FOR INFORMATION | NGĀ MŌHIOTANGA · 7/29/2020 · PORTFOLIO HOLDER/S Mayor Policy portfolio...
Transcript of FOR INFORMATION | NGĀ MŌHIOTANGA · 7/29/2020 · PORTFOLIO HOLDER/S Mayor Policy portfolio...
Whaarangi 1 | 6 M 2787877
FOR INFORMATION |
NGĀ MŌHIOTANGA
TO Mayor and Councillors
AUTHOR Nina Murphy
STRATEGIC PLANNER
FILE REFERENCE Document: 2787877
Appendix A: Project Reports
PORTFOLIO HOLDER/S Mayor
Policy portfolio
MEETING DATE 29 July 2020
SUBJECT Wharekawa Coast 2120 – Project budget update
RECOMMENDATION | TE WHAIKUPU
THAT the report be received.
1 PURPOSE | TE ARONGA
This report provides Council with further detail on the budget for the Wharekawa Coast 2120
project and outlines the potential for overspend.
2 BACKGROUND | TE KŌRERO Ā MUA
In November 2018, Council approved a total budget of $290,000 for the community plan
project, to be spent over three years (2018/19-2020/21). Refer Council resolution C18/586.
Council then approved a further $30,000, for the community plan project, for the 2020/21
year, as part of the Annual Plan process, thus bringing the total budget to $320,000. This is
detailed further in section 3 below.
In June 2020, Council considered a report providing an update on the Wharekawa Coast 2120
project. In this report, the budget estimate and actual spend to date for the 2018/19 and
2019/20 financial years were presented, as well as the budget estimate for 2020/21. Refer
extract below:
Council Agenda - 29-07-20 Page 114
Whaarangi 2 | 6 M 2787877
As the 2019/20 financial year has now ended, we can report that spending on the Wharekawa
Coast 2120 project was $5,000 under budget ($165,000). The remaining amount will be
formally requested to be carried forward to 2020/21 as part of a combined organisational wide
report expected in August 2020.
3 BUDGET 2020/21
Of the $120,000 budget for 2020/21, $90,000 is for the Project Advisor and external
facilitators (Simon Bendall and staff from Traverse Environmental). The remaining $30,000 is
for payment of meeting allowances for iwi representatives, and community panel members
(except for those whose attendance is paid for by the organisation they represent e.g. DOC),
and associated expenses such as venue hire and refreshments.
Note, that the $30,000 for iwi representatives and the community panel was not budgeted for
within the original project, and the amount exceeded the Council’s budget available for
democracy services. Refer table below.
These extra costs were considered by the Wharekawa Coast 2120 Joint Working Party (Joint
Working Party) prior to being added to the project budget as part of the 2020/21 Annual Plan
process.
Waikato Regional Council has contributed $15,000 to the project for implementing their risk
assessment methodology, as a case study.
Budget 2020/21 Descriptor
Original Budget (Nov 2018) $90,000 Cost of project advisor and external
facilitators
Amount added through
Annual Plan (April 2020)
$30,000 Costs associated with iwi
representatives and community panel.
TOTAL $120,000
4 POTENTIAL OVERSPEND
The project is being undertaken over three years and covers complex issues. It requires
specialist reports to be prepared to allow us to answer questions such as:
what are the natural hazards for this area?
what will be affected by these natural hazards (e.g. cultural values, social values, council
and community assets)?
what can we do about it (options + option analysis)?
Council Agenda - 29-07-20 Page 115
Whaarangi 3 | 6 M 2787877
A list of the project reports and who is responsible for preparing them is in Appendix A.
Note, that many of these reports are being prepared by the Waikato Regional Council’s staff or
consultants.
Our Council is contributing $320,000 to the project, as noted above, paying for most of the
cost of the Project Advisor and external facilitators, and for the iwi representatives meeting
allowances and community panel expenses.
The potential for overspend on this project may arise when specialist information is required
that has not been foreseen in the original budget and project plan, such as when the
community panel seeks further detailed information.
The cultural values assessment report is considered a key report for this project, however, it
was not included in the original budget (but was in the project plan); due to the uncertainties
around gaining tangata whenua input in the project. After scoping what the cultural values
assessment will cover and discussions with iwi and mana whenua representatives, staff advise
that the cost can be met from existing operational budgets.
There are no other reports/information identified at this stage which require further funding
outside of the budget. In the first instance, the in-house resources of both councils will be used
wherever possible.
The process for identifying and seeking further funding for the project, is that a proposal be
presented to the Joint Working Party for their consideration, and if agreed a recommendation
be made to the partner councils to seek further funding, as required.
Further budget provision for implementing the Wharekawa Coast 2120 community plan is
suggested for the Long Term Plan 2021-31 (LTP). This will be considered by Council as part of
the LTP process.
NEXT STEPS | TE ARA KI MUA
Timeframe Action Comments
Ongoing Any requests for further funding will be
presented to the Joint Working Party
for their consideration, in the first
instance.
Further updates on the
project/budget will also be
provided to Council on an ongoing
basis.
Approval
Prepared by Nina Murphy
Strategic Planner
Approved by Peter Thom
Group Manager Planning & Environmental
Council Agenda - 29-07-20 Page 116
Whaarangi 4 | 6 M 2787877
APPENDIX A - PROJECT REPORTS
Subject Title Author Description Status
Backg
ro
un
d R
ep
orts
Wharekawa Coast 2120
- Community Overview
Nina Murphy -
Hauraki District
Council (HDC)
This document is a high-level stock take of information
relating to Wharekawa Coast 2120. It provides a
summary of; the demographics of the area, land use
and zoning, environmental features, co-governance, and
infrastructure.
Final Draft
Wharekawa Coast 2120
- Economic Profile
Nina Murphy - HDC This report provides an overview of the economy of the
Wharekawa coast area. It covers employment and
industry trends, including identifying factors that are
contributing to comparative advantage in the area e.g.
natural resources, as well as what are the limitations to
work/business opportunities, and what are the future
trends for the economy of the area.
Final Draft
Natu
ral
Hazard
Rep
orts
Wharekawa Coast 2120
Coastal Processes and
Hazards
Dr Terry Hume –
Hume Consulting Ltd
(funded by Waikato
Regional Council
(WRC))
An assessment of coastal drivers and hazards in respect
to the coastal geomorphology in order to inform a
community strategy so that discussions and adaptive
planning options are based on a common understanding
of coastal processes.
Final draft – awaiting
external peer review.
Circulated to
Community Panel.
Rapid flood hazard
assessment of Hauarahi
Stream
Duncan Grant,
Sophie Marsh &
Adam Munro - WRC
An initial assessment on:
which areas are at most risk of flooding from the
Hauarahi Stream;
how the severity of flooding changes with different
frequency flood events; and
how the severity of flooding may change with the
projected effects of climate change.
Final draft – awaiting
external peer review.
Circulated to
Community Panel
Flood risk information
report
Rick Liefting – WRC Compilation of hazard information supplied through the
Community Panel. Information is likely to be primarily
flood hazard or impact related.
Draft awaiting final
confirmation of
information from the
Community Panel
Council Agenda - 29-07-20 Page 117
Whaarangi 5 | 6 M 2787877
Subject Title Author Description Status
Im
pact
Assessm
en
ts
Social impact and
implications of sea-level
rise on communities
along the Wharekawa
Coast
Cerasela Stancu &
Tasman Gillies -
EnviroStrat (funded
jointly by HDC and
WRC)
Identification of social issues, concerns and outcomes
related to coastal hazards before an intervention is
planned to aid in development of effective solutions.
Final
Cultural Values/Impact
Assessment
TBC Possible report which provides an overview of cultural
values in the Wharekawa Coast 2120 project area and
identifies potential impacts on cultural values from
natural hazards.
Not yet commissioned
Ecological Values
Assessment
Stephen Hunt &
Michael Townsend -
WRC
Report which provides an overview of ecological values
in the Wharekawa Coast 2120 project area and identifies
potential impacts on ecological values from natural
hazards.
Draft – currently
being internally peer
reviewed
In
form
ati
on
Rep
ort
Land stability Phil Mourot – WRC A broad scale assessment of landslide susceptibility
within the Wharekawa Coast 2120 project area. The
report uses geological and geomorphological data to
identify which areas are particularly susceptible to
landslide hazards. This initial assessment refers to the
downward movement of large masses of rocks and soil.
Heavy rainfall and earthquakes are the most common
triggers for landslides.
Draft – currently
being internally peer
reviewed in WRC
Coastal Compartments Rick Liefting – WRC Delineation of compartments along the study area to
define similar coastal process areas. The compartments
also include river catchments. The compartments are to
be used to align areas that have similar processes,
hazard, impacts and management options. Output is a
GIS layer/map and short methodology report.
Draft completed -
circulated to
community panel
Ris
k
Assessm
en
t
Wharekawa Coast 2120
- Natural Hazard Risk
Assessment
Sophie Marsh,
Whitney Mills & Phil
Mourot – WRC
Brings together the natural hazard assessments, impact
assessments and information from the community, and
uses RiskScape to model river flooding and coastal
hazard risk quantitative
Drafting underway
Council Agenda - 29-07-20 Page 118
Whaarangi 6 | 6 M 2787877
Council Agenda - 29-07-20 Page 119
Whaarangi 1 | 11 M 2787657
FOR INFORMATION
NGĀ MŌHIOTANGA
TO Mayor and Councillors
AUTHOR Lukas de Haast
Transportation Manager
FILE REFERENCE Document: M2787657
Appendix A: REG 2018/19 Hauraki District Council RCA Report
Appendix B: Waitawheta Road Bridge Controls Options Study
Report (M2781550)
Appendix C: Whiritoa Lighting Level Review Report
PORTFOLIO HOLDER/S Mayor Adams
Transport portfolio
MEETING DATE Wednesday, 29 July 2020
SUBJECT Transportation Report June 2020
SUMMARY | TE WHAKARĀPOPOTANGA
This report provides the latest information on the Hauraki District Council’s Transportation
activities for the period ending 30 June 2020.
It is noted that all major projects are progressing and that maintenance activities are
recommenced after the COVID19 lockdown and that it had significant effects on delivery and
budgets.
Drought damage to roads on the Hauraki Plains also has a significant effect on delivery of the
Transport Activity at the moment.
RECOMMENDATION | TE WHAIKUPU
THAT the report be received.
Council Agenda - 29-07-20 Page 120
Whaarangi 2 | 11 M 2787657
1 PURPOSE | TE ARONGA
This report provides the latest information on the Hauraki District Council’s Transportation
activities for the period ending 30 June 2020.
2 ACTIVITY UPDATE
2.1 ASSET MANAGEMENT
S17A Review of Land Transport Activity completed and interviews with councillors to be
scheduled.
NZTA endorsed the Land Transport Procurement Strategy in June. The Land Transport
Procurement Strategy is a requirement for funding from NZTA.
Approval was given for Visual Road Condition Ratings to proceed under Level 3. This
work is still ongoing.
Traffic Counting was halted as traffic movements under Level 3 will not be representative
of long term trends. The traffic counting programme has not started up yet.
All high speed data collection is completed and received, except for detailed cracking
data which is still being processed.
LTP work on finalising the Activity Management Plan is continuing
The first dTIMS trigger model was received and is currently being field validated. The
output of the trigger model is a forecast of treatments expected to be required on each
road section in the next ten years.
Work to compile and prioritise all Minor Projects from potential project lists into a
Forward Works Programme for the LTP is progressing well with Engineering decision
making criteria being finalised.
As resources becomes available within the Transport Team additional in-house
assessments of the HSD will also be done to improve our understanding of the
pavement deterioration trends. Specific emphasis will be placed on understanding the
relationship between pavement deterioration, seal age and underlying soil types.
General performance of Contractor with regard to cyclic activity has been deficient in
some areas. This is being reflected in performance monitoring results. Deficiencies in
cyclic activities are to be addressed in workshops with the Contractor.
The Road Efficiency Group (REG) published a new report using individual performance
results and evidence for each of New Zealand’s 67 Road Controlling Authorities. This
report is included in Appendix A.
Department of Conservation requested that gates are to be installed on Maratoto Rd and
Taieri Rd to prevent motorised traffic to enter the Public Conservation Land.
Discussions on this proposal are ongoing.
Preparation of a retrospective resource consent for the construction of a rock revetment
wall next to East Coast Rd in Kaiaua is still ongoing.
2.2 CAPITAL PROJECTS
2.2.1 PROJECT ACHIEVEMENTS
Table 1 below shows the progress on the main capital projects scheduled for the 2019/20
financial year.
Council Agenda - 29-07-20 Page 121
Whaarangi 3 | 11 M 2787657
Table 1: Main Capital Projects – 2019/20
Budget, Programmes and
Projects
Progress
% complete
Comments / explanations (if off-track)
Reseals – 2019/20 100% Reseals completed in January 2020
Pavement Rehabilitation –
2019/20 100%
Construction of Pavement Rehabilitation
sections on Old Tauranga Rd, Central Rd
South and Kaihere Rd are completed.
Pavement Rehabilitation –
2020/21 95%
Awaiti & East Coast Rd design and contract
documentation is complete. Will be ready to
go out to market in July with construction
scheduled for summer of 20/21.
Due to large quantity of immediate
pavement repairs needed on Pipiroa rd
because of drought damage the road is
currently treated as heavy maintenance and
not as a pavement rehabilitation project.
The treated areas will be included in the
2020/21 reseal programme.
Minor Improvements (2019-
20) 60%
Progress on current projects:
Station Rd/SH25 intersection
pedestrian crossing construction
completed.
Waitete Rd footpath between Kimberley
and Rata Streets. Construction to
start after Thorn Rd footpath is
completed.
Top 11 Safety Risk roads – low cost
treatments of 9 roads: Roadmarking
partially completed and signage
installation completed
Mahuta Rd North Bridge No. 2:
Approved to proceed to detail
design.
Network wide assessment and making
safe of slips on unsealed roads – final
report received. Site instructions to
the Contractor to be processed.
Signage to indicate the end of
maintained network – design stage
Warning signage at Kindy’s and
Playcentres – completed
New Kea crossing at school in
Coronation Rd – completed
Potential upgrades to existing Kea
Crossings in Norwood Ave – updated
changes to intersection with
Ohinemuri Place - presented to
Ward. Decision report required.
Whiritoa streetlighting upgrade – light
survey of entire town are completed
and mapping work completed. The
Lighting Review Report is attached in
Appendix C. Detail design of infill
lighting on Whiritoa Beach Rd and
Marlin Place to progress.
Council Agenda - 29-07-20 Page 122
Whaarangi 4 | 11 M 2787657
Budget, Programmes and
Projects
Progress
% complete
Comments / explanations (if off-track)
Package of edge lines and centrelines
to be implemented district wide as
part of annual remark –delayed to
next annual remark due to Covid-
19
Speed limit bylaw review (speed
management) – Speed Management
Plan to be done. Discussions on
project plan ongoing
Hauraki/Huirau intersection widening
project – detail design underway
Waitawheta Bridge Minor Safety
Improvements – design being
reviewed
Waitawheta Bridge Long Term Safety
Improvements – options report
received (Appendix B)
Ward Projects 2019/20 100%
Plains Ward:
Kerepehi Town Rd Footpath – Construction
completed
Waihi Ward:
Whiritoa Footpath Renewals: Completed.
Thorn Rd Footpath: 90% completed.
Paeroa Ward:
Queen str footpath renewal completed.
Raroa Rd/Thames Rd footpath renewal and
extension complete
Bridge and Structures
Component Replacement 25%
Design inspections completed and design of
package of high priority works progressing.
Selected projects to be implemented during
current LTP.
Bradford Street Extension 45%
Design and land agreements completed.
Land purchase is currently going through the
process. The tender process is scheduled to
start in July 2020. Construction is planned to
be done in summer of 2020/21 due to land
purchase delays.
Ainslie Rd Footpath Extension
and Streetlighting 65%
Ainslie Rd footpath extension and road
widening related to the new Kindy has been
completed.
The Contractor lodged an application to
Powerco to attach the new streetlights to
the existing power poles.
Mahuta Rd North Underslip 65% The project is currently on hold until after
winter.
Council Agenda - 29-07-20 Page 123
Whaarangi 5 | 11 M 2787657
Progress Key:
= Off track / behind schedule / over budget
= Rescheduled
= Off track but will be back on track soon
= On track
= Completed
2.2.2 PROJECT GOALS FOR NEXT MONTH
The work scheduled for July 2020 is shown in Table 2 below.
Table 2: Capital Work Programme for July 2020
Project Ward Comments
Pavement Rehabilitation –
2020/21 District
Tender process for Awaiti West Rd and East
Coast Rd AWT’s to commence
Minor Improvements District Project designs to continue.
Mahuta Rd North Underslip District Construction to restart in August
Ward projects Wards
Paeroa Ward – No work at the moment.
Waitete and Thorn Rd Footpath construction to
continue
Plains Ward – No work at the moment
Maintenance Contract
Renewals District
Unsealed road re-metalling and culvert
replacement programmes to continue
2.2.3 KEY ISSUES AND RISKS
The following major risks associated with the capital programme have been identified.
Table 3: Capital Programme Risks
Issue or Risk Budget Implications Mitigation Measures
Claims for cost and time
extensions due to CV19
lockdown
The contractor submitted a
claim of approximately $37k
for lost opportunity
The details of the claim is
being evaluated
Council Agenda - 29-07-20 Page 124
Whaarangi 6 | 11 M 2787657
2.3 OPERATIONAL ACTIVITIES
The Government Covid-19 Alert Level reduced from Level 2 to Level 1 in early June 2020,
meaning operational activities began to return to some sort of normality in terms of
importance and priorities. However, there was extra burden on the team as a direct result of
Covid-19 interruptions and drought damage, which were occurring simultaneously. Most
notably, the complicated nature of Covid-19 contractual implications, and planning &
inspections for the additional pavement repairs proposed for completion in the 2020/21
construction season. These repairs include outstanding 2020/21 repairs previously stopped due
to lockdown restrictions, 2021/22 pre-reseal repairs, and drought related repairs.
For the early part of June 2020, both the road and street lighting maintenance contractors kept
in place Level 3 Health & Safety protocols for field staff during Alert Level 2. However, the drop
to Alert Level 1 negated the need for Covid-19 related Health & Safety protocols for the bulk of
June 2020.
A summary of routine operational maintenance work done during the month of June 2020 is
shown in Table 4, with further discussion on other operational activity following.
Table 4: Ongoing cyclic maintenance activities during June 2020
Activity Description Unit June 2020
Quantity
Sealed pavement pothole repairs ea 70
Unsealed pavement pothole repairs ea 128
Unsealed road additional aggregate (Gobles Rd) m3 186
Storm water structures checked and cleared (Drainage routine
maintenance)
*Note: Additional patrols in June 2020 due to Autumn leaf fall and
prolonged mild Autumn conditions this year.
ea 309
Detritus and slip removal for sealed surfaces and rural lined &
unlined channels
m3 20
Sign routine maintenance (replace sign, reinstate pole, rehang
sign)
ea 20
Edge marker post (EMP) replacement ea 44
Raised pavement marker (RPM) maintenance
*Note: 1120 EMPs replaced in May 2020 following night inspection
observations
ea 0
Volume of litter & refuse removal m3 6
Roadside mowing m 342,959
Upcoming Pre-reseal and Drought Repairs
As touched upon earlier, the upcoming construction season (2020/21) pavement repairs
include consideration of:
20/21 Pre-seal repairs (including any new and rework sites);
21/22 Pre-seal repairs; and
2020 Drought repairs.
A brief summary of each aspect is detailed below.
o 20/21 Pre-seal repairs:
Due to the impacts of Covid-19 restrictions on construction progress, 2020/21
pre-reseal repairs were not completed in full during the last construction season.
As well as this, following a review to consider drought impacts, there are also
changes to the proposed 20/21 reseal sites. This affected the scope and location
Council Agenda - 29-07-20 Page 125
Whaarangi 7 | 11 M 2787657
of pre-reseal repairs, an operational activity, with several roads now deemed too
damaged for a reseal treatment. Instead, these roads will have drought repairs
completed by way of stabilisation patches and a second coat seal within 12
months to further waterproof the pavement. The removal of these sites, and
addition of several alternative sites, has resulted in an approximate additional
6,000m2 of stabilisation repairs to 20/21 reseal sites.
o 21/22 Pre-seal Repairs:
The pre-reseal repairs for 21/22 are yet to be quantified. It is expected these will
be marked out on the ground and associated schedule compiled during August
2020.
o 2020 Drought repairs:
The road maintenance contractor completed 3,610m2 of pavement repairs in June
2020 on several roads identified as a high safety issue, including:
Front Miranda Rd;
Hauraki Rd;
Moehau Rd;
Orchard East; and
River Rd (Plains).
Programming of drought related pavement repairs continued through June 2020,
although progress was again delayed by wet weather conditions. The quantum
of work and potential cost implications will be reported upon completion of the
programming in full.
Emergency Response
o Back Miranda Rd Waitakaruru - surface debris removal;
o Cadman Rd Waihi – attend to illegally dumped refuse scattered over road;
o Orokawa Rd Heights Waihi - tree blocking road;
o Pukekauri Rd Waitawheta – slip debris removal;
o Pukekauri Rd Waitawheta - ongoing temporary traffic management monitoring on
culverts currently being designed for replacement;
o Toft Rd Kaiaua – delineate flooding hazard;
o Trig Rd North – inspect reported cones blocking road (no issue found on
inspection);
o Trig Rd South Waihi – inspect reported pothole hazard (no pothole hazard found
on inspection);
o Victoria St Waihi - manhole cover reinstatement; and
o Wires Rd Maratoto - unblocking ford.
Rural roadside spraying
o A full network roadside weed spraying round was completed in June 2020
(knapsack spraying was completed in June 2020 to get to areas which could
not be reached by the machinery boom arm).
Bridge Works
o Routine type maintenance:
The road maintenance contractor continues to complete bridge works across the
district for routine type maintenance identified during structural inspections.
o Kaihere Rd Bridge No.1:
Repair works substantially completed. The bridge was still under a temporary
speed limit which was left in place until final surfacing can be reinstated on
two of the replaced deck units to restore road crossfalls. Several surfacing
options are being considered by the team.
Unsealed Roads
o A full grading round was completed in June 2020, noting that Mangawhero Rd was
revisited.
Council Agenda - 29-07-20 Page 126
Whaarangi 8 | 11 M 2787657
Signs and delineation
o A signs safety and road marking upgrade works package is ongoing and largely
completed (approximately 90% complete). This involves linemarking and
signage (delineation) improvements on high volume roads, including:
Awaiti Rd;
Bush Rd (Plains);
East Coast Rd;
Golden Valley Rd;
Hauraki Rd;
Kaihere Rd;
Pipiroa Rd;
Pukekauri Rd; and
Waihi Beach Rd.
o The annual line marking remark was completed in May 2020 after initially being
disrupted by Covid-19 restrictions.
Ultra-Fast Broadband (UFB) Rollout
o A number of reinstatement works, most notably within the Paeroa CBD, have been
identified as unacceptable. Council is working with the Contractor to improve
workmanship.
o QA and Inspection Support is being provided by WSP. This includes provision of
project management and coordination for the Paeroa UFB project, daily site visits
and dealing with issues as needed.
o Council are still yet to sign off completion certification for any of the townships in
the district. The transport team continue inspections while also considering
outstanding issues with the Waters Services Team, which largely relate to
seeking reimbursement for the costs of utilities strikes.
3 NEXT STEPS | TE ARA KI MUA
In conclusion it is noted that all major projects are progressing and that maintenance activities
are implemented on a monthly basis.
It is hereby recommended:
THAT the report be received
Approval
Prepared by Lukas de Haast
Transportation Manager
Approved by Adrian de Laborde
Group Manager - Engineering Services
Council Agenda - 29-07-20 Page 127
Whaarangi 9 | 11 M 2787657
APPENDIX A: REG 2018/19 Hauraki District Council RCA Report
Council Agenda - 29-07-20 Page 128
6/17/2020 Page 1
1/1
Co-Investor Assurance
Source: Waka Kotahi, Audit and Assurance, Technical Audit Report
Dec-14
Service Performance
Delivery and Achievements
Activity Management
Transport Outcomes
Ride quality, pavement and surfacecondition (peer group lighter)
90%
95%
2016 2018
Surface Pavement Ride
All transport activities
$0M
$5M
2016 2018
New roads and road improvements(>$1M ea)
$0.0M
$0.5M
$1.0M
2016 2018
Road maintenance, operations andrenewals
$0M
$5M
2016 2018
Road safety promotion
$0.0M
$0.1M
2016 2018
TA Peer Group
Investment management, network andproperty management
$0.0M
$0.5M
$1.0M
2016 2018
TA Peer Group
New and improved walking and cyclingfacilities (excl. low cost <$1M, low risk)
$0M
$1M
2016 2018
TA Peer Group
Four grades: l Effective l Some improvement needed l Significant improvement needed l Unacceptable l Not available
New and improved roads and bridges
-1
0
1
-1
0
1
Roa
d La
ne k
m
Brid
ge L
ane
m
2016 2018
Roads Bridges
Pavement rehabilitation (lane kms)
0
5
10
2016 2018
Planned Actual
AMP reflect network needs
Total expenditure / length ($1000 / km)
$0
$10
2016 2018
TA Peer Group
Contract management
Co-Invested Expenditure
Works Completed Road Condition (Sealed Roads)
Data quality
Source: Waka Kotahi Data and Tools
Maintenance, operations and renewalsexpenditure / length ($1000 / km)
$0
$5
$10
2016 2018
TA Peer Group
Financial management
Cost Efficiency
Type Provision of roads and footpaths
2015/16
2016/17
2017/18
2018/19
PM1 Road safety
PM2 Condition of the sealed road network
PM3 Maintenance of the sealed road network
PM4 Condition of the footpaths within the local road network
PM5 Response to service requests
⬤⬤⬤⬤⬤
⬤⬤⬤⬤⬤
⬤⬤⬤⬤⬤
⬤⬤⬤⬤⬤
Network condition and management
Procurement Professional services
l Target achieved l Partially achieved l Target not achieved l Not reported
Safety performance
Previous audit issues
LGA Non-Financial Performance Measures
Asset management and ONRC atexpected standard
60%
80%
2016 2018
AM Peer AM ONRC Peer ONRC
Planning, Procurement and Data Quality
Source: REG 2018 AMP Assessment, Waka Kotahi 2018 AMP Assessment Source: RCA Smart Buyer Self-Assessment
Healthy and Safe People
Source: REG Annual Data Quality Assessment
Source: Waka Kotahi Crash Analysis System andMBIE Regional Economic Activity Tool
Co-investment planning quality
Total
0
50
2016 2018
TA Peer Group
Planning quality Smart buyer self-assessment
Cycling
0
2
4
2016 2018
TA Peer Group
l Good l Fit for purposel Room for improvement l Not assessed
Walking
0
10
2016 2018
TA Peer Group
Investment Performance
2018/19 Hauraki District Council RCA Report
ate: June 2020 June 2020
v1.0
156No. of bridges
Road
0
20
40
2016 2018
TA Peer Group
l Road maintenance l Walking and cyclingl Road improvement l Other
l Minor improvements (low cost, low risk)l Resilience and improvements l Roads and bridges l Other
l Corridor, environment and drainage l Pavement and seal l Emergency l Other
Source: Waka Kotahi, Audit and Assurance, Procedural Audit Report
Previous audit issues
Nov-19
Source: TA Annual Reports
Page 1 of 2Status: Final for Publication
1.13
2015-25 Long Term Plan 2018-28 LTP
02.00
Annual Targets Achieved
Fatal and Serious Injuries by Mode(No. per 100,000 Population)
l A smart buyer l Developingl Limited l Basicl Not assessed
Technical Audit
Procedural Audit
1
1
Pavement resurfacing (lane kms)
0
50
2016 2018
Planned Actual
Data QualityProcurementActivity Management Planning
Three grades: l Effective l Improvement needed l Unacceptable l Not available
Expenditure, Cost Efficiency, Works Completed and Road Condition
19,950Population
$606GDP ($M)
$239Valuation ($M)
$6.8Expenditure ($M)
$338Expenditure per capita
60%FAR
632Total (km)
519Sealed (km)
113Unsealed (km)
508Rural (km)
124Urban (km)
(Four Grades)
(Three Grades)
Council Agenda - 29-07-20 Page 129
6/17/2020 Page 2
1/1
Customer Outcomes
Technical Outputs
Top 5 TA IndustriesAgriculture
Forestry, Fishing, Mining, Electricity, Gas, Water And Waste Services
Gst On Production, Import Duties And Other Taxes
Rental, Hiring And Real Estate Services
Owner-Occupied Property Operation
Territorial Activity
No. per annum
0
10
2016 2018
TA Peer Group
Network Physical Characteristics
No. per 100 M VKT (personal risk)
0
5
10
2016 2018
TA Peer Group
No. per 1000 km (collective risk)
0
10
2016 2018
TA Peer Group
Ride quality (roughness of the roads)
90%
100%
2016 2018
TA Peer Group
Safety and Amenity
0
500
2016 2018
Source: REG ONRC Performance Measure Reporting
-1
0
1
2016 2018
Peak and average road roughness(NAASRA) (peer group lighter)
80
100
120
140
2016 2018
Peak (85th Percentile) Average
Source: Waka Kotahi Crash Analysis System andData and Tools
Urban % by length
0%
10%
2016 2018
No. bridges
0
100
2016 2018
Total Single lane Timber
Source: Waka Kotahi Data and Tools
Road Network Use
$0M
$5M
2016 2018
GDP by industry
$0M
$100M
2014 2016
Resident population
0K
10K
0
200
400
Popu
latio
n
Annu
al C
hang
e
2014 2016 2018
Population Annual Change
GDP per capita
$0K
$20K
$40K
2014 2016 2018
TA New Zealand
NO RELEVANT DATA AVAILABLE
Guest nights per capita
0
5
2014 2016 2018
TA New Zealand
NO RELEVANT DATA AVAILABLE
New dwellings per 10,000 capita
0
50
2012 2014 2016 2018
TA New ZealandNO RELEVANT DATA AVAILABLE
Source: Waka Kotahi Data and Tools0%
0%
0%
3%
9%
22%
37%
29%
0%
0%
0%
25%
25%
31%
15%
4%
Source: MBIE Regional Economic Activity Tool
Vehicle kilometers travelled (VKT)
0M
50M
2016 2018
$0M
$200M
2016 2018
Economic Activity and Financials
No. of restricted bridges
0
1
2
2016 2018
Speed Weight
Service life
0%
50%
2016 2018
TA New Zealand
Roads, Bridges and Public Transport
Source: Waka Kotahi Data and Tools
Passenger kms
-1
0
1
Service kms
-1
0
1
Public Transport (Region Only)
Roads, Cycleways and Bridges
Source: Waka Kotahi Data and Tools
Source: REG ONRC Performance Measure Reporting
Roads and Bridges
2018/19 Hauraki District Council RCA Report
Date: June 2020 June 2020
v1.0
Source: Waka Kotahi Crash Analysis System and Data and Tools
Loss of control at night
0
1
2
2016 2018
TA Peer Group
At intersections
0
2
2016 2018
TA Peer Group
Involving vulnerable users
0
5
10
2016 2018
TA Peer Group
Loss of control on wet roads
0
1
2016 2018
TA Peer Group
Fatal and Serious Injuries (No. per 100,000,000 Vehicle km Travelled)
Fleet size (No.)
-1
0
1
Road Condition
Source: Waka Kotahi Data and Tools
0%
0%
0%
3%
9%
22%
37%
29%
0%
0%
0%
17%
40%
20%
17%
6%
Source: REG ONRC Performance Measure Reporting
Page 2 of 2Status: Final for Publication
Length vs VKT l Length % l Vehicle kilometers travelled %
Length vs no. of fatal and serious injuries l Length % l Fatal and serious %
High Volume
National
Regional
Primary Collector
Secondary Collector
Access
Low Volume
Arterial
High Volume
National
Regional
Primary Collector
Secondary Collector
Access
Low Volume
Arterial
Fatal and Serious Injuries
Safety
Population
Tourism
Housing
FinancialsEconomic
Roads Cycleways Bridges
Crash Distribution
Journey Distribution
Source: TA Annual Reports
Roading valuation l Total estimated replacement cost l Carrying amount
Co-invested expenditure and funding
Network length (km)
l TA l Waka Kotahi
l Sealed l Unsealed
l Rural l Urban
Network length (km)
Council Agenda - 29-07-20 Page 130
Whaarangi 10 | 11 M 2787657
APPENDIX B: Waitawheta Road Bridge Controls Options Study
Report (M2781550)
Council Agenda - 29-07-20 Page 131
Whaarangi 11 | 11 M 2787657
APPENDIX C: Whiritoa Lighting Level Review Report
Council Agenda - 29-07-20 Page 132
Whiritoa Lighting Level Review For Hauraki District Council
Jon Stevens
Power Solutions Ltd. June 2020
Council Agenda - 29-07-20 Page 133
Scope Hauraki District Council (HDC) engaged Power Solutions Ltd (PSL) to carry out a detailed assessment of the existing street lighting installation in the township of Whiritoa.
The aim of the assessment was to identify any areas in the township where the existing lighting levels were particularly poor, with particular attention paid to Whiritoa Beach Road and Marlin Place, Whiritoa Beach Road being the main traffic route into and through the township.
Once any areas of poor lighting are identified, Hauraki District Council will look at options for improving the lighting in the township, in consultation with local residents and the community board.
Methodology The existing street lighting installations were visited on site and their individual locations checked and if required fixed, using GPS, into the HDC street lighting database.
Once this was completed, the locations were then plotted onto a cadastral plan of Whiritoa which showed both the road reserve and property boundaries within the township.
This plan was then used with the AGI lighting design software to calculate the lighting levels on the roads within the township. The AGI software uses the photometric files, (Supplied by the street lighting lantern manufacturers of the various types of LED lanterns used in the township) along with the mounting height and location details to produce a linear representation (Isolux plot) of the lighting levels on the road reserves.
Figure 1 below shows a typical section of the road reserve with the street light and the Isolux lines for the various lighting levels.
Figure 1
Council Agenda - 29-07-20 Page 134
The various coloured lines represent a specific light level. In this case the red line represents 0.14 Lux and the green line represents 0.3 Lux. Ideally, Whiritoa Beach Road and Kon Tiki Road would have a lighting level of 0.3 lux (P3 category) between the road reserve boundaries and along the length of the road. All other roads in the township would have a lighting level of 0.14 Lux (P4 category).
When looking at the coloured lines, this would mean, ideally, that the green line would sit on the road reserve boundary on Whiritoa Beach Road and Kon Tiki Road and the red line would do the same for all other roads.
Results Appended to this report is a plan showing the Isolux plot for the whole of the Whiritoa township.
It can be seen from this plan that there are large areas within Whiritoa where the lighting levels have significant “holes”. This is particularly visible on Whiritoa Beach Road, Marlin Place, Mako Ave, Tuna Place and Moray Place.
It is interesting to note that the newer section of Dolphin Drive has a much better light distribution, this is because the lighting on the road has been specifically designed as part of the new sub division. The older roads in Whiritoa have power pole mounted lights or lights sited at intersections, cul-de-sacs and on bends only and were not designed as such, just lit strategically.
Recommendations The most economical solution to improving the lighting levels would be to install infill lighting in the “holes” in the existing lighting layout highlighted by the lighting assessment.
It is recommended therefore that a detailed lighting design is carried out to determine the quantity and wattage of any infill lighting required.
Once the requirements are established and based on available budget and in consultation with residents, additional lighting is installed where required. This process could be carried out in phases, perhaps starting with Whiritoa Beach Road and Marlin Place, as Whiritoa Beach Road is the main collector road in the township and as such will have the most vehicular and pedestrian traffic and Marlin Place has been highlighted as particularly poorly lit by residents.
Council Agenda - 29-07-20 Page 135
Council Agenda - 29-07-20 Page 136
Whaarangi 1 | 10 M 2783935
FOR INFORMATION |
NGĀ MŌHIOTANGA
TO Mayor and Councillors
AUTHOR EJ Wentzel - Water Services Manager
FILE REFERENCE Document: 2783935
Appendix A: NA
Appendix B: NA
PORTFOLIO HOLDER/S Councillor Harris
MEETING DATE 29 July 2020
SUBJECT Water Services - Monthly Activity Report for July
SUMMARY | TE WHAKARĀPOPOTANGA
This report summarises performance and issues in the Water Services work area. The body of
the report refers to the June period.
RECOMMENDATION | TE WHAIKUPU
THAT the report be received.
Council Agenda - 29-07-20 Page 137
Whaarangi 2 | 10 M 2783935
1 PURPOSE | TE ARONGA
To provide an overview on the maintenance activities, project progress, risks and financial
standing of the Water Services activity.
2 BACKGROUND | TE KŌRERO Ā MUA
This report provide an overview of the activities in the Water Services environment.
3 FINANCIAL MEASURES
There will be no financial report for this month.
4 WATER SUPPLY
4.1 Water Networks Operations Notebook
Various water mains renewals are underway in:
Wani Road – Plains
George Street – Paeroa
Lewis Street - Paeroa
A significant number of breaks were experienced on the Plains network due to the drought and
ageing infrastructure.
4.2 Water Treatment Operations Notebook
Tetley’s Quarry water level is climbing slowly, although we are filling as fast as our
Resource Consent allows depending on the Waitakaruru River level. It is still predicted to
be a dry winter and spring. The Mangatarata River (Suicide Intake) level is now high
enough to partially supply Waitakaruru WTP as well. But to preserve the Quarry storage
for summer, when we may not take from the Mangatarata Stream, Waitakaruru WTP will
be shut off whenever demand allows.
Two new Treatment Technicians have started with HDC.
Both intake lines at Pekapeka Intake on the Waihou River were removed and repaired.
We now have full flow from both intake pumps.
The WSM and Treatment Team Leader met with their regular SCADA/automation supplier
to discuss entering into a Service Level Agreement. All Councils Water and Wastewater
treatment plants and most of our pump stations are managed through a SCADA system.
It is crucial that this system is fully functional at all times as it affects the quality and
surety of supply of our service. The purpose of entering into such an agreement is to
make sure we build a long term relationship with a supplier, the expectations and service
levels are clearly defined and we have surety in rates. The WSM will investigate joining
in their contract with MPDC.
4.3 August / September Planned Works
Water main replacements: Waikino Bridge, Consols Street – Waihi, Abbot Rd – Pipiroa
and Wharf Street - Kerepehi.
Council Agenda - 29-07-20 Page 138
Whaarangi 3 | 10 M 2783935
Dead end flushing of water mains to start – this has been delayed due to the current
water shortage and concerns about consents.
Longer term repairs to hot water tanks.
5 WASTEWATER
5.1 Wastewater Networks Operations Notebook
Junction Road pumpstation works to bring the station back to a more stable level of
operation after the power surge are underway.
Junction Road pump 1 suffered a failure and was sent to Pump & Valve to determine if it
was fixable. The cost of repair is un-economical therefore a new one has been ordered
ex Sweden (6-8 weeks delivery time)
There was a wastewater overflow at the back of Subway in Ngatea caused by metal being
pushed into a damaged manhole. The overflow was able to be minimised by turning off
the contributing pumpstations while the block was cleared. The lines were video
inspected to ensure that they are now clean. This was reported to WRC as the discharge
reached the open drain.
Large rain events have caused a number of wet weather overflows through the region.
All trouble spots were checked while it was raining to confirm overflows.
5.2 Wastewater Treatment Operations Notebook
There were eight Resource Consent (RC) exceedances reported at Hauraki District
Council (HDC) wastewater/sewage treatment plants (WWTP/STP) in June 2020, for
samples taken in June 2020:
1. Whiritoa STP Faecal Coliforms
a. 18 000 cfu/100 mL
b. This value is above the median limit (10 000 cfu/100 mL). This was only the
second monthly exceedance of the median limit.
2. Turua STP Total Suspended Solids (TSS)
a. 72 g/m3
b. This value is above the median consent limit (50 g/m3), but still below the 90th
percentile limit (170 g/m3). This is in line with previous years’ seasonal results.
The plant needs to be desludged, which works will be considered once the new RC
is issued.
3. Ngatea STP Total Suspended Solids (TSS)
a. 74 g/m3
b. This value is above the consent limit (70 g/m3). This is in line with annually
increasing results visible in long term trending. The plant needs to be desludged,
which works will be considered once the new RC is issued.
4. Kerepehi STP Total Suspended Solids (TSS)
a. 31 g/m3
b. This value is above the lower consent limit (No more than 8 exceedances above
30 g/m3; No more than 2 exceedances above 50 g/m3). It is the 6th monthly
exceedance of the lower limit, with no exceedances of the higher limit. Low flows
through the ponds due to the drought are suspected to have caused algal blooms,
hindering the digestion process.
5. Kerepehi STP Escherichia coli (E. coli)
a. 1 600 cfu/100 mL
Council Agenda - 29-07-20 Page 139
Whaarangi 4 | 10 M 2783935
b. This value is above the lower consent limit, but not the higher consent limit (No
more than 4 exceedances above 2 000 cfu/100 mL; No more than 8 exceedances
above 1 000 cfu/100 mL). It is the 9th exceedance above 1 000 cfu/100 mL and
the 4th exceedance above 2 000 cfu/100 mL. Low flows through the ponds due to
the drought are suspected to have caused algal blooms, hindering the digestion
process.
6. Ngatea STP Escherichia coli (E. coli)
a. 15 000 cfu/100 mL
b. This value is above the median consent limit (13 850 cfu/100 mL). This is
attributable to high TSS in the plant, as reported below. This is also consistent
with previous years’ results, where high results were recorded after the first heavy
rainfall of the season. The plant needs to be desludged, which works will be
considered once the new RC is issued.
7. Paeroa STP Total Suspended Solids (TSS)
a. 38 g/m3
b. This value is above the 90th percentile limit of 22 g/m3. It is the 5th monthly
exceedance of the 90th percentile limit. Overall plant performance is affected by
the build-up of sludge. Council have budgeted for the removal of sludge and is
considering its options to find the most effective method to reduce the sludge in
the ponds. Further discussions are required between Hauraki District Council and
Waikato Regional Council to agree on a long-term strategy on how to deal with
sludge and also about future upgrades.
8. Paeroa STP Total Ammoniacal Nitrogen (TAN)
a. 13.7 g/m3
b. This value is above the 90th percentile limit of 10 g/m3. It is the 7th monthly
exceedance of the 90th percentile limit. Overall plant performance is affected by
the build-up of sludge. Council have budgeted for the removal of sludge and is
considering its options to find the most effective method to reduce the sludge in
the ponds. Further discussions are required between Hauraki District Council and
Waikato Regional Council to agree on a long-term strategy on how to deal with
sludge and also about future upgrades.
The Whiritoa Wastewater Treatment plant discharge consent process is ongoing. The
application has been submitted to Waikato Regional Council for consideration. WRC has
asked for more information that is currently being prepared.
An application was submitted for the renewing of the Paeroa WTP’s resource consent. HDC
has received a recommendation from the WRC Resource Officer that WRC allow us to
continue operating Paeroa WTP under the existing consent until new consents are
granted.
There is a project ongoing at Whiritoa STP to replace the gum trees with redwood trees.
Some photographs of the project are shown below:
Council Agenda - 29-07-20 Page 140
Whaarangi 5 | 10 M 2783935
Council Agenda - 29-07-20 Page 141
Whaarangi 6 | 10 M 2783935
Council Agenda - 29-07-20 Page 142
Whaarangi 7 | 10 M 2783935
Council Agenda - 29-07-20 Page 143
Whaarangi 8 | 10 M 2783935
5.3 August / September Planned Works
Continue repairs and maintenance at WWTP’s around sensor renewal and calibration,
vulnerable wiring and similar housekeeping issues.
Maintenance on Waitakaruru pressure pump network
Preventative network cleaning about pit rim walkway sewers.
Install Multismarts at wastewater pump stations
Council Agenda - 29-07-20 Page 144
Whaarangi 9 | 10 M 2783935
6 STORM WATER
6.1 Storm water Networks Operations Notebook
Only critical stormwater maintenance were done during the lockdown period. It was a
relatively dry period and is it unlikely that the lack of maintenance impacted on the
community.
6.2 August / September Planned Works
Plans have now been completed for 40 Thames Road/3c Claremont. Owner permission
is being sought
Obtain quotations for Walker St Waihi stormwater scour remediation gabion design
Removal of piles of soil next to drain at 1638 SH 25, Whiritoa.
A work order has been given for repair works to a large flood gate north of Kaiaua
Council Agenda - 29-07-20 Page 145
Whaarangi 10 | 10 M 2783935
7 NEXT STEPS | TE ARA KI MUA
Timeframe Action Comments
NA
Approval
Prepared by Karen Steffek, Connan Negus, Dave Richards and EJ Wentzel
Approved by Adrian de Laborde
Group Manager Engineering
Council Agenda - 29-07-20 Page 146