FOR USER MANUAL - Perihal MIDA Declaration Mechanism... · Page 3 SPM 1of 17 / 2014 INTRODUCTION...
Transcript of FOR USER MANUAL - Perihal MIDA Declaration Mechanism... · Page 3 SPM 1of 17 / 2014 INTRODUCTION...
MALAYSIAN INVESTMENT DEVELOPMENT AUTHORITY
DIGITAL CERTIFICATE ONLINE APPLICATION
APPLICATION FOR
Self-Declaration Mechanism for Import Duty and/or Sales Tax Exemption on Machinery, Equipment, Spare Parts,
and Consumables Through the Customs Duties (Exemption)
Order 2013 and Sales Tax (Exemption) Order 2013
FOR
Manufacturers in the Principal Custom Area
SPM 1/2014
USER MANUAL
May 2014
TABLE OF CONTENTS CHAPTER B-1 INTRODUCTION............................................................................................................. 3 B-1-1 Introduction about Web Submission Module .................................................................................. 3 B-1-2 Manufacturers in the Principal Custom Area key areas of the exemptions................................... 3 CHAPTER B-2 COMMON FUNCTIONS AND DEFINITIONS................................................................... 4 CHAPTER B-3 COMPANY PARTICULARS.................................................................................................. 5 B-3-1 Introduction ........................................................................................................................................ 5 B-3-2 Action to Take .................................................................................................................................... 5 CHAPTER B-4 FACTORY LOCATION........................................................................................................ 6 B-4-1 Introduction ..................................................................................................................................... 6 B-4-2 Action to Take ............................................................................................................................... 6 CHAPTER B-5 PROJECT COST………............................................................................................. 8 B-5-1 Introduction .................................................................................................................................. 8 B-5-2 Action to Take ................................................................................................................................ 8 CHAPTER B-6 FINISHED PRODUCTS..................................................................................................... 9 B-6-1 Introduction ...................................................................................................................................... 9 B-6-2 Action to Take ............................................................................................................................... 9 CHAPTER B-7 CHECKLIST OF ATTACHMENT...................................................................................... 11 B-7-1 Introduction ..................................................................................................................................... 11 B-7-2 Action To Take ............................................................................................................................ 11 CHAPTER B-8 ATTACH DOCUMENTS............................................................................................... 12 B-8-1 Introduction .................................................................................................................................. 12 B-8-2 Action To Take .............................................................................................................................. 12 CHAPTER B-9 PREVIEW FORM........................................................................................................... 14 B-9-1 Introduction ................................................................................................................................... 14 B-9-2 Action To Take .............................................................................................................................. 14 CHAPTER B-10 CANCEL APPLICATION ................................................................................................ 15 B-10-1 Introduction ........................................................................................................................... 15 B-10-2 Action to Take .............................................................................................................................. 15
Page 3 of 17 SPM 1/ 2014
INTRODUCTION
Chapter B-1 Introduction
B-1-1 Introduction about Web Submission Module
Web Submission module is developed to allow applications submitted by applicants/companies though online. It will simplify the authentication process; it is also to minimize print-out documents and also to speed up the whole process.
B-1-2 Manufacturers in the Principal Custom Area key areas of the exemptions
a) Import duty exemption on machinery and equipment excluding spare parts and consumables imported or purchased from a Licensed Manufacturing Warehouse, Bonded Warehouse or Free Zone under item 115 Customs Duties (Exemption) Order 2013
b) Sales tax exemption on machinery, equipment, spare parts and consumables
imported or purchased from a Licensed Manufacturing Warehouse, Bonded Warehouse or Free Zone under item 106 Sales Tax (Exemption) Order 2013
c) Sales tax exemption on machinery, equipment, spare parts and consumables
purchased from a manufacturer (licensed under the Sales Tax Act 1972) under item 106 Sales Tax (Exemption) Order 2013
Page 4 of 17 SPM 1/ 2014
Chapter B-2 Common Functions and Definitions
Some of the common fields and icon are available in the system screens as follows:
Field Description
Input Field • This Field requires the user to key in the necessary information based on its label.
• Examples of usage :
• Input Field with Asterisk (*) is mandatory field.
Check box • This field requires user either to enabling it or disabling it. The select and deselect actions can be done by clicking on the square box. It is allow user to make multiple selection.
• Example of usage :
Drop down List • This field requires the user to select an option from the displayed list. These options will be displayed in the list by clicking the arrow down button.
• Example of usage:
Calendar • This Icon is use to select date. If user clicks at this button, calendar will pop up on screen. User can select the necessary date from the calendar.
Page 5 of 17 SPM 1/ 2014
Chapter B-3 COMPANY PARTICULARS B-3-1 Introduction
This chapter will explain on how to key in the COMPANY PARTICULARS information. B-3-2 Action To Take
Below is the step-by-step instruction:
Step Action
1. Click on Company Particulars to go to the page.
Result: Company Particulars page will be displayed.
2. Fill up all the field needed
3. Click on button to save the information.
Result: message will be displayed.
11. Click on button to go to next page.
Page 6 of 17 SPM 1/ 2014
Chapter B-4 FACTORY LOCATION
B-4-1 Introduction
This chapter will explain on how to key in the FACTORY LOCATION information. B-4-2 Action To Take
Below is the step-by-step instruction:
Step Action
1. Click on FACTORY LOCATION to go to the page. Result: FACTORY LOCATION page will be displayed.
2. Click on button to add factory location. Result: Field box will be displayed for user to enter information.
3. Fill in all relevant information for the factory location in the field boxes.
4. Click on button to add subsequence factory location. Result: Field box will be displayed for user to enter information.
Page 7 of 17 SPM 1/ 2014
Step Action
5. If users want to delete the factory location, tick on the check box and click on
button to delete information.
Result: The following pop-up will be displayed.
6. Click on button to continue delete information or click on button to cancel option.
7. Click on button to save the information.
Result: message will be displayed.
8. Click on button to go to previous page.
9. Click on button to go to next page.
Page 8 of 17 SPM 1/ 2014
Chapter B-5 PROJECT COST
B-5-1 Introduction
This chapter will explain on how to key in the PROJECT COST information
B-5-2 Action To Take
Below is the step-by-step instruction:
Step Action
1. Click on PROJECT COST to go to the page. Result: PROJECT COST page will be displayed.
2. Fill up all the field needed and tick the related checkbox Click on button to save the information.
Result: message will be displayed. Note : All Project cost value must be total of detail cost in RM.
Page 9 of 17 SPM 1/ 2014
Chapter B-6 FINISHED PRODUCTS
B-6-1 Introduction
This chapter will explain on how to key in the FINISHED PRODUCTS information. B-6-2 Action To Take
Below is the step-by-step instruction:
Step Action
1. Click on FINISHED PRODUCTS to go to the page. Result: FINISHED PRODUCTS page will be displayed.
2. Select the Factory Location Result: The add and delete button will enable.
3. Click on add button to add finished product information
Click on add button to add more subsequence finished product for that factory
location.
Page 10 of 17 SPM 1/ 2014
Step Action
4. If users want to delete the finished product, tick on the check box and click on
button to delete information.
Result: The following pop-up will be displayed.
6. Click on button to continue delete information or click on button to cancel option.
7. Click on button to save the information.
Result: message will be displayed.
8. Click on button to go to previous page.
9. Click on button to go to next page.
Page 11 of 17 SPM 1/ 2014
Chapter B-7 Checklist of Attachment
B-7-1 Introduction
Checklist of Attachment
B-7-2 Action To Take
Below is the step-by-step instruction:
Step Action
1. Click on Checklist to go to the page. Result: Checklist page will be displayed.
2.
Tick the box. Click on button to save the information.
Result: message will be displayed.
Page 12 of 17 SPM 1/ 2014
Chapter B-8 ATTACH DOCUMENTS
B-8-1 Introduction
This chapter will explain on how to attach document B-8-2 Action To Take
Below is the step-by-step instruction:
Step Action
1. Click on attach documents to go to the page. Result: attach documents page will be displayed.
2. Click on the browse button to locate the file need to attach Result:
Locate and choose the file, then click open button
Page 13 of 17 SPM 1/ 2014
Result: Click on the Attach File button to proceed
Result: The message appears mention the file successfully attached. Other function To remove the attachment file, select the file and click remove button. To view the attachment file, select the file and click download. Note: User can attach any type of attachment unlimited, each file must not exceed size 10mb.
Page 14 of 17 SPM 1/ 2014
Chapter B-9 Preview Form
B-9-1 Introduction
This chapter will explain on how to preview form
B-9-2 Action To Take
Below is the step-by-step instruction:
Click on ‘Preview Application’ button
Result: It will show the data user have entered in pdf format and create a file name MIDAFORMSPM1.pdf in the attach document list.
Other function To remove the attachment file, select the file and click remove button. To view the attachment file, select the file and click download.
Page 15 of 17 SPM 1/ 2014
Chapter B-10 Cancel Application
B-10-1 Introduction
This section allow user to cancel the application B-10-2 Action To Take
Below is the step-by-step instruction: Click on ‘Cancel’ button to cancel application.
Result: The following page will be displayed
Click on ‘Yes’ button to proceed or else click ‘No’ button.
Page 16 of 17 SPM 1/ 2014
Result: The following page will be displayed
Page 17 of 17 SPM 1/ 2014
To submit the application please refer to this link on how to submit https://jpc.online.mida.gov.my/midawebpki/forms/usermanual/PKI%20General%20User%20Guide_Online.pdf
Any problem upon using our system, please log the report to http://jpchelpdesk.mida.gov.my/JPCHelpdesk/ Our technical support officers will response onto the problem
CONTACT PERSON
1. Online Technical Support
i) Mohammad Radzie Hashim 03-2267 3743 [email protected]
ii) Mohd Nor Izuan Ibrahim 03-2267 3729 [email protected]
2. Enquires Business / Process Flow / Approval Check / Application Status
a. Pn.Jasbir Kaur Bachan Singh - Pengarah Bahagian 03 - 2267 3539 [email protected]
b. Pn.Zuraidah Othman - Timbalan Pengarah 03 - 2267 6759 [email protected]
c. Siti Halimaton Mohd Rejab - Timbalan Pengarah 03 - 2267 6701 [email protected]
d. Puan Azliza Ahmad 03 - 2267 3753 [email protected]
e. Puan Siti Hajar 03 - 2267 3602 [email protected]