Floodplain Management Permit Process. In 100-Yr (1% Chance) Floodplain? a. Document how determined....
-
Upload
nataly-dunlow -
Category
Documents
-
view
219 -
download
1
Transcript of Floodplain Management Permit Process. In 100-Yr (1% Chance) Floodplain? a. Document how determined....
FloodplainFloodplainManagementManagement
Permit Process Permit Process
In 100-Yr (1% Chance) Floodplain?
a. Document how determined. b. Continue permit process.
YES
Determine if: 1. General Floodplain (GFP)2. Flood Fringe (FF), or 3. Floodway (FW)
NO
FLOOD FRINGE PERMITTED USES---------------------------------------------------
Document permitted use standards met: aFlood Protection Elevation (FPE) bFill elevation w/in 15’ of structurecDryland access
FOLLOW 12-STEP PROCESS
Meets Stds?Deny permitNO
YES
GFP (“A Zone”)
FF
Determine if site is in FW or FF; Calculate the 1% chance flood elevation
& FW/ FF boundaryRegistered P.E. must do study
If Floodway – Go to FW process If Flood Fringe – Go to FF process
YES
NO
FLOODWAY PERMITTED USES---------------------------------------------------------------
Document permitted use standards met: aLow damage potentialbAssociated with permanent open space use cDoes not obstruct flows (0.01 foot standard)edNo permanent structures
Meets Stds?
aIssue permitbInspect
FW
Floodplain Permit ProcessFloodplain Permit Process
12-Step Permit Process12-Step Permit Process
Applicant submits project description
Determine project location
Determine flood zone at site
Determine applicable standards
Can the project meet the standards?
Check for substantial improvement
12-Step Permit Process12-Step Permit Process
Check for other required permits
Verify structure’s proposed lowest floor elevation (LFE)
Issue permit (include E.C. in file)
Verify LFE after 1st pour
Verify as-built LFE
Issue Certificate of Occupancy
Elevation Certificate FormElevation Certificate Form
Download from:www.fema.gov/nfip/elvinst.htmwww.fema.gov/nfip/elvinst.htmNFIP Surveyor TrainingNFIP Surveyor Training::
http://training.nfipstat.com/ecsurveyor/
Information for Local Officials: http://www.fema.gov/business/nfip/infosl.shtm
NFIP ELEVATION / NFIP ELEVATION / FLOODPROOFINGFLOODPROOFING CERTIFICATESCERTIFICATES
Serve as record of lowest floor elevation
Necessary to obtain actuarial insurance rating
CRS credit
NEW NEW Elevation Elevation CertificateCertificate
NEW Elevation CertificateNEW Elevation Certificate
DIAGRAM 1DIAGRAM 1
All slab-on-grade single- and multiple-All slab-on-grade single- and multiple-floor buildings (other than split-level) floor buildings (other than split-level) and high-rise buildings, either detached and high-rise buildings, either detached or row type (e.g., townhouses); with or or row type (e.g., townhouses); with or without attached garage.without attached garage.Distinguishing Feature – The bottom floor is at or Distinguishing Feature – The bottom floor is at or above ground level (grade) on at least one side. * above ground level (grade) on at least one side. *
NEXT HIGHER FLOOR
BOTTOM FLOOR
ba
GRADE
ff (determined by existing (determined by existing grade)grade)
gg
NEXT HIGHER FLOOR
BOTTOM FLOOR
b
a
GRADE
ff (determined by existing grade)gg
Elevation Certificate – Diagram 1Elevation Certificate – Diagram 1•“Lowest Floor” for Insurance Purposes
•“Lowest Floor” = lowest habitable floor
RFPERFPE
BasementBasementBelow Grade on All Sides
GradeGrade
Next Higher Next Higher FloorFloor
BasementBasement
Elevation Certificate – Diagram 2 Elevation Certificate – Diagram 2 BasementBasement
BOTTOM FLOOR(BASEMENT)
NEXT HIGHERFLOOR
b
a
GRADE
f (determined by existing grade)g
If ResidentialIf Residential
Elevation Certificate – Diagram 3Elevation Certificate – Diagram 3
BOTTOMFLOOR
NEXT HIGHERFLOOR
HIGHERFLOORS b
a
GRADEf (determined by existing grade)(determined by existing grade)g
•Basement
•Lowest Floor
RFPERFPE
ELEVATING WITH ELEVATING WITH METHODS OTHER THAN METHODS OTHER THAN
FILLFILL
ALTERNATIVE ELEVATING ALTERNATIVE ELEVATING METHODSMETHODS
Only apply to N/C structuresOnly apply to N/C structures Examples:
Pilings/PiersBasements with openingsInternally flooded crawl spaces
Elevation Certificate – Diagram 7Elevation Certificate – Diagram 7
NEXT HIGHERFLOOR
bb
ffggWALKOUT WALKOUT
LEVELLEVEL
OPENINGS*OPENINGS*
aa
•Basement
•Enclosure below Lowest Floor
EnclosureEnclosure That Portion of That Portion of
an Elevated an Elevated Building Below Building Below the Lowest the Lowest Elevated Floor Elevated Floor that is Either that is Either Partially or Partially or Fully Shut-in by Fully Shut-in by Rigid Walls.Rigid Walls.
Bayport CondosBayport Condos
DRYDRY FLOODEDFLOODED
NEXT HIGHERFLOOR
a
OPENINGS** CRAWL SPACE
f
g
b
Elevation Certificate – Diagram 8Elevation Certificate – Diagram 8
Internally Flooded Crawl SpaceInternally Flooded Crawl Space
• Crawl space not a basement (not sub-grade on all sides) Crawl space not a basement (not sub-grade on all sides) • Top of floor of crawl space not lowest floor since it is Top of floor of crawl space not lowest floor since it is
properly internally flooded.**properly internally flooded.**
**Note: Crawl **Note: Crawl space can be used space can be used
for limited for limited storage, parking storage, parking of vehicles and of vehicles and building access building access
only.only.GradeGrade
Main Level
top of main level floor is lowest floor leveltop of main level floor is lowest floor level
RFPE
Criteria for Elevation on Criteria for Elevation on Perimeter Wall FoundationsPerimeter Wall Foundations
Criteria for Elevation on Criteria for Elevation on Perimeter Wall FoundationsPerimeter Wall Foundations All A Zones, with low-velocity flooding
(less than 5 feet per second) The inside grade of the crawlspace floor
must match the outside grade on at least one side of the building.
Designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for the entry and exit of floodwaters
Minimum Standards for Minimum Standards for Foundation OpeningsFoundation Openings
Minimum Standards for Minimum Standards for Foundation OpeningsFoundation Openings
A minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding.
The bottom of all openings shall be no higher than one foot above grade.
Openings may be equipped with screens, louvers, valves, or other “automatic” coverings
Caveats for Enclosed Areas Caveats for Enclosed Areas Under Lowest FloorsUnder Lowest Floors
Additional flood insurance rating flood insurance rating requirementsrequirements so the enclosed area is not considered a basement: the automatic openings are on at least 2
sides of the structure, and The enclosed space cannot be finished (no
finished wall-paneling, flooring, etc.)
(source: Flood Insurance Manual, Page LFG 1)
LowestFloorOpening
(typical)
1 foot
Crawl Space Foundation Crawl Space Foundation with Openingswith Openings
Walkout Lower Level Not at RFPEWalkout Lower Level Not at RFPEWith Internal Flooding**With Internal Flooding**
Lower Level
GradeGradeGradeGrade
RFPE
top of lower level floor is lowest leveltop of lower level floor is lowest level
Garage
**Internal Flooding Meets TB 1-93 and space **Internal Flooding Meets TB 1-93 and space used only for storage, access and vehicle storageused only for storage, access and vehicle storage
Walkout Lower Level Not at RFPEWalkout Lower Level Not at RFPE
Upper Level
Lower Level
Garage GradeGradeGradeGradeRFPERFPE
top of lower level floor is lowest leveltop of lower level floor is lowest level
Note: NO Internal FloodingNote: NO Internal Flooding
(Not Permitted)(Not Permitted)
Basement ExampleBasement Example
Main Level
Basement
GarageGradeGrade
RFPE
top of basement floor is lowest top of basement floor is lowest floor levelfloor level
(Not Permitted)(Not Permitted)
Crawl Space Example Crawl Space Example
This crawl space IS considered a basement (since it This crawl space IS considered a basement (since it is sub-grade on all sides). It is NOT ALLOWED.is sub-grade on all sides). It is NOT ALLOWED.
top of crawl space floor is lowest floor leveltop of crawl space floor is lowest floor level
GradeGradeGradeGradeMain Level Garage
Crawl Space
RFPE
((Not Permitted)Not Permitted)
Is this a Basement?Is this a Basement?
RFPE
Lowest Floor ElevationsLowest Floor ElevationsBasement FoundationBasement Foundation
BasementLowest Floor
Lowest Floor
Walkout Lower Level AT RFPEWalkout Lower Level AT RFPE
Upper Level
Lower Level
GarageGradeGrade
RFPE
top of lower level floor is lowest top of lower level floor is lowest floor levelfloor level
Floodplain Permit ProcessFloodplain Permit Process
Floodway (FW), Flood Fringe (FF) or General Floodplain
(GFP)
NOa. Document how
determined.
b. Continue normal permit process.
In 1% Chance Floodplain?
FF FW
Determine if FW or FF & BFE -------------------
Detailed (PE)
GFP “A Zone”
YES
FF Permit ProcessFF Permit Process
Permitted Use (elevated on
fill)?
NO Go to Variance Process
YES
Determine & Document: a. RFPE b. Fill elevation w/in 15’ c. Dryland access
Flood Fringe BasicsFlood Fringe BasicsStandards for Permitted Standards for Permitted
StructuresStructures• Top of lowest floor, including
basement, at FPE• Fill at RFE plus one foot• Fill extends 15 feet from structure• Access road at or above RFE
State Minimums for Structures State Minimums for Structures in Flood Fringe Areasin Flood Fringe Areas
Top of Floor at FPE*
*FPE = 100-year flood (RFE) + 2' (minimum) *FPE = 100-year flood (RFE) + 2' (minimum)
>1’
100-year flood 100-year flood elevation (RFE)elevation (RFE)
> 15'> 15'> 15'> 15'
Not to ScaleNot to Scale
Standards for Elevation on Standards for Elevation on Fill...Fill...
Standards for Elevation on Standards for Elevation on Fill...Fill...
Fill should extend a minimum of 15 feet beyond all sides of the structure
Erosion protection is required for high velocities / steep slopes
Standards for Elevation on FillStandards for Elevation on FillStandards for Elevation on FillStandards for Elevation on Fill
Fill should be placed in maximum 12-inch lifts, and compacted to 95% of the maximum density obtainable with the Standard Proctor Test Method
Fill slopes should be no steeper than 1.0-foot vertical to 1.5-feet horizontal
c. *Calculation of Regulatory Flood Protection Elevation (RFPE)*
d. Regional Flood (100-yr.) Elevation: = 1091.0
e. Freeboard Fill Req’d by ordinance = 1.0
f. FPE: = 1.0 (add above) = 1093.0
1. Structure’s Elevation Requirements In:[ ] N.G.V.D. [ ] Assumed Datum [ ] In relation to street
proposed required
a. Basement or lowest floor = ________ - __________
b. First Floor (above grade): = ________ - __________
c. Max. Building height: = _______ - ________
d. Fill Elev. Adjacent to Structure: = ________ - ________
1091
x
1093
1092
Elevation Elevation Certificate Certificate (As Built)(As Built)
Required By Actual Ordinance As-
Built
2. Structure: a. Elevation of first floor: =_________ - _______
b. Basement elevations: =_________ - _______
b. Lowest adjacent grade: =_________ - _______
c. Highest adjacent grade: =_________ - _______
3. Sewer: a. Top of septic or holding tank: =_________ - _______
b. Bottom of drainfield trench or bed: =_________ - _______
4. Low point of access/road: =_________ - _______
5. Compacted fill elevation around building: =_________ - _______
6. Top of well casing: =_________ - _______
7. Elevation to which structure is flood proofed: =_________ - _______
10931093
(no basement)(no basement)
10921092
NANA
NANA
10911091
10921092
NANA
10931093
NEW NEW Elevation Elevation CertificateCertificate
Where are the vents?Where are the vents?
?Picture
Is this really 1 foot ….or less?
Don’t Forget Manufactured Don’t Forget Manufactured Homes, Mobile Homes, etcHomes, Mobile Homes, etc
MANUFACTURED HOMEANCHORING ON A PIER FOUNDATION
GROUND ANCHORS
MANUFACTURED HOMEANCHORING ON POST OR
PILE FOUNDATIONS
OVER-THE-TOP TIES
MANUFACTURED HOMEANCHORING ON POST OR
PILE FOUNDATIONS
FRAME TIES
Manufactured home park
Recreational Vehicles – WI Recreational Vehicles – WI Sample Ordinance BasicsSample Ordinance Basics
Floodplain CampgroundsFloodplain Campgrounds The campground is approved by the Department of Health and Family Services.
A land use permit for the campground is issued by the zoning administrator.
The character of the river system and the elevation of the campground is such that a 72-hour warning of a flood can be given to all campground occupants.
Adequate flood warning procedure and coordination with emergency government and sheriff’s office which specifies the flood elevation at which evacuation shall occur, personnel responsible for monitoring flood elevations, types of warning systems and the procedures for notifying at-risk parties.
Agreement reviewed and updated every year to remain in compliance with all
applicable regulations.
Only camping units are allowed.
The camping units may not occupy any site in the campground for more than 180 consecutive days.
Floodplain CampgroundsFloodplain Campgrounds All camping units that remain on site for more than 30 days shall be issued a
limited authorization by the campground operator, a written copy of which is kept on file at the campground. Such authorization shall allow placement of a camping unit for a period not to exceed 180 days and shall ensure compliance with all the provisions of this section.
The municipality shall monitor the limited authorizations issued by the campground operator to assure compliance with the terms of this section.
All camping units that remain in place for more than 180 consecutive days must meet the applicable requirements in either s. 3.0 or s. 4.0 for the floodplain district in which the structure is located.
The campground shall have signs clearly posted at all entrances warning of the flood hazard and the procedures for evacuation when a flood warning is issued.
All service facilities, including but not limited to refuse collection, electrical service, natural gas lines, propane tanks, sewage systems and wells shall be properly anchored and placed at or floodproofed to the flood protection elevation
Road ConstructionRoad Construction
It is development It does require a land use permit If in floodway, impacts must be analyzed If the project causes any increase in RFE,
practicable alternatives must be reviewed and implemented if feasible
If none exist, can proceed with CLOMR
Road ConstructionRoad Construction
When completed, CLOMR data must be adopted by community
All affected property owners must be notified of any RFE increase
Flood easements must still be obtained before project can proceed
These rules apply to any road project not funded or managed by DOT