This image cannot currently be displayed. Footer Text Date WURZBACH PARKWAY NW Military Hwy Focus Group Meeting # 2 June 13, 2017 6:00 to 8:00 PM The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 2014, and executed by FHWA and TxDOT.

Transcript of Focus Group Presentation -...

This image cannot currently be displayed.

Footer Text Date

WURZBACH PARKWAYNW Military HwyFocus Group Meeting # 2June 13, 20176:00 to 8:00 PM

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 2014, and executed by FHWA and TxDOT.

2

A Partnership between:

and

City of San Antonio

Welcome

Thank you for participating in Focus Group Meeting # 2 for the proposed Wurzbach Parkway improvements.

3

Please plan to:

Listen to the presentation View the project information and schematics of the proposed

improvement options Visit with team members and ask questions Share your comments

Project Location

4

Project History – Focus Group Meeting #1

Focus Group Meeting # 1 was held on July 14, 2016.

– Shared Innovative Concepts

– Asked for feedback and preferred concept.

– Single Point Urban Interchange (SPUI) was the preferred concept

– Heard concerns about:

• construction impacts,

• loss of trees,

• inability to travel eastbound and westbound through the intersection.

5

Project History – Public Meeting

Open House Public Meeting held on February 28, 2017.

– Schematic layouts of SPUI at NW Military Highway & Lockhill-Selma improvements

– Traffic analysis results for Build & No Build 2030

– Visualization of SPUI

– Asked for comments and feedback.

127 Comments Received

Project History – Public Meeting

Open House Public Meeting held on February 28, 2017

Most common comments:

• Concerned about construction impacts,

• Keep trees• Need signals at neighborhood

driveways• Keep frontage roads • Analysis assumptions may not

reflect neighborhood trips• Do not want increased

congestion/delay at Lockhill-Selma

Opposed39%

In Favor24%

Neutral37%

Position on Project

We Heard You and We Are Here to Update You On:

8

Results of survey of resident’s travel patterns.

Evaluation of additional options:

Non-grade separated

Grade-separated

Additional Options

Grade Separated Options with Underpass:

Single Point Urban Interchange (SPUI) with signals added on NW Military at TurnberryWay/Fairfield Bend and Alon Loop

Modified SPUI (adding Frontage Roads)

Diamond Interchange

Partial Grade Separation (Eastbound Wurzbach Only)

9

At- Grade Options

At-Grade Improvements

No Build – no physical improvements

Travel Survey Results – Survey Locations

Survey conducted on Thursday, May 18, 2017

7 to 9 AM3 to 6 PM

Alon Loop

Alon Loop

Inverness Blvd

Fairfield BendTurnberry Way

Bluffton Oaks

SUMMERFIELD

INVERNESS

ESTATESOF ALON

10

Travel Survey Results – Total Vehicles Counted by Location

Alon Loop

Alon Loop

Inverness Blvd

Fairfield BendTurnberry Way

SUMMERFIELD

INVERNESS

ESTATESOF ALON

752

122

89

183

350

487

Bluffton Oaks

350

Survey conducted on Thursday, May 18, 2017

7 to 9 AM3 to 6 PM

11

Travel Survey Results

Fairfield Bend38%

Bluffton Oaks6%

Turnberry Way4%

Inverness Blvd9%

Alon Loop at

Wurzbach18%

Alon Loop at NW

Military25% 487

350

183

752

12289

Total Vehicles Counted by Location

0

200

400

600

800

1000

1200

1400

1600

1800

2000

Survey Participation

Drivers Not Surveyed Drivers Surveyed

1310

673

34% of drivers

participated in the survey

12

Travel Survey Questions

1. Are you a resident?

2. Is this a daily trip?

3. Do you usually use this driveway, for this trip?

4. Where are you going to/coming from? Please give the nearest intersection.

13

Travel Survey Results

0% 20% 40% 60% 80% 100%

Question 1: Are you a Resident?

Question 2: Is this a daily trip?

Question 3: Do you usually use thisentrance/exit?

512

577

599

161

89

63

Responses to Questions

Yes No

14

Travel Survey Results Peak Hour Adjusted Movement VolumesExisting Geometry 23 35 21 PM(Peak Hour Only) 20 25 23 AM

Wurzbach Pky AM PM

9 7131 1519 15

64 3914 936 18

PM AM

33 17 15 AM41 67 0 PM

NW Military

Expanded Neighborhood Volumes Traveling Through the Intersection

Wurzbach Parkway

NW

Mili

tary

Hw

y

15

Travel Survey Results % of Total Volumes 2017Existing 14% 4% 3% PM

8% 2% 3% AM

AM PM

2% 9%3% 2%5% 4%

19% 19%1% 1%

56% 31%

PM AM

16% 2% 6% AM16% 5% 0% PM

Neighborhood Volumes as a Percent of Total Intersection Volumes

Wurzbach Parkway

NW

Mili

tary

Hw

y

16

Travel Survey Results

17

Assumed Volumes from Previous AnalysisExisting Geometry 17 29 12 PM(Peak Hour Only) 24 40 9 AM

Wurzbach Pky AM PM

15 68139 4827 10

47 35114 10015 22

PM AM

7 30 18 AM20 14 12 PM

NW Military

Assumed Movements of Neighborhood Volumes Traveling Through the Intersection

Wurzbach Parkway

NW

Mili

tary

Hw

y

Analysis was conservative and

overestimated neighborhood traffic

traveling on WurzbachParkway across NW

Military.

Lockhill-Selma at Wurzbach Parkway Improvements

Adding eastbound and westbound lane through the intersection

Signal timing adjustments

Improvements included for all options at NW Military

Cost: Included in Wurzbach & NW Military Options

18

Lockhill-Selma at Wurzbach Parkway Improvements

Adding eastbound and westbound lane through the intersection

Signal timing adjustments

Improvements included for all options at NW Military

Cost: Included in Wurzbach & NW Military Options

19

Single Point Urban Interchange (SPUI) With Signals

Allows for concurrent left turns on WurzbachParkway and on NW Military

Large turning radii for left and right turns

3-phase operation with single signal

Includes signals at Turnberry/Fairfield and at Alon Loop & NW Military

Cost: $29 M

20

A

Single Point Urban Interchange (SPUI) With Signals

Allows for concurrent left turns on WurzbachParkway and on NW Military

Large turning radii for left and right turns

3-phase operation with single signal

Includes signals at Turnberry/Fairfield and at Alon Loop & NW Military

Cost: $29 M

21

A

Single Point Urban Interchange (SPUI) With Signals

22

A

PROS CONSMore efficient than all other design options – 3 phase operation

Excludes through movements for Wurzbach Parkway at grade

Larger turning radii increases efficiency; similar to through lane capacity

Less intuitive for drivers

Tree removal

High construction costs

Construction impacts

Modified Single Point Urban Interchange (SPUI)

Like a SPUI but with Frontage Roads included

4-phase signal operation

Does not include signals at Turnberry/Fair-field and at Alon Loop & NW Military

Cost: $28.5M

23

B

Modified Single Point Urban Interchange (SPUI)

Like a SPUI but with Frontage Roads included

4-phase signal operation

Does not include signals at Turnberry/Fair-field and at Alon Loop & NW Military

Cost: $28.5M

24

B

PROS CONSMore efficient than all but SPUI design option Less intuitive for drivers

Maintains large turning radii and concurrent left turns which improves capacity and throughput

Tree removal

Maintains adjacent property access High construction cost

Construction impacts

Modified Single Point Urban Interchange (SPUI)B

22

Diamond Interchange

Traditional interchange design

Underpass for WurzbachParkway through traffic

Frontage Roads for Wurzbachincluded

4-phase signal operation

Cost: $27M

26

C

Diamond Interchange

Traditional interchange design

Underpass for WurzbachParkway through traffic

Frontage Roads for Wurzbachincluded

4-phase signal operation

Cost: $27M

27

C

Diamond Interchange

28

C

PROS CONSDriver familiarity Less effective than SPUI options for

throughput and reducing delayMaintains adjacent property access Tree removal

High construction costs

Construction impacts

Partial Grade Separation

Underpass for eastbound WurzbachParkway only

Westbound WurzbachParkway traffic at-grade, controlled by traffic signal

4-phase signal operation

Cost: $21.5M

29

D

Partial Grade Separation

Underpass for eastbound WurzbachParkway only

Westbound WurzbachParkway traffic at-grade, controlled by traffic signal

4-phase signal operation

Cost: $21.5M

30

D

Partial Grade Separation

31

D

PROS CONSDoesn’t increase WB congestion downstream at Lockhill-Selma

Very inefficient due to imbalancedsignal operation

Maintains adjacent property access Tree removal

Lower construction cost than other grade separated options

High-cost option with much lower capacity benefit

Construction impacts

At-Grade Improvements

No underpass; all movements at grade

Adds lanes on WurzbachParkway

Adds lanes on NW Military Highway

4-phase signal operation

Cost: $7.5M

32

E

At-Grade Improvements

No underpass; all movements at grade

Adds lanes on WurzbachParkway

Adds lanes on NW Military Highway

4-phase signal operation

Cost: $7.5M

33

E

At-Grade Improvements

34

E

PROS CONSLow construction impacts Most inefficient operation of all options

Retains some tree canopy Does not allow for concurrent left turn movements

Maintains property access Least effective for adding capacity and reducing delay and congestion

Lower construction costs All movements controlled by signal

No Build

Keep current intersection configuration

No physical improvements

Cost: $5,000

35

F

7-ELEVEN

INVERNESS

JEWISH COMMUNITY

CENTER

ALON TOWN CENTER

SELF STORAGE

No Build

36

F

PROS CONSRetains median and trees Traffic congestion not improved

Little to no cost for signal timing Does nothing to address futuregrowth/increase in traffic

No construction impacts

Access is not affected

Traffic Operations Benefits of Full Grade Separation

31

Traffic Operations Benefits of Full Grade Separation

31

Traffic Operations Benefits of Full Grade Separation

31

Traffic Operations Benefits of Full Grade Separation

31

Traffic Operations Benefits of Full Grade Separation

31

Traffic Benefits of At-Grade Solution

Good reduction in delay for all but southbound NW

Military movement

Minimal increase in delay and congestion

at Lockhill-Selma intersection

Benefits at NW Military & Wurzbach Parkway will

have a short life-span as traffic volumes increase.

32

Level-of-Service (LOS) at a Signalized Intersection

43

Best to Worst

• Little or no delay.

• May arrive on green.

• May be a few cars waiting.

• No delay. • Arrive at

the signal on green.

• No waiting cars.

• Some delay.

• Some congestion.

• Most cars make it through the signal when it turns green.

• Noticeable delay.

• May wait for more than one cycle.

• Not all cars make it through when signal turns green

• Congested conditions.

• Will wait for more than one cycle.

• Many cars do not make it through signal.

• Very congested

• May wait for two or more cycles.

• Many cars do not make it through signal.

Traffic Performance Comparison

Options forWurzbach Parkway

at NW Military

NW Military & WurzbachParkway

Intersection LOS

AM PM

2017 2030 2017 2030

SPUI With Signals C C C D

Modified SPUI D D D E

Diamond D F F F

Partial Grade Separation E E F F

At-Grade Improvements D F F F

Existing Geometry F F F F

34

Traffic Performance Comparison

Options forWurzbach Parkway

at NW Military

Lockhill-Selma at Wurzbach Parkway

WB Through Queue Length

(feet) 2017AM PM

AM PM 2017 2030 2017 2030

SPUI With Signals 542 341 D E D F

Modified SPUI D E D F

Diamond D E D F

Partial Grade Separation 388 305 D E D F

At-Grade Improvements D E D F

Existing Geometry 493 425 D F F F

35

Qualitative Comparison Matrix

46

Criteria SPUI W/Signals

ModSPUI Diamond At-

GradePartial

GSNo

Build

Traffic Operations

Access Impacts

Lockhill-SelmaCongestion/DelayLifespan Effectiveness Construction Impacts

Tree Preservation

Cost

This image cannot currently be displayed.

Footer Text Date

WURZBACH PARKWAYNW Military HwyFocus Group Meeting # 2June 13, 20176:00 to 8:00 PM

POLLING SESSION

47Template with layouts

Polling Instructions

48

Please participate in our real-time polling exercise! What you will need: a smartphone or tabletInstructions

1. Sign onto wifi: or use your cellular service.

1. Open your web browser and enter www.pollev.com/satexas

• You do not need to create an account. • Once the poll is opened by the moderator, a poll question will

automatically appear on your phone or tablet screen.• When the moderator moves to the next question, it will

automatically update on your screen.• You will only be able to vote once.• You can change your answer before submitting.

Polling Slides – Test Question:

49

Did you attend the first Focus Group Meeting on July 14, 2016?

1. Yes2. No3. I don’t remember.

Polling Slides – Question 1:

50

As an HOA representative, what is your biggest concern about the project?

Write in your answer, with as few words possible. You can also just choose an answer on the screen.

NW Military & Wurzbach Parkway Options for Polling

A B C

D E F

SPUI W/SIGNALS

MOD SPUI W/FRONTAGEROADS

DIAMOND

PARTIAL GRADESEPARATION

AT-GRADEIMPROVEMENTS

NO BUILD

40

Polling Slides – Question 2

52

Select your MOST favorite option:A – SPUI With SignalsB – Modified SPUI (Frontage Roads included)C – DiamondD – Partial Grade Separation (EB Wurzbach only)E – At-Grade ImprovementsF – No Build

One answer only.

NW Military & Wurzbach Parkway Options for Polling

A B C

D E F

SPUI W/SIGNALS

MOD SPUI W/FRONTAGEROADS

DIAMOND

PARTIAL GRADESEPARATION

AT-GRADEIMPROVEMENTS

NO BUILD

42

Polling Slides – Question 3

54

Select your LEAST favorite option:A – SPUI With SignalsB – Modified SPUI (Frontage Roads included)C – DiamondD – Partial Grade Separation (EB Wurzbach only)E – At-Grade ImprovementsF – No Build

One answer only.

Provide Your Comments

55

Leave a comment card Email your comments to: [email protected] Mail your comments to:

WSP|Parsons-BrinckerhoffAttn: Ibette CavazosBank of America Plaza300 Convent Street, Suite 1330San Antonio, TX 78205

Comments must be submitted or postmarked by

June 30, 2017