FortisBC Energy Incto Fortis BC Energy Inc •FortisBC will now be the corporate name used by both...
Transcript of FortisBC Energy Incto Fortis BC Energy Inc •FortisBC will now be the corporate name used by both...
FortisBC Energy Inc
Kingsvale - Oliver Pipeline Reinforcement Project
(“KORP”)
Presentation to RDOS
March 15, 2012
Terasen Gas Inc. Name Change
to
FortisBC Energy Inc.
• On March 01, 2011, Terasen Gas Inc changed its name to Fortis BC Energy Inc
• FortisBC will now be the corporate name used by both the Fortis electrical and gas utility operations
KOR Project Rationale
Scope of Project
• 161 km of 24” diameter pipeline “loop” from Kingsvale to Oliver generally following the existing 12” FortisBC pipeline
• 1 km extension of the Southern Crossing Pipeline in the Yahk area
• New compression at Kingsvale, Trail and Yahk
The KOR Project will remove constraints on the existing pipeline system and thereby increase the capability of moving additional volumes of natural gas both east and west to the benefit of all FortisBC customers
Western North America Transmission
Systems
FortisBC
Spectra Energy
161 km 24” Kingsvale to Oliver Segment
KORP - Route
First Nations potentially impacted
• The KOR Project area lies in the claimed territories of the
Nlaka’pamux, Ktunaxa and Okanagan Nations.
• In total there may be twenty eight First Nations and five
First Nations’ organizations associated with the Project
area.
• The project crosses the Ashnola and Blind Creek
reserves of the Lower Similkameen Indian Band
Typical pipeline construction in progress
Typical Compressor Station
Typical pipeline Right of Way
The following FN have been identified • Nicola Tribal Association:
• Coldwater Indian Band • Cook’s Ferry Indian Band • Nicomen Indian Band • Nooaitch Indian Band • Shackan Indian Band • Siska First Nation • Upper Nicola Band (also member of Okanagan Nation Alliance, as below)
• Okanagan Nation Alliance: • Westbank First Nation • Lower Similkameen Indian Band (pipeline crosses reserves) • Upper Similkameen Indian Band • Osoyoos Indian Band • Penticton Indian Band • Okanagan Indian Band • Upper Nicola Band (Also member of Nicola Tribal Association, as above)
• Nlaka’pamux Nation Tribal Council • Ashcroft Indian Band • Boothroyd Indian Band • Boston Bar First Nation • Oregon Jack Creek Indian Band • Lytton First Nation • Spuzzum First Nation • Kanaka Bar First Nation • Skuppah First Nation
• Ktunaxa Nation Council Society: • Tobacco Plains Indian Band • ?Akisq’nuk First Nation • Lower Kootenay Band (Yaqan Nukiy) • St. Mary’s Band
• Unaffiliated • o Splatsin First Nation (Spallumcheen) • o Lower Nicola Indian Band • o Shuswap Indian Band
Local Governments
The KOR Project is located in/near the following areas of
the province:
• Nicola Regional District
• Regional District Okanagan Similkameen
• Boundary Regional District
• Central Kootenay Regional District
• Village of Keremeos
• Town of Princeton
• Town of Oliver
• City of Merritt
• East Kootenay Regional District
Status to date • Preliminary field studies commenced in 2010 to
determine whether a technically and environmentally suitable route existed primarily located alongside its existing 12” pipeline (known as looping).
• Studies continue in 2011 and 2012 including
• studying commercial feasibility
• overview assessments of potential environmental issues and locating a preferred route
• initiating engagement with local governments and potentially affected First Nations.
• Initiating the BC Environmental Assessment Act (BCEAO) and Canadian Environmental Assessment Act (CEAA)
• Drafting Application Information Requirements (dAIR) for BCEAO/CEAA Harmonized review
• first BCEAO/CEAA Working Group meeting held on Feb. 15 in Princeton to begin review of the dAIR
KORP – earliest Schedule Task Name Q1 Q2 Q3 Q4 Q2 Q3 Q3 Q1 Q2 Q3 Q1 Q2 Q3
1. First Nations, Government, and
Stakeholder Engagement
2. Planning and Environmental
Field Studies; submit Project
Description, prepare final
Application Information
Requirements; prepare
EAC Application
3. Submit Regulatory
Applications
4. Environmental Assessment
Process
5. Regulatory Approval
6. Detailed Engineering and
Permitting
7. Clearing and Right-of-Way
Preparation
8. Pipeline Construction
9. Compressor Station
Construction
10. System Start-Up
11. Restoration
at end of construction
2016
Q4
20132010 2012
Q3 Q4Q1 Q1 Q4Q4Q1
Q1 Q4 Q2Q2
2011
Task Milestone
2014 2015
Q2 Q3 Q4
KORP – earliest Key Dates
• Receive AIR from BCEAO and CEAA
• Commence environmental field studies to respond to AIR
• Complete research and file the Environmental Application
• Receive Environmental Assessment Certificate
• Request BCUC CPCN and confirm financial decision to construct
• Commence clearing
• Construct
• In-service
• Q2 2012
• Q2 2012
• Q1 2013
• Q4 2013
• Q4 2013
• Q4 2014
• Q2-Q4 2015
• Q4 2015
KORP–Regulatory Authorizations
Environmental
• FortisBC must receive an Environmental Assessment Certificate (EAC) from the BCEAO and approval under the CEAA
Public Interest and Financial
• FortisBC cannot proceed with construction without also receiving a Certificate of Public Convenience and Necessity (CPCN) from the BC Utilities Commission
Technical
• The BC Oil and Gas Commission (OGC) will provide final construction permits
KOR Project Next Steps
• The BCEAO will soon issue a Section 11 Order that will set out the scope of the project and the requirements for the Environmental Review
• BCEAO and CEAA have commenced contacting affected First Nations and local governments to determine their interest in participating in the Review
• Review of draft AIR to confirm study requirements commenced on February 15
• Field work to complete the environmental assessment to study the potential impacts of the project and propose mitigation could commence summer 2012