Florida Department of Environmental Protection
Environmental Resource Program Workshop Series 2010/2011
-Exemptions and Self Certification Process
Construction, repair, and replacement of mooring pilings
Construction of private docks (non-commercial)
(1,000-sq. ft. limitation/500-sq. ft. if aquatic preserve)
Construction of private dock in artificially created waterways
(1,000-sq. ft. limitation)
Repair and replacement of functional docks or mooring pilings
Construction and maintenance of boat ramps on artificial waterways and associated structures
The 5 regulatory dock exemptions
Proprietary (Not in an Aquatic Preserve)- Consent by Rule
Must be 1,000-sq. ft. or less Structure is only dock or pier per parcel and not private multi-
family with 3 or more slips Can’t impede navigation (25% Rule of Thumb) Must be a water dependent structure Cannot be revenue generating
Proprietary - Letter of Consent All docks proposed in AP’s 500-sq. ft. or less Considered one minimum size private single-family dock or pier
per parcel Can’t extend beyond 20% of the water body or 500 feet,
whichever is less Must be a water dependent structure Setbacks of 10 feet (marginal) or 25 feet (other design), unless
it gets Consent by Rule or <65’ shoreline
Proprietary forms of authorization-Docks
Proprietary Letter of Consent (cont’d) Private single-family or multi-family that cumulatively preempt
no more than 10 sq. ft. for each linear foot of shoreline
Proprietary - Lease Larger than minimum size or over 10:1 ratio Commercial revenue-generating
Proprietary forms of authorization-Docks
Construction of seawall or riprap in artificially created waterway
- No more fill than necessary-Constructed at the MHW line
Repair and replacement of seawalls or riprap-within one foot of existing (as measured
wetface to wetface)Construction of private vertical seawalls and riprap
-connecting existing adjacent seawalls
Proprietary Authorization:Consent by Rule- seawall repairLetter of Consent- new seawalls located
at MHW*No filling of SSL
Seawall Exemptions
-Regulatory-Associated Docks must be < or = 500 square feet-Navigational access must exist-Must be open to the public-< 30 feet wide-No more than 25 cubic yards of material severed-No return water from dredging
ProprietaryNo proprietary approval is necessary – Proprietary does not apply to artificial water bodies
Boat Ramp Exemptions
Maintenance DredgingExisting man-made canals/artificial water bodiesMax. of -5 feet MLW, if no prior permit existsNo return of deleterious water
ProprietaryNo proprietary approval is necessary – proprietary does not apply to artificial water bodies
Other Exemptions
(5) Transmission and Distribution Lines and Utility Poles
(6) Repair, replacement of bridges
9September 25, 2007
Floating vessel platforms (FVP) Statute 403.813(2)(s)
Float at all timesSole purpose to support vessel out of water when not in useNot used to moor vessels in the water (no mooring cleats)Not used for any commercial purposeWholly within previously permitted boat slip (size limited to size of slip)
If associated with exempt dock or permitted dock with no defined boat slip:
<< 500 sq. ft. outside OFWs 500 sq. ft. outside OFWs<< 200 sq. ft. inside OFWs 200 sq. ft. inside OFWs
Exemption Review Process
Department receives application Application Set of drawings $100 processing fee per
exemption verification
30 Day Review process-Does it meet exemption criteria??? Complete upon receipt-Issue within 30 days
Incomplete-Request for additional information sent to applicant
Exemptions
• Proprietary Review:• GRANTED- if on state lands
• Consent by Rule• Letter of Consent• Letter of no objection
• NOT REQUIRED-if not on state lands• PENDING-if proprietary is still being
processed (Leases, Easements, Etc.)
• Federal Review (State Programmatic General Permit (SPGP))– GRANTED- can grant Corps authorization
– NOT GRANTED-can’t issue on behalf of Corps
– NOT REQUIRED-out of Corps jurisdiction
• Regulatory Review: • VERIFIED- with reference to what rule it
meets• NOT VERIFIED-Department was not able to
verify qualification of exemption criteria
MAJOR POINT
If a project is exempt from having to get an ERP permit or a proprietary consent by rule, then the applicant need not come to our Department......
About the Online Business Portal
• Allows online application, payment and other services.
• Gathers and integrates DEP’s existing online services in one place.
• Provides new features to enhance and simplify online access.
• Make DEP’s work more transparent.
• www.fldepportal.com
What are the benefits of Self Certification?
Helpful to Agents/Homeowners
• Easy to use
• Obtain DEP and USCOE authorization together
• No waiting for time clocks
• Takes Less than 30 minutes
Helpful to DEP
• Essentially free to maintain
• Easy to teach (online process)
• Workload reduction
• DEP Case Managers can focus on other DEP applications
• Streamlining efforts
ESSA
Enterprise Self Service Authorization • Department Wide• Currently supports ERP & Waste
Applications
New Self-Service Authorizations
Receive an exemption for: construction of a new single-family dock; repair and replacement of a single-family
dock; installation of a boat lift at a single-family
dock; and construction of a new single-family dock
and installation of a boat lift. Receive a Noticed General Permit for
installation of riprap along the face of an existing seawall.
Apply - Build
Access DEP’s e-permitting application to apply to build the following online. The online application provides for payment of the permit fee online by credit card and emails the issued permit at the end of the application process.•Boat Lift •Riprap Structure •Single Family Dock •Single Family Dock (Repair or Replace)