the period under review. Demand management is also taken into account through demand response capacity, including within the framework of mar-ket mechanisms.
Regarding the closure of generation units, RTE’s assumptions take into account the shutdowns officially announced by generators, which have the most up-to-date information about their capacities and the economic outlook for them. The internal market is factored into supply forecasts by including capacity assumptions for 11 Western European countries.
221
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
developed to allow comparisons of supply between different
countries, this merit order has been seen from a European
standpoint, meaning that at any given time, the units with
the lowest production costs in Europe can be called upon
to meet demand expressed in Europe as a whole. The merit
order is respected provided that exchange volumes do not
exceed transmission capacity between countries or regions
within a same country308.
The simulations take into account the main contingencies that
can threaten security of supply, including weather conditions
and especially outdoor temperatures, unscheduled unavailabi-
lity of thermal generation capacities, water resources and wind
and photovoltaic power production. The spatial and temporal
correlations of a given natural hazard are taken into account at
the European scale.
A set of temporal series, loads on the demand side and avai-
lable capacity of units generating supply reflecting various
possible outcomes are created for each of the phenomena
considered. These series are then combined in sufficient
number (1,000 for each scenario) to give statistically signifi-
cant results in shortfall (risk of demand not being met due to
a lack of generation) and annual energy balances (output of
different units and exchanges with neighbouring systems)309.
The supply-demand balance is assessed by comparing each
demand scenario with the supply scenarios. Moreover, as
required by the decree of 20 September 2006, the “Baseline”
demand scenario is compared to supply forecasts with and with-
out exchanges to identify the contribution interconnections
make to covering the shortfall risk in France.
In the zero exchange balance analysis required by the decree,
the shortfall criterion is exceeded under the “Baseline” scenario
over the duration of the period considered (including today),
illustrating how crucial electricity imports are to security of supply
in France. The capacity that would be needed to meet the crite-
rion without interconnections exceeds 6 GW starting in 2016310.
10.2.1.1.5 Compatibility with ENTSO-E’s methodology
RTE’s Adequacy Forecast Report is compatible with ENTSO-E’s
“Scenario Outlook and Adequacy Forecast”311. However, the
results vary due to differences between assumptions applied to
countries other than France and the fact that the probabilistic
simulations used in the Adequacy Forecast Report are more ela-
borate that the deterministic calculations in the “Scenario Out-
look and Adequacy Forecast”.
ENTSO-E has publicly announced that it plans to propose
changes to the methodology used in the “Scenario Outlook
and Adequacy Forecast” and participate in their implementa-
tion, notably to generate studies at a European scale based on
the same probabilistic approach as the one RTE uses in the
Adequacy Forecast Reports for France.
ENTSO-E is already committed to examining possible changes
with particular regard to treatment of RES-E resources. These
range from small changes to existing methodologies to fully
implementing probabilistic adequacy assessments in the
short and long term. However any changes need to consider
the conflicting objectives of depth of analysis with the asso-
ciated need for increasing requirements against the timely
production of useful outlook reports.
[…]
Nevertheless ENTSO-E and its member TSOs are actively
developing the tools and techniques to address these issues
over time.
[…]
It would be highly desirable if stakeholders (EC,
ACER, market participants) and ENTSO-E could
further discuss and agree on a high-level vision
on the expected scope and content of the ade-
quacy reports. Thereafter appropriate and neces-
sary adjustments in methodology and structure
of the report could be made312.
308[RTE, 2012a]
309[RTE, 2012a]
310[RTE, 2012a]
311[ENTSO-E, 2013]
312[ENTSO-E, 2013]
infrastructure; recommendations on taking the internal market into account are complied with since the simulations are carried out for the West-ern European power system. Moreover, the com-parison of simulation results with and without exchanges highlights the role interconnections play in ensuring security of supply in France. As regards the inclusion of variable sources, the simulations respect the spatial and temporal cor-relations of individual contingencies (including for wind power) at the European level.
The probabilistic approach used by RTE to assess the supply-demand balance complies with the European Commission’s recommendations on taking into account European energy and cli-mate policy (20-20-20 objectives) and upholding the provisions of Regulation 347/2013 by factor-ing in the development of new interconnection
222
10.2.1.1.6 Conclusions regarding generation adequacy
assessments
The European Commission’s first consideration in evaluating the
need for public intervention to safeguard security of supply is
that a facts-based, objective and comprehensive assessment
of adequacy and security of supply has been conducted. RTE’s
Adequacy Forecast Report is used to assess the electricity sup-
ply and demand balance in France, and the methodology used
to carry out this assessment complies with the European Com-
mission’s recommendations:
> Demand forecasts take into account European energy and cli-
mate policies (particularly with regard to demand-response);
> Supply forecasts take the internal market into account
through the integration of hypotheses regarding the genera-
tion fleet of other European countries;
> Simulations are carried out using a probabilistic approach with
a careful modelling of contingencies and their corre-
lations (particularly for variable sources);
> All requirements in terms of transparency and
stakeholder consultation are met.
The results presented in the most recent update of
the Adequacy Forecast Report (2013), outlined in
chapter 1 of this report, show that safety margins
vis-à-vis the security of supply criterion will gradually
shrink and then disappear in 2017. This suggests
that security of supply in France will have to be care-
fully monitored and will be at risk in 2017, particu-
larly if a cold spell occurs.
10.2.1.2 Other measures to improve the supply-
demand balance
On the basis of this comprehensive assessment, the Euro-
pean Commission recommends a series of measures that can
improve the supply-demand balance and help resolve adequacy
gap situations.
Questions about retail price regulation313, renewable support
mechanisms and support schemes for fossil and nuclear gene-
ration do not pertain to areas in which RTE is directly involved.
These issues are therefore not addressed in this report.
Lastly, the issue of whether the capacity mechanism will lock in
high-carbon generation capacity, which would be counter to EU
energy and climate objectives, is addressed in chapter 2 of this
report, where the main architectural choices proposed for the
capacity mechanism are outlined.
10.2.1.2.1 Measures to improve the functioning of the
wholesale market and intraday, balancing and system
services markets
10.2.1.2.1.1 Wholesale market
The European Commission has voiced concerns that energy
price caps could hinder the formation of prices that send ade-
quate signals to market participants. In the North Western
Europe day-ahead market coupling, prices transmitted through
bids by market participants in the French market have ranged
between -€500/MWh and €3,000/MWh since NWE price cou-
pling was launched on 4 February 2014. Price caps were har-
monised across the region in order to reduce constraints in the
market. As the European Commission notes in its “Generation
Adequacy in the internal electricity market” guidelines, these
limits are among the highest in Europe.
It should also be noted that these price limits are not defined
through laws or regulations and can thus be periodically revised.
Wholesale market participants can trade on the EPEX SPOT mar-
ket but also over the counter or through a broker. There is no
regulated tariff governing prices on the wholesale market. The
ARENH mechanism, a specific regulation governing the ability
for alternative suppliers to source electricity directly from EDF
at a regulated price, was introduced to open the French supply
market to competition under the control of the European Com-
mission. Since 1 July 2011, in accordance with the provisions of
the NOME Act, suppliers have been able to exercise their right
to regulated access to historical nuclear electricity (ARENH) by
313The introduction of the market mechanisms presented in chapters 1 and 10 of this report, e.g. the NEBEF mechanism, allows demand response to participate in electricity markets over all time horizons and thus help make the load curve more flexible, even when regulated tariffs are applied. Moreover, the French Government recently committed to reintroducing demand response tariffs to create incentives to reduce consumption.
As part of the work being done by the Electricity Coordination Group at the European scale and by the Pentalateral Forum for Western Europe, Mem-ber States and the European Commission have asked transmission system operators to adapt the methodologies used by ENTSO-E to enhance the quality of its European reports. ENTSO-E has also created a workgroup focusing on adapting the methodologies used in the Scenario Outlook and Adequacy Forecast, one priority of which will be to propose a harmonised probabilistic methodology for adequacy assessments.
With this in mind, RTE considers that any discrep-ancies between the Adequacy Forecast Report and ENTSO-E’s Scenario Outlook and Adequacy Forecast will narrow as ENTSO-E’s methodologies are updated, and that current differences are not a hindrance. Should hypotheses continue to differ over the long term, it will be for reasons such as time gaps between studies.
223
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
buying electricity directly from EDF at a regulated price and in
quantities defined by the regulator. This measure was intended
to stimulate competition in the French wholesale market by
allowing new entrants to make competitive offers.
10.2.1.2.1.2 Intraday market
Price limits are higher on the intraday market than on the day-
ahead market, ranging between -€9,999/MWh and €9,999/MWh.
Mechanisms are already in place to enable the integration of
the French intraday market at the European level. For instance,
on 26 June 2013, intraday market mechanisms between France,
Germany, Austria and Switzerland were launched in order to allow
market participants in these countries, EPEX SPOT members, to
engage in intraday cross-border trades.
This mechanism will be an essential building block in fostering
migration to the intraday solution called for in the European tar-
get model.
10.2.1.2.1.3 Balancing and ancillary services markets
Bids submitted to the balancing mechanism are not subject to
price limits. Since the mechanism was created in 2003, it has been
possible for demand response bids to participate in the same way
as bids from generators. Cross-border bids have been possible
with Switzerland since 2003 and with Germany since 2005.
RTE has also participated in the creation of cross-border balan-
cing mechanisms to allow cross-border trading, including after
the intraday cut-off. For instance, the BALIT mechanism (BALan-
cing Inter TSO) allows transmission system operators RTE and
National Grid to exchange balancing energy (beyond requi-
red margins). BALIT enhances competition on the balancing
mechanism by bringing new market participants into national
mechanisms, thereby boosting economic efficiency. The
mechanism is a precursor for the development of cross-border
balancing energy trading at the European level, in keeping with
the provisions of the Electricity Balancing Network Code. RTE is
also taking part in the TERRE project in partnership with National
Grid, REN and Terna314.
Where frequency containment reserves and frequency resto-
ration reserves (ancillary services)are concerned, article L. 321-
11 of the Energy Code charges RTE with “ensuring that ancillary
services for the operation of the grid are available and effecti-
vely provided” and with setting terms of participation and rules
for calculating the remuneration of system services, subject to
approval by CRE.
To this end, RTE conducted a consultation through
a Transmission System Users’ Committee (CURTE)
workgroup in 2013 to consider the design of
an organised secondary market for Frequency
Containment Reserve and automated Frequency
Restoration Reserve and propose rules to govern
the participation of demand response in system
services315.
The idea of an organised secondary market to
help optimise the power system emerged from
the consultation with market stakeholders. Par-
ticipation in this market should be optional and
standard products would have to be defined to
facilitate trading initially. It was on the basis of this
consultation that RTE introduced technical and
legal prerequisites into the system service rules316 to make the
creation of a secondary Frequency Containment Reserve and
automated Frequency Restoration Reserve market possible.
All of RTE’s proposals were approved by CRE in its deliberation
of 28 November 2013 approving the system service rules. The
new rules have superseded system service contracts since
1 January 2014. RTE will specify procedures for notifying reserve
exchanges and financial guarantees by 1 January 2015.
10.2.1.2.2 Participation of demand-response
in electricity markets
The sections below elaborate on the summary data presented in
chapter 1 of this report about the various mechanisms in place
or being developed to allow the demand side to participate in
the French electricity market over different time horizons.
314The TERRE project is designed to allow the trading of replacement reserves between France, Italy, Portugal and Great Britain and was selected as a pilot project for the implementation of the Electricity Balancing Network Code.
315See section 10.2.1.2.2.1.
316In particular, the role of the “reserve manager” was introduced and a system was created for notifying exchanges of reserves along with a related financial guarantee system.
Changes are being effected in many areas to add new functionalities to markets, only one of which is the creation of an organised secondary market for ancillary services.
Implementation of the capacity mechanism will not prevent improvements from being made to the existing market architecture.
France continues to be increase its integration into the European electricity market and is playing a pioneering role through the initiatives in which It is actively involved (NWE market coupling, flow-based capacity allocation in the CWE region, inte-gration of French, Swiss, German and Austrian intraday markets, BALIT mechanism, etc.)
224
10.2.1.2.2.1 Participation of demand-response in
the balancing mechanism, reserves procurement
and ancillary services
The balancing mechanism gives RTE real-time access to upward
and downward balancing reserves so it can ensure equilibrium
in the power system.
Since it was created in 2003, the balancing mechanism has
allowed the activation of demand response by industrial users
connected to the public transmission system. In 2007, an expe-
riment was launched to enable the participation of distributed
demand response as well.
The experiment RTE is conducting in Brittany will give market partici-
pants additional opportunities to participate in the balancing mecha-
nism and contribute to the supply-demand balance. It makes it pos-
sible to offer local generation connected to the public distribution grid
or demand response that can be activated on the balancing mecha-
nism, subject to minimum aggregate power of 1 MW.
Article L.321-11 of the Energy Code authorises RTE to enter into
contracts with generators and suppliers for replacement reserves
that can be activated on the balancing mechanism. These
contracts are established through “competitive, non-discriminatory
and transparent procedures”. Since 2008, it has been possible to
select demand response for rapid replacement reserve contracts.
The market share of demand response has been growing steadily
ever since, thanks to the product segmentation proposed by RTE.
Lastly, specific mechanisms have been introduced to allow
demand response to participate in short-term market
mechanisms.
In accordance with article 1 of the order of 10 December 2012
applying article L. 321-19 of the Energy Code, RTE “enters every
year into one-year interruptibility contracts with consumption
sites connected to the transmission system with ins-
tant interruptibility profiles […]”.
Article 7 of the NOME law calls for the organisation of
“a call for tenders (…) to secure additional demand-
response capacity for a period of three years”. In
other words, it has been possible for demand res-
ponse capacities to participate in specific tenders
since 2011. The tender organised in 2012 allowed at
least 400 MW of capacity that can be activated until
September 2013, along with at least 200 MW that
can be activated until 2015.
The consultation process organised in 2013317 led RTE to pro-
pose an experimental phase during which extraction sites
will be allowed to provide ancillary services (FCR and aFRR) in
limited quantities starting on 1 July 2014. Extraction sites’ abi-
lity to provide frequency containment or restoration reserves
will be rewarded indirectly: operators can sell these reserves to
obligated generators, setting their own price. Transactions will
be conducted over the counter and then, if applicable, through
an organised secondary market. The methods used to certify
and verify the performances of these capacities will be defined
in the first half of 2014, based on a consultation with market
stakeholders.
The CRE deliberation of 28 November 2013 approving the ancil-
lary services rules calls for RTE to submit to CRE draft ancillary
services rules for allowing the participation of extraction sites,
based on the outcome of the experiment conducted in 2014, by
1 September 2015 at the latest.
10.2.1.2.2.2 Explicit participation of demand-response
in the energy market
Demand-response can be a competitive alternative to electricity
generation. It thus makes economic sense to adopt provisions
that allow demand response to participate in electricity mar-
kets, i.e. to be activated (on the day-ahead or intraday market)
in the same way as available generation capacity to ensure that
forecast demand is covered (and not just to offset residential
imbalances).
Demand-response can be rewarded “implicitly” via private opti-
misation within a supply portfolio, for instance through dyna-
mic pricing318, or “explicitly”, as provided for in the Brottes law.
Thanks to the NEBEF mechanism introduced on January, 1st
2014, demand-side operators can capitalise on the flexibility of
consumption sites to fully leverage short-term optimisation pos-
sibilities, since a site that reduces load benefits either directly or
through a demand-side operator from any differential between
market and supply prices over the period. In sum, it is a tool for
enhancing the flexibility of the load curve including when sites
are on regulated tariffs or have entered into fixed-price supply
contracts through the market.
The NEBEF experimental rules notably specify the conditions
and terms under which a demand-side operator can sell a block
of energy resulting from explicit load reduction on electricity
markets, and how the block must be perfectly fungible with
other energy blocks traded on markets.
317See section 10.2.1.2.1.3.
318For instance peak/off-peak hours (allowing water heaters to be switched on at off-peak times). This implicit valuation of the storage potential is emphasised by the European Commission in the Staff Working Document, “Incorporating demand side flexibility, in particular demand response, in electricity markets“.
225
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
The rules are designed to create a level playing field for dif-
ferent stakeholders in the demand response market, suppliers,
demand-side operators and consumers. With this in mind, the
proposed design is based on:
> A new regulation framework, based on competitive assess-
ment319, especially regarding the financial relations between
demand-side operators and suppliers320;
> The nomination of a third party (RTE) as the “independent
third party” and intermediary between suppliers and demand-
side operators, charged with protecting the confidentiality of
data transferred, handling the certification process and the
control of data used and of the physical reality of the demand-
response activated.
10.2.1.2.3 Development of interconnections
The points discussed below are intended to complement chap-
ter 1 of this report, which notably highlighted the fact that five
of the projects RTE is conducting with European partners have
been identified as Projects of Common Interest as defined in
Regulation 347/2013321, and briefly describe the cross-border
projects included in RTE’sten-year plan of 2012.
RTE and its partners are planning to develop new intercon-
nection capacity with the British Isles, Italy, Spain, Belgium,
Luxembourg and Germany, which together could add 10 GW
of exchange capacity between France and partner countries by
2025. RTE estimates that it will invest some 1.5 billion euros a
year in these projects over the next ten years322.
RTE’s ten-year plan presents a number of intercon-
nection projects:
> France/England: The IFA 2 project under way
involves a 1,000 MW, approximately 250 km link
that could be operational before 2020. It will
connect the Normandy coast with southern
England at the Isle of Wight. The “France-Alder-
ney-Britain” (FAB) project, intended to harness
the tidal power potential off the coast of Auri-
gny, includes the study of a new interconnection
between France and the United Kingdom with
a capacity of between 1,000 MW and 1,400 MW
that could be in place in 2022.
> France/Ireland: RTE and the Irish TSO, Eirgrid,
are studying the feasibility of a new link between
France and Ireland with a maximum capacity of
700 MW.
> INELFE (Interconnexion Électrique France-
Espagne, a mixed-capital corporation shared
by REE and RTE) is leading a project to build an
underground interconnection by 2015 between
France and Spain, in the Eastern Pyrenees, to lift
exchange capacity between the countries to 2,800 MW. Joints
studies are also under way to study the possibility of building
a direct current line running under the sea between Bilbao
and Aquitaine, through the Gulf of Gascony, which would take
exchange capacity between the countries to 4,000 MW in
2020.
> France/Italy: The Savoie-Piemont project conducted with the
Italian system operator will ultimately boost exchange capa-
city with Italy by 500 MW.
> France/Belgium: RTE and Elia are looking into strengthening
interconnections to increase exchange capacity by about
1,000 MW.
> France/Germany: RTE is working with Amprion and TransnetBW
on ways to increase interconnection capacity between the
countries, notably by strengthening existing interconnectors.
> Through ENTSO-E, RTE is working with Swissgrid to study the
feasibility of increasing interconnection capacity by streng-
thening existing interconnectors.
319Decision 13-A-25 of 20 December 2013 on demand response in the electricity sector – paragraphs 204 – 217 on methods for calculating payment by demand-side operator to the supplier of the site that reduces demand.
320Decision 13-A-25 of 20 December 2013 on demand response in the electricity sector – paragraphs 177 – 185 on the absence of agreement from the electricity supplier for the demand-side operator to activate demand response at sites supplied by this supplier.
321Regulation 347/2013 on guidelines for energy infrastructure.
322[RTE, 2012 ten-year plan 2012]
The electricity market design in France is cur-rently undergoing structural changes to allow the participation of demand-response in all mar-kets, in keeping with the European Commission’s recommendations.
In this regard, the NEBEF experimental rules rep-resent a big step forward for electricity market design in France and Europe and enable demand-response to be an additional competitive tool to balance the system in an optimal way.
The ability for demand-response to participate in the balancing mechanism and contracts for the provision of system services and restoration reserves is another crucial building block for inte-grating the demand-side into markets. Specific mechanisms are also in place for demand response (demand-response and interruptibility auctions).
The launch in 2014 of an experiment testing the participation of demand-response in ancillary ser-vices is the third pillar of the new market design.
The interconnection projects presented in RTE’s ten-year plan are proof that the introduction of the capacity mechanism will not interfere with the development of interconnections between France and neighbouring countries.
226
10.2.1.2.4 Conclusions about the adoption of other
measures to improve the supply-demand balance
The European Commission only considers public intervention
in the form of capacity mechanisms necessary when structu-
ral measures have been taken to improve the functioning and
integration of energy markets. Such measures have a favourable
impact on the price signals generated by the market and its abi-
lity to assign the right value to energy.
The measures discussed in chapter 1 and the present chap-
ter of this report show that the actions undertaken in French
electricity markets comply with the European Commission’s
recommendations.
These measures promote the integration of markets and
improve their functioning. In this regard, they help correct
market imperfections and allow system needs, notably in
terms of flexibility, to be taken into account. The French capa-
city mechanism is not being introduced as a standalone ini-
tiative, but rather in the light of all the measures taken and
their positive effects. In other words, these measures cannot
be substituted for the capacity mechanism, which remains
necessary to generate an additional signal targeting security
of supply.
Without a capacity mechanism in place, these measures cannot
address the existence of externalities discussed in chapter 1.
In addition, measures must be planned taking into account
the time dimension. These actions are not taken on the same
timescale, and their effects on the supply-demand balance are
not simultaneous. For instance, it takes at least ten years to build
an interconnection, whereas new demand response capacity
can be made available with much shorter time constraints. The
European Commission’s checklist does not address this time
dimension.
It can also be advisable to introduce a capacity mechanism
before an imminent threat to security of supply is identified:
Waiting entails a significant risk, because it is not possible to
monitor the market and forecast generation adequacy with
sufficient certainty, far enough into the future, to allow time
for policy intervention when it becomes apparent that a shor-
tage of generating capacity looms.
[…]
The smoother transition and the lower risk to the reliability
of service are arguments in favor of a ’preventive’ strategy323.
Indeed, measures are less effective when taken curatively and
in haste than when their effects are proportionate to their
objective.
10.2.2 Principle of proportionality
Having established the necessity of the mechanism, this sec-
tion discusses its proportionality: the capacity mechanism
implemented in France should not go beyond what is strictly
necessary to meet the objective of security of supply as an aim
of public interest. In other words, it must be demonstrated that
the market architecture adopted is best suited to the objectives
pursued.
The compatibility of this market architecture with the European
Commission’s recommendations will also be discussed.
10.2.2.1 Proportionality regarding the security of
supply objective
The information in chapters 2 through 7 of this report can be
used to evaluate the proportionality of the architectural choices
made to the security of supply objective, or in other words to
demonstrate that these choices do not go beyond what is
strictly necessary to meet this objective.
A market-based architecture was chosen because it ensures
economic efficiency by allowing obligated parties to trade certi-
ficates to minimise the cost of their capacity obligation.
A market-wide mechanism was adopted to ensure that secu-
rity of electricity supply is truly guaranteed and to avoid discri-
minating between market participants. It also creates the right
incentives for demand to participate in the capacity mechanism,
thereby increasing competition.
Insofar as suppliers can cover their obligation by trading in a
decentralised market, the French capacity mechanism pre-
serves the responsibility structure of energy markets where
investments are concerned and avoids having public authorities
make decisions in lieu of market participants. Parties subject to
obligations in the capacity market are responsible for forecas-
ting their customers’ needs, covering these needs, and settling
any differences between their coverage and actual results. The
positive aspect of a decentralised market architecture on the
responsibility of market participants is reflected by economic
efficiency and proper cost allocation, and thus upholds the prin-
ciple of proportionality. 323[De Vries, 2006]
227
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
One key priority for RTE in applying the provisions of the decree
in the proposed rules was to ensure that power system stake-
holders’ real contributions to security of supply are accurately
reflected. Five key choices demonstrate this priority:
> A mechanism based on available capacity is consistent with
the proposal to adopt a market-wide capacity mechanism and
ensure that capacities are rewarded based on their real contri-
bution to security of supply;
> Using a demand-based approach to define the capacity com-
mitment period – i.e. securing commitments for the periods
when demand is highest – is a way to ensure that the capacity
mechanism’s effects target the needs of the power system
when security of supply is threatened;
> The parameters used for calculating suppliers’ capacity obliga-
tion – such as the security factor – and the amount of certificates
issued for capacity – for instance technical constraints impacting
the capacity’s contribution to reducing the shortfall risk – must
be set in such a way as to reflect as accurately as possible the real
contribution of suppliers to the shortfall risk and the real contribu-
tion of capacities to reducing the shortfall risk;
> Taking into account actual measurements for consumption
and capacity availability during the delivery year allows the
contribution of each market stakeholder to security of supply
to be recognised. Small imbalances between the data submit-
ted and actual results lead to a mere adjustment. To ensure
a balance between this need for individualisation and market
stakeholders’ request for stability and predictability, a norma-
tive approach can also be taken in calculating capacity levels
for intermittent capacity;
> The methods used to calculate capacity obligations and cer-
tify capacity must be defined in such a way as to guarantee
non-discrimination between the implicit and explicit valuation
of demand response. To ensure that demand response capa-
cities effectively contribute to security of supply, capacities
that are certified must be subjected to the same availability
commitments as generation capacities during the period
considered (PP2), and demand-side management measures
factored into the reduction of suppliers’ obligations must be
effectively activated during the period considered for the cal-
culation of the obligation (PP1).
In drafting the capacity mechanism rules, special attention was
also paid to ensuring that stakeholders would have confidence
in the “capacity certificate” product, this being essential to facili-
tating trading and allowing the capacity mechanism to produce
effects proportionate to the security of supply objective. For ins-
tance, the decision to publish the mechanism parameters and
stabilise them over the entire mechanism term guarantees that
trading will be conducted in a steady regulatory framework, and
that the value of the product will not be modified due to inter-
vention from outside the market. Moreover, the fact that capa-
city certificates are recorded in a register held by RTE makes the
product credible. In this regard, the architecture adopted, similar
to that of the energy market, enables bilateral trading, and lays
the groundwork for an exchange platform on which supply and
demand can be matched.
Various provisions have been included to ensure that stakehol-
ders in the capacity market will have full knowledge of the security
of supply outlook. In addition to RTE’s Adequacy Forecast Reports,
which is already published by RTE, they will be able to consult the
data in two registers that RTE will make open to the public:
> The certified capacity register, which will list all certified capa-
cities individually;
> The peak demand management register, where all demand-
side measures impacting the mechanism will be recorded.
The choices allowing the implicit participation of foreign capaci-
ties in the mechanism initially and the milestones set for a pos-
sible explicit participation further out are also taken into account
in assessing the capacity mechanism’s proportionality to the
security of supply objective for France.
10.2.2.2 Compatibility with the European Commission’s
recommendations on market design
The European Commission looks first at the type of capacity
mechanism proposed and had expressed a preference for
targeted mechanisms such as strategic reserves and one-off
tenders. The reasoning behind the adoption of a market-wide
mechanism is discussed in detail in chapter 2 of this report, with
evidence to support that strategic reserves or one-off tenders
would not meet the security of supply objective in a proportio-
nate manner. For instance, a strategic reserve would, in France,
result in excess capacities being created to meet the physical
needs of the power system during peak demand periods, which
are the primary risk for the French power system.
RTE’s analysis shows that the design of the French capacity
mechanism complies with all of the European Commission’s
All findings presented in this report show that the architecture adopted for the French capacity mechanism, as described in the decree and RTEs proposed rules, is proportionate to the objective of ensuring security of supply.
228
recommendations except with regard to the par-
ticipation of cross-border capacities. This specific
recommendation in partially addressed in the pre-
sent chapter as well as in 9. The information provi-
ded shows that a mechanism that initially allows the
implicit participation of cross-border capacities and
lays out steps to be taken to subsequently enable
their explicit participation is compatible with the European Com-
mission’s recommendations.
The table below provides an overview of the issues discussed in
detail in the previous chapters to demonstrate the compatibility
of the French capacity mechanism with the European Commis-
sion’s other recommendations.
324Enel Produzione case cited above, paragraph 75: “As regards the duration of the intervention provided for under the legislation at issue in the main proceedings, it must be limited to the length of time that is strictly necessary for attaining the objectives which it pursues. In that regard, it must be held that, since the list of essential installations is annually reviewed and updated, it would appear that installations are not kept on it for more than a limited period”.
Table 7 – Compatibility of the French mechanism with the European Commission’s recommendations presented during the RTE WG, 5/12/13
Guideline RTE analysis
Participation of new and existing capacities Participation of all capacities in the mechanism.
Technological neutrality Single product, certification based on technical performances.
Zero price in situations of excess capacity Market price: excess supply will drive the price toward 0.
2/4 year timescale Mechanism term starting in Y- 4, shorter timescales possible to better fit with demand response.
No export restrictionsNo clause specifying the destination of energy produced by capacities participating in the mechanism.
No restrictions on energy sales No price caps associated with participation in the capacity mechanism, no restrictions of offers.
No inefficient production The capacities participating in the mechanism commit to availability, not production.Commitment periods are limited (short PP2 period).
No impact on coupling or intraday
No changes affecting the functioning of energy markets or stakeholders' behaviours (marginal cost offers).
Participation of demandPerfectly compatible mechanism with two forms of participation possible (implicit/explicit) to better reflect the specific characteristics of demand response.Mechanism encouraging better consumption behaviours.
Real adequacy guarantees with unnecessary excess costs avoided
Commitments secured for all capacity: the fact that all capacities are committed to availability enhances security of supply benefits. Capacity that is not available is not rewarded through the capacity mechanism.Market price: the price tends toward zero in situations of overcapacity.Importance of measuring actual results to guarantee that market results reflect reality.
Virtuous cost allocation
The obligation reflects the contribution to the shortfall risk = to ensure a virtuous allocation of costs, the obligation must be calculated carefully taking into account the specific characteristics of demand with stakeholders being held responsible individually.There are no exemptions from the obligation.
Transitional mechanism
With a market-based mechanism, the price reflects the real value of the capacity need, and will tend toward zero if no capacity is needed; it will be possible to review how this system functions based on CRE's annual reports on the mechanism and reassess it if necessary.CRE will report annually on the mechanism’s functioning and integration into the European market. The European Court of Justice determined in its Enel Produzione decision that a measure that is reviewed and reassessed annually can be considered transitional 324.
RTE considers that the French capacity market design is compatible with the European Commission’s recommendations and does not go beyond what is necessary to ensure security of supply in France.
229
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
10.3 Conclusion
The introduction of a capacity mechanism in France, as provi-
ded for in the NOME Act, must be considered within a European
perspective. Indeed, while security of supply is ensured through
European Union Member States’ energy policies, there is in rea-
lity a high degree of interplay between the policies adopted by
Member States in an integrated market.
While the European Union has competence in energy-related
matters, security of supply is a Member States competence,
according to the provisions of article 194 of the TFEU. In this
regard, the EU acquis does not prohibit public intervention to
guarantee security of supply, and capacity mechanisms are
included in the measures listed in Directive 2005/89/EC of the
European Parliament and of the Council of 18 January 2006
concerning measures to safeguard security of electricity supply
and infrastructure investment.
Analysis of the legal framework governing public intervention in
the energy sector in Europe shows that two forms of public inter-
vention are possible for capacity mechanisms: State aid and public
service obligations, as provided for in Directive 2009/72/EC.
It is not RTE’s place to determine the legal qualification of the
capacity mechanism, though the architecture adopted for the
mechanism can be considered with regard to the framework
for public service obligations. The obligation is imposed on
suppliers, which contribute to compliance with the security of
supply criterion set by public authorities by having sufficient
capacities to ensure electricity supply to their final customers.
Generators are required to participate in the mechanism and
ensure that it functions properly by having all of their generation
capacity certified. The commitments undertaken during the
certification process to make certified capacity available ensure
that the capacity will effectively contribute to security of supply
during peak periods.
That being said, regardless of how the capacity mechanism
is qualified, the legality of the public intervention is evaluated
notably based on necessity and proportionality tests, particu-
larly based on the specific analytical framework proposed in the
Staff Working Document “Generation Adequacy in the internal
electricity market - guidance on public interventions”.
Regarding necessity, RTE’s Adequacy Forecast Reports comply
with the European Commission’s recommendations:
> Demand forecasts take into account EU energy and climate
policy (particularly with regard to demand management);
> Supply forecasts take the internal market into account
through estimates of generation capacity in Europe;
> Simulations are carried out using a probabilistic approach with
a careful modelling of contingencies and their correlations
(particularly for variable sources);
> All requirements in terms of transparency and stakeholder
consultation are met.
The results presented in the most recent update of the Ade-
quacy Forecast Report (2013), outlined in chapter 1 of this
report, show that safety margins vis-à-vis the security of supply
criterion will gradually shrink and then disappear in 2017. This
suggests that security of supply in France will have to be care-
fully monitored and will be at risk in 2017, particularly if a cold
spell occurs.
Actions undertaken to increase liquidity in French electricity
markets also comply with the European Commission’s recom-
mendations, notably by supporting projects to integrate the
European market over all time horizons, since they allow
demand response to participate in all market mechanisms
over all timescales, and by fostering the continued develop-
ment of interconnections between France and neighbouring
countries.
These measures all promote the integration of markets and
improve how they function. In this regard, they help correct
market imperfections and allow system needs, notably in
terms of flexibility, to be taken into account. That being said,
the French capacity mechanism is not being introduced as a
standalone initiative, but rather in the light of all the measures
undertaken and their positive effects. In other words, these
measures cannot be substituted for the capacity mechanism,
which is necessary to generate an additional signal targeting
security of supply.
As regards proportionality, the analyses presented in this report
demonstrate compliance with the European Commission’s
recommendations and show that the choices made are pro-
portionate to the objective of ensuring security of supply. The
one remaining open point is the participation of cross-border
capacities in the mechanism. Indeed, some legitimate questions
can be raised about the compatibility with European rules of the
230
decision to account for the contribution of foreign capacities to
security of supply in France implicitly. It should be noted that
this implicit solution results in a high degree of economic effi-
ciency. By reducing domestic capacity needs and thus avoiding
situations of overcapacity, the contribution of foreign capacities
to security of supply is already factored in as a positive exter-
nality. Moreover, chapter 9 features a roadmap outlining the
specific milestones included in the rules for moving toward a
target mechanism that explicitly recognises the contribution of
foreign capacities to security of supply in France and discusses
the kind of market architecture that would allow such effective
participation. The European Commission considers this to be
one possible approach.
RTE thus considers that the French capacity mechanism takes
into account the provisions of the EU acquis, particularly those
included in Directives 2009/72/EC and 2005/89/EC, and that
it complies with the principles of necessity and proportionality
described in the European Commission’s recommendations.
231
COMPLIANCE WITH EUROPEAN PROVISIONS AND PRINCIPLES / 10
232
BIBLIOGRAPHYACER (2013), Capacity Remuneration Mechanisms and the Inter-
nal Energy Market, Report of the Agency for the Cooperation of
Energy Regulators, 30/07/2013
ADLC (2012a), Opinion 12-A-09 of 12 April 2012 concerning a
draft decree on the creation of a capacity mechanism in the elec-
tricity sector, Competition Authority, April 2012
ADLC (2012b), Opinion 12-A-19 of 26 July 2012 concerning demand
response in the electricity sector, Competition Authority, 2012
ADLC (2013), Opinion 13-A-25 of 20 December 2013 concerning
demand response in the electricity sector, Competition Authority,
2013
AEEG (2013), Verifica finale di conformità dello schema di disci-
plina del nuovo mercato della capacità consultato da terna, Deli-
berazione 5 Settembre 2013, 375/2013/R/EEL, Autorità per
l’Energia Elettrica e il Gas, 2013
Arango, S., Larsen, E. (2011), Cycles in deregulated electricity mar-
kets: Empirical evidence from two decades, Energy Policy Volume
39, Issue 5, May 2011, pp. 2457-2466
Batlle C. (2012), Introduction to capacity mechanism; Market
failure and mechanism design, FSR webinar, Florence School of
Regulation, 2012
BDEW (2013) Design of a Decentralized Capacity Market, Position
Paper, BDEW German Association of Energy and Water Industries,
Berlin 18/09/2013
BG (2011), Energy Strategy of the Republic of Bulgaria till 2020
for Reliable, Efficient and Cleaner Energy, Report of the Bulgarian
Government, June 2011
Boiteux, M. (1960), Peak-load pricing, The Journal of Business, Vol.
33, No. 2, pp. 157-179, April, 1960
Bushnell, J., Mansur E. T., Saravia, C. (2008), Vertical Arrangements,
Market Structure, and Competition: An Analysis of Restructured
US Electricity Markets, American Economic Review, Vol. 98, N°1,
March 2008, pp. 237-266
Cepeda M. (2011), Security of electricity supply, market integra-
tion and the development of intermittent generation: Analysis of
the changing treatment of a public good, Doctoral thesis, Econo-
mic Sciences, EHESS-CIRED, 2011
Cepeda, M., Finon, D. (2011), Generation capacity adequacy in
interdependent electricity markets, Energy Policy, Vol. 39, Issue 6,
June 2011, pp. 3128-3143
CGSP (2014), The crisis of the European Electricity System – Dia-
gnosis and Possible Ways Forward, General Commission for Stra-
tegy and Foresight, January 2014
Coase, R. (1960), The Problem of Social Cost, Journal of Law and
Economics, III (1960), pp. 1-44, October 1960
European Council (2011), Conclusions of the European Council
of 4 February 2011
CRE (2012), Deliberation of 29 March 2012 on the draft decree
implementing article L.335-6 of the Energy Code concerning the
contribution of suppliers to security of electricity supply and institu-
ting a capacity mechanism, Energy Regulatory Commission, 2012
De Vries L. (2004), Securing the public interest in electricity gene-
ration markets. The myths of the invisible hand and the copper
plate, PhD dissertation, Delft University of Technology, Faculty of
Technology, Policy and Management, 2004
De Vries, L.J. (2007), Generation adequacy: Helping the market do
its job, Utilities Policy, Vol. 15, Issue 1, March 2007, pp. 20–35
De Vries, L., Heijnen, P. (2008), The impact of electricity market design
upon investment under uncertainty: The effectiveness of capacity
mechanisms, Utilities Policy, Vol. 15, Issue 1, March 2007, pp. 20-35
DECC, (2013) Electricity Market Reform: Capacity Market –
Detailed Design Proposals, Department of Energy and Climate
Change, Cm-8637, June 2013
Department of Justice (DOJ) (2010), Horizontal Mergers Guide, U.S.
Department of Justice and the Federal Trade Commission, August
2010
DGEC (2010), Draft bill on the new organisation of the electricity
market (NOME), Impact study, April 2010
DGEC (2013), Consultation document on changes to support
mechanism for facilities benefiting from purchase obligations, French
Department on Energy and Climate (DGEC), December 2013
ENTSO-E (2012), Communication Paper on Capacity Remunera-
tion Mechanisms, Working Group RES, ENTSO-E, 2012
ENTSO-E (2013), Scenario Outlook and Adequacy Forecast,
ENTSO-E, 03/04/2013
Eurelectric (2012), Powering Investments: Challenges for the libe-
ralized electricity sector, Eurelectric report, December 2012
Eurelectric (2013) Options for coordinating different capacity
mechanisms, A background note to the Eurelectric presentation
at the conference “Future electricity markets with or without
capacity mechanisms: What does Europe say?” – December 2013
European Commission (2011a), Roadmap for moving to a com-
petitive low-carbon economy in 2050. Communication from the
European Commission to the European Parliament, the Council,
the European Economic and Social Committee and the Commit-
tee of the Regions, COM (2011)112, 2011
European Commission (2011b), Energy Roadmap 2050. Commu-
nication from the European Commission to the European Parlia-
ment, the Council, the European Economic and Social Committee
and the Committee of the Regions, COM (2011)885,2011
233
European Commission (2012), Communication from the Com-
mission to the European Parliament, the Council, the Euro-
pean Economic and Social Committee and the Committee of
the Regions, “Making the internal energy market work”, COM
(2012)-663
European Commission (2013), Generation Adequacy in the inter-
nal electricity market - guidance on public interventions, Commis-
sion Staff Working Document, SWD (2013)438 accompanying the
Commission Communication Delivering the internal electricity
market and making the most of public intervention, C(2013)7243,
5 November 2013
European Commission (2013b), European Commission guidance
for the deisgn of renewables support schemes, Commission
Staff Working Document, SWD(2013)439, accompany the Com-
mission Communication Delivering the internal electricity mar-
ket and making the most of public intervention, C(2013)7243,
5 November 2013
Finon, D. (2011), Obligatory decentralised capacity, the best capa-
city mechanism in the context of the Nome regime, Revue de
l’Énergie, No. 604
Finon, D. (2013), The transition of the electricity system towards
decarbonization: the need for change in the market regime, Cli-
mate Policy, Vol. 13, Supplement 01, March 2013, pp. 130-145
Finon, D., Pignon, V. (2008), Electricity and long-term capacity ade-
quacy: The quest for regulatory mechanism compatible with elec-
tricity market, Utilities Policy, Vol. 16, Issue 3, September 2008, pp.
143-158
Finon, D., Roques, F. (2013), European Electricity Market Reforms:
The “Visible Hand” of Public Coordination, Economics of Energy &
Environmental Policy, Vol. 2, No. 2, 2013
Ford, A. (1999), Cycles in Competitive Electricity Markets: A Simu-
lation Study of the Western United States, Energy Policy, Vol. 27,
Issue 11, pp. 637-658, October
Ford, A. (2002), Boom and Bust in Power Plant Construction: Les-
sons from the California Electricity Crisis, Journal of Industry, Com-
petition and Trade, Vol. 2 no. 1-2, pp. 59-74
GDF-Suez (2013), GDF-Suez response to the European Commis-
sion consultation “Generation adequacy, capacity mechanisms
and the internal market in electricity”, GDF-Suez, 04/02/2013
Green R. (2006), Investment and generation capacity, in Com-
petitive Electricity Markets and Sustainability, Edited by François
Lévêque, Edward Elgar Publisher, December 2006, pp. 21-53
Hendricks, K. & McAfee, P. (2010), Theory of Bilateral Oligopoly,
Economic Inquiry, Western Economic Association International,
Vol. 48(2), pp. 391-414, April 2010
Joskow, P. L. (2007), Competitive Electricity Markets and Invest-
ment in New Generating Capacity, in The New Energy Paradigm
(Dieter Helm, Editor), Oxford University Press
Keppler, J.-H., Finon, D., Geoffron, P. (2013), Seven Proposals for an
Effective, Dynamic, Electric Europe, Revue de l’énergie, v. 64, No.
612, March-April 2013, pp. 95-105
Knittel, C. R. and Roberts, M. R. (2005), An empirical examination of
restructured electricity prices, Energy Economics, Vol. 27, Issue 5,
September 2005, pp. 791-817
Léautier, T.-O. (2012), The visible hand: ensuring optimal invest-
ment in electric power generation, IDEI Working Paper, No 605,
September 2011, revised in March 2013
Olsina, F., Garcés, F., Haubrich, H.-J. (2006), Modeling long-term
dynamics of electricity markets, Energy Policy, Vol. 34, Issue 12,
August 2006, pp. 1411-1433
Poignant-Sido (2010), Poignant-Sido report, Peak demand mana-
gement workgroup, April 2010
French Republic (2013), Response from French authorities to the
European Commission consultation on capacity mechanisms
and the internal energy market, 2013
RTE (2013), Experimenting with the participation of demand
response in energy markets (“NEBEF 1”), RTE report, 16 October
2013
RTE (2011), Report to the Minister of Industry, Energy and the Digi-
tal Economy on the institution of the capacity obligation mecha-
nism called for in the NOME Act, 1 October 2011
RTE (2012a), Adequacy Forecast Report for France, 2012 edition,
Réseau de Transport d’Electricité, 2012
RTE (2012b), Ten-year transmission network development plan,
Réseau de Transport d’Electricité, 2012
RTE (2013), Update of Adequacy Forecast Report for France, 2013
edition, Réseau de Transport d’Electricité, 2013
SEWRC (2004), Ordinance on Regulating the Prices of Electric
Power, SEWRC, 04/05/2004, State Energy and Water Regulatory
Commission, Bulgaria, http://www.dker.bg/docsen.php?d=53
Stoft, S.E., (2002), Power System Economics: Designing Markets
for Electricity, IEEE Press, Wiley-Interscience
Veyrenc, T. & Bhavaraju, M. (2008), Investments in generating
capacity: markets failures and capacity instruments in France and
the United States, CIGRE C5 Proceedings, 2008
Wolak, Frank A. (2003), Measuring Unilateral Market Power in
Wholesale Electricity Markets: The California Market 1998 to
2000, American Economic Review, May 2003, 425-430.
Weitzmann, M. (1974), Prices vs. quantities, Review of Economic
Studies, Vol. 41, Issues 4, pp. 477-491, October 1974
BIBLIOGRAPHIE
234
ANNEXE 1: LIST OF PARTICIPANTSIN MAC CONSULTATION
RTE contributors:
Clotilde LEVILLAIN (Présidente de la CAM) (RTE)
Mathilde BOURIGA (RTE)
Colas CHABANNE (RTE)
Mathieu CHUPIN (RTE)
Jean-Jacques COURSOL (RTE)
Gabriel DA-SILVA (RTE)
Christophe DERVIEUX (RTE)
Anne DUBUISSON (RTE)
Arthur HUBERT (RTE)
RTE would like to thank all participants in the consultation:
Chloé LATOUR (RTE)
Cédric LEONARD (RTE)
Céline MARCY (RTE)
Bruno MENU (RTE)
Marie PETITET (RTE)
Rebecca NAKACHE (RTE)
Thomas VEYRENC (RTE)
Gérald VIGNAL (RTE)
Hervé LEXTRAIT (EDF)
Christophe TRZPIT (EDF)
Nicolas BARBANNAUD (EDF-T)
Bertrand CHAMINAUD (EGL)
Vincent HOFFBECK (ELECTRICITE DE STRASBOURG)
Alexis JACQUILLARD (ELECTRICITE DE STRASBOURG)
Marc KOENIG (ELECTRICITE DE STRASBOURG)
Benoit DOIN (ENEL)
Juan LOPEZ-TERRADAS (ENEL)
Anne-Soizic RANCHERE (ENERGY POOL)
Emilie SCHOLTES (ENERGY POOL)
Emmanuelle CARPENTIER (EON)
Maëlle DURANT (EON)
Emmanuelle JOUBERT (EON)
Gad PINTO (EON)
Bruno GAILLARD (EOS)
Aurore LANTRAIN (EPEX SPOT)
Audrey MAHUET (EPEX SPOT)
Rémi OUDOUL (EPEX SPOT)
Florence ARNOUX-GUISSE (ERDF)
Remi GRASSET (ERDF)
Christophe GROS (ERDF)
Mehdi HAJJAM (ACTILITY)
Géry LECERF (ALPIQ)
Natacha HAKWIK (ALPIQ)
Pierre BAUD (ANPEEP)
Sylvain ROMIEUX (ANROC)
Barbara WUYTS (AXPO)
Quentin HARLE (COFELY)
Yann MICHEL (CRE)
Aurélien PAILLARD (CRE)
Emmanuel WATRINET (CRE)
Antoine CARON (DGEC)
Etienne HUBERT (DGEC)
Thibault LEINEKUGEL (DGEC)
Antoine PELLION (DGEC)
Julien TOGNOLA (DGEC)
David CHANTELOU (DIRECT ENERGIE)
Fabien CHONE (DIRECT ENERGIE)
Arnaud BORTOLOTTI (EDF)
Julian BOUCHARD (EDF)
Clotilde BRETON (EDF)
Richard COMBESCURE (EDF)
Jean-Christophe GAULT (EDF)
235
ANNEXES
Coralie NASLIN (ERDF)
Alexis SAUVAGE (ERDF)
Johann ZAMBONI (FLEXIWATT)
Francisco DELFINI (FNSICAE)
Raphael LAUBRÉAUX (FNSICAE)
Jean-Michel MICLO (FNSICAE)
Alain FUSER (GDF-SUEZ)
Stephane HECQ (GDF-SUEZ)
Redha LOUIDA (GDF-SUEZ)
Chantal LY (GDF-SUEZ)
Arnault MARTIN (GDF-SUEZ)
Patrick GODFRIN (GEG/ELE)
Sandra EDOU (HEX)
Aurora ALVAR MIRO (IBERDROLA)
Guillaume FAUCONNIER (MARKENER)
Aurélie LEMERCIER (NOVAWATT)
Philippe COUCHE (Planete OUI)
Jean ANGOTTI (POWEO Pont sur Sambre Production)
Stéphanie BOUCHET (POWEO Pont sur Sambre Production)
Thomas ULRICH (RWE)
Maxime DAUBY (SGE)
Antoine DEBROVES (SGE)
Philippe GAY (SGE)
Pascal GAT (SNCF)
Claude CONRARD (SOLVAY)
Julien DELAGRANDANNE (SOREGIES/ELE)
Lillian DALE (STATKRAFT)
Thibault CHRISTEL (TOTAL)
Baptiste MAMET (UEM)
Gildas BARREYRE (UNIDEN)
Stephane DELPEYROUX (UNIDEN)
Sophia ELASRI (UNIDEN)
Raphaelle IMBAULT (UNIDEN)
Dorothée COUCHARRIERE (VATTENFALL)
Laurence MARTIN (VATTENFALL)
Stephane CHANCY (VERBUND)
Pierre BIVAS (VOLTALIS)
Nicolas GAULY (VOLTALIS)
Jérôme SIMON (WATTVALUE)
236
Workgoup/Questionnaire # Stakeholders
Q1 28/01 Basic parameters 14Alpiq, ELD, EDF, Enel, Energy Pool, ERDF, EON, GDF Suez, NovaWatt, Direct Energie, SmartGrid Energy, Statkraft, Total Gas & Power, UNIDEN
WG of 07/02 on questionnaire 1 3 RTE, EDF, GDF Suez
Q2 12/02 Obligation 12Alpiq, ELD, EDF, Enel, Energy Pool, ERDF, EON, GDF Suez, Direct Energie, SmartGrid Energy, Statkraft, UNIDEN
WG of 19/02 on questionnaire 2 2 RTE, UNIDEN
Q3 20/02 Certification 13Alpiq, ELD, EDF, Enel, Energy Pool, ERDF, EON, GDF Suez, NovaWatt, Direct Energie, SmartGrid Energy, Statkraft, UNIDEN
WG of 27/02 on questionnaire 2 (continued) 3 RTE, EDF, ERDF
WG of 20/03 on questionnaire 3 4 RTE, EDF, ERDF, GDF Suez
WG of 02/04 on overall scheme 2 RTE, Direct Energie
WG of 25/04 Illustrations 2 RTE, EDF
WG of 17/05 Settlement 4 RTE, EDF, Energy Pool, GDF Suez
WG of 29/05 Certification of controllable capacities 6 RTE, EDF, Energy Pool, EON, GDF Suez, UNIDEN
WG of 07/06 Obligation parameters 3 RTE, EDF, GDF Suez
WG of 19/06 Certification of intermittent capacities and reduced contribution
3 RTE, EDF, ERDF
WG of 28/06 Capacity verification 4 EDF, ERDF, EON, GDF Suez
WG of 09/07 Calculation of obligation 3 RTE, EDF, ERDF
WG of 02/10 Draft rules, parts 1 to 4, 7 and 8 7 Alpiq, EDF, ENEL, EON, EPEX SPOT, ERDF, GDF-Suez
WG of 09/10 Draft rules, part 5 8 Alpiq, Direct Energie, EDF, ENEL, Energy Pool, EON, ERDF, GDF-Suez
WG of 14/10 Draft rules part 6 7 Alpiq, EDF, ENEL, Energy Pool, EON, ERDF, GDF-Suez
Feedback from consultation on draft rules 16
Alpiq, Direct Energie, ELD, EDF, EFET, Energy Pool, EON, ERDF, GDF-Suez, Novawatt, Poweo Pont sur Sambre Production, SGE, Statkraft, UIC, UNIDEN, Voltalis
WG of 14/11: Exchanges, transparency and competition in the market
1 RTE
WG of 22/11 Treatment of intermittent capacities 2 RTE, EDF
WG of 28/11 Calculation of temperature sensitivity 3 RTE, Direct Energie, EDF
WG of 05/12 Capacity monitoring and verification; European aspects 3 RTE, ERDF, GDF-Suez
All contributions can be found on the CURTE concerte website (https://concerte.fr).
ANNEXE 2: CONTRIBUTIONS TOTHE STAKEHOLDER CONSULTATION
RTE Réseau de transport d’électricité, Société anonyme à Directoire et Conseil de surveillance au capital de 2 132 285 690 € - RCS Nanterre 444 619 258Conception & réalisation : Good Eye’D - ©Fotolia - Impression sur papiers issus de forêts gérées durablement.