Free PMP® Exam Sample Questions
pm-exam-simulator.com
![Page 2: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/2.jpg)
PMP® Exam Sample Question
Presented by Cornelius Fichtner, PMP
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
![Page 3: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/3.jpg)
Provided by
www.pm-exam-simulator.com
This presentation showcases free sample
questions to help you study for the PMP exam
![Page 4: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/4.jpg)
The critical path in a project can be
determined by which of the following
techniques?
![Page 5: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/5.jpg)
A. Parametric Estimating
B. Pareto Chart
C. Sensitivity Analysis
D. Precedence Diagramming Method
![Page 6: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/6.jpg)
PDM is used for this purpose.
![Page 7: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/7.jpg)
D. Precedence Diagramming Method
![Page 8: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/8.jpg)
AOA (Activity on Arrow), AON (Activity on Node) and
PDM (Precedence Diagramming Method) are all valid
methods to use when determining a project's critical
path. PDM is also referred to as AON.
![Page 9: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/9.jpg)
The risk shared between the buyer
and the seller is determined by which
of the following?
![Page 10: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/10.jpg)
A. The Scope of Work
B. The Teaming Agreement
C. The Contract Type
D. The Project Charter
![Page 11: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/11.jpg)
How can you control the project risk
while negotiating the scope
of work with a seller?
![Page 12: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/12.jpg)
C. The Contract Type
![Page 13: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/13.jpg)
The risk shared between the buyer and seller is
determined by the contract type. For example,
fixed-price contracts have a higher risk for the
seller while cost-reimbursable contracts have a
higher risk for the buyer.
![Page 14: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/14.jpg)
You planned for contingency reserves for
your office building construction project
and used contingency plans to control
risks. However, your attempts to control
project risks were not effective. What is the
next step you should take?
![Page 15: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/15.jpg)
A. Use a fallback plan
B. Escalate to the project team
C. Perform the Plan Risk Responses
process again
D. Escalate to the sponsor
![Page 16: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/16.jpg)
If the primary risk response plan fails,
there should be one more plan to use
as a reaction to a risk.
![Page 17: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/17.jpg)
A. Use a fallback plan
![Page 18: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/18.jpg)
A fallback plan is used when a
contingency plan is not effective.
![Page 19: Free PMP® Exam Sample Questions](https://reader030.fdocuments.net/reader030/viewer/2022020219/5695d1471a28ab9b0295e071/html5/thumbnails/19.jpg)