For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
Transcript of For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
1/39
Seoul FLNG Conference, 25 October 2011
Philip Eystein Fjeld
Chief Executive Officer
FLEX LNG
Collin F Visaggio
Chief Financial Officer
InterOil Corporation
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
2/39
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
3/39
InterOils Vision
Papua New GuineaPoised to Join the Ranks of Asian LNG Suppliers
3
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
4/39
InterOil A Trusted PNG Partner That Delivers
InterOil is a domestic company (PNG Only)looking for long-term sustainable economicdevelopment for the nation, InterOil, and thecitizens of PNG.
InterOil considers itself a partner with thecountry, its people, and government.
InterOil acts in good faith, using best efforts forall stakeholders.
4
nter as a proven an a r trac recor .
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
5/39
InterOil Vertically Located and Positioned for Growth
5
Exploration Portfolio3.9 million acres
Midstream Portfolio - Refinery36, 500 bpd capacity
Downstream DomesticDistribution
MidstreamLNG Project
Condensate Stripping ProjectGenerates Early Cash Flow
and Revenue to AllStakeholders
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
6/39
The World Woke Up: A World Record Rate of Over 700 MMCF/D
6
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
7/39
The Resource: 2010 Third Party Resource Estimate of Elk and AntelopeUnderpins a large LNG development with a 5% increase over 2009
As at December 31, 2010 Case
Low(C1)
Best(C2)
High(C3)
Initial Recoverable Sales Gas(Tcf) 6.47 8.59 10.44
Initial Recoverable Condensate (MMBbls) 105.3 128.9 151.4
Initial Recoverable MMBOE 1,183.6 1,560.4 1,891.1
Gross Contingent Resource Estimate for Gas and Condensate as of December 31, 2010
An evaluation of the potentialresources of gas and condensate forthe Elk/Antelope field has been
completed by GLJ PetroleumConsultants Ltd., an independentqualified reserves evaluator, as ofDecember 31, 2010
The estimates presented are inaccordance with the definitions anduidelines in the COGE Handbook
and Canadian NI 51-101
Gas in place increased almost 1TCFfrom 2009 to 2010
C1 enough to produce 8mtpa LNG, and C2 enough to produce 11 mtpa, for 15 years
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
8/39
InterOil Has a Proven Track Record in Papua New Guinea
InterOil was formed in 1997 - Vision to create an integrated energy company
Exploration licenses signed under incentive program - 2003 Elk-1 discovery of Elk fault block 2006
Antelope-1 discovery of Antelope reef 2008 Third-party certified contingent resources estimate 2009 over 3.8 Tcfe ~ 630 mmBOE* Third-party certified contingent resources estimate 2010 over 9.1 Tcfe ~ 1.52 BBOE* Third-party certified contingent resources estimate 2011 over 9.4 Tcfe ~ 1.56 BBOE* Potential for 2.5 Billion BOE
8
Refinery commissioned in 2004, Mechanical completion - 2006
Completed refinery project agreement Secured land rights - harbor rights OPIC Financing
Distribution asset acquisitions to vertically integrate with refinery - 2003/2005 Purchased distribution assets from BP and Shell in PNG
InterOil Gulf LNG Project Current Activity Start-up configuration of:
Condensate stripping plants 3 mtpa land-based, modular LNG plant 2 mtpa fixed floating LNG plant Gas and liquids pipeline to LNG plant and Jetty on the coast Ramp up LNG to 8 mtpa
*
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
9/39
Papua New Guinea is Now Poised to Emergeas a Global LNG Supplier
Two LNG Project Agreements approved bythe PNG Government
InterOil led Gulf LNG Project
5 mtpa start-up capacity
Expansion to 10.8 mtpa
Exxon led PNG LNG Project
9
.
Expansion to ~ 10 mtpa
Largest carbonate reef trend in Asia
World-class exploration potential
Active Highlands area
Strong off-shore Gulf area
A number of new Potential LNG players
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
10/39
World Class Hydrocarbon Province InterOils 3.9 Million Acres
10
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
11/39
Attractive Economics Relative to Asia-Pacific LNG Projects
Natural Gas Supply - InterOil
High productivity reservoir >300 Mmcf/d Antelope flow
tests
Tests indicate 5-6% CO2
InterOil field tested over 20 Bbls/MMcf of condensate
Minimal pre-LNG processing requirements
Favorable Geography
Protected geographic region
Onshore, near coast (115 Km)
Close to largest global LNG market
11
Proposed Infrastructure CSP EPC bids in, Mitsui to optimise financing
Mid-size LNG plant funded by EWC
Fixed-floating FLNG plant funded by Samsung and FLEX LNG
InterOil LNG plant and infrastructure costs well below competitiveproposals
Fiscal Policy 30% flat tax rate
Major project incentives and exemptions available from the State
Government resource project protection
Experienced LNG Management Team
Marathon EGLNG Team Members now at InterOil and affiliates
EG LNG project completed ahead of schedule and under budget
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
12/39
InterOil Gulf LNG Development Map
Upstream Gas ProjectPetroleum Development Licence
Elk and Antelope Fields Elk Antelope fields, - 8.59 tcf Recoverable Sales Gas, and 129 mmbbls
Condensate (2C resource) 7 to 12 wells producing up to 200 -400mmscfpd each (initial capacity) 1 water reinjection well and 1 surveillance well Compression facilities
Condensate Stripping Facilities 12-14 Infield gas gathering pipelines
Fields to CSP wet gas trunk line Condensate stripping plants - up to 1.8 BCF capacity Produced water re-injection pipeline from CSP to fields injection well
Pipeline Licence CondensateCondensate Pipeline ~120km buried 12 3/4 condensate pipeline from CSP to condensate
storage tanks at Gulf 100,000bbl condensate storage tank at the Gulf with plans to add
additional tanks when needed
Development Map
PDL Elk AntelopePDL Elk Antelope
12
Midstream LNG ProjectPipeline License Gas
Dry Gas Pipeline ~120km buried 32 dry gas pipeline from CSP to liquefaction plants at
Gulf and a 12-20 pipeline to floating LNG at jetty export terminalfacilities
Petroleum Processing Facilities Licences
Liquefaction Facilities Liquefaction plants land based and fixed floating of 11 mtpa capacity LNG storage tanks 180,000 m3
Pipeline connecting the LNG storage tanks to the export terminalloading facilities
LNG loading facilities Return pipeline from loading facilities to liquefaction plants and LNG
storage tanks (6000m x 0.5m)Export Terminal and Common Facilities ~6km breakwater, causeway, moorings and jetty Offices, warehouses and accommodation
on ensa e recovery p pe ne rom que ac on p an s o con ensa estorage tanks
Pipeline connecting condensate storage tanks to ship loading facilities Condensate ship loading facilities
PPFL LandPPFL Land
PPFL Fixed FloatingPPFL Fixed Floating
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
13/39
Lessons from EGLNG and Others: US$1.2 Billion in Pre-FIDinvestments to maintain schedule 2014 LNG Start-Up
Ordering up to $100 million of:
Condensate Line Pipe
Processed gas Line Pipe
13
Critical long lead infrastructure
Purchased over $20 million inConstruction Equipment:
Dump Trucks
Bulldozers
Excavators
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
14/39
InterOils Gulf LNG Project Update and Future Milestones
InterOil is moving ahead to reach FID
LNG facilities increased from 2mtpa to 5mtpa withSamsung & FLEX LNG fixed floating proposal,targeting 8mtpa
CSP facilities re-engineered for increased
production volumes are nearing completion & readyfor bid
Pipelines for natural gas and condensate have beendesigned to handle the capacities required for ourtarget LNG volumes
14
LNG with Energy World is almost complete
Continuing LNG pre-investment to lower bidderrisks and secure lower project costs
LNG off-take HOA was signed with Noble Group for1 mtpa for 10 years, in addition to the 300,000tonnes per annum dedicated to the PhilippinesPower Project
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
15/39
InterOils #1 Priority is Achieving CSP and LNG Project FIDs
Making good progress on early development requirements
Increasing local employment, InterOil is already one of the largest employers in PNG
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
16/39
The LNG Plants: EWC LNG & FLEX LNG /Samsung Project Partnerships
On February 2, 2011, InterOil and PACLNG and Energy WorldCorporation completed final documentation for a 3 mtpa plant.
The initial 3 mtpa modular LNG plant is expected to process anestimated 2.25 Tcf of natural gas over 15 years.
On April 11, 2011, InterOil and Pacific LNG Operationsexecuted agreements with FLEX LNG LTD and SamsungHeavy Industries for a floating liquefaction project in PapuaNew Guinea with targeted start of LNG production in 2014.
The FLNG vessel will be moored alongside the jetty and have a
16
. -
LNG per annum.Samsung provides the construction financing and allperformance guarantees for the FLNG vessel
,agreed deductions and premiums, 14.5%of the proceeds from the sale of LNG bythe upstream partners from the FLNGvessel for an initial 15-year period.
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
17/39
InterOil Engages Advisors on Sale of Interest in Resource and Exploration
InterOil has retained Morgan Stanley, Macquarie and UBS as jointfinancial advisors to assist InterOil with its evaluation ofproposals from potential strategic partners in the liquefied naturalgas project
Obtain an internationally recognized LNG operating partner
Accelerate the LNG capacity to 7.6 mtpa or more
Partial sale of an interest in the Elk and Antelope fields
Possible LNG off-take
Possible participation in InterOils exploration tenements in Papua
17
The timing is right for engaging in partnering process
Strengthening Asian LNG market, >$17/mcf spot prices
Company has received proposals from internationally recognizedLNG operators
Increased interest in exploration and investment in PNG
Third annual Elk and Antelope resourse estimate supports LNGproject
Substantial progress in LNG project engineering and design
Opportunity to book proven reserves on declaration of FID
Spudding of Triceratops 2 well this quarter.
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
18/39
In Summary
Papua New Guinea was an under-discovered frontier, with world class assetsstrategically located on the doorstep of LNG Asia: Ignored and bushed aside bymost majors
The world awoke to PNGs LNG Value as Spot Prices near US$19/mmbtu
Quality gas for the Asian LNG Buyers, with diversification from Qatar and Australia
Vast exploration and resources to ensure reserves for all stakeholders
Modular LNG can build 20 to 30 mtpa of LNG capacity in PNG
nd
18
,
InterOil has a significant F&D advantage, and early cashflow with Modular and FLNGdevelopment
15 years in PNG with the best track record in PNG Exploration
The only PNG refinery operator providing operator advantages for LNG
Bottom line: PNG passed the turning point for LNG; and is now on the path to beinga Major Supplier of clean energy as a portfolio including FLNG with Korea
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
19/39
InterOil: Working with all stakeholders and the future of Papua New
Guinea
19
An Energy Company With Innovated LNGDevelopment and Loyalty to PNG
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
20/39
Gulf LNG ProjectThe Worlds First FLNG Project
London, 30th July 20109th May 2011
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
21/39
FLEX LNG Ltd Brief introduction
FLEX LNG is a pure-play developer of floating liquefaction projects
Lump-sum, turnkey EPCIC for entire unit (hull and topsides)
Long-standing partnership with Samsung Heavy Industries
Pure FLNG Provider
Firm orders
Strong SHI support
21
Strong shareholder base (K-Line and InterOil among the largest
shareholders)
Offering an advanced and mature FLNG design
LNG Producer offers great adaptability for different applications
Gulf LNG project being developed together with InterOil Corp. andpartners for an at-shore FLNG project in Papua New Guinea
Strong shareholder base
Mature FLNG concept
Large adaptability
Delivery in 2014
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
22/39
Gulf LNG Project FLNG Scope and Interfaces
Samsung Heavy Industries
FLNG FEED for Gulf LNG Project
FLNG vs Onshore Development Costs
Summary
22
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
23/39
Gulf LNG Project- FLEX LNG interfaces and battery limits
FLEX LNG Scope
23
Includes the LNG FPSO + LNGoffloading-arms.
Excludes breakwater, FSU, LNGC
Battery limits:-Feed gas loading arms-LNG jettyhead manifold-Mooring lines & fender dolphins
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
24/39
Main Particulars LNG FPSO Gulf LNG Project
Main particulars (preliminary)Length overall (approx) 276 m
Breadth, moulded (approx) 50.0 m
Depth to upper deck, moulded (approx) 32 m
Full load draught (approx) 13 m
LNG Storage Capacity (approx) 170 000 m3
Condensate Storage Capacity (approx) 5 000 m3
LNG Production Capacity (approx) 2 mtpa
24
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
25/39
Offshore Marine Infrastructure
The offshore marine infrastructure willbe located 6-7 km from the shoreline inapproximately 15 m water depth
The offshore marine infrastructure willconsist of the following:
A breakwater
A single LNG FPSO jetty berth consistingof a single jetty head, and anarrangement of mooring dolphins, fenderdolphins and a HP feed gas transfer
system A dual berth for the LNG offtake vessel
and a Floating Storage Unit comprising ofa dual jetty head and an arrangement ofmooring dolphins, fender dolphins andLNG loading arms
Tug berth
25
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
26/39
LNG FPSO Mooring to Jetty- Top view and side view
The LNG FPSO mooring system will bedesigned according to offshore rules -DNV-OS-E301 Position Mooring
The mooring system is to be designedfor the site specific 100 year returnwind, wave, current conditions(resulting wave and current conditionsbehind the breakwater)
Top View
26
The offshore design philosophyrequires redundancy in the mooringlines and fenders at the 100 yearreturn metocean conditions
The mooring arrangement will consist
of between 18 to 20 mooring linesdeployed from the LNG FPSO tomooring dolphins
Side View
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
27/39
Ship to Jetty LNG and Gas Transfer
Four 16 marine loading arms will beinstalled on the LNG FPSO midships
Two loading arms will be dedicated forLNG, one loading arm will be a hybrid arm
(capable of either LNG or vapour returntransfer) and one will be dedicated forvapour return
The total LNG transfer flowrate will be10,000 m3/hr
Gas transfer from the jetty head to the LNGPwill be performed by CNG gas loading arms
This method of CNG transfer is proven froma number of operating jetty moored
FSRU/Gas Port projects ie Pecem, GuanabaraBay (Brazil), Bahai Blanca (Argentina),Teeside (UK), Mina Al-Ahmadi (Kuwait)
A single CNG loading can provide a gasflowrate equivalent to the maximum LNG
27
Production rate (310 mscfd) at 65 barg.
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
28/39
Gulf LNG Project FLNG Scope and Interfaces
Samsung Heavy Industries
FLNG FEED for Gulf LNG Project
FLNG vs Onshore Development Costs
Summary
28
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
29/39
Benefits of Constructing in a Controlled Environment- SHI is arguably the best qualified yard to construct an LNG FPSO
The FLNG unit is constructed in a highly efficient shipyard, utilizing existingproduction facilities and infrastructire. This results in better control overfactors such as:
Samsung Marine Samsung Offshore
Construction Schedule -known workshop capacity / production rates
Quality Control -constructed in a clean, sheltered environment
HSE Performance -mainly using the yards regular workforce
CAPEX -benefits from existing, highly efficient infrastructure
29
FLEX LNG Producer
scope
Hull and Marine
systems
Topsides and
Integration
Production Capacity 5,400,000 GT/yr 160,000 mt/yr
Products
Crude Oil Tankers,Container Vessels,Cruiser & Ferries,
Gas Carriers(LNG,LPG),FPSO, Drill ships, etc.
Offshore Platforms,Drill ship, FPSO, FLNGTopsides,TLP, Semi Rig,
Material HandlingEquipment,Desalination Plant
Production (2009) 61 Vessels 12 Offshore Units
Samsung Heavy Industries, Geoje - Korea
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
30/39
EPCIC Contract With Samsung Heavy Industries- SHI takes the single-point responsibility for the entire LNG FPSO
Contract Structure
Single, lump-sum, turnkey EPCIC
Hull and Topsides aligned under Umbrella contract
Final lump-sum conversion after field-specific FEEDPerformance Guarantees and LDs
Production capacity
Fuel efficiency
Plant reliability
Defect rectification liability
Contract Particulars
30
Technology risk mitigation
Minimise risk for cost overruns
Minimise risk for delays
Minimise integration risks
Favourable performance guarantees & LDs
Engineering flexibility to adapt the design
Optimised to Satisfy Lenders & LNG Offtaker
Interests/Requirements Contract structure (i.e. single, lump-sum, turnkey)
Risk allocation (Cost, Schedule, Performance, Integration)
Alignment of interests Owner & Contractor
Project Benefits: Favourable Risk Profile and Risk Allocation
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
31/39
Gulf LNG Project FLNG Scope and Interfaces
Samsung Heavy Industries
FLNG FEED for Gulf LNG Project
FLNG vs Onshore Development Costs
Summary
31
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
32/39
Gulf LNG FEED Contract
FEED period and resources
May 2011 Nov 2011
Currently more than 150 engineers mobilised to complete FEED for Gulf LNG project
Main objectives Adapt the generic hull and topside design to match the field-specific requirements of the Gulf
LNG project
Provide a sound basis for lump sum based execution contracts (EPCIC contract and SBC)
Prepare to start EPCIC works immediately following Final Investment Decision in December
Hull FEED scope is executed by SHI shipbuilding division, Geoje, S. Korea
Subcontractor IHI undertaking SPB tank design in Japan
Topside FEED scope is subcontracted to WorleyParsons (WP) and is carried out atWPs office in London
WP has teamed up with Kanfa Aragon, Costain Group, and NLI Engineering, which were allinvolved in the development of the generic design
SHI is present at the WP office with a resident engineering team to control the FEED works
32
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
33/39
FLEX LNG
Samsung Heavy Industries
Project Execution- Contractor structure
Lump sum turn key contract
Overall project mgm. and interface mgm.
FLEX LNG technical and commercial team manages SHI- Provide design basis and project specifications- Interface management towards InterOil (jetty, feed gas,etc.)
Offshore Division
Topside EPCTopside & Hull IntegrationTopside Commissioning
Shipbuilding Division
Hull EPCHull CommissioningGas & Sea Trials
33
Engineering & ProcurementSubcontrractor
SHI resident engineering team to manage subcontractor
Subcontractor to be nominatedOption: WorleyParsons
SHIs specialised organisations & yard,Geoje, S. Korea
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
34/39
Gulf LNG Project FLNG Scope and Interfaces
Samsung Heavy Industries
FLNG FEED for Gulf LNG ProjectFLNG vs Onshore Development Costs
Summary
34
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
35/39
The Benefits of the FLNG are NumerousLow cost, early LNG, construction risk mitigation, and flexibility
Work closely with the yard to ensure constructability of design
-
Maximize LNG production capacity within a standard LNG hull-size
MinimizeCAPEX
Modularisation
Maximise use of proven technology and existing equipment ranges.Simplify the design and complexity
Select inherently safe and robust technologies. Design for safety
Minimize
projectexecutionschedule
Minimizetechnology
andoperational
risks
35
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
36/39
LNG Projects Are More Costly Than Ever to Develop- FLNG reduces CAPEX and has significant schedule advantages
CAPEX/ton of installed liquefactioncapacity has during the last decademade a permanent shift from anaverage figure below 500 USD/ton toa typical range of range of 1500
3000 USD/ton
The IHS CERA Upstream Capital CostsIndex (UCCI) shows more than adoublin of costs in the oil and as
Onshore LNG Development Costs Continue toIncrease
210
230
210
202
201 207
120
140
160
180
200
220
240
UCCIInd
ex
industry. However, due to the
uniqueness often attributed todeveloping LNG projects, current LNGdevelopment costs exceed theaverage for the oil and gas industry
Traditional onshore liquefaction
projects continue to overshoot onschedule and cost
36
Source: IHS Cambridge Energy Research Associates (IHS CERA)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 2 4 6 8 10 12 14 16
USD/tonliqu
efaction
capacity
Annual LNG liquefaction capacity (mtpa)
Source: FLEX LNG, Tri-Zen, Industry Reports
FLEX LNG(2014)
ALNG(Trinidad 2003)
Gorgon LNG(late 2014)
Pluto LNG(2011)
Angola(late 2012)
PNG LNG(2014)
QCLNG(2014)
GLNG(2014)
Nov
2005
May
2006
Nov
2006
May
2007
Nov
2007
May
2008
Nov
2008
May
2009
Nov
2009
May
2010
Nov
2010
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
37/39
Gulf LNG Project FLNG Scope and Interfaces
Samsung Heavy Industries
FLNG FEED for Gulf LNG ProjectFLNG vs Onshore Development Costs
Summary
37
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
38/39
FLNG is Revolutionising the LNG Industry.... and combined with the Gulf LNG Project offers an unique value proposition for PNG
LNG FPSOs offer compelling arguments.....
Lead time less than 50% of a traditional liquefaction project
Unit CAPEX of less than 50% of cost of traditional onshore liquefaction capacity
Strategic and commercial independence
Increased revenue/taxation for host governments compared to traditionalonshore developments
Considerably reduced environmental impact compared to a traditional onshoredevelopment
.....and as the first FLNG units are deployed the industry will see thefollowing changes:
LNG supply projects can be developed in 2-3 years
LNG supply projects will appear in locations unimaginable today (i.e. liquefyingpipeline gas supplied from existing grid)
Onshore liquefaction projects will have to innovate and become more cost
effective to remain competitive Traditional end-users of LNG will integrate upstream and take control over their
own LNG supply destiny
Companies with no previous affiliation to the LNG industry will becomesubstantial LNG suppliers
38
-
8/3/2019 For Web FLEX LNG and InterOil Presentation at Seoul FLNG Conference 25 October 2011
39/39
Questions?
Collin F Visaggio
Chief Financial Officer
InterOil Corporation
Philip Eystein Fjeld
Chief Executive Officer
FLEX LNG
39