FLORIDA DEPARTMENT OF TRANSPORTATION LAKELAND INTELLIGENT RAIL BYPASS PROJECT POLK COUNTY Financial Project ID: 436650-1-52-01 January 2019 CONSTRUCTION PROJECT www.SWFLroads.com | twitter.com/MyFDOT_SWFL | facebook.com/MyFDOTSWFL PROJECT CONTRACTOR Florida Safety Contractors, Inc. CONTACT US Brian R. Rick, Communications Specialist (863) 519-2828 | [email protected] Sandra Mancil, Community Outreach (863) 519-4116 | [email protected] STAY INFORMED www.swflroads.com/sr37/railbypass.pdf JOIN US ON THE WEB Project design began in April 2018. Construction began in January 2019. Project completion is expected by spring 2019, weather permitting. Lane closures on Florida Avenue are only allowed at night between 7:30 p.m. and 5 a.m. Lane closures on all other side streets may occur during the day from 9 a.m. to 4 p.m., and at night between 7 p.m. to 6 a.m. Design and Construction costs are estimated at $918,123. PROJECT SCHEDULE & COST Si tiene preguntas relacionadas con el proyecto de construcción, los residentes pueden llamar a: Alice Ramos, (863) 797-7202 The Florida Department of Transportation (FDOT) is constructing an Intelligent Transportation System (ITS) project designed to alert motorists of an alternate route when a train is crossing their path on Florida Avenue in downtown Lakeland. The City of Lakeland Transportation Management Center will control and operate the system once it is in place. The new system will activate at the same time as the crossings warning devices when a train is approaching Florida Avenue between Main Street and Pine Street. Once activated, 14 blank-out signs will light up along Florida Avenue with messages notifying motorists of delays ahead and guiding them to the alternate route. Northbound drivers on SR 37/Florida Avenue will be guided west onto Lime Street, north beneath the railroad overpass on Sikes Boulevard, then east onto George Jenkins Boulevard back to US 98/Florida Avenue. Southbound motorists on US 98/Florida Avenue will be guided west onto George Jenkins Boulevard, south beneath the railroad overpass on Sikes Boulevard, then east onto Lime Street back to SR 37/Florida Avenue. George Jenkins Boulevard US 98/ Lime Street Lake Wire Lake Mirror Florida Avenue Tennessee Avenue Massachuses Avenue Lime Street Orange Street Parker Street Main Street Munn Park Lemon Street MLK Jr Avenue 98 98 37 Pine Street

Transcript of FLORIDA DEPARTMENT OF TRANSPORTATION LAKELAND ... - Lakeland, Florida · florida department of...

Page 1: FLORIDA DEPARTMENT OF TRANSPORTATION LAKELAND ... - Lakeland, Florida · florida department of transportation lakeland intelligent rail bypass project polk county financial project

FLORIDA DEPARTMENT OF TRANSPORTATION

LAKELAND INTELLIGENT RAIL BYPASS PROJECT

POLK COUNTY

Financial Project ID: 436650-1-52-01 January 2019

CONSTRUCTION PROJECT

www.SWFLroads.com | twitter.com/MyFDOT_SWFL | facebook.com/MyFDOTSWFL

PROJECT CONTRACTOR

Florida Safety Contractors, Inc.

CONTACT US

Brian R. Rick, Communications Specialist (863) 519-2828 | [email protected]

Sandra Mancil, Community Outreach (863) 519-4116 | [email protected]

STAY INFORMED www.swflroads.com/sr37/railbypass.pdf

JOIN US ON THE WEB

• Project design began in April 2018.

Construction began in January 2019.

• Project completion is expected by spring

2019, weather permitting.

• Lane closures on Florida Avenue are

only allowed at night between 7:30 p.m.

and 5 a.m.

• Lane closures on all other side streets may

occur during the day from 9 a.m. to 4 p.m.,

and at night between 7 p.m. to 6 a.m.

• Design and Construction costs are estimated

at $918,123.

PROJECT SCHEDULE & COST

Si tiene preguntas relacionadas con el proyecto

de construcción, los residentes pueden llamar a:

Alice Ramos, (863) 797-7202

The Florida Department of Transportation (FDOT) is constructing an Intelligent Transportation System (ITS) project designed to alert motorists of an alternate route when a train is crossing their path on Florida Avenue in downtown Lakeland. The City of Lakeland Transportation Management Center will control and operate the system once it is in place.

The new system will activate at the same time as the crossing’s warning devices when a train is approaching Florida Avenue between Main Street and Pine Street. Once activated, 14 blank-out signs will light up along Florida Avenue with messages notifying motorists of delays ahead and guiding them to the alternate route.

Northbound drivers on SR 37/Florida Avenue will be guided west onto Lime Street, north beneath the railroad overpass on Sikes Boulevard, then east onto George Jenkins Boulevard back to US 98/Florida Avenue. Southbound motorists on US 98/Florida Avenue will be guided west onto George Jenkins Boulevard, south beneath the railroad overpass on Sikes Boulevard, then east onto Lime Street back to SR 37/Florida Avenue.

George Jenkins Boulevard US 98/

Lime Street

Lake Wire

Lake

Mirror

Flo

rid

a A

ven

ue

Te

nn

esse

e A

ven

ue

Mas

sach

use

tts

Ave

nu

e

Lime Street

Orange Street

Parker Street

Main Street

Munn

Park

Lemon Street

MLK

Jr

A

ven

ue

98

98

37

Pine Street