FOR THE PROPOSED EXPANSION OF ALUMINIUM...
Transcript of FOR THE PROPOSED EXPANSION OF ALUMINIUM...
PRE-FEASIBILITY REPORT FOR
THE PROPOSED EXPANSION OF ALUMINIUM SMELTER PRODUCTION
CAPACITY FROM 16 LTPA SMELTER &1215 MW CPP TO 18 LTPA SMELTER
&1215 MW CPP AT
BHURKAMUNDA/BRUNDAMAL VILLAGE, JHARSUGUDA DISTRICT,
ODISHA
Submitted to:
Ministry of Environment, Forest and Climate Change New Delhi
Prepared by:
M/s Vedanta Limited (VL) Jharsuguda, Odisha
November, 2017
Pre-Feasibility Report for the Proposed Expansion of Aluminium
Smelter Production Capacity from 16 LTPA smelter & 1215 MW CPP to
18 LTPA smelter & 1215 MW CPP at Bhurkamunda/Brundamal Village, Jharsuguda District, Odisha
Vedanta Limited PFR-1
1.0 EXECUTIVE SUMMARY
1.1 Introduction
Vedanta Ltd. (VL) is promoted by Vedanta Resources (PLC) UK which is a non-
ferrous metals Conglomerate having mining/metal processing in India & abroad.
Vedanta Jharsuguda Plant has presently capacity of 16 LTPA corresponding to
GP-320 KA prebaked technology from GAMI, China. Vedanta group now desires
to expand Aluminium Smelter of Vedanta– Jharsuguda plants.
Vedanta – Jharsuguda aluminium smelter plant desires to increase the capacity
by 2 LTPA (2,00,000 TPA) i.e. from 16 LTPA smelter & 1215 MW CPP to 18 LTPA
smelter & 1215 MW CPP.
Vedanta is having a total revenue of more than 13 billion US$ sustaining global
leadership of nonferrous metals and optic fibre business. Vedanta has a growing
interest in copper aluminium, zinc, silver lead, iron ore, gold & optical fibre cable
in India, Australia, North America, Zambia and the UK.
1.2 Project at a Glance
The proposed expansion project at a glance is given in Table-1.
TABLE-1
PROJECT AT A GLANCE
General Description
Type of Project Expansion of aluminium smelter capacity from 16
LTPA smelter & 1215 MW CPP to 18 LTPA smelter &
1215 MW CPP
Owner M/s. Vedanta Limited (VL)
Bhurkamunda Village, Jharsuguda District, Odisha
Location of Plant The proposed expansion site is planned within the
existing plant premises of Vedanta at Bhurkamunda
Village, Jharsuguda, Odisha
Technology Energy efficient pre- baked technology, state of art
340 kA pot line technology with Pre-baked anodes.
Inputs to Aluminium Smelter
Alumina About 1.93 T of Alumina / Tonne of Metal (or
about 3,86,000 TPA additional
Calcined Petroleum
Coke, cryolite as
Na3AlF6, Aluminium
Fluoride (AlF3), CT Pitch
Additional requirement for expansion:
Calcined Petroleum Coke: 74,000 TPA;
Cryolite: 400 TPA;
Aluminium fluoride: 4000 TPA;
Coal Tar Pitch: 16,000 TPA.
Land requirement Present total plant area: 2061.41 acres. Proposed
Expansion will be within the existing plant.
Power requirement Estimated additional power requirement considering
Pre-Feasibility Report for the Proposed Expansion of Aluminium
Smelter Production Capacity from 16 LTPA smelter & 1215 MW CPP to
18 LTPA smelter & 1215 MW CPP at Bhurkamunda/Brundamal Village, Jharsuguda District, Odisha
Vedanta Limited PFR-2
General Description
auxiliary loads, anode effects etc. would be around
350-400 MW.
Water requirement Around 1 m3 /T (or around 24 m3/hr additional) of
Aluminium. Source: Hirakud Reservoir
Manpower requirement 800 persons additional
2.0 INTRODUCTION OF THE PROJECT/ BACK GROUND INFORMATION
2.1 Identification of Project Proponent and Project
Vedanta is having a total revenue of more than 13 Billion US$ with clear focus on
achieving and sustaining global leadership in non-ferrous metals (with mining also) and
Optic Fiber business. VEDANTA has a growing interest in copper, aluminium, zinc,
silver, lead, iron ore business, Gold and Optic Fiber Cable in India, Australia, North
America, Zambia and the U.K.
Vedanta Ltd. (VL) is proposing for expansion of aluminium smelter capacity from 16
LTPA to 18 LTPA. The proposed expansion will be inside the existing plant
premises. The additional facility will be built up in an identified area of 15 acres in
the existing Vedanta Ltd Aluminium Smelter plant located at Bhurkamunda village,
Jharsuguda District, Odisha.
2.2 Brief Description of Nature of the Project
The existing Vedanta Limited Aluminium Smelter plant has 16 LTPA capacity along
with all auxiliary facilities, Green Anode Plant (GAP) of 4 x 35 TPH, Bake oven plants,
Rodding plants of 1 x 90 RPH, 1 x 160 RPH, Captive Power Plant (CPP) of 9 x 135 MW.
Further 2400 MW TPP is established in the same complex,( 3 x 600 MW CPP1 x 600 MW
TPP).
Now Vedanta intends to expand the aluminium smelter plant by 2 LTPA through
modernization and increase of current efficiency, addition of pots power would be
required for additional smelter capacity as about 13500 kwh/Tonne (DC). Estimated
additional power requirement considering auxiliary loads, anode effects etc. would be
around 350-400 MW.
The estimated project cost is about Rs. 1,240 Crores.
2.3 Need and Justification for the Project
The demand of aluminium in India and worldwide is growing rapidly. To meet the
growing demand of the aluminium, the production capacity in the country needs to
be augmented.
Pre-Feasibility Report for the Proposed Expansion of Aluminium
Smelter Production Capacity from 16 LTPA smelter & 1215 MW CPP to
18 LTPA smelter & 1215 MW CPP at Bhurkamunda/Brundamal Village, Jharsuguda District, Odisha
Vedanta Limited PFR-3
The debottlenecking and additional facility will be taken up in respective location at
Smelter-2 as follows.
Green Anode Plant (GAP)
Basis of calculation are as follows for smelter-2:
Requirement of anode : 1.5 anodes / day/pot
Total Consumption : 2000 anodes/day
Working days : 289
Availability : 85%
Weight of each anode : 1040 kg
Total Consumption /day : 1.04 x 2000 = 2080 T
Existing GAP design capacity: 70 TPH
GAP PRODUCTION : (70 x 24 x 0.85 x 289)/365 = 1150 TPD
Additional requirement : (2080 – 1150) = 930 TPD
New Design Capacity : 930/ (24 x 0.85 x 289/365) = 58 TPH
1 x 60 T/H GAP is recommended.
Rodding Plant :
Production : 80 RPH
Working hours : 2 shifts / day (6.5 hrs/shift)
Total production required : 2080 (in 13hrs) = 160 RPH
Extra production required : 160-80 = 80 RPH
Proposed New Design Capacity = 120 RPH
From the above it is seen that additional GAP and Rodding Plant will be required.
Storage requirement for Calcined Petroleum Coke and coal tar pitch also would require
enhancement. Original proposal for Calcined Petroleum Coke storage capacity was 4 x
7500 T of which 2 have been installed. Balance 2x7500 T Silos along with tie-in
facilities for conveyors will be sufficient for expansion.
As regards coal tar pitch storage, original considerations were 4 x1000 T of which 2
were installed. Balance tanks shall be installed along with tie-in with existing system to
cater for the expansion.
Cast House
The present capacity to cast the desire metal is already installed, whereas further
addition on capacity will be done based on requirement for value added product.
Employment Generation
The proposed expansion project will be operated with skilled and semi-skilled personal.
The total employment for expansion of smelter plant will be 800 persons of direct and
indirect employment.
Pre-Feasibility Report for the Proposed Expansion of Aluminium
Smelter Production Capacity from 16 LTPA smelter & 1215 MW CPP to
18 LTPA smelter & 1215 MW CPP at Bhurkamunda/Brundamal Village, Jharsuguda District, Odisha
Vedanta Limited PFR-4
3.0 PROJECT DESCRIPTION
3.1 Type of the Project
The proposed expansion project is expansion of aluminium smelter capacity from 16
LTPA smelter and 1215 MW CPP to 18 LTPA smelter and 1215 MW CPP through
modernization and additional pots and increasing current efficiency.
3.2 Details of Alternative sites
The proposed expansion of aluminium smelter capacity will be implemented within the
existing plant premises. Hence, there is no alternative sites study for this expansion
project.
3.3 Location of the Project
The proposed expansion project site is within the existing plant premises at
Bhurkamunda village, Jharsuguda district, Odisha. The index map of the project site
is shown in Figure-1. Similarly, the study area showing topographical features
within 10 km radius from the project site boundary is shown in Figure-2. The
Google image of proposed expansion project site and 10 km radius are shown in
Figure-3(A) & 3(B) respectively.
3.4 Size or Magnitude of Operation
The proposed aluminium smelter plant for production of primary aluminium metal is
given in Table-4. The overall layout plan is shown in Figure-4.
TABLE-4
PROJECT DETAILS FOR ADDITIONAL CAPACITY
Sr. No. Description Details
1 Additional Aluminium
production capacity
2 LTPA
2 Land requirement 15 acres (available land inside plant
premises)
3 Water consumption and
source
Around 1 m3 /T (or around 24 m3/hr) of
Aluminium
4 Power consumption Around 350-400 MW
5 Alumina requirement 1.93 T /Tonnes of metal (or about 3,86,000
TPA additional)
6 Fuel requirement (Furnace
Oil)
Around 100 T/day
7 Manpower requirement 800 additional
Pre-Feasibility Report for the Proposed Expansion of Aluminium
Smelter Production Capacity from 16 LTPA smelter & 1215 MW CPP to
18 LTPA smelter & 1215 MW CPP at Bhurkamunda/Brundamal Village, Jharsuguda District, Odisha
Vedanta Limited PFR-5
FIGURE-1
INDEX MAP OF THE PROJECT SITE
Project Site
Pre-Feasibility Report for the Proposed Expansion of Aluminium
Smelter Production Capacity from 16 LTPA smelter & 1215 MW CPP to
18 LTPA smelter & 1215 MW CPP at Bhurkamunda/Brundamal Village, Jharsuguda District, Odisha
Vedanta Limited PFR-6
FIGURE-2
STUDY AREA MAP (10 KM RADIUS)
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-7
FIGURE-3
GOOGLE IMAGE MAP (10 KM RADIUS)
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-8
FIGURE-4
OVERALL LAYOUT PLAN
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-9
3.5 Project Description with Process Details
The process adopted for production of aluminium is the process of electrolytic reduction
of alumina to metallic aluminium as being practiced in present age advanced aluminium
smelting plant globally. The aluminium production flow sheet is shown in Figure-5.
3.5.1 Process Description of Aluminium Smelter
The process of reduction is the well-known and commercially established Hall- Héroult
process of electrolysis and will employ state of art specific amperage technology.
Electrolytic operations are proposed to be carried out at cell amperage of 340 kA.
Higher cell amperages are conducive to more economical production & tendency over
time has been to achieve higher current intensities.
The anode system proposed to be used is prebaked centre feed type. Aluminium metal
is deposited in molten form on the cathode under the electrolyte layer and is tapped
under vacuum. As the operation is continuous, alumina is charged at suitable intervals
after breaking the crust that is formed at the top of electrolyte layer.
Fume liberated at the anode during the electrolytic process consists primarily of Oxides
of Carbon & fluorine compounds. The former are obtained by Chemical reaction of the
anode mass whereas the later result from the dissociation of fluorides in the cell bath.
Additionally entrained fluorides, alumina dust are also included in liberated gases. The
gases are vented through dry scrubber type gas cleaning system.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-10
FIGURE-5
ALUMINIUM PRODUCTION FLOW SHEET
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-11
3.5.2 Process Related Facilities
Electrolysis
Because of solubility of aluminium oxide in molten Cryolite (Na3AlF6), it is possible to
complete the electrolysis of oxide at a temperature of 950⁰ - 980⁰C. Aluminium oxide
has a melting point of 2050⁰C but is soluble in Cryolite bath upto 10% by weight. The
basic equation describing the Chemical decomposition of aluminium oxide is
2Al2O3 4Al + 3O2
Earlier electrolyte cells were small with current intensities of only several thousand
amperes. With larger sized cells being built, baked anodes started to become popular.
Some of the major factors influencing usage of baked anodes are
It allows higher current densities (presently cells with 500 KA rating or more are
in Vogue)
Distribution of magnetic flux is better & gas flow becomes favourable
Possibility of better thermal balance
Working area is comparatively free of obnoxious fumes
Higher Metal Purity
Electrolytic cell consists of a box shaped steel shell which contains the cathode and
anode assembly. Bottom of steel shell is lined with refractory bricks which support the
cathode assembly. The cathode assembly consists of blocks and cathode bar which
extends over the entire width of the cell & is externally connected to the bus bars with
flexible connectors. Anode assemblies consist of anode block and anode rods. These are
clamped to anode beam. Electrical & mechanical connection between blocks & rods is
made by means of cast iron stubs, which are locked in stub holes of anode blocks.
Pot is placed side by side in the room, completely enclosed by sheet metal hoods,
serviced by multipurpose overhead pot tending machines (PTM), fully controlled by a
process computer, connected though a central hyper dense phase pneumatic transport
system to alumina & fluoride supply & vented through a duct system to the central dry
scrubbing waste gas cleaning installation.
Carbon Plant
Smelter will be self-contained for anode requirement. Anode production facility will
comprise:
Green anode plant;
Baking Furnace; and
Rodding facility.
The process flow sheet of carbon plant is shown in Figure-6.
Green Anode Plant
Major raw material for the manufacture of GAP is Calcined Petroleum Coke & blinder
such as Coal tar pitch.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-12
The following material processing circuits will be encountered in the Green Anode Plant.
Calcined Petroleum Coke : (around 60%)
Butts : (around 25%)
Green Scrap : (around 1%)
Pitch : (around 14%)
Paste mixing & compacting
Through different unit operations in the above circuits, different size fractions of Coarse
butts, medium, and fine coke, mill & dust are weighed, heated and mixed with green
scrap& liquid pitch and paste is made by kneading. Anode us formed by vibrating
forming machine. The process flow sheet of green anode plant is shown in Figure-7.
FIGURE-6
CARBON PLANT FLOW SHEET
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-13
FIGURE-7
GREEN ANODE PLANT FLOW SHEET
Baking Furnace
The following processing will be done after the anode is formed
Cooling & Storing
Baking
Baked Anode Clearing & Storage
The above processing requires extensive storage and movement area for materials.
From Green Anode storage area, green anodes are transported by Crane & roller
Conveyor in suitable package to anode baking furnace.
Rodding Plant
Subsequent to baking, anodes are subjected to cleaning operation and the rods which
have been removed from butts are cleaned, inspected and reused. The stub holes of
baked anodes are preheated, rods are positioned & secured in place with molten cast
Iron & used after quality check.
3.6 Requirement and Resources
3.6.1 Land Requirement
Vedanta Aluminium smelter plant along with CPP is spread over an area of 2061.41
acres. The proposed expansion will be implemented in the existing plant premises.
Land breakup of facility is given in Table-7.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-14
TABLE-7
ITEM WISE BREAK-UP OF LAND
Sr. No Plant Unit Area (acres) Area (ha)
1 Total smelter and other areas 1234.81 499.72
2
Captive power plant incl main power plant,
green belt and ash pond area 621.48
251.51
3 Railway sidings 48.93 19.80
4 Township existing 65.19 26.38
5 Township proposed 91.00 36.826
Total 2061.41 834.236
3.6.2 Raw Material Requirement
Major raw material for smelter is smelter grade alumina. Other material will be
cryolite, aluminium fluoride, calcined petroleum coke, coal tar pitch for anode
manufacture.
Alumina will be sourced from captive refinery and also shall be imported. Aluminium
Fluoride will be imported. CP coke will be procured for indigenous or overseas
suppliers. Coal tar pitch will be procured from local sources.
The details of raw material requirement of project are presented in Table-8.
TABLE-8
DETAILS OF RAW MATERIAL REQUIREMENT
Sr. No. Description Quantity
1 Alumina 1.93 T/Tonne of metal or 386,000 TPA
additional
2 Cryolite 2 kg/T or 400 TPA
3 Calcined Petroleum Coke 0.37 T/T (gross anode consumption is around
545 kg/T) or 74000 TPA additional
4 Coal Tar Pitch 0.08 T/T or 16000 TPA additional
5 Aluminum Fluoride 20 Kg/T or 4000 TPA additional
Details of chemical analysis of raw materials is presented in Table-9.
TABLE-9
DETAILS OF CHEMICAL ANALYSIS OF RAW MATERIALS
Sr. No Details of Chemical Constituents Results
I Alumina
a Code AL2O3 Contents >%
Impurities <%
SiO2 Fe2O3 Na2O Loss on Ignition
Al2O3-1 98.6 0.02 0.03 0.50 0.8
Al2O3-2 98.5 0.04 0.04 0.55 0.8
Al2O3-3 98.4 0.06 0.04 0.55 0.8
Al2O3-4 98.3 0.08 0.04 0.60 1.0
Al2O3-5 98.2 0.10 0.05 0.60 1.0
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-15
Sr. No Details of Chemical Constituents Results
b Other Metal Impurities Limits
TIO2 <0.005 %
V2O5 <0.003 %
P2O5 <0.003 %
ZnO <0.005 %
c Physical Characteristics
Specific surface area >35 m2/g
Α-Alumina Maximum 10%
(-) 325 mesh Maximum 10%
II Calcined Petroleum Coke
1 Moisture (max) 0.3%
2 Volatile matters (max) 0.5%
3 Ash content 0.35%
4 Iron (max) 350 ppm
5 Silicon (max) 350 ppm
6 Nickel (max) 250 ppm
7 Vanadium (max) 300 ppm
8 Sulfur 2.5 – 3.5%
9 Sodium + Calcium (max) 200 ppm
10 Real density 2.05 -2.10 g/cm3
11 Apparent density >1.70 g/cm3
12 Bulk density >0.8 g/cm3
13 Resistivity <600 m
14 Hardness index 32 – 46
III Pitch
1 Softening point (R & B) 105oC – 113oC Coking value
2 (Conardson) 54% (min)
3 QI 6 – 10%
4 TI 30 – 37%
5 Resin 20-26%
6 Density 1.15-1.30 g/cm3
7 Ash content 0.5% (max)
8 Moisture 0.5% (max)
9 Sodium 400 ppm (max)
10 Iron 200 ppm (max)
11 Sulfur 0.7% (max)
12 Viscosity 2x104 cps
13 (1600C) 3x104 cps
IV Aluminium Fluoride Special grade 1 Special grade 2
1 Fluorine as F 61 60
2 Aluminium as Al 30 30
3 Sodium as Na 0.5 0.5
4 Sulphate + Iron as SO3 + Fe2O3 0.38 0.43
5 SO4 0.5 0.8
6 Phosphorus as P2O5 0.04 0.04
7 Loss on ignition at 550oC for 30 Min. 0.5 1.0
V Fuel Oil
Heavy Diesel Oil (HDO)
1 Total Sulphur content 4.5% (Max.)
2 Gross Calorific Value (Kcal/kg) 10,000
3 Flash Point (Min.) 66 oC
4 Water content by Volume (Max.) 1.0%
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-16
Sr. No Details of Chemical Constituents Results
5 Sediment by weight (Max.) 0.25%
6 Asphaltene content by weight (Max.) 2.5%
7 Kinematic Viscosity in Centistokes at 50o C (Max.)
370
At 98.90 C 20 – 30
8 Ash Content by weight (Max.) 0.1%
9 Acidity (in inorganic) Nil
10 Pour Point (Max .) 50 oC
11 Sodium Content --
12 Vanadium Content 25 ppm
13 Specific heat (kCal/kg. Deg. C) 0.5
14 Relative density at 15oC 0.89 (Approx)
VI Light Diesel Oil (LDO)
1 Pour Point (Max) 12⁰C& 21⁰C for Summer and Winter
respectively
2 Kinematic viscosity in centistokes at 38 Deg.C
2.5 to 15.7
3 Water content, percent by volume (Max.) 0.25
4 Sediment Percent by Mass (Max) 0.10
5 Total Sulphur percent by Mass (Max) 1.8
6 Ash percent by Mass (Max) 0.02
7 Carbon Residue (Rans bottom) percent
by Weight (Max)
1.50
8 Acidity in organic Nil
9 Flash point (Min) (Pensky Martens)
closed cup
66oC
10 Acidity Total, mg of KOH/g (Max) Nil
11 Copper strip corrosion for 3 hours at 100 oC
Not worse than No.2
12 Relative density at 15oC 0.82 – 0.86
3.6.3 Water Requirement
Make up water requirement is not substantial, around 1 m3 /T (or around 24 m3/hr-576
KLD additional) of Aluminium. Requirement would be met from existing facility.
Recirculating cooling water system using wet evaporative cooling towers are deployed
for the existing station. It is used for the condenser and auxiliary equipment cooling in
a semi-open cooling water circuit.
3.6.4 Electrical Power
For smelter, 13,500 kwh (DC)/tonne of metal will be required. Considering auxiliary
units & other factors estimated requirement of Power would be 14,200 kwh/T. Required
amount of power will be taken from 2400 MW TPP/Grid.
As there is no basic change in design of pot room and only modification and current
efficiency improvements with few pots are being added, the existing design cushions in
rectifier & transformer substation will be adequate to take care of the electrolysis
operation.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-17
3.6.5 Fuel Oil
Fuel Oil will be required for baking furnace: 48 kg/T of baked anode would be fuel oil
requirement. Such amount (around 100 T/day) will be available from existing facility.
3.7 Waste Generation and Management
3.7.1 Wastewater Management
The additional waste water generated for Aluminium smelter plant is 576 m3/day.
The major consumptive units and wastewater generation units in the smelter are
cooling towers. The wastewater is treated and reused recycled for fire protection,
dust suppression and gardening.
Major consumption water requirement are cooling towers and domestic water. Waste
water will be treated and recycled to the extent possible. Zero-discharge policy will
be followed.
The existing ETP will be augmented for treating the wastewater generated.
3.7.2 Storm Water Management
Storm water will be collected and utilized in smelter operation.
During first showers in monsoon season, the fugitive emissions of fluorides, which
get deposited on roof top and other areas, is washed out and this rainwater is
collected in storm water guard pond. The necessary drains are constructed within the
plant area to collect the run-off water. Storm water collection pond is constructed
appropriately to prevent contamination of ground water. The stored storm water is
utilized in smelter operation after treatment in ETP.
3.7.3 Solid Waste
With expansion of the plant, the solid wastes will marginally increase which will be
taken care in ongoing solid waste management system. Anode Butts & green scrap
will be recycled in GAP. Solid waste generation details of the existing plant are given
in Table-10.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-18
TABLE-10
ESTIMATED EXISTING SOLID WASTE GENERATION All units in Tonnes
Waste Existing generation (16 LTPA)
Proposed generation (18 LTPA)
Spent Pot lining (Cathode residues)-(T) 40,000 45,000
Used Oil (KL) 530 564
Shot blasting dust (T) 3,000 3,375
ETP Sludge (T) 520 585
Battery (Nos) 150 170
Aluminium Dross (T) 35,000 39,375
Anode Butt (T) 3,00,000 3,37,500
4.0 SITE ANALYSIS
4.1 Connectivity
The proposed expansion project is well connected with road network. Nearest road is
State Highway, SH-10 which is 1.1 km away from the site connecting Jharsuguda and
Sambalpur. The nearest railway station is Jharsuguda Railway Station at a distance of
3.9 km in NNW direction of the proposed expansion project site.
This site is located near Bhurkamunda/ Brundamal villages in Jharsuguda district of
Odisha. Sambalpur town is situated at a distance of 45 km from this area. The
Rourkela-Jharsuguda-Sambalpur broad gauge railway line is passing within a distance
2.5 km from the site. This line is connected to Titlagarh / Rayagada also. The IB Valley
coalfield is very close to this area where from coal can be brought by railway.
Site Selection Background
The basic reasons in favouring Jharsuguda - Sambalpur area for identifying the Smelter
& Captive Power Plant were as follows:
Rourkela - Jharsuguda - Sambalpur – Titlagarh Broad gauge line is passing
adjacent to this area, and this line connects all major bauxite deposits in Odisha.
The State Highway SH -10 connecting Jharsuguda and Sambalpur is also passing
through this area.
Hirakud reservoir, which is considered to be the largest water reservoir in Odisha,
is situated in this area. Availability of large quantum of water from this reservoir is
possible with reasonable pipe length.
The IB Valley area, which is one of the two major coal bearing areas of Odisha, is
spread over a large area within close vicinity.
Social infrastructural facility of Sambalpur and Jharsuguda could be utilized for
plant personnel and thus will minimize the capital investment.
The work culture of the labour force in this area is quite conducive and thus
favourable to any private entrepreneur.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-19
4.2 Land Form, Land Use and Land Ownership
Total land requirement for aluminium smelter expansion plant including greenbelt is
around 15 acres within the existing integrated complex. The overall land for the
proposed expansion is in industrial use, which is under the possession of Vedanta.
The State Highway SH-10 is running within 1.1 km from this site.
Site was selected based on an in-depth study conducted by Vedanta, site was
selected near Brundamal-Bhurkamunda.
4.3 Topography
The land in the plant site fairly flat with a general elevation of about 200 m to 215 m
above MSL and no water streams are present in the site area.
4.4 Existing Land Use Pattern
The existing land use is already under industrial category. The proposed expansion
will be carried out within the existing premises of Vedanta aluminium smelter plant
at Jharsuguda. There is no additional land necessary for the proposed expansion
project.
4.5 Environmental Setting of the Site
The environmental setting of the existing and proposed expansion project site is given
in Table-11.
TABLE-11
ENVIRONMENTAL SETTING OF THE SITE
Sr. No. Particulars Details
1 Latitude & Longitude a) Latitude: 21048’’47”N
b) Longitude: 84002’45”E
2 General elevation above MSL 200m- 215m
3 Present land use at the site Industrial area
4 Nearest highway SH-10 (1.1 km, W), NH-200 (1.9 km, N) NH-200
5 Nearest railway station Jharsuguda Railway Station (3.9 km, NNW)
6 Nearest airport Bhubaneshwar (380 km, NW)
7 Nearest town/City Jharsuguda (3.0 km, NNW)
8 Hills/valleys Nil in 15 km radius
9 Topography Fairly Flat
10 Archaeologically important places
Nil within 15 km radial area
11 National Parks / Wildlife
Sanctuaries
Nil within 15 km radial area
12 Reserved/ Protected Forests Katikela R.F (0.1 km, NE) Shriyapali R.F (2.9 km, NE) Ghichamura R.F (5.8 km, SE) Khait R.F (6.5 km WSW)
Malda R.F (6.8 km, SW) Rampur R.F (7.7 km, SW)
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-20
Sr. No. Particulars Details
Patrapali R.F (7.8 km, SW)
13 Seismicity Seismic Zone-II as per IS 1893 (Part I): 2002
14 Streams/Rivers Kharkhari Nala, (within the plant site)
Bhedan River (0.3 km, S ) Ib River (7.6 km, W) Hirakud Reservoir (7.8 km, S)
15 Defence Installations Nil
*all values are aerial distances
Industrial Development in the Study Area
The region is industrially developed with many industries operating in the study area
besides existing aluminium smelter of Vedanta. The list of industries in 10-km radius is
given in Table-12.
TABLE-12
LIST OF INDUSTRIES IN 10-KM RADIUS
Sr. No. Name of Industry Location
(Village) Distance (km) from Plant Site/ Direction
1 L.N. Metallic Sponge Iron
Plant
Sirpura 1.7 km, SW
2 SPS Steel & Power Ltd. Badmal 2.5 km, NW
3 Bhusan Steel Plant Thelkolai 2.7 km, SW
4 Bhagwati Steels Badmal 2.7 km, NW
5 Pawansuit Sponge Iron Plant Badmal 2.9 km, NW
6 Sree Madhar Ispat Ltd.
Sponge Iron Plant
Siripali 3.1 km, NE
7 Singal Sponge Iron Hirma 3.2 km, W
8 SMC Sponge Iron Hirma 3.8 km, WSW
9 Aluminium smelter and
Captive Power Plant (CPP) of
Aditya Aluminum Project
Bamloi 4.0 km, S
10 Action Ispat Sponge Kulitodia 4.7 km, NW
11 Samleswari Sponge Iron Plant Pulcharghai 7.7 km, SSW
*all values are aerial distances
4.6 Climatic Data from the Secondary Sources
The meteorological data is collected from the IMD-Jharsuguda, which is the nearest
IMD station to the existing plant site area. The data collected from IMD includes wind
speed, temperature, relative humidity, atmospheric pressure; rainfall and cloud
cover over a period of 10 years. The monthly maximum, minimum and average
values are collected for all the parameters except wind speed and direction. The
collected data is presented in Table-13.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-21
TABLE-13
CLIMATOLOGICAL DATA-STATION: IMD, JHARSUGUDA (1999-2004)
Month Atmospheric
Pressure (mb)
Temperature (0C) Relative
Humidity (%)
Rainfall
(mm)
0830 1730 Max. Min. 0830 1730
January 992.20 988.17 33.8 6.5 65 42 7.3
February 991.48 986.69 37.6 8.7 58 34 9.6
March 986.90 982.35 42.2 13.1 45 26 15.2
April 984.01 979.04 45.6 19.0 40 20 12.1
May 978.93 974.11 44.4 19.0 44 23 10.92
June 976.86 973.10 46.4 19.0 65 54 161.01
July 976.67 973.68 39.0 19.8 87 79 417.37
August 977.06 974.10 35.2 21.7 86 80 366.2
September 981.95 978.50 37.1 21.0 82 78 217.05
October 988.06 984.05 36.2 16.1 76 64 86.28
November 991.03 986.96 35.6 10.4 65 53 0.7
December 992.94 989.03 32.8 8.0 68 48 5.93
Total 1309.66
Source: India Meteorological Department, Pune
4.7 Infrastructure Facility
Aluminum production of capacity 16 LTPA has been operating for quite few years and
have all infrastructures required for operating such plants. VL already invested for
infrastructural facilities like road access from SH-10 to plant, township its expansion
along with hospital etc.
The proposed expansion will mainly affect GAP & Rodding plant area. Pot line
configuration will remain unchanged with just modification and addition of pots.
Residential Area will be affected to inclusion of additional manpower of around 800
personnel. Green belt was already been considered during preparation of original
layout. Additional power requirement will be sourced from 2400 MW TPP/grid.
Industrial Waste Management, drinking water management, sewage system will be
taken care of from the existing facilities.
Related road/ railway infrastructural requirement is foreseen for the expansion
project to cater the additional volume.
5.0 PLANNING BRIEF
5.1 Existing and Proposed Land Use Details
The existing and proposed plant land use details are given in Table-14.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-22
TABLE-14
EXISTING AND PROPOSED PLANT LAND USE DETAILS
Sr. No Plant Unit Area (acres) Area (ha)
1 Total smelter and other areas 1234.81 499.72
2
Captive power plant including main power
plant, green belt and ash pond area 621.48 251.51
3 Railway sidings 48.93 19.80
4 Existing Township 65.19 26.38
5 Proposed Township 91 36.826
Total 2061.41 834.83
5.2 Brief Description of Main Process and Equipment of Different Anode
Production Facilities
5.2.1 Anode Plant (GAP, Bake Oven, Rodding)
a) Storage and Transportation of calcined petroleum coke
Calcined Petroleum Coke storage capacity of 24 x 7500 T have been installed.
Balance 2 x 7500 T Silos along with tie-in facilities for conveyors proposed.
b) Storage and Transportation of Coal Tar Pitch
2 x 1000 T installed. 2x1000 T proposed along with tie-in with existing system to
cater for the expansion.
c) Recycled Material Treatment
The recycled materials treatment section treats the reject paste, reject green
anode, and reject baked anode from mixing, compacting, anode baking and
anode rodding sections etc., as well as the recycled butts from pot room. The
recycled materials are sent by the bridge crane to suitable crushing equipment
for primary and secondary crushing, and then they are sent respectively to the
green scraps or butts silo bucket elevator and belt conveyor. The pre-crushed
butts from pot room are crushed by suitable crusher and then sent to the butts
silo via conveyors. For the recycled materials treatment, it will be stored in two
butts silos and one green scraps silo. The existing butt storage capacity would
be augmented by installing more butt silos with butt unloading facility
d) Intermediate crushing and screening of petroleum cokes and
recycled materials
The intermediate crushing and screening system of petroleum cokes treats
calcined petroleum cokes, while the intermediate crushing and screening
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-23
system of recycled materials treats butts, baked scraps and green scraps. The
main equipment of the two systems are similar, consisting of one speed-
variable impact crusher, two (for the petroleum cokes system) or one (for the
recycled materials system) horizontal vibrating screen(s).
All kinds of calcined petroleum cokes stored in the calcined materials silos are
sent to the impact crusher through volumetric feeder, belt conveyor and electro-
magnetic separator etc. Then they are sent to the two-stage horizontal
vibrating screen by the bucket elevator for being separated as the required four
kinds of grain sizes: 12 - 6mm, 6 - 3mm, 3 – 0.8mm, 0.8- 0mm. Remaining
materials larger than 6mm and cokes larger than 12mm are recycled to the
crusher for re-crushing. For the remaining materials smaller than 6mm, part
are sent to the feeding silo for grinding in the ball mill and part are stored in
the packing materials silo for baking. The packing cokes are sent to the anode
baking furnace by truck.
Green scraps, baked scraps and butts stored in the green scraps and butts silos
enter into the middle crushing and screening system of recycled materials.
Green scraps which are crushed to be smaller than 12mm enter into the green
scraps proportioning silo while those larger than 12mm are recycled to the
crusher for re-crushing. Butts are divided into two grain sizes: 12 - 3mm and 3
- 0mm. They are sent respectively to different proportioning silos while butts
larger than 12mm are recycled to crusher for re-crushing. Butts and green
scraps share one set of system that operates by turns.
e) Grinding
Petroleum cokes stored in the silo are fed into the ball mill. The oversize coarse
particles are recycled to the ball mill for re-grinding while the required fine
materials are collected by the cyclone precipitator and bag filter and then sent to
the fine materials proportioning silo.
f) Pre-heating, mixing, paste cooling, compacting, green anode cooling &
Conveying
Petroleum coke particle materials, fine materials and butts particle materials
stored in different proportioning silos are sent continuously and volumetrically to
the preheating screw by their own continuous proportioning scales as per the
required recipes for being preheated to about 17 oC, then they are sent together
with the green scraps weighed by the continuous proportioning scale according
to the ratio and the liquid pitch from the liquid pitch proportioning system to the
continuous mixer. The paste of required quality from the continuous mixer is
cooled in the paste cooler and then sent to the vibro-compactor. The compacted
green anodes are measured with height, calculated with bulk density and printed
with marks and then enter into the overhead conveyor which transports the green
anodes to the cooling tank. The cooled tested green anodes are sent to be stored
in the carbon transfer station via chain conveyor, while the reject blocks are sent
to the recycled materials treatment section via roller conveyor and fork lifts. The
reject paste is sent by bucket loader to the recycled materials treatment section
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-24
g) Anode Baking Facility
In the furnace, the green anode and packing coke will be baked according to the
preset baking curve and the anode baking temperature is about 1100C. The baked
anode is cooled with the fan. When the anode temperature is lower than 200C, it
will be unloaded and sent by the conveyor to the carbon blocks cleaning machine for
removing the packing cokes stuck on the anode. The cleaned anode is sent for
quality inspection. After that, the qualified anode is sent to the carbon blocks
transfer station and stacked by the stacking crane, or sent to the anode rodding
section. The reject block is sent to the recycled materials treatment section.
h) Baking Furnace Fume Treatment
The baking furnace is state-of-art open ring type with auto firing and computerized
temperature control system. The fume from baking furnace contains tar fume and
dust. It is used in the up-to-date open ring type baking furnace and the volatile
matters and tar could be controlled sufficiently and efficiently, so that the fume
amount and pollutants content could be reduced effectively.
It is proposed to use the treatment measure of dry type filter for the tar, dust
contents of the fume. The baking furnace fume goes into the pre-precipitator firstly
for removing the coarse dust, and then it is cooled by the spray cooling device. After
that, it enters into the dry type tar trap for removing the tar and dust the fume. The
purified fume is released through stack. There will be two baking furnaces in the
project, attached with two sets of treatment systems. Both the systems emit treated
fume through the stacks.
i) Rodding
Subsequent to baking, anodes are subjected to cleaning operation and the rods which
have been removed from butts are cleaned, inspected and reused. The stub holes of
baked anodes are preheated, rods are positioned & secured in place with molten cast
Iron & used after quality check.
j) Power Distribution of Anode Production System
The green anode manufacturing unit will be equipped with suitable transformers,
which can meet with the power supply requirements of various sections of green
anode manufacturing, and circulating water system of anode compacting.
The baking plant is equipped with transformers, which can meet with the power
supply requirements of baking unit and various auxiliary systems.
5.2.2 Pot Line & Control Philosophy
Electrolytic cell consists of a box shaped steel shell which contains the cathode and
anode assembly. Bottom of steel shell is lined with refractory bricks which support the
cathode assembly. The cathode assembly consists of blocks and cathode bar which
extends over the entire width of the cell & is externally connected to the bus bars with
flexible connectors. Anode assemblies consist of anode block and anode rods. These are
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-25
clamped to anode beam. Electrical & mechanical connection between blocks & rods is
made by means of cast iron stubs, which are locked in stub holes of anode blocks.
Pot is placed side by side in the room, completely enclosed by sheet metal hoods,
serviced by multipurpose overhead pot tending machines (PTM), fully controlled by a
process computer, connected though a central hyper dense phase pneumatic transport
system to alumina & fluoride supply & vented through a duct system to the central dry
scrubbing waste gas cleaning installation.
Operation of pots will be fully automatic and computer controlled. Two level
control is envisaged:-
a) Supervision Level of Potroom: Industrial PCs will be used for the
monitoring and supervision of computer control system of pot lines.
b) Control Level: pot controllers will be used for controlling production
process of pots.
Data communication between supervision level and control level will be through
Local Area Network bus constituted by intelligent communication boards.
Description of Control Functions
a) The following major functions shall be realized by the Pot Control System:-
Data collection & treatment
Pot resistance (voltage) control (lifting anode and lowering anode)
Normal Feed Control
Anode Effect inspection, alarm and treatment control
Anode Effect forecast and feeding control
Bus bar raising tracing
Alumina concentration control
Tapping inspection and control of pot resistance after tapping
Anode changing inspection & control of pot resistance after anode
changing
Voltage fluctuation inspection and control of pot resistance after
voltage fluctuation inspection
Aluminium fluoride feed control
Pot control during start-up
b) Main functions of master computers
Setting & modification of parameters
Preparing & printing of shift-wise, day & month-wise report data and
work order for the next shift
Displaying & printing comprehensive historical curves
Automatic annunciation / alarm of important information
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-26
5.3 Existing Facilities within Vedanta Aluminium Smelter Plant
5.3.1 Lightning Protection System
Adequate lightning protection facilities are provided as per the applicable Indian
codes of practice.
5.3.2 Fire Protection System
Adequate fire protection system is provided as per the applicable Indian codes of
practice and Tariff Advisory Committee (TAC) guidelines. Also an appropriate On-site
Disaster Management Plan (DMP) is implementing for the plant which is included in
this report.
5.3.3 Road and Site Drainage
Adequate circular and other roads are provided for smooth operation and effective
emergency response. The drainage network is constructed to prevent water
accumulation in the plant area and to avoid mixing of plant effluent with storm
water.
5.3.4 Communication
Independent telephone exchange is provided to cater the requirement of the smelter
& CPP plant complex. Intercom network is served as the main communication link for
internal communication of the plant & township.
5.3.5 Water Receipt & Storage System
Raw water is received from water reservoir through pipe lines. The drinking water
pumped and stored in overhead tanks. From overhead tank the drinking water is
supplied at various points of smelter. However, for fire water system, separate lines
are to be laid from water reservoir.
For cooling water system, only filtered water as make-up water is provided at the
battery limit of cooling towers. For the distribution of make-up water, one overhead
tank is provided at the smelter and supplied through separate line.
Cooling Water System
From the underground storage tank, filtered water will be pumped to an overhead
tank. The overhead tank will supply make-up water to various cooling towers in
smelter plant and also be an emergency source of water supply to critical units in
case of power failure.
Drinking Water System
Filtered water of underground storage tank will be chlorinated through gravity flow
type chlorinator for dosing of chlorine in water. The distribution of drinking water will
be done by gravity from the overhead storage tank through a network of G.I pipes.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-27
Fire Water System
The system will consist of storage, pumping station and the firewater main ring with
hydrant installed along the road side to fight fire in the off-site areas, and the rising
main will be provided with isolation valves inside the buildings.
Sprinkler Water System
The system consists of storage, pumping station, sprinkler and piping manifolds etc
and will cover the following areas viz., Paste plant, Solid pitch storage and Green
anode storage.
5.3.6 Compressed Air
Compressed air system is used as plant air for the service applications, and as
instrument air for plant instruments. The overall system is consists of 12 High
Pressure compressors and 5 Low pressure compressor. All are power driven. Also Air
dryers are provided to supply dry air to the distribution network.
6.0 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
The existing aluminium smelter complex and captive power plant area is 2061.41 acres
and the proposed expansion of smelter plant is about 6.0 ha (15 acres). The total
industrial area after proposed expansion will be 2,061.41 acres.
6.2 Residential Area (Non processing Area)
Housing of additional man power will be taken care of by expansion of existing township
or available social infrastructure in the vicinity.
6.3 Greenbelt
The greenbelt in the Smelter and CPP is around 527 acres. The greenbelt and green
coverage will be strengthened.
6.4 Connectivity
The proposed expansion project is well connected with road network. Nearest road is
State Highway, SH-10 which is 1.1 km away from the site connecting Jharsuguda and
Sambalpur. The nearest railway station is Jharsuguda Railway Station at a distance of
3.9 km in NNW direction of the proposed expansion project site.
6.5 Drinking Water Management (Source & Supply of Water)
Water is sourced from Hirakud reservoir. The raw water is treated in clarifier and
filter beds. The total additional water requirement (fresh and recycled) is about 576
m3/day.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-28
6.6 Sewage System and Industrial Waste Management
Expected quality of wastewater generated is given in Table-15. Existing ETP will be
augmented with Reverse Osmosis (RO) proposed to be treated and reused in the
process.
TABLE-15
EXPECTED QUALITY OF WASTEWATER
Sr.
No.
Parameter Unit Raw
wastewater
Treated
Wastewater
Permissible Limits as
per GSR 422 (E) for
On-land Discharge (Irrigation)
1 pH - 5.5 to 9.0 6.0 to 8.5 5.5 to 9.0
2 Suspended Solids mg/l 100 to 500 < 100 200
3 Oil & Grease mg/l 10 to 200 < 5 10
4 Total Dissolved Solids
mg/l 500 to 10000 < 1000 --
5 BOD mg/l 250 to 350 < 30 100
6 COD mg/l 450 to 600 < 100 --
ETP and STP has been designed suitably. Treated sewage is conformed to the standards
for land application. Oil and grease removal system is provided. Regular monitoring of
ground water and surface water as part of the post-project monitoring is carried out.
Oily wastewater generated due to oil spills is collected in separate tanks which is having
skimmers. The skimmed waste oil from each of these areas is sent back to the oil
storage tank and oil free wastewater is pumped to ETP.
6.7 Solid Waste Management
With expansion of the plant, the solid wastes will marginally increase which will be
taken care in ongoing solid waste management system Butts & green scrap will be
recycled in GAP.
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
During acquisition of 2061.41 acres of land for Smelter & its infrastructure R & R plan
was duly considered and was utilized for R & R plan for development of necessary R & R
infrastructure.
As the proposed 2 LTPA expansion facility will be within existing plant premises and no
additional land acquisition is contemplated, issues of Rehabilitation & Resettlement do
not arise.
8.0 PROJECT SCHEDULE & COST ESTIMATES
The estimated capital cost is Rs. 1,240 Crores for the additional 2 LTPA Aluminium
smelter capacity.
There is no requirement of land acquisition. 2 nos. CPC silos & 2 nos. of pitch tanks
will be installed.
Pre-Feasibility Report for the Proposed Expansion of Aluminium Smelter Production Capacity from 16 LTPA smelter and 1215 MW CPP
to 18 LTPA smelter and 1215 MW CPP at Bhurkamunda Village,
Jharsuguda District, Odisha
Vedanta Limited PFR-29
Pot line refurbishment will be done in the existing pot rooms together with utility tie
in facilities. GAP & Rodding plant will be executed on EPC basis. The estimated
hardware costs are as follows:
Sr.No. Facilities Cost (in Crores)
1 GAP (on EPC basis & the tie in with utilities). 350
2 Rodding Plant (on EPC basis) 250
3 Refurbishment/Construction of new pots along with
utility tie-in facilities
320
4 Infrastructure 220
5 Equipment for Pollution control Inclusive above
6 Contingency, Interest 100
Total Rs. 1240 Crores
The proposed expansion project construction activities will start after obtaining all
necessary statutory clearances from concern authorities and construction will be
completed within the 24 months.
9.0 ANALYSIS OF PROPOSAL
The proposed expansion project is likely to generate direct employment opportunities
during the operation of plant and indirect employment opportunities in the field of
transportation of employees, transportation of raw material & product to nearest port,
development of ancillary units and canteen services and greenbelt development work
etc.
The major advantage in planning the proposed expansion of aluminium smelter plant
is summarized below:
The land available is in possession of Vedanta and within their plant.
Water required will be availed at site from Hirakud Reservoir.
Existing Captive Power Plant (CPP) and other infrastructural facilities are
available.
As part of the Corporate Social Responsibility (CSR), Vedanta is to take steps in
developing education, health, infrastructure development, women empowerment,
sports and vocational training facilities etc.