Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Corey Walker
Office of Program Management
Sound Transit Steel Casing Product Substitution Review
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Seattle Light Rail Project
15.6 Miles from Downtown to Airport13 stations35 Light Rail VehiclesTotal Cost $2.7 BillionFTA Share $500 MillionFFGA awarded 2003Opened to S. 154th St July 2009Airport Station Opened December 2009
2
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Project Map
3
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Tukwila Freeway Route
Approximately 4.9 miles of guideway87% elevated187 columns support the elevated guidewayColumns up to 80 feet highThree types of footings used depending on
height and soil type
4
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Elevated Guideway
5
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Construction of Guideway
6
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Steel Casings on Site
7
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Casing Installation
8
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Foundation Ready for Concrete
9
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Foundation Casings
Prevent shaft from collapsing during construction
Provide additional shear strength to resist earthquake forces
Have little effect on ability of column to support the weight of trains and guideway (not counted on in design)
10
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Product Substitution
Sound Transit (ST) specified 50,000 psi (50 ksi) steel
Subcontractor provided 36,000 psi (36 ksi) steelST issued a Non-Conformance reportSubcontractor provided letter indicating that it
was 50 ksi steelLetter was found to be falsified
11
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
ST Response
Designers calculated strength of columns with 36 ksi steel
Columns still provided necessary strength with a reduced factor of safety
Concluded that no additional measures were required to ensure safety
12
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
FTA Oversight
FTA Project Management Oversight Consultant (PMOC) was on project since it began
Two on-site staff, task order manager and technical expert
Reviewed ST Construction Management and Quality Assurance procedures
Visited construction sites weekly
13
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
PMOC Actions
PMOC Confirmed ST construction managers had issued a Non-Conformance report
Checked ST engineers calculations and verified conclusions
Performed independent analysis to ensure structure was safe
14
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
PMOC Analysis
Brought in structural engineering specialist to perform analysis
Made computer model of columns, shafts, casings and foundations with the 36 ksi steel
Ran computer simulation of how the structure would fail when stressed to the point of failure
15
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
Model Results
Columns fail outside of the areas surrounded by the casings
The casings are not the part of the structure that would fail during an earthquake
Therefore, the use of weaker steel in the casings does not impact the ability of the structure to resist the design earthquake
In other words, the safety of the structure is not compromised
16
Fraud Awareness ConferenceFEDERAL TRANSIT ADMINISTRATION
FTA Costs
Expert was not part of PMOC team assigned to monitor project
Charged 202 hours to FTA Flew from New York to Seattle to review
documents, visit siteTotal cost was $30,523Appleby reimbursed FTA for costs of review
17