Forest hill station open house
-
Upload
crosstown-to -
Category
Government & Nonprofit
-
view
1.517 -
download
3
Transcript of Forest hill station open house
EGLINTON CROSSTOWN LRT
Forest Hill Station Open House
October 20, 2016
INFORMATION IS CURRENT AS OF
October 20, 2016
AND SUBJECT TO CHANGE
Safety First – Our #1 Priority
• Always have a site specific safety plan and site specific emergency plan.• Ensure pre-work hazard assessments are complete and understood.• Ensure job hazards analyses are complete and understood. • Identify and report unsafe behaviour and coach each other to make improvements.• Do everything possible to protect themselves, co-workers and members of the
public• Stop work if the safety of themselves, co-workers and members of the public
cannot be assured• Be prepared and equipped to work safely.
We train and direct staff to:
Construction of the Eglinton Crosstown LRT LineBackground
• In September 2008, Metrolinx launched a regional transportation plan – a 25-year, $50 billion plan -- to coordinate and integrate transportation and transit in the Greater Toronto Area
• In 2010, City of Toronto approved the project to build the Eglinton Crosstown from Weston Road in the west to Kennedy Station in the east.
• Following a competitive process, Crosslinx Transit Solutions (CTS) was awarded a contract in July 2015 to design, build, finance, and maintain the Eglinton Crosstown Light Rail Transit (LRT).
Benefits of P3s:
• The Crosstown is being delivered using a public private partnership model called Alternative Financing and Procurement (AFP).
• It was procured as one design-build-finance-maintain project to minimize integration risk – historically, a factor for project cost overruns under traditional models.
• Under the AFP model, CTS assumes most project risks, including: design, project management and sub-
contractor coordination increases in construction material prices
and labour costs schedule and project completion delays maintenance and lifecycle replacement of
materials within the stations and stops, rails, control systems, and vehicles
Project Players Roles
What are we building – a new modern LRT
• 15 underground stations and 10 surface stops• A maintenance and storage facility• A 19-kilometre route separated from regular traffic• Communications system • Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station
14
Design Excellence Principles & Objectives
15
Design Approach: Design from City to Object
S i m p l i c i t y I c o n o g r a p h y Transparency Ur b a n i t y
Simplicity and elegance of the design solution at all scales, from the city to the object;
Iconography of the architectural elements to create a unique and highly recognizable signature on Eglinton Avenue, from the slanted portal celebrating kinetic movement, to the profiled wing delineating shelters and waiting areas;Transparency of the entrances and through the station to magnify the presence of natural light, to enact as a way-finding strategy and to uplift the passenger’s experience;
Urbanity of the signature layers from landscape to architecture, to underline the genius loci and contextualize the stations and stops within the civic scale of the avenue.
Design Concepts
• Passenger First
Passenger First Light-filled Stations
Simplicity of Circulation
17
Clarity and Simplicity of Architectural Expression
Street Level – Contextual & Inviting
An International Signature for Toronto Entrance – Bright & Secure
Concourse – Simple & Pristine
Concourse – Transparent & Open
Platform – Spacious & Animated
Crosstown Design Approach
Features• About half of the 19 km line is
tunneled• Stations and stops are about 0.6 km
apart• Features will include:
• time arrival information• safe access for people walking
and biking to the station • clear route maps, seating, bike
parking
Design ApproachComply with nine design principles developed by City of Toronto and Metrolinx.• Provide a legacy for generations to come. • Have natural lighting during the day and well-lit
entrances at night.• Have safe, clean, intuitive wayfinding at
all the stations and stops.• Put passengers first.• Provide visible entrances, bicycle facilities and
sustainable practices to ensure all stations comply with Toronto Green Standard Tier.
• Landscaped entrances, including planters with trees and ornamental grasses.
• Public plazas and retail components at some stations.
• Clean and minimalist space at platform level.• Accessible to passengers with disabilities,
strollers, and bicycles.
Accessibility for All
Station and stops are designed to support ease of access and use by persons with differing levels of mobility, sight, hearing, sensory and cognitive abilities. The project site and facilities are designed to be universally accessible including satisfying the requirements of Accessibility for Ontarians with Disabilities Act (AODA) and applicable City of Toronto Guidelines, Ontario Building Code (OBC) and Canadian Standards Association (CSA) Standards. Some of these features include:
• Barrier‐free path from the entrance level to the station platform level• Tactile warning strips and tactile walking surface indicators• Signage system with tactile indicators • Passenger Assistance Intercom (PAI)• Low floor Light Rail Vehicle (LRV) with designated wheelchair locations• Nominal gap from platform edge to LRV entry• Automated visual and audible stop announcements • On-street and off-street paratransit passenger pick-up/drop-off
• The underground stations run between Weston Road in the west to Laird Street in the east.
• Construction began at Keelesdale station, located at Keele Street /Trethewey Drive and Eglinton Avenue in March 2016.
• Installing support of excavation is the first step in constructing an underground station.
• All underground stations will be brand new, including the three LRT interchange stations connecting to
other transit modes.• Most of the underground stations will be
in construction by the end of 2016.
What to expect in 2016 – Start of Stations Construction
How we’re building: Cut-and-Cover Stations
Forest Hill
Locations: Keelesdale (Keele), Caledonia, Fairbank (Dufferin), Forest Hill (Bathurst), Chaplin, Mount Pleasant, Leaside (Bayview), Science Centre
How we’re building: Mined Stations
Avenue
tLocations: Oakwood, Avenue, Leaside (part), Laird
• There are three interchange stations.
• Interchange stations will allow transit riders to connect to other transit modes, such as TTC, GO and the UP Express.
• The three interchange stations will be built with the ‘Cut and Cover’ method.
How we’re building – Interchange Stations
Subway Station Longitudinal Section
Locations: Cedarvale (Allen), Eglinton (Yonge), Kennedy
How we’re building Forest Hill Station - Construction OverviewDistinct phases of construction:• Preparatory works• Utility relocations• Support of excavation (shoring)• Road restoration• Deep excavation• Underground station construction• Track work and systems installation• Station structure construction• Traction power system• Signalling system• Testing and commissioning
• A modified version of the cut-and-cover method,
whereby following support of excavation, a large
concrete roof slab is constructed and placed over
top of the excavated area, the roadway is restored
and work continues safely below ground
• The roof slab is used to support utilities and the
roadway
• Benefits include reduction in road disruption
(compared to tradition method), increased utility
stability and improved safety and working
conditions
How we’re building Forest Hill Station – Station Construction
Reinstate Roadway
• A concrete roof slab will be
constructed over top of the
excavated area, utilities will be
buried, and the roadway will be
reinstated above the roof slab.
Excavation
• Once the roadway is reinstated,
crews will work safely beneath the
roadway to construct the station box,
build the platform and install rail
infrastructure.
Architectural & Building Work
• Construction of the station entrance
structures will begin in 2018.
How we’re building Forest Hill Station – Station Construction (cont’d)
Forest Hill Station Map
Main Entrance
Secondary Entrance
Station Box
Forest Hill Station Main Entrance
Forest Hill Station Secondary Entrance
Forest Hill Station Aerial View
Forest Hill Station Unique Design Concepts
• Fully glazed glass main station entrance
• Solid cool roofs with high albedo
surfaces, designed to reduce heat island
effect and contribute to energy efficiency
• Outdoor bike canopy with 60 bike
parking spots
• On-street connections to TTC bus routes
• Retail space
Forest Hill Station Tunnel Ventilation System (TVS)
• Designed to extract and control smoke from tunnels and stations in the
event of a fire.
• Controls excessive air velocities and air pressure transients.
• Removes heat and controls air temperature during operations.
• Supplies outdoor air ventilation and facilitates contaminant removal.
• Forest Hill Station TVS is comprised of axial fans, dampers, electrical
equipment, tunnel ventilation panels, supervisory control and data
acquisition (SCADA) interface, and Tunnel Ventilation Fire Command Post.
• Vents are located on top of the secondary station entrance.
Forest Hill Station Construction Lookahead (2016 – 2017)
Fall 2016
• Continue Bell utilities relocation
• Continue installation of geotechnical monitoring instrumentation
• Continue traffic signal relocation and reconfiguration
• Backfilling and compaction of the secondary entrance
• Relocation of overhead hydro utilities and poles
• Relocation of overhead Rogers utilities to an underground duct bank
• Site mobilization and drill rig/crane pad construction
• Support of excavation (shoring) beginning on the south side of Eglinton Avenue West
Winter 2016
• Continue shoring on the south side of Eglinton Avenue West
• Watermain services
Traffic and Pedestrian Changes
• To accommodate the utilities relocation and shoring
construction stages, temporary traffic changes, such as road
closures, lane reductions, turn restrictions, pedestrian
rerouting and bus stop relocations may be in effect
• Additionally, changes to existing traffic conditions, such as
relaxation of turn prohibitions or additional restrictions, may be
enacted in development with local elected officials, traffic
engineers and the local community to accommodate station
construction
Forest Hill Station Construction Stages
Stage Activity Duration Start DateShoring Stage 1
Utilities Relocation, Shoring and Roof Slab 5 months Fall 2016
Shoring Stage 2
Utilities Relocation, Shoring and Roof Slab 3 months Winter 2017
Shoring Stage 3 Shoring and Roof Slab 3 months Summer
2017Shoring Stage 4 Shoring and Roof Slab 3.5 months Fall 2017
Utilities Relocation – Current Staging PlanBegan July 2016
Forest Hill Station – Shoring Stage 1Beginning as early as Fall 2016 (20 weeks)
Forest Hill Station – Shoring Stage 2Beginning as early as Winter 2017 (12 weeks)
Forest Hill Station – Shoring Stage 3Beginning as early as Summer 2017 (12 weeks)
Forest Hill Station – Shoring Stage 4Beginning as early as Fall 2017 (14 weeks)
Summary of Proposed Traffic Changes for Forest Hill Station
Stage Traffic Changes Construction Activities
Approx. Start Date
Approx. Duration
1
• Close Peveril Hill N at Eglinton Ave W
• Restrict all turns at the intersection of Bathurst St and
Eglinton Ave W
• Reduce traffic to one lane in each direction on Bathurst
St and Eglinton Ave W
Utilities
Relocation &
shoring
Fall 2016 20 weeks
2 Continue Stage 1 configurationUtilities
Relocation &
shoring
Winter
201712 weeks
3
Continue Stage 2 configuration, plus:• Restore northbound right turn onto Eglinton Ave W
• Restore eastbound right turn onto Bathurst St
ShoringSummer
201712 weeks
4 Continue Stage 3 configuration Shoring Fall 2017 14 weeks
Summary of Proposed Pedestrian Changes for Forest Hill Station
Stage Pedestrian Changes Construction Activities
Approx. Start Date
Approx. Duration
1
• Restrict the east crosswalk
• Reroute pedestrians south on Peveril Hill N and east to
Bathurst St
Utilities
Relocation and
shoring
Fall 2016 20 weeks
2
Continue Stage 1 configuration, plus:• Restore east crosswalk
• Restrict west crosswalk
Utilities
Relocation and
shoring
Winter
201712 weeks
3
Continue Stage 2 configuration, plus:• Restore west crosswalk
• Restrict east crosswalk
ShoringSummer
201712 weeks
4
Continue Stage 3 configuration, plus:• Restore east crosswalk
• Restrict west crosswalk
Shoring Fall 2017 14 weeks
Proposed Closure of Peveril Hill N
Why?
• To provide a truck entry and egress route
from the work zone during shoring stages 1
and 2
Proposed Mitigation
• Temporary relaxation of the left turn
prohibition from northbound Bathurst Street
onto Dewbourne Avenue (in place)
• Temporary relaxation of the right turn
prohibition from eastbound Eglinton Avenue
West onto Chiltern Hill Road
Duration
• Approximately eight (8) months beginning in
fall 2016
RELAX EXISITING
RIGHT TURN RESTRICTION
RELAX EXISITING
LEFT TURN RESTRICTION
Proposed Restriction of Turns at Eglinton Avenue West and Bathurst StreetWhy?
• Insufficient turn radius due to location of station box
• To prevent traffic congestion during construction stages
1 through 4
Mitigation
• Temporary relaxation of turn prohibitions on nearby
streets to provide alternative travel routes for local traffic
Duration• For approximately 15 months
Summary of Turn Prohibitions to be considered for Temporary Relaxation
Prohibited Movement From To Prohibited
TimeRight turn Eglinton Ave W (WB) Vesta Dr (NB) 7 AM – 6 PM
Right turn Eglinton Ave W (EB) Gardiner Rd (SB) 7 AM – 7 PM
Right turn Eglinton Ave W (EB) Old Forest Hill Rd (SB) 7 AM – 7 PM (everyday)
Left turn Eglinton Ave W (WB) Old Forest Hill Rd (SB) 7 AM – 9 AM
Through traffic Old Forest Hill Rd (SB) @ Eglinton Ave W Peak Hours
Through traffic Old Forest Hill Rd (NB) @ Eglinton Ave W Peak Hours
Left turn Old Forest Hill Rd (NB) Eglinton Ave W (WB) Peak Hours
Left turn Bathurst St (SB) Burton St (EB) All Times
Right turn Ava Rd (WB) Bathurst St (NB) 4 PM – 6 PM
Left turn Bathurst St (NB) Avenal Dr (WB) Peak Hours
Left turn Bathurst St (NB) Dewbourne Ave (WB) Peak Hours
Summary of Turn Prohibitions to be considered for Temporary Relaxation (cont’d)
Prohibited Movement From To Prohibited
TimeRight turn Rosemary Ln (WB) Bathurst St (NB) 4 PM – 6 PM
Right turn Eglinton Ave W (EB) Chiltern Hill Rd (SB) Peak Hours
Right turn Eglinton Ave W (EB) Rostrevor Rd (SB) Peak Hours
Left turn Glen Cedar Rd (NB) Eglinton Ave W (WB) Peak Hours
Left turn Bathurst St (NB) Wembley Rd (WB) Peak Hours
Right turn Bathurst St (SB) Wembley Rd (WB) 7 AM – 9 AM
Left turn Bathurst St (SB) Shallmar Blvd (EB) 7 AM – 9 AM
Left turn Bathurst St (SB) Rosemary Ln (EB) 7 AM – 9 AM
Left turn Bathurst St (SB) Ava Rd (EB) 7 AM – 9 AM
Haul Routes
• During the shoring and deep excavation stages of construction, approximately 30 trucks will haul more than 80 loads of construction material, such as soil and concrete, to-and-from Forest Hill Station per day
• To minimize traffic congestion along Eglinton Avenue, construction vehicles will use a combination of arterial, minor arterial, collector and local roads on a rotating basis to haul loads
• The following roads will be used as haul routes for Forest Hill Station:
• Bathurst Street• Eglinton Avenue West• Spadina Road• Old Forest Hill Road• Ava Road• Chadwick Avenue• Dewbourne Avenue• Gardiner Road
• Hilltop Road• Peveril Hill North• Rosemary Lane• Vesta Drive• Wembley Road
Summary of Streets to be used as Haul Routes for Forest Hill Station
Street Name From ToVesta Drive Ava Rd Bathurst St
Ava Rd Bathurst St Rosemary Ln
Rosemary Ln Bathurst St Dewbourne Ave
Dewbourne Ave Rosemary Ln Bathurst St
Chadwick Ave Spadina Rd Vesta Dr
Gardiner Rd Eglinton Ave W Old Forest Hill Rd
Peveril Hill N Eglinton Ave W Dewbourne Ave
Advanced Signage
• Advanced signage will be placed
along Eglinton Ave W and cross
streets to inform motorists and
pedestrians of traffic changes at the
intersection
• At Forest Hill Station, advanced
signage will be placed as far north as
Wembley Rd, as far south as
Dewbourne Ave, as far east as Old
Forest Hill Rd and as far west as
Chiltern Hill Rd
Bus Stop Relocations
Four (4) TTC bus stops at the four corners of Eglinton Avenue West and Bathurst Street will be relocated throughout various stages of utilities relocation and shoring.
• The TTC bus stop on the southwest corner has been relocated approximately 140 meters to the east.
• The TTC bus stop on the southeast corner will be relocated approximately 90 meters to the north
• The TTC bus stop on the northwest corner will be relocated approximately 70 meters to the north
• The TTC bus stop on the northeast corner will be relocated approximately 50 meters to the east to the next available stop
The stops service the following TTC bus routes:
• 7/307 Bathurst North• 310 Bathurst South• 32/332 Eglinton West
Please look for signage informing passengers of the new temporary stop locations.
TTC Bus Stop Relocation Map
Relocate 50m east to next
stop
Relocated 140m east
Relocate 90m northRelocate 70m
north
TTC Bus Route 33 Detour
• To accommodate construction staging
at Forest Hill Station, TTC bus route #
33 will be detour north on Mayfair
Avenue and west on Shallmar
Boulevard to Bathurst Street
• The approximate duration of the
detour is 15 months, beginning as
early as October 2016
• Changes to traffic calming conditions
on Mayfair Avenue and Shallmar
Boulevard will be implemented
Experience EglintonAdvertising and marketing initiatives, ranging from subway and local newspapers advertisements, to postcards, coupon booklets and flyers all focused on encouraging residents in the neighbourhood to shop locally.
Support for Businesses – Shop Local
Community Benefits
Commit to Social Procurement and Local Investmentto maximize business opportunities along the project corridor.
Visit CTS’ website www.crosslinxtransit.ca for updated postings.
The Eglinton Crosstown LRT is the first time a Community Benefits Framework has been included as part of a major infrastructure project in Ontario.
Partner with Local Workforce Agenciesto recruit candidates from the project corridor and from historically disadvantaged communities.
Work with Subcontractorsto maximize opportunities for apprentices.
Stay in touch
416-782-8118
www.thecrosstown.ca
facebook.com/thecrosstown
twitter.com/crosstownTO
instagram.com/eglinton_crosstown
Crosstown West Office1848 Eglinton Ave W (at Dufferin)
Crosstown East Office660 Eglinton Ave E (at Bayview)