FOUNDATIONS FOR THE NEW INTERNATIONAL … Lecture. Bangkok Airport, ASCE Seattle... · 1...
Transcript of FOUNDATIONS FOR THE NEW INTERNATIONAL … Lecture. Bangkok Airport, ASCE Seattle... · 1...
1
FOUNDATIONS FOR THE NEW INTERNATIONAL AIRPORT IN BANGKOK, THAILAND
ASCE Seattle SectionGeotechnical Group
May 16, 2009
THAILANDBengt H. Fellenius
FOUNDATIONS FOR THE NEW INTERNATIONAL AIRPORT IN BANGKOK, THAILAND
Bengt H. Fellenius
A presentation to the ASCE Seattle Section 2009 Spring Seminar on
Recent Developments and Case Histories in Deep Foundations.
AbstractThe Suvarnabhhumi airport, the new international airport in Bangkok, Thailand, covering an area of 8 Km by 4 Km (8,000 acres), is located in a former swamp, a flat marine delta about 30 Km outside Bangkok. The soil profile consists of a thin weathered crust on typical soft to stiff, compressible Bangkok clay deposited on a sand layer at a depth of about 25 m extending to about 47 m. Below the sand lies an about 10 m thick layer of hard silty clay followed by very dense sand to large depth. Most of the area is devoted to runways, roadways, and parking, which required extensive ground improvement to minimize settlement. The structures consist of several units sharing footprints: terminal building, conourse, trellis structure, parking garage, and elevated roadways. The structures are founded on three types of piles installed to the sand below the clay layer, 1,000 mm bored pile, 600 mm diameter bored piles, and 600 mm driven cylinder piles. The stress-bulbs from the various foundations overlap resulting in a complicated settlement analysis. A total of 25,000+ piles were installed. The design of the airport started in 1995 and construction was completed in 2005 at a total cost of close to us$30 billion. The lecture will present aspects of the soil improvement work, analysis of results from pile tests, and the design of the piled foundations for capacity, settlement, and downdrag. The main part of the presentation consists of information quoted from papers published in Geotechnical Engineering Special Issue, Vol.37, No. 3, December 2006.
2
The New International Airport, Bangkok Thailand
Foundation Design by TAMS/Earth Tech, NY
with Dr. Bengt H. Fellenius as outside consultant
The presentation is primarily based on papers published in the Special Issue of the Journal of South-East Asian Geotechnical Society, "Geotechnical Engineering", December, 2006, as listed in the next slide.
Buttling, S. 2006. Bored piles and bi-directional load tests. Special Issue of the Journal of South-East Asian Geotechnical Society, December 2006, 37(3) 207-215.
Cortlever, N.G., Visser, G.T, and deZwart, T.P., 2006. Geotechnical History of the development of the Suvarnabhumi International Airport. Special Issue of the Journal of South-East Asian Geotechnical Society, December 2006, 37(3) 189-194.
Moh, Z.C. and Lin, P.C., 2006. Geotechnical History of the development of the Suvarnabhumi International Airport. Special Issue of the Journal of South-East Asian Geotechnical Society, December 2006, 37(3) 143-170.
Seah, T.H., 2006. Design and construction of ground improvement works at Suvarnabhumi International Airport. Special Issue of the Journal of South-East Asian Geotechnical Society, December 2006, 37(3) 171-188.
AND
Fox, I., Du, M. and Buttling, S, 2004. Deep Foundations For New International Airport Passenger Terminal Complex in Bangkok. Proceedings of the Fifth International Conference on Case Histories in Geotechnical Engineering, New York, April 13-14, Paper 1.22, 11 p.
33
44
55
Suvarnabhumi
International AirportAn 8 Km x 4 Km
area close to the Gulf of Thailand
66
Data from:
Fox, Du, and Buttling, (2004), Buttling
(2006), Moh
and Lin (2006), Seah
(2006), Cortlever, Visser, and deZwart
(2006)
Basic Soil Parameters
0
5
10
15
20
1,000 1,500 2,000
Density, ρt (%)
Dep
th (
m)
0
5
10
15
20
0 50 100 150
Water Content, wn (%)
Dep
th (
m)
0
5
10
15
20
0 25 50 75 100
Vane Strength, τu (KPa)
Dep
th (
m)
τu
Firm
Stiff to Very
Stiff
Very softto
Soft
wP
≈
30wL
≈
80 -
100
FILL
7
0
5
10
15
20
0 5 10 15 20
Virgin Modulus Number, m
Dep
th (
m)
0
5
10
15
20
0 50 100 150
Reloading Modulus Number, mr
Dep
th (
m)
Compressibility
Red Lines show distribution for designCircles are data points
CR = Cc
/(1+ e0
) m = ln10 (1 + e0
)/Cc
0
5
10
15
20
0.0 0.2 0.4 0.6 0.8Compression Ratio, CR
Dep
th (
m)
88
Comparison between the Cc
/e0
approach and the Janbu Modulus Number method
Data from a 20 m thick sedimentary deposit
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40 0.60 0.80 1.00 1.20
VOID RATIO, e0
CO
MPR
ESSI
ON
IND
EX, C
c
Do these values indicate a compressible soil, a medium compressible soil, or a non-
compressible soil?0
5
10
15
20
25
30
35
0.400.600.801.001.20
VOID RATIO, e0VI
RG
IN M
OD
ULU
S N
UM
BER
, m
The Cc
-e0
approach (based on Cc
) implies that the the
compressibility varies by 30±
%.
However, the Janbu methods shows it to vary only by 10±
%. The modulus number, m, ranges from 18 through 22; It would be unusual to find a clay with less variation.
99
0
100
200
300
400
500
600
700
1975 1980 1985 1990 1995 2000 2005
YEAR
SETT
LEM
ENT
(mm
)
Settlement of the Ground Surface Observed at Airport SiteRegional settlement occurs at and around the airport area due to
mining of ground water
Start of design work
10
Current and Future (long-term)
Pore Pressure Distribution
0
5
1015
20
25
30
35
40
45
50
0 100 200 300 400 500
Pore Pressure (KPa)
Dep
th (
m)
Long-Term
Short-Term (Current)
0
10
20
30
40
50
60
70
1975 1980 1985 1990 1995 2000 2005 2010
YEAR
Dep
th to
Gra
ounw
ater
Tab
le (
m)
DesignPhase
ConstructionPhase
Nearby Observations of Groundwater Table
Pumping (mining) of groundwater has reduced the pore pressures in the Bangkok delta resulting in significant regional settlement. In 1996, coinciding the beginning of the design process, pumping in the area was stopped. Pore pressure measurements indicate that the desired effect is being reached; the pore pressures are rising and the distribution may become hydrostatic
in the future.
1111
0
20
40
60
80
100
120
140
YEAR
WA
TER
DEP
TH (
m)
132a- 14m217 - 26m216a- 39m115 -153m209 -159m111 -161m501a-180m912 -206m114a-261m
618 -267m606 -301m501b-365m132b-442m114b-480m
1925 1935 1945 1955 1965 1975 1985 1995 2005 2015
SHALLOW WELLS
DEEP WELLS
The lowering of the groundwater table due to mining of water in the Bangkok delta is not unique. Below is a compilation of depth to
the water table measured in the San Jacinto-Houston-Pasadena area in Texas.
12
-83 KPa
105 KPa
34 KPa
85 KPa
105 + 34 + 85 = 224 - 83 141 KPa
110 m
38 m74 m
Briaud et al. 2007; Fellenius and Ochoa 2008
0
50
100
150
200
250
300
3501936 1946 1956 1966 1976 1986 1996 2006
SETT
LEM
ENT
(mm
)
YEAR
SETTLEMENT OF MONUMENT RELATIVE TO BENCHMARK
0
50
100
150
200
250
300
350
400
1 10 100
YEAR
SETT
LEM
ENT
(mm
)
1936 1937 1940 1945 1950 1960 1975 2000
LINEAR PLOTLOWER SCALE
LOGARITHMIC PLOTUPPER SCALE
1936 1946 1956 1966 1976 1986 1996 2006
13
0
50
100
150
200
250
300
350
400
1 10 100
YEARSE
TTLE
ME
NT (
mm
)
1936 1937 1940 1945 1950 1960 1975 2000
DEPTH TO WATER TABLE
SETTLEMENT
0
25
50
75
100
125
DEP
TH T
O W
ATE
R T
AB
LE (
m)
Monument only
Measured depths to water table and measured settlement of the Monument plus estimated settlement of the Monument had there been no drawdown of the water table.
1414
And in the San Joaquin Valley in California:
1977
1955
1925
Subsidence at San Joaqu in Valley, California
Devin Galloway and Francis S. Riley, U.S. Geological Survey
Approximate location of maximum subsidence in United States identified by research efforts of Joseph Poland (pictured).Signs
on pole show approximate altitude of land surface in 1925, 1955,
and 1977. The pole is near benchmark S661 in the San Joaquin Valley southwest of Mendota, California,
1515
Circles are preconsolidation data pointsDashed green line shows distribution for design“Short-term”
: Effective stress distribution at time of design“Long-term”
: Effective stress distribution after groundwater table is raised
0
5
10
15
20
0 50 100 150 200
Stress (KPa)
Dep
th (
m)
Long-term
σ'0
σ'c
Short-term
σ'0
Stress ProfileBut back to Bangkok:
1616
MainTerminal
Acess Roads
Concourses
17
-400
-300
-200
-100
0
100
200
300
400
500
6000 40 80 120 160 200 240
DAYS
SETT
LEM
ENT
(mm
)
Construction Period
Full Height = 3.0 m
Calculated Immediate Settlement
Calculated Total Settlement
Measured Total Settlement
HE
IGH
T (m
)
3.0
2.0
1.0
0
Calculated Consolidation Settlement
40 m 10 m
First a few words on the soil improvement work
Measured and Calculated Settlement at center line of for a 3.0 m
Embankment during 200 days. No drains, i.e., incomplete consolidation.
1818
Settlement at center line of a 3.6m Embankment on Wick Drains
AVERAGE MEASURED SETTLEMENT
DESIGN CURVE FOR THISSURCHARGE (75 KPa)
1.0 m
FINAL HEIGHTOF FILL
SETT
LEM
ENT
(mm
)
Wick Drains Installed
≈200 days
For reference, the curve of the 3.0m "undrained" embankment
19
Settlement and Horizontal Movement for the 3.6 m Embankment
Time from start to end of surcharge placement = 9 monthsObservation time after end of surcharge placement = 11 months
WICK DRAINS TO 10 m DEPTH
1.0 m
2.0 m
WICK DRAINS TO 10 m DEPTH
WICK DRAIN
Settlement was monitored in center and at embankment sides and horizontal movement was monitored near sides of embankment
2020
Horizontal Movement versus Settlement at Different Test LocationsH
OR
IZO
NTA
L M
OVE
MEN
T (c
m)
SETTLEMENT (cm)
2121
Lateral spreading
Settlement with risk for downdrag
The Problem
Piles
2222
2323
These photos of the bridge foundations illustrate a common problem affecting maintenance ($$$!), as well as, on occasions, being one compromising safety.
2424
The problem is not limited to bridge foundations
2525
Consolidation Coefficient, cv (m2/s)
Consolidation Coefficient, cv (m2/s)
Settlement after 4 months
as a function of the Consolidation Coefficient
and Drain Spacing
Degree of Consolidation after 4 months as a
function of the Consolidation Coefficient
and Drain Spacing
vv c
HTt2
=
SETTLEMENT (m)
CONSOLIDATION (%)
2626
The clay is soft and normally consolidated with a modulus number
smaller than 10.
All foundations —
the trellis roof, terminal buildings, concourse, walkways, etc.
—
are placed on piles. The stress-bulbs from the various foundations will overlap each other’s areas resulting in a complicated settlement analysis.
1,000 mm Bored Piles
600 mm Bored Piles 600 mm Driven Closed-toe Cylinder Piles 1,000 mm Bored Piles
600 mm Bored Piles
2727
Horizontal soil movement ("lateral spreading") toward piles can be critical
TRELLIS ROOF PILE CAP
FOOTPRINTS OF PILE CAPS FOR TERMINAL BUILDING NEAR TRELLIS ROOF
TYPICAL FOOTPRINT LAYOUT OF TRELLIS AND BUILDING FOUNDATIONS
Additional features, such as Embankments, Aprons, Concourse foundations, Area Fills, etc. adversely affect the piles and the piled foundations.
The stress interference between the foundations is significant and must be
considered in the design analyses
2828
To minimize lateral spreading toward adjacent foundations, some embankments were "supported" on soil-cement columns. For others, vacuum surcharge was employed together with fill surcharge.
Vacuum surcharge will cause the perimeter soil to move inward. Combining vacuum and fill surcharge can minimize the horizontal soil movement.
Vacuum surcharge can theoretically reach a stress of 100 KPa, but in practice, the maximum stress is about 60 KPa, equivalent to a fill height of about 3 m.
The final design employed a vacuum surcharge (considered tobe effective at 60 KPa) combined with an about 3 m surcharge fill (= 56 KPa) and a 0.9 m c/c
triangular drain spacing. The target time for 60 % consolidation was 4 months at which time the extra surcharge was removed to bring the degree of consolidation to about 85 %.
2929
3030
0
1,000
2,000
3,000
4,000
5,000
6,000
0 5 10 15 20 25 30
MOVEMENT (mm)
LOA
D (
KN
)
STATIC LOADING TEST600 mm, 35 m Long Bored Pile
0
5
10
15
20
25
30
35
40
0 1,000 2,000 3,000 4,000 5,000 6,000LOAD (KN)
DEP
TH (
m)
3131
Stage 1Lower Cell activatedUpper cell closed
Stage 2Lower Cell openUpper Cell activated
Stage 2Lower Cell closedUpper Cell activated
Data fromFox, I., Du, M. and Buttling,S. (2004)Buttling, S. (2006)
Bi-directional Static Loading Test, "O-cell" test —
1,000 mm Pile
3232
O-Cell tests
Downward movements during test phases 1, 2, and 3
Concern was expressed that the toe resistance (Phase 1) was ≈3,000 KN and the shaft resistance for the lower segment was ≈5,000 KN (Phase 2), while in Phase 3 the combined shaft and toe resistances were only ≈6,000 KN. Should not the Phase 3 resistance be ≈8,000 KN rather than ≈6,000 KN (i.e., the sum of the values ≈5,000 KN and ≈3,000)?
0
25
50
75
100
125
150
175
0 2,000 4,000 6,000 8,000 10,000
LOAD (KN)M
OVE
MEN
T (m
m)
Active CellInactive, Open CellInactive, Closed Cell
P1 P2P3
1 2 3
3333
Downward toe movements
0
25
50
75
100
125
150
175
0 2,000 4,000 6,000 8,000 10,000
LOAD (KN)
MO
VEM
ENT
(mm
)
Active CellInactive, Open CellInactive, Closed Cell
P1 P2P3
1 2 30
25
50
75
100
125
150
175
0 2,000 4,000 6,000 8,000 10,000
LOAD (KN)
DO
WN
WA
RD
MO
VEM
ENT
(mm
)
Active CellInactive, Open CellInactive, Closed Cell
P2
P1 and P2 data combined
P3
1 2 3
are best plotted per sequence of testing. Particularly when considering toe resistance, one must evaluate the load-movement response in comparing Phase 1 + Phase 2 to Phase 3 (i.e., P2 shaft below cell plus P1
toe).
3434
0
5
10
15
20
25
30
35
40
45
0 2,000 4,000 6,000
Load (KN)
Dep
th (m
)
Stage 1
101 mm toeMovement
0
5
10
15
20
25
30
35
40
45
0 2,000 4,000 6,000
Load (KN)
Dep
th (m
)
Stage 2
62 mm DownwardMovement
0
5
10
15
20
25
30
35
40
45
0 2,000 4,000 6,000
Load (KN)
Dep
th (m
)
Stage 2
Stage 3Max Load
Load Distributions
3535
0
5
10
15
20
25
30
35
40
45
0 2,000 4,000 6,000
Load (KN)
Dep
th (m
)
Stage 3
48 mm DownwardMovement
0
5
10
15
20
25
30
35
40
45
0 2,000 4,000 6,000 8,000 10,000 12,000
Load (KN)
Dep
th (m
)
Stage 2 Stage 3Stage 1
??
3636
The test data —
settlement data as well as pile test data —
were applied to
the design of the piled foundations employing the Unified Design Method.
3737
The Unified Design Method is a three-step approach
1. The dead plus live load
must be smaller than the pile capacity
divided by an appropriate factor of safety. The drag load is not included when designing against the bearing capacity. [The capacity of the pile toe should be defined from a movement criterion].
2. The dead load plus the drag load
must be smaller than the structural strength
divided with a appropriate factor of safety. [The live load must not be included because live load and drag load cannot coexist].
3. The settlement
of the pile (pile group) must be smaller than a limiting value. The live load and drag load are not included in this analysis. [The value(s) of acceptable settlement often governs a piled foundation design].
3838
Construing the Neutral Plane and Determining the Allowable Load
393939
A repeat: Distribution of unit shaft shear and of load and resistance
SHAFT SHEAR
DEP
TH (–)
(+)
LOAD
DEP
TH
Settling Soil
Non-Settling
Soil
1
0
5
10
15
20
25
30
35
40
45
0 500 1,000 1,500 2,000 2,500 3,000
LOAD and RESISTANCE (KN)
DEP
TH (
m)
0
5
10
15
20
25
30
35
40
45
0 10 20 30 40 50 60 70 80
SETTLEMENT (mm)
DEP
TH (
m)
NEUTRAL PLANE
TOE MOVEMENT THAT MOBILIZES THE TOE
RESISTANCE
SETTLEMENT OF PILE HEAD
TOE RESISTANCE
PILE "CAPACITY"
DEAD LOAD
DRAGLOAD
*) Portion of the toe resistance will have developed from the driving
*)
The Unified Method (typical example)
41
Force and settlement (downdrag) interactive design. The unified pile design for capacity, drag load, settlement, and
downdrag
0
5
10
15
20
25
30
0 2,000 4,000 6,000LOAD (KN)D
EPTH
(m)
O-cell
SiltSand
Clay
Till
Qd
Pile toe load in the load distribution diagram must match the toe load induced by the toe movement (penetration), which match is achieved by a trial-and-error procedure.
0
5
10
15
20
25
30
0 50 100 150 200
SETTLEMENT (mm)
DEP
TH (m
)
0
5
10
15
20
25
30
0 2,000 4,000 6,000LOAD (KN)D
EPTH
(m)
O-cell
SiltSand
Clay
Till
0
1,000
2,000
3,000
4,0000 50 100
TOE
LOA
D (K
N)
Qd
Pile toe load in the load distribution diagram must match the toe load induced by the toe movement (penetration), which match is achieved by a trial-and-error procedure. PILE TOE PENETRATION (mm)
Pile Cap Settlement
Soil Settlement
q-z relation
4242
Applied to the Bangkok Airport case
Several static loading tests on instrumented piles were performed to establish the load-transfer conditions at the site at the time of the testing, i.e., short-term conditions. Effective stress analysis of the test results for the current pore pressures established the coefficients applicable to the long-term conditions after water tables had stabilized.
A total of 25,400+
piles were installed.
4343
The extensive testing and the conservative assumption on future pore pressures allowed an Fs
of 2.0. The structural strength of the pile is more than adequate for the load at the neutral plane: Qd
+ Qn
≈
1,500 KN.
Example of calculated resistance distribution for 600 mm diameter bored pile installed to a 30 m embedment depth.
0
10
20
300 1,000 2,000 3,000
LOAD (KN)
DEP
TH (
m)
Qn = 770 KN
Qd = 1,040 KN RULT = 2,870 KNFs = 2.0
Short-Term
Fs = 2.0 on long-term capacity
0
10
20
300 1,000 2,000 3,000
LOAD (KN)
DEP
TH (
m)
Long-Term
Qn = 500 KN
Qd = 1,040 KN RULT = 2,080 KNFs = 2.0
Clay
Sand
4444
The settlements for the piled foundations were calculated to:
Construction
Long-term
TotalTrellis Roof Pylons
20 mm
90 mm
110 mm
Terminal Building
30
15
45
Concourse
35
20
55
* * *
4545
Contour lines of settlement of ground surface and pile caps near
a trellis roof pile cap
4646