Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA At Village Dadam, Tehsil Tosham , DistrictBhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates 1 APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information S. No. Item Details 1. Name of the project/s Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA. 2. S. No. in the schedule As per EIA Notification dated 14.09.2006 and as amended from time to time, this project falls under Category DzAdz, Project or Activity 1(a) (3). 3. Proposed capacity/area/length/tonnage handled/ command area/lease/number of wells to be drilled Area: 55.50 ha Production capacity: 15 MTPA 4. New/Expansion /Modernization Modernization (Amendment in name of E.C from M/s KJSL-Sunder (JV) to M/S Sunder Marketing Associates ) 5. Existing Capacity /Area etc. 15 MTPA 6. Category of Project i.e.' A' or 'B' Category DzAdz 7. Does it attract the general condition? If yes, please specify. No, it does not attract the general condition. 8. Does it attract the specific condition? If yes, please specify. No, it does not attract the specific condition. 9. Location 10. Plot/Survey/Khasra No 132 (Min.), 133 11. Villages Dadam 12. Tehsil Tosham 13. District Bhiwani 14. State Haryana 15. Nearest railway station/airport along with distance in kms Nearest Railway Station: Bawani Khera Railway station (~18 km in NE direction). Nearest Airport: Indira Gandhi International Airport,

Transcript of Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil...

Page 1: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 1

APPENDIX I

(See paragraph – 6)

FORM 1

(I) Basic Information

S. No. Item Details

1. Name of the project/s Proposed minor mineral Mining Project (ML Area: 55.50

ha) Production of Stone along with Associated Minor

minerals 15 MTPA.

2. S. No. in the schedule As per EIA Notification dated 14.09.2006 and as amended from time to time, this project falls under Category A , Project or Activity 1(a) – (3).

3. Proposed

capacity/area/length/tonnage

handled/ command

area/lease/number of wells to be

drilled

Area: 55.50 ha

Production capacity: 15 MTPA

4. New/Expansion /Modernization Modernization (Amendment in name of E.C from M/s

KJSL-Sunder (JV) to M/S Sunder Marketing Associates )

5. Existing Capacity /Area etc. 15 MTPA

6. Category of Project i.e.' A' or 'B' Category A

7. Does it attract the general

condition? If yes, please specify.

No, it does not attract the general condition.

8. Does it attract the specific condition?

If yes, please specify.

No, it does not attract the specific condition.

9. Location

10. Plot/Survey/Khasra No 132 (Min.), 133

11. Villages Dadam

12. Tehsil Tosham

13. District Bhiwani

14. State Haryana

15. Nearest railway station/airport

along with distance in kms

Nearest Railway Station: Bawani Khera Railway

station (~18 km in NE direction).

Nearest Airport: Indira Gandhi International Airport,

Page 2: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 2

New Delhi (~127 km in ESE direction)

16. Nearest Town, city, District Head

quarters along with distance in

kms.

Nearest Town:- Tosham (~ 6.0 km In ESE direction).

Nearest City & District Headquarter: - Bhiwani (~30.0

km in SE direction).

17. Village Panchayats, Zilla Parishad,

Municipal Corporation, Local body

(complete postal addresses with

telephone nos. to be given)

Gram Panchayat Dadam, Tehsil: Tosham, District: Bhiwani

(Haryana).

18. Name of the applicant M/s Sunder Marketing Associates

19. Registered Address M/s Sunder Marketing Associates, 702, Pearls Business

Park, Netaji Subhash Palace, Pitampura

Delhi – 110034

20. Address for correspondence Project Proponent EIA Consultant

21. Name Naveen Goel N/A

22. Designation (Owner/ Partner/

CEO)

Proprietor N/A

23. Address M/s Sunder Marketing

Associates, 702, Pearls

Business Park, Netaji Subhash

Palace, Pitampura

Delhi.

N/A

24. Pin Code 110034 N/A

25. E-mail [email protected] N/A

26. Telephone No 9999666911 N/A

Fax No - N/A

27. Details of Alternative Sites

examined, if any. Location of these

sites should be shown on a topo

sheet.

No alternative site has been examined since it is a site

specific mining project based on availability of mineral

potentiality in the area. E.C for the said site is issued dated

03/07/15 on the name of M/S KJSL-Sunder(JV), but now

the Mining department has allowed for the transfer of

Mining Lease from M/s KJSL- Sunder (JV) to M/s Sunder

Marketing Associates through letter no.

Page 3: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 3

DMG/HY/ML/Dadam/2013/7024 dated 16/07/2015, by

the Director General, Mines and Geology Department

Haryana.

28. Interlinked Projects No interlinked projects

29. Whether separate application of

interlinked project has been

submitted?

Not Applicable

30. If yes, date of submission Not applicable

31. If no, reason Not applicable.

32. Whether the proposal involves

approval/ clearance under: if yes,

details of the same and their status

to be given.

(a) The Forest (Conservation) Act

1980?

(b) The Wildlife (Protection) Act

1972?

(c) The C.R.Z Notification. 1991?

Not applicable.

33. Whether there is any Government

Order/ Policy relevant/ relating to

the site?

No

34. Forest land involved (hectares) No Forest land is involved in the lease area.

35. Whether there is any litigation

pending against the project and/ or

land in which the project is

proposed to be set-up.

(a) Name of the Court

(b) Case No

(c) Orders/ Directions of the court,

If any and its relevance with the

proposed project

No litigation is pending.

Page 4: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 4

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will

cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S. No Information/Checklist

confirmation

Yes

/No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

1.1 Permanent or temporary

change in land use, land cover

or topography including increase

in intensity of land use (with

respect to local land use plan)

Yes Total Mining area is 55.50 ha. It is Govt. land (as per

revenue record)

The topography of the area is hilly and having sharp

slopes. There will be a permanent change of land

use of mining activity area. The mining activity will

leave excavated area which will be converted into

reservoir.

Dense green belt/plantation will be developed along

the lease boundary, near mine office etc.

1.2 Clearance of existing land,

vegetation and buildings?

Yes There is no building & structure which need to be

demolished/ removed from mining lease area

except some shrubs existing on the lease area which

will be cleared when required

1.3 Creation of new land uses? Yes Mining activity will involve excavation of the area,

which will be converted into water reservoir.

Dense green belt/plantation will be developed along

the lease boundary, haul roads, around mine office

etc.

1.4 Pre-construction investigations e.g.

bore houses, soil testing?

Yes Pre-construction investigations like Exploratory

Drilling has already been carried out and found

satisfactory.

1.5 Construction works? Yes Being a mining project it requires very little

construction work.

1.6 Demolition works? No No demolition work shall be there.

1.7 Temporary sites used for

construction works or housing of

construction workers?

No As the project involves only minor construction of

mines office, haul roads thus there is no need of

temporary sites for housing of construction

Page 5: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 5

workers.

Local Laborers will be employed on need basis from

the nearby villages. Amenities / Facilities will be

provided to construction workers.

1.8 Above ground buildings, structures

or earthworks including linear

structures, cut and fill or

excavations.

Yes There will be excavation, cut and fill during

construction of mines office, within the mining lease

area. Excavation during mining operation will be

carried out. Voids will be formed by excavation of

mineral.

1.9 Underground works including

mining or tunneling?

No No underground works including mining or

tunneling is required.

1.10 Reclamation works? Yes There will be a permanent change of land use of

mining activity area. The mining activity will leave

excavated area which will be converted into

reservoir.

Dense green belt/plantation will be developed along

the lease boundary, near mine office etc.

1.11 Dredging? No There will be no dredging.

1.12 Offshore structures? No There are no offshore structures.

1.13 Production and manufacturing

processes?

Yes The mining operations will be by mechanized

opencast method which include blasting, excavation,

sorting of mineral & transportation by trucks to the

existing crushers.

1.14 Facilities for storage of goods or

materials?

Yes Facilities will be required for storage of goods and

materials as per mining plan.

1.15 Facilities for treatment or

disposal of solid waste or liquid

effluents?

Yes No OB Waste will be generated.

Small quantities of liquid effluent will be

generated from the workshop, which will be

treated by oil water separator. And waste water

generated from mine office (Drinking, office

toilets etc.) will be disposed off via soak pit/

septic tank.

1.16 Facilities for long term housing of No Permanent workers and staff members will be

Page 6: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 6

operational workers? mostly residents of nearby villages. Thus, no land

will be used for residential purposes within mining

area. Technical supervisors will be provided

accommodations in nearby village close to the area

1.17 New road, rail or sea traffic during

construction or operation?

No No new road, rail or sea traffic will be required

during construction or operation of the proposed

mining project.

Haul roads and other internal roads will be

constructed within mining lease area for raw

material transport. Existing road network will be

used for transporting stone.

1.18 New road, rail, air waterborne or

other transport infrastructure

including new or altered routes

and stations, ports, airports etc?

No No new road, rail, air, waterborne or other

transport infrastructure including new or altered

routes and stations, ports, airports, etc will be

required.

1.19 Closure or diversion of existing

transport routes or infrastructure

leading to changes in traffic

movements?

No Closure or diversion of existing transport routes or

infrastructure leading to changes in traffic

movements is not involved.

1.20 New or diverted transmission

lines or pipelines?

No No new or diverted transmission lines or pipelines

are proposed.

1.21 Impoundment, damming,

culverting, realignment or other

changes to the hydrology of

watercourses or aquifers?

No There will be no impoundment, damming,

culverting, realignment or other changes to the

hydrology of watercourses or aquifers.

1.22 Stream crossings? No There is no stream crossing through the mine site.

1.23 Abstraction or transfers of water

from ground or surface waters?

Yes The total water requirement for mining project is

estimated 100 KLD. Water for dust suppression,

Green belt, and drinking water will be used from

nearby villages. C.G.W.B has given us the permission

for that.

1.24 Changes in water bodies or the No There is no surface water body within in the Lease

Page 7: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 7

land surface affecting drainage or

run-off?

area. There will be no change in water bodies during

mining operation. There will be a permanent change

of land use of mining activity area. The mining

activity will leave excavated area, which will be

converted into reservoir.

Dense green belt/plantation will be developed along

the lease boundary, near mine office etc.

1.25 Transport of personnel or

materials for construction,

operation or decommissioning?

Yes Mine workers are residing in nearby area hence

does not require any transport. Materials will be

transported by trucks.

1.26 Long-term dismantling or

decommissioning or restoration

works?

No No long-term dismantling or decommissioning or

restoration works is required.

1.27 Ongoing activity during

decommissioning which could

have an impact on the

environment?

No Not applicable, as no such activities are involved.

1.28 Influx of people to an area in

either temporarily or

permanently?

Yes Manpower will be sourced from nearby villages so

there will be influx of people to the area.

1.29 Introduction of alien species? No No, there is no possible source for transportation of

alien species by transport of mineral as the stone

will be transported to the nearby areas.

1.30 Loss of native species or genetic

diversity?

No There will be no loss of native species or genetic

diversity.

1.31 Any other actions? No Not Applicable

Page 8: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 8

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

S.

No.

Information/checklist

confirmation

Yes/No Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

2.1 Land especially undeveloped or

agricultural land (ha)

Yes Total Mining area is 55.50 ha. It is total Govt. Land.

The mining area is completely barren.

2.2 Water (expected source &

competing users) unit: KLD

Yes The total water requirement for mining project is

estimated 100 KLD. Water for dust suppression,

Green belt, will be sourced from nearby villages.

C.G.W.B has given us the permission for the same.

2.3 Minerals (MT) Yes 15 MTPA Stone along with Associated Minor

minerals shall be mined and used for Construction

material.

2.4 Construction material – stone,

aggregates, sand/soil (expected

source – MT)

Yes Construction material as available locally will be

used for construction of mine office, workshop &

haul roads.

2.5 Forests and timber (source – MT) No No forests and timber is required.

2.6 Energy including electricity and

fuels (source, competing users)

Unit: fuel (MT), energy (MW)

Yes Electricity will be obtained from Haryana

Electricity Board.

Fuel: Diesel will be used every day for machinery.

2.7 Any other natural resources (use

appropriate standard units)

No Not applicable, as there will not be use of any other

natural resources.

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived

risks to human health.

S. No. Information/Checklist

confirmation

Yes

/No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

3.1 Use of substances or materials,

which are hazardous (as per

MSIHC rules) to human health or

the environment (flora, fauna, and

water supplies)

No Explosives, used for blasting, will be stored in

mines magazine. Safety will be ensured and

eco-friendly blasting will be practiced, the

entire blasting operations will be carried out as

per provisions of MMR, 1961 and Indian

Explosives Act and Rules. MSDS will be

Page 9: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 9

maintained and followed to avoid any error.

3.2 Changes in occurrence of disease

or affect disease vectors (e.g.

insect or water borne diseases)

No No effect envisaged due to this mining project.

Services of a Mobile dispensary will be

provided to locals of project surrounding area

to improve their health status.

3.3 Affect the welfare of people e.g. by

changing living conditions?

Yes There will be positive impact of the project in

the area as follows :

Providing better employment opportunities,

both direct and indirect, this will enhance

the living standards and economic status of

the local people.

Communication and transport facilities will

be improved

Education facilities will be improved.

Community Health care programmes will

provide better health and medical facilities

not only to the employees but also to

villagers.

3.4 Vulnerable groups of people who

could be affected by the project

e.g. hospital patients, children, the

elderly etc.,

No No effect envisaged.

3.5 Any other causes No None.

4. Production of solid wastes during construction or operation or decommissioning

(MT/month)

S. No. Information/Checklist

confirmation

Yes

/No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

4.1 Spoil, overburden or mine wastes No No OB Waste will be generated.

Top soil where ever available will be carefully

removed and stored (with vegetation cover) and

simultaneously used for green belt

development.

4.2 Municipal waste (domestic and or

commercial wastes)

Yes Only domestic waste will be generated from the

mines office which will be properly disposed off.

Page 10: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 10

4.3 Hazardous wastes (as per

Hazardous Waste Management

Rules)

Yes Small quantities of oil and grease will be

generated, which will be disposed off via

authorized recyclers.

4.4 Other industrial process wastes No There will be no other industrial process waste

generation.

4.5 Surplus product No There will not be any surplus product.

4.6 Sewage sludge or other sludge

from effluent treatment

No Domestic waste water generated from mine

office will be disposed in soak pits via septic

tank.

4.7 Construction or demolition wastes No No construction waste will be generated.

4.8 Redundant machinery/ equipment No There will be no redundant machinery or

equipment.

4.9 Contaminated soils or other

materials

No There is no contamination of soil or any other

materials.

4.10 Agricultural wastes No There will not be any agricultural wastes

4.11 Other solid wastes Yes There will be very minor scrap from stores/

Office during the operational phase of the mine.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S.

No.

Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

5.1 Emissions from combustion of

fossil fuels from stationary or

mobile sources

Yes The emission of SO2 & NO2 may be due to use of

diesel operated surface miners/Loader/dumper

etc. Vehicular emission will be kept under

control by proper maintenance and by regular

monitoring of fuel and oil consumption of Heavy

Earth Moving equipment as well as auxiliary

equipments. Every effort will be made to

minimize emissions.

5.2 Emissions from production

process

Yes There will be fugitive and gaseous emissions

from HEMMs during excavation of stone.

5.3 Emissions from materials handling

including storage or transport

Yes The loading of material and transportation will

emit some amount of pollutants. Proper

maintenance of HEMMs will help reduce

emissions. The fugitive emission on haul road

Page 11: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 11

will be suppressed by water spray.

5.4 Emissions from construction

activity including plant &

equipment

Yes Fugitive dust emissions may be generated due

to vehicular movement. These emissions will be

temporary and will be controlled.

5.5 Dust or odours from handling of

materials including construction

materials, sewage and waste

Yes Dust which is generated during excavation,

loading/unloading & transportation will be

suppressed by the sprinkling the water.

5.6 Emission from incineration of

waste

No Incineration activity is not involved in the

project.

5.7 Emissions from burning of waste

in open air (e.g. slash

materials, construction debris)

No There is no burning of waste in open air.

5.8 Emissions from any other sources No There will be no emissions from any other

sources.

6. Generation of Noise and Vibration and Emissions of Light and heat:

S. No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data with source of

information data

6.1 From operation of equipment e.g.

engines, ventilation plant,

crushers.

Yes There is likelihood of some increase in noise due

to operation of machinery like surface miner,

hydraulic excavators, and loaders at source.

However persons working just close to machine

will be provided with Ear plugs / Ear muffs for

further protection. There will not be continuous

exposure of operators to high noise areas.

All the new HEMMs will be equipped with noise

insulated cabins and all the machines having

acoustic enclosures will only be procured.

Greenbelt will be developed which minimizes

noise level.

6.2 From industrial or similar process No There is no other industrial process.

6.3 From construction or demolition Yes The noise generated from construction will be

temporary in nature.

6.4 From blasting or pilling Yes Generation of Noise and Vibration will be there

Page 12: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 12

due to drilling & blasting. This will be minimized

by taking precautionary measures such as proper

blasting method, selection of explosive and

quantity of explosive etc.

Green belt all around the mining area serves as

noise barrier.

Workers working in close vicinity of machines

will be provided with personal protective

equipments, etc.

6.5 From construction or operational

traffic

Yes During vehicular movement, the noise is likely to

be high, which is intermittent process. All the

HEMMs are equipped with noise insulated cabins

with very less noise inside the cabin having

acoustic enclosures be procured.

Noise during construction activities will be

temporary & will be resolved.

6.6 From lighting or cooling systems No Not envisaged

6.7 From any other sources No Not envisaged

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea:

S. No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

7.1 From handling, storage, use

or spillage of hazardous

materials

No No use/handling of hazardous material will take

place except periodical oil change, which will be

handled in closed containers. Spillage of

Oil/Grease during maintenance of heavy

vehicles will be controlled by using collection

tray etc. Care will be taken during its use for

lubrication of equipment, so that nothing falls

on ground to contaminate soil. Equipment will

be kept well maintained to keep them leakage

free. The used oil and grease will be sold to

authorized vendors.

7.2 From discharge of sewage or

other effluents to water or the

Yes Domestic waste water generated from mine

office will be disposed in soak pits via septic

Page 13: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 13

land (expected mode and place of

discharge).

tank.

7.3 By deposition of pollutants

emitted to air into the land or

into water.

No No deposition of pollutants emitted to air, into

the land or into water will take place; as the

emissions are limited to the site itself which will

be mitigated by regular water sprinkling for

dust suppression.

Regular/periodical Ambient Air Quality

Monitoring will be carried out.

7.4 From any other sources. No Not envisaged

7.5 Is there a risk of long term build

up of pollutants in the

environment from these

sources?

No Risk of long term build up of pollutants in the

environment from these sources is not

envisaged.

8. Risk of accidents during construction or operation of the Project, which could affect

human health or the environment

S.

No.

Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

8.1 From explosions, spillages, fires etc

from storage, handling, use or

production of hazardous

substances

No Possibility of accident on account of explosion,

spillages, fire or hazardous substances etc is

very less or negligible. Proper maintenance,

operation and leak proof condition of machinery

eliminates possibilities of fire.

However fire extinguishers will be provided

near workshop, mines office in each vehicles etc.

and all persons shall be properly trained to

quench the fire at source itself. No other major

risks will be involved, as mines will be working

following provisions of mines act, rules and

regulations and under supervision of qualified

persons.

8.2 From any other causes No Not envisaged

8.3 Could the project be affected by

natural disasters causing

environmental damage (e.g. floods,

No The site is generally plain without many

undulations and it falls in Zone-III as per IS:

1893 (Part-1) 2002.

Page 14: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 14

earthquakes, landslides, cloudburst

etc)?

9. Factors which should be considered (such as consequential development) which could lead

to environmental effects or the potential for cumulative impacts with other existing or

planned activities in the locality

S.

No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

9.1 Lead to development of supporting

facilities, ancillary development or

development stimulated by the

project which could have

impact on the environment e.g.:

Supporting infrastructure

(roads, power supply, waste

or waste water treatment,

etc.)

Housing development

Extractive industries

Supply industries

Other

Yes Employment opportunities will increase due to

the requirement of workers for the proposed

project. Local people will be preferred for

employment. This will contribute in raising the

socio-economic status and standard of living of

the nearby villagers.

Greenery of the surrounding area will be

enhanced which will further add the area

aesthetic beauty to the area.

This will contribute in raising the socio-

economic status and standard of living of the

nearby villagers

9.2 Lead to after-use of the site, which

could have an impact on the

environment

Yes The after use of site planned would be helpful to

the society, owing to better greenery and

development of water reservoir supporting the

surrounding localities.

9.3 Set a precedent for later

developments

Yes A better after-use scenario which is likely to

increase aesthetic beauty of area in addition to

benefit of better water regime & greenery would

set a precedence for subsequent entrepreneurs

who venture such projects.

9.4 Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects

No

No cumulative effects as there is no other

existing or planned projects.

Page 15: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 15

Page 16: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 16

(III) Environmental Sensitivity

S. No. Areas

Name/

Identity

Aerial distance (within 15 km.)

Proposed project location boundary

1 Areas protected under international

conventions, national or local

legislation for their ecological,

landscape, cultural or other related

value

None No National Park, Wild Life Sanctuary or

any other protected area under

international conventions, national or

local legislation.

2. Areas which are important or

sensitive for ecological reasons -

Wetlands, watercourses or other

water bodies, coastal zone,

biospheres, mountains, forests

Water bodies Some small seasonal village pond exists.

3 Areas used by protected, important

or sensitive species of flora or fauna

for breeding, nesting, foraging,

resting, over wintering, migration

None No such major area is located within the

15 km radius of the mining lease area.

4 Inland, coastal, marine or

underground waters.

None

5 State, National boundaries. None Nil

6 Routes or facilities used by the

public for access to recreation or

other tourist, pilgrim areas.

None Nil

7 Defense installations. None Nil

8 Densely populated or built-up area. Tosham (~6.0 km in ESE direction)

9 Areas occupied by sensitive man-

made land uses (hospitals, schools,

places of worship, community

facilities).

Yes Well established educational, medical &

other facilities exist in nearby area.

10 Areas containing important, high

quality or scarce resources

(Ground water resources, surface

resources, forestry, agriculture,

fisheries, tourism, minerals).

No No such hot spots or scarce resources in

the project vicinity

11 Areas already subjected to pollution None No such areas in the project vicinity.

Page 17: Form - I / Appendix Ienvironmentclearance.nic.in/writereaddata/... · A t Village Dadam, Tehsil Tosham , District Bhiwani (Haryana) Form - I / Appendix I M/s. Sunder Marketing Associates

Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA

At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)

Form - I / Appendix – I

M/s. Sunder Marketing Associates 17

S. No. Areas

Name/

Identity

Aerial distance (within 15 km.)

Proposed project location boundary

or environmental damage. (Those

where existing legal environmental

standards are exceeded).

12 Areas susceptible to natural hazard

which could cause the project to

present environmental problems

(Earthquakes, subsidence,

landslides, erosion, flooding or

extreme or adverse climatic

conditions).

None Nil

(IV) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES

As per EIA Notification dated 14th September, 2006 amended as on date; following are proposed

Terms of Reference (ToR) for preparation of Environmental Impact Assessment Report and

Environmental Management Plan:-

1. Introduction

2. Project description

3. Description of the environment

4. Anticipated environmental impacts & mitigation measures-

5. Analysis of alternatives (technology & site)

6. Environmental monitoring program

7. Additional studies

8. Project benefits

9. Environmental cost benefit analysis, if any.

10. Environmental management plan

11. Summary & conclusion.