1. PRE-FEASIBILITY REPORT
FOR
IOB GALAXY II
(GROUP HOUSING PROJECT)
(EXPANSION OF IOB GALAXY BUILDING PROJECT) ( Plot Area : 43728.98 Sqm. ’ Builtup Area : 224576.57 Sqm.)
At:
Painal, Bihta, Dist. Patna (Bihar)
OF
M/s ASHIRWAD ENGICON PRIVATE LIMITED Gokul Marg
House No.1 , North S.K. Puri
Boring Road
Dist.: PATNA - 800 001
( BIHAR )
INDEX
Contents Page Nos.
1. Executive Summary 01
2. Introduction of the Project / Background Information
02
3. Project Description 05
4. Site Analysis 08
5. Planning Brief 10
6. Proposed Infrastructure 10
7. Rehabilitation and Resettlement (R & R) Plan 11
8. Project Schedule & Cost Estimates 11
9. Analysis of Proposal 12
Page 1 of 20
1. Executive Summary:
The project involves expansion of “IOB Galaxy Building” project by
construction of additional buildings including LIG and EWS residential
blocks, in the name of “IOB Galaxy II”. The proposed project is coming up at
Mauza : Painal, Block Bihta, Dist. Patna, State Bihar at Khata No. 2317,
2330, 2338, 2038, 724, 704, 1983, 2298, 2305, 1987, Plot Nos. 8647, 8648,
8649, 8650, 8658, 8659, 8643, 8644, 8645, 8389, 8390, 8391,8392. Geo
coordinates of project area are, latitude 25°34'42.38"N & longitude
84°57'11.94"E.
SEIAA, Bihar has granted EC for earlier project “IOB Galaxy Building”
(Proposal No. SIA/BR/MIS/127441/2019) vide F. No. SIA/8(a)/699/19 Dt:
23.07.2020, having 39273.06 Sq. M. land area & built-up area 146136.87
Sq. M. as B2 category project under Sl. 8(a) of Schedule of EIA Notification
2006 and amendments thereof.
Now, total land area of the project is 43728.98 Sq. M. and total built-up area
of the project will be 224576.57 Sq. M. (including above referred EC granted
project). Total Cost of Project will be Rs. 300 Crores. Thus, as per Schedule
of EIA Notification 2006 and amendments thereof issued by Ministry of
Environment, Forests & Climate Change, Govt. of India present expansion
project comes under Sl. 8(b) as ‘B1’ category project. Salient Features of the
project is as under ;
Total plot area : 43728.98 sq. M.
Plot area for Group housing & LIG : 40652.34 sq. M
1.Tower G (G+19 ) 30186.23 Sq. M.
2. Tower I (G+19 ) 30186.23 Sq. M.
3. Tower J (S/G+19 ) 23076.42 Sq. M.
4.tower K (S/G+8 ) 10070.57 Sq. M.
5. Tower L (G+8 ) 14345.44 Sq. M.
6. Tower M (S/G+14 ) 17138.74 Sq. M.
7. Tower M (S/G+14 ) 17138.74 Sq. M.
8. Tower H (LIG block) (G+16) 10590.66 Sq. M.
Total group housing & LIG built- up area 152733.03 Sq m
Total parking area (Stilt + both basement) 60160.24 Sq. M
Page 2 of 20
Total built- up area area including parking) 212893.27 Sq. M
Total no. of flats in group housing 1432 nos.
Total no. of flats in LIG 170 nos.
EWS plot area : 3076.64 sq. M.
Tower O (EWS block) (S+13) 10726.35 sq. M.
Total Parking area (Stilt) 956.95 sq. M
Total Built- up area area including parking) 11683.3 sq. M
Total No. Of Flats in e.w.s 274 nos.
Total built- up area 224576.57 sq. M.
Total no. of flats (Group Housing + LIG + EWS )
1876 nos.
FAR
Permissible : 3.5 (142283.19 Sqm.)
Proposed : 3.49 (142142.37 Sqm.)
Green Area 13191.10 Sqm. (30.15% of Plot
Area)
Maxm. height of buildings 57.10 m.
Parking Facilities 61117.19 Sq. M. (Basement & Stilt)
Power Requirement & Source
5000 kW sourced through
South Bihar Power Distribution Co. Ltd.
Water Requirement & Source
Total Requirement : 1299 KLD
Fresh Water : 819 STP Treated Water Recycle : 480
Waste Water Treatment & Disposal
1300 KLD STP will be installed for waste water treatment and treated water will be recycle
and reuse for toilet flushing, car washing, Fire Water Tanks
and Green area irrigation.
2. Introduction of the Project/Background information:
(i) Identification of Project & Project Proponent.
Project :
The project involves expansion of “IOB Galaxy Building” project by
construction of additional building including LIG and EWS residential
blocks, in the name of “IOB Galaxy II”. The proposed expansion project is
coming up at Mauza : Painal. Khata No. 2317, 2330, 2338, 2038, 724,
Page 3 of 20
704, 1983, 2298, 2305, 1987, Plot Nos. 8647, 8648, 8649, 8650, 8658,
8659, 8643, 8644, 8645, 8389, 8390, 8391,8392.
Project Proponent :
Ajay Singh Managing Director Ashirwad Engicon Pvt. Ltd.
Gokul Marg House No. 1 North S.K. Puri
Boring Road PATNA – 800 001
(ii) Brief description of nature of project:
IOB Galaxy II group housing project involves construction of residential
flats including LIG and EWS Flats. In the proposed project total 1876
nos. residential flats will be constructed out of which 170 nos. LIG Flats
and 274 nos. EWS flats. Total land area of the project is 43728.98 Sq. M.
and total built-up area of the project will be 224576.57 Sq. M.
(iii) Need for the project and its importance to the country and or region
Group Housing project consists of residential infrastructure development
project. Adequate housing facility is the basic need for all sections of
society and the proposed project will cater to the needs of all section of
society including lower income group (LIG) and economically weaker
section (EWS). Additionally, proposed project will generate employment
opportunities in the direct and indirect form for locals.
(iv) Demand and Supply Gap
Now a days, housing development projects are one of the leading growth
sector in India. This sector generates revenue for Govt. and employment
opportunities. The government is now collaborating with private builders
and developers under a public-private partnership (PPP) model to make
‘Housing for All by 2022’ a reality. Many developers have responded
positively, which is not surprising. It is no secret that affordable housing
promises a lot of growth for all concerned.
Page 4 of 12
Google Imagery Showing Site Location
Page 5 of 12
(v) Imports vs. Indigenous Production:
Not Applicable, this is a group housing project only.
(vi) Export Possibility:
Not Applicable, this is a group housing project only.
(vii) Domestic/Export Market:
Not Applicable, this is a group housing project only. No export is
envisaged.
(viii) Employment Generation (Direct & Indirect)
The proposed production will generate direct employment for more than
50 nos. of person in the form of security and maintenance staffs and
more than 100 nos. in the form of indirect employment.
3. Project Description:
(i) Type of project including interlinked and inter dependent project:
The IOB Galaxy II project is an infrastructure project involves group
housing project involves construction of residential flats including LIG
and EWS Flats. In the proposed project total 1876 nos. residential flats
will be constructed out of which 170 nos. LIG Flats and 274 nos. EWS
flats. Total land area of the project is 43728.98 Sq. M. and total built-up
area of the project will be 224576.57 Sq. M. There is no interlinked or
inter dependent project.
(ii) Location: The proposed project is coming up at Mauza : Painal, Block Bihta, Dist.
Patna, State Bihar at Khata No. 2317, 2330, 2338, 2038, 724, 704, 1983,
2298, 2305, 1987, Plot Nos. 8647, 8648, 8649, 8650, 8658, 8659, 8643,
8644, 8645, 8389, 8390, 8391,8392. Geo coordinates of project area are,
latitude 25°34'42.38"N & longitude 84°57'11.94"E.
Page 6 of 12
(iii) Details of alternate sites Considered and the basis of selecting the proposed site, particularly the environment consideration gone into
should be highlighted. No alternative site has been considered for the project.
(iv) Size or magnitude of operation:
Total land area of the project is 43728.98 Sq. M. and total built-up area
of the project will be 224576.57 Sq. M.
(v) Project description with process details: (a schematic
diagram/flowchart layout, components of the project)
Total plot area : 43728.98 sq. M.
Plot area for Group housing & LIG : 40652.34 sq. M
1.Tower G (G+19 ) 30186.23 Sq. M.
2. Tower I (G+19 ) 30186.23 Sq. M.
3. Tower J (S/G+19 ) 23076.42 Sq. M.
4.tower K (S/G+8 ) 10070.57 Sq. M.
5. Tower L (G+8 ) 14345.44 Sq. M.
6. Tower M (S/G+14 ) 17138.74 Sq. M.
7. Tower M (S/G+14 ) 17138.74 Sq. M.
8. Tower H (LIG block) (G+16) 10590.66 Sq. M.
Total group housing & LIG built- up area 152733.03 Sq m
Total parking area (Stilt + both basement) 60160.24 Sq. M
Total built- up area area including parking) 212893.27 Sq. M
Total no. of flats in group housing 1432 nos.
Total no. of flats in LIG 170 nos.
EWS plot area : 3076.64 sq. M.
Tower O (EWS block) (S+13) 10726.35 sq. M.
Total Parking area (Stilt) 956.95 sq. M
Total Built- up area area including parking) 11683.3 sq. M
Total No. Of Flats in e.w.s 274 nos.
Total built- up area 224576.57 sq. M.
Total no. of flats (Group Housing + LIG +
EWS ) 1876 nos.
Page 7 of 12
(vi) Raw Material required along with estimated Quantity, likely source, marketing area of final products, mode of Transport of raw material
& finished product. Building materials, viz., Sand, Cement, Aggregates (Fine & Coarse),
bricks and structural steels will be utilized as raw materials for
construction of proposed group housing project.
(vii) Resources optimization/recycling and reuse envisaged in the
project, if any, should be briefly outlined.
Waste building materials will be recycle and reused at project site by
using the same as filling materials to maintain ground level and for
construction of internal roads and pavements.
(viii) Quantity of waste to be generated (Liquid and solid) and scheme for
their management.
Waste water generated from the proposed project will be treated in STP
within premises and treated water will be recycle and reused for toilet
flushing, car washing, irrigation of green belt and green area.
Solid Waste Management:
Due to proposed group housing project, approx. 4.5 TPD of municipal
solid waste will be generated which consists of biodegradable and non
biodegradable waste. Biodegradable waste will be used for biocomposting
and also sold to piggeries and non biodegradable waste will be disposed
off through govt. waste collection system.
Page 8 of 12
4. Site Analysis:
(i) Connectivity:
The proposed project is coming up at Mauza : Painal, Block Bihta, Dist.
Patna, State Bihar at Khata No. 2317, 2330, 2338, 2038, 724, 704,
1983, 2298, 2305, 1987, Plot Nos. 8647, 8648, 8649, 8650, 8658, 8659,
8643, 8644, 8645, 8389, 8390, 8391,8392. Geo coordinates of project
area are, latitude 25°34'42.38"N & longitude 84°57'11.94"E.
Project site is well connected with all country through roads and located
near the Howrah-Delhi Main Line of ECR under Danapur Division.
Project site of connected to NH-30 through Shiwala Bihta Road and
nearest railway station is Neora 3.39 Km. in SW direction.
ii) Land Form, Land use & Land ownership:
Land Form:
The land is agriculture in nature and is under the complete ownership of
Project Proponent.
Classification of land:
The proposed land has been classified as Residential land in approved
Patna Master Plan 2031 of Urban Development & Housing Department,
Govt. of Bihar, issued vide Memo No. 11/N.Vi.Ma.Plan(Samiti)-
17/2014/832/UD&HD/Patna Dt: 28.10.2016.
Land use pattern:
The proposed land will be used only for construction of residential
project.
iii) Topography (along with map):
The area is plain in terrain. Topography map of the project area is
appended on next page.
Page 9 of 12
TOPOGRAPHICAL MAP
Page 10 of 12
5. Planning Brief:
i) Planning concept (type of Industries, facilities, transportation etc)
Town and country planning/Development authority classification.
The project involves expansion of “IOB Galaxy Building” project by
construction of additional buildings including LIG and EWS residential
blocks, in the name of “IOB Galaxy II”. The proposed project is coming up
at Mauza : Painal, Block Bihta, Dist. Patna, State Bihar at Khata No.
2317, 2330, 2338, 2038, 724, 704, 1983, 2298, 2305, 1987, Plot Nos.
8647, 8648, 8649, 8650, 8658, 8659, 8643, 8644, 8645, 8389, 8390,
8391,8392. Geo coordinates of project area are, latitude 25°34'42.38"N &
longitude 84°57'11.94"E.
ii) Population Projection:
During both construction and operation phase of the project manpower
from local nearby areas will be preferred.
iii) Assessment of Infrastructure demand (physical & social) :
2-lane road is already existing in front of the project which connects the
project site from District Headquarter and rest of the country. Clean
drinking water and medical facilities will be provided to the workers
during construction stage.
6. Proposed Infrastructure:
i) Industrial Area (Processing Area):
Not Applicable, this is an group housing project for construction of
residential flats only.
ii) Social Infrastructure:
Medical: - First aid facility and ambulance will be provided.
Drinking Water :- Drinking water will be provided through borewells.
Page 11 of 12
iii) Sewerage System:
Internal sewerage system will be developed and will be connected to govt.
sewerage system.
iv) Solid Waste Management:
Due to proposed group housing project, approx. 4.5 TPD of municipal
solid waste will be generated which consists of biodegradable and non
biodegradable waste. Biodegradable waste will be used for biocomposting
and also sold to piggeries and non biodegradable waste will be disposed
off through govt. waste collection system.
v) Power Requirement & Supply/Source:
5000 kW power is required for proposed group housing project which will
be sourced through SBPDCL. For meeting the emergency power
requirement during power failure 2 Nos. 1000 KVA DG Set and 4 Nos.
500 KVA DG Sets will be provided.
7. Rehabilitation & Resettlement (R & R) Plan:
R & R plan is not required as the land for the project is under full
ownership of project proponent.
8. Project Schedule & Cost Estimates:
i) Likely date of start of construction & likely date of completion:-
Construction of the project will be started as soon as the environment
clearance will be granted.
ii) Estimated Project cost along with analysis in terms of economic
validity:
Total cost of the proposed group housing project will be approx. 300
crores.
Page 12 of 12
9. Analysis of Proposal (Final Recommendation):
(Financial & Social benefits with special emphasis on the benefit to
the local people including tribal population, if any, in the area.)
The project is group housing project which provides residential flats for
all section of society including low income group (LIG) and economically
weaker section (EWS). It is important for the area/region for improving
the socio-economic conditions of the local population due to generation of
employment opportunities.
* * * * *